XML 46 R16.htm IDEA: XBRL DOCUMENT v3.8.0.1
Other Material Contingencies
9 Months Ended
Sep. 30, 2017
Commitments and Contingencies Disclosure [Abstract]  
Other Material Contingencies
Other Material Contingencies
Manhattan Explosion and Fire
On March 12, 2014, two multi-use five-story tall buildings located on Park Avenue between 116th and 117th Streets in Manhattan were destroyed by an explosion and fire. CECONY had delivered gas to the buildings through service lines from a distribution main located below ground on Park Avenue. Eight people died and more than 50 people were injured. Additional buildings were also damaged. The National Transportation Safety Board (NTSB) investigated. The parties to the investigation included the company, the City of New York, the Pipeline and Hazardous Materials Safety Administration and the NYSPSC. In June 2015, the NTSB issued a final report concerning the incident, its probable cause and safety recommendations. The NTSB determined that the probable cause of the incident was (1) the failure of a defective fusion joint at a service tee (which joined a plastic service line to a plastic distribution main) installed by the company that allowed gas to leak from the distribution main and migrate into a building where it ignited and (2) a breach in a City sewer line that allowed groundwater and soil to flow into the sewer, resulting in a loss of support for the distribution main, which caused it to sag and overstressed the defective fusion joint. The NTSB also made safety recommendations, including recommendations to the company that addressed its procedures for the preparation and examination of plastic fusions, training of its staff on conditions for notifications to the City’s Fire Department and extension of its gas main isolation valve installation program. In February 2017, the NYSPSC approved a settlement agreement with the company related to the NYSPSC's investigations of the incident and the practices of qualifying persons to perform plastic fusions. Pursuant to the agreement, the company will not recover from customers $126 million of costs it incurred for gas emergency response activities in 2014, 2015 and 2016 in excess of the amounts reflected in its gas rate plan and will provide $27 million of future benefits to customers (for which it has accrued a regulatory liability, see Note B). Approximately eighty suits are pending against the company seeking generally unspecified damages and, in some cases, punitive damages, for wrongful death, personal injury, property damage and business interruption. The company has notified its insurers of the incident and believes that the policies in force at the time of the incident will cover the company’s costs, in excess of a required retention (the amount of which is not material), to satisfy any liability it may have for damages in connection with the incident. The company is unable to estimate the amount or range of its possible loss for damages related to the incident. At September 30, 2017, the company had not accrued a liability for damages related to the incident.
Other Contingencies
See "Other Regulatory Matters" in Note B and “Uncertain Tax Positions” in Note I.
Guarantees
Con Edison and its subsidiaries enter into various agreements providing financial or performance assurance primarily to third parties on behalf of their subsidiaries. Maximum amounts guaranteed by Con Edison totaled $2,162 million and $2,370 million at September 30, 2017 and December 31, 2016, respectively.
A summary, by type and term, of Con Edison’s total guarantees at September 30, 2017 is as follows:
 
Guarantee Type
0 – 3 years
4 – 10 years

> 10 years

Total
 
(Millions of Dollars)
Con Edison Transmission
$643
$404

$—

$1,047
Energy transactions
459
30
211
700
Renewable electric production projects
268

19
287
Other
128


128
Total
$1,498
$434
$230
$2,162

Con Edison Transmission — Con Edison has guaranteed payment by CET Electric of the contributions CET Electric agreed to make to New York Transco LLC (NY Transco). CET Electric acquired a 45.7 percent interest in NY Transco when it was formed in 2014. In May 2016, the transmission owners transferred certain projects to NY Transco, for which CET Electric made its required contributions. NY Transco has proposed other transmission projects in the New York Independent System Operator's competitive bidding process. These other projects are subject to certain authorizations from the NYSPSC, the FERC and, as applicable, other federal, state and local agencies. Guarantee amount shown is for the maximum possible required amount of CET Electric’s contributions for these other projects as calculated based on the assumptions that the projects are completed at 175 percent of their estimated costs and NY Transco does not use any debt financing for the projects. Guarantee term shown is assumed as the selection of the projects and resulting timing of the contributions is not certain. Also included within the table above is a guarantee for $25 million from Con Edison on behalf of CET Gas in relation to a proposed gas transmission project in West Virginia and Virginia.
Energy Transactions — Con Edison guarantees payments on behalf of the Clean Energy Businesses in order to facilitate physical and financial transactions in electricity, gas, pipeline capacity, transportation, oil, renewable energy credits and energy services. To the extent that liabilities exist under the contracts subject to these guarantees, such liabilities are included in Con Edison’s consolidated balance sheet.
Renewable Electric Production Projects — Con Edison, Con Edison Development, and Con Edison Solutions guarantee payments on behalf of their wholly-owned subsidiaries associated with their investment in, or development for others of, solar and wind energy facilities.
Other — Other guarantees include $70 million in guarantees provided by Con Edison to Travelers Insurance Company for indemnity agreements for surety bonds in connection with operation of solar energy facilities and energy service projects of Con Edison Development and Con Edison Solutions, respectively. Other guarantees also includes Con Edison's guarantee (subject to a $53 million maximum amount) of certain obligations of Con Edison Solutions under the agreement pursuant to which it sold its retail electric supply business. In addition, Con Edison issued a guarantee estimated at $5 million to the Public Utility Commission of Texas covering obligations of Con Edison Solutions as a retail electric provider. As part of the sale agreement for the retail electric supply business discussed above, the purchaser has agreed to pay Con Edison Solutions for draws on the guarantee to the Public Utility Commission of Texas.