XML 45 R19.htm IDEA: XBRL DOCUMENT v3.10.0.1
Other Material Contingencies
12 Months Ended
Dec. 31, 2018
Commitments and Contingencies Disclosure [Abstract]  
Other Material Contingencies
Other Material Contingencies
Manhattan Explosion and Fire
On March 12, 2014, two multi-use five-story tall buildings located on Park Avenue between 116th and 117th Streets in Manhattan were destroyed by an explosion and fire. CECONY had delivered gas to the buildings through service lines from a distribution main located below ground on Park Avenue. Eight people died and more than 50 people were injured. Additional buildings were also damaged. The National Transportation Safety Board (NTSB) investigated. The parties to the investigation included the company, the City of New York, the Pipeline and Hazardous Materials Safety Administration and the NYSPSC. In June 2015, the NTSB issued a final report concerning the incident, its probable cause and safety recommendations. The NTSB determined that the probable cause of the incident was (1) the failure of a defective fusion joint at a service tee (which joined a plastic service line to a plastic distribution main) installed by the company that allowed gas to leak from the distribution main and migrate into a building where it ignited and (2) a breach in a City sewer line that allowed groundwater and soil to flow into the sewer, resulting in a loss of support for the distribution main, which caused it to sag and overstressed the defective fusion joint. The NTSB also made safety recommendations, including recommendations to the company that addressed its procedures for the preparation and examination of plastic fusions, training of its staff on conditions for notifications to the City’s Fire Department and extension of its gas main isolation valve installation program. In February 2017, the NYSPSC approved a settlement agreement with the company related to the NYSPSC's investigations of the incident and the practices of qualifying persons to perform plastic fusions. Pursuant to the agreement, the company is providing $27 million of future benefits to customers (for which it has accrued a regulatory liability) and will not recover from customers $126 million of costs for gas emergency response activities that it had previously incurred and expensed. Approximately eighty suits are pending against the company seeking generally unspecified damages and, in some cases, punitive damages, for wrongful death, personal injury, property damage and business interruption. The company has notified its insurers of the incident and believes that the policies in force at the time of the incident will cover the company’s costs, in excess of a required retention (the amount of which is not material), to satisfy any liability it may have for damages in connection with the incident. The company is unable to estimate the amount or range of its possible loss for damages related to the incident. At December 31, 2018, the company had not accrued a liability for damages related to the incident.

Manhattan Steam Main Rupture
In July 2018, a CECONY steam main located on Fifth Avenue and 21st Street in Manhattan ruptured. Debris from the incident included dirt and mud containing asbestos. The response to the incident required the closing of buildings and streets for various periods. The NYSPSC has commenced an investigation. As of December 31, 2018, with respect to the incident, the company incurred estimated operating costs of $14 million for property damage, clean-up and other response costs and invested $8 million in capital and retirement costs. The company has notified its insurers of the incident and believes that the policies currently in force will cover the company’s costs, in excess of a required retention (the amount of which is not material), to satisfy any liability it may have for damages to others in connection with the incident. The company is unable to estimate the amount or range of its possible loss related to the incident. At December 31, 2018, the company had not accrued a liability related to the incident.
Other Contingencies
For information about the PG&E bankruptcy, see "Long-Lived and Intangible Assets" in Note A. Also, for additional contingencies, see “Other Regulatory Matters” in Note B and "Uncertain Tax Positions" in Note L.
Guarantees
Con Edison and its subsidiaries have entered into various agreements providing financial or performance assurance primarily to third parties on behalf of their subsidiaries. Maximum amounts guaranteed by Con Edison under these agreements totaled $2,439 million and $2,073 million at December 31, 2018 and 2017, respectively.
A summary, by type and term, of Con Edison’s total guarantees under these other agreements at December 31, 2018 is as follows:
Guarantee Type
0 – 3 years
 
4 – 10 years

 
> 10 years

 
Total
 
(Millions of Dollars)
Con Edison Transmission
$742
 
$404
 

$—

 
$1,146
Energy transactions
462
 
20
 
201
 
683
Renewable electric production projects
137
 

 
403
 
540
Other
70
 

 

 
70
Total
$1,411
 
$424
 
$604
 
$2,439

Con Edison Transmission – Con Edison has guaranteed payment by CET Electric of the contributions CET Electric agreed to make to New York Transco LLC (NY Transco). CET Electric acquired a 45.7 percent interest in NY Transco when it was formed in 2014. In May 2016, the transmission owners transferred certain projects to NY Transco, for which CET Electric made its required contributions. NY Transco has proposed other transmission projects in the New York Independent System Operator's competitive bidding process. These other projects are subject to certain authorizations from the NYSPSC, the FERC and, as applicable, other federal, state and local agencies. Guarantee amount shown is for the maximum possible required amount of CET Electric's contributions for these other projects as calculated based on the assumptions that the projects are completed at 175 percent of their estimated costs and NY Transco does not use any debt financing for the projects. Guarantee term shown is assumed as the selection of the projects and resulting timing of the contributions is not certain. Also included within the table above are guarantees for $124 million from Con Edison on behalf of CET Gas in relation to Mountain Valley Pipeline (MVP), LLC, a company developing a proposed gas transmission project in West Virginia and Virginia. See Note U.
Energy Transactions — Con Edison guarantees payments on behalf of the Clean Energy Businesses in order to facilitate physical and financial transactions in electricity, gas, pipeline capacity, transportation, oil, renewable energy credits and energy services. To the extent that liabilities exist under the contracts subject to these guarantees, such liabilities are included in Con Edison’s consolidated balance sheet.
Renewable Electric Production Projects – Con Edison, Con Edison Development and Con Edison Solutions guarantee payments on behalf of their wholly-owned subsidiaries associated with their investment in, or development for others of, solar and wind energy facilities. See Note U.
Other – Other guarantees include $70 million in guarantees provided by Con Edison to Travelers Insurance Company for indemnity agreements for surety bonds in connection with operation of solar energy facilities and energy service projects of Con Edison Development and Con Edison Solutions, respectively.