-----BEGIN PRIVACY-ENHANCED MESSAGE----- Proc-Type: 2001,MIC-CLEAR Originator-Name: webmaster@www.sec.gov Originator-Key-Asymmetric: MFgwCgYEVQgBAQICAf8DSgAwRwJAW2sNKK9AVtBzYZmr6aGjlWyK3XmZv3dTINen TWSM7vrzLADbmYQaionwg5sDW3P6oaM5D3tdezXMm7z1T+B+twIDAQAB MIC-Info: RSA-MD5,RSA, AV2M7t6PZ6VH80V7sg/PUS/q9mw297MCOjckRIPaeAw6wbYKC1eu4YY710E5Ypna JVIEuUjpj5BTdXy2GSADRw== 0001108426-10-000022.txt : 20100301 0001108426-10-000022.hdr.sgml : 20100301 20100301105649 ACCESSION NUMBER: 0001108426-10-000022 CONFORMED SUBMISSION TYPE: 10-K PUBLIC DOCUMENT COUNT: 20 CONFORMED PERIOD OF REPORT: 20091231 FILED AS OF DATE: 20100301 DATE AS OF CHANGE: 20100301 FILER: COMPANY DATA: COMPANY CONFORMED NAME: TEXAS NEW MEXICO POWER CO CENTRAL INDEX KEY: 0000022767 STANDARD INDUSTRIAL CLASSIFICATION: ELECTRIC SERVICES [4911] IRS NUMBER: 750204070 STATE OF INCORPORATION: TX FISCAL YEAR END: 1231 FILING VALUES: FORM TYPE: 10-K SEC ACT: 1934 Act SEC FILE NUMBER: 002-97230 FILM NUMBER: 10642454 BUSINESS ADDRESS: STREET 1: 4100 INTERNATIONAL PLZ STREET 2: PO BOX 2943 CITY: FORT WORTH STATE: TX ZIP: 76113 BUSINESS PHONE: 8177310099 MAIL ADDRESS: STREET 1: 4100 INTERNATIONAL PLAZA STREET 2: PO BOX 2943 CITY: FORT WORTH STATE: TX ZIP: 76113 FORMER COMPANY: FORMER CONFORMED NAME: COMMUNITY PUBLIC SERVICE CO DATE OF NAME CHANGE: 19810617 FILER: COMPANY DATA: COMPANY CONFORMED NAME: PUBLIC SERVICE CO OF NEW MEXICO CENTRAL INDEX KEY: 0000081023 STANDARD INDUSTRIAL CLASSIFICATION: ELECTRIC & OTHER SERVICES COMBINED [4931] IRS NUMBER: 850019030 STATE OF INCORPORATION: NM FISCAL YEAR END: 1231 FILING VALUES: FORM TYPE: 10-K SEC ACT: 1934 Act SEC FILE NUMBER: 001-06986 FILM NUMBER: 10642453 BUSINESS ADDRESS: STREET 1: ALVARADO SQUARE CITY: ALBUQUERQUE STATE: NM ZIP: 87158 BUSINESS PHONE: 5058482700 MAIL ADDRESS: STREET 1: ALVARADO SQUARE CITY: ALBUQUERQUE STATE: NM ZIP: 87158 FILER: COMPANY DATA: COMPANY CONFORMED NAME: PNM RESOURCES INC CENTRAL INDEX KEY: 0001108426 STANDARD INDUSTRIAL CLASSIFICATION: ELECTRIC SERVICES [4911] IRS NUMBER: 850019030 STATE OF INCORPORATION: NM FISCAL YEAR END: 1231 FILING VALUES: FORM TYPE: 10-K SEC ACT: 1934 Act SEC FILE NUMBER: 001-32462 FILM NUMBER: 10642452 BUSINESS ADDRESS: STREET 1: ALVARADO SQUARE STREET 2: NEW MEXICO CITY: ALBUQUERQUE STATE: NM ZIP: 87158 BUSINESS PHONE: 5052412700 MAIL ADDRESS: STREET 1: ALVARADO SQUARE CITY: ALBUQUERQUE STATE: NM ZIP: 87158 FORMER COMPANY: FORMER CONFORMED NAME: MANZANO CORP DATE OF NAME CHANGE: 20000303 10-K 1 f10k_123109pnmr.htm FORM 10-K f10k_123109pnmr.htm

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
WASHINGTON, D.C. 20549
______________________
 
FORM 10-K

ANNUAL REPORT PURSUANT TO SECTION 13 OR 15(d)
OF THE SECURITIES EXCHANGE ACT OF 1934

For the Fiscal Year Ended December 31, 2009

Commission
File Number
 
Names of Registrants, State of Incorporation,
Address and Telephone Number
 
I.R.S. Employer
Identification No.
  001-32462
 
PNM Resources, Inc.
(A New Mexico Corporation)
Alvarado Square
Albuquerque, New Mexico  87158
(505) 241-2700
 
85-0468296
         
  001-06986 
 
Public Service Company of New Mexico
(A New Mexico Corporation)
Alvarado Square
Albuquerque, New Mexico  87158
(505) 241-2700
 
85-0019030
         
  002-97230
 
Texas-New Mexico Power Company
(A Texas Corporation)
577 N. Garden Ridge Blvd.
Lewisville, Texas  75067
(972) 420-4189
 
75-0204070

Securities Registered Pursuant To Section 12(b) Of The Act:
       
Name of Each Exchange
Registrant
 
Title of Each Class
 
on Which Registered
PNM Resources, Inc.
 
Common Stock, no par value
 
New York Stock Exchange

Securities Registered Pursuant To Section 12(g) Of The Act:
Registrant
 
Title of Each Class
Public Service Company of New Mexico
 
1965 Series, 4.58% Cumulative Preferred Stock
   
($100 stated value without sinking fund)

Indicate by check mark whether each registrant is a well-known seasoned issuer, as defined in Rule 405 of the Securities Act.
 
PNM Resources, Inc. (“PNMR”)
YES   ü
NO     
Public Service Company of New Mexico (“PNM”)
YES      
NO  ü
Texas-New Mexico Power Company (“TNMP”)
YES      
NO  ü
 
Indicate by check mark if each registrant is not required to file reports pursuant to Section 13 or Section 15(d) of the Act.

PNMR
YES      
NO  ü
PNM
YES      
NO  ü
TNMP
YES   ü
NO     


 
 

 

Indicate by check mark whether PNMR and PNM (1) have filed all reports required to be filed by Section 13 or 15(d) of the Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the registrant was required to file such reports) and (2) have been subject to such filing requirements for the past 90 days.  YES   ü    NO     

Indicate by check mark whether TNMP (1) has filed all reports required to be filed by Section 13 or 15(d) of the Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the registrant was required to file such reports) and (2) has been subject to such filing requirements for the past 90 days.
YES         NO  ü (NOTE:  As a voluntary filer, not subject to the filing requirements, TNMP filed all reports under Section 13 or 15(d) of the Securities Exchange Act of 1934 during the preceding 12 months.)

Indicate by check mark whether the registrants have submitted electronically and posted on its corporate Web sites, if any, every Interactive Data File required to be submitted and posted pursuant to Rule 405 of Regulation S-T during the preceding 12 months (or for such shorter period that the registrant was required to submit and post such files).  YES___    NO___  (NOTE:  No Interactive Data Files required to be submitted.)

Indicate by check mark if disclosure of delinquent filers pursuant to Item 405 of Regulation S-K is not contained herein, and will not be contained, to the best of registrants’ knowledge, in definitive proxy or information statements incorporated by reference in Part III of this Form 10-K or any amendment to this Form 10-K.  ü

Indicate by check mark whether registrant is a large accelerated filer, an accelerated filer, or a non-accelerated filer or a smaller reporting company (as defined in Rule 12b-2 of the Act).

 
Large accelerated filer
 
Accelerated filer
 
Non-accelerated filer
 
Smaller Reporting Company
PNMR
ü
 
   
 
   
 
   
PNM
   
 
   
 
ü
 
   
TNMP
   
 
   
 
ü
 
   

Indicate by check mark whether the registrants are a shell company (as defined in Rule 12b-2 of the Exchange Act). YES          NO   ü

As of February 15, 2010, shares of common stock outstanding were.

PNMR
86,673,174
PNM
39,117,799
TNMP
6,358

On June 30, 2009 the aggregate market value of the voting stock held by non-affiliates of PNMR as computed by reference to the New York Stock Exchange composite transaction closing price of $10.71 per share reported by The Wall Street Journal, was $925,123,470.

PNM AND TNMP MEET THE CONDITIONS SET FORTH IN GENERAL INSTRUCTIONS (I) (1) (a) AND (b) OF FORM 10-K AND ARE THEREFORE FILING THIS FORM WITH THE REDUCED DISCLOSURE FORMAT PURSUANT TO GENERAL INSTRUCTION (I) (2).

DOCUMENTS INCORPORATED BY REFERENCE

Portions of the following document are incorporated by reference into Part III of this report:

Proxy Statement to be filed by PNMR with the SEC pursuant to Regulation 14A relating to the annual meeting of stockholders of PNMR to be held on May 18, 2010.

This combined Form 10-K is separately filed by PNMR, PNM and TNMP.  Information contained herein relating to any individual registrant is filed by such registrant on its own behalf.  Each registrant makes no representation as to information relating to the other registrants.   When this Form 10-K is incorporated by reference into any filing with the SEC made by PNMR, PNM or TNMP, as a registrant, the portions of this Form 10-K that relate to each other registrant are not incorporated by reference therein.



 
ii

 

PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

 
 
 INDEX  
    Page
GLOSSARY
      iv
 PART I  
ITEM 1.     BUSINESS
 A-1
THE COMPANY  A-1
PNMR WEBSITE  A-1
OPERATIONS  A-2
PNM Electric  A-2
TNMP Electric  A-3
PNM Gas  A-4
Altura  A-4
Optim Energy  A-5
First Choice  A-5
Corporate and Other  A-6
SOURCES OF POWER  A-6
FUEL AND WATER SUPPLY  A-8
RATES AND REGULATION  A-9
ENVIRONMENTAL MATTERS  A-10
COMPETITION  A-11
EMPLOYEES  A-11
DISCLOSURE REGARDING FORARD LOOKING STATEMENTS  A-12
SECURITIES ACT DISCLAIMER  A-13
ITEM 1A.    RISK FACTORS  A-13
ITEM 1B.     UNRESOLVED STAFF COMMENTS  A-21
ITEM 2.        PROPERTIES  A-22
ITEM 3.        LEGAL PROCEEDINGS  A-24
ITEM 4.        SUBMISSION OF MATTERS TO A VOTE OF SECURITY HOLDERS  A-24
SUPPLEMENTAL ITEM – EXECUTIVE OFFICERS OF PNM RESOURCES, INC.  A-24
 PART II  
ITEM 5.      MARKET FOR PNMR’S COMMON EQUITY, RELATED  
STOCKHOLDER MATTERS AND ISSUER PURCHASES OF EQUITY SECURITIES   A-25
ITEM 6.      SELECTED FINANCIAL DATA  A-27
ITEM 7.      MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL  
CONDITION AND RESULTS OF OPERATIONS  A-31
ITEM 7A.  QUANTITATIVE AND QUALITATIVE DISCLOSURE ABOUT  
MARKET RISK  A-64
ITEM 8.      FINANCIAL STATEMENTS AND SUPPLEMENTARY DATA  B-1
ITEM 9.      CHANGES IN AND DISAGREEMENTS WITH ACCOUNTANTS ON  
ACCOUNTING AND FINANCIAL DISCLOSURE  C-1
ITEM 9A.   CONTROLS AND PROCEDURES
 C-1
ITEM 9B.    OTHER INFORMATION
 C-2
 PART III  
ITEM 10.     DIRECTORS, EXECUTIVE OFFICERS OF PNMR AND CORPORATE GOVERANCE
 C-2
ITEM 11.     EXECUTIVE COMPENSATION  C-3
ITEM 12.     SECURITY OWNERSHIP OF CERTAIN BENEFICIAL OWNERS AND  
MANAGEMENTAND RELATED STOCKHOLDER MATTERS  C-3
ITEM 13.     CERTAIN RELATIONSHIPS AND RELATED TRANSACTIONS,  
AND DIRECTOR INDEPENDENCE  C-3
ITEM 14.     PRINCIPAL ACCOUNTING FEES AND SERVICES  C-3
 PART IV  
ITEM 15.     EXHIBITS, FINANCIAL STATEMENT SCHEDULES
 D-1
 SIGNATURES  E-1
   


 
iii

 


Definitions:
   
Afton
Afton Generating Station
 
AG
New Mexico Attorney General
 
ALJ
Administrative Law Judge
 
Altura
Optim Energy Twin Oaks, LP; formerly known as Altura Power L.P.
 
Altura Cogen
Optim Energy Altura Cogen, LLC; formerly known as Altura Cogen, LLC (the CoGen Lyondell Power Generation Facility)
 
AOCI
Accumulated Other Comprehensive Income
 
APBO
Accumulated Postretirement Benefit Obligation
 
APS
Arizona Public Service Company, which is the operator and a co-owner of PVNGS and
  Four Corners
 
ARO
Asset Retirement Obligation
 
BART
Best Available Retrofit Technology
 
Board
Board of Directors of PNMR
 
BTU
British Thermal Unit
 
CAIR
Clean Air Interstate Rule
 
Cal PX
California Power Exchange
 
Cal ISO
California Independent System Operator
 
Cascade
Cascade Investment, L.L.C.
 
CCB
Coal Combustion Byproducts
 
Constellation
Constellation Energy Commodities Group, Inc.
 
Continental
Continental Energy Systems, L.L.C.
 
CRHC
Cap Rock Holding Corporation, a subsidiary of Continental
 
CTC
Competition Transition Charge
 
Decatherm
Million BTUs
 
Delta
Delta-Person Limited Partnership
 
DOE
Department of Energy
 
ECJV
ECJV Holdings, LLC
 
EIP
Eastern Interconnection Project
 
EnergyCo
EnergyCo, LLC, a limited liability company, owned 50% by each of PNMR and ECJV; now known as Optim Energy
 
EPA
United States Environmental Protection Agency
 
EPE
El Paso Electric
 
ERCOT
Electric Reliability Council of Texas
 
ESPP
Employee Stock Purchase Plan
 
FASB
Financial Accounting Standards Board
 
FERC
Federal Energy Regulatory Commission
 
FIP
Federal Implementation Plan
 
First Choice
First Choice Power, L. P. and Subsidiaries
 
Four Corners
Four Corners Power Plant
 
FPL
FPL Energy New Mexico Wind, LLC
 
FPPAC
Fuel and Purchased Power Adjustment Clause
 
GAAP
Generally Accepted Accounting Principles in the United States of America
 
GEaR
Gross Earnings at Risk
 
GHG
Greenhouse Gas Emissions
 
GWh
Gigawatt hours
 
IBEW
International Brotherhood of Electrical Workers, Local 611
 
IRS
Internal Revenue Service
 
ISO
Independent System Operator
 
KWh
Kilowatt Hour
 
LBB
Lehman Brothers Bank, FSB, a subsidiary of LBH
 
LBCS
Lehman Brothers Commodity Services, a subsidiary of LBH
 
LBH
Lehman Brothers Holdings Inc.
 
LCC
Lyondell Chemical Company
 
LIBOR
London Interbank Offered Rate
 
Lordsburg
Lordsburg Generating Station
 
 
 
iv

 
Luna
Luna Energy Facility
 
MD&A
Management’s Discussion and Analysis of Financial Condition and Results of Operations
 
Moody’s
Moody’s Investor Services, Inc.
 
MW
Megawatt
 
MWh
Megawatt Hour
 
Navajo Acts
Navajo Nation Air Pollution Prevention and Control Act, the Navajo Nation Safe Drinking Water Act, and the Navajo Nation Pesticide Act
 
NDT
Nuclear Decommissioning Trusts for PVNGS
 
Ninth Circuit
United States Court of Appeals for the Ninth Circuit
 
NMGC
New Mexico Gas Company, a subsidiary of Continental
 
NMED
New Mexico Environment Department
 
NMPRC
New Mexico Public Regulation Commission
 
NOX
Nitrogen Oxides
 
NOI
Notice of Inquiry
 
NRC
United States Nuclear Regulatory Commission
 
NSR
New Source Review
 
O&M
Operations and Maintenance
 
OCI
Other Comprehensive Income
 
OPEB
Other Post Employment Benefits
 
Optim Energy
Optim Energy, LLC, a limited liability company, owned 50% by each of PNMR and ECJV; formerly known as EnergyCo
 
PBO
Projected Benefit Obligation
 
PCRBs
Pollution Control Revenue Bonds
 
PGAC
Purchased Gas Adjustment Clause
 
PG&E
Pacific Gas and Electric Co.
 
PNM
Public Service Company of New Mexico and Subsidiaries
 
PNM Facility
PNM’s $400 Million Unsecured Revolving Credit Facility
 
PNMR
PNM Resources, Inc. and Subsidiaries
 
PNMR Facility
PNMR’s $600 Million Unsecured Revolving Credit Facility
 
PPA
Power Purchase Agreement
 
PRP
Potential Responsible Party
 
PSA
Power Supply Agreement
 
PSD
Prevention of Significant Deterioration
 
PUCT
Public Utility Commission of Texas
 
PV
Photovoltaic
 
PVNGS
Palo Verde Nuclear Generating Station
 
Pyramid
Tri-State Pyramid Unit 4
 
RCRA
Resource Conservation and Recovery Act
 
RCT
Reasonable Cost Threshold
 
REC
Renewable Energy Certificates
 
Reimbursement Agreement
PNM’s $100 Million Letter of Credit Facility
 
REP
Retail Electricity Provider
 
RMC
Risk Management Committee
 
SCE
Southern Cal Edison Company
 
SCPPA
Southern California Public Power Authority
 
SEC
United States Securities and Exchange Commission
 
SJCC
San Juan Coal Company
 
SJGS
San Juan Generating Station
 
SO2
Sulfur Dioxide
 
SPS
Southwestern Public Service Company
 
SRP
Salt River Project
 
S&P
Standard and Poor’s Ratings Services
 
TCEQ
Texas Commission of Environmental Quality
 
TECA
Texas Electric Choice Act
 
Term Loan Agreement
PNM’s $300 Million Unsecured Delayed Draw Term Loan Facility
 
Throughput
Volumes of gas delivered, whether or not owned
 
TNMP Texas-New Mexico Power Company and Subsidiaries  
TNMP Bridge Facility
TNMP’s $100 Million Bridge Term Loan Credit Agreement
 
     
 
 
v

 
TNMP Facility
TNMP’s $200 Million Unsecured Revolving Credit Facility
 
TNP
TNP Enterprises, Inc. and Subsidiaries
 
TNMP Revolving Credit
   Facility
 
TNMP's $75 million Unsecured Revolving Credit Facility
 
Tri-State
Tri-State Generation and Transmission Association, Inc.
 
Tucson
Tucson Electric Power Company
 
Twin Oaks
Assets of Twin Oaks Power, L.P. and Twin Oaks Power III, L.P.
 
UAMPS
Utah Associated Municipal Power System
 
Valencia
Valencia Energy Facility
 
VaR
Value at Risk
 
WSPP
Western Systems Power Pool
 
     


 
vi

 

PART I

ITEM 1.
BUSINESS

THE COMPANY

Overview

    PNMR is an investor-owned holding company of energy and energy-related businesses.  PNMR’s primary subsidiaries are PNM, TNMP, and First Choice.  PNM is a public utility with regulated operations primarily engaged in the generation, transmission and distribution of electricity and, through January 29, 2009, the transmission and distribution and sale of natural gas.  PNM began service to New Mexico customers formerly served by TNMP effective January 1, 2007.  TNMP is a regulated utility operating in Texas and through December 31, 2006 in New Mexico.  In Texas, TNMP provides regulated transmission and distribution services.  First Choice is a competitive REP operating in Texas.  PNMR owns 50% of Optim Energy (formerly, EnergyCo), which is focused on unregulated electric operations, principally within the areas of Texas covered by ERCOT, including the development, operation and ownership of diverse generation assets and wholesale marketing.

    On January 12, 2008, PNM entered into an agreement to sell its natural gas operations, which comprised the PNM Gas segment, to NMGC, a subsidiary of Continental, for $620.0 million in cash, subject to adjustment based on the level of working capital at closing.  Financial information regarding PNM’s gas operations, which are reflected as discontinued operations herein, is presented in Note 23.  In a separate transaction conditioned upon the sale of the natural gas operations, PNMR proposed to acquire CRHC, Continental’s regulated Texas electric transmission and distribution business, for $202.5 million in cash.  On July 22, 2008, PNMR and Continental agreed to terminate the agreement for the acquisition of CRHC.  The termination agreement provided that Continental pay PNMR $15.0 million upon the closing of the PNM Gas transaction.  PNMR completed the sale of its gas operations on January 30, 2009.  PNM used proceeds from the sale to retire short-term debt and paid a dividend of $220.0 million to PNMR. The remaining proceeds were used to pay income taxes on the gain from the sale.  PNMR used the dividend from PNM and the $15.0 million from Continental to retire debt.

    PNMR’s common stock trades on the New York Stock Exchange under the symbol PNM.  PNMR was incorporated in the State of New Mexico in 2000.

Other Information

    These filings for PNMR, PNM and TNMP include disclosures for PNMR, PNM and TNMP.  For discussion purposes, this report will use the term “Company” when discussing matters of common applicability to PNMR, PNM and TNMP.  Discussions regarding only PNMR, PNM or TNMP will be indicated as such.  A reference to “MD&A” in this report refers to Part II, Item 7. – Management’s Discussion and Analysis of Financial Condition and Results of Operations in this report.  A reference to a “Note” refers to the accompanying Notes to Consolidated Financial Statements.

Financial information relating to amounts of sales, revenue, net income and total assets of reportable segments is contained in Part II, Item 7. - Management’s Discussion and Analysis of Financial Condition and Results of Operations and Note 3.

WEBSITES
 
The PNMR website, www.pnmresources.com, is an important source of Company information and PNMR encourages investors, analysts and other interested parties to visit the website frequently. PNMR keeps the site updated and routinely posts new or updated information. PNMR encourages analysts, investors and other interested parties to register on the website to automatically receive Company information by e-mail. Once registered, participants can choose from a menu to automatically receive requested information, including news releases, notices of webcasts and filings with the SEC. Participants can unsubscribe at any time and will not receive information that was not requested.
 
PNMR’s Internet address is http://www.pnmresources.com; PNM’s Internet address is http://www.pnm.com; TNMP’s Internet address is http://www.tnpe.com.  The contents of these websites are not a part of this Form 10-K.  The filings of PNMR, PNM, and TNMP with the SEC, including annual reports on Form 10-K, quarterly reports on
 
 
A-1

 
Form 10-Q, current reports on Form 8-K and amendments to those reports, filed or furnished pursuant to Section 13(a) or 15(d) of the Securities and Exchange Act of 1934, are accessible free of charge at http://www.pnmresources.com as soon as reasonably practicable after they are filed with, or furnished to, the SEC.  These reports are also available upon request in print from PNMR free of charge.  Additionally, PNMR's Corporate Governance Principles, code of ethics (Do the Right Thing-Principles of Business Conduct) and charters of its Audit and Ethics Committee, Board Governance and Human Resources Committee, Finance Committee, and Public Policy and Sustainability Committee are available at http://www.pnmresources.com/investors/governance.cfm and such information is available in print, without charge, to any shareholder who requests it.   The Company will post amendments to or waivers from its code of ethics (to the extent applicable to the Company’s executive officers and directors) at this location on its website.

OPERATIONS

PNM Electric

    PNM Electric is an electric utility that is primarily focused on providing service to its rate-regulated customers.  PNM Electric’s operations consist of generation, transmission and distribution of electricity for retail electric customers in New Mexico subject to the jurisdiction of the NMPRC and for wholesale customers in New Mexico and Arizona subject to the jurisdiction of FERC.  PNM Electric also provides transmission services to third parties.  PNM Electric also includes the generation and sale of electricity into the wholesale market.  PNM Electric provides retail electric service to a large area of north central New Mexico, including the cities of Albuquerque and Santa Fe, and certain other areas of southern New Mexico, including those formerly served by TNMP.  PNM Electric owns or leases transmission lines, interconnected with other utilities in New Mexico, Texas, Arizona, Colorado and Utah.  The largest non-affiliated retail electric customer served by PNM Electric accounted for 2.5% of the PNM Electric’s revenues for the year ended December 31, 2009. PNM was incorporated in the State of New Mexico in 1917.

Customer rates for retail electric service are set by the NMPRC.  In February 2007, PNM filed a general rate case with the NMPRC for all of its New Mexico retail customers except those formerly served by TNMP.  Following NMPRC approvals, PNM implemented new electric rates reflecting an annual $34.4 million rate increase in May 2008 and, beginning in June 2008, an Emergency FPPAC through which changes in the cost of fuel and purchased power, above or below the costs included in base rates, are passed through to customers on a monthly basis. In September 2008, PNM filed its 2008 Electric Rate Case requesting an increase in electric rates of $123.3 million and a more traditional FPPAC.  In this rate case, PNM proposed that its Luna and Lordsburg generating plants, as well as the Valencia PPA and the portion of PVNGS Unit 2 previously owned by another subsidiary of PNMR and leased to PNM, be included in resources subject to NMPRC jurisdiction and recovered through rates charged to retail customers.  In June 2009, the NMPRC approved a stipulation resolving all issues in the 2008 Electric Rate Case, including the inclusion of additional sources of power in determining rates.  The approved stipulation allows for an increase in annual non-fuel revenues of $77.1 million, 65% of which was implemented for bills rendered beginning July 1, 2009 and the remainder of which will be implemented April 1, 2010.  As an offset to the non-fuel revenue increase, PNM implemented a credit to customers totaling $26.3 million, representing the amount of revenues from past sales of SO2 allowances. This amount is being credited to customers over 21 months beginning July 1, 2009. PNM is prohibited from requesting a rate increase that would go into effect prior to January 1, 2011 for customers formerly served by TNMP.

Weather-normalized retail electric loads decreased by 1.7% in 2009.  PNM Electric’s system peak demands for its retail customers and firm requirements customers in the summer and the winter for the last three years are shown in the following table:

System Peak Demands

 
2009
 
2008
 
2007
 
(Megawatts)
           
Summer
1,866
 
1,901
 
1,933
Winter
1,531
 
1,643
 
1,606


 
A-2

 
PNM holds long-term, non-exclusive franchise agreements for its electric retail operations, with varying expiration dates.  These franchise agreements allow PNM to access public rights-of-way for placement of PNM’s electric facilities.  Franchise agreements have expired in some areas PNM serves, including Albuquerque, Santa Fe, and the City of Rio Rancho.  PNM remains obligated under New Mexico state law to provide service to customers in these franchise areas despite the absence of an effective franchise agreement, so the expirations should not have a material adverse impact on PNM’s business.  The Albuquerque, Rio Rancho, and Santa Fe metropolitan areas accounted for 43.7%, 9.1%, and 8.6% of PNM Electric’s 2009 revenues and no other franchise area represents more than 5%.  Although PNM does not collect or pay franchise fees in some areas it serves, PNM continues to collect and pay franchise fees in certain parts of its service territory, including Albuquerque, Santa Fe, and the City of Rio Rancho. A recent New Mexico Court of Appeals decision has raised concerns about the lawfulness of continuing to abide by expired franchise arrangements more than 25 years after the franchise was initially entered into.  The New Mexico Legislature has passed a bill validating the continuing use of expired franchise agreements regardless of age.  The Governor of New Mexico has until noon March 10, 2010 to sign or veto the bill.  Although the Company cannot predict what the Governor will do, it expects him to sign the bill. 

PNM Electric owns or leases 3,170 circuit miles of electric transmission lines, interconnected with other utilities in New Mexico, Arizona, Colorado, Texas and Utah.  Due to rapid load growth in PNM Electric’s service territory in recent years and the lack of transmission development, most of the capacity on this transmission system is fully committed during peak hours and there is very little or no additional access available on a firm commitment basis. These factors result in physical constraints on the system and limit the ability to wheel power into PNM Electric’s service area from outside of New Mexico.

PNM Electric includes wholesale activities that consist of the generation and sale of electricity into the wholesale market.   PNMR completed its undertaking to move away from certain wholesale merchant activities within PNM Electric.  In June 2008, PNM completed the sale of certain wholesale power, natural gas and transmission contracts. See Note 8.  In addition, the Luna and Lordsburg assets became included in retail rates beginning in July 2009 with the rates set pursuant to PNM’s 2008 Electric Rate Case.  See Note 17.  Because PNM's share of Unit 3 at the PVNGS is excluded from retail rates, it can remain within PNM and its power can continue to be sold on the wholesale market. In April 2008, PNM entered into three separate contracts for the sale of capacity and energy related to its entire ownership interest in PVNGS Unit 3, which is 135 MW, through December 31, 2010.  PNM Electric also engages in activities to optimize its existing jurisdictional assets and long-term purchase power agreements through spot market, hour ahead, day ahead, week ahead and other sales of any excess generation not required to fulfill PNM Electric’s retail load and contractual commitments.  Revenues from these sales are credited to retail customers through the FPPAC.

PNM Electric has entered into various firm-requirements wholesale electric sales contracts.  These contracts contain fixed capacity charges in addition to energy charges.  Capacity charges are fixed monthly payments for a commitment of resources to service the contract requirements.  Energy charges are payments based on the amount of electricity delivered to the customer intended to compensate PNM Electric for its variable costs incurred to provide the energy.  PNM Electric’s firm-requirements demand was 110 MW in 2009, and is expected, based solely on existing contracts, to be 108 MW in 2010, 111 MW in 2011, and 115 MW in 2012.  No firm-requirements customer of PNM Electric accounted for more than 1.7% of the PNM Electric's revenues for the year ended December 31, 2009.

TNMP Electric

    TNMP Electric consists of all the operations of TNMP.  TNMP is a regulated utility operating in Texas and, through December 31, 2006, in New Mexico. TNMP’s predecessor was organized in 1925 and TNMP is incorporated in the State of Texas.

In Texas, TNMP Electric provides regulated transmission and distribution services under the provisions of TECA and the Texas Public Utility Regulatory Act.  TNMP Electric serves a market of small-to-medium-sized communities most of which have populations of less than 50,000.  In most areas that TNMP Electric serves, it is the exclusive provider of transmission and distribution services.

TNMP Electric’s Texas territory consists of three non-contiguous areas.  One portion of this territory extends from Lewisville, which is approximately 10 miles north of the Dallas-Fort Worth International Airport, eastward to municipalities near the Red River, and to communities north, west and south of Fort Worth.  The second portion of
 
 
A-3

 
its territory includes the area along the Texas Gulf Coast between Houston and Galveston, and the third portion includes areas of far west Texas between Midland and El Paso.  TNMP Electric’s Texas operations lie entirely within the ERCOT region.  ERCOT is the independent system operator that is responsible for maintaining reliable operations for the bulk electric power supply system in the ERCOT region, which is located entirely within Texas.  See Rates and Regulation below for more information about ERCOT.

TNMP Electric provides transmission and distribution services at regulated rates to various REPs that, in turn, provide retail electric service within TNMP Electric’s Texas service area.  As of December 31, 2009, 70 active REPs served customers that receive transmission and distribution services from TNMP Electric.  First Choice, TNMP Electric’s affiliated REP, was TNMP Electric’s largest customer and accounted for 21.5% of TNMP's revenues for the year ended December 31, 2009.  Revenues of TNMP’s next largest customers accounted for 20.4% and 13.0% of revenues.  No other customers accounted for more than 10% of revenues.
 
In August 2008, TNMP filed with the PUCT for an $8.7 million increase in revenues, which would be TNMP’s first increase in rates since 2002.  Hurricane Ike, which struck the Texas Gulf Coast on September 13, 2008, caused extensive damage to the city of Galveston and the surrounding communities.  In March 2009, TNMP filed supplemental testimony, requesting an additional revenue increase of $15.7 million annually relating to costs incurred during Hurricane Ike and anticipated increased financing costs. In June 2009, TNMP and the other parties in the rate case announced that a unanimous settlement had been reached. The settlement permits TNMP to increase revenues by $12.7 million annually.  This increase reflects interest and other costs associated with its March 2009 debt refinancing and the settlement adjusts the interest rate TNMP is allowed to collect on its CTC to reflect those costs.  The rate increase includes recovery of $17.6 million of Hurricane Ike restoration costs plus carrying costs over five years. The settlement was approved by the PUCT in August 2009 and rates went into effect for bills rendered on or after September 1, 2009.
 
TNMP holds long-term, non-exclusive franchise agreements for its electric transmission and distribution services with varying expiration dates, including some that have expired.  TNMP intends to negotiate and execute new or amended franchise agreements with municipalities where the agreements have expired or will be expiring.  Since TNMP Electric is the exclusive provider of transmission and distribution services in most areas that it serves, the need to renew or renegotiate franchise agreements should not have a material adverse impact on TNMP’s business.  TNMP also earns revenues from service provided to facilities in its service area that lie outside the territorial jurisdiction of the municipalities with which TNMP has franchise agreements.

PNM Gas

PNM Gas distributed natural gas to most of the large communities in New Mexico, including Albuquerque and Santa Fe, through January 29, 2009 under rates that were subject to traditional rate regulation by the NMPRC.  On January 12, 2008, PNM entered into an agreement to sell PNM Gas.   On January 30, 2009, PNM completed the sale.  See Note 2 and Note 23.

PNM Gas had a customer base that included both sales-service customers and transportation-service customers.  Sales-service customers purchased natural gas and received transportation and delivery services from PNM Gas for which PNM Gas received both cost-of-gas and cost-of-service revenues.  Cost-of-gas revenues collected from its sales-service customers were recovered in accordance with NMPRC regulations through the PNM Gas PGAC and represented a pass-through of the cost of natural gas to the customer.  As a result, increases or decreases in gas revenues resulting from wholesale gas price fluctuations did not impact gross margin.  Additionally, PNM Gas made occasional gas sales to off-system sales customers.  Off-system sales deliveries generally occurred at pipeline interconnections with the PNM Gas system and profits were shared between PNM Gas and its regulated customers on a 30%/70% basis.

Altura

    On April 18, 2006, PNMR’s wholly owned subsidiary, Altura, purchased Twin Oaks, which included a 305 MW coal-fired power plant located 150 miles south of Dallas, Texas.  PNMR acquired Twin Oaks to expand its merchant generation capacity in order to serve a growing wholesale market in the Southwest. Effective June 1, 2007, PNMR contributed Altura, including Twin Oaks, to Optim Energy.  See Note 2 and Note 22.  The results of Twin
 
 
A-4

 
Oaks operations have been included in the Consolidated Financial Statements of PNMR from April 18, 2006 through May 31, 2007.

Optim Energy

In January 2007, PNMR and ECJV created EnergyCo to serve expanding U.S. markets, principally the areas of Texas covered by ERCOT.  In February 2009, the name of EnergyCo was changed to Optim Energy and references to Optim Energy herein encompass periods prior to the name change.  ECJV is a wholly owned subsidiary of Cascade, which is a large PNMR shareholder.  PNMR and ECJV each have a 50 percent ownership interest in Optim Energy, a limited liability company.  On June 1, 2007, PNMR contributed its ownership of Altura, including the Twin Oaks plant, to Optim Energy at fair value of $549.6 million, as adjusted to reflect changes in working capital.  ECJV made a cash contribution to Optim Energy equal to 50% of the fair value amount and Optim Energy distributed that cash to PNMR. In August 2007, Optim Energy completed the acquisition of the Altura Cogen plant, a cogeneration electric and steam generating plant.  Optim Energy co-developed another electric generating unit at Cedar Bayou that was completed in June 2009.

