XML 73 R11.htm IDEA: XBRL DOCUMENT v2.4.0.8
Regulatory Matters
3 Months Ended
Mar. 31, 2014
Regulatory Matters

Note B — Regulatory Matters

Other Regulatory Matters

In February 2009, the New York State Public Service Commission (NYSPSC) commenced a proceeding to examine the prudence of certain CECONY expenditures following the arrests of employees for accepting illegal payments from a construction contractor. Subsequently, additional employees were arrested for accepting illegal payments from materials suppliers and an engineering firm. The arrested employees were terminated by the company and have pled guilty or been convicted. Pursuant to NYSPSC orders, a portion of the company’s revenues (currently, $249 million, $32 million and $6 million on an annual basis for electric, gas and steam service, respectively) is being collected subject to potential refund to customers. The amount of electric revenues collected subject to refund, which was established in a different proceeding, and the amount of gas and steam revenues collected subject to refund were not established as indicative of the company’s potential liability in this proceeding. At March 31, 2014, the company had collected an estimated $1,462 million from customers subject to potential refund in connection with this proceeding. In January 2013, a NYSPSC consultant reported its estimate, with which the company does not agree, of $208 million of overcharges with respect to a substantial portion of the company’s construction expenditures from January 2000 to January 2009. The company is disputing the consultant’s estimate, including its determinations as to overcharges regarding specific construction expenditures it selected to review and its methodology of extrapolating such determinations over a substantial portion of the construction expenditures during this period. The NYSPSC’s consultant has not reviewed the company’s other expenditures. The company and NYSPSC staff are exploring a settlement in this proceeding. In May 2014, the NYSPSC’s Chief Administrative Law Judge appointed a settlement judge to assist the parties. There is no assurance that there will be a settlement, and any settlement would be subject to NYSPSC approval. At March 31, 2014, the company had a $38 million regulatory liability relating to this matter. Included in the regulatory liability was $16 million the company recovered from vendors, arrested employees and insurers relating to this matter. Pursuant to the current rate plans, the company is applying $15 million of these recovered amounts for the benefit of customers to offset a like amount of regulatory assets. The company currently estimates that any additional amount the NYSPSC requires the company to refund to customers could range in amount from $25 million up to an amount based on the NYSPSC consultant’s $208 million estimate of overcharges.

In late October 2012, Superstorm Sandy caused extensive damage to the Utilities’ electric distribution system and interrupted service to approximately 1.4 million customers. Superstorm Sandy also damaged CECONY’s steam system and interrupted service to many of its steam customers. As of March 31, 2014, CECONY and O&R incurred response and restoration costs for Superstorm Sandy of $490 million and $93 million, respectively (including capital expenditures of $149 million and $15 million, respectively). Most of the costs that were not capitalized were deferred for recovery as a regulatory asset under the Utilities’ electric rate plans. See “Regulatory Assets and Liabilities” below. CECONY’s current electric rate plan includes collection from customers of deferred storm costs (including for Superstorm Sandy), subject to refund following NYSPSC review of the costs. O&R expects to request recovery of deferred storm costs for its New York electric operations, which are also subject to NYSPSC review, when it next files with the NYSPSC for a new electric rate plan. In March 2013, the NJBPU established a proceeding to review the prudency of costs incurred by New Jersey utilities in response to major storm events in 2011 and 2012. In November 2013, RECO filed an electric rate request with the NJBPU which includes a proposal for recovery over a three-year period of its deferred storm costs of $27 million. In May 2014, RECO, the NJBPU staff and the New Jersey Division of Rate Counsel entered into a stipulation of settlement regarding RECO’s deferred storm costs. The stipulation, which is subject to NJBPU approval, provides that RECO’s deferred storm costs are deemed reasonable, prudent and eligible for recovery over a period to be determined in RECO’s electric rate proceeding.

