AIRPORT REDEVELOPMENT (Details)
12 Months Ended 72 Months Ended
Dec. 31, 2022
USD ($)
gate
Dec. 31, 2021
USD ($)
gate
Dec. 31, 2020
USD ($)
Dec. 31, 2019
gate
concourse
Dec. 31, 2022
USD ($)
Jan. 31, 2023
USD ($)
Dec. 31, 2017
USD ($)
Agreements and Obligations [Line Items]              
Operating lease liability $ 7,580,000,000       $ 7,580,000,000    
Financial Guarantee | Revolving Credit Facility              
Agreements and Obligations [Line Items]              
Aggregate commitments guaranteed 800,000,000       800,000,000    
Financial Guarantee | Revolving Credit Facility | Subsequent event              
Agreements and Obligations [Line Items]              
Aggregate commitments guaranteed           $ 700,000,000  
JFK IAT Member LLC              
Agreements and Obligations [Line Items]              
Operating lease liability 2,300,000,000       2,300,000,000    
JFK Terminal Redevelopment Project              
Agreements and Obligations [Line Items]              
Number of new gates | gate   10          
Total expected project costs $ 1,600,000,000       1,600,000,000    
LAX Redevelopment Project              
Agreements and Obligations [Line Items]              
Number of new gates | gate 14            
Total expected project costs $ 2,400,000,000       2,400,000,000    
Expected net projects costs $ 600,000,000       600,000,000    
Project costs reflected as investing cash flows         350,000,000    
Number of new gates open | gate 11            
LAX Redevelopment Project | City of Los Angeles              
Agreements and Obligations [Line Items]              
Total appropriation to date by city $ 1,800,000,000       1,800,000,000    
Maximum reimbursement by city $ 1,800,000,000       1,800,000,000    
LaGuardia Airport Redevelopment Project              
Agreements and Obligations [Line Items]              
Number of new gates | gate 12            
Total expected project costs $ 4,300,000,000       4,300,000,000    
Expected net projects costs $ 3,800,000,000       3,800,000,000    
Number of new gates open | gate 4     7      
Number of new gates planned | gate       37      
Number of concourses for gates | concourse       4      
Port Authority contribution to redevelopment project             $ 500,000,000
Amount spent on project costs $ 650,000,000 $ 950,000,000 $ 600,000,000   $ 3,200,000,000