XML 35 R55.htm IDEA: XBRL DOCUMENT v2.4.0.8
Contractual Obligations with Yankee Companies (Details) (USD $)
In Millions, unless otherwise specified
9 Months Ended
Sep. 30, 2014
Jun. 30, 2014
Dec. 31, 2013
Loss Contingency, Information about Litigation Matters [Abstract]      
Court of Federal Claims Ruling To CYAPC     $ 126.3
Court Of Federal Claims Ruling To YAEC     73.3
Court Of Federal Claims Ruling To MYAPC     35.8
Connecticut Yankee Proceeds Received 90.0 36.3  
Yankee Atomic Proceeds Received 73.3    
Maine Yankee Proceeds Received $ 35.8    
Refund Obligation To Customers As of September 30, 2014, CL&P's refund obligation to customers of $65.4 million was recorded as an offset to the deferred storm restoration costs regulatory asset, as directed by PURA. NSTAR Electric's, PSNH's and WMECO's refund obligation to customers of $29.1 million, $13.1 million and $18.1 million, respectively, was recorded as a regulatory liability in each company's respective regulatory tracker mechanisms. Refunds to customers for these DOE proceeds began in the third quarter of 2014. For further information, see Note 2, "Regulatory Accounting," to the financial statements.    
MYAPC Phase One Damages Proceeds To Member Companies DOE Phase I Damages - Proceeds Received – On September 17, 2014, in accordance with the MYAPC refund plan, MYAPC returned a portion of the DOE Phase I Damages proceeds to the member companies, including CL&P, NSTAR Electric, PSNH, and WMECO, in the amount of $3.2 million, $1.1 million, $1.4 million and $0.8 million, respectively. These amounts reduced receivables at CL&P, NSTAR Electric, PSNH and WMECO.