 

Regulatory Assets and Liabilities

Regulatory assets and liabilities at March 31, 2014 and December 31, 2013 were comprised of the following items:

 

     Con Edison     CECONY  
(Millions of Dollars)   2014     2013     2014     2013  

Regulatory assets

       

Unrecognized pension and other postretirement costs

    $2,591        $2,730        $2,478        $2,610   

Future income tax

    2,183        2,145        2,070        2,030   

Environmental remediation costs

    921        938        814        830   

Deferred storm costs

    411        441        307        334   

Revenue taxes

    216        207        204        196   

Pension and other postretirement benefits deferrals

    191        237        163        211   

Surcharge for New York State assessment

    144        78        136        74   

Net electric deferrals

    78        83        78        83   

Unamortized loss on reacquired debt

    63        65        60        62   

O&R transition bond charges

    31        33                 

Preferred stock redemption

    28        28        28        28   

Property tax reconciliation

    25        22                 

Workers’ compensation

    12        12        12        12   

Deferred derivative losses – noncurrent

    6        8        5        7   

Other

    182        174        167        162   

Regulatory assets – noncurrent

    7,082        7,201        6,522        6,639   

Deferred derivative losses – current

    7        25        5        22   

Recoverable energy costs – current

    1        4               4   

Regulatory assets – current

    8        29        5        26   

Total Regulatory Assets

    $7,090        $7,230        $6,527        $6,665   

Regulatory liabilities

       

Allowance for cost of removal less salvage

    $   558        $   540        $   466        $   453   

Property tax reconciliation

    299        322        299        322   

Property tax refunds

    119        130        119        130   

Long-term interest rate reconciliation

    99        105        99        105   

Carrying charges on repair allowance and bonus depreciation

    81        88        80        87   

New York State income tax rate change

    66               62          

Net unbilled revenue deferrals

    61        133        61        133   

World Trade Center settlement proceeds

    57        62        57        62   

Other postretirement benefit deferrals

    51        50        47        50   

2014 rate plan base rate revenue deferral

    50               50          

Prudence proceeding

    38        40        38        40   

Unrecognized other postretirement benefits costs

    32               23          

Carrying charges on T&D net plant – electric and steam

    27        28        21        20   

Electric excess earnings

    22        22        18        18   

Other

    240        208        207        178   

Regulatory liabilities – noncurrent

    1,800        1,728        1,647        1,598   

Refundable energy costs – current

    160        100        128        66   

Deferred derivative gains – current

    44        14        36        11   

Revenue decoupling mechanism

    23        34        19        30   

Future income tax

    16               16          

Regulatory liabilities – current

    243        148        199        107   

Total Regulatory Liabilities

    $2,043        $1,876        $1,846        $1,705   

 

 

CECONY [Member]
 
Regulatory Matters

Note B — Regulatory Matters

Other Regulatory Matters

In February 2009, the New York State Public Service Commission (NYSPSC) commenced a proceeding to examine the prudence of certain CECONY expenditures following the arrests of employees for accepting illegal payments from a construction contractor. Subsequently, additional employees were arrested for accepting illegal payments from materials suppliers and an engineering firm. The arrested employees were terminated by the company and have pled guilty or been convicted. Pursuant to NYSPSC orders, a portion of the company’s revenues (currently, $249 million, $32 million and $6 million on an annual basis for electric, gas and steam service, respectively) is being collected subject to potential refund to customers. The amount of electric revenues collected subject to refund, which was established in a different proceeding, and the amount of gas and steam revenues collected subject to refund were not established as indicative of the company’s potential liability in this proceeding. At March 31, 2014, the company had collected an estimated $1,462 million from customers subject to potential refund in connection with this proceeding. In January 2013, a NYSPSC consultant reported its estimate, with which the company does not agree, of $208 million of overcharges with respect to a substantial portion of the company’s construction expenditures from January 2000 to January 2009. The company is disputing the consultant’s estimate, including its determinations as to overcharges regarding specific construction expenditures it selected to review and its methodology of extrapolating such determinations over a substantial portion of the construction expenditures during this period. The NYSPSC’s consultant has not reviewed the company’s other expenditures. The company and NYSPSC staff are exploring a settlement in this proceeding. In May 2014, the NYSPSC’s Chief Administrative Law Judge appointed a settlement judge to assist the parties. There is no assurance that there will be a settlement, and any settlement would be subject to NYSPSC approval. At March 31, 2014, the company had a $38 million regulatory liability relating to this matter. Included in the regulatory liability was $16 million the company recovered from vendors, arrested employees and insurers relating to this matter. Pursuant to the current rate plans, the company is applying $15 million of these recovered amounts for the benefit of customers to offset a like amount of regulatory assets. The company currently estimates that any additional amount the NYSPSC requires the company to refund to customers could range in amount from $25 million up to an amount based on the NYSPSC consultant’s $208 million estimate of overcharges.

