XML 57 R43.htm IDEA: XBRL DOCUMENT  v2.3.0.11
Ownership of Coal-fired Facilities (Ownership Interests) (Details) (USD $)
In Millions, unless otherwise specified
6 Months Ended
Jun. 30, 2011
mW
Construction Work in Process 49.0
DP&L [Member] | DP&L Share [Member]
 
Production Capacity (MW) 2,465
DP&L [Member] | DP&L Share [Member] | Beckjord Unit 6 [Member]
 
Ownership (%) 50.00%
Production Capacity (MW) 207
DP&L [Member] | DP&L Share [Member] | Conesville Unit 4 [Member]
 
Ownership (%) 16.50%
Production Capacity (MW) 129
DP&L [Member] | DP&L Share [Member] | East Bend Station [Member]
 
Ownership (%) 31.00%
Production Capacity (MW) 186
DP&L [Member] | DP&L Share [Member] | Killen Station [Member]
 
Ownership (%) 67.00%
Production Capacity (MW) 402
DP&L [Member] | DP&L Share [Member] | Miami Fort Units 7 and 8 [Member]
 
Ownership (%) 36.00%
Production Capacity (MW) 368
DP&L [Member] | DP&L Share [Member] | Stuart Station [Member]
 
Ownership (%) 35.00%
Production Capacity (MW) 808
DP&L [Member] | DP&L Share [Member] | Zimmer Station [Member]
 
Ownership (%) 28.10%
Production Capacity (MW) 365
DP&L [Member] | DP&L Share [Member] | Transmission (At Varying Percentages) [Member]
 
Production Capacity (MW)  
DP&L [Member] | DP&L Share [Member] | Hutchings Station [Member]
 
Ownership (%) 100.00%
Production Capacity (MW) 390
DP&L [Member] | DP&L Investment [Member]
 
Gross Plant In Service 3,236
Accumulated Depreciation 1,596
Construction Work in Process 49.0
DP&L [Member] | DP&L Investment [Member] | Beckjord Unit 6 [Member]
 
Gross Plant In Service 75
Accumulated Depreciation 55
Construction Work in Process 1.0
SCR and FGD Equipment Installed and In Service No
DP&L [Member] | DP&L Investment [Member] | Conesville Unit 4 [Member]
 
Gross Plant In Service 119
Accumulated Depreciation 30
Construction Work in Process 4.0
SCR and FGD Equipment Installed and In Service Yes
DP&L [Member] | DP&L Investment [Member] | East Bend Station [Member]
 
Gross Plant In Service 201
Accumulated Depreciation 132
Construction Work in Process  
SCR and FGD Equipment Installed and In Service Yes
DP&L [Member] | DP&L Investment [Member] | Killen Station [Member]
 
Gross Plant In Service 617
Accumulated Depreciation 294
Construction Work in Process 2.0
SCR and FGD Equipment Installed and In Service Yes
DP&L [Member] | DP&L Investment [Member] | Miami Fort Units 7 and 8 [Member]
 
Gross Plant In Service 354
Accumulated Depreciation 134
Construction Work in Process 10.0
SCR and FGD Equipment Installed and In Service Yes
DP&L [Member] | DP&L Investment [Member] | Stuart Station [Member]
 
Gross Plant In Service 719
Accumulated Depreciation 274
Construction Work in Process 17.0
SCR and FGD Equipment Installed and In Service Yes
DP&L [Member] | DP&L Investment [Member] | Zimmer Station [Member]
 
Gross Plant In Service 1,060
Accumulated Depreciation 620
Construction Work in Process 15.0
SCR and FGD Equipment Installed and In Service Yes
DP&L [Member] | DP&L Investment [Member] | Transmission (At Varying Percentages) [Member]
 
Gross Plant In Service 91
Accumulated Depreciation 57
Construction Work in Process  
DP&L [Member] | DP&L Investment [Member] | Hutchings Station [Member]
 
Gross Plant In Service 124
Accumulated Depreciation 113
Construction Work in Process 1.0
SCR and FGD Equipment Installed and In Service No