Optim Energy’s strategy had been focused on expanding unregulated operations in one of the nation’s growing power markets.  Optim Energy’s business consisted of development, operation and ownership of diverse generation assets, and wholesale marketing to optimize its assets. In 2009, Optim Energy was affected by continuing adverse market conditions, primarily low natural gas and power prices.  In response to those adverse conditions, Optim Energy changed its current strategy and near-term focus in October 2009. Optim Energy is currently focused on utilizing cash flow from operations to reduce debt and optimizing its current generation assets as a stand-alone independent power producer.  The goal is to position Optim Energy to optimize its performance under current market conditions with the expectation of being able to take advantage of any economic recovery in the power and gas markets over the next several years.

 PNMR accounts for its 50% ownership interest in Optim Energy using the equity method of accounting because PNMR’s ownership interest results in significant influence, but not control, over Optim Energy and its operations.  PNMR records as income its percentage share of earnings or losses of Optim Energy and carries its investment at cost, adjusted for its share of undistributed earnings or losses.  Accordingly, Optim Energy’s revenues and expenses are not included in PNMR’s consolidated revenues and expenses. See Note 22.

First Choice

First Choice is a certified REP operating in ERCOT, which provides electricity to residential, small commercial and governmental customers.  First Choice’s services include acquiring retail customers, setting up retail accounts, handling customer inquiries and complaints, and acting as a liaison between the transmission and distribution companies and retail customers.  First Choice focuses its competitive customer acquisition efforts in the major Texas metropolitan areas that are open to electric choice within ERCOT, including Dallas-Fort Worth, Houston, Corpus Christi, and McAllen-Harlingen.  Due to the competitive nature of the Texas market, First Choice, similar to other REPs, experiences significant turnover in its customer base.  There is no provision under Texas regulation that requires customers to pay their previous REP before obtaining service from another REP.  In 2008 and early 2009, this was exacerbated by the impacts of Hurricane Ike and depressed economic conditions, which resulted in significant increases in the levels of uncollectible accounts and bad debt expense.  Although First Choice is regulated in certain respects by the PUCT under ERCOT, its business is not subject to traditional rate of return regulation.

First Choice’s load fluctuates continuously due to, among other things, customer additions and losses, changes in customer usage, and seasonality of weather.  First Choice continually monitors and revises its load forecast to account for changing competitive customer loads.  First Choice develops short-term load forecasts to identify short-term load surpluses and shortages, and to ensure that hedges are in place to cover forecasted sales.  To the extent these short-term load forecasts identify shortages, First Choice covers shortages through short-term power purchases or through purchases on the ERCOT balancing market.

First Choice experiences increased sales and operating revenues during the summer months as a result of increased air conditioner usage in hot weather.  In 2009, approximately 33% of First Choice’s consolidated annual revenues were recorded in June, July, and August.

 
A-5

 
    First Choice is exposed to market risk to the extent that its retail rates or cost of supply fluctuates with market prices.  Additionally, fluctuations in First Choice retail load requirements that are greater than anticipated may subject First Choice to market risk.  First Choice’s basic strategy is to minimize its exposure to fluctuations in market energy prices by matching fixed price sales contracts with fixed price supply.

Corporate and Other

PNMR Services Company provides corporate services through shared services agreements to PNMR, to all of PNMR's business units, including First Choice, PNM and TNMP, and to Optim Energy.  These services are charged and billed on a monthly basis to the business units.  Billings are at cost, except for Optim Energy, which includes a profit element.  PNMR Services Company is included in the Corporate and Other segment.

SOURCES OF POWER

PNMR

First Choice assumed the energy supply activities of TNMP in Texas in 2002.  Constellation was the primary supplier of power for First Choice’s customers through the end of 2006.  Additionally, Constellation agreed to supply power in certain transactions under the PSA beyond the date when that commitment expired.  The obligations of Constellation were extended until January 31, 2008.  First Choice currently has no long-term power supply agreements.  Therefore, First Choice is exposed to market risk if power prices increase faster or in excess of its ability to increase rates to its customers.  Power to serve First Choice’s customers is being obtained through short-term market purchases.

PNM

As of December 31, 2009, the total net generation capacity of facilities owned or leased by PNM was 2,336 MW.  See Item 2. Properties.  PNM also obtains power under long-term PPAs as described below.  PNM Electric’s total generation capacity from these sources is:

Owned and leased
2,336 MW
Long-term PPAs:
 
New Mexico Wind Energy Center
200 MW
SPS contingent
125 MW
Tri-State
50 MW
Total
2,711 MW

Owned and Leased

SJGS’ equivalent availability was 84.9% and 76.5% for the years ended December 31, 2009 and 2008.  PVNGS’ equivalent availability was 87.0% and 83.0% for the years ended December 31, 2009 and 2008.  Four Corners’ equivalent availability was 87.5% and 78.8% for the years ended December 31, 2009 and 2008.  SJGS is operated by PNM. Four Corners and PVNGS are operated by APS.

PNM’s Lordsburg plant was built to serve wholesale customers and other sales rather than New Mexico retail customers.  In 2004, a subsidiary of PNMR purchased a one-third interest in Luna, a 570 MW, partially constructed, natural gas-fired power plant near Deming in southern New Mexico.  In 2005, the one-third interest in Luna was transferred to PNM.  These plants became included in retail rates beginning in July 2009 pursuant to the 2008 Electric Rate Case.   See Note 17.

In 2007, PNM Electric completed the conversion of Afton to a combined cycle plant.  The NMPRC approved bringing Afton into retail rates, with 50% of Afton's capacity designated to serve customers formerly served by TNMP that became customers of PNM effective January 1, 2007, and the other 50% designated to serve PNM Electric's other retail customers.

PNM leases portions of PVNGS and the lease payments are recovered through retail rates approved by the NMPRC.  In July 2009, PNM acquired the ownership of a portion of PVNGS Unit 2 previously owned by another
 
 
A-6

 
PNMR subsidiary and leased to PNM, including it in rates charged to retail customers on an ownership basis.  See Item 2. Properties, Note 7, and Note 17 for additional information.

In 1996, PNM entered into an operating lease agreement for the rights to all the output of the Delta gas-fired generating plant for 20 years.  The plant received FERC approval for "exempt wholesale generator" status. The maximum dependable capacity under the lease is 132 MW.  The gas turbine generating unit is operated by Delta and is located on PNM’s retired Person Generating Station site in Albuquerque.  Primary fuel for the gas turbine generating unit is natural gas provided by wholesale gas purchases.  In addition, the unit has the capability to utilize low sulfur fuel oil if natural gas is neither available nor cost effective.

On April 18, 2007, PNM entered into a PPA to purchase all of the electric capacity and energy from Valencia, a natural gas-fired power plant near Belen, New Mexico.  Valencia became operational on May 30, 2008.  A third-party built, owns and operates the facility.  PNM is the sole purchaser of the electricity generated. The term of the PPA is for 20 years beginning June 1, 2008.  Valencia became included in retail rates charged to customers beginning with the 2008 Electric Rate Case.  PNM has evaluated the accounting treatment of this arrangement and concluded that the third party entity that owns Valencia is a variable interest entity and that PNM is the primary beneficiary of the entity under GAAP since PNM will absorb the majority of the variability in the cash flows of the plant.  As the primary beneficiary, PNM consolidates the entity in its financial statements.  Accordingly, the assets of Valencia are included in the consolidated financial statements of PNM although PNM has no legal ownership interest or voting control of the variable interest entity.  The 145 MW capacity of Valencia is reflected as owned in the above table.  See Note 9 and Note 17.

Joint Projects

SJGS, PVNGS, and Four Corners are joint projects each owned or leased by several different utilities.  Some participants in the joint projects are investor-owned utilities, while others are municipally or co-operatively owned.  Furthermore, participants in SJGS and Four Corners may have varying percentage interests in different generating units within the project.  The primary operating or participation agreements for the joint projects expire in 2017 for Four Corners, 2022 for SJGS, and 2027 for PVNGS.  In addition, SJGS and Four Corners are coal-fired generating plants that obtain their coal requirements from mines near the plants.  The agreements for coal supply expire in 2016 for Four Corners and 2017 for SJGS.  Four Corners is situated on land under a lease from the Navajo Nation, which expires in 2017, but provides for a 50 year renewal option.  Portions of PNM’s interests in PVNGS Units 1 and 2 are through leases that expire in 2015 and 2016, but contain certain fixed-rate renewal and fair market value purchase options.  Several of the participants in the joint projects are located in California.  There are legislative and regulatory mandates in California that prohibit utilities from entering into new, or extending existing, arrangements for coal-fired generation.  It is also possible that the participants in the joint projects have changed circumstances and objectives from those existing at the time of becoming participants.  The status of the joint projects is further complicated by the uncertainty surrounding the form of potential legislation and/or regulation of GHG, CCBs and other air emissions, as well as the impacts of the costs of compliance and operational viability of all or certain units within the joint projects.  It is unclear how these factors will enter into discussion and negotiations concerning the status of the joint projects as the expiration of basic operational agreements approaches and PNM can provide no assurance that its participation in the joint projects will continue in the manner that currently exists.

PPAs

In addition to generating its own power, PNM Electric purchases power in the open market under long-term PPAs.  PNM also purchases power in the forward, day-ahead and real-time markets.

In 2002, PNM entered into an agreement with FPL to develop a 200 MW wind generation facility in New Mexico.  PNM began receiving commercial power from the project in June 2003.  FPL owns and operates the New Mexico Wind Energy Center, which consists of 136 wind-powered turbines on a site in eastern New Mexico.  PNM has a contract to purchase all the power and RECs generated by the New Mexico Wind Energy Center for 25 years.  In 2003, PNM received approval from the NMPRC for a voluntary tariff that allows PNM retail customers to buy wind-generated electricity for a small monthly premium.  Power from the New Mexico Wind Energy Center is used to service load under the voluntary tariff and as part of PNM’s electric supply mix for meeting retail load, as well as for meeting wholesale load.

 
A-7

 
In addition, PNM has long-term PPAs with SPS to purchase 125 MW of interruptible power through November 2010, reducing to 100 MW through May 2011, and with Tri-State to purchase 50 MW of firm power and capacity through June 2010.  See Owned and Leased above regarding the Valencia PPA.
 
A summary of purchased power is as follows:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
                   
Purchased under long-term PPAs
                 
MWh
    1,574,062       2,274,276       2,370,364  
Cost per MWh
  $ 48.64     $ 57.43     $ 47.23  
                         
Other purchased power
                       
Total MWh
    1,083,272       2,640,131       6,575,882  
Cost per MWh
  $ 37.42     $ 68.82     $ 61.97  

TNMP

TNMP provides only transmission and distribution services and does not sell power.

FUEL AND WATER SUPPLY

PNMR

The coal requirements for Twin Oaks were supplied by a long-term fuel supply agreement during the period PNMR owned Twin Oaks.  PNMR and Altura are not responsible under this agreement for the decommissioning or reclamation costs of the supplying mine.  Upon PNMR’s contribution of Altura to Optim Energy, PNMR has no benefits or obligations under this fuel supply agreement.

PNM

The percentages of PNM’s generation of electricity (on the basis of KWh) fueled by coal, nuclear fuel and gas and oil, and the average costs to PNM of those fuels per million BTU, during the past three years were as follows:

 
Coal
 
Nuclear
 
Gas and Oil
 
Percent of
 
Average
 
Percent of
 
Average
 
Percent of
 
Average
 
Generation
 
Cost
 
Generation
 
Cost
 
Generation
 
Cost
                       
2009
61.3%
 
$2.25
 
27.6%
 
$0.56
 
11.1%
 
$3.52
2008
58.7%
 
$2.28
 
27.9%
 
$0.51
 
13.4%
 
$8.10
2007
65.1%
 
$1.79
 
27.2%
 
$0.53
 
7.7%
 
$5.28

The generation mix for 2010 is expected to be 62.6% coal, 26.0% nuclear and 11.4% gas and oil.  Due to locally available natural gas and oil supplies, the utilization of locally available coal deposits and the generally adequate supply of nuclear fuel, PNM believes that adequate sources of fuel are available for its generating stations into the foreseeable future.  See Sources of Power - PNM - PPAs for information concerning the cost of purchased power.

Coal

See Note 16 for information about PNM’s coal supply.

Natural Gas

The natural gas used as fuel for the electric generating plants is procured on the open market and delivered by third party transportation providers and PNM Gas (through January 29, 2009 and thereafter by NMGC) through its transportation facilities.
 
 
A-8

 
Nuclear Fuel

PNM is one of several participants in PVNGS. See Note 14.  The fuel cycle for PVNGS is comprised of the following stages:

  
mining and milling of uranium ore to produce uranium concentrates;
  
conversion of uranium concentrates to uranium hexafluoride;
  
enrichment of uranium hexafluoride;
  
fabrication of fuel assemblies;
  
utilization of fuel assemblies in reactors; and
  
storage and disposal of spent nuclear fuel.

    The PVNGS participants are continually identifying their future fuel needs and negotiating arrangements to fill those needs.  The PVNGS participants have contracted for all of PVNGS’s requirements for uranium concentrates through 2011.  New contracts are currently being negotiated that would meet the plant’s conversion services needs through 2011, taking into account available inventory.  The participants have also contracted for all of PVNGS’s enrichment services through 2013 and all of PVNGS’s fuel assembly fabrication services until at least 2015.

PVNGS has sufficient capacity at its on-site independent spent fuel storage installation (“ISFSI”) to store all of the nuclear fuel that will be irradiated during the initial operating license period, through 2027.  Additionally, PVNGS has sufficient capacity at its on-site ISFSI to store a portion of the fuel that will be irradiated during the period of extended operation.  If uncertainties regarding the United States government’s obligation to accept and store used fuel are not favorably resolved, the PVNGS participants will evaluate alternative storage solutions that may obviate the need to expand the ISFSI to accommodate all of the fuel that will be irradiated during the period of extended operation.  See Note 16.

Water Supply

See Note 16 for information about PNM's water supply.

RATES AND REGULATION

The items below describe certain of the more significant rate and regulatory matters that are relevant to the Company.  See Notes 16 and 17 for a discussion of additional rate and regulatory matters.

PNMR

First Choice

First Choice is a member of ERCOT, the ISO responsible for maintaining reliable operations of the bulk electric power grid in the Texas deregulated electricity market.  ERCOT does not operate a centrally dispatched pool and does not procure energy on behalf of its members other than to maintain the reliable operation of the transmission system.  ERCOT also serves as a clearinghouse for procuring ancillary services.

Members of ERCOT include independent REPs, investor owned utilities, municipals, cooperatives, independent generators, independent power marketers, and consumers.  The electric market served by ERCOT operates under the reliability standards set by the North American Electric Reliability Council.  The PUCT has primary jurisdictional authority over the electric market served by ERCOT and the reliability of electricity across Texas' main interconnected power grid.

First Choice provides energy to retail customers in ERCOT.  As a result of the deregulated electricity market in Texas, there are no provisions for the specific recovery of fuel and purchased power costs by First Choice.  The rates charged to new customers acquired by First Choice are not regulated by the PUCT, but are negotiated by First Choice with each customer.  As a result, purchased power costs will affect First Choice’s operating results.



 
A-9

 

PNM

Regulation

    PNM is subject to the jurisdiction of the NMPRC with respect to its retail electric rates, service, accounting, issuances of securities, construction of major new generation, transmission, and distribution facilities and other matters regarding retail utility services provided in New Mexico.  The NMPRC approved PNM implementing new electric rates reflecting a $34.4 million rate increase in May 2008 and also implementing an Emergency FPPAC in June 2008. In the 2008 Electric Rate Case, the NMPRC approved PNM implementing new electric rates reflecting an increase in annual non-fuel revenues of $77.1 million, of which 65% was implemented for bills beginning on July 1, 2009 and the remaining 35% will be implemented in rates as of April 1, 2010. The NMPRC also approved a more traditional FPPAC.  See Note 17.  FERC has jurisdiction over rates and other matters related to wholesale electric sales and cost recovery for a portion of PNM’s transmission network.

Operations Transferred from TNMP

In connection with obtaining the approval of the NMPRC for PNMR’s acquisition of TNP, including TNMP, PNMR agreed to reduce rates for TNMP’s New Mexico customers, except one large industrial customer, by 1.851 cents per KWh in 2006 through 2007, by an additional 0.1 cents per KWh in 2008, and by a further 0.1 cents per KWh in 2009. No rate increase can be requested that would go into effect prior to January 1, 2011.  Effective January 1, 2007, the New Mexico utility operations of TNMP were transferred to PNM and these provisions regarding rates remain in effect.

Renewable Portfolio Standard

The Renewable Energy Act of 2004 was enacted to encourage the development of renewable energy in New Mexico.  The act establishes a mandatory renewable energy portfolio standard requiring a utility to acquire a renewable energy portfolio equal to 5% of retail electric sales by January 1, 2006 and, as amended effective July 1, 2007, increasing to 10% by 2011, 15% by 2015 and 20% by 2020.  The act provides for streamlined proceedings for approval of utilities’ renewable energy procurement plans, assures utilities recovery of costs incurred consistent with approved procurement plans and requires the NMPRC to establish RCT for the procurement of renewable resources to prevent excessive costs being added to rates.

TNMP

Regulation

In Texas, TNMP provides regulated transmission and distribution services and is subject to the jurisdiction of the PUCT and certain municipalities with respect to rates and service.  TNMP is subject to traditional cost-of-service regulation in Texas.  TNMP’s transmission and distribution activities in Texas are not subject to FERC regulation, because those activities occur solely within the ERCOT system of Texas.

In August 2008, TNMP filed with the PUCT for an $8.7 million increase in revenues.  TNMP amended its request by $15.7 million to include recovery of costs related to Hurricane Ike, as well as anticipated debt financing costs.  In August 2009, the PUCT approved a settlement that permits TNMP to increase revenues by $12.7 million annually.  This increase reflects interest and other costs associated with its March 2009 debt refinancing and adjusts the interest rate TNMP is allowed to collect on its CTC to reflect those costs.  The rate increase includes recovery of $17.6 million of Hurricane Ike restoration costs plus carrying costs over five years. See Note 17.

ENVIRONMENTAL MATTERS

Electric and gas utilities are subject to stringent laws and regulations for protection of the environment by local, state, federal and tribal authorities. In addition, PVNGS is subject to the jurisdiction of the NRC, which has the authority to issue permits and licenses and to regulate nuclear facilities in order to protect the health and safety of the public from radioactive hazards and to conduct environmental reviews pursuant to the National Environmental Policy Act.  The liabilities under these laws and regulations can be material and, in some instances, may be imposed without regard to fault, or may be imposed for past acts, whether or not such acts were lawful at the time they occurred.  See MD&A - Critical Accounting Policies for a discussion of applicable accounting policies and – Other
 
 
A-10

 
Issues Facing the Company – Climate Change Issues for information on greenhouse gas emissions.  In addition, see Notes 16 and 18 for information related to the following matters, incorporated in this item by reference.
 
  Note 16
  
PVNGS Decommissioning Funding
  
Nuclear Spent Fuel and Waste Disposal
  
Environmental Matters under the caption “The Clean Air Act”
  
Santa Fe Generating Station
  
Environmental Matters under the caption “Coal Combustion Waste Disposal”
  
Gila River Indian Reservation Superfund Site

  Note 18
  
Environmental Issues

COMPETITION

Through certain of its subsidiaries, PNMR is a merchant utility and a regulated energy service provider.  Regulated utilities are generally not subject to competition from other utilities in areas that are under the jurisdiction of state regulatory commissions.  In New Mexico, PNM does not have competition for services provided to its retail electric customers.  In Texas, TNMP is not currently in any direct retail competition with any other regulated electric utility.  However, the Company is subject to customer conservation activities and initiatives to utilize alternative energy sources.  As a merchant utility, PNMR is subject to competition in the wholesale markets and the deregulated electricity market in Texas.  Additional information relating to the competitive environment in which the Company operates in is contained in MD&A.

    The Company is subject to varying degrees of competition in certain territories adjacent to or within the areas it serves with other utilities in its region as well as with rural electric cooperatives and municipal utilities.  The Company is involved in the generation and sale of electricity into the wholesale market.  It is subject to competition from regional utilities with similar opportunities to generate and sell energy at market-based prices and larger trading entities that do not own or operate generating assets.   The Texas electricity market has been open to retail competition since 2002.  The Company is exposed to competition in the unregulated Texas retail electricity market through First Choice, which serves customers at competitive rates.  In order to compete effectively in the Texas retail electricity market, First Choice must be able to attract and retain customers on the basis of cost and service, while managing the cost of its energy supply. 

    Since 2002, electric consumers in Texas have been encouraged to switch from their traditional retail energy provider, such as TNMP, to a competitive REP, such as First Choice.  Currently under TECA, consumers whose chosen retail energy provider has exited the Texas market are provided electric service by a “provider of last resort.”  Rates of the provider of last resort are regulated by the PUCT and are fixed for the two-year period that each provider of last resort serves.  First Choice and other REPs, formerly subject to price-to-beat rates, currently market retail electricity at competitive rates, which has resulted in increased pressure on margins. 

EMPLOYEES

The following table sets forth the number of employees of PNMR, PNM and TNMP and for each business segment as of December 31, 2009:

 
PNMR
 
PNM
 
TNMP
Corporate *
556
 
-
 
-
PNM Electric
1,146
 
1,146
 
-
TNMP Electric
350
 
-
 
350
First Choice
81
 
-
 
-
Total
2,133
 
1,146
 
350

*   Represents employees of PNMR Services Company.


 
A-11

 
As of December 31, 2009, PNM Electric had 660 employees in its power plant and operations areas that are currently covered by a collective bargaining agreement with the IBEW that was entered into in May 2009 and expires April 30, 2012.  PNMR has no other employees represented by unions.

DISCLOSURE REGARDING FORWARD LOOKING STATEMENTS

    Statements made in this filing that relate to future events or PNMR’s, PNM’s, or TNMP’s expectations, projections, estimates, intentions, goals, targets and strategies, are made pursuant to the Private Securities Litigation Reform Act of 1995.  Readers are cautioned that all forward-looking statements are based upon current expectations and estimates and PNMR, PNM, and TNMP assume no obligation to update this information.

    Because actual results may differ materially from those expressed or implied by these forward-looking statements, PNMR, PNM, and TNMP caution readers not to place undue reliance on these statements.  PNMR’s, PNM’s, and TNMP’s business, financial condition, cash flow and operating results are influenced by many factors, which are often beyond their control, that can cause actual results to differ from those expressed or implied by the forward-looking statements.  These factors include:

  
Conditions affecting the Company’s ability to access the financial markets and negotiate new credit facilities for those expiring in 2011 and 2012, or Optim Energy’s access to additional debt financing following the utilization of its existing credit facility, including actions by ratings agencies affecting the Company’s credit ratings,
  
The recession, its consequent extreme disruption in the credit markets, and its impacts on the electricity usage of the Company’s customers,
  
State and federal regulatory and legislative decisions and actions, including appeals of prior regulatory proceedings, and including provisions relating to climate change, reduction of GHG, CCBs, and other power plant emissions,
  
The ability of PNM to meet the renewable energy requirements established by the NMPRC, including the resource diversity requirement, within the specified cost parameters, and the Company’s ability to obtain federal and/or state funding and incentives for the development of alternative or renewable energy,
  
The ability of PNM to successfully utilize a future test year in a rate filing with the NMPRC, including PNM’s ability to accurately forecast operating and capital expenditures and withstand challenges by regulators and intervenors,
  
The performance of generating units, including PVNGS, SJGS, Four Corners, and Optim Energy generating units, and transmission systems,
  
The risk that Optim Energy desires to expand its generation capacity but is unable to identify and implement profitable acquisitions or that PNMR and ECJV will not agree to make additional capital contributions to Optim Energy,
  
The potential unavailability of cash from PNMR’s subsidiaries or Optim Energy due to regulatory, statutory or contractual restrictions,
  
The impacts of the decline in the values of marketable equity securities on the trust funds maintained to provide nuclear decommissioning funding and pension and other postretirement benefits, including the levels of funding and expense,
  
The ability of First Choice to attract and retain customers and collect amounts billed,
  
Changes in ERCOT protocols,
  
Changes in the cost of power acquired by First Choice,
  
Collections experience,
  
Insurance coverage available for claims made in litigation,
  
Fluctuations in interest rates,
  
Weather,
  
Water supply,
  
Changes in fuel costs,
  
Availability of fuel supplies,
  
Uncertainty regarding the requirements and related costs of decommissioning power plants owned or partially owned by PNM and Optim Energy and coal mines supplying certain PNM power plants, as well as the ability to recover decommissioning costs through charges to customers,


 
 
A-12

 

  
The risk that replacement power costs incurred by PNM related to not meeting the specified capacity factor for its generating units under its Emergency FPPAC will not be approved by the NMPRC,
  
The risk that PNM may not be able to renew rights-of-way on Native American lands or that the costs of rights-of-way are not allowed to be recovered through rates charged to customers,
  
The effectiveness of risk management and commodity risk transactions,
  
Seasonality and other changes in supply and demand in the market for electric power,
  
The impact of mandatory energy efficiency measures on customer energy usage,
  
Variability of wholesale power prices and natural gas prices,
  
Volatility and liquidity in the wholesale power markets and the natural gas markets,
  
Uncertainty regarding the ongoing validity of government programs for emission allowances,
  
The risk that the resolution of the bankruptcy of LCC results in significant adverse impacts on the operations of the Altura Cogen facility and Optim Energy,
  
Changes in the competitive environment in the electric industry,
  
The risk that the Company and Optim Energy may have to commit to substantial capital investments and additional operating costs to comply with new environmental requirements including possible future requirements to address concerns about global climate change, and the resultant impacts on the operations and economic viability of generating plants in which PNM and Optim Energy have interests,
  
The risks associated with completion of generation, transmission, distribution, and other projects, including construction delays and unanticipated cost overruns,
  
Uncertainty surrounding the status of PNM’s participation in jointly-owned projects resulting from the scheduled expiration of the operational documents for the projects beginning in 2015 and potential changes in the objectives of the participants in the projects,
  
The outcome of legal proceedings,
  
Changes in applicable accounting principles, and
  
The performance of state, regional, and national economies.

See Item 7A. Quantitative and Qualitative Disclosure About Market Risk for information about the risks associated with the use of derivative financial instruments.

SECURITIES ACT DISCLAIMER

Certain securities described in this report have not been registered under the Securities Act of 1933, as amended, or any state securities laws and may not be reoffered or sold in the United States absent registration or an applicable exemption from the registration requirements of the Securities Act of 1933 and applicable state securities laws.  This Form 10-K does not constitute an offer to sell or the solicitation of an offer to buy any securities.

ITEM 1A.              RISK FACTORS

The business and financial results of PNMR, PNM and TNMP are subject to a number of risks and uncertainties, including those set forth below and in MD&A, Note 16 and Note 17.  Optim Energy, which is 50% owned by PNMR, is subject to many of the same risks and uncertainties.

The economic recession and its consequent extreme disruption in the credit and capital markets may impact our growth strategy and ability to raise capital and negotiate new credit facilities for those expiring in 2011 and 2012.
 
What has been characterized as a “credit crisis” developed in the latter part of 2008 in the United States, along with the most significant economic recession in decades.  It is generally perceived that the recession has ended, but that the credit markets remain fragile.  PNMR and its operating subsidiaries rely on access to both short-term money markets and longer-term capital markets as a source of liquidity for any capital requirements not satisfied by cash flow from operations, which could include capital requirements for energy infrastructure investments and funding new projects.  If PNMR, its operating subsidiaries, or Optim Energy are not able to access capital at competitive rates, or at all, PNMR’s ability to finance capital requirements, if needed, and its ability to implement its growth strategy will be limited.  In addition, TNMP’s $75.0 million revolving credit facility expires in April 2011 and PNMR’s $600.0 million and PNM’s $400.0 million revolving credit facilities each primarily expire in 2012.  Also, the bank financing arrangement of Optim Energy expires in 2012.  Industry experts suggest that the reduction in the number of banks and currently available credit coupled with numerous bank credit facilities across the utility
 
 
A-13

 
industry expiring in 2011 and 2012 could result in substantially higher pricing and shorter maturities of credit facilities.  Additional disruptions in the credit markets, which could negatively impact our access to capital could be caused by:

  
a further or “double-dip” economic recession,
  
declines in the health of the banking sector generally, and the failure of specific banks who are parties to our credit facilities,
  
the bankruptcy of an unrelated energy company,
  
increased market prices for electricity and gas,
  
terrorist attacks or threatened attacks on facilities of PNMR’s operating subsidiaries or those of unrelated energy companies, and
  
deterioration in the overall health of the utility industry.

Market disruptions may increase the cost of borrowing or adversely affect our ability to raise capital through the issuance of securities or other borrowing arrangements, which could have a material adverse effect on business, financial position, results of operations and liquidity.
 
Additionally, economic recession or downturn may affect the actions of our customers and result in decreased consumption and increased bad debt expense, and could also negatively impact our suppliers, all of which could negatively impact us.
 
    In addition to affecting the capital markets generally, recession indicates an overall reduction in the level of economic activity.  Decreased economic activity can lead to declines in energy consumption, which could adversely affect future revenues, earnings and growth.  Rises in unemployment rates both inside our service territories and nationwide could result in commercial customers ceasing operations and lower levels of income for our residential customers, causing them to be unable to pay their bills on time, which could impact our cash flows and increase our bad debt expense, which will impact results of operations.  Decreased consumption, late or absence of payments and increases in bad debt expense would all negatively impact our results.

    Economic conditions also impact the supply of commodities and materials needed to construct or acquire utility assets or make necessary repairs.  Recession may affect the supply of concrete, copper, steel, and aluminum.  The costs of those items are also affected by economic conditions and could increase significantly over forecasted amounts.
 
Declines in values of marketable securities held in trust funds for pension and other postretirement benefits and in the NDT could result in sustained increases in costs and funding requirements for those obligations, which may affect our results of operations.

    The Company targets 57.5% of its pension trust funds and 70.0% of its trust funds for other postretirement benefits to be invested in marketable equity securities.  There has been a significant decline in the general price levels of marketable equity securities in the second half of 2008 and early 2009. Although market prices generally improved later in 2009, increased levels of funding will be required beginning in 2010 and additional amounts will be recorded as expense. Also, a significant portion of funds held in the NDT are invested in marketable equity securities.  The declines in market values resulted in the recognition of losses as impairments of the certain securities held in the NDT in 2008 and early 2009.  Further declines in market value could result in additional impairments.
 
Any failure to renegotiate our credit facilities could harm our business, financial condition and results of operations.
 
    As of February 15, 2010, the Company had consolidated short-term debt outstanding of $269.0 million through existing revolving credit facilities.  The PNMR Facility and the PNM Facility both primarily expire in 2012 and the TNMP Revolving Credit Facility expires in April 2011.  These facilities provide short-term borrowing capacity and also allow letters of credit to be issued, which reduce the available capacity under the facilities.  These credit facilities will need to be renegotiated or replaced prior to their expiration in order to provide sufficient liquidity to finance operations and construction expenditures.  The availability of such credit facilities and their terms and conditions will depend on the credit markets at that time, as well as the Company’s credit ratings and operating results.  Also, the Company is projecting total construction expenditures for the years 2010-2014 to be $1,509.8
 
 
A-14

 
million. The Company is exploring financial alternatives to meet these anticipated expenditures and currently believes that internal cash generation, credit arrangements, and access to the public and private capital markets will provide sufficient resources to meet capital requirements.  To cover the difference in the amounts and timing of cash generation and cash requirements, the Company intends to use short-term borrowings under current or then existing liquidity arrangements.
 
    If our cash flow and credit and capital resources are insufficient to fund our capital expenditure plans, we may be forced to sell assets, seek additional equity or debt capital or restructure our debt.  In addition, any failure to make scheduled payments on our outstanding indebtedness would likely result in reductions of our credit ratings, which could harm our ability to incur additional indebtedness on acceptable terms and would result in an increase in the interest rates applicable under our credit facilities.  Our cash flow and capital resources may be insufficient to pay interest and principal on our debt in the future.  If that should occur, our capital raising or debt restructuring measures may be unsuccessful or inadequate to meet our scheduled debt service obligations, which could cause us to default on our obligations and further impair our liquidity.
 
Future reduction in the credit ratings of PNMR or its operating subsidiaries could materially and adversely affect their business, financial position, results of operations and liquidity.

The credit ratings for the debt of PNMR, PNM, and TNMP were downgraded in April and May 2008 and in some instances are below investment grade.  PNMR, PNM and TNMP cannot be sure that any of their current ratings will remain in effect for any given period of time or that a rating will not be lowered or withdrawn entirely by a rating agency.  Any downgrade could result in:

  
increased borrowing costs, which would diminish financial results,
  
required payment of a higher interest rate in future financings and a smaller potential pool of investors and  decreased funding sources,
  
required provision of additional support in the form of letters of credit or cash or other collateral to various counterparties, and
  
limited access to or increased costs of access to the commercial paper and other credit markets.

Failure of PNMR’s PNM and TNMP subsidiaries, which are subject to rate regulation by state regulators, to adequately recover the costs incurred to provide service to customers and to earn a fair return on invested capital could have a significant impact on the Company’s future financial condition and results of operations.

Critical to PNMR’s success for the foreseeable future is the financial health of its regulated operating subsidiaries, which is highly dependent on continued favorable regulatory treatment. Although the NMPRC approved rate increases for PNM in 2008 and 2009 and the PUCT approved a rate increase for TNMP in 2009, these were the first rate increases for the regulated operations in a number of years and there can be no assurance applications for rate increases in the future will be approved.  Furthermore, the Company anticipates a trend toward increasing costs of providing electric service resulting from a period of plant expansion, primarily from renewable energy sources, as well as anticipated increases in costs related to renewals of right of way on Native American lands, pension and benefits, and depreciation. If regulators do not allow the increased costs to be recovered from customers in a timely manner, the Company’s liquidity and results of operations could be negatively impacted.

PNM intends to file an electric rate case with the NMPRC in mid-2010.  It is anticipated that PNM will utilize a future test year in that filing.  As with any forward looking financial information, utilizing a future test year in a rate filing presents challenges that are inherent in the forecasting process.  PNM will need to forecast both operating and capital expenditures that will necessitate reliance on many assumptions concerning future conditions and operating results.  In the ratemaking process, PNM’s assumptions will be subject to challenge by regulators and intervenors who may assert different interpretations or assumptions.  If PNM cannot successfully support the use of a future test year, including defending its ability to reasonably forecast operating and capital expenditures and to withstand challenges by regulators and intervenors, cash flows and results of operations will be negatively impacted.

The financial performance of PNMR, PNM and TNMP may be adversely affected if their power plants and transmission and distribution system are not successfully operated. Further, the financial performance of PNMR may be adversely affected if Optim Energy’s power plants are not successfully operated.