In late October 2012, Superstorm Sandy caused extensive damage to the Utilities’ electric distribution system and interrupted service to approximately 1.4 million customers. Superstorm Sandy also damaged CECONY’s steam system and interrupted service to many of its steam customers. As of March 31, 2014, CECONY and O&R incurred response and restoration costs for Superstorm Sandy of $490 million and $93 million, respectively (including capital expenditures of $149 million and $15 million, respectively). Most of the costs that were not capitalized were deferred for recovery as a regulatory asset under the Utilities’ electric rate plans. See “Regulatory Assets and Liabilities” below. CECONY’s current electric rate plan includes collection from customers of deferred storm costs (including for Superstorm Sandy), subject to refund following NYSPSC review of the costs. O&R expects to request recovery of deferred storm costs for its New York electric operations, which are also subject to NYSPSC review, when it next files with the NYSPSC for a new electric rate plan. In March 2013, the NJBPU established a proceeding to review the prudency of costs incurred by New Jersey utilities in response to major storm events in 2011 and 2012. In November 2013, RECO filed an electric rate request with the NJBPU which includes a proposal for recovery over a three-year period of its deferred storm costs of $27 million. In May 2014, RECO, the NJBPU staff and the New Jersey Division of Rate Counsel entered into a stipulation of settlement regarding RECO’s deferred storm costs. The stipulation, which is subject to NJBPU approval, provides that RECO’s deferred storm costs are deemed reasonable, prudent and eligible for recovery over a period to be determined in RECO’s electric rate proceeding.

 

Regulatory Assets and Liabilities

Regulatory assets and liabilities at March 31, 2014 and December 31, 2013 were comprised of the following items:

 

     Con Edison     CECONY  
(Millions of Dollars)   2014     2013     2014     2013  

Regulatory assets

       

Unrecognized pension and other postretirement costs

    $2,591        $2,730        $2,478        $2,610   

Future income tax

    2,183        2,145        2,070        2,030   

Environmental remediation costs

    921        938        814        830   

Deferred storm costs

    411        441        307        334   

Revenue taxes

    216        207        204        196   

Pension and other postretirement benefits deferrals

    191        237        163        211   

Surcharge for New York State assessment

    144        78        136        74   

Net electric deferrals

    78        83        78        83   

Unamortized loss on reacquired debt

    63        65        60        62   

O&R transition bond charges

    31        33                 

Preferred stock redemption

    28        28        28        28   

Property tax reconciliation

    25        22                 

Workers’ compensation

    12        12        12        12   

Deferred derivative losses – noncurrent

    6        8        5        7   

Other

    182        174        167        162   

Regulatory assets – noncurrent

    7,082        7,201        6,522        6,639   

Deferred derivative losses – current

    7        25        5        22   

Recoverable energy costs – current

    1        4               4   

Regulatory assets – current

    8        29        5        26   

Total Regulatory Assets

    $7,090        $7,230        $6,527        $6,665   

Regulatory liabilities

       

Allowance for cost of removal less salvage

    $   558        $   540        $   466        $   453   

Property tax reconciliation

    299        322        299        322   

Property tax refunds

    119        130        119        130   

Long-term interest rate reconciliation

    99        105        99        105   

Carrying charges on repair allowance and bonus depreciation

    81        88        80        87   

New York State income tax rate change

    66               62          

Net unbilled revenue deferrals

    61        133        61        133   

World Trade Center settlement proceeds

    57        62        57        62   

Other postretirement benefit deferrals

    51        50        47        50   

2014 rate plan base rate revenue deferral

    50               50          

Prudence proceeding

    38        40        38        40   

Unrecognized other postretirement benefits costs

    32               23          

Carrying charges on T&D net plant – electric and steam

    27        28        21        20   

Electric excess earnings

    22        22        18        18   

Other

    240        208        207        178   

Regulatory liabilities – noncurrent

    1,800        1,728        1,647        1,598   

Refundable energy costs – current

    160        100        128        66   

Deferred derivative gains – current

    44        14        36        11   

Revenue decoupling mechanism

    23        34        19        30   

Future income tax

    16               16          

Regulatory liabilities – current

    243        148        199        107   

Total Regulatory Liabilities

    $2,043        $1,876        $1,846        $1,705