AIRPORT REDEVELOPMENT
12 Months Ended
Dec. 31, 2023
Commitments and Contingencies Disclosure [Abstract]  
AIRPORT REDEVELOPMENT AIRPORT REDEVELOPMENT
New York-JFK Airport

We are enhancing and expanding our facilities at Terminal 4 of JFK to strengthen our competitive position and offer a premium travel experience for customers in New York City. Terminal 4 is operated by JFK International Air Terminal LLC ("IAT"), a private party, under its lease with the Port Authority of New York and New Jersey ("Port Authority"). We have a long-term agreement with IAT to sublease space in Terminal 4 through 2043 ("Sublease").

In 2021, the Port Authority approved plans to renovate and expand Terminal 4 in order to facilitate Delta's relocation from Terminal 2 and consolidation of its operations into Terminal 4. The project is adding 10 new gates and other complementary facilities, including an additional Delta Sky Club and a new Delta premium lounge. The project is estimated to cost approximately $1.6 billion and will be funded primarily with bonds issued in 2022 by the NYTDC for which our landlord, IAT, is the obligor. The majority of project costs are being used to expand or modify Delta's leased premises. Construction started in late 2021 and in 2023 we substantially completed a majority of Delta's portion of the project and consolidated all operations to Terminal 4. Based on our assessment of the project, we concluded that we do not control the underlying assets being constructed, and therefore, we do not have the project asset or related obligation recorded on our balance sheets.
Equity Investment. We have an equity method investment in JFK IAT Member LLC, which owns IAT. The Sublease requires us to pay certain fixed management fees. We determined the investment is a variable interest entity and assessed whether we have a controlling financial interest in IAT. Our rights under the Sublease, with respect to management of Terminal 4, are consistent with rights granted to an anchor tenant under a standard airport lease. Accordingly, we do not consolidate this entity in our Consolidated Financial Statements. See Note 4, "Investments" for additional information on our equity investments.

Los Angeles International Airport ("LAX")

As part of the terminal redevelopment project at LAX, we are modernizing, upgrading, and providing post-security connection to Terminals 2 and 3. We announced this project and executed a modified lease agreement during 2016 with the City of Los Angeles (the "City"), which owns and operates LAX. This project includes a new centralized ticketing and arrival hall, a new security checkpoint, core infrastructure to support the City's planned airport people mover, ramp improvements and a post-security connector to the north side of the Tom Bradley International Terminal.

The project is expected to cost approximately $2.4 billion. A substantial majority of the project costs are being funded through the Regional Airports Improvement Corporation ("RAIC"), a California public benefit corporation, using a revolving credit facility provided by a group of lenders. The credit facility was executed in 2017 and we have guaranteed the obligations of the RAIC under the credit facility. During 2023, the revolving credit facility agreement was amended and the revolver capacity was reduced to $626 million. Loans made under the credit facility are being repaid with the proceeds from the City’s purchase of completed project assets. Under the lease agreement and subsequent project component approvals by the City's Board of Airport Commissioners, the City has appropriated to date approximately $1.8 billion to purchase completed project assets, representing the maximum allowable reimbursement by the City. Costs incurred in excess of the $1.8 billion maximum will not be reimbursed by the City. We currently expect our net project costs to be approximately $600 million, of which approximately $350 million has been reflected as investing activities and approximately $200 million as operating activities in our cash flows statement since the project started in 2017.

In 2020, we enhanced the project’s scope to include a more customer-friendly design of Terminal 3, an expanded Delta Sky Club and baggage system upgrades designed to increase the terminals’ operational efficiency going forward. In 2023, we substantially completed all construction for this project.

Based on our assessment of the project, we concluded that we do not control the underlying assets being constructed, and therefore, we do not have the project asset or related obligation recorded on our balance sheets, except for certain assets recorded as leasehold improvements within property and equipment, net on our balance sheets.

We have recorded approximately $200 million as a ROU asset on our balance sheets related to certain costs incurred in excess of RAIC funding, though we have not recognized a ROU asset and lease liability on our balance sheets for the variable lease payments in our agreement with the City. See Note 7, "Leases" for more information on our ROU assets and lease liabilities.

New York-LaGuardia Airport

As part of the terminal redevelopment project at LaGuardia Airport, we are partnering with the Port Authority to replace Terminals C and D with a new state-of-the-art terminal facility consisting of 37 gates across four concourses connected to a central headhouse. The completed terminal redevelopment features a new, larger Delta Sky Club, wider concourses, more gate seating and nearly double the amount of concessions space than the prior terminals. The completed facility also offers direct access between the parking garage and terminal and improved roadways and drop-off/pick-up areas. Construction is underway and is being phased to limit passenger inconvenience.

We have opened Concourse E, Concourse G, the headhouse (including the Delta Sky Club), the terminal roadways and portions of Concourse D and Concourse F. Due to an acceleration effort that commenced in 2020, substantial completion is expected by the end of 2024.
In connection with the redevelopment, during 2017, we entered into an amended and restated terminal lease with the Port Authority with a term through 2050. Pursuant to the lease agreement, as amended to date, we (1) are funding (through debt issuance and existing cash) and undertaking the design, management and construction of the terminal and certain off-premises supporting facilities, (2) are receiving a Port Authority contribution of approximately $500 million to facilitate construction of the terminal and other supporting infrastructure, (3) will be responsible for all operations and maintenance during the term of the lease and (4) will have preferential rights to all gates in the terminal subject to Port Authority requirements with respect to accommodation of designated carriers.

The project is expected to cost $4.3 billion and the total amount spent to date is approximately $3.7 billion. We currently expect our net project cost to be approximately $3.8 billion and we bear the risks of project construction, including any potential cost over-runs. We entered into loan agreements to fund a portion of the construction, which are recorded on our balance sheets as debt with the proceeds reflected as restricted cash. Using funding primarily provided by these arrangements, we spent approximately $500 million, $650 million and $950 million during 2023, 2022 and 2021, respectively. Based on our assessment of the project, we concluded that we do not control the underlying assets being constructed. Costs incurred by Delta are accounted for as leasehold improvements recorded in property and equipment, net on our balance sheets. See Note 6, "Debt," for additional information on the debt (NYTDC Special Facilities Revenue Bonds) related to this redevelopment project.