 
A-15

 
The financial performance of PNMR, PNM and TNMP, as well as that of Optim Energy, depends on the successful operation of their generation, transmission and distribution assets.  The financial performance of PNMR and PNM may also be adversely affected if the NRC imposes restrictions on operation of PVNGS or any of the three units at the plant.  Unscheduled or longer than expected maintenance outages, other performance problems with the electric generation assets, severe weather conditions, accidents and other catastrophic events, disruptions in the delivery of fuel and other factors could reduce generation capacity and therefore limit the ability to sell power. Diminished generation capacity could also result in PNM’s aggregate net open forward electric sales position, including its retail load requirements, being larger than forecasted generation capacity.  If this were to occur, purchases of electricity in the wholesale market by PNM would be required under contracts priced at the time of execution or, if in the spot market, at the then-current market price.  There can be no assurance that sufficient electricity would be available at reasonable prices, or at all, if such a situation were to occur. Failures of transmission or distribution facilities may also cause interruptions in the services that PNM and TNMP provide.  These potential generation, distribution and transmission problems, and any potentially related service interruptions, could result in lost revenues and additional costs.

Demand for power could exceed supply capacity, resulting in increased costs for purchasing capacity in the open market or building additional generation capabilities.

Through its operating subsidiaries, PNMR is currently obligated to supply power to retail customers and wholesale customers. At peak times, the demand for power required to meet this obligation could exceed PNMR’s available generation capacity. Market or competitive forces may require that PNMR’s operating subsidiaries purchase capacity on the open market or build additional generation capabilities. Because regulators or market conditions may not permit the operating subsidiaries to pass all of these purchases or construction costs on to their customers, the operating subsidiaries may not be able to recover any of these costs or may have exposure to regulatory lag associated with the time between the incurrence of costs of purchased or constructed capacity and the recovery in customers’ rates. These situations could have negative impacts on net income and cash flows for PNMR and the affected operating subsidiary.

Costs of environmental compliance, liabilities and litigation could exceed estimates by PNMR and its operating subsidiaries and Optim Energy, which could adversely affect their business, financial position, results of operations and liquidity.  In addition, while there is uncertainty about the timing and form of regulation of climate change, CCBs, and other power plant emissions proposed and/or anticipated forms of regulation could have a material impact on operations.

Compliance with federal, state and local environmental laws and regulations may result in increased capital, operating and other costs, including remediation and containment expenses and monitoring obligations.  PNMR, PNM, TNMP and Optim Energy cannot predict exactly how they would be affected if existing environmental laws and regulations were to be revised, or if new environmental laws and regulations seeking to protect the environment were to be adopted.

In addition, while there continues to be significant debate regarding the existence and extent of the emission of so-called GHG (particularly CO2) from fossil-fired generation facilities, PNMR and its operating subsidiaries believe that future governmental regulations applicable to their operations will limit GHG, although the framework and timing of legislation to be enacted is currently unclear. A number of bills have been introduced in the U.S. Congress, and under a number of the bills, it is likely that the incurrence of substantial costs across the utility industry would be required in order to comply, assuming that technology is available.  Material changes in existing environmental laws and regulations, as well as new environmental laws and regulations, including the regulation of GHG, could increase financing requirements or otherwise adversely affect the business, financial position, results of operations and liquidity of PNMR, its operating subsidiaries and Optim Energy, unless increased environmental costs are recovered in customer rates or otherwise.  Although PNM has begun the process of assessing the impacts of potential climate change legislation or regulation, the assessment is very preliminary and is based on numerous speculative assumptions regarding the final form of legislation or regulation. Revised or additional environmental laws and regulations could also result in additional operating restrictions on facilities and increased compliance costs that may not be fully recoverable in rates or otherwise, thereby reducing earnings.

CCBs, consisting of fly ash, bottom ash, and gypsum, from operation of PNM’s SJGS are currently being disposed of in the surface mine pits adjacent to the plant.  The EPA is considering a proposal to regulate CCBs, but the timing of the release of EPA’s proposal is unclear.   It is possible that the EPA could classify CCBs as a
 
 
A-16

 
hazardous waste.  PNM cannot predict the outcome of the EPA’s actions regarding CCB regulation and whether such actions will have a material adverse impact on its operations or financial position.  However, if the regulation ultimately prevents the CCBs from SJGS to be disposed of in the adjacent mine, the increased costs of disposal could be significant, which would negatively impact PNM’s customers and the Company.  The Company’s results of operations would be negatively impacted unless the costs are recovered in PNM’s customer rates.

In addition, PNM or TNMP may be designated as a responsible party for environmental clean up at a site identified by a regulatory body.  PNMR, PNM and TNMP cannot predict with certainty the amount and timing of all future expenditures related to environmental matters because of the difficulty of estimating clean-up and compliance costs, and the possibility that changes will be made to the current environmental laws and regulations. There is also uncertainty in quantifying liabilities under environmental laws that impose joint and several liability on all potentially responsible parties.  Failure to comply with environmental laws and regulations, even if caused by factors beyond PNM’s or TNMP’s control, may result in the assessment of civil or criminal penalties and fines.

Costs of decommissioning, remediation, and restoration of nuclear and fossil-fueled power plants, as well as related coal mines could exceed estimates of PNMR, its subsidiaries, and Optim Energy, which could negatively impact results of operations and liquidity if regulators do not allow the increased costs to be recovered from customers.

PNM has interests in a nuclear power plant, two coal-fired power plants, and several natural gas-fired power plants.  PNM is obligated to pay for the costs of decommissioning its share of the nuclear power plant as well as its share of the fossil-fueled power plants.  PNM is also obligated to pay for the costs of decommissioning the mines that supply coal to the coal-fired power plants.  Rates charged by PNM to its customers, as approved by the NMPRC, include a provision for recovery of certain costs of decommissioning, remediation, and restoration.  As discussed in Note 17, the NMPRC has established a cap on surface mine decommissioning cost.   In the event the costs exceed current estimates and PNM is unsuccessful in recovering the costs through increased rates, results of operations will be negatively impacted.

Optim Energy has interests in a coal-fired power plant and two gas-fired power plants and is obligated for decommissioning of its share of these facilities.  Since Optim Energy is not subject to rate regulation, cost recovery can only be achieved through power sales at market-based rates.  To the extent, market-based rates are not adequate to recover the costs of decommissioning, results of operations will be negatively impacted.

PNM may not be able to recover the costs of renewing rights of way, primarily on Native American lands, in rates charged to customers, which could negatively impact its liquidity and results of operations.

Many of PNM’s electric transmission and distribution facilities are located on lands that require the grant of rights-of-way from governmental entities, Native American tribes, or private parties.  Several of the agreements granting the rights-of-way have expired or will expire within the next few years.  PNM is actively reviewing these matters and negotiating with certain parties for the renewal of these rights-of-way.  If rights-of-way on Native American lands are renewed, it is likely they will be renewed at prices that are higher than historical levels, based on current renewal experience.  If PNM is not successful in renewing the rights-of-way on Native American lands, it could be forced to remove its facilities from or abandon its facilities on the property covered by the rights-of-way and seek alternative routes for its transmission or distribution facilities.  If PNM is not successful in recovering the costs of the rights-of-way renewals or of removal and securing alternative routes in rates approved by the NMPRC, its liquidity and results of operations will be negatively impacted.

PNMR may be unable to meet its ongoing and future financial obligations and to pay dividends on its common and convertible preferred stock if its subsidiaries are unable to repay funds borrowed from PNMR or if PNMR’s subsidiaries or Optim Energy are unable to pay upstream dividends or distributions to PNMR.

PNMR is a holding company and has no operations of its own. PNMR’s ability to meet its financial obligations and to pay dividends on its common and convertible preferred stock at the current rate is primarily dependent on the net income and cash flows of its subsidiaries and Optim Energy and their ability to pay upstream dividends or distributions or, in the case of PNMR’s subsidiaries, to repay funds borrowed from PNMR. Prior to providing funds to PNMR, PNMR’s subsidiaries and Optim Energy have financial obligations that must be satisfied, including among others, debt service and, in the case of PNM, preferred stock dividends.

 
A-17

 
PNM can pay dividends to PNMR from earnings as well as equity contributions made by PNMR.  The NMPRC has placed certain restrictions on the ability of PNM to pay dividends to PNMR, including the restriction that PNM cannot pay dividends that cause its debt rating to fall below investment grade. The NMPRC has also restricted PNM from paying dividends in any year, as determined on a rolling four quarter basis, in excess of net earnings, including carryover amounts, without prior NMPRC approval.  Additionally, PNM has various financial covenants that limit the transfer of assets, through dividends or other means.

In addition, the ability of PNMR to declare dividends is dependent upon the extent to which cash flows will support dividends, the availability of retained earnings, the financial circumstances and performance, the NMPRC’s and PUCT’s decisions in various regulatory cases currently pending and which may be docketed in the future, the effect of federal regulatory decisions, Congressional and legislative acts and economic conditions in the United States.  Conditions imposed by the NMPRC or PUCT, future growth plans and the related capital requirements and business considerations may also affect PNMR’s ability to pay dividends.

PNMR, PNM and TNMP are subject to complex government regulation, which may have a negative impact on their business, financial position and results of operations.

PNMR, PNM and TNMP are subject to comprehensive regulation by several federal, state and local regulatory agencies, which significantly influences their operating environment and may affect their ability to recover costs from utility customers. In particular, the NMPRC, PUCT, FERC, NRC, EPA, ERCOT, NMED and TCEQ regulate many aspects of their utility operations, including siting and construction of facilities, the purchase of power under long-term contracts, conditions of service, the issuance of securities, and the rates that the regulated entities can charge customers. PNMR, PNM and TNMP are required to have numerous permits, approvals and certificates from these agencies to operate their business.  The rates that PNM and TNMP are allowed to charge for their retail services significantly influence PNMR’s and those subsidiaries’ business, financial position, results of operations and liquidity.  Due to continuing federal regulatory reforms, the public utility industry continues to undergo change.  Although Optim Energy’s operations are generally not subject to regulation by the utility regulatory agencies, its operations are subject to regulation by other regulators such as environmental authorities.
 
    The NRC has broad authority under federal law to impose licensing and safety-related requirements for the operation of nuclear generation facilities.  In the event of noncompliance, the NRC has the authority to impose monetary civil penalties or a progressively increased inspection regime, which could ultimately result in the shut down of a unit, or both, depending upon the NRC’s assessment of the severity of the situation, until compliance is achieved.  PVNGS was subject to this heightened scrutiny until March 2009, when it exited the NRC’s enhanced inspection regime.  Increased costs resulting from penalties, a heightened level of scrutiny and implementation of plans to achieve compliance with NRC requirements, could adversely affect PNM’s financial condition, results of operations, and cash flows.
 
Under the Energy Policy Act of 2005, FERC has issued a number of rules pertaining to preventing undue discrimination in transmission services and electric reliability standards.  PNMR monitors and participates in the FERC and other proceedings involving implementation of the Energy Policy Act, in order to assess the implications of the law and rules on its operations.

PNMR and its subsidiaries are unable to predict the impact on their business and operating results from the future regulatory activities of any agency that regulates them or from the implementation of the Energy Policy Act.  Changes in regulations or the imposition of additional regulations may require PNMR and its regulated subsidiaries to incur additional expenses or change business operations, and therefore may have an adverse impact on PNMR’s and those subsidiaries’ results of operations. 

The operating results of PNMR and its operating subsidiaries and Optim Energy are affected by weather conditions and regional drought and may fluctuate on a seasonal and quarterly basis.

Electric power generation and distribution are generally seasonal businesses with demand for power from PNMR’s and Optim Energy’s electric operations traditionally peaking during the hot summer months. As a result, the operating results of PNMR and its operating subsidiaries and Optim Energy will likely fluctuate substantially on a seasonal basis. In addition, the sale of PNM Gas on January 30, 2009 and the absence of revenues from gas operations, which peaked in the winter months, changed quarterly earnings distribution.

 
A-18

 
In addition, PNMR and its operating subsidiaries have historically sold less power, and consequently earned less income, when weather conditions are milder.  Unusually mild weather in the future could reduce the revenues, net earnings, available cash and borrowing ability of PNMR and its operating subsidiaries.

Drought conditions in New Mexico generally, and especially in the “four corners” region, in which SJGS and the Four Corners plant are located, may affect the water supply for PNM’s generating plants.  If adequate precipitation is not received in the watershed that supplies that region, PNM may have to decrease generation at these plants, which would require the purchase of power to serve PNM’s customers and/or reduce PNM’s ability to sell excess power on the wholesale market and reduce its revenues.  Drought conditions or actions taken by regulators or legislators could limit PNM’s supply of water, and PNM’s and PNMR’s business may be adversely impacted.  Although PNM has been able to maintain adequate access to water through supplemental contracts and voluntary shortage sharing agreements with tribes and other water users in the “four corners” region, PNM cannot be certain that it will be able to do so in the future.

TNMP, First Choice, and Optim Energy have operations in the Gulf coast area of Texas, which experiences periodic hurricanes.  In addition to potentially causing physical damage to Company or Optim Energy owned facilities, which disrupt the ability to transmit, distribute, and/or generate energy, hurricanes can reduce customers’ usage and demand for energy.  These factors reduce revenues and earnings.

The ability of First Choice to attract and retain customers, its ability to collect amounts billed to customers, and its ability to mitigate the fluctuation in costs of energy supply could have a significant adverse effect on PNMR’s business, financial position, results of operations and liquidity.

PNMR is exposed to competition in the unregulated Texas retail electricity market through First Choice, which serves customers at competitive rates.  In order to compete effectively in the Texas retail electricity market, First Choice must be able to attract and retain customers on the basis of cost and service, while managing the cost of its energy supply.  The rates charged to many of First Choice’s customers are fixed for the term of the contract and do not include automatic adjustments for changes in the cost of its energy supply.  In the event of rapid increases in the costs First Choice incurs to obtain the energy supplied to customers, the results of operations of First Choice will be negatively impacted unless increased costs have been successfully hedged.  The competitive nature of the Texas market results in significant turnover in the customer base of First Choice.  There is no provision under Texas regulation that requires customers to pay their previous REP before obtaining service from another REP.  This has been exacerbated by the impacts of Hurricane Ike and depressed economic conditions and has resulted in significant increases in the levels of uncollectible accounts and bad debt expense. The ability of First Choice to compete successfully in the Texas market could have a significant effect on PNMR’s business, financial position, results of operations and liquidity.

There are inherent risks in the ownership and operation of nuclear facilities, such as environmental, health, fuel supply, spent fuel disposal, regulatory and financial risks, and the risk of a terrorist attack.

PNM has a 10.2% undivided interest in PVNGS, with portions of its interests in Units 1 and 2 held under leases.  PVNGS is subject to environmental, health and financial risks such as the ability to obtain adequate supplies of nuclear fuel, the ability to dispose of spent nuclear fuel, the ability to maintain adequate reserves for decommissioning, potential liabilities arising out of the operation of these facilities and the costs of securing the facilities against possible terrorist attacks and unscheduled outages due to equipment and other problems.  PNM maintains nuclear decommissioning trust funds and external insurance coverage to minimize its financial exposure to some of these risks; however, it is possible that damages could exceed the amount of insurance coverage.  See Note 16.  Although the decommissioning trust funds are designed to provide adequate funds for decommissioning at the end of the expected life of the PVNGS units, there is the risk of insufficient decommissioning trust funds in the event of early decommissioning of the units.

The NRC has broad authority under federal law to impose licensing and safety-related requirements for the operation of nuclear generation facilities.  In the event of noncompliance, the NRC has the authority to impose monetary civil penalties or a progressively increased inspection regime, which could ultimately result in the shut down of a unit, or both, depending upon its assessment of the severity of the situation, until compliance is achieved.  In addition, although the PVNGS participants have no reason to anticipate a serious nuclear incident at PVNGS, if an incident did occur, it could materially and adversely affect the results of operations and financial condition of
 
 
A-19

 
PNM and PNMR.  A major incident at a nuclear facility anywhere in the world could cause the NRC to limit or prohibit the operation or licensing of any domestic nuclear unit.

    The operation of each of the three PVNGS units requires an operating license from the NRC.  The NRC issued full power operating licenses for Unit 1 in June 1985, Unit 2 in April 1986 and Unit 3 in November 1987.  The full power operating licenses are valid for a period of approximately 40 years.  APS, on behalf of the PVNGS participants, applied for renewed operating licenses for each unit on December 15, 2008 for a period of 20 years beyond the expirations of the current licenses.  The NRC is currently reviewing the application.   The PVNGS participants do not anticipate any problems renewing these licenses.  However, as a result of potential terrorist threats and increased public scrutiny of utilities, the licensing process could result in increased licensing or compliance costs that are difficult or impossible to predict.

Impairments of tangible and intangible long-lived assets of PNMR, PNM and TNMP could adversely affect their business, financial position, liquidity and results of operations.

PNMR, PNM and TNMP evaluate their intangible long-lived assets, including goodwill and non-amortizing intangible assets, for impairment annually or, along with tangible long-lived assets, whenever indicators of impairment exist. The market capitalization of PNMR’s common stock was significantly below book value during 2008, which is an indicator that intangible assets may be impaired. Other potential impairment indicators could include changing customer purchase commitments and market share; fluctuating market and commodity prices resulting from weather patterns; changing fuel costs; increased environmental regulation; industry deregulation and other economic and market conditions and trends. In addition, changes in the ERCOT market in which First Choice operates significantly impacted its results of operations.  Also, Optim Energy made a strategic decision not to pursue the Twin Oaks expansion and wrote off its development rights as an impairment.  After tax impairment losses for PNMR, its consolidated subsidiaries, and PNMR’s share of Optim Energy totaled $212.1 million for the year ended December 31, 2008.

Although no impairments were recorded in 2009, if further indicators of impairment become evident, additional analysis could result in future charges.  In addition, the impairment analyses already performed were based on operating results expected to occur in the future.  If the anticipated future results are not achieved, we may be required to perform additional assessments that could result in further impairment charges.  Significant impairments adversely affect business, financial position, liquidity and results of operations.

PNM’s PVNGS leases describe certain events, including “Events of Loss” and “Deemed Loss Events”, the occurrence of which could require PNM to pay the lessors and the equity investors, in return for the investors' interest in PVNGS, cash in the amount provided in the leases and assume debt obligations relating to the PVNGS leases.

The “Events of Loss” generally relate to casualties, accidents and other events at PVNGS, including the occurrence of specified nuclear events, which would severely, adversely affect the ability of the operating agent, APS, to operate, and the ability of PNM to earn a return on its interests in, PVNGS.  The “Deemed Loss Events” consist mostly of legal and regulatory changes (such as issuance by the NRC of specified violation orders, changes in law making the sale and leaseback transactions illegal, or changes in law making the lessors liable for nuclear decommissioning obligations). PNM believes that the probability of such “Events of Loss” or “Deemed Loss Events” occurring is remote for the following reasons: (1) to a large extent, prevention of “Events of Loss” and some “Deemed Loss Events” is within the control of the PVNGS participants, including PNM, and the PVNGS operating agent, through the general PVNGS operational and safety oversight process and (2) with respect to other “Deemed Loss Events,” which would involve a significant change in current law and policy, PNM is unaware of any pending proposals or proposals being considered for introduction in Congress, or in any state legislative or regulatory body that, if adopted, would cause any of those events.  See Note 7.



 
 
A-20

 

Provisions of PNMR’s organizational documents, as well as several other statutory and regulatory factors, will limit another party’s ability to acquire PNMR and could deprive PNMR’s shareholders of the opportunity to gain a takeover premium for shares of PNMR’s common stock.

PNMR’s restated articles of incorporation and by-laws include a number of provisions that may have the effect of discouraging persons from acquiring large blocks of PNMR’s common stock or delaying or preventing a change in control of PNMR. The material provisions that may have such an effect include:
  
authorization for the Board to issue PNMR’s preferred stock in series and to fix rights and preferences of the series (including, among other things, whether, and to what extent, the shares of any series will have voting rights, subject to certain limitations, and the extent of the preferences of the shares of any series with respect to dividends and other matters),
  
advance notice procedures with respect to any proposal other than those adopted or recommended by PNMR’s Board, and
  
provisions specifying that only a majority of the Board, the chairman of the Board, the president or holders of not less than one-tenth of all of PNMR's shares entitled to vote may call a special meeting of stockholders.

Under the New Mexico Public Utility Act, NMPRC approval is required for certain transactions that may result in PNMR’s change in control or exercise of control.  Certain acquisitions of PNMR’s outstanding voting securities would also require FERC approval.

ITEM 1B.
UNRESOLVED STAFF COMMENTS

 
None.



 
 
A-21

 

ITEM 2.
PROPERTIES

PNMR

The significant properties owned by PNMR include those owned by PNM and TNMP and are disclosed below.

PNM

Electric

PNM’s owned and leased capacity in electric generating stations in commercial service as of December 31, 2009 is:
 

 
           
Total Net
 
           
Generation
 
           
Capacity
 
Type
 
Name
 
Location
 
(MW)
 
               
 Coal
 
SJGS (a)
 
Waterflow, New Mexico
   783  
 Coal  
Four Corners (b)
 
Fruitland, New Mexico
   195  
 Gas/Oil
 
Reeves Station
 
Albuquerque, New Mexico
   154  
 Gas/Oil  
Las Vegas (c)
 
Las Vegas, New Mexico
   20  
 Gas/Oil  
Afton (combined cycle) (d)
 
La Mesa, New Mexico
   235  
 Gas  
Lordsburg (e)
 
Lordsburg, New Mexico
   80  
 Nuclear  
PVNGS (f)
 
Wintersburg, Arizona
   402  
 Gas/Oil  
Delta (g)
 
Albuquerque, New Mexico
   132  
 Gas/Oil  
Luna (combined cycle)  (h)
 
Deming, New Mexico
   190  
 Gas  
Valencia (i)
 
Belen, New Mexico
   145  
             2,336  
 

(a)  
SJGS Units 1, 2 and 3 are 50% owned by PNM; SJGS Unit 4 is 38.5% owned by PNM.
(b)  
Four Corners Units 4 and 5 are 13% owned by PNM.  Units 4 and 5 at Four Corners are jointly owned with SCE, APS, SRP, Tucson and EPE and are operated by APS.  PNM has no ownership interest in Four Corners Units 1, 2 or 3.
(c)  
PNM will seek NMPRC approval for the June 1, 2012 abandonment of the Las Vegas Generating Station.
(d)  
In 2007, PNM completed the conversion of Afton to a combined cycle plant, with 50% of Afton's capacity designated to serve customers formerly served by TNMP that became customers of PNM effective January 1, 2007, and the other 50% designated to serve PNM's remaining retail customers.
(e)  
PNM’s Lordsburg plant was built to serve wholesale customers and other sales rather than New Mexico retail customers, but became included in the retail rates in July 2009.  See Note 17.
(f)  
PNM is entitled to 10.2% of the power and energy generated by PVNGS.  PNM has ownership interests of 2.3% in Unit 1, 4.6% in Unit 2 and 10.2% in Unit 3 and has leasehold interests of 7.9% in Unit 1 and 5.6% in Unit 2.
(g)  
PNM is entitled to the energy and capacity of Delta under a PPA that is deemed to be an operating lease.
(h)  
PNM owns 33.3% of Luna.  Luna became included in retail rates in July 2009.  See Note 17.
(i)  
PNM has a PPA that entitles it to the entire output of Valencia.  Valencia became included in retail rates under the 2008 Electric Rate Case.  Valencia is a variable interest entity and is consolidated by PNM as required by GAAP.  Therefore, Valencia is reflected in the above table as if it were owned.  See Sources of Power above and Note 9 and Note 17.



 
 
A-22

 

Fossil-Fueled Plants

SJGS is located in northwestern New Mexico, and consists of four units operated by PNM. Units 1, 2, 3 and 4 at SJGS have net rated capacities of 340 MW, 340 MW, 497 MW and 507 MW.  SJGS Units 1 and 2 are owned on a 50% shared basis with Tucson.  SJGS Unit 3 is owned 50% by PNM, 41.8% by SCPPA and 8.2% by Tri-State.  SJGS Unit 4 is owned 38.457% by PNM, 28.8% by M-S-R Public Power Agency, 10.04% by the City of Anaheim, California, 8.475% by the City of Farmington, New Mexico, 7.2% by the County of Los Alamos, New Mexico and 7.028% by UAMPS.

Four Corners and a portion of the facilities adjacent to SJGS are located on land held under easements from the United States and also under leases from the Navajo Nation.  The easement and lease for Four Corners expire in 2016.  The lease contains an option to extend for an additional 25-year period from the end of the existing lease term, for a rental amount tied to the original rent payment adjusted based on an index.  The easement does not contain an express renewal option and it is unclear what conditions to renewal or extension of the easements may be imposed.  The ultimate cost of renewal of the Four Corners lease and easement is uncertain.

The power from Reeves, Lordsburg, Delta, and Valencia is used primarily for peaking and transmission support.  See Item 1. Business. – Sources of Power.

Nuclear Plant

PNM is participating in the three units of PVNGS, also known as the Arizona Nuclear Power Project, with APS (the operating agent), Salt River Project, EPE, SCE, SCPPA and the Department of Water and Power of the City of Los Angeles.    See Note 16 in the Notes to Consolidated Financial Statements for information on other PVNGS matters.

Transmission and Distribution

As of December 31, 2009, PNM owned, jointly owned or leased, 3,170 circuit miles of electric transmission lines, 5,990 miles of distribution overhead lines, 5,448 cable miles of underground distribution lines (excluding street lighting) and 270 substations.

Other Information

PNM’s electric transmission and distribution lines are generally located within easements and rights-of-way on public, private and Native American lands.  PNM leases interests in PVNGS Units 1 and 2 and related property, Delta, EIP and associated equipment, data processing, communication, office and other equipment, office space, vehicles and real estate.  PNM also owns and leases service and office facilities in Albuquerque and in other areas throughout its service territory.  See Note 7 and Note 16.

TNMP

TNMP’s facilities consist primarily of transmission and distribution facilities located in its three non-contiguous Texas service areas.  TNMP owned New Mexico transmission and distribution facilities which are located in southwest and south central New Mexico, including the cities of Alamogordo, Ruidoso, Silver City, Lordsburg and surrounding communities until TNMP’s New Mexico assets were transferred to PNM on January 1, 2007.  TNMP also owns and leases service and office facilities in other areas throughout its service territory.

As of December 31, 2009, TNMP owned 958 circuit miles of overhead electric transmission lines, 7,033 pole miles of overhead distribution lines, 1,045 circuit miles of underground distribution lines, and 103 substations.



 
 
A-23

 

ITEM 3.
LEGAL PROCEEDINGS

See Note 16 and Note 17 for information related to the following matters for PNMR, PNM and TNMP, incorporated in this item by reference.

Note 16
    ●  
Regional Haze
    ●  
Citizen Suit Under the Clean Air Act
    ●  
Navajo Nation Environmental Issues
    ●  
Four Corners Federal Implementation Plan Litigation
    ●  
Santa Fe Generating Station
    ●  
Sierra Club Allegations
    ●  
Gila River Indian Reservation Superfund Site
    ●  
PVNGS Water Supply Litigation
    ●  
San Juan River Adjudication
    ●  
Western United States Wholesale Power Market
    ●  
Begay v. PNM et al

Note 17
    ●  
PNM – 2007 Electric Rate Case
    ●  
PNM – Emergency FPPAC
    ●  
TNMP Competitive Transition Charge True-Up Proceeding
    ●  
TNMP Interest Rate Compliance Tariff

ITEM 4.
SUBMISSION OF MATTERS TO A VOTE OF SECURITY HOLDERS

None.

SUPPLEMENTAL ITEM - EXECUTIVE OFFICERS OF PNM RESOURCES, INC.

All officers are elected annually by the Board of PNMR.  Executive officers, their ages as of February 27, 2010 and offices held with PNMR for the past five years, or other companies if less than five years with PNMR, are as follows:

Name
Age
Office
Initial Effective Date
       
J. E. Sterba
54
Chairman and Chief Executive Officer
August 2008
   
Chairman, President and Chief Executive Officer
August 2001
       
P. K. Collawn
51
President and Chief Operating Officer
August 2008
   
President, Utilities
June 2007
   
President and CEO - Public Service Company of
October 2005
   
Colorado, Xcel Energy
 
   
President, Customer and Field Operations, Xcel Energy
July 2003
       
C. N. Eldred
56
Executive Vice President and Chief
 
   
Financial Officer
July 2007
   
Senior Vice President and Chief Financial Officer
January 2006
   
Vice President and Chief Financial Officer,
 
   
Omaha Public Power District
November 1999
       
P.V. Apodaca
58
Senior Vice President, General Counsel and Secretary
January 2010
   
University Counsel, University of New Mexico
May 2006
   
Shareholder and Director, Keleher & McLeod, P.A.
October 1986
       
       


 
A-24

 
A. A. Cobb
62
Senior Vice President and Chief Administrative Officer
June 2005
   
Senior Vice President, Peoples Services and
 
   
Development
December 2001
       
E. J. Ferland
43
Senior Vice President, Utility Operations
May 2007
   
Vice President of Global Nuclear Field Services
September 2006
   
Westinghouse
 
   
President and CEO, Louisiana Energy Services
October 2003
       
T. G. Sategna
56
Vice President and Corporate Controller
October 2003

J. E. Sterba has announced his intention to retire as CEO of PNMR as of March 1, 2010, but will continue as Chairman of the Board.  On February 16, 2010, the Board selected P.K. Collawn to be PNMR’s CEO and a member of the Board effective upon the retirement of J. E. Sterba.

PART II

ITEM 5.      MARKET FOR PNMR’S COMMON EQUITY, RELATED
STOCKHOLDER MATTERS AND ISSUER PURCHASES OF EQUITY SECURITIES

PNMR’s common stock is traded on the New York Stock Exchange (Symbol: PNM).  Ranges of sales prices of PNMR’s common stock, reported as composite transactions, and dividends declared on the common stock for 2009 and 2008, by quarters, are as follows:

 
Quarter Ended
 
Range of
Sales Prices
 
 
Dividends
 
High
 
Low
 
Per Share
2009
         
March 31
$ 11.50
 
$ 5.94
 
$0.125
June 30
$ 11.09
 
$ 7.68
 
$0.125
September 30
$ 12.92
 
$10.36
 
$0.125
December 31
$ 13.08
 
$ 9.75
 
$0.125
Fiscal Year
$ 13.08
 
$ 5.94
 
$  0.50
           
2008
         
March 31
$ 21.69
 
$   8.95
 
$ 0.230
June 30
$ 15.52
 
$ 11.32
 
$ 0.125
September 30
$ 13.06
 
$   9.88
 
$ 0.125
December 31
$ 10.95
 
$   7.56
 
$ 0.125
Fiscal Year
$ 21.69
 
$   7.56
 
$ 0.605

Dividends on PNMR’s common stock are declared by its Board.  The timing of the declaration of dividends is dependent on the timing of meetings and other actions of the Board.  This has historically resulted in dividends considered to be attributable to the second quarter of each year being declared through actions of the Board during the third quarter of the year.  The Board declared dividends on common stock considered to be for the second quarter of $0.125 per share in August 2008 and in July 2009, which are reflected as being in the second quarter above.  The Board declared dividends on common stock considered to be for the third quarter of $0.125 per share in September 2008 and in September 2009, which are reflected as being in the third quarter above.  The dividend of $0.125 per share common stock declared by the Board on August 11, 2008 represents a reduction of 46 percent from the previous quarter. PNMR’s indicated annual dividend rate is $0.50 per share. The Board took this action to improve the Company’s liquidity and set a new foundation for long-term value creation.  The reduction also better aligns PNMR’s dividend yield with industry averages.   On December 9, 2009 and February 16, 2010, the Board declared quarterly dividends of $0.125 per share.  PNMR targets a payout ratio of 50% to 60% of consolidated earnings. Beginning with the dividend declared on December 9, 2008, the Series A convertible preferred stock is entitled to receive dividends equivalent to any dividends paid on PNMR common stock as if the preferred stock had been converted into common stock.
 
 
A-25

 
On February 15, 2010, there were 13,157 holders of record of PNMR’s common stock.

See Note 5 for a discussion on limitations on the payments of dividends and the payment of future dividends, as well as dividends paid by PNM and TNMP.
 
See Part III. Item 12. Security Ownership of Certain Beneficial Owners and Management and Related Stockholder Matters.

Cumulative Preferred Stock

PNMR and PNM are not aware of any active trading market for their preferred stock.  Quarterly cash dividends were paid on PNM’s outstanding cumulative preferred stock at the stated rates during 2009 and 2008.  Holders of PNMR’s convertible preferred stock, which was issued in November 2008, receive dividend payments that are equivalent to the dividends that would have been received on the number of shares of common stock into which the preferred stock was convertible.  TNMP does not have any cumulative preferred stock outstanding.

Sales of Unregistered Securities

None other than as previously reported on Form 8-K.

 


 
 
A-26

 

ITEM 6.                 SELECTED FINANCIAL DATA

The selected financial data and comparative operating statistics for PNMR should be read in conjunction with the Consolidated Financial Statements and Notes thereto and Management’s Discussion and Analysis of Financial Condition and Results of Operations.  PNMR results include TNP results, which are included from the date of acquisition on June 6, 2005.  PNMR results also include results for the Twin Oaks business from the date of acquisition on April 18, 2006 through May 31, 2007, when it was contributed to Optim Energy.  On January 30, 2009, PNM completed the sale of its gas operations, which are considered discontinued operations and excluded from continuing operations information in the table below.

PNM RESOURCES, INC. AND SUBSIDIARIES
 
      2009       2008       2007       2006        2005  
              (In thousands except per share amounts and ratios)           
                                         
Total Operating Revenues from Continuing Operations
  $ 1,647,744     $ 1,959,522     $ 1,914,029     $ 1,963,360     $ 1,566,110  
Earnings (Loss) from Continuing Operations
  $ 65,933     $ (297,565 )   $ 59,886     $ 108,488     $ 54,001  
Net Earnings (Loss)
  $ 136,734     $ (262,937 )   $ 75,402     $ 121,346     $ 68,799  
Net Earnings (Loss) Attributable to PNMR
  $ 124,316     $ (270,644 )   $ 74,874     $ 120,818     $ 65,931  
Earnings (Loss) from Continuing Operations Attributable to
 PNMR per Common Share
                                       
Basic
  $ 0.58     $ (3.66 )   $ 0.77     $ 1.55     $ 0.78  
Diluted
  $ 0.58     $ (3.66 )   $ 0.76     $ 1.53     $ 0.76  
Net Earnings (Loss) Attributable to PNMR per Common Share
                                       
Basic
  $ 1.36     $ (3.24 )   $ 0.98     $ 1.73     $ 1.00  
Diluted
  $ 1.36     $ (3.24 )   $ 0.96     $ 1.71     $ 0.98  
Cash Flow Data
                                       
Net cash flows from operating activities
  $ 87,706     $ 88,625     $ 223,061     $ 244,952     $ 212,976  
Net cash flows from investing activities
  $ 379,726     $ (320,715 )   $ (73,531 )   $ (799,575 )   $ (154,300 )
Net cash flows from financing activities
  $ (593,435 )   $ 354,943     $ (255,158 )   $ 609,843     $ (7,672 )
Total Assets
  $ 5,359,921     $ 6,147,982     $ 5,872,136     $ 6,230,834     $ 5,124,709  
Long-Term Debt, including current installments
  $ 1,567,331     $ 1,584,705     $ 1,681,078     $ 1,769,205     $ 1,746,395  
Common Stock Data
                                       
Market price per common share at year end
  $ 12.65     $ 10.08     $ 21.45     $ 31.10     $ 24.49  
Book value per common share at year end
  $ 19.13     $ 19.13     $ 22.03     $ 22.24     $ 18.89  
Tangible book value per share at year end
  $ 15.33     $ 15.31     $ 14.59     $ 14.44     $ 10.49  
Average number of common shares outstanding
    91,435       83,468       76,719       69,829       65,928  
Dividends declared per common share
  $ 0.500     $ 0.605     $ 0.920     $ 0.880     $ 0.785  
Return on average PNMR common equity
    7.0 %     (16.0 ) %     4.4 %     8.0 %     5.5 %
Capitalization
                                       
PNMR common stockholders’ equity
    49.6 %     49.3 %     50.0 %     49.0 %     42.5 %
Convertible preferred stock
    3.0       3.0       -       -       -  
Preferred stock of subsidiary, without mandatory redemption requirements
    0.3       0.3       0.3       0.3       0.4  
Long-term debt
    47.1       47.4       49.7       50.7       57.1  
      100.0 %     100.0 %     100.0 %     100.0 %     100.0 %

Note – The book value per common share at year end, tangible book value per share at year end, average number of common shares outstanding, and return on average common equity reflect  the Series A convertible preferred stock as if it was converted into common stock at the date of its  issuance on November 17, 2008.
 
