XML 60 R49.htm IDEA: XBRL DOCUMENT v3.7.0.1
Commitments And Contingencies (Other Contingencies) (Detail)
$ in Thousands
3 Months Ended 6 Months Ended 12 Months Ended
Jun. 30, 2017
USD ($)
Jun. 30, 2016
USD ($)
Sep. 30, 2014
USD ($)
Jun. 30, 2017
USD ($)
Jun. 30, 2016
USD ($)
Dec. 31, 2016
USD ($)
Dec. 31, 2014
Apr. 22, 2016
USD ($)
Feb. 09, 2016
USD ($)
Jul. 02, 2015
USD ($)
Dec. 31, 2012
acre
Jul. 31, 2006
Loss Contingencies [Line Items]                        
Airplane operating lease period, years             five          
Guarantees, Fair Value Disclosure $ 7,800     $ 7,800                
Fair Value Of Residual Value Guarantee 5,800     5,800                
Fair Value Of Residual Value Guarantee, Fair Value of Operating Lease Asset Threshold     $ 9,500                  
Asbestos Commitments and Contingencies                        
Loss Contingencies [Line Items]                        
Gross Settlement And Defense Incurred Costs 16,800 $ 16,500   44,800 $ 37,800 $ 73,500            
Environmental Claims For A Site In Goodyear Arizona                        
Loss Contingencies [Line Items]                        
Estimated liability 45,400     45,400                
Amount of additional remediation activities     $ 49,000                  
Accrued environmental loss contingencies current 16,000     16,000                
Loss contingency reimbursement rate                       21.00%
Other receivables $ 9,300     $ 9,300                
Environmental Claims For Crab Orchard National Wildlife Refuge Superfund Site                        
Loss Contingencies [Line Items]                        
Approximate size of referenced site, acres | acre                     55,000  
Huttig [Domain]                        
Loss Contingencies [Line Items]                        
Litigation Settlement, Amount   $ 5,000                    
James Poage [Member] | Asbestos Commitments and Contingencies                        
Loss Contingencies [Line Items]                        
compensatory_damages                   $ 1,500    
Additional damages                   10,000    
Court Judgment                   $ 10,800    
Valent Rabovsky [Member] | Asbestos Commitments and Contingencies                        
Loss Contingencies [Line Items]                        
Court Judgment               $ 400        
Share Of Responsibility Of Verdict                 30.00%      
Jury Verdict Total                 $ 1,085      
George Coulbourn [Member] | Asbestos Commitments and Contingencies                        
Loss Contingencies [Line Items]                        
Court Judgment               $ 6,800        
Share Of Responsibility Of Verdict               20.00%        
Jury Verdict Total               $ 9,000        
Court Reduced damages               $ 5,000