XML 95 R71.htm IDEA: XBRL DOCUMENT v3.8.0.1
COMMITMENTS AND CONTINGENCIES - Schedule of Complaints and Base ROEs (Details) - USD ($)
$ in Millions
3 Months Ended 15 Months Ended 16 Months Ended 30 Months Ended 36 Months Ended
Mar. 27, 2018
Oct. 06, 2017
Jun. 08, 2017
Apr. 29, 2016
Mar. 31, 2018
Jul. 28, 2017
Mar. 26, 2014
Dec. 31, 2012
Oct. 30, 2015
Apr. 14, 2017
Oct. 15, 2014
FERC ROE First Complaint                      
Loss Contingencies [Line Items]                      
Original Base ROE Authorized by FERC at Time of Complaint (in percentage)               11.14%      
Base ROE Subsequently Authorized by FERC for First Complaint Period and also Effective from October 16, 2014 through April 14, 2017 (as a percentage)               10.57%   10.57%  
Reserve (Pre-Tax and Excluding Interest) as of March 31, 2018 (in millions)         $ 0.0            
Percentage of maximum ROE for any incentive project                   11.74%  
Customer refund payments         38.9            
FERC ROE Second Complaint                      
Loss Contingencies [Line Items]                      
Original Base ROE Authorized by FERC at Time of Complaint (in percentage)             11.14%        
Reserve (Pre-Tax and Excluding Interest) as of March 31, 2018 (in millions)         39.1            
FERC ALJ Recommendation of base ROE on Second and Third Complaints (Issued March 22, 2016) (in percentage)             9.59%        
Percentage of maximum ROE for any incentive project             11.74%        
Base ROE percentage of complaint period             10.57%        
FERC ROE Third Complaint                      
Loss Contingencies [Line Items]                      
Original Base ROE Authorized by FERC at Time of Complaint (in percentage)                 11.14%    
Base ROE Subsequently Authorized by FERC for First Complaint Period and also Effective from October 16, 2014 through April 14, 2017 (as a percentage)                 10.57%    
Reserve (Pre-Tax and Excluding Interest) as of March 31, 2018 (in millions)         0.0            
FERC ALJ Recommendation of base ROE on Second and Third Complaints (Issued March 22, 2016) (in percentage)                 10.90%    
FERC ROE Fourth Complaint                      
Loss Contingencies [Line Items]                      
Original Base ROE Authorized by FERC at Time of Complaint (in percentage)   11.74%       10.57%          
Base ROE Subsequently Authorized by FERC for First Complaint Period and also Effective from October 16, 2014 through April 14, 2017 (as a percentage)           10.57%          
Reserve (Pre-Tax and Excluding Interest) as of March 31, 2018 (in millions)         0.0            
FERC ALJ Recommendation of base ROE on Second and Third Complaints (Issued March 22, 2016) (in percentage)           10.57%          
Percentage of maximum ROE for any incentive project   10.57%                  
Base ROE percentage of complaint period 10.57%     10.57%              
FERC ROE First, Second and Third Complaints                      
Loss Contingencies [Line Items]                      
Percentage of maximum ROE for any incentive project     13.50%                
The Connecticut Light And Power Company | FERC ROE First Complaint                      
Loss Contingencies [Line Items]                      
Customer refund payments         22.4            
The Connecticut Light And Power Company | FERC ROE Second Complaint                      
Loss Contingencies [Line Items]                      
Reserve (Pre-Tax and Excluding Interest) as of March 31, 2018 (in millions)         21.4            
NSTAR Electric Company | FERC ROE First Complaint                      
Loss Contingencies [Line Items]                      
Customer refund payments         13.7            
NSTAR Electric Company | FERC ROE Second Complaint                      
Loss Contingencies [Line Items]                      
Reserve (Pre-Tax and Excluding Interest) as of March 31, 2018 (in millions)         14.6            
Public Service Company Of New Hampshire | FERC ROE First Complaint                      
Loss Contingencies [Line Items]                      
Customer refund payments         2.8            
Public Service Company Of New Hampshire | FERC ROE Second Complaint                      
Loss Contingencies [Line Items]                      
Reserve (Pre-Tax and Excluding Interest) as of March 31, 2018 (in millions)         $ 3.1            
Minimum | FERC ROE First, Second and Third Complaints                      
Loss Contingencies [Line Items]                      
Percentage of maximum ROE for any incentive project                     11.14%
Maximum | FERC ROE First, Second and Third Complaints                      
Loss Contingencies [Line Items]                      
Percentage of maximum ROE for any incentive project                     13.10%