 
A-27

 
PNM RESOURCES, INC. AND SUBSIDIARIES
COMPARATIVE OPERATING STATISTICS
                               
   
2009
   
2008
   
2007
   
2006
   
2005
 
   
(In thousands)
 
PNM Electric Revenues
                             
Residential
  $ 320,965     $ 296,121     $ 265,418     $ 222,099     $ 216,890  
Commercial
    330,552       326,408       294,755       257,763       254,580  
Industrial
    79,540       100,665       99,970       62,515       61,146  
Public authority
    19,770       19,135       15,112       13,517       13,484  
Transmission
    36,075       33,161       32,325       25,116       20,049  
Firm requirements wholesale
    29,048       46,854       46,257       42,653       40,836  
Other sales for resale
    140,314       345,948       396,583       459,865       520,549  
Mark-to-market activity
    151       56,560       (44,318 )     3,092       1,817  
Other
    11,594       18,090       30,872       28,844       35,406  
Total PNM Electric Revenues
  $ 968,009     $ 1,242,942     $ 1,136,974     $ 1,115,464     $ 1,164,757  
TNMP Electric Revenues
                                       
Residential
  $ 74,739     $ 71,673     $ 69,488     $ 89,378     $ 57,145  
Commercial
    73,346       72,786       70,146       88,767       51,670  
Industrial
    12,113       13,849       7,876       40,501       25,189  
Other
    32,434       31,974       32,911       38,344       20,346  
Total TNMP Revenues
  $ 192,632     $ 190,282     $ 180,421     $ 256,990     $ 154,350  
Altura Wholesale Revenues
                                       
Long-term contracts
  $ -     $ -     $ 65,395     $ 125,131     $ -  
First Choice Revenues
                                       
Residential
  $ 349,629     $ 407,350     $ 390,329     $ 345,961     $ 198,218  
Mass-market
    25,652       52,700       60,955       81,917       53,111  
Mid-market
    133,145       149,315       141,587       129,171       46,584  
Trading gains (losses)
    14       (49,931 )     (3,553 )     9,322       5,970  
Other
    20,378       22,790       11,377       18,528       12,447  
Total First Choice Revenues
  $ 528,818     $ 582,224     $ 600,695     $ 584,899     $ 316,330  


 
Notes:
TNMP and First Choice are reported from the date of acquisition, June 6, 2005.
Altura Wholesale includes Twin Oaks from the date of acquisition, April 18, 2006 through May 31, 2007 when Altura was contributed to Optim Energy.
Effective January 1, 2007, TNMP’s New Mexico operations were transferred to PNM Electric.
PNM Electric revenues have been reclassified to be consistent with the current year presentation.
PNM Gas, which was sold on January 30, 2009, is reported as discontinued operations and has been excluded from the above table.



 
 
A-28

 

PNM RESOURCES, INC. AND SUBSIDIARIES
COMPARATIVE OPERATING STATISTICS
 
   
2009
   
2008
   
2007
   
2006
   
2005
 
                               
PNM Electric MWh Sales
                             
Residential
    3,264,378       3,221,894       3,208,593       2,764,299       2,652,475  
Commercial
    3,899,121       4,029,802       4,006,373       3,636,637       3,527,268  
Industrial
    1,454,480       1,657,580       1,920,086       1,327,287       1,277,156  
Public authority
    249,554       253,079       236,651       229,308       228,394  
Firm requirements wholesale
    689,740       1,123,539       1,121,695       1,074,161       1,019,574  
Other sales for resale
    3,996,317       5,095,183       6,897,307       8,091,146       9,038,284  
Total PNM Electric MWh Sales
    13,553,590       15,381,077       17,390,705       17,122,838       17,743,151  
TNMP Electric MWh Sales
                                       
Residential
    2,582,555       2,533,025       2,520,605       2,734,385       1,839,741  
Commercial
    2,216,870       2,206,155       2,195,962       2,579,854       1,399,864  
Industrial
    1,983,165       2,094,789       1,927,934       2,157,507       1,263,452  
Other
    107,091       107,524       100,581       121,227       72,262  
Total TNMP MWh Sales
    6,889,681       6,941,493       6,745,082       7,592,973       4,575,319  
Altura Wholesale MWh Sales
                                       
Long-term contracts
    -       -       915,883       1,683,707       -  
First Choice MWh Sales
                                       
Residential
    2,441,550       2,547,490       2,796,864       2,481,557       1,591,006  
Mass-market
    145,618       278,304       371,825       549,143       400,840  
Mid-market
    1,063,602       1,176,840       1,197,329       1,159,160       478,531  
Other
    9,729       16,256       21,075       20,921       29,780  
Total First Choice MWh Sales
    3,660,499       4,018,890       4,387,093       4,210,781       2,500,157  

 
Notes:
 
TNMP and First Choice are reported from the date of acquisition, June 6, 2005.
 
Altura Wholesale includes Twin Oaks from the date of acquisition, April 18, 2006 through May 31, 2007 when Altura was contributed to Optim Energy.
 
Effective January 1, 2007, TNMP’s New Mexico operations were transferred to PNM Electric.
 
Under TECA, customers of TNMP Electric in Texas can choose First Choice or any other REP to provide energy.  However, TNMP Electric delivers energy to customers
   within its service area regardless of the REP chosen.  Therefore, TNMP Electric earns revenue for energy delivery and First Choice earns revenue on the usage of
   that energy by its customers.  The MWh reported above for TNMP Electric and First Choice include 1,131,907, 1,563,260, 2,018,110, 2,332,098, and 1,644,675 MWh
    used by customers of TNMP Electric in 2009, 2008, 2007, 2006, and 2005 who have chosen First Choice as their REP.
 
PNM Electric MWh sales have been reclassified to be consistent with the current year presentation.
 
PNM Gas, which was sold on January 30, 2009, is reported as discontinued operations and has been excluded from the above table.





 
 
A-29

 


PNM RESOURCES, INC. AND SUBSIDIARIES
COMPARATIVE OPERATING STATISTICS


   
2009
   
2008
   
2007
   
2006
   
2005
 
PNM Electric Customers
                             
Residential
    445,637       442,647       438,990       388,775       378,116  
Commercial
    53,787       53,059       52,780       45,678       44,721  
Industrial
    270       284       276       279       281  
Other sales for resale
    44       55       54       75       76  
Other
    991       991       1,023       829       838  
Total PNM Electric Customers
    500,729       497,036       493,123       435,636       424,032  
TNMP Electric Customers
                                       
Residential
    190,963       189,961       184,304       224,424       222,819  
Commercial
    37,834       38,733       39,979       47,566       44,119  
Industrial
    73       74       76       78       125  
Other
    2,060       2,122       2,104       2,224       2,244  
Total TNMP Customers
    230,930       230,890       226,463       274,292       269,307  
Altura Wholesale Customers
                                       
Long-term
    -       -       1       1       -  
First Choice Customers
                                       
Residential
    183,842       192,517       209,833       206,393       178,150  
Mass-market
    9,290       11,544       16,392       21,858       24,364  
Mid-market
    25,165       24,764       21,325       16,051       6,475  
Other
    6,679       8,606       10,819       9,427       10,539  
Total First Choice Customers
    224,976       237,431       258,369       253,729       219,528  
PNMR Generation Statistics
                                       
Reliable Net Capability - MW
    2,711       2,713       2,206       1,934       1,744  
Coincidental Peak Demand - MW
    1,866       1,901       1,933       1,855       1,779  
Average Fuel Cost per Million BTU
  $ 1.895     $ 2.404     $ 1.7539     $ 1.7143     $ 1.4711  
BTU per KWh of Net Generation
    10,277       10,269       10,850       10,641       10,706  

 
Notes:
TNMP and First Choice are reported from the date of acquisition, June 6, 2005.
Altura Wholesale includes Twin Oaks from the date of acquisition, April 18, 2006 through May 31, 2007 when Altura was contributed to Optim Energy.
Effective January 1, 2007, TNMP’s New Mexico operations were transferred to PNM Electric.
The customers reported above for TNMP Electric and First Choice include 81,277, 92,792, 127,328, 147,094, and 158,828 customers of TNMP Electric at
   December 31, 2009, 2008, 2007, 2006, and 2005 who have chosen First Choice as their REP.  These TNMP Electric customers are also included in the First Choice customers.
First Choice customers have been reclassified to be consistent with the current year presentation.
PNM Gas, which was sold on January 30, 2009, is reported as discontinued operations and has been excluded from the above table.





 
 
A-30

 

ITEM 7.
MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS

The following Management’s Discussion and Analysis of Financial Condition and Results of Operations for PNMR is presented on a combined basis, including certain information applicable to PNM and TNMP.  The MD&A for PNM and TNMP is presented as permitted by Form 10-K General Instruction I (2).  A reference to a “Note” in this Item 7 refers to the accompanying Notes to Consolidated Financial Statements included in Item 8, unless otherwise specified.  Certain of the tables below may not appear visually accurate due to rounding.

MD&A FOR PNMR

BUSINESS AND STRATEGY

Overview
 
    PNMR provides electricity and energy efficiency products and services in core regulated and unregulated markets to help customers meet and manage their energy needs.  PNM sold its gas operations on January 30, 2009 and is now focused on its regulated electric business going forward.

PNM

Critical to PNMR’s success for the foreseeable future is the financial health of PNM, PNMR’s largest subsidiary, which is highly dependent on continued favorable regulatory treatment.  As discussed in Note 17, on September 22, 2008, PNM filed its 2008 Electric Rate Case requesting the NMPRC to approve an increase in electric service rates to all PNM retail customers except those formerly served by TNMP. The proposed rates were designed to increase annual operating revenue by $123.3 million. PNM also proposed a more traditional FPPAC.  In June 2009, the NMPRC approved a stipulation resolving all issues in the rate case, including the inclusion of additional sources of power in determining rates.  The approved stipulation allows for an increase in annual non-fuel revenues of $77.1 million, 65% of which was implemented for bills rendered beginning July 1, 2009 and the remainder of which will be implemented April 1, 2010.  As an offset to the non-fuel revenue increase, PNM implemented a credit to customers totaling $26.3 million, representing the amount of revenues from past sales of SO2 allowances.  This amount is being credited to customers over 21 months beginning July 1, 2009.  PNM recorded an expense for the regulatory disallowance and recorded a regulatory liability for the amount to be credited to customers. The stipulation also provided for a more traditional FPPAC that went into effect with the new rates.  The new FPPAC has an annual rather than a monthly adjustment mechanism, but is based on forecasted fuel and purchased power costs.  The stipulation provides that 100% of off-systems sales revenues from resources included in retail rates be credited against fuel and purchased power costs in the FPPAC.

PNM anticipates a trend toward increasing costs of providing electric service and a period of plant expansion, primarily from renewable energy sources under the renewable energy portfolio requirements established pursuant to New Mexico’s Renewable Energy Act and related regulations of the NMPRC.  PNM also anticipates increases in costs related to renewals of rights of way on Native American lands, pension and benefits, and depreciation at SJGS.  PNM will seek to recover these increased costs of providing service to regulated customers through future rate filings, which may occur more frequently than in the past.  The impact that rate increases may have on customers’ usage and their ability to pay is unknown.

Senate Bill 477 (“SB 477”) became effective in June 2009.  SB 477 is designed to promote more timely recovery of reasonable costs of providing utility service in two ways.  First, SB 477 requires the NMPRC, when setting rates, to use the test period that best reflects the conditions the utility will experience when new rates are anticipated to go into effect.  The NMPRC is required to give due consideration that a future test period may be the one that best meets this requirement.  A future test period is defined as a twelve month period beginning no later than the date a proposed rate change is expected to take effect.  Traditionally, the NMPRC has used a historical test period, adjusted for known and measurable changes occurring within five to six months after the end of the test period, which reflects costs that could be up to two years old at the time new rates become effective.  It is possible, however, that NMPRC staff or intervenors would argue that continued use of a historical test period, adjusted for known and measurable changes, best meets the requirement.  Second, SB 477 requires the NMPRC to include
 
 
A-31

 
construction work in progress in rate base, without an offset for allowance for funds used during construction, for environmental improvement projects and generation and transmission projects for which a certificate of public convenience and necessity has been issued.   This provision will allow utilities to collect costs as projects are being built rather than waiting until they are finished to include them in rate base, so long as the projects will be in service no later than two years after the filing date of the rate case.

PNM anticipates filing a rate case with the NMPRC in mid 2010 using a future test period as allowed by SB 477.  The magnitude of amounts to be requested is currently unknown and PNM cannot predict the amount that the NMPRC will approve.   PNM also anticipates filing a rate case with FERC in the fourth quarter of 2010 for its firm transmission customers.  The magnitude of the rate increase is currently unknown and PNM cannot predict the amount FERC will approve.  The rate base for the firm transmission customers is estimated to be between $160 million and $170 million.

The use of a future test year should help PNM to mitigate the adverse effects of regulatory lag, which is inherent when using a historical test year, by focusing on what costs are likely to be when new rates go into effect rather than what they were in the past.  The mitigation of the adverse effects of regulatory lag should result in PNM’s earnings more closely approximating the rate of return allowed by the NMPRC.  PNMR believes that achieving earnings that approximate its allowed rate of return is an important factor in attracting equity investors, as well as being an important metric utilized by credit rating agencies and financial analysts.  PNM’s debt securities are currently rated below investment grade by S&P, although Moody’s still rates PNM’s debt at the lowest level of investment grade.  PNM currently expects it will access the credit and capital markets in order to finance at least a portion of the anticipated construction expenditures discussed in Capital Requirements under Liquidity and Capital Resources below.  To the extent such financing includes the issuance of debt securities that are rated below investment grade, the debt would carry a higher interest rate than if the securities were investment grade.  Those higher interest costs would then be included in requests for rate relief, placing additional upward pressure on rates charged to customers.

As with any forward looking financial information, utilizing a future test year in a rate filing presents challenges that are inherent in the forecasting process.  PNM will need to forecast both operating and capital expenditures that will necessitate reliance on many assumptions concerning future conditions.  Among others, these would include assumptions about future economic conditions in PNM’s service territory, levels of employment, load growth and conservation, weather, usage patterns of customers, availability and technology regarding renewable energy sources, interest rates and other financing costs, access to capital markets, inflation, and impacts of regulatory actions.  In the rate making process, PNM’s assumptions will be subject to challenge by regulators and intervenors who may assert different interpretations or assumptions.

    PNM has completed the separation of its merchant operations from its regulated operations to comply with a 2003 NMPRC order.  The separation of merchant operations was accomplished in several steps.  Afton was transferred from merchant plant status and was included in retail rates in PNM’s 2007 Electric Rate Case.  In June 2008, PNM completed the sale of certain merchant wholesale power, natural gas and transmission contracts.  In addition, Luna and Lordsburg had been classified as merchant plant but in June 2009, the NMPRC approved PNM’s request in its 2008 Electric Rate Case that Luna and Lordsburg be included in retail rates.  See Note 17. This completed the separation required by the NMPRC.  The NMPRC did not require that PNM’s interest in PVNGS Unit 3 be separated from PNM.  PNM has entered into contracts for the sale of capacity and energy from its entire ownership interest in PVNGS Unit 3 through December 31, 2010. 

    PNM also serves customers in New Mexico formerly served by TNMP.  When PNMR acquired TNMP, PNM was required to maintain the former TNMP customers under rates separate from the rest of PNM.  Pursuant to a stipulation approved by the NMPRC, PNM was prohibited from consolidating the cost of service for the two areas until January 1, 2015, unless the consolidation would not result in shifting more than $1.5 million in revenue requirements from the former TNMP customers to other PNM customers.  In addition, the stipulation provided that PNM would not seek rate changes for the former TNMP customers that would go into effect before January 1, 2011.  During 2009, the NMPRC requested the parties to the stipulation meet to discuss ways and means of mitigating possible large rate increases to the former TNMP customers that may occur when the rate moratorium expires.  The parties have been meeting periodically under the direction of a NMPRC Hearing Examiner, who was appointed by the NMPRC to serve as mediator for the discussions.   See Note 17.

 
 
A-32

 
 
TNMP
 
    TNMP’s financial health is also highly dependent on continued favorable regulatory treatment.  On August 29, 2008, TNMP filed with the PUCT for an $8.7 million increase in revenues.  Subsequently, TNMP supplemented its filing to request an additional revenue increase of $15.7 million to recover costs caused by Hurricane Ike and costs related to the financing completed in March 2009.  In June 2009, TNMP and the other parties in the rate case reached a unanimous settlement resolving all issues in the rate case and permitting TNMP to increase its rates by $12.7 million annually.  This increase reflects interest and other costs associated with debt refinancing in March 2009 and the settlement adjusts the interest rate TNMP is allowed to collect on its CTC to reflect those costs.  The rate increase includes recovery of Hurricane Ike restoration costs plus carrying costs over five years.  The settlement was approved by the PUCT in August 2009.  TNMP now has the ability to update its transmission rates annually to reflect changes in its invested capital.  TNMP anticipates filing a request to update its rates under this provision in early to mid 2010.  Updated rates will reflect the addition and retirement of transmission facilities, including appropriate depreciation, federal income tax and other associated taxes, and the approved rate of return on such facilities.
 
Environmental Sustainability
 
    The Company’s focus on the electric businesses also includes environmental sustainability efforts.  These efforts include environmental upgrades, improving energy efficiency, expanding the renewable energy portfolio of generation resources, and proactively addressing climate change. In early 2009, PNM completed environmental upgrades to each of the four units at SJGS.  PNM’s share of the costs of these upgrades, which reduced the levels of NOX, SO2, and mercury emissions, amounted to $161 million.  As described in Note 17, PNM is subject to the renewable portfolio standard established by New Mexico’s Renewable Energy Act and related regulations issued by the NMPRC, which require utilities to achieve certain levels of energy sales from renewable sources within its generation mix, including wind, solar, distributed generation, and other sources.  PNM is actively engaged in activities to meet the NMPRC standard.  PNM has also established various programs to promote energy efficiency, subject to the approval of the NMPRC.  The Company monitors initiatives regarding legislation or regulation regarding climate change, including GHG, and participates in organizations and forums concerning climate change. The Company has expressed support for the Waxman-Markey bill (see MD&A – Other Issues Facing the Company) and is generally supportive of a federal program that includes an economy-wide system of limitations on GHG that would include a cap and trade provision and a system of allowances and offsets designed to mitigate rate increases to utility customers.  The Company is exploring various methods to mitigate its GHG in anticipation of climate change legislation or regulation, including increasing energy efficiency programs and increased reliance on renewable energy resources.  See Climate Change Issues under Other Issues Facing the Company below for additional discussion of climate change matters.  All of these efforts involve costs that the Company believes should be recoverable through rates charged to customers to the extent the costs are attributable to regulated operations.  However, recovery of these costs is subject to the approval of regulators and will cause upward pressure on rates.

First Choice

As a REP, First Choice operates in the highly competitive Texas retail market, which experienced extreme price volatility and transmission congestion in 2008.  ERCOT controls the transmission of power in the areas that First Choice supplies.  ERCOT historically has operated through a series of geographic zones, which has led to congestion of the transmission system when large volumes of power were being transmitted between zones. Congestion tends to drive prices up in the spot market. These situations caused First Choice to incur losses in its speculative trading portfolio and led First Choice to exit its speculative activities in the second quarter of 2008.  These anomalies also negatively impacted the margins realized from end use customers.  These conditions were exacerbated by the impacts of Hurricane Ike and depressed economic conditions resulting in very high levels of customer turnover and levels of uncollectible accounts significantly higher than historical experience.  ERCOT has made changes in its control protocols and is scheduled to change from the zonal system to a nodal system in December 2010, both of which should reduce congestion and price volatility.  During 2009, the Texas retail market was more stable and First Choice does not anticipate the levels of extreme congestion and price volatility will reoccur in the near future.  In addition, both power and natural gas prices decreased significantly, resulting in a
 
 
A-33

 
substantial increase in margins realized by First Choice.  These factors and increased focus on growing commercial accounts, customer credit standards, and improved customer service have contributed to an improvement in the results of operations at First Choice. However, similar to how the ERCOT market conditions - along with First Choice's buying and selling positions within that market - had a negative impact on the business in 2008, those same factors worked in First Choice’s favor in 2009.  For 2010, First Choice expects market conditions to continue to be a key factor for the business and believes margins will return to more historic levels.

Economic Conditions

    In the last half of 2008 and early 2009, global economic conditions deteriorated dramatically, encompassing the U.S. residential housing market, and global and domestic equity and credit markets, which resulted in reduced usage of electricity by the Company’s customers.  The tightening of the credit markets coupled with extreme volatility in commodity markets has had a direct, negative impact on several of First Choice’s competitors in the ERCOT retail market.

    Although New Mexico and Texas do not seem to be impacted as greatly as some other areas of the United States, with unemployment rates that are somewhat lower than the rest of the nation, the territories served by the Company’s electric businesses have been impacted by the recession and general economic downturn.  As a result, the weather-adjusted volume of electric sales decreased in 2009 compared to 2008. The Company believes that electric sales volume will be relatively flat for the immediate future.

    The unprecedented disruption in the credit markets in late 2008 and early 2009 had a significant adverse impact on numerous financial institutions, including several of the financial institutions that have dealings with the Company. However, at this time, the Company’s existing liquidity instruments have not been materially impacted by the credit environment and management does not expect that it will be materially impacted in the near future.  The Company’s revolving credit facilities expire in 2011 and 2012 and will need to be renegotiated or replaced in order to provide sufficient liquidity to finance operations and construction expenditures.  The availability of such credit facilities and their terms and conditions will depend on the credit markets at that time, as well as the Company’s credit ratings and operating results. The Company is closely monitoring its liquidity and the credit markets.  In late 2008 and early 2009, there was also a significant decline in the level of prices of marketable equity securities, including those held in trusts maintained for future payments of benefits under pension and retiree medical plans.  Although the general price levels of marketable equity securities has recovered somewhat, the stock market decline will likely result in increased levels of funding and expense applicable to these trusts.

Optim Energy

PNMR has previously reported that it intended to capitalize on growth opportunities in its unregulated business through its participation and ownership in Optim Energy.  PNMR’s 50 percent ownership of Optim Energy allows it to participate in the operation of Optim Energy’s assets and business and the formulation of Optim Energy’s business strategy.  Optim Energy owns electric generating assets in one of the nation’s growing power markets, and its strategy has been focused on acquiring or developing additional assets in that market.  Consistent with this strategy, Optim Energy acquired the Twin Oaks plant in June 2007 and the Altura Cogen plant in August 2007 and completed co-developing an electric generation unit at Cedar Bayou in June 2009.

In 2009, however, Optim Energy was affected by continuing adverse market conditions, primarily low natural gas and power prices.  In response to those adverse conditions, in October 2009, Optim Energy changed its current strategy and near-term focus. Optim Energy is currently focused on utilizing cash flow from operations to reduce debt and optimizing its current generation assets as a stand-alone independent power producer.  The change resulted in staff positions being eliminated at Optim Energy, as well as integration of certain operations.  The goal is to position Optim Energy to optimize its performance under current market conditions with the expectation of being able to take advantage of any economic recovery in the power and gas markets over the next several years.

Any decisions in the future to grow capacity will be subject to the approval of both of Optim Energy’s members and will be based on many then-existing market and other factors, including the cost to acquire or construct capacity, the anticipated demand for power, the anticipated market prices for power, the ability and cost to deliver power to the anticipated markets, and Optim Energy’s financial resources.
 
 
A-34

 
RESULTS OF OPERATIONS – PNMR

Executive Summary

A summary of net earnings (loss) attributable to PNMR is as follows:

   
Year Ended December 31,
   
Change
 
   
2009
   
2008
   
2007
      2009/2008       2008/2007  
         
(In millions, except per share amounts)
 
                   
Earnings (loss) from continuing operations
  $ 53.5     $ (305.3 )   $ 59.4     $ 358.8     $ (364.6 )
Earnings from discontinued operations,
net of income taxes
    70.8       34.6       15.5       36.2       19.1  
Net earnings (loss)
  $ 124.3     $ (270.6 )   $ 74.9     $ 394.9     $ (345.5 )
Average common and common equivalent shares
    91.7       83.5       77.9       8.2       5.6  
Earnings (loss) from continuing operations per diluted share
  $ 0.58     $ (3.66 )   $ 0.76     $ 4.24     $ (4.42 )
Net earnings (loss) per diluted share
  $ 1.36     $ (3.24 )   $ 0.96     $ 4.60     $ (4.20 )

The components of the changes in earnings (loss) from continuing operations attributable to PNMR by segment are:

   
Change
 
      2009/2008       2008/2007  
   
(In millions)
 
PNM Electric
  $ 86.5     $ (89.9 )
TNMP Electric
    21.0       (27.2 )
Altura
    -       (5.2 )
First Choice
    222.0       (204.8 )
Corporate and Other
    29.6       (15.1 )
Optim Energy
    (0.3 )     (22.5 )
  Net change
  $ 358.8     $ (364.6 )

Results of operations improved significantly in 2009 due largely to rate increases at our regulated utilities and strong performance at First Choice. On July 1, 2009, PNM Electric implemented the first phase of a $77.1 million non-fuel base rate increase for retail customers, except those formerly served by TNMP. PNM Electric was also granted a more traditional FPPAC, which replaced the Emergency FPPAC that terminated on July 1, 2009. On September 1, 2009, TNMP implemented a $6.8 million base rate increase. Additionally, retail margins at First Choice significantly improved.  Increases in 2009 were partially offset by regulatory disallowances of $16.2 million, after income taxes, primarily relating to prior sales of SO2 emission allowances that resulted from the settlement of PNM’s 2008 Electric Rate Case and a $19.3 million after-tax charge related to the settlement of the California energy crisis legal proceeding by PNM.  In addition, Optim Energy reduced the value of its held for sale NOx emission allowances. PNMR’s share of the after-tax charge was $15.6 million.

 Results of operations were negatively impacted by several major factors during 2008.  Impairments of goodwill and other intangible assets were recorded at PNM, TNMP, and First Choice, as well as at Optim Energy.  After-tax impairment losses reduced net earnings by $212.1 million.  PNM Electric recorded regulatory disallowances of $18.3 million after-tax resulting from its 2007 Electric Rate Case.  General declines in the stock market negatively impacted the values of investments in the NDT resulting in an after-tax decrease in earnings of $16.2 million in 2008 compared to 2007.  As a result of anomalies in the Texas energy market, First Choice experienced after-tax losses in its speculative trading operations, which were terminated in 2008, that were $29.8 million greater in 2008 than 2007.  In addition, economic conditions resulted in high default rates and uncollectible accounts at First Choice resulting in First Choice bad debt expense being $23.6 million greater after-tax in 2008 than
 
A-35

 
in 2007.  Optim Energy wrote-off its inventory of emissions allowances related to CAIR as a result of that program being invalidated.  PNMR’s share of the after-tax loss was $9.6 million.  Income tax expense or benefit for 2008 was significantly impacted by the impairments of goodwill since the expense recorded for the impairments is not deductible for income tax purposes.  The consolidated effective income tax rates for 2008 were 23.38% for PNMR, 14.47% for PNM, and 476.65% for TNMP.  Excluding the losses due to goodwill impairment, the effective income tax rates would have been 42.43% for PNMR, 55.16% for PNM, and 30.25% for TNMP. The consolidated effective income tax rates for 2009 were 30.41% for PNMR, 30.08% for PNM, and 39.63% for TNMP.
 
    The increase in the number of common and common equivalent shares is primarily due to new issuances of PNMR common stock in connection with the equity-linked units in 2008. See Note 6.

Segment Information

The following discussion is based on the segment methodology that PNMR’s management uses for making operating decisions and assessing performance of its various business activities.  See Note 3 for more information on PNMR’s operating segments.

The following discussion and analysis should be read in conjunction with the Consolidated Financial Statements and Notes thereto.  Trends and contingencies of a material nature are discussed to the extent known.  Refer also to Disclosure Regarding Forward Looking Statements in Item 1 and to Part II, Item 7A. Risk Factors.

PNM Electric

The table below summarizes operating results for PNM Electric:

   
Year Ended December 31,
   
Change
 
   
2009
   
2008
   
2007
      2009/2008       2008/2007  
   
(In millions)
 
                   
Total revenues
  $ 968.0     $ 1,242.9     $ 1,137.0     $ (274.9 )   $ 106.0  
Cost of energy
    378.1       698.1       638.7       (319.9 )     59.4  
Gross margin
    589.9       544.9       498.3       45.0       46.6  
Operating expenses
    420.5       465.7       381.1       (45.2 )     84.6  
Depreciation and amortization
    92.1       85.7       83.2       6.4       2.5  
Operating income (loss)
    77.3       (6.5 )     34.0       83.8       (40.5 )
Other income (deductions)
    37.4       7.1       53.3       30.4       (46.2 )
Net interest charges
    (69.1 )     (69.9 )     (52.7 )     0.8       (17.2 )
Earnings (loss) before income taxes
    45.6       (69.3 )     34.6       115.0       (103.9 )
Income (taxes) benefit
    (13.7 )     10.0       (11.2 )     (23.8 )     21.2  
Valencia non-controlling interest
    (11.9 )     (7.2 )     -       (4.7 )     (7.2 )
Preferred stock dividend requirements
    (0.5 )     (0.5 )     (0.5 )     -       -  
Segment earnings (loss)
  $ 19.5     $ (67.0 )   $ 22.9     $ 86.5     $ (89.9 )

The table below summarizes the significant changes to total revenues, cost of energy, and gross margin:

 
   
2009/2008 Change
   
2008/2007 Change
 
    Total     Cost of     Gross     Total     Cost of     Gross  
    Revenues     Energy     Margin     Revenues     Energy     Margin  
                 (In millions)              
                                     
Retail rate increases
  $ 37.3     $ 16.4     $ 20.9     $ 36.3     $ -     $ 36.3  
Retail load, fuel and transmission
    (55.5 )     (102.3 )     46.8       66.6       65.6       1.0  
Sales of SO2 credits
    -       -       -       (17.2 )     -       (17.2 )
Unregulated margins
    (199.4 )     (163.7 )     (35.7 )     (81.1 )     (89.2 )     8.1  
Sale of merchant portfolio
    (56.4 )     (51.3 )     (5.1 )     56.4       51.3       5.1  
Net unrealized economic hedges
    (0.9 )     (11.2 )     10.3       44.9       42.1       2.8  
Consolidation of Valencia PPA
    -       (7.8 )     7.8       -       (10.4 )     10.4  
 Other                       0.1              0.1   
    Total increase (decrease)    $ (274.9    $ (319.9   45.0      $  106.0     59.4      46.6   
 
 
 
A-36

 
The following table shows PNM Electric operating revenues by customer class, including intersegment revenues and average number of customers:

   
Year Ended December 31,
   
Change
 
   
2009
   
2008(1)
   
2007(1)
      2009/2008       2008/2007  
   
(In millions, except customers)
 
                                   
Residential
  $ 321.0     $ 296.1     $ 265.4     $ 24.9     $ 30.7  
Commercial
    330.6       326.4       294.8       4.2       31.6  
Industrial
    79.5       100.7       100.0       (21.2 )     0.7  
Public authority
    19.8       19.1       15.1       0.7       4.0  
Transmission
    36.1       33.2       32.3       2.9       0.9  
Firm requirements wholesale
    29.0       46.9       46.3       (17.9 )     0.6  
Other sales for resale
    140.3       345.9       396.6       (205.6 )     (50.7 )
Mark-to-market activity
    0.1       56.6       (44.3 )     (56.5 )     100.9  
Other
    11.6       18.0       30.8       (6.4 )     (12.7 )
    $ 968.0     $ 1,242.9     $ 1,137.0     $ (274.9 )   $ 106.0  
Average retail customers (thousands)
    499.0       495.3       489.4       3.7       5.9  

(1)  The customer class revenues have been reclassified to be consistent with the current year presentation.

The following table shows PNM Electric GWh sales by customer class:

   
Year Ended December 31,
   
Change
 
   
2009
   
2008(1)
   
2007(1)
      2009/2008       2008/2007  
   
(Gigawatt hours)
 
                                   
Residential
    3,264.4       3,221.9       3,208.6       42.5       13.3  
Commercial
    3,899.1       4,029.8       4,006.4       (130.7 )     23.4  
Industrial
    1,454.5       1,657.6       1,920.1       (203.1 )     (262.5 )
Public authority
    249.6       253.1       236.7       (3.5 )     16.4  
Firm requirements wholesale
    689.7       1,123.5       1,121.7       (433.8 )     1.8  
Other sales for resale
    3,996.3       5,095.2       6,897.3       (1,098.9 )     (1,802.1 )
      13,553.6       15,381.1       17,390.8       (1,827.5 )     (2,009.7 )

      (1)  The customer class volumes have been reclassified to be consistent with the current year presentation.

The results of operations of PNM Electric are primarily driven by the rate making decisions and other actions of the NMPRC.  On July 1, 2009, PNM Electric implemented the first phase of a $77.1 million non-fuel base rate increase for retail customers, except those formerly served by TNMP.  The first phase allowed PNM to increase customer bills for 65% of the annual base rate increase or $50.1 million.  PNM will implement the second phase, or the remaining 35% of the annual base rate increase, beginning April 1, 2010.  In the 2008 Electric Rate Case, PNM Electric was also granted a more traditional FPPAC, which replaced the Emergency FPPAC on July 1, 2009.  PNM Electric revenues and margin further increased because of a rate increase that was implemented in the second quarter of 2008.

In 2009, decreases in retail revenues were driven by lower retail loads, due to milder weather combined with lower usage per customer and reduced operations of a major industrial customer.   In addition, retail revenues were further reduced by lower economy sales volumes and prices in 2009.  These decreases in revenues were more than offset by recovery of fuel costs through the FPPAC for retail customers, except those formerly served by TNMP, and lower natural gas and economy purchase costs improved regulated margins for those customers without a FPPAC.

