XML 21 R8.htm IDEA: XBRL DOCUMENT v3.8.0.1
CESSATION OF MINING AT LEASED PUEBLO GRAVEL SITE
12 Months Ended
Dec. 30, 2017
CESSATION OF MINING AT LEASED PUEBLO GRAVEL SITE  
CESSATION OF MINING AT LEASED PUEBLO GRAVEL SITE

2. CESSATION OF MINING AT LEASED PUEBLO GRAVEL SITE

 

On September 15, 2016 a Partial Summary Judgment Order was issued regarding the Company’s previously disclosed litigation, Continental Materials Corporation v. Valco, Inc., Civil Action No. 2014-cv-2510, filed in the United States District Court for the District of Colorado. The suit regards a sand and gravel lease between the Company and Valco, Inc. (“Valco”) that calls for the payment of royalties over the life of the lease on an agreed 50,000,000 tons of sand and gravel reserves. In the suit the Company sought, among other things, to reform the sand and gravel lease in regard to the agreed amount of sand and gravel reserves and to recover approximately $1,282,000 of royalty overpayments included in other long-term assets. Valco asserted counterclaims against the Company alleging breach of contract and declaratory judgment regarding the Company’s refusal to make further royalty payments under the Lease. In the ordinary course of business and absent any breach by Valco, the Company is required to make quarterly royalty payments amounting to not less than $300,000 in a calendar year. In response to Valco’s breaches of contract, the Company stopped making royalty payments at the start of the 2015 calendar year. The Company has asserted partial failure of consideration as an affirmative defense to Valco’s counterclaims to offset the alleged back-due quarterly royalty payments and the amount due on quarterly royalty payments in the future. The Partial Summary Judgment Order resolved many of the Company’s claims in Valco’s favor, but the Company’s claim for the return of royalty overpayments made during the statutorily allowed period is still pending. The Partial Summary Judgment Order did not resolve Valco’s counterclaims or the Company’s affirmative defense. During the third quarter of 2016, the Company recorded a $632,000 write-down representing the portion of the royalty overpayment paid prior to the statutorily allowed period because of litigation risk attendant to recovering that amount. The Company sought certification of the Partial Summary Judgment Order because it and its legal counsel believe the court improperly resolved factual issues in its Partial Summary Judgment Order that should have been decided by a jury. The Company and its legal counsel believe there is a likelihood that some, or all, of the issues resolved by the Partial Summary Judgment Order may be reversed on appeal and remanded for trial by jury although there can be no assurance that an appeal will result in reversal. The Company paid royalties on approximately 17,700,000 tons, including the overpayments, of the 50,000,000 tons of sand and gravel reserves through the end of the third quarter of 2014. The impact of these proceedings could have a material financial effect on the Company; however, the Company does not believe that there is a reasonable basis for estimating the financial impact, if any, of the final outcome of these proceedings and accordingly no accrual or reserve has been recorded in compliance with accounting principles generally accepted in the United States of America. On February 23, 2017, the Partial Summary Judgment Order was certified for immediate appeal, and all other claims, counterclaims and affirmative defenses were stayed pending the resolution of that appeal. The Company filed a notice of appeal on March 24, 2017. The appeal is currently pending.