XML 57 R28.htm IDEA: XBRL DOCUMENT v3.7.0.1
COMMITMENTS AND CONTINGENCIES (Tables)
3 Months Ended
Mar. 31, 2017
Commitments and Contingencies Disclosure [Abstract]  
Schedule of Environmental Loss Contingencies by Site
The number of environmental sites and related reserves for which remediation or long-term monitoring, preliminary site work or site assessment is being performed are as follows:
 
As of March 31, 2017
 
As of December 31, 2016
 
Number of Sites
 
Reserve
(in millions)
 
Number of Sites
 
Reserve
(in millions)
Eversource
60

 
$
58.2

 
61

 
$
65.8

CL&P
14

 
5.3

 
14

 
4.9

NSTAR Electric
13

 
1.0

 
13

 
3.2

PSNH
11

 
5.3

 
11

 
5.3

WMECO
4

 
0.7

 
4

 
0.6

Schedule of Guarantor Obligations
The following table summarizes Eversource parent's exposure to guarantees and indemnifications of its subsidiaries to external parties, as of March 31, 2017:  
Company
 
Description
 
Maximum
 Exposure
(in millions)
 
Expiration Dates
On behalf of subsidiaries:
 
 
 
 
 
 
Eversource Gas Transmission LLC
 
Access Northeast Project Capital Contributions Guaranty
 
$
185.1

 
2021
Various
 
Surety Bonds (1)
 
38.7

 
2017 - 2018
Eversource Service and Rocky River Realty Company
 
Lease Payments for Vehicles and Real Estate
 
8.8

 
2019 - 2024

(1) 
Surety bond expiration dates reflect termination dates, the majority of which will be renewed or extended.  Certain surety bonds contain credit ratings triggers that would require Eversource parent to post collateral in the event that the unsecured debt credit ratings of Eversource parent are downgraded.  
Schedule of Complaints and Base ROE
A summary of the four separate complaints and the base ROEs pertinent to those complaints are as follows:
Complaint
15-Month Time Period
of Complaint
(Beginning as of Complaint Filing Date)
Original Base ROE Authorized by FERC at Time of Complaint
Filing Date (1)
Base ROE Subsequently Authorized by FERC for First Complaint Period and also Effective from
October 16, 2014 through April 14, 2017 (1)
Reserve
(Pre-Tax and Excluding Interest) as of March 31, 2017
(in millions)
 
FERC ALJ Recommendation of Base ROE on Second and
Third Complaints
(Issued March 22, 2016)
First
10/1/2011 - 12/31/2012
11.14%
10.57%
$—
(2) 
N/A
Second
12/27/2012 - 3/26/2014
11.14%
N/A
39.1
(3) 
9.59%
Third
7/31/2014 - 10/30/2015
11.14%
10.57%
 
10.90%
Fourth
4/29/2016 - 7/28/2017
10.57%
10.57%
 
N/A

(1) The total ROE between October 1, 2011 and October 15, 2014 was within a range of 11.14 percent to 13.1 percent. In 2014, as a result of a FERC order, the incentive cap was set at 11.74 percent for the first complaint period and also effective from October 16, 2014 through April 14, 2017.
 
(2) CL&P, NSTAR Electric, PSNH and WMECO have refunded all amounts associated with the first complaint period, totaling $38.9 million (pre-tax and excluding interest) at Eversource (including $22.4 million at CL&P, $8.4 million at NSTAR Electric, $2.8 million at PSNH, and $5.3 million at WMECO), reflecting both the base ROE and incentive cap prescribed by the FERC order.

(3) The reserve represents the difference between the ROEs billed during the second complaint period and a 10.57 percent base ROE and 11.74 percent incentive cap. The reserve was $21.4 million for CL&P, $8.5 million for NSTAR Electric, $3.1 million for PSNH, and $6.1 million for WMECO as of March 31, 2017.