In 2008, PNM Electric revenues and gross margins increased compared to 2007 due to a base rate increase and the implementation of the Emergency FPPAC in second quarter 2008.  These increases were partially offset due
 
A-37

 
to higher coal prices and higher replacement power prices for market purchases required when resources were not sufficient to meet load requirements, largely due to reduced availability at SJGS.  These costs were partially offset by an increase in off-system sales revenues largely due to increased availability at PVNGS, which allowed for market sales when resources were in excess of load requirements.

Beginning with the implementation of new rates on July 1, 2009, the retail portion of sales of SO2 emission allowances are passed through to retail customers via a rate rider.  In 2008, lower sales of SO2 emission allowances reduced revenues and margin.

Prior to May 2009, the revenues and cost associated with Luna, Lordsburg, and the Valencia PPA were included in unregulated margins. Upon approval of the Resource Stipulation (see Note 17), the costs of the Valencia PPA and Luna and Lordsburg, net of off-system revenues are recovered through the regulatory process, which reduces unregulated margins.  Unregulated revenues and margins were further reduced due to pre-tax charges of $32.0 million associated with a settlement with California Parties arising out of certain transactions in the California energy markets during 2000 and 2001 (see Note 16).  Other increases in unregulated margins due to favorable pricing terms under a forward sales agreement for power from PNM’s interest in PVNGS Unit 3 are offset by the settlement of favorable pricing from hedge positions taken in the prior year.

PNM Electric analyzes results associated with the Valencia PPA as costs of energy, which prior to the approval of the Resources Stipulation were reflected in unregulated margins.  As discussed above, beginning in May 2009, the Valencia PPA is being recovered through regulated rates. Under GAAP, the Valencia PPA is consolidated, which results in costs being reflected as operating expenses and non-controlling interest that would have been included in cost of energy if the Valencia PPA was not consolidated.

In 2008, unregulated revenues and cost of energy related to unregulated margins decreased due to the sale of the merchant portfolio in June 2008.  PNM’s merchant portfolio included certain wholesale power, natural gas and transmission contracts that reflected a significant portion of unregulated activity at PNM.  These decreases were partially offset by increased revenues and cost of energy, including demand charges, from the dispatch of unregulated gas plants based on market profitability.  Additionally, unregulated revenues increased due to increased PVNGS availability and more favorable pricing terms under the forward sales agreement at PVNGS, resulting in a net increase to margin.

Operating expenses decreased in 2009, primarily due to a $51.1 million impairment loss on goodwill in 2008.  No impairments were recorded in 2009.  In 2009, PNM Electric recorded regulatory disallowances of $26.3 million relating to prior sales of SO2 emission allowances and $0.5 million of deferred rate case expenses that resulted from the settlement of the 2008 Electric Rate Case, compared to regulatory disallowances in 2008 as a result of the 2007 Electric Rate Case of $10.6 million and $19.6 million related to the write-off of deferred costs of RECs and coal mine decommissioning costs.  Lower operating expenses due to reduced planned environmental outages at SJGS and planned outages at PVNGS, the impairment of certain Afton costs above amounts approved in a regulatory order in 2008, and labor savings, are more than offset by increases in pension and benefit costs, increased allocation of corporate overhead costs, and higher taxes other than income resulted from technology tax credits taken in 2008.

Depreciation and amortization costs increased in 2009 and 2008.  These cost increases are primarily driven by the completion of the environmental upgrades on all four units at SJGS and increases in distribution and transmission plant.    In 2008, depreciation expense increased primarily due to the completion of Afton.

In 2009, PNM recognized interest income related to uncertain income tax positions associated with changes in book to tax differences on capitalization, compared to a reduction in interest income in 2008.  In addition, other income increased in 2009 due to improved performance of the NDT assets.  In 2008, other income and deductions were reduced due to realized losses as well as impairment losses related to the NDT assets.

In 2009, higher long-term interest costs on debt are offset by lower outstanding debt balances and lower interest rates and transaction fees on short-term borrowings.  In 2008, interest expenses increased due to higher borrowings at higher long-term interest rates, along with transaction fees associated with the refinancing of debt.


 
 
A-38

 

TNMP Electric

The table below summarizes the operating results for TNMP Electric:


   
Year Ended December 31,
   
Change
 
   
2009
   
2008
   
2007
      2009/2008       2008/2007  
   
(In millions)
 
                   
Total revenues
  $ 192.6     $ 190.3     $ 180.4     $ 2.4     $ 9.9  
Cost of energy
    34.7       32.7       29.5       2.1       3.2  
Gross margin
    157.9       157.6       150.9       0.3       6.7  
Operating expenses
    75.5       101.5       67.8       (25.9 )     33.6  
Depreciation and amortization
    37.3       38.7       30.4       (1.4 )     8.3  
Operating income
    45.1       17.4       52.7       27.7       (35.2 )
Other income (deductions)
    2.9       3.2       1.6       (0.4 )     1.7  
Net interest charges
    (27.8 )     (18.3 )     (25.2 )     (9.5 )     6.8  
Earnings before income taxes
    20.2       2.3       29.1       17.8       (26.7 )
Income (taxes)
    (8.0 )     (11.1 )     (10.6 )     3.1       (0.5 )
Segment earnings (loss)
  $ 12.2     $ (8.8 )   $ 18.4     $ 21.0     $ (27.2 )

The table below summarizes the significant changes to total revenues, cost of energy, and gross margin:

   
2009/2008 Change
     2008/2007 Change  
   
Total
   
Cost of
   
Gross
   
Total
   
Cost of
   
Gross
 
   
Revenues
   
Energy
   
Margin
   
Revenues
   
Energy
   
Margin
 
   
(In millions)
 
                                     
Rate increase
  $ 4.5     $ -     $ 4.5     $ -     $ -     $ -  
Customer growth/usage
    0.2       -       0.2       4.9       -       4.9  
Hurricane Ike margin impact
    1.6       -       1.6       (1.6 )     -       (1.6 )
PUCT order
    -       -       -       4.2       -       4.2  
Other
    (3.9 )     2.1       (6.0 )     2.4       3.2       (0.8 )
Total increase (decrease)
  $ 2.4     $ 2.1     $ 0.3     $ 9.9     $ 3.2     $ 6.7  

The following table shows TNMP Electric operating revenues by customer class, including intersegment revenues, and average number of customers:

   
Year Ended December 31,
   
Change
 
   
2009
   
2008
   
2007
      2009/2008       2008/2007  
   
(In millions, except customers)
 
                   
Residential
  $ 74.7     $ 71.7     $ 69.5     $ 3.0     $ 2.2  
Commercial
    73.3       72.8       70.1       0.5       2.7  
Industrial
    12.1       13.8       7.9       (1.7 )     5.9  
Other
    32.5       32.0       32.9       0.6       (0.9 )
    $ 192.6     $ 190.3     $ 180.4     $ 2.4     $ 9.9  
Average customers (thousands) (1)
    230.9       229.5       226.2       1.4       3.3  

          (1)  
Under TECA, customers of TNMP Electric in Texas have the ability to choose First Choice or any other REP to provide energy.  The average customers reported above include 86,575, 112,638, and 137,015 customers of TNMP Electric at December 31, 2009, 2008, and 2007 who have chosen First Choice as their REP.  These customers are also included in the First Choice segment.


 
 
A-39

 

The following table shows TNMP Electric GWh sales by customer class:

   
Year Ended December 31,
   
Change
 
   
2009
   
2008
   
2007
      2009/2008       2008/2007  
   
(Gigawatt hours)(1)
 
                   
Residential
    2,582.6       2,533.0       2,520.6       49.6       12.4  
Commercial
    2,216.9       2,206.2       2,196.0       10.7       10.2  
Industrial
    1,983.2       2,094.8       1,927.9       (111.6 )     166.9  
Other
    107.1       107.5       100.6       (0.4 )     6.9  
      6,889.8       6,941.5       6,745.1       (51.7 )     196.4  

          (1)  
The GWh sales reported above include 1,131.9, 1,563.3, and 2,018.1 GWhs for December 31, 2009, 2008, and 2007 used by customers of TNMP Electric who have chosen First Choice as their REP.  These GWhs are also included below in the First Choice segment.

On September 1, 2009, TNMP implemented a $6.8 million base rate increase.  In addition to the base rate increase, TNMP was allowed to increase the cost of debt on its competitive transition charges as well as to recover Hurricane Ike system restoration costs and rate case expenses through additional rate riders.  In 2009, a small increase in average customers and the absence of a major hurricane in 2009 increased revenues and margins.  These increases were partially offset by milder weather and lower customer usage.  Other changes to revenues, cost of energy and margin include transmission charges to and from other transmission and distribution providers, miscellaneous service fees, and revenues associated with TNMP’s CTC.  Other revenues and margin decreased primarily due to a rate decrease on TNMP’s CTC effective January 2009 and lower miscellaneous service fee revenues.  Reductions in lower CTC revenues are offset with lower CTC amortization discussed below.

In 2008, increases in the average customer count and higher per-customer usage increased sales volumes, revenues and gross margin.  In 2008, warmer temperatures in June and July were partially offset by milder temperatures at the beginning and ending of the year along with Hurricane Ike, which struck the Gulf Coast in September 2008 and resulted in a decrease to customer usage.  2007 revenues included a fuel credit to industrial customers, as ordered by the PUCT.  The conclusion of this credit in December of 2007 resulted in increased revenues and gross margin in 2008.  Additionally, the collection of stranded costs incurred by TNMP as part of the deregulation of the Texas energy market increased revenues slightly, as collections are based on customer usage.  These increases are offset by increases in depreciation and amortization related to the amortization of these regulatory assets.

Operating expenses decreased due to an impairment of goodwill in 2008 of $34.5 million.  No impairments were recorded in 2009.  Other than the impairment, increases in operating expenses in 2009 resulted from higher distribution maintenance costs for tree trimming, increased pension and benefit costs, increased allocation of corporate overhead costs, higher property and street rental taxes, and write-off of $0.7 million in Hurricane Ike restoration costs that were not authorized to be recovered in the rate rider discussed above.  These costs were partially offset by the approval and recovery of costs related to achieve savings associated with the Company’s business improvement plan which resulted in a reduction of administrative and general costs of $1.1 million. Operating expenses increased in 2008 due to an impairment of goodwill amounting to $34.5 million as a result of the annual impairment testing.

Depreciation and amortization expense decreased in 2009 due to lower amortization costs associated with TNMP’s CTC, which is partially offset with amortization for Hurricane Ike restoration costs, which are recovered in rates described above, and higher depreciation costs due to increase in transmission plant. Depreciation and amortization expense increased in 2008 due to increased amortizations of regulatory assets for stranded costs, depreciation on higher plant balances, and the absence of amortizations of a regulatory liability in 2007 related to the industrial fuel credit.

In 2009, other income and deductions decreased due to lower revenues associated with contributions in aid of construction and the gain on disposal of certain assets recorded in 2008, which were offset by the recovery of carrying costs on the Hurricane Ike restoration costs of $1.3 million.  In 2008, other income and deductions
 
 
A-40

 
increased due to gains on the sale of non-utility property and higher contributions in aid of construction, partially offset by a decrease in interest income on uncertain income tax positions.

Interest charges increased in 2009 due to higher interest rates on long-term debt issued in March 2009, which repaid short-term borrowings that were at lower interest rates.  The higher cost of the long-term debt is reflected in the rate increase effective September 2009.  Interest charges decreased in 2008 due to a $100 million reduction of long-term debt in the second quarter of 2007, along with the repayment of $148.9 million of long-term debt in the second quarter of 2008 utilizing additional short-term debt with a lower interest cost.

PNM Gas

The table below summarizes the operating results for PNM Gas, which is classified as discontinued operations in the Consolidated Statements of Earnings:

   
Year Ended December 31,
   
Change
 
   
2009
   
2008
   
2007
      2009/2008       2008/2007  
   
(In millions)
 
                   
Total revenues
  $ 65.7     $ 507.0     $ 508.5     $ (441.3 )   $ (1.6 )
Cost of energy
    44.7       346.6       352.8       (301.9 )     (6.2 )
Gross margin
    21.0       160.4       155.7       (139.4 )     4.6  
Operating expenses
    11.3       92.2       97.1       (80.9 )     (4.9 )
Depreciation and amortization
    -       -       21.6       -       (21.6 )
Operating income
    9.7       68.2       37.0       (58.5 )     31.2  
Other income (deductions)
    0.3       2.6       1.1       (2.3 )     1.4  
Net interest charges
    (1.0 )     (13.2 )     (12.2 )     12.2       (1.0 )
Gain on disposal
    98.4       -       -       98.4       -  
Earnings before income taxes
    107.5       57.6       25.9       49.9       31.7  
Income (taxes)
    (36.7 )     (23.0 )     (10.4 )     (13.7 )     (12.6 )
Segment earnings
  $ 70.8     $ 34.6     $ 15.5     $ 36.2     $ 19.1  

PNM completed the sale of PNM Gas on January 30, 2009.  As a result of the sale, the above table reflects operations from the PNM Gas business from January 1 through January 30, 2009, compared to a full year of operations for 2008 and 2007.  The other tables presented below exclude 2009 since it is not meaningful.

The table below summarizes the significant changes to total revenues, cost of energy, and gross margin:

   
2008/2007 Change
 
   
Total
   
Cost of
   
Gross
 
   
Revenues
   
Energy
   
Margin
 
         
(In millions)
       
               
Gas prices
  $ (1.7 )   $ (1.7 )   $ -  
Rate increase
    5.1       -       5.1  
Customer growth/usage
    4.6       3.7       0.9  
Off-system activities
    (8.5 )     (8.2 )     (0.3 )
Other
    (1.1 )     -       (1.1 )
Total increase (decrease)
  $ (1.6 )   $ (6.2 )   $ 4.6  


 
 
A-41

 

The following table shows PNM Gas operating revenues by customer class and average number of customers:

 
Year Ended December 31,
   
Change
 
   
2008
   
2007
      2008/2007  
 
(In millions, except customers)
 
           
Residential
  $ 342.5     $ 338.5     $ 4.0  
Commercial
    103.9       102.3       1.6  
Industrial
    3.9       2.7       1.2  
Transportation(1)
    16.2       15.1       1.1  
Other
    40.5       49.9       (9.5 )
    $ 507.0     $ 508.5     $ (1.6 )
Average customers (thousands)
    496.5       491.6       4.9  

          (1)  
Customer-owned gas.

The following table shows PNM Gas throughput by customer class:

   
Year Ended December 31,
   
Change
 
   
2008
   
2007
      2008/2007  
   
(Thousands of decatherms)
 
             
Residential
    31,981.0       29,468.1       2,512.9  
Commercial
    11,302.1       10,655.6       646.5  
Industrial
    417.3       313.1       104.2  
Transportation(1)
    37,073.2       40,299.3       (3,226.1 )
Other
    3,107.4       5,356.8       (2,249.4 )
      83,881.0       86,092.9       (2,211.9 )

          (1)  
Customer-owned gas.

Differences between operating results of PNM Gas for 2009 and 2008 are primarily due to 2009 only including one month of operations.  Milder weather combined with lower usage-per customer reduced overall sales volumes in 2009 when compared to the same period in the prior year.  A pre-tax gain of $98.4 million was recognized on the sale of the PNM gas business.  In 2009, PNM expensed $5.4 million primarily associated with retained liabilities from discontinued operations in other income and deductions.  Implementation of an approved NMPRC rate increase resulted in an increase to revenues and gross margin in 2008.  In 2008, a slight increase in the average customer count and a 2.0% increase in heating-degree days, both of which were mostly offset by economic conditions, resulted in increased revenues and gross margin.  During 2008, revenues from off-system activities decreased due to a lack of market activity.

PNM Gas purchased natural gas in the open market and sold it at no profit to its sales-service customers. As a result, increases or decreases in gas revenues driven by gas costs did not impact the gross margin or operating income of PNM Gas. Increases or decreases to gross margin caused by changes in sales-service volumes represented margin earned on the delivery of gas to customers based on regulated rates.

In 2008, operating expenses decreased due to reductions in shared service costs resulting from the business improvement plan, along with a reduction for costs incurred in 2007 for self-insurance costs and severance and consulting costs associated with the business improvement plan to reduce costs and improve processes in future years.  Certain corporate items that historically were allocated to the PNM Gas segment cannot be included as discontinued operations and were reassigned to PNM Electric for 2007.  These items include officer compensation, depreciation on common utility and shared-service assets, and postage costs.  The after-tax amount of costs reassigned in 2007 totaled $6.4 million.  Beginning in 2008, these costs were reallocated among all PNMR business segments, other than PNM Gas.


 
 
A-42

 

Due to the sale of the gas business, the assets held for sale were not depreciated in accordance with GAAP.  If PNM Gas were not treated as discontinued operations, depreciation of $1.8 million and $21.5 million would have been recorded in 2009 and 2008.

Changes in other income and deductions are primarily due to interest on PGAC balances.

Interest charges were primarily allocated from PNM and increased in 2008 due to higher borrowings at higher long-term rates.

Altura

The table below summarizes the operating results for Altura:

   
Year Ended
December 31,  2007
 
   
(In millions)
 
       
Total revenues
  $ 65.4  
Cost of energy
    22.1  
Gross margin
    43.3  
Operating expenses
    18.6  
Depreciation and amortization
    7.7  
Operating income
    17.0  
Interest income
    0.1  
Other income (deductions)
    -  
Net interest charges
    (8.5 )
Earnings before income taxes
    8.6  
Income (taxes)
    (3.4 )
Segment earnings
  $ 5.2  

Altura was contributed to Optim Energy on June 1, 2007.  Forced outages in the first quarter of 2007 reduced earnings, in addition to the impairment of the value of developmental rights for the expansion of the plant.  See Note 2.  This decrease was partially offset by reduced interest expense associated with the pay down of outstanding debt.

First Choice

The table below summarizes the operating results for First Choice:
 
 
     
Year Ended December 31,
      Change  
      2009       2008       2007       2009/2008       2008/2007  
                      (In millions)                   
                                         
Total revenues
  $ 528.8     $ 582.2     $ 600.7     $ (53.4 )   $ (18.5 )
Cost of energy
    346.5       564.3       500.8       (217.9 )     63.5  
Gross margin
    182.4       17.9       99.9       164.5       (82.0 )
Operating expenses
    107.4       238.4       57.3       (131.0 )     181.1  
Depreciation and amortization
    1.8       2.4       1.9       (0.6 )     0.5  
   Operating income (loss)
    73.2       (222.8 )     40.8       296.0       (263.6 )
Other income (deductions)
    (0.4 )     1.7       2.1       (2.1 )     (0.4 )
Net interest charges
    (2.8 )     (4.0 )     (0.8 )     1.2       (3.2 )
   Earnings (loss) before income taxes
    70.0       (225.1 )     42.1       295.2       (267.2 )
Income (taxes) benefit
    (25.6 )     47.6       (14.9 )     (73.2 )     62.5  
  Segment earnings (loss)   $ 44.4     $ (177.6   $ 27.2     $ 222.0     $ (204.8 )
 
 


 
 
A-43

 

The following table summarizes the significant changes to total revenues, cost of energy, and gross margin:

   
2009/2008 Change
   
2008/2007 Change
 
   
Total
   
Cost of
   
Gross
   
Total
   
Cost of
   
Gross
 
   
Revenues
   
Energy
   
Margin
   
Revenues
   
Energy
   
Margin
 
               
(In millions)
             
                                     
Retail margins
  $ (47.8 )   $ (156.1 )   $ 108.3     $ 78.0     $ 94.1     $ (16.1 )
Weather
    7.7       6.2       1.5       0.9       1.1       (0.2 )
Customer growth/usage
    (67.4 )     (59.4 )     (8.0 )     (49.5 )     (37.2 )     (12.3 )
Hurricane Ike
    4.2       0.9       3.3       (4.2 )     (0.9 )     (3.3 )
Trading margins
    49.9       -       49.9       (46.3 )     -       (46.3 )
Unrealized economic hedges
    -       (9.5 )     9.5       2.6       6.4       (3.8 )
Total increase (decrease)
  $ (53.4 )   $ (217.9 )   $ 164.5     $ (18.5 )   $ 63.5     $ (82.0 )

The following table shows First Choice operating revenues by customer class, including intersegment revenues, and actual number of customers:

   
Year Ended December 31,
   
Change
 
   
2009
   
2008
   
2007
      2009/2008       2008/2007  
   
(In millions, except customers)
 
                   
Residential
  $ 349.6     $ 407.3     $ 390.3     $ (57.7 )   $ 17.0  
Mass-Market
    25.7       52.7       61.0       (27.0 )     (8.3 )
Mid-Market
    133.1       149.3       141.6       (16.2 )     7.7  
Trading gains (losses)
    -       (49.9 )     (3.6 )     49.9       (46.3 )
Other
    20.4       22.8       11.4       (2.4 )     11.4  
    $ 528.8     $ 582.2     $ 600.7     $ (53.4 )   $ (18.5 )
Actual customers (thousands) (1,2)
    225.0       237.4       258.4       (12.4 )     (21.0 )

          (1)  
See note above in the TNMP Electric segment discussion about the impact of TECA.

          (2)  
Due to the competitive nature of First Choice’s business, actual customer count at December 31 is presented in the table above as a more representative business indicator than the average customers that are shown in the table for TNMP customers.

The following table shows First Choice GWh electric sales by customer class:

   
Year Ended December 31,
   
Change
 
   
2009
   
2008
   
2007
      2009/2008       2008/2007  
   
(Gigawatt hours(1))
 
                   
Residential
    2,441.6       2,547.5       2,796.9       (105.9 )     (249.4 )
Mass-Market
    145.6       278.3       371.8       (132.7 )     (93.5 )
Mid-Market
    1,063.6       1,176.8       1,197.3       (113.2 )     (20.5 )
Other
    9.7       16.3       21.1       (6.6 )     (4.8 )
      3,660.5       4,018.9       4,387.1       (358.4 )     (368.2 )

(1)  See note above in the TNMP Electric segment discussion about the impact of TECA.

During 2009, a decrease in the average sales price, lower MWh sales, and a reduction in the number of customers resulted in decreased operating revenues compared to 2008.   However, significantly lower purchased power costs and favorable weather in 2009 resulted in decreased cost of energy and a net increase in gross margins.  Margins were also higher in 2009 due to the impacts of Hurricane Ike and the LBCS bankruptcy in 2008 that did not recur in 2009.

 
 
A-44

 
During 2008, a decrease in customers and lower MWh sales decreased gross margins compared to 2007.  Average retail sales prices increased although contractual delays in implementing price increases on fixed price term customer renewals, coupled with contractual limitations on monthly price increases for floating rate customers prevented First Choice from recouping the dramatic increase in purchase power costs in 2008.  The impact of Hurricane Ike decreased sales and resulted in an excess purchased power supply that had to be sold in the spot market at prices less than cost, which decreased gross margins.

First Choice entered into a series of speculative forward trades that arbitraged basis differentials among certain ERCOT delivery zones that decreased trading margins by $49.9 million in 2008.  This decrease includes a speculative loss position of $3.3 million related to the LBCS bankruptcy.  The LBCS contracts were subsequently replaced with other counterparty contracts resulting in no material net change in First Choice’s future position.  Because of continued market volatility and concern that the forward basis market would continue to deteriorate, First Choice ended any further speculative trading in 2008.  No significant additional costs were incurred in 2009 and none are expected in the future related to speculative trading.  Gains or losses on unrealized economic hedges represent unrealized fair value estimates related to forward energy contracts and are not necessarily indicative of the amounts that will be realized upon settlement.

The allowance for uncollectible accounts and related bad debt expense is based on collections and write-off experience.  Bad debt expense decreased $10.7 million in 2009 compared to 2008 which is partially attributable to lower operating revenues in 2009.  In late 2008 and early 2009, the customer default rates experienced were significantly above historic levels due to macroeconomic conditions, higher average final bills, and an increase in customer churn.  This resulted in an increase in bad debt expense of $36.7 million in 2008 compared to 2007.  Management of First Choice is addressing the bad debt situation through several initiatives which also contributed to a reduction in bad debt expense in 2009.  These initiatives include efforts to reduce the default rate experienced for customers switching to another REP and increased focus on identifying new customer prospects that are more likely to demonstrate desired payment behavior.  To accomplish these initiatives, First Choice is focusing its marketing efforts on commercial customers and customers with established payment patterns.  In addition, First Choice is increasing the credit score required to become a customer and expanding the circumstances where customers are required to provide advance deposits to obtain service, or both.  In addition, possible regulatory changes are under discussion with the PUCT that would impede a customer's ability to switch REPs until past due balances are paid.

Total operating expenses decreased in 2009 due to 2008 impairments of goodwill of $88.8 million, the First Choice trade name of $42.6 million, and the First Choice customer list of $4.8 million pre-tax (aggregating $119.6 million after-tax) resulting from the annual impairment testing.  No impairments have been recorded in 2009.  See Note 25.  These decreases were partially offset by increased operational costs in 2009, largely attributable to customer acquisition and support expenses. Increased operational costs, which include expenses related to customer acquisition and services, as well as employee labor, pension and benefits, resulted in a decrease to segment earnings when comparing 2008 to 2007.


 
 
A-45

 

Corporate and Other

The table below summarizes the operating results for Corporate and Other:

 
 
      Year Ended December 31,       Change  
      2009        2008        2007       2009/2008       2008/2007  
                      (In millions)                   
                                         
Total revenues
    (41.7 )     (55.9 )     (69.5 )     14.2       13.5  
Cost of energy
    (41.3 )     (55.2 )     (69.5 )     13.9       14.3  
Gross margin
    (0.4 )     (0.7 )     -       0.4       (0.8 )
Operating expenses
    (13.5 )     (0.4 )     6.9       (13.1 )     (7.4 )
Depreciation and amortization
    16.7       17.6       12.5       (0.8 )     5.1  
   Operating income (loss)
    (3.6 )     (17.9 )     (19.4 )     14.3       1.5  
Equity in net earnings (loss) of Optim Energy
    (30.1 )     (29.7 )     7.6       (0.4 )     (37.3 )
Other income (deductions)
    15.2       (7.9 )     (6.4 )     23.1       (1.5 )
Net interest charges
    (22.5 )     (40.8 )     (33.0 )     18.2       (7.7 )
   Earnings (loss) before income taxes
    (41.1 )     (96.3 )     (51.3 )     55.2       (45.0 )
Income (taxes) benefit
    18.5       44.4       37.0       (25.9 )     7.4  
   Segment earnings (loss)
  $ (22.5 )   $ (51.9 )   $ (14.3 )   $ 29.4     $ (37.6 )
                                         

The Corporate and Other Segment includes consolidation eliminations of revenues and cost of energy between business segments, primarily related to TNMP’s sale of transmission to First Choice.

Operating expenses decreased $13.1 million in 2009 compared to 2008 and $7.4 million in 2008 compared to 2007.  These decreases were primarily related to $10.7 million in severances and consulting charges related to the business improvement plan that were incurred in 2008, but not in 2009 and $3.1 million in 2008 compared to 2007.  Other operating expenses also decreased due to reduced consulting expenses and an overall reduction in labor due to the business improvement plan and synergies from the divestiture of PNM Gas. In 2009, there was an offsetting increase in incentive compensation expense.  The overall decreases include an offset to depreciation expense described below.  Operating expenses in 2008 and 2007 also include a credit related to the elimination of operating lease expense paid by PNM to PNMR related to a portion of PVNGS Unit 2, which was purchased in 2007, contributing a favorable variance of $4.8 million in 2008 compared to 2007. Operating expenses includes a $3.1 million loss in 2007 related to the contribution of Altura to Optim Energy.  In addition, 2007 includes $2.8 million related to Optim Energy formation costs.  Favorable variances were also partially offset by higher consulting and legal costs related to the sale of PNM Gas in the amount of $3.4 million in 2008 compared to 2007.

Depreciation expense decreased $0.8 million 2009 compared to 2008 and increased $5.1 million 2008 compared to 2007.  These changes include $0.8 million and $2.9 million increases, respectively, related to increased depreciation on shared services asset base, which is offset in operating expenses in the Corporate and Other segment as a result of allocation of these costs to other business segments.  The remaining variances are primarily due to depreciation on a portion of PVNGS Unit 2, which was purchased by a subsidiary of PNMR in mid 2007 and was leased to PNM through mid 2009, when beneficial ownership was transferred to PNM.

Corporate and Other results include earnings associated with Optim Energy.  Further explanation of equity in Optim Energy is shown below.

Other income and deductions increased in 2009 compared to 2008 primarily due to a $15.0 million fee received upon termination of the CRHC acquisition agreement and a gain of $7.3 million on the repurchase of $157.4 million of PNMR’s 9.25% senior unsecured notes.  In addition, increases in 2008 compared with 2007 include the effects of the elimination of interest income associated with the PVNGS lessor notes in the amount of $2.0 million.

Net interest charges decreased by $18.2 million in 2009 compared to 2008 and increased $7.7 million in 2008 compared to 2007.  The decrease in 2009 compared to 2008 was primarily driven by lower debt borrowing volumes for both long-term and short-term debt.  The increase in 2008 compared to 2007 was primarily driven by the
 
 
A-46

 
issuance of $350.0 million senior unsecured notes and $4.9 million increase in interest on uncertain income tax positions, partially offset by $10.6 million in savings related to short-term borrowing volumes and rates.

Optim Energy

The table below summarizes the operating results for Optim Energy:

   
Year Ended December 31,
     2009/2008      2008/2007  
   
2009
   
2008
   
2007
   
Change
   
Change
 
         
(In millions)
         
                                   
Total operating revenues
  $ 319.5     $ 472.7     $ 224.3     $ (153.2 )   $ 248.4  
Cost of energy
    201.5       366.5       147.3       (165.0 )     219.2  
Gross margin
    118.0       106.2       77.0       11.8       29.2  
Operating expenses
    123.7       117.8       33.5       5.9       84.3  
Depreciation and amortization
    37.2       30.5       15.6       6.7       14.9  
Operating income (loss)
    (42.9 )     (42.1 )     27.9       (0.8 )     (70.0 )
Other income (deductions)
    (0.3 )     0.7       0.6       (1.0 )     0.1  
Net interest charges
    (13.8 )     (19.2 )     (17.9 )     5.4       (1.3 )
Earnings (loss) before income taxes
    (57.0 )     (60.6 )     10.6       3.6       (71.2 )
Income (tax) benefit on margin
    0.2       0.1       (0.4 )     0.1       0.5  
Net earnings (loss)
  $ (56.8 )   $ (60.5 )   $ 10.2     $ 3.7     $ (70.7 )
                                         
50 percent of net earnings (loss)
  $ (28.4 )   $ (30.2 )   $ 5.1     $ 1.8     $ (35.3 )
Plus amortization of basis difference
 in Optim Energy
    (1.7 )     0.5       2.5       (2.2 )     (2.0 )
PNMR Equity in net earnings of
Optim Energy
  $ (30.1 )   $ (29.7 )   $ 7.6     $ (0.4 )   $ (37.3 )

Optim Energy has changed its current strategy and near-term focus due to current adverse market conditions.  Optim Energy is currently focused on utilizing cash flow from operations to reduce debt and optimizing its generation assets as a stand-alone independent power producer.  The goal is to position Optim Energy to optimize its performance in the current market with expectation of being able to take advantage of any economic recovery in the power and gas market over the next several years.

Optim Energy’s management evaluates the results of operations on an on-going earnings before interest, income taxes, depreciation, amortization, and mark-to-market (“On-going EBITDA”) basis. Altura (Twin Oaks), Altura Cogen, and Cedar Bayou 4 generating stations comprise Optim Energy’s core business.  Cedar Bayou 4, which was completed in June 2009, ahead of schedule and slightly under budget, contributed $4.6 million, excluding depreciation, to operating income for the year ended December 31, 2009.  Generation increased from 1,481 GWh for the year ended December 31, 2007 to 5,295 GWh for the year ended December 31, 2008, and 5,755 GWh for the year ended December 31, 2009.  Operating expenses increased as Optim Energy completed the build-out of its organization.  Revenue related to power sales and purchases is included net in operating revenues.  Costs related to fuel purchases and sales are recorded net in cost of sales.

On-going EBITDA excludes purchase accounting amortization included in gross margin related to out of market contracts and emission allowances that were recorded at the acquisition of Altura and Altura Cogen.  Amortization related to out of market contracts decreased total operating revenues $6.7 million in 2009 and increased total operating revenues by $2.2 million and $36.4 million in 2008 and 2007.  Amortization for out of market contracts will continue through the expiration of each contract, which is 2010 for Altura and 2021 for Altura Cogen.  In addition, 2009, 2008, and 2007 cost of energy includes $4.7 million, $11.2 million and $2.3 million of amortization related to emission allowances acquired in the 2007 transactions.  The amortizations for emission allowances are recorded as the allowances are used in plant operations, sold or expire.


 
 
A-47

 
 
    Optim Energy has a multi-year hedging program.  The level of hedging at any given time varies depending on current market conditions and other factors.  Economic hedges that do not qualify for or are not designated as cash flow hedges or normal purchases/sales are derivative instruments that are required to be marked to market.  Due to the extreme market volatility experienced in the first quarter of 2008 in the ERCOT market, Optim Energy made the decision to exit the speculative trading business and close out the speculative trading positions in early 2008.  Optim Energy incurred $2.4 million of speculative trading losses and has since settled all speculative positions.  On-going EBITDA excludes the forward mark-to-market losses of $6.9 million for 2009, gains of $6.3 million for 2008, and losses of $0.3 million for 2007.

Optim Energy has emission allowance inventory from the purchase of Altura Cogen and contribution of Altura, a portion of which falls under the CAIR program.  In July 2008, a federal appeals court ruling by the U.S. Court of Appeals for the District of Columbia Circuit Court invalidated CAIR.  This ruling appeared to remove the need for emissions allowance credits under the CAIR program.  In 2008, Optim Energy recorded a pre-tax write off, included in operating expenses, of $31.7 million for all inventory held under the CAIR program.  Optim Energy values its remaining emission allowances at the lower of cost or market.  In December 2009, Optim Energy reduced the value of its held for sale NOx emission allowances by $51.6 million because of significant price declines in an illiquid market.  At December 31, 2009, Optim Energy has $4.9 million remaining held for sale allowances in inventory. As of December 31, 2009, Optim Energy also has $54.6 million remaining in inventory for emission allowances that are held to meet the emission requirements of its generating facilities.

The assets of Altura transferred to Optim Energy included the development rights for a possible 600-megawatt expansion of the Twin Oaks plant, which was classified as an intangible asset.  In the year ended December 31, 2008, Optim Energy made a strategic decision not to pursue the Twin Oaks expansion and wrote off the development rights as an impairment of intangible assets amounting to $21.8 million. In addition, Optim Energy expensed $1.2 million in the year ended December 31, 2008, of deferred administrative and general costs related to this project.

LCC is Optim Energy’s counterparty in several agreements for power and steam sales.  In addition, LCC leases Optim Energy the land for the Altura Cogen facility and provides other services, including water, to that facility.  On January 6, 2009, LCC filed for bankruptcy protection under Chapter 11 of the US Bankruptcy Code.  The pre-petition amount due from LCC is immaterial and was fully reserved as of December 31, 2008.  LCC has continued to perform under the existing contracts since the filing.

The contribution of Altura created a basis difference between PNMR’s recorded investment in Optim Energy and 50 percent of Optim Energy’s equity.  The PNMR net earnings impact does not equal 50 percent of the Optim Energy amortization because of this basis difference.  While the portion of the basis difference related to contract amortization will only continue through 2010, other basis differences, including a difference related to emission allowances, will continue to exist through the life of the Altura plant.  The basis difference adjustment reflected above relates primarily to contract amortization with insignificant offsets related to the other minor basis difference components.


 
 
A-48

 

LIQUIDITY AND CAPITAL RESOURCES

Statements of Cash Flows

The information concerning PNMR’s cash flows is summarized as follows:

       
   
Year Ended December 31,
   
Change
 
   
2009
   
2008
   
2007
      2009/2008       2008/2007  
   
(In millions)
 
                                   
Net cash flows from:
   Operating activities
  $ 87.7     $ 88.6     $ 223.1     $ (0.9 )   $ (134.5 )
   Investing activities
    379.7       (320.7 )     (73.5 )     700.4       (247.2 )
   Financing activities
    (593.4 )     355.0       (255.2 )     (948.4 )     610.2  
Net change in cash and cash equivalents
  $ (126.0 )   $ 122.9     $ (105.6 )   $ (248.9 )   $ 228.5  

The changes in PNMR’s cash flows from operating activities relate primarily to increased margins and reduced collateral requirements at First Choice in 2009. PNMR also received a $9.1 million after-tax settlement in 2009 due to the termination of the CRHC acquisition agreement. Increases were partially offset by the payment of taxes related to earnings and the sale of PNM Gas in 2009, as well as only one month of operations from the PNM Gas segment. In 2008, lower earnings primarily due to results of operations and increased collateral requirements at First Choice decreased cash flows from operating activities. Higher interest payments in 2008 compared to 2009 and 2007 also contributed to the changes.

The changes in cash flows from investing activities relate primarily to the proceeds from the sale of PNM Gas in 2009 as well as reduced utility plant additions at PNM, including for the PNM Gas segment. The contribution of Altura resulting in net cash distributions to PNMR from Optim Energy in 2007 (see Note 22) and higher expenditures for utility plant additions in 2007, including the purchase of assets underlying a portion of PVNGS leased by PNM (see Note 2), expansion of Afton, environmental upgrades at SJGS, and higher purchases of nuclear fuel for PVNGS also contributed to the changes.

The changes in cash flows from financing activities relate primarily to the 2009 use of the proceeds from the sale of PNM Gas to retire short-term borrowings at PNM and PNMR. In 2008, the issuance of common stock by PNMR in connection with the settlement of equity purchase obligations of the holders of publicly held equity-linked units and the issuance of long-term debt by PNMR and PNM was partially offset by the redemption of long-term debt by PNM.  TNMP issued new long-term debt in 2009 using the proceeds to retire both long-term and short-term debt.  In 2008, the redemption of long-term debt by TNMP was offset by new short-term borrowings. Cash used for the redemption of long-term debt by TNMP in 2007 was partially offset by proceeds from the issuance of PCRBs by PNM.

Financing Activities

See Note 6, for additional information concerning the Company’s financing activities.

    On January 5, 2009, PNMR commenced a tender offer whereby it offered to repurchase up to $150.0 million of its 9.25% senior unsecured notes due 2015.  Prior to expiration of the offer, $157.5 million of notes were tendered to PNMR for purchase.  Under the applicable rules for this type of arrangement, PNMR was able to purchase $157.0 million of notes at 93% of face value.  On February 5, 2009, PNMR repurchased and retired these notes for $146.0 million plus accrued interest. On February 26, 2009, PNMR purchased an additional $0.4 million of the 9.25% senior unsecured notes at 93% of face value in a private transaction.

On March 23, 2009, TNMP issued $265.5 million aggregate principal amount of 9.50% First Mortgage Bonds, due 2019, Series 2009A (the “Series 2009A Bonds”) at a price equal to 97.643% of their face value.  The
 
 
A-49

 
bonds bear interest at the rate of 9.50% per annum of their face value. TNMP may redeem some or all of the Series 2009A Bonds at any time at a redemption price that reflects a make-whole provision, plus accrued interest.  The Series 2009A Bonds are secured by a first mortgage on substantially all of TNMP’s property.

On March 25, 2009, TNMP entered into a $50.0 million loan agreement with Union Bank, N. A. (the “2009 Term Loan Agreement”).   TNMP borrowed $50.0 million under this agreement on March 30, 2009.  Borrowings under the 2009 Term Loan Agreement must be repaid by March 25, 2014 and are secured by $50.0 million aggregate principal amount of TNMP first mortgage bonds (the “Series 2009B Bonds”).  Through hedging arrangements, TNMP has established fixed interest rates for the 2009 Term Loan Agreement.

TNMP used the proceeds received from the Series 2009A Bonds and the 2009 Term Loan Agreement to repay the $100.0 million borrowed under the TNMP Bridge Facility and the $150.0 million outstanding under the TNMP Facility.  The remaining proceeds, after offering expenses, were used to reduce intercompany borrowings from PNMR.

On April 30, 2009, TNMP entered into a new $75.0 million revolving credit facility (the “TNMP Revolving Credit Facility”) and the existing TNMP Facility was terminated.  Borrowings under the TNMP Revolving Credit Facility are secured by $75.0 million aggregate principal amount of TNMP first mortgage bonds (the “Series 2009C Bonds”).  The TNMP Revolving Credit Facility will expire in April 2011.
 
    On May 23, 2003, PNM issued $36.0 million of 4.00% PCRB senior unsecured notes, which had a scheduled maturity in 2038, but were subject to mandatory repurchase and remarketing on July 1, 2009.  PNM repurchased these notes for $36.0 million on July 1, 2009 utilizing available cash balances and borrowings under the PNM Facility.  PNM held these bonds (without legally canceling them) until December 1, 2009, on which date they were remarketed.  The remarketed bonds bear interest at 6.25% and mature on January 1, 2038.

On February 10, 2010, PNM filed an application with the NMPRC requesting approvals and authorizations to refund up to $403.8 million of callable PCRBs issued by the City of Farmington, New Mexico and Maricopa County, Arizona Pollution Control Corporation to replace the current bonds with new tax-exempt pollution control revenue bonds.  The current bonds have been used to support a portion of the cost of certain pollution control systems, facilities and related improvements at SJGS and PVNGS.   The new tax-exempt bonds will be collateralized by PNM senior unsecured notes, similar to the current bonds.   Timing of any refunding and issuing new bonds will depend on approval of the NMPRC, as well as market and other conditions.

PNMR offers new shares of PNMR common stock through the PNMR Direct Plan.  On July 15, 2009, PNMR began purchasing shares of its common stock on the open market rather than issuing additional shares to satisfy subscriptions under the PNMR Direct Plan.  PNMR had offered new shares of its common stock through an equity distribution agreement, which was terminated in July 2009.

    As discussed in Note 2, on January 12, 2008, PNM reached a definitive agreement to sell its natural gas operations, which comprise the PNM Gas segment.  The sale was completed on January 30, 2009.  PNM used  the proceeds of approximately $640 million, including a preliminary adjustment for the level of working capital at closing, to retire short-term debt and pay a dividend to PNMR of $220.0 million.  The remaining funds were used to pay income taxes on the gain from the sale.

Capital Requirements

Total capital requirements consist of construction expenditures and cash dividend requirements for both common and preferred stock.  The Series A convertible preferred stock is entitled to receive dividends equivalent to any dividends paid on PNMR common stock as if the preferred stock had been converted into common stock.  The main focus of PNMR’s current construction program is upgrading generation resources, including renewable energy resources to be owned by PNM, upgrading and expanding the electric transmission and distribution systems, and purchasing nuclear fuel.  Projections for total capital requirements for 2010 are $331.3 million, including construction expenditures of $285.1 million.  Total capital requirements for the years 2010-2014 are projected to be $1,770.4 million, including construction expenditures of $1,509.8 million.  See Commitments and Contractual
 
 
A-50

 
Obligations below.  These amounts do not include forecasted construction expenditures of Optim Energy.  These estimates are under continuing review and subject to on-going adjustment, as well as to Board review and approval.

    During the year ended December 31, 2009, PNMR utilized cash generated from operations and cash on hand, as well as its liquidity arrangements and proceeds from the sale of PNM Gas, in addition to the financing activities described in Note 6, to meet its capital requirements and construction expenditures.

    TNMP’s $50.0 million in borrowings under the 2009 Term Loan Agreement, which is secured by the Series 2009B Bonds, are due in 2014.  PNMR and its subsidiaries have no other long-term debt that comes due prior to 2015, except for $9.3 million that is due in installments through 2013.

    As discussed in Note 22, Optim Energy co-developed a generating unit, which was completed in June 2009.  Optim Energy’s share of the construction costs was $209.6 million, which was financed through Optim Energy’s credit facility and operating cash flows.  If Optim Energy undertakes additional projects, which require funds that would exceed the capacity of its current credit facility and Optim Energy is unable to obtain additional financing capabilities, PNMR and ECJV may be asked to provide additional funding, but such funding would be at the option of PNMR and ECJV and no assurance can be given that such funding will be available to Optim Energy.  PNMR is unable to predict if additional funding will be requested or, if requested, the amount or timing of additional funds that would be provided to Optim Energy.

Liquidity

    PNMR’s liquidity arrangements include the PNMR Facility and the PNM Facility both of which primarily expire in 2012 and the TNMP Revolving Credit Facility, which expires in April 2011.  These facilities provide short-term borrowing capacity and also allow letters of credit to be issued, which reduce the available capacity under the facilities.  Commercial paper programs previously available under the PNMR and PNM facilities were terminated on July 2, 2009.  These credit facilities will need to be renegotiated or replaced prior to their expirations in order to provide sufficient liquidity to finance operations and construction expenditures.  The availability of such credit facilities, including their amounts for borrowing thereunder and their terms and conditions, will depend on the credit markets at that time, as well as the Company’s credit ratings and operating results.  Both PNMR and PNM also have lines of credit with local financial institutions.  As of February 15, 2010, the Company had short-term debt outstanding of $269.0 million.

    Although accessing the capital markets at the current time could be difficult as well as costly, the Company currently believes that its internal cash generation, existing credit arrangements, and access to public and private capital markets will provide sufficient resources to meet the Company’s capital requirements.  To cover the difference in the amounts and timing of cash generation and cash requirements, the Company intends to use short-term borrowings under its current and future liquidity arrangements.  However, if market difficulties experienced during the recession resurge or worsen, the Company may not be able to access the capital markets or renew credit facilities when they expire.  In such event, the Company would seek to improve cash flows by reducing capital expenditures and PNM would consider seeking authorization for the issuance of first mortgage bonds in order to improve access to the capital markets, as well as any other alternatives that may remedy the situation at that time.

In addition to cash received from the sale of PNM Gas and its internal cash generation, the Company anticipates that it will be necessary to obtain additional long-term financing in the form of debt refinancing, new debt issuances, and/or new equity in order to fund its capital requirements during the 2010-2014 period.

The Company’s ability, if required, to access the credit and capital markets at a reasonable cost and to provide for other capital needs is largely dependent upon its ability to earn a fair return on equity, its results of operations, its credit ratings, its ability to obtain required regulatory approvals and conditions in the financial markets.

On April 18, 2008, S&P lowered the credit ratings for PNMR, PNM, and TNMP and placed them on negative outlook for possible additional downgrades.  On May 6, 2008, S&P again lowered the credit ratings for PNMR, PNM, and TNMP and the outlook was changed to stable for all entities.  On April 25, 2008, Moody’s lowered the credit ratings for PNMR and PNM and continued a review for possible downgrade, while reaffirming TNMP’s
 
 
A-51

 
ratings with a negative outlook.  On May 23, 2008, Moody’s changed the outlook for PNMR and PNM from rating under review for possible downgrade to negative outlook.  On December 9, 2008, S&P changed the outlook for PNMR, PNM, and TNMP from stable to negative.  The ratings actions have increased borrowing costs for PNMR and PNM and could increase future borrowing costs for PNMR, PNM, and TNMP. In addition, certain contractual arrangements required that following downgrades the Company obtain commercial insurance for risks that were previously self-insured.  On October 2, 2008, Fitch Ratings announced credit ratings for PNMR, PNM, and TNMP.  On December 9, 2009, S&P revised its outlook to stable from negative on PNMR, PNM and TNMP.  As of February 15, 2010, ratings on the Company’s debt securities were as follows:

 
PNMR
 
PNM
 
TNMP
           
S&P
         
Senior secured
*
 
BB+
 
BBB-
Senior unsecured
BB-
 
BB+
 
*
Preferred stock
*
 
B
 
*
Moody’s
         
Senior secured
*
 
*
 
Baa2
Senior unsecured
Ba2
 
Baa3
 
*
Preferred stock
*
 
Ba2
 
*
Fitch Ratings
         
Senior secured
*
 
BBB-
 
BBB
Senior unsecured
BB
 
BB+
 
*
Preferred stock
*
 
BB-
 
*

*  Not applicable

Investors are cautioned that a security rating is not a recommendation to buy, sell or hold securities, that it is subject to revision or withdrawal at any time by the assigning rating organization, and that each rating should be evaluated independently of any other rating.

A summary of liquidity arrangements as of February 15, 2010 is as follows:

   
PNMR
   
PNM
   
TNMP
   
PNMR
 
   
Separate
   
Separate
   
Separate
   
Consolidated
 
         
(In millions)
       
                         
Financing Capacity:
                       
Revolving credit facility
  $ 600.0     $ 400.0     $ 75.0     $ 1,075.0  
Local lines of credit
    5.0       5.0       -       10.0  
Total financing capacity
  $ 605.0     $ 405.0     $ 75.0     $ 1,085.0  
                                 
Amounts outstanding as of February 15, 2010:
                               
Revolving credit facility
  $ 107.0     $ 162.0     $ -     $ 269.0  
Local lines of credit
    -       -       -       -  
Total short-term debt outstanding
    107.0       162.0       -       269.0  
                                 
Letters of credit
    67.6       13.3       1.5       82.4  
                                 
Total short term-debt and letters of credit
  $ 174.6     $ 175.3     $ 1.5     $ 351.4  
                                 
Remaining availability as of February 15, 2010
  $ 430.4     $ 229.7     $ 73.5     $ 733.6  
                                 
Invested cash as of February 15, 2010
  $ 16.4     $ 2.6     $ -     $ 19.0  


 
 
A-52

 

The above table excludes intercompany debt.  The remaining availability under the revolving credit facilities varies based on a number of factors, including the timing of collections of accounts receivables and payments for construction and operating expenditures.   LBB was a lender under the PNMR Facility and the PNM Facility.  LBH, the parent of LBB, has filed for bankruptcy protection.  Subsequent to the bankruptcy filing by LBH, LBB declined to fund a borrowing request under the PNMR Facility amounting to $5.3 million. The above availability includes $29.9 million that represents the unfunded portion of the PNMR Facility attributable to LBB.  PNMR is discussing with the participants in the PNMR Facility amending the PNMR Facility to remove LBB, which would reduce the total capacity under the PNMR facility to $568.0 million.  In addition the PNMR Facility and the PNM Facility will reduce by $26.0 million and $14.0 million in 2010 and an additional $25.0 million and $18.0 million in 2011 according to their terms.  The Company does not believe amending the PNMR Facility to remove LBB, the scheduled reduction in the facilities, or the LBH bankruptcy will have a significant impact on PNMR’s and PNM’s liquidity.

For offerings of debt securities registered with the SEC, PNMR has an effective shelf registration statement expiring in April 2011.  This shelf registration statement has unlimited availability and can be amended to include additional securities, subject to certain restrictions and limitations.  PNMR can offer new shares of PNMR common stock through the PNM Resources Direct Plan under a separate SEC shelf registration statement that expires in August 2012.  In April 2008, PNM filed a new shelf registration statement for the issuance of up to $750.0 million of senior unsecured notes that expires in April 2011.  As of February 15, 2010, PNM had $600.0 million of remaining unissued securities registered under this and a prior shelf registration statement.

As discussed above and in Note 6, disruption in the credit markets has had a significant adverse impact on a number of financial institutions and several of the financial institutions that the Company deals with have been impacted. However, at this point in time, the Company’s liquidity has not been materially impacted and management does not expect that it will be materially impacted in the near-future.

Information concerning PNMR’s common stock, dividends, and recent financing activities is set forth above as well as in Note 5 and Note 6.

Off-Balance Sheet Arrangements

PNMR’s off-balance sheet arrangements include PNM’s operating lease obligations for PVNGS Units 1 and 2, the EIP transmission line and Delta, a 132 MW gas-fired generating plant.

In 1985 and 1986, PNM consummated sale and leaseback transactions for its interest in PVNGS Units 1 and 2. The original purpose of the sale-leaseback financing was to lower revenue requirements and to levelize the ratemaking impact of PVNGS being placed in-service.  The lease payments reflected lower capital costs as the equity investors were able to capitalize the investment with greater leverage than PNM and because the sale transferred tax benefits that PNM could not fully utilize.  Under traditional ratemaking, the capital costs of ownership of a major rate base addition, such as a nuclear plant, are front-end loaded.  The revenue requirements are high in the initial years and decline over the life of the plant as depreciation occurs.  On the other hand, the lease payments are level over the lease term.  The leases, which expire in 2015 and 2016, contain options to renew the leases at a fixed price or to purchase the property for fair market value at the end of the lease terms.  PNM is exploring its alternatives.

 
Additionally, in 1996, PNM entered into an operating lease agreement for the rights to all the output of the Delta generating plant through June 2020.  The gas turbine generating unit is operated by Delta, which is a variable interest entity.  See Note 9.  The plant is mainly used as a peaking plant to meet peak load requirements.

These arrangements help ensure PNM the availability of lower-cost generation needed to serve customers.

For reasons similar to the above, PNM built the EIP Transmission Line and sold it in sale and leaseback transactions in 1985.  The EIP line is 216 miles long and runs from near Albuquerque to the Texas-New Mexico border.  It is a 345 kilovolt line with a capacity of 200 MW and is one of two interconnections in New Mexico linking the Western regional electrical grid with the West Texas grid.  PNM currently owns 60% and operates 40% of the EIP line under the terms of a lease agreement extending into 2015 with fixed-rate and fair market value renewal options and a fair market value purchase option.
 
 
A-53

 

    In addition to operating costs, PNM is required to make payments under these leases.  The future lease payments shown below for the PVNGS and EIP leases have been reduced by amounts that will be returned to PNM through its ownership in related lessor notes.

               
Delta
       
   
PVNGS
         
Person
       
   
Units 1&2
   
EIP
   
PPA
   
Total
 
   
(In thousands)
 
2010
  $ 12,742     $ 113     $ 5,956     $ 18,811  
2011
    13,435       54       5,956       19,445  
2012
    25,078       498       5,956       31,532  
2013
    27,427       2,845       5,956       36,228  
2014
    32,236       2,845       5,956       41,037  
Thereafter
    20,352       1,422       33,253       55,027  
Total
  $ 131,270     $ 7,777     $ 63,033     $ 202,080  

See Sources of Power, Investments in Note 1, and Note 7 for additional information.

Commitments and Contractual Obligations

The following table sets forth PNMR’s long-term contractual obligations as of December 31, 2009. See also Note 7 for further details about the Company’s significant leases, including those for PNM and TNMP:

   
Payments Due
 
                     
2015 and
       
Contractual Obligations
 
2010
      2011 -2012       2013 - 2014    
Thereafter
   
Total
 
   
(In thousands)
 
                                   
Long-term debt (a)
  $ 2,125     $ 4,639     $ 52,530     $ 1,513,962     $ 1,573,256  
Interest on long-term debt (b)
    116,236       232,471       232,471       606,592       1,187,770  
Operating leases (c)
    27,797       68,945       95,010       56,661       248,413  
PPAs (d)
    22,199       30,065       16,620       20,296       89,180  
Coal contracts (e)
    55,322       115,607       122,195       181,332       474,456  
Outsourcing
    24,543       39,484       27,328       -       91,355  
Pension and retiree medical (f)
    22,699       133,998       134,998       -       291,695  
Construction expenditures (g)
    285,100       741,200       483,500       -       1,509,800  
Other
    15,974       8,265       -       -       24,239  
                                         
Total (h)
  $ 571,995     $ 1,374,674     $ 1,164,652     $ 2,378,843     $ 5,490,164  

(a)  Represents total long-term debt excluding unamortized discount of $5.9 million.
(b)  Represents interest payments during the period.
(c)  The operating lease amounts are net of amounts to be returned to PNM as payments on its investments in related lessor notes. See Investments in Note 1 and Note 7.
(d)  PPA amounts do not include amounts for Valencia that PNM is obligated to pay since Valencia is consolidated by PNM in accordance with GAAP.  See Note 9.
(e)  Represents only certain minimum payments that may be required under the coal contracts if no deliveries are made.
(f)  The Company only forecasts funding for its pension and retiree medical plan for the next five years.
(g)  Represents forecasted capital expenditures, under which substantial commitments have been made.  The Company only forecasts capital expenditures for the next five years.
(h)  PNMR is unable to reasonably estimate the timing of liability and interest payments for uncertain income tax positions in individual years due to uncertainties in the timing of the effective settlement of tax positions.  Therefore, PNMR’s liability of $22.6 million and interest payable of $1.1 million are not reflected in this table.
 
 
A-54

 
Contingent Provisions of Certain Obligations

PNMR, PNM and TNMP have a number of debt obligations and other contractual commitments that contain contingent provisions.  Some of these, if triggered, could affect the liquidity of the Company.  PNMR, PNM or TNMP could be required to provide security, immediately pay outstanding obligations or be prevented from drawing on unused capacity under certain credit agreements if the contingent requirements were to be triggered.  The most significant consequences resulting from these contingent requirements are detailed in the discussion below.

The PNMR Facility, the PNM Facility, and the TNMP Revolving Credit Facility contain “ratings triggers,” for pricing purposes only.  If PNMR, PNM, or TNMP is downgraded or upgraded by the ratings agencies, the result would be an increase or decrease in interest cost, respectively.  In addition, these facilities contain contingent requirements that require the maintenance of debt-to-capital ratios, including for PNMR and PNM the present value of payments under the PVNGS and EIP leases as debt, of less than 65%.  If such ratio were to exceed 65%, the entity could be required to repay all borrowings under its facility, be prevented from drawing on the unused capacity under the facility, and be required to provide security for all outstanding letters of credit issued under the facility.

If a contingent requirement were to be triggered under the PNM Facility resulting in an acceleration of the outstanding loans under the PNM Facility, a cross-default provision in the PVNGS leases could occur if the accelerated amount is not paid.  If a cross-default provision is triggered, the lessors have the ability to accelerate their rights under the leases, including acceleration of all future lease payments.

PNM's standard purchase agreement for the procurement of gas for its fuel needs contains a contingent requirement that could require PNM to provide security for its gas purchase obligations if the seller were to reasonably believe that PNM was unable to fulfill its payment obligations under the agreement.

The master agreement for the sale of electricity in the WSPP contains a contingent requirement that requires PNM to provide security if its debt falls below investment grade rating.  Additionally, both PNM and FCP utilize standard derivative contracts to financially hedge and trade energy. These agreements contain contingent requirements that require PNM or PNMR to provide security if its debt falls below investment grade rating. The Company has provided the required security under these agreements.  The WSPP agreement also contains a contingent requirement, commonly called a material adverse change provision, which could require PNM to provide security if a material adverse change in its financial condition or operations were to occur.

No conditions have occurred that would result in any of the above contingent provisions being implemented.

 
 
A-55

 

Capital Structure

The capitalization tables below include the current maturities of long-term debt, but do not include short-term debt and do not include operating lease obligations as debt.

   
December 31,
 
PNMR
 
2009
   
2008
 
             
PNMR common equity
    49.6 %     49.3 %
Convertible preferred stock
    3.0 %     3.0 %
Preferred stock of subsidiary
    0.3 %     0.3 %
Long-term debt
    47.1 %     47.4 %
Total capitalization
    100.0 %     100.0 %
                 
PNM
               
                 
PNM common equity
    51.9 %     55.7 %
Preferred stock
    0.5 %     0.5 %
Long-term debt
    47.6 %     43.8 %
Total capitalization
    100.0 %     100.0 %
                 
TNMP
               
                 
Common equity
    59.3 %     71.6 %
Long-term debt
    40.7 %     28.4 %
Total capitalization
    100.0 %     100.0 %

OTHER ISSUES FACING THE COMPANY

Climate Change Issues

In April 2007, the U.S. Supreme Court held that the EPA has the authority to regulate GHG under the Clean Air Act.  This decision, coupled with an increased focus in Congress on legislation to address climate change, has heightened the importance of this issue for the energy industry.   Although there continues to be debate over the details and best design for state and federal programs, increased state and federal legislative and regulatory activities calling for regulation of GHG indicate that climate change protection legislation and regulation are likely in the future.  

In July 2008, the EPA published the Greenhouse Gas Advanced Notice of Proposed Rulemaking.   The notice identified, but did not choose among, options for GHG regulation and requested comments on the options presented.  Absent Congressional action, in due course the Company expects the EPA to adopt regulations relating to GHG.

In December 2009, the EPA released its final endangerment finding stating that the atmospheric concentrations of six key greenhouse gases (carbon dioxide, methane, nitrous oxide, hydrofluorocarbons, perfluorocarbons, and sulfur hexafluoride) endanger the public health and welfare of current and future generations.  The finding does not by itself impose any requirements on producers of GHG, but the finding does set the groundwork for the EPA to regulate GHG from new and existing stationary sources such as power plants and for new motor vehicles.  The EPA proposed several rules regulating GHG in anticipation of the final endangerment finding.   In September 2009, the EPA proposed GHG motor vehicle standards and expects to finalize those standards in March 2010.  Promulgation of the motor vehicle standards will trigger the applicability of Prevention of Significant Deterioration (“PSD”) and operating permit requirements for stationary sources that emit GHG.   With respect to PSD and operating permit requirements, the EPA proposed a rule that focuses on large facilities emitting
 
 
A-56

 
over 25,000 metric tons of GHG per year.  These facilities would be required to obtain air permits that demonstrate they are using the best available control technology to minimize GHG.  Each of the Company’s fossil-fueled electric generating plants emit over 25,000 metric tons of GHG per year.  At this time, the Company cannot predict what the impact of the proposed rule will be on the operation of our fossil-fueled power plants, although it could require the Company to incur capital costs and increased operating costs in order to fulfill the applicable standard.

In addition, several legislative initiatives are under consideration in Congress that would regulate GHG. These initiatives range from general limitations on GHG to the imposition of a so-called “cap and trade” system to the imposition of a tariff on GHG.  It is unclear whether or when legislation will be passed, although the Obama administration and several leading members of Congress continue to express their intent to pass legislation.

    In June 2009, the United States House of Representatives passed H.R. 2454, the American Clean Energy and Security Act of 2009.  This bill, commonly referred to as the Waxman-Markey Bill, if ultimately passed into legislation, would establish an economy-wide program, with cap and trade as its cornerstone, regulating GHG.  The bill defines specific emissions reductions requirements and timelines, provides for the allocation of free allowances to electric utilities in the early years of the program to help mitigate cost impacts to ratepayers and allows for compliance flexibility through cost control mechanisms including the establishment of an offset program that will further help mitigate costs to consumers.

    On November 5, 2009, the Senate Environment and Public Works Committee reported the Clean Energy Jobs and American Power Act (S. 1733) out of committee.  While the bill is broadly similar to the climate change framework in the Waxman-Markey Bill, it includes a more aggressive GHG reduction target for 2020.  It appears unlikely that S. 1733 has the bipartisan support required to pass the Senate.  On December 10, 2009, Senator Kerry (D, MA), an original cosponsor of S. 1733, Senator Graham (R, SC) and Senator Lieberman (I, CN) announced a framework for climate change legislation that may be the basis for a bipartisan support of a future bill.

    The Company has assessed, and continues to assess, the impacts of potential climate change legislation or regulation on its business.  This assessment is preliminary, and changes in the legislative or regulatory process could impact the assessment significantly.  The Company’s assessment includes assumptions regarding the specific greenhouse gas emission limits, the timing of implementation of these limits, the level of emissions allowances allocated and the level that must be purchased, the development of technologies for renewable energy and to reduce emissions, the cost of emissions allowances, the degree to which offsets may be used for compliance, and provisions for cost containment.  Moreover, the assessment assumes various market reactions such as with respect to the price of coal and gas and regional plant economics.  These assumptions, at best, are preliminary and speculative.  However, based upon these assumptions, the enactment of climate change legislation would likely, among other things, result in significant compliance costs, including significant capital expenditures, and could jeopardize the economic viability of certain generating facilities.  For example, see the discussion of Four Corners in Note 16 under the caption The Clean Air Act – Regional Haze.  In turn, these consequences would lead to increased costs to customers and could affect results of operations, cash flows, and financial condition if the incurred costs are not fully recovered through regulated rates.  Higher rates could also contribute to reduced demand for electricity.  The Company’s assessment process is ongoing but too preliminary and speculative at this time for the meaningful prediction of financial impact.
 
Pursuant to New Mexico law, each utility must submit an integrated resource plan to the NMPRC every three years to evaluate renewable energy, energy efficiency, load management, distributed generation and conventional supply-side resources on a consistent and comparable basis.  The integrated resource plan is required to take into consideration risk and uncertainty of fuel supply, price volatility and costs of anticipated environmental regulations when evaluating resources options to meet supply needs of PNM’s customers.  The NMPRC issued an order in June 2007, requiring that New Mexico utilities factor a standardized cost of carbon emissions into their integrated resource plans using prices ranging between $8 and $40 per metric ton of CO2 emitted and escalating these costs by 2.5% per year.  Under the NMPRC order, each utility must analyze these standardized prices as projected operating costs in 2010 and thereafter.  Reflecting the developing nature of this issue, the NMPRC order states that these prices may be changed in the future to account for additional information or changed circumstances.   PNM is required, however, to use these prices for purposes of its integrated resource plan, and the prices may not reflect the costs that it ultimately will incur.  PNM’s integrated resource plan filed with the NMPRC in September 2008 showed that incorporation of the NMPRC required carbon emissions costs did not significantly change the dispatch of existing facilities or the resource decisions regarding future facilities over the next 20 years.  Much higher GHG costs than assumed in the NMPRC analysis are necessary to impact the dispatch
 
 
A-57

 
of existing resources or future resource decisions. The primary consequence of GHG costs was an increase to generation portfolio costs.  The public involvement phase of PNM’s next integrated resource plan will begin by July 2010.

Seven western states, including New Mexico and three Canadian provinces have entered into an accord, called the Western Regional Climate Action Initiative (the “WCI”), to reduce GHG from automobiles and certain industries, including utilities.   The WCI released design recommendations for elements of a regional cap and trade program in September 2008, and has created several subcommittees to develop detailed implementation recommendations.  The subcommittees are slated to complete their work in 2010.  Under the WCI recommendations, GHG from the electricity sector and fossil fuel consumption of the industrial and commercial sectors will be capped at then current levels and subject to regulation starting in 2012.  Over time, producers will be required to reduce their GHG.   Implementation of the design elements for GHG reductions will fall to each state and province.  In New Mexico, the Company believes this will require new legislation and rulemaking.  The Company will not be able to fully assess the implications of the recommendations until implementing legislation and rules have been enacted.  In the event federal cap and trade legislation is adopted, it may replace state and regional initiatives.

In December 2008, New Energy Economy (“NEE”), a non-profit environmental advocacy organization, petitioned the New Mexico Environmental Improvement Board (“EIB”) to amend existing regulations and adopt new regulations requiring a cap on GHG, including a statewide GHG limit of 25% below 1990 levels by 2020.  The proposal provides for an absolute cap without the ability to purchase allowances from other entities to cover GHG.  The EIB ordered legal briefs to be filed on the issue of the EIB’s authority to regulate GHG.  After review of the briefs and a hearing in April 2009, the EIB decided it does have authority to regulate GHG.  During the hearing, NEE agreed to amend its proposal to be a cap and trade program.  At the EIB meeting held in July 2009, the NMED outlined its proposed schedule for the adoption and implementation of regulations necessary to implement the proposals under the WCI. PNM and other interested parties filed a motion to temporarily stay further action on the NEE petition pending introduction of the NMED’s WCI regulatory proposals so that the NMED proposal could be considered together with the NEE proposal.  In August 2009, the EIB denied the motion for the temporary stay.  The EIB will commence a hearing on the NEE proposal beginning in June 2010 and a public comment session to begin on March 1, 2010.  NEE and the NMED sought to bifurcate the proceeding to consider the “science of climate change” at an initial hearing and proposals to implement regulation to reduce GHG at a subsequent hearing.  The EIB took the issue of bifurcation under advisement and decided against bifurcating the hearing.  On January 13, 2010, PNM along with a diverse group of other New Mexico businesses, legislators, and agriculture interests filed a lawsuit in state court against the EIB challenging its authority to regulate GHG as proposed in the NEE petition.   The suit also requests a preliminary and permanent injunction enjoining the EIB from conducting further proceedings on the NEE petition.  We cannot predict the outcome of this proceeding.
 
In February 2009, a bill was introduced in the New Mexico legislature proposing to require the implementation by EIB of a cap and trade system designed to reduce GHG. This legislation died in committee during the session.  The New Mexico House of Representatives did pass a memorial, which requests the New Mexico Legislative Council to direct the appropriate committee to study the WCI final design recommendations as well as federal proposals relating to reducing GHG.  The memorial is a study of impacts and not a regulation. The memorial further states that the committee is requested to report its findings and recommendations to the New Mexico legislature by December 2010.

In January 2010, a similar bill was introduced in the New Mexico House of Representatives that would have allowed EIB to adopt rules for implementing particular portions of WCI, including rules of early reduction allowances and offset allowances and mandatory reporting of GHG emission for persons importing electricity or heating or transportation fuels. The bill was tabled in committee where it died.

Approximately 82.6% of PNM’s owned and leased generating capacity consists of coal or gas-fired generation that produces GHG.  All of Optim Energy’s owned generation produces GHG.  Based on our current forecasts, we do not expect our output of GHG to increase significantly in the near-term.  Many factors affect the amount of GHG, including plant performance.  For example, if PVNGS experienced prolonged outages, it may require PNM to utilize other power supply resources such as gas-fired generation, which could increase GHG.  
 
 
A-58

 
Because of our dependence on fossil-fueled generation, any legislation that imposes a limit or cost on GHG will impact the cost at which we produce electricity.  While PNM expects to be entitled to recover that cost through rates, the timing and outcome of proceedings for cost recovery is uncertain.  In addition, to the extent that we recover any additional costs through rates, our customers may reduce their demand, relocate facilities to other areas with lower energy costs or take other actions that ultimately will adversely impact us.

Given the geographic location of our facilities and customers, we generally have not been exposed to the extreme weather events and other physical impacts commonly attributed to climate change, with the possible exception of drought conditions periodically, and we generally do not expect physical changes to be of material consequence to us in the near-term. Drought conditions in northwestern New Mexico could impact the availability of water for cooling coal plants.  Water shortage sharing agreements have been in place since 2003, although no shortage has been declared due to sufficient snow pack in the San Juan Basin.  PNM also has a supplemental water contract in place with the Jicarilla Tribe to help address any water shortages from primary sources. The contract expires December 31, 2016. 

In 2006, the Company became a founding member of the United States Climate Action Partnership (“USCAP”), a coalition currently consisting of 35 businesses and national environmental organizations calling on the federal government to enact national legislation to reduce GHG at the earliest practicable date.   USCAP released A Call To Action, a set of principles and recommendations outlining a policy framework for federal climate protection legislation in January 2007, and released its Blueprint for Legislative Action to the U.S. Congress and the Obama Administration in December 2008.   As a member of USCAP, it is the Company’s position that a mandatory, economy-wide, market-driven approach that includes a cap and trade program, combined with other complementary state and federal policies, is the most cost effective and environmentally efficient means of addressing GHG reductions.  The Company intends to continue working with USCAP, government agencies, and Congress to advocate for federal action to address this challenging environmental issue that is closely linked with the U.S. economy, energy supply, and energy security. The basic framework of the part of the Waxman-Markey Bill described above that addresses global warming is consistent with the framework proposed by USCAP in its Blueprint for Legislative Action.

In 2008, PNMR’s interests in generating plants, through PNM and Optim Energy, emitted approximately 7.9 million metric tons of carbon dioxide, the vast majority of its GHG.  By comparison, the total GHG in the United States in 2007, the latest year for which the EPA has compiled this data, were approximately 7.2 billion metric tons, of which approximately 6.1 billion metric tons were carbon dioxide.  Electricity generation accounted for approximately 2.4 billion metric tons of the carbon dioxide emissions.

PNM has several programs underway to mitigate its GHG, and thereby to reduce its climate change risk.  See Note 17.  On January 25, 2010, PNM filed with the NMPRC its revised renewable procurement plan that, if approved, will result in up to 80 MWs of new solar generation on PNM’s system.  In 2008, PNM filed requests for approval to implement additional electric energy efficiency and load management programs with the NMPRC, which approved the programs in May 2009.  Over the next 19 years, PNM projects the expanded energy efficiency and load management programs will provide the equivalent of approximately 15,000 GWh of electricity, which will avoid about 8.5 million metric tons of GHG. These estimates are subject to change given that it is difficult to estimate avoidance accurately because of the many variables that impact it, including changes in demand for electricity.

The Board is updated by management and regularly considers the issues around climate change, our GHG and potential financial consequences that might result from climate change and the possible regulation of GHG.  In particular, management periodically reports to the Board on all of the matters discussed in this section.  In December 2008, the Board established a new stand-alone committee, the Public Policy and Sustainability Committee. This committee monitors Company practices and procedures to assess the sustainability impacts of our operations and products on the environment.  This committee also has responsibility to review the Company’s environmental management systems, monitor the implementation of the Company’s corporate environmental policy, monitor the promotion of energy efficiency, and the use of renewable energy resources.  The committee will report to the Board on a periodic basis regarding the Company’s activities and initiatives in these areas.

 
A-59

 
The regulation of GHG is expected to have a material impact on the utility industry both in terms of increased costs associated with fossil fuels and increased opportunities associated with fuels other than fossil fuels, but it is premature to attempt to quantify the possible costs and other implications of these impacts on the Company.

Other Matters

See Notes 16, 17 and 18 for a discussion of commitments and contingencies, rate and regulatory matters and environmental issues facing the Company.  See Note 21 for a discussion of accounting pronouncements that have been issued, but are not yet effective and have not been adopted by the Company.

CRITICAL ACCOUNTING POLICIES AND ESTIMATES
 
    The preparation of financial statements in accordance with GAAP requires management to apply accounting policies and to make estimates and judgments that best provide the framework to report the results of operations and financial position for PNMR, PNM and TNMP.   As a result, there exists the likelihood that materially different amounts would be reported under different conditions or using different assumptions. Management has identified the following accounting policies that it deems critical to the portrayal of the financial condition and results of operations and that involve significant subjectivity.  The following discussion provides information on the processes utilized by Management in making judgments and assumptions as they apply to its critical accounting policies.

Unbilled Revenues

    As discussed in Note 1, the Company records unbilled revenues representing management's assessment of the estimated amount customers will be billed for services rendered between the meter-reading dates in a particular month and the end of that month. Management estimates unbilled revenues based on sales recorded in the billing system, taking into account weather impacts. The method is consistent with the approach to normalization employed for rate case billing determinants and the load forecast. To the extent the estimated amount differs from the amount subsequently billed, revenues will be affected. Unbilled revenues are separately reported on the Consolidated Balance Sheets of PNMR, PNM and TNMP.

Regulatory Accounting

    The Company is subject to the provisions of GAAP for rate-regulated enterprises, as discussed in Note 1. Accordingly, the Company has recorded assets and liabilities resulting from the effects of the ratemaking process, which would not be recorded under GAAP for non-regulated entities.  The Company's continued ability to meet these provisions may be affected in the future by competitive forces and restructuring in the electric industry. In the event these provisions no longer apply to all or a separable portion of the Company's operations, the related regulatory assets and liabilities would be written off unless an appropriate regulatory recovery mechanism is provided.

    The Company evaluates whether or not recovery of regulatory assets through future rates is probable and makes various assumptions in those analyses. The expectations of future recovery are generally based on orders issued by regulatory commissions or historical experience, as well as discussions with applicable regulatory authorities.  If future recovery of these costs ceases to be probable, the utility would be required to record a charge in current period earnings for the portion of the costs that were not recoverable.

Impairments

    Tangible long-lived assets and amortizable intangible assets are evaluated for impairment when events and circumstances indicate that the assets might be impaired in accordance with GAAP.  These potential impairment indicators include management's assessment of fluctuating market conditions as a result of industry deregulation; planned and scheduled customer purchase commitments; future market penetration; fluctuating market prices resulting from factors including changing fuel costs and other economic conditions; weather patterns; and other market trends. The amount of impairment recognized, if any, is the difference between the fair value of the asset and the carrying value of the asset and would reduce both the asset and current period earnings.  Variations in the

 
 
A-60

 

assessment of potential impairment or in the assumptions used to calculate an impairment could result in different outcomes, which could lead to significant effects on the consolidated financial statements.

    Goodwill and non-amortizable other intangible assets are evaluated for impairment at least annually, or more frequently if events and circumstances indicate that the goodwill and intangible assets might be impaired. Note 25 contains information on the impairment testing performed by the Company on goodwill and intangible assets.  No impairments were indicated in the Company’s annual goodwill testing, which was performed as of April 1, 2009.  Since the annual evaluation, there have been no indications that the fair values of the reporting units with recorded goodwill have decreased below the carrying values.  The annual testing was based on certain critical estimates and assumptions.  Changes in the estimates or the use of different assumptions could affect the determination of fair value and the conclusion of impairment for each reporting unit.

    Application of the impairment test requires judgment, including the identification of reporting units, assignment of assets and liabilities to reporting units and determination of the fair value of each reporting unit.    The fair value of each reporting unit is estimated using a discounted cash flow methodology.  This analysis requires significant judgments, including estimation of future cash flows, which is dependent on internal forecasts, estimation of long-term growth rates for the business and determination of appropriate weighted average cost of capital (“WACC”) for each reporting unit.

    In determining the fair value of each reporting unit, the WACC is a significant factor.  The Company considers many factors in selecting a WACC, including the market view of risk for each individual reporting unit, the appropriate capital structure, and the borrowing rate appropriate for each reporting unit.  The Company considers available market-based information and may consult with third parties to help us to determine the WACC.  The selection of a WACC is subjective and modifications to this rate could significantly increase or decrease the fair value of a reporting unit.

    The other primary factor impacting the determination of the fair value of each reporting unit is the estimation of future cash flows.  The Company consider budgets, long-term forecasts, historical trends and expected growth rates in order to estimate future cash flows.  Any forecast contains a degree of uncertainty and modifications to these cash flows could significantly increase or decrease the fair value of a reporting unit.  For the reporting units subject to rate-regulation, a fair recovery of and return on costs prudently incurred to serve customers is assumed.  Should the regulators not allow recovery of certain costs or not allow these reporting units to earn a fair rate of return on invested capital, the fair value of the reporting units could decrease. For the unregulated reporting unit, assumptions regarding customer usage, pricing, retention and payment behavior, in addition to fluctuations in the cost of energy, significantly impact estimates of future cash flows.  Negative impacts of changes in these assumptions would cause the fair value of this reporting unit to decrease.

    The Company believes that the WACCs and cash flow projections utilized in the 2009 testing appropriately reflect the fair value of each reporting unit.  Since any cash flow projection contains uncertainty, the Company adjusted the WACCs used to reflect that uncertainty.  The Company does not believe that there are indications of goodwill impairment in any of its reporting units, but this analysis is highly subjective.  Summarized below are the results of the 2009 impairment testing.  The fair value of each reporting unit exceeded its carrying value by less than ten percent as of April 1, 2009.  Due to the subjectivity and sensitivities of the assumptions and estimates underlying the impairment analysis, there can be no assurance that future analyses, which will be based on the appropriate assumptions and estimates at that time, will not result in impairments.

Reporting Unit
Goodwill
(in millions)
Percent by which Fair Value
Exceeded Carrying Value in
Annual Test
PNM
$   51.6
9.6%
TNMP Electric
$ 226.7
4.2%
First Choice
$   43.0
1.5%


 
 
A-61

 

Decommissioning Costs

    Accounting for decommissioning costs for nuclear and fossil-fuel generation involves significant estimates related to costs to be incurred many years in the future after plant closure. Changes in these estimates could significantly impact PNMR's and PNM's financial position, results of operations and cash flows. PNM owns and leases nuclear and fossil-fuel generation facilities. In accordance with GAAP, PNM is only required to recognize and measure decommissioning liabilities for tangible long-lived assets for which a legal obligation exists. Nuclear decommissioning costs are based on site-specific estimates of the costs for removing all radioactive and other structures at PVNGS and are dependent upon numerous assumptions. PVNGS Unit 3 is excluded from PNM's retail rates while PVNGS Units 1 and 2 are included. PNM collects a provision for ultimate decommissioning of PVNGS Units 1 and 2 and its fossil-fuel generation facilities in its rates and recognizes a corresponding expense and liability for these amounts. PNM believes that it will continue to be able to collect in rates for its legal asset retirement obligations for nuclear generation activities included in the ratemaking process.  Asset retirement obligations and nuclear decommissioning costs are discussed in Note 15.

In connection with both the SJGS coal agreement and the Four Corners fuel agreement, the owners are required to reimburse the mining companies for the cost of contemporaneous reclamation as well as the costs for final reclamation of the coal mines.  The reclamation costs are based on site-specific studies that estimate the costs to be incurred in the future and are dependent upon numerous assumptions. PNM considers the contemporaneous reclamation costs part of the cost of its delivered coal costs.  See Note 16 for discussion of the final reclamation costs.

Derivatives

    The Company follows the provisions set forth in GAAP to account for derivatives. These provisions establish accounting and reporting standards requiring derivative instruments to be recorded in the balance sheet as either an asset or liability measured at their fair value. GAAP also requires that changes in the derivatives' fair value be recognized currently in earnings unless specific hedge accounting or normal purchase and sale criteria are met. Special accounting for qualifying hedges requires that a company must formally document, designate, and assess the effectiveness of transactions that receive hedge accounting. These rules allow derivative gains and losses for fair-value hedges to offset related results on the hedged item in the statement of earnings.  GAAP provides that the effective portion of the gain or loss on a derivative instrument designated and qualifying as a cash flow hedging instrument be reported as a component of accumulated other comprehensive income and be reclassified into earnings in the period during which the hedged forecasted transaction affects earnings. The results of hedge ineffectiveness and the portion of the change in fair value of a derivative that an entity has chosen to exclude from hedge effectiveness are required to be presented in current earnings.

Pension and Other Postretirement Benefits

The Company maintains qualified defined benefit pension plans, postretirement benefit plans providing medical and dental benefits, and executive retirement programs. The net periodic benefit income (cost) and the calculation of the projected benefit obligations are both recognized in the Company’s financial statements and depend on investment performance, the level of contributions made to the plans, and employee demographics. They both require the use of a number of actuarial assumptions and estimates.  The most critical of the actuarial assumptions are the expected long-term rate of return, the discount rate, and projected health care cost trend rates.  The Company reviews and evaluates its actuarial assumptions annually and adjusts them as necessary.  See Note 12.

Accounting for Contingencies

    The financial results of the Company may be affected by judgments and estimates related to loss contingencies.  A significant contingency the Company accounts for is the loss associated with uncollectible trade accounts receivable.  The determination of bad debt expense is based on factors such as historical write-off experience, aging of accounts receivable balances, regulatory rulings and general economic conditions and customer behavior.


 
 
A-62

 

Contingencies related to litigation and claims, as well as environmental and regulatory matters, also require the use of significant judgment and estimation.  The Company attempts to take into account all known factors when determining the proper accrual, however the actual outcomes can vary from the amount accrued.

Income Taxes
 
The Company’s income tax expense and related balance sheet amounts involve significant judgment and use of estimates.  Amount of deferred income tax assets and liabilities, as well as current and noncurrent accruals, involve judgment and estimates related to timing and probability of the recognition of income and deductions by taxing authorities.  In addition, some temporary differences are accorded flow-through treatment by the Company’s regulators and impact the Company’s effective tax rate.  In assessing the likelihood of the realization of deferred tax assets, management considers the estimated amount and character of future taxable income.  Actual income taxes could vary from estimated amounts due to the future impacts of various items, including changes in income tax laws, the Company’s forecasted financial condition and results of operations in future periods, as well as the final review from taxing authorities.

Market Risk

See Item 7A. Quantitative and Qualitative Disclosure About Market Risk for discussion regarding the Company's accounting policies and sensitivity analysis for the Company's financial instruments and derivative energy and other derivative contracts.

MD&A FOR PNM

RESULTS OF OPERATIONS

    PNM’s continuing operations are presented in the PNM Electric segment, which is identical to the segment presented above in Results of Operations for PNMR.  PNM’s discontinued operations are presented in the PNM Gas segment, which is identical to the total earnings from discontinued operations, net of income taxes, shown on the Consolidated Statements of Earnings for both PNM and PNMR.  See Note 23.

MD&A FOR TNMP

RESULTS OF OPERATIONS

TNMP operates in one reportable segment, TNMP Electric, as presented above in Results of Operations for PNMR.


 
 
A-63

 

ITEM 7A.      QUANTITATIVE AND QUALITATIVE DISCLOSURE ABOUT MARKET RISK

PNMR controls the scope of its various forms of risk through a comprehensive set of policies and procedures and oversight by senior level management and the Board.  The Board’s Finance Committee sets the risk limit parameters.  The RMC, comprised of corporate and business segment officers, oversees all of the risk management activities, which include commodity risk, credit risk, interest rate risk, and business risk.  The RMC has oversight for the ongoing evaluation of the adequacy of the risk control organization and policies.  PNMR has risk control organizations, which are assigned responsibility for establishing and enforcing the policies, procedures and limits and evaluating the risks inherent in proposed transactions, on an enterprise-wide basis.

The RMC’s responsibilities specifically include: establishment of policies regarding risk exposure levels and activities in each of the business segments; authority to approve the types of derivatives entered into; authority to establish a general policy regarding counterparty exposure and limits; authorization and delegation of transaction limits; review and approval of controls and procedures for derivative activities; review and approval of models and assumptions used to calculate mark-to-market and market risk exposure; authority to approve and open brokerage and counterparty accounts for derivatives; review of hedging and risk activities; the extent and type of reporting to be performed for monitoring of limits and positions; and quarterly reporting to the Audit and Finance Committees on these activities.  The RMC also proposes risk limits, such as VaR and GEaR, to the Finance Committee for its approval.
 
It is the responsibility of each business segment to create its own control procedures and policies within the parameters established by the Corporate Financial Risk Management Policy, approved by the Finance Committee.  The RMC reviews and approves these policies, which are created with the assistance of the Risk Management Department and the Vice President and Treasurer.  Each business segment’s policies address the following controls:  authorized instruments and markets; authorized personnel; policies on segregation of duties; policies on mark-to-market accounting; responsibilities for deal capture; confirmation responsibilities; responsibilities for reporting results; statement on the role of derivative transactions; and limits on individual transaction size (nominal value).

To the extent an open position exists, fluctuating commodity prices can impact financial results and financial position, either favorably or unfavorably.  As a result, the Company cannot predict with certainty the impact that its risk management decisions may have on its businesses, operating results or financial position.

Information concerning accounting for derivatives and the risks associated with commodity contracts is set forth in Note 8.  Note 8 also contains a summary of the fair values of mark-to-market energy related derivative contracts included in the Consolidated Balance Sheets.


 
 
A-64

 

The following table details the changes in the net asset or liability balance sheet position for mark-to-market energy transactions other than cash flow hedges:


   
Trading
   
Economic
Hedges
   
Total
 
Year Ended December 31, 2009
 
(In thousands)
 
PNMR
     
Sources of fair value gain (loss):
                 
Net fair value at beginning of year
  $ 2,556     $ (5,422 )   $ (2,866 )
Amount realized on contracts delivered during period
    (1,414 )     23,249       21,835  
Changes in fair value
    97       (12,362 )     (12,265 )
Net change recorded as mark-to-market
    (1,317 )     10,887       9,570  
Unearned/prepaid option premiums
    -       (563 )     (563 )
Transfer of de-designated cash flow hedges
    -       (2,685 )     (2,685 )
             Net fair value at end of year
  $ 1,239     $ 2,217     $ 3,456  
       
PNM
     
Sources of fair value gain (loss):
                       
Net fair value at beginning of year
  $ 261     $ (3,300 )   $ (3,039 )
Amount realized on contracts delivered during period
    (345 )     11,743       11,398  
Changes in fair value
    84       (6,995 )     (6,911 )
Net change recorded as mark-to-market
    (261 )     4,748       4,487  
Transfer of de-designated cash flow hedges
    -       (17 )     (17 )
             Net fair value at end of year
  $ -     $ 1,431     $ 1,431  

Year Ended December 31, 2008
     
PNMR
     
Sources of fair value gain (loss):
                 
Net fair value at beginning of year
  $ (1,577 )   $ (13,136 )   $ (14,713 )
Adoption of amendment to GAAP regarding fair value measurement
    -       17,253       17,253  
Adjusted beginning fair value
    (1,577 )     4,117       2,540  
Amount realized on contracts delivered during period
    44,540       976       45,516  
Changes in fair value
    (41,701 )     (10,895 )     (52,596 )
Net change recorded as mark-to-market
    2,839       (9,919 )     (7,080 )
Unearned/prepaid option premiums
    1,294       380       1,674  
             Net fair value at end of year
  $ 2,556     $ (5,422 )   $ (2,866 )
       
PNM
     
Sources of fair value gain (loss):
                       
Net fair value at beginning of year
  $ 2     $ (13,663 )   $ (13,661 )
Adoption of amendment to GAAP regarding fair value measurement
    -       17,253       17,253  
Adjusted beginning fair value
    2       3,590       3,592  
Amount realized on contracts delivered during period
    (4,281 )     (1,044 )     (5,325 )
Changes in fair value
    4,540       (5,552 )     (1,012 )
Net change recorded as mark-to-market
    259       (6,596 )     (6,337 )
Unearned/prepaid option premiums
    -       (294 )     (294 )
             Net fair value at end of year
  $ 261     $ (3,300 )   $ (3,039 )


 
 
A-65

 

The following table provides the maturity of the net assets (liabilities) other than cash flow hedges, giving an indication of when these mark-to-market amounts will settle and generate (use) cash.  The following values were determined using broker quotes and option models:

Fair Value of Mark-to-Market Instruments at December 31, 2009

   
Less than
                   
   
1 year
   
1-3 Years
   
4+ Years
   
Total
 
PNMR
       
(In thousands)
       
Trading
  $ 1,239     $ -     $ -     $ 1,239  
Economic hedges
    4,353       (2,155 )     19       2,217  
Total
  $ 5,592     $ (2,155 )   $ 19     $ 3,456  
PNM
                     
Economic hedges
  $ 1,987     $ (575 )   $ 19     $ 1,431  
Total
  $ 1,987     $ (575 )   $ 19     $ 1,431  

The fair value of PNMR’s and PNM’s commodity derivative instruments designated as cash flow hedging instruments decreased $17.8 million and $20.2 million for year ended December 31, 2009 and increased $38.2 million and $40.8 million for the year ended December 31, 2008.

Risk Management Activities

PNM measures the market risk of its long-term contracts and wholesale activities using a VaR calculation to measure price movements.  The VaR calculation reports the possible market loss for the respective transactions.  This calculation is based on the transaction’s fair market value on the reporting date.  Accordingly, the VaR calculation is not a measure of the potential accounting mark-to-market loss.  PNM utilizes the Monte Carlo VaR simulation model.  The Monte Carlo model utilizes a random generated simulation based on historical volatility to generate portfolio values.  The quantitative risk information, however, is limited by the parameters established in creating the model.  The instruments being evaluated may trigger a potential loss in excess of calculated amounts if changes in commodity prices exceed the confidence level of the model used.  The VaR methodology employs the following critical parameters:  historical volatility estimates, market values of all contractual commitments, appropriate market-oriented holding periods, and seasonally adjusted and cross-commodity correlation estimates.  The VaR calculation considers PNM’s forward positions, if any.  PNM uses a holding period of three days as the estimate of the length of time that will be needed to liquidate the positions.  The volatility and the correlation estimates measure the impact of adverse price movements both at an individual position level as well as at the total portfolio level.  The two-tailed confidence level established is 95%.  For example, if VaR is calculated at $10.0 million, it is estimated that in 950 out of 1,000 market simulations the pre-tax gain or loss in liquidating the portfolio would not exceed $10.0 million in the three days that it would take to liquidate the portfolio.

PNM measures VaR for all transactions that are not directly asset-related and have economic risk.  For the year ended December 31, 2009, the average, high, and low VaR amounts for these transactions were less than $0.1 million.  The VaR amount for these transactions at December 31, 2009 was zero.  For the year ended December 31, 2008, the average VaR amount for these transactions was $0.3 million with high and low VaR amounts for the period of $1.4 million and zero.  The total VaR amount for these transactions at December 31, 2008 was less than $0.1 million.

First Choice measures the market risk of its retail sales commitments and supply sourcing activities using a GEaR calculation to monitor potential risk exposures related to taking contracts to settlement and a VaR calculation to measure short-term market price impacts.

Because of its obligation to serve customers, First Choice must take certain contracts to settlement.  Accordingly, a measure that evaluates the settlement of First Choice’s positions against earnings provides management with a useful tool to manage its portfolio.  First Choice uses a hold-to-maturity at risk for 12 months calculation for its GEaR measurement.  The calculation utilizes the same Monte Carlo simulation approach described above at a 95% confidence level and includes the retail load and supply portfolios. Management believes
 
 
A-66

 
the GEaR results are a reasonable approximation of the potential variability of earnings against forecasted earnings.  The quantitative risk information, however, is limited by the parameters established in creating the model.  The instruments being evaluated may trigger a potential loss in excess of calculated amounts if changes in commodity prices exceed the confidence level of the model used.  The GEaR calculation considers First Choice’s forward position for the next twelve months and holds each position to settlement.  The volatility and the correlation estimates measure the impact of adverse price movements both at an individual position level as well as at the total portfolio level.  For example, if GEaR is calculated at $10.0 million, it is estimated that in 950 out of 1,000 market scenarios calculated by the model the losses against the Company’s forecasted earnings over the next twelve months would not exceed $10.0 million.

For the year ended December 31, 2009, the average GEaR amount was $5.0 million, with high and low GEaR amounts for the period of $11.4 million and $1.7 million.  The total GEaR amount at December 31, 2009 was $1.9 million.  For the year ended December 31, 2008, the average GEaR amount for these transactions was $16.1 million, with high and low GEaR amounts for the period of $44.3 million and $6.0 million.  The total GEaR amount for these transactions at December 31, 2008 was $10.2 million.

First Choice utilizes a short-term VaR measure to manage its market risk.  The VaR limit is based on the same total portfolio approach as the GEaR measure; however, the VaR measure is intended to capture the effects of changes in market prices over a 10-day holding period.  This holding period is considered appropriate given the nature of First Choice’s supply portfolio and the constraints faced by First Choice in the ERCOT market.  The calculation utilizes the same Monte Carlo simulation approach described above at a 95% confidence level.  The VaR amount for these transactions was $0.7 million at December 31, 2009.  For the year ended December 31, 2009, the high, low and average mark-to-market VaR amounts were $2.0 million, $0.2 million and $0.8 million.  The VaR amount for these transactions was $1.0 million at December 31, 2008.  For the year ended December 31, 2008, the high, low and average mark-to-market VaR amounts were $12.1 million, $0.9 million and $3.8 million.

The Company's risk measures are regularly monitored by the Company's RMC.  The RMC has put in place procedures to ensure that increases in risk measures that exceed the prescribed limits are reviewed and, if deemed necessary, acted upon to reduce exposures.  In the first quarter of 2008, First Choice experienced pre-tax speculative trading losses of $47.1 million. These transactions triggered exceedences of the GEaR limit and the 10-day VaR limit, which contributed to the decision to exit the basis transactions and speculative trading.  There were no such exceedences in 2009.

The VaR and GEaR limits represent an estimate of the potential gains or losses that could be recognized on the Company’s portfolios, subject to market risk, given current volatility in the market, and are not necessarily indicative of actual results that may occur, since actual future gains and losses will differ from those estimated.  Actual gains and losses may differ due to actual fluctuations in market prices, operating exposures, and the timing thereof, as well as changes to the underlying portfolios during the year.

Credit Risk

The Company conducts counterparty risk analysis across business segments and uses a credit management process to assess the financial conditions of counterparties.  Credit exposure is regularly monitored by the RMC. The RMC has put procedures in place to ensure that increases in credit risk that exceed the prescribed limits are reviewed and, if deemed necessary, acted upon to reduce exposures.


 
 
A-67

 

The following table provides information related to credit exposure as of December 31, 2009.  The table further delineates that exposure by the credit worthiness (credit rating) of the counterparties and provides guidance as to the concentration of credit risk to individual counterparties.

Schedule of Credit Risk Exposure
December 31, 2009

               
Net
 
         
Number
   
Exposure
 
   
(b)
   
of
   
of
 
   
Credit
   
Counter
   
Counter-
 
   
Risk
   
-parties
   
parties
 
Rating (a)
 
Exposure
   
>10%
   
>10%
 
   
(Dollars in thousands)
 
PNMR
                 
External ratings:
                 
Investment grade
  $ 48,367       3     $ 13,778  
Non-investment grade
    4,982               -  
Internal ratings:
                       
Investment grade
    67               -  
Non-investment grade
    460               -  
Total
  $ 53,876             $ 13,778  
                         
PNM
                       
External ratings:
                       
     Investment grade
  $ 44,235       3     $ 13,778  
     Non-investment grade
    -               -  
Internal ratings:
                       
     Investment grade
    67               -  
     Non-investment grade
    460               -  
          Total
  $ 44,762             $ 13,778  

      (a)        The Rating included in “Investment Grade” is for counterparties with a minimum S&P rating of BBB- or Moody's rating of Baa3.  If the counterparty has provided a guarantee by a higher rated entity (e.g., its parent), determination is based on the rating of its guarantor.  The category “Internal Ratings - Investment Grade” includes those counterparties that are internally rated as investment grade in accordance with the guidelines established in the Company’s credit policy.
 
           (b)       The Credit Risk Exposure is the gross credit exposure, including long-term contracts, forward sales and short-term sales. The exposure captures the amounts from receivables/payables for realized transactions, delivered and unbilled revenues, and mark-to-market gains/losses (pursuant to contract terms).  Exposures are offset according to legally enforceable netting arrangements but are not reduced by available credit collateral.  Credit collateral includes advance payments, cash deposits, letters of credit, and parental guarantees received from counterparties.  Amounts are presented before the application of such credit collateral instruments.  At December 31, 2009, PNMR and PNM held advance payments of $27.8 million and PNMR held credit collateral of $3.4 million to offset its credit exposure.  PNM held no credit collateral.


 
 
A-68

 

The following table provides an indication of the maturity of credit risk by credit ratings of the counterparties.

Maturity of Credit Risk Exposure
December 31, 2009

               
Greater
   
Total
 
   
Less than
         
than
   
Net
 
Rating
 
2 Years
   
2-5 Years
   
5 Years
   
Exposure
 
         
(In thousands)
       
PNMR
                       
External ratings:
                       
Investment grade
  $ 48,083     $ 145     $ 139     $ 48,367  
Non-investment grade
    4,982       -       -       4,982  
Internal ratings:
                               
Investment grade
    67       -       -       67  
Non-investment grade
    460       -       -       460  
Total
  $ 53,592     $ 145     $ 139     $ 53,876  
                                 
PNM
                               
External ratings:
                               
     Investment grade
  $ 44,096     $ -     $ 139     $ 44,235  
     Non-investment grade
    -       -       -       -  
Internal ratings:
                               
     Investment grade
    67       -       -       67  
     Non-investment grade
    460       -       -       460  
          Total
  $ 44,623     $ -     $ 139     $ 44,762  

The Company provides for losses due to market and credit risk.  Credit risk for PNMR's and PNM’s largest counterparty as of December 31, 2009 and December 31, 2008 was $7.3 million and $52.3 million.

Interest Rate Risk

PNMR has long-term debt which subjects it to the risk of loss associated with movements in market interest rates.  The majority of PNMR’s long-term debt is fixed-rate debt and does not expose PNMR’s earnings to a major risk of loss due to adverse changes in market interest rates.  However, the fair value of all long-term debt instruments would increase by 2.97%, if interest rates were to decline by 50 basis points from their levels at December 31, 2009.  In general, an increase in fair value would impact earnings and cash flows to the extent not recoverable in rates if all or a portion of debt instruments were acquired in the open market prior to their maturity.  As described in Note 6, TNMP has long-term debt of $50.0 million that bears interest at a variable rate.  However, TNMP has also entered into a hedging arrangement that effectively results in this debt bearing interest at a fixed rate, thereby eliminating interest rate risk.  At February 15, 2010, PNMR has $269.0 million of consolidated short-term debt outstanding under its revolving credit facilities and local lines of credit, which allow for a maximum aggregate borrowing capacity of $1,085.0 million.  These facilities bear interest at variable rates, which averaged 1.12% of February 15, 2010 borrowings, and the Company is exposed to interest rate risk to the extent of future increases in variable interest rates.

The securities held by PNM in the NDT and in trusts for pension and other post-employment benefits had an estimated fair value of $556.7 million at December 31, 2009, of which 29.1% were fixed-rate debt securities that subject PNM to risk of loss of fair value with movements in market interest rates.  If interest rates were to increase by 50 basis points from their levels at December 31, 2009, the decrease in the fair value of the fixed-rate securities would be 4.4%, or $7.2 million.  The securities held by TNMP in trusts for pension and other post-employment benefits had an estimated fair value of $64.9 million at December 31, 2009, of which 24.3% were fixed-rate debt securities that subject TNMP to risk of loss of fair value with movements in market interest rates.  If interest rates were to increase by 50 basis points from their levels at December 31, 2009, the decrease in the fair value of the fixed-rate securities would be 5.8%, or $0.9 million.
 
 
A-69

 
PNM and TNMP do not directly recover or return through rates any losses or gains on the securities in the trusts for nuclear decommissioning or pension and other post-employment benefits.  However, the overall performance of these trusts does enter into the periodic determinations of expense and funding levels, which are factored into the rate making process to the extent applicable to regulated operations.  PNM and TNMP are at risk for shortfalls in funding of obligations due to investment losses, including those from the equity market and alternatives investment risks discussed below to the extent not ultimately recovered through rates charged to customers.

Equity Market Risk

The NDT and trusts established for PNM’s pension and post-employment benefits hold certain equity securities at December 31, 2009.  These equity securities expose PNM to losses in fair value should the market values of the underlying securities decline.  Equity securities comprised 57.0% of the securities held by the various PNM trusts as of December 31, 2009.  PNM does not recover or earn a return through rates on any losses or gains on these equity securities.  The trusts established for TNMP’s pension and post-employment benefits hold certain equity securities.  These equity securities expose TNMP to losses in fair value should the market values of the underlying securities decline.  Equity securities comprised 56.3% of the securities held by the TNMP trusts as of December 31, 2009.  There was a significant decline in the general price levels of marketable equity securities in late 2008 and in early 2009. The impacts of these declines were considered in the funding and expense valuations performed for 2009, which resulted in reduced amounts of income related to the pension plans being recorded in 2009 and will require increased levels of funding beginning in 2010.  See Note 12.

Alternatives Investment Risk

The Company has a target of investing 20% of its pension assets in the alternatives asset class, which amounted to 21.4% as of December 31, 2009.  This includes real estate, private equity, and hedge funds. These investments are limited partner structures that are multi-manager multi-strategy funds. This investment approach gives broad diversification and minimizes risk compared to a direct investment in any one component of the funds. The general partner oversees the selection and monitoring of the underlying managers. The Company’s Corporate Investment Committee, assisted by its investment consultant, monitors the performance of the funds and general partner’s investment process. There is risk associated with these funds due to the nature of the strategies and techniques and the use of investments that do not have readily determinable fair value.  The valuation of the alternative asset class has also been impacted by the significant decline in the general price levels of marketable equity securities.

 

 
 
A-70

 


ITEM 8.
FINANCIAL STATEMENTS AND SUPPLEMENTARY DATA

PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

INDEX



 
Page
   
   
Management’s Annual Reports on Internal Control Over Financial Reporting
B-2
Reports of Independent Registered Public Accounting Firm
B-5
Financial Statements:
 
PNM Resources, Inc. and Subsidiaries
 
Consolidated Statements of Earnings (Loss)
B-10
Consolidated Balance Sheets
B-11
Consolidated Statements of Cash Flows
B-13
Consolidated Statements of Changes in PNMR Common Stockholders’ Equity
B-15
Consolidated Statements of Comprehensive Income (Loss)
B-16
Public Service Company of New Mexico and Subsidiaries
 
Consolidated Statements of Earnings (Loss)
B-17
Consolidated Balance Sheets
B-18
Consolidated Statements of Cash Flows
B-20
Consolidated Statements of Changes in PNM Common Stockholder’s Equity
B-22
Consolidated Statements of Comprehensive Income (Loss)
B-23
Texas-New Mexico Power Company and Subsidiaries
 
Consolidated Statements of Earnings (Loss)
B-24
Consolidated Balance Sheets
B-25
Consolidated Statements of Cash Flows
B-27
Consolidated Statements of Changes in Common Stockholder’s Equity
B-29
Consolidated Statements of Comprehensive Income (Loss)
B-30
Notes to Consolidated Financial Statements
B-31
Supplementary Data:
 
Reports of Independent Registered Public Accounting Firm on Schedules
B-124
Schedule I Condensed Financial Information of Parent Company
B-126
Schedule II Valuation and Qualifying Accounts
B-129



 
 
B-1

 

Management’s Annual Report on Internal Control Over Financial Reporting


Management of PNM Resources, Inc. and subsidiaries (“PNMR”) is responsible for establishing and maintaining adequate internal control over financial reporting as defined in Rule 13a-15(f) under the Securities Exchange Act of 1934, as amended.

Management assessed the effectiveness of PNMR’s internal control over financial reporting based on the Internal Control – Integrated Framework set forth by the Committee of Sponsoring Organizations of the Treadway Commission.  Based on the assessment performed, management concludes that PNMR’s internal control over financial reporting was effective as of December 31, 2009.

Deloitte & Touche LLP, an independent registered public accounting firm, has issued an attestation report on PNMR’s internal control over financial reporting which is included herein.
 
 

 
/s/ Jeffry E. Sterba
Jeffry E. Sterba,
Chairman and
Chief Executive Officer




/s/ Charles Eldred
Charles Eldred
Executive Vice President and
Chief Financial Officer

 
 
B-2

 

Management’s Annual Report on Internal Control Over Financial Reporting


Management of Public Service Company of New Mexico and subsidiaries (“PNM”) is responsible for establishing and maintaining adequate internal control over financial reporting as defined in Rule 13a-15(f) under the Securities Exchange Act of 1934, as amended.

Management assessed the effectiveness of PNM’s internal control over financial reporting based on the Internal Control – Integrated Framework set forth by the Committee of Sponsoring Organizations of the Treadway Commission.  Based on the assessment performed, management concludes that PNM’s internal control over financial reporting was effective as of December 31, 2009.

Deloitte & Touche LLP, an independent registered public accounting firm, has issued an attestation report on PNM’s internal control over financial reporting which is included herein.

 

 
/s/ Patricia K. Collawn
Patricia K. Collawn,
President and Chief Executive Officer


 

/s/ Charles Eldred
Charles Eldred
Executive Vice President and
Chief Financial Officer



 
 
B-3

 

Management’s Annual Report on Internal Control Over Financial Reporting


Management of Texas-New Mexico Power Company and subsidiaries (“TNMP”) is responsible for establishing and maintaining adequate internal control over financial reporting as defined in Rule 13a-15(f) under the Securities Exchange Act of 1934, as amended.

Management assessed the effectiveness of TNMP’s internal control over financial reporting based on the Internal Control – Integrated Framework set forth by the Committee of Sponsoring Organizations of the Treadway Commission.  Based on the assessment performed, management concludes that TNMP’s internal control over financial reporting was effective as of December 31, 2009.




/s/ Patricia K. Collawn
Patricia K. Collawn,
President and
Chief Executive Officer




/s/ Thomas G. Sategna
Thomas G. Sategna
Vice President and Controller


 
 
B-4

 

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM

To the Board of Directors and Stockholders of
PNM Resources, Inc.
Albuquerque, New Mexico

We have audited the internal control over financial reporting of PNM Resources, Inc. and subsidiaries (the "Company") as of December 31, 2009, based on criteria established in Internal Control — Integrated Framework issued by the Committee of Sponsoring Organizations of the Treadway Commission.  The Company's management is responsible for maintaining effective internal control over financial reporting and for its assessment of the effectiveness of internal control over financial reporting, included in the accompanying Management’s Annual Report on Internal Control Over Financial Reporting.  Our responsibility is to express an opinion on the Company's internal control over financial reporting based on our audit.

We conducted our audit in accordance with the standards of the Public Company Accounting Oversight Board (United States). Those standards require that we plan and perform the audit to obtain reasonable assurance about whether effective internal control over financial reporting was maintained in all material respects. Our audit included obtaining an understanding of internal control over financial reporting, assessing the risk that a material weakness exists, testing and evaluating the design and operating effectiveness of internal control based on the assessed risk, and performing such other procedures as we considered necessary in the circumstances. We believe that our audit provides a reasonable basis for our opinion.

A company's internal control over financial reporting is a process designed by, or under the supervision of, the company's principal executive and principal financial officers, or persons performing similar functions, and effected by the company's board of directors, management, and other personnel to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles. A company's internal control over financial reporting includes those policies and procedures that (1) pertain to the maintenance of records that, in reasonable detail, accurately and fairly reflect the transactions and dispositions of the assets of the company; (2) provide reasonable assurance that transactions are recorded as necessary to permit preparation of financial statements in accordance with generally accepted accounting principles, and that receipts and expenditures of the company are being made only in accordance with authorizations of management and directors of the company; and (3) provide reasonable assurance regarding prevention or timely detection of unauthorized acquisition, use, or disposition of the company's assets that could have a material effect on the financial statements.

Because of the inherent limitations of internal control over financial reporting, including the possibility of collusion or improper management override of controls, material misstatements due to error or fraud may not be prevented or detected on a timely basis. Also, projections of any evaluation of the effectiveness of the internal control over financial reporting to future periods are subject to the risk that the controls may become inadequate because of changes in conditions, or that the degree of compliance with the policies or procedures may deteriorate.

In our opinion, the Company maintained, in all material respects, effective internal control over financial reporting as of December 31, 2009, based on the criteria established in Internal Control — Integrated Framework issued by the Committee of Sponsoring Organizations of the Treadway Commission.

We have also audited, in accordance with the standards of the Public Company Accounting Oversight Board (United States), the consolidated financial statements and financial statement schedules of the Company as of and for the year ended December 31, 2009 and our reports dated February 27, 2010 relating to the consolidated financial statements and financial statement schedules of the Company expressed an unqualified opinion on those consolidated financial statements and financial statement schedules.

/s/ DELOITTE & TOUCHE LLP
 
Dallas, Texas
February 27, 2010

 
 
B-5

 

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM

To the Board of Directors and Stockholders of
Public Service Company of New Mexico
Albuquerque, New Mexico
 
We have audited the internal control over financial reporting of Public Service Company of New Mexico and subsidiaries (the "Company") as of December 31, 2009, based on criteria established in Internal Control — Integrated Framework issued by the Committee of Sponsoring Organizations of the Treadway Commission.  The Company's management is responsible for maintaining effective internal control over financial reporting and for its assessment of the effectiveness of internal control over financial reporting, included in the accompanying Management’s Annual Report on Internal Control Over Financial Reporting.  Our responsibility is to express an opinion on the Company's internal control over financial reporting based on our audit.
 
We conducted our audit in accordance with the standards of the Public Company Accounting Oversight Board (United States). Those standards require that we plan and perform the audit to obtain reasonable assurance about whether effective internal control over financial reporting was maintained in all material respects. Our audit included obtaining an understanding of internal control over financial reporting, assessing the risk that a material weakness exists, testing and evaluating the design and operating effectiveness of internal control based on the assessed risk, and performing such other procedures as we considered necessary in the circumstances. We believe that our audit provides a reasonable basis for our opinion.

A company's internal control over financial reporting is a process designed by, or under the supervision of, the company's principal executive and principal financial officers, or persons performing similar functions, and effected by the company's board of directors, management, and other personnel to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles. A company's internal control over financial reporting includes those policies and procedures that (1) pertain to the maintenance of records that, in reasonable detail, accurately and fairly reflect the transactions and dispositions of the assets of the company; (2) provide reasonable assurance that transactions are recorded as necessary to permit preparation of financial statements in accordance with generally accepted accounting principles, and that receipts and expenditures of the company are being made only in accordance with authorizations of management and directors of the company; and (3) provide reasonable assurance regarding prevention or timely detection of unauthorized acquisition, use, or disposition of the company's assets that could have a material effect on the financial statements.

Because of the inherent limitations of internal control over financial reporting, including the possibility of collusion or improper management override of controls, material misstatements due to error or fraud may not be prevented or detected on a timely basis. Also, projections of any evaluation of the effectiveness of the internal control over financial reporting to future periods are subject to the risk that the controls may become inadequate because of changes in conditions, or that the degree of compliance with the policies or procedures may deteriorate.
 
In our opinion, the Company maintained, in all material respects, effective internal control over financial reporting as of December 31, 2009, based on the criteria established in Internal Control — Integrated Framework issued by the Committee of Sponsoring Organizations of the Treadway Commission.
 
We have also audited, in accordance with the standards of the Public Company Accounting Oversight Board (United States), the consolidated financial statements and financial statement schedules of the Company as of and for the year ended December 31, 2009 and our reports dated February 27, 2010 relating to the consolidated financial statements and financial statement schedules of the Company expressed an unqualified opinion on those consolidated financial statements and financial statement schedules.
 
/s/ DELOITTE & TOUCHE LLP

Dallas, Texas
February 27, 2010

 
 
B-6

 

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM

To the Board of Directors and Stockholders of
PNM Resources, Inc.
Albuquerque, New Mexico

We have audited the accompanying consolidated balance sheets of PNM Resources, Inc. and subsidiaries (the “Company”) as of December 31, 2009 and 2008, and the related consolidated statements of earnings (loss), changes in common stockholders’ equity, comprehensive income (loss), and cash flows for each of the three years in the period ended December 31, 2009. These financial statements are the responsibility of the Company's management. Our responsibility is to express an opinion on these financial statements based on our audits.

We conducted our audits in accordance with the standards of the Public Company Accounting Oversight Board (United States). Those standards require that we plan and perform the audits to obtain reasonable assurance about whether the financial statements are free of material misstatement. An audit includes examining, on a test basis, evidence supporting the amounts and disclosures in the financial statements. An audit also includes assessing the accounting principles used and significant estimates made by management, as well as evaluating the overall financial statement presentation. We believe that our audits provide a reasonable basis for our opinion.
 
In our opinion, such consolidated financial statements present fairly, in all material respects, the financial position of PNM Resources, Inc. and subsidiaries as of December 31, 2009 and 2008, and the results of their operations and their cash flows for each of the three years in the period ended December 31, 2009, in conformity with accounting principles generally accepted in the United States of America.

As discussed in Note 8 to the consolidated financial statements, the Company changed the method of accounting for fair value measurements in 2008.
 
We have also audited, in accordance with the standards of the Public Company Accounting Oversight Board (United States), the Company's internal control over financial reporting as of December 31, 2009, based on the criteria established in Internal Control—Integrated Framework issued by the Committee of Sponsoring Organizations of the Treadway Commission and our report dated February 27, 2010 expressed an unqualified opinion on the Company's internal control over financial reporting.
 
/s/ DELOITTE & TOUCHE LLP

Dallas, Texas
February 27, 2010



 
 
B-7

 

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM

To the Board of Directors and Stockholders of
Public Service Company of New Mexico
Albuquerque, New Mexico

We have audited the accompanying consolidated balance sheets of Public Service Company of New Mexico and subsidiaries (the “Company”) as of December 31, 2009 and 2008, and the related consolidated statements of earnings (loss), changes in common stockholder’s equity, comprehensive income (loss), and cash flows for each of the three years in the period ended December 31, 2009. These financial statements are the responsibility of the Company's management. Our responsibility is to express an opinion on these financial statements based on our audits.

We conducted our audits in accordance with the standards of the Public Company Accounting Oversight Board (United States). Those standards require that we plan and perform the audits to obtain reasonable assurance about whether the financial statements are free of material misstatement. An audit includes examining, on a test basis, evidence supporting the amounts and disclosures in the financial statements. An audit also includes assessing the accounting principles used and significant estimates made by management, as well as evaluating the overall financial statement presentation. We believe that our audits provide a reasonable basis for our opinion.

In our opinion, such consolidated financial statements present fairly, in all material respects, the financial position of Public Service Company of New Mexico and subsidiaries as of December 31, 2009 and 2008, and the results of their operations and their cash flows for each of the three years in the period ended December 31, 2009, in conformity with accounting principles generally accepted in the United States of America.
 
As discussed in Note 8 to the consolidated financial statements, the Company changed the method of accounting for fair value measurements in 2008.
 
 
We have also audited, in accordance with the standards of the Public Company Accounting Oversight Board (United States), the Company's internal control over financial reporting as of December 31, 2009, based on the criteria established in Internal Control—Integrated Framework issued by the Committee of Sponsoring Organizations of the Treadway Commission and our report dated February 27, 2010 expressed an unqualified opinion on the Company's internal control over financial reporting.
 

/s/ DELOITTE & TOUCHE LLP

Dallas, Texas
February 27, 2010





 
 
B-8

 

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM

To the Board of Directors and Stockholder of
Texas-New Mexico Power Company
Lewisville, Texas

We have audited the accompanying consolidated balance sheets of Texas-New Mexico Power Company and subsidiaries (the “Company”) as of December 31, 2009 and 2008, and the related consolidated statements of earnings (loss), statements of changes in common stockholder’s equity, comprehensive income (loss), and cash flows for each of the three years in the period ended December 31, 2009.  These financial statements are the responsibility of the Company's management.  Our responsibility is to express an opinion on these financial statements based on our audits.

We conducted our audits in accordance with the standards of the Public Company Accounting Oversight Board (United States).  Those standards require that we plan and perform the audits to obtain reasonable assurance about whether the financial statements are free of material misstatement.  The Company is not required to have, nor were we engaged to perform, an audit of its internal control over financial reporting.  Our audits included consideration of internal control over financial reporting as a basis for designing audit procedures that are appropriate in the circumstances, but not for the purpose of expressing an opinion on the effectiveness of the Company's internal control over financial reporting.  Accordingly, we express no such opinion.  An audit includes examining, on a test basis, evidence supporting the amounts and disclosures in the financial statements.  An audit also includes assessing the accounting principles used and significant estimates made by management, as well as evaluating the overall financial statement presentation.  We believe that our audits provide a reasonable basis for our opinion.

In our opinion, such consolidated financial statements present fairly, in all material respects, the financial position of Texas-New Mexico Power Company and subsidiaries as of December 31, 2009 and 2008, and the results of their operations and their cash flows for each of the three years in the period ended December 31, 2009, in conformity with accounting principles generally accepted in the United States of America.


/s/ DELOITTE & TOUCHE LLP

Dallas, Texas
February 27, 2010



 
 
B-9

 

PNM RESOURCES, INC. AND SUBSIDIARIES
CONSOLIDATED STATEMENTS OF EARNINGS (LOSS)

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands, except per share amounts)
 
Operating Revenues:
                 
Electric
  $ 1,647,485     $ 1,959,241     $ 1,912,824  
Other
    259       281       1,205  
Total operating revenues
    1,647,744       1,959,522       1,914,029  
                         
Operating Expenses:
                       
Cost of energy
    717,989       1,239,854       1,121,525  
Administrative and general
    262,282       253,311       214,588  
Energy production costs
    185,228       193,899       201,483  
Impairment of goodwill and other intangible assets
    -       221,769       -  
Regulatory disallowances
    27,542       30,248       -  
Depreciation and amortization
    147,949       144,362       135,695  
Transmission and distribution costs
    63,311       58,702       57,774  
Taxes other than income taxes
    51,501       47,191       57,922  
Total operating expenses
    1,455,802       2,189,336       1,788,987  
Operating income (loss)
    191,942       (229,814 )     125,042  
                         
Other Income and Deductions:
                       
Interest income
    28,389       24,096       43,154  
Gains (losses) on investments held by NDT
    4,502       (15,233 )     11,599  
Other income
    31,629       6,478       7,443  
Equity in net earnings (loss) of Optim Energy
    (30,145 )     (29,687 )     7,581  
Other deductions
    (9,361 )     (11,266 )     (11,552 )
Net other income (deductions)
    25,014       (25,612 )     58,225  
                         
Interest Charges
    122,205       132,955       120,155  
                         
Earnings (Loss) before Income Taxes
    94,751       (388,381 )     63,112  
                         
Income Taxes (Benefit)
    28,818       (90,816 )     3,226  
                         
Earnings (Loss) from Continuing Operations
    65,933       (297,565 )     59,886  
                         
Earnings from Discontinued Operations, net of Income
                       
Taxes of $36,687, $22,957, and $10,394
    70,801       34,628       15,516  
                         
Net Earnings (Loss)
    136,734       (262,937 )     75,402  
                         
Earnings Attributable to Valencia Non-controlling Interest
    (11,890 )     (7,179 )     -  
                         
Preferred Stock Dividend Requirements of Subsidiary
    (528 )     (528 )     (528 )
                         
Net Earnings (Loss) Attributable to PNMR
  $ 124,316     $ (270,644 )   $ 74,874  
                         
Earnings (Loss) from Continuing Operations Attributable to PNMR per Common Share:
                       
Basic
  $ 0.58     $ (3.66 )   $ 0.77  
Diluted
  $ 0.58     $ (3.66 )   $ 0.76  
Net Earnings (Loss) Attributable to PNMR per Common Share:
                       
Basic
  $ 1.36     $ (3.24 )   $ 0.98  
Diluted
  $ 1.36     $ (3.24 )   $ 0.96  
                         
Dividends Declared per Common Share
  $ 0.500     $ 0.605     $ 0.920  

The accompanying notes, as they relate to PNMR, are an integral part of these financial statements.

 
 
B-10

 

PNM RESOURCES, INC. AND SUBSIDIARIES
CONSOLIDATED BALANCE SHEETS

   
December 31,
 
   
2009
   
2008
 
   
(In thousands)
 
ASSETS
           
Current Assets:
           
Cash and cash equivalents
  $ 14,641     $ 140,619  
Special deposits
    52       3,480  
Accounts receivable, net of allowance for uncollectible accounts of $12,783 and $21,466
    106,593       119,174  
Unbilled revenues
    78,274       81,126  
Other receivables
    77,672       73,083  
Materials, supplies, and fuel stock
    50,631       49,397  
Regulatory assets
    7,476       1,541  
Derivative instruments
    50,619       51,250  
Income taxes receivable
    129,171       49,584  
Current assets of discontinued operations
    -       107,986  
Other current assets
    63,076       75,393  
                 
Total current assets
    578,205       752,633  
                 
Other Property and Investments:
               
Investment in PVNGS lessor notes
    137,511       168,729  
Equity investment in Optim Energy
    195,666       239,950  
Investments held by NDT
    137,032       111,671  
Other investments
    25,528       32,966  
Non-utility property, net of accumulated depreciation of $3,779 and $2,582
    7,923       9,135  
                 
Total other property and investments
    503,660       562,451  
                 
Utility Plant:
               
Plant in service and plant held for future use
    4,693,530       4,476,745  
Less accumulated depreciation and amortization
    1,611,496       1,545,950  
      3,082,034       2,930,795  
Construction work in progress
    181,078       202,556  
Nuclear fuel, net of accumulated amortization of $19,456 and $16,018
    69,337       58,674  
                 
Net utility plant
    3,332,449       3,192,025  
                 
Deferred Charges and Other Assets:
               
Regulatory assets
    524,136       629,141  
Goodwill
    321,310       321,310  
Other intangible assets, net of accumulated amortization of $5,272 and $4,672
    26,567       27,167  
Derivative instruments
    2,413       25,620  
Non-current assets of discontinued operations
    -       561,915  
Other deferred charges
    71,181       75,720  
                 
Total deferred charges and other assets
    945,607       1,640,873  
    $ 5,359,921     $ 6,147,982  

The accompanying notes, as they relate to PNMR, are an integral part of these financial statements.

 
 
B-11

 

PNM RESOURCES, INC. AND SUBSIDIARIES
CONSOLIDATED BALANCE SHEETS

   
December 31,
 
   
2009
   
2008
 
   
(In thousands, except share information)
 
LIABILITIES AND STOCKHOLDERS’ EQUITY
           
Current Liabilities:
           
Short-term debt
  $ 198,000     $ 744,667  
Current installments of long-term debt
    2,125       205,694  
Accounts payable
    111,432       174,068  
Accrued interest and taxes
    45,341       51,618  
Regulatory liabilities
    908       1,746  
Derivative instruments
    24,025       33,951  
Current liabilities of discontinued operations
    -       77,082  
Other current liabilities
    181,442       139,562  
                 
Total current liabilities
    563,273       1,428,388  
                 
Long-term Debt
    1,565,206       1,379,011  
                 
Deferred Credits and Other Liabilities:
               
Accumulated deferred income taxes
    531,166       572,719  
Accumulated deferred investment tax credits
    20,518       23,834  
Regulatory liabilities
    350,324       327,175  
Asset retirement obligations
    70,963       63,492  
Accrued pension liability and postretirement benefit cost
    281,923       246,136  
Derivative instruments
    4,549       6,934  
Non-current liabilities of discontinued operations
    -       94,615  
Other deferred credits
    121,394       149,237  
                 
Total deferred credits and other liabilities
    1,380,837       1,484,142  
                 
Total liabilities
    3,509,316       4,291,541  
                 
Commitments and Contingencies (See Note 16)
               
                 
Cumulative Preferred Stock of Subsidiary
               
without mandatory redemption requirements ($100 stated value, 10,000,000 shares authorized:
               
issued and outstanding 115,293 shares)
    11,529       11,529  
                 
Equity:
               
PNMR Convertible Preferred Stock, Series A, without mandatory redemption requirements
               
(no stated value, 10,000,000 shares authorized: issued and outstanding 477,800 shares)
    100,000       100,000  
PNMR common stockholders’ equity:
               
Common stock outstanding (no par value, 120,000,000 shares authorized: issued
               
and outstanding 86,673,174 and 86,531,644 shares)
    1,289,890       1,288,168  
Accumulated other comprehensive income (loss), net of income taxes
    (46,057 )     30,948  
Retained earnings
    405,884       327,290  
Total PNMR common stockholders’ equity
    1,649,717       1,646,406  
Non-controlling interest in Valencia
    89,359       98,506  
Total equity
    1,839,076       1,844,912  
                 
    $ 5,359,921     $ 6,147,982  

The accompanying notes, as they relate to PNMR, are an integral part of these financial statements.

 
 
B-12

 

PNM RESOURCES, INC. AND SUBSIDIARIES
CONSOLIDATED STATEMENTS OF CASH FLOWS

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
         
(In thousands)
       
Cash Flows From Operating Activities:
                 
Net earnings (loss)
  $ 136,734     $ (262,937 )   $ 75,402  
Adjustments to reconcile net earnings (loss) to net cash flows from operating activities:
                       
Depreciation and amortization
    173,446       167,111       179,396  
Amortization of prepayments on PVNGS firm-sales contracts
    (26,150 )     (16,637 )     -  
Bad debt expense
    44,071       59,635       20,265  
Deferred income tax expense (benefit)
    27,727       (46,692 )     35,423  
Equity in net (earnings) loss of Optim Energy
    30,145       29,687       (7,581 )
Net unrealized (gains) losses on derivatives
    (9,570 )     7,370       9,138  
Realized (gains) losses on investments held by NDT
    (4,502 )     15,233       (11,599 )
Realized loss on Altura contribution
    -       -       3,089  
Impairment of goodwill and other intangible assets
    -       221,769       3,380  
Impairment of utility plant
    -       -       19,500  
Gain on sale of PNM Gas
    (98,425 )     -       -  
Gain on reacquired debt
    (7,317 )     -       -  
Amortization of fair value of acquired Twin Oaks sales contract
    -       -       (35,073 )
Stock based compensation expense
    2,188       3,261       7,557  
Regulatory disallowances
    27,542       30,248       -  
Settlement of legal proceeding
    31,969       -       -  
Other, net
    (5,789 )     (6,345 )     (5,131 )
Changes in certain assets and liabilities:
                       
Accounts receivable and unbilled revenues
    (79,546 )     (42,702 )     (41,137 )
Materials, supplies, and fuel stock
    (1,083 )     (9,921 )     (104 )
Other current assets
    47,559       (34,399 )     19,147  
Other assets
    725       (28,300 )     (4,316 )
Accounts payable
    (70,540 )     2,516       4,423  
Accrued interest and taxes
    (94,996 )     (16,051 )     (6,402 )
Other current liabilities
    (20,980 )     3,314       (26,588 )
Other liabilities
    (15,502 )     12,465       (15,728 )
Net cash flows from operating activities
    87,706       88,625       223,061  
                         
Cash Flows From Investing Activities:
                       
Utility plant additions
    (288,031 )     (344,951 )     (455,944 )
Proceeds from sales of investments held by NDT
    124,054       180,296       163,642  
Purchases of investments held by NDT
    (129,833 )     (185,439 )     (172,327 )
Proceeds from sale of PNM Gas
    652,933       -       -  
Transaction costs for sale of PNM Gas
    (11,162 )     -       -  
Proceeds from sales of utility plant
    -       1,458       55,041  
Return of principal on PVNGS lessor notes
    27,068       22,506       22,842  
Investments in Optim Energy
    -       -       (45,040 )
Distributions from Optim Energy
    -       -       362,282  
Change in restricted special deposits
    359       7,493       (7,852 )
Other, net
    4,338       (2,078 )     3,825  
Net cash flows from investing activities
    379,726       (320,715 )     (73,531 )

The accompanying notes, as they relate to PNMR, are an integral part of these financial statements.


 
 
B-13

 

PNM RESOURCES, INC. AND SUBSIDIARIES
CONSOLIDATED STATEMENTS OF CASH FLOWS

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
Cash Flows From Financing Activities:
                 
Short-term borrowings (repayments), net
    (546,667 )     78,767       (98,445 )
Long-term borrowings
    345,242       452,750       20,000  
Repayment of long-term debt
    (352,084 )     (450,826 )     (102,284 )
Issuance of common stock
    1,245       250,956       4,281  
Proceeds from stock option exercise
    -       86       11,001  
Purchase of common stock to satisfy stock awards
    (951 )     (1,401 )     (18,267 )
Excess tax benefits (tax shortfall) from stock-based payment arrangements
    (760 )     (560 )     12  
Payments received on PVNGS firm-sales contracts
    30,737       88,509       -  
Dividends paid
    (46,229 )     (58,026 )     (70,864 )
Equity transactions with Valencia’s owner
    (13,639 )     -       -  
Debt issuance costs and other
    (10,329 )     (5,312 )     (592 )
Net cash flows from financing activities
    (593,435 )     354,943       (255,158 )
                         
Change in Cash and Cash Equivalents
    (126,003 )     122,853       (105,628 )
Cash and Cash Equivalents at Beginning of Year
    140,644       17,791       123,419  
Cash and Cash Equivalents at End of Year
  $ 14,641     $ 140,644     $ 17,791  
                         
Supplemental Cash Flow Disclosures:
                       
Interest paid, net of capitalized interest
  $ 118,798     $ 144,944     $ 121,845  
Income taxes paid (refunded), net
  $ 118,160     $ (2,751 )   $ (21,390 )
                         
Supplemental schedule of noncash investing and financing activities:
                       
As of June 1, 2007, PNMR contributed its ownership of Altura to Optim Energy at a fair value of $549.6 million after an adjustment for working capital changes. See Note 22. In conjunction with the contribution, PNMR removed Altura’s assets and liabilities from its balance sheet as follows:
 

  Current assets
        $ 22,529  
  Utility plant, net
          575,906  
  Deferred charges
          46,018  
       Total assets contributed
    644,453  
         
  Current liabilities
          63,268  
  Deferred credits and other liabilities
          38,095  
       Total liabilities contributed
    101,363  
  Other comprehensive income
          (12,651 )
       Total liabilities and OCI contributed
    88,712  
         
          Net contribution to Optim Energy
        $ 555,741  
         
Utility plant purchased in 2007 through assumption of long-term debt that eliminates
         
a portion of investment in PVNGS lessor notes in consolidation.  See Note 2.
        $ 41,152  
 
             
Activities related to consolidation of Valencia:
       
    Initial consolidation at May 30, 2008:
             
          Utility plant additions
  $ 87,310          
          Increase in short-term borrowings
    82,468          
     Non-controlling interest transactions as of July 10, 2008:
               
          Reduction in short-term borrowings
    88,059          
          Increase in non-controlling interest in Valencia
    90,148          
                 
Convertible preferred stock issued under forward purchase contract upon
               
tender of senior unsecured notes
  $ 100,000          

The accompanying notes, as they relate to PNMR, are an integral part of these financial statements.

 
 
B-14

 

PNM RESOURCES, INC. AND SUBSIDIARIES
CONSOLIDATED STATEMENTS OF CHANGES IN PNMR COMMON STOCKHOLDERS’ EQUITY

         
Accumulated
         
Total PNMR
 
   
Common Stock
   
Other
         
Common
 
   
Number of
   
Aggregate
   
Comprehensive
   
Retained
   
Stockholders’
 
   
Shares
   
Value
   
Income (Loss)
   
Earnings
   
Equity
 
         
(Dollars in thousands)
 
                               
Balance at December 31, 2006
    76,648,472     $ 1,040,451     $ 28,909     $ 635,550     $ 1,704,910  
Purchase of common stock to satisfy stock awards
    -       (9,327 )     -       -       (9,327 )
Tax benefit from stock-based compensation arrangements
    -       12       -       -       12  
Stock based compensation expense
    -       7,557       -       -       7,557  
Sale of common stock
    110,134       2,914       -       -       2,914  
Common stock issued to ESPP
    55,885       1,367       -       -       1,367  
Net earnings attributable to PNMR
    -       -       -       74,874       74,874  
Total other comprehensive income (loss)
    -       -       (17,701 )     -       (17,701 )
Adoption of amendment to GAAP regarding uncertain tax positions
    -       -       -       (1,576 )     (1,576 )
Dividends declared on common stock
    -       -       -       (70,619 )     (70,619 )
Balance at December 31, 2007
    76,814,491       1,042,974       11,208       638,229       1,692,411  
Adoption of amendment to GAAP regarding fair value measurements
    -       -       -       10,422       10,422  
Purchase of common stock to satisfy stock awards
    -       (1,285 )     -       -       (1,285 )
Tax shortfall from stock-based compensation arrangements
    -       (560 )     -       -       (560 )
Stock based compensation expense
    -       3,261       -       -       3,261  
Sale of common stock
    9,624,929       249,977       -       -       249,977  
Stock issuance costs
    -       (7,177 )     -       -       (7,177 )
Common stock issued to ESPP
    92,224       978       -       -       978  
Net earnings (loss) attributable to PNMR
    -       -       -       (270,644 )     (270,644 )
Total other comprehensive income
    -       -       19,740       -       19,740  
Dividends declared on common stock
    -       -       -       (50,717 )     (50,717 )
Balance at December 31, 2008
    86,531,644       1,288,168       30,948       327,290       1,646,406  
Purchase of common stock to satisfy stock awards
    -       (951 )     -       -       (951 )
Tax shortfall from stock-based compensation arrangements
    -       (760 )     -       -       (760 )
Stock based compensation expense
    -       2,188       -       -       2,188  
Sale of common stock
    93,328       818       -       -       818  
Common stock issued to ESPP
    48,202       427       -       -       427  
Net earnings attributable to PNMR
    -       -       -       124,316       124,316  
Total other comprehensive income (loss)
    -       -       (77,005 )     -       (77,005 )
Dividends declared on common stock
    -       -       -       (45,722 )     (45,722 )
Balance at December 31, 2009
    86,673,174     $ 1,289,890     $ (46,057 )   $ 405,884     $ 1,649,717  

The accompanying notes, as they relate to PNMR, are an integral part of these financial statements.


 
 
B-15

 

PNM RESOURCES, INC. AND SUBSIDIARIES
CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME (LOSS)

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
         
(In thousands)
       
                   
Net Earnings (Loss)
  $ 136,734     $ (262,937 )   $ 75,402  
                         
Other Comprehensive Income (Loss):
                       
                         
Unrealized Gain (Loss) on Investment Securities:
                       
Unrealized holding gains (losses) arising during
                       
the period, net of income tax (expense) benefit
                       
of $(7,462), $1,949,and $(3,029)
    11,386       (2,974 )     4,621  
Reclassification adjustment for (gains) losses included in
                       
net earnings (loss), net of income tax expense (benefit)
                       
of $1,538, $5,433, and $4,913
    (2,348 )     (8,290 )     (7,497 )
                         
Pension liability adjustment, net of income
                       
tax (expense) benefit of $43,542, $2,642, and $(948)
    (66,448 )     (4,204 )     1,446  
                         
Fair Value Adjustment for Designated Cash Flow Hedges:
                       
Change in fair market value, net of income tax (expense)
                       
benefit of $(7,471), $(26,184), and $11,674
    9,473       40,376       (17,889 )
Reclassification adjustment for (gains) losses included in
                       
net earnings (loss), net of income tax expense (benefit)
                       
of $20,421, $2,893, and $(992)
    (29,068 )     (5,168 )     1,618  
                         
Total Other Comprehensive Income (Loss)
    (77,005 )     19,740       (17,701 )
                         
Comprehensive Income (Loss)
    59,729       (243,197 )     57,701  
                         
Comprehensive Income Attributable to Valencia Non-controlling Interest
    (11,890 )     (7,179 )     -  
                         
Preferred Stock Dividend Requirements of Subsidiary
    (528 )     (528 )     (528 )
                         
Comprehensive Income (Loss) Attributable to PNMR
  $ 47,311     $ (250,904 )   $ 57,173  

The accompanying notes, as they relate to PNMR, are an integral part of these financial statements.


 
 
B-16

 

PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED STATEMENTS OF EARNINGS (LOSS)

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
                   
Electric Operating Revenues
  $ 968,009     $ 1,242,942     $ 1,136,974  
                         
Operating Expenses:
                       
Cost of energy sold
    378,145       698,054       638,675  
Administrative and general
    135,027       120,712       122,002  
Energy production costs
    190,634       203,419       190,828  
Impairment of goodwill
    -       51,143       -  
Regulatory disallowances
    26,872       30,248       -  
Depreciation and amortization
    92,140       85,724       83,223  
Transmission and distribution costs
    41,022       37,616       39,137  
Taxes other than income taxes
    26,918       22,543       29,138  
Total operating expenses
    890,758       1,249,459       1,103,003  
Operating income (loss)
    77,251       (6,517 )     33,971  
                         
Other Income and Deductions:
                       
Interest income
    30,543       24,674       41,655  
Gains (losses) on investments held by NDT
    4,502       (15,233 )     11,599  
Other income
    6,002       2,477       5,137  
Other deductions
    (3,613 )     (4,857 )     (5,089 )
Net other income (deductions)
    37,434       7,061       53,302  
                         
Interest Charges
    69,058       69,868       52,662  
                         
Earnings (Loss) before Income Taxes
    45,627       (69,324 )     34,611  
                         
Income Taxes (Benefit)
    13,726       (10,029 )     11,220  
                         
Earnings (Loss) from Continuing Operations
    31,901       (59,295 )     23,391  
                         
Earnings from Discontinued Operations, net of Income
                       
Taxes of $36,687, $22,957, and $10,394
    70,801       34,628       15,516  
                         
Net Earnings (Loss)
    102,702       (24,667 )     38,907  
                         
Earnings Attributable to Valencia Non-controlling Interest
    (11,890 )     (7,179 )     -  
                         
Net Earnings (Loss) Attributable to PNM
    90,812       (31,846 )     38,907  
                         
Preferred Stock Dividends Requirements
    (528 )     (528 )     (528 )
                         
Net Earnings (Loss) Available for PNM Common Stock
  $ 90,284     $ (32,374 )   $ 38,379  

The accompanying notes, as they relate to PNM, are an integral part of these financial statements.

 
 
B-17

 

PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED BALANCE SHEETS

   
December 31,
 
   
2009
   
2008
 
   
(In thousands)
 
ASSETS
           
Current Assets:
           
Cash and cash equivalents
  $ 1,373     $ 46,596  
Special deposits
    2       3,430  
Accounts receivable, net of allowance for uncollectible accounts of $1,483 and $1,345
    70,515       74,257  
Unbilled revenues
    38,067       37,350  
Other receivables
    74,120       72,096  
Affiliate accounts receivable
    33       -  
Materials, supplies, and fuel stock
    47,789       47,254  
Regulatory assets
    7,476       1,541  
Derivative instruments
    24,498       28,852  
Income taxes receivable
    59,299       -  
Current assets of discontinued operations
    -       107,986  
Other current assets
    40,197       49,690  
                 
Total current assets
    363,369       469,052  
                 
Other Property and Investments:
               
Investment in PVNGS lessor notes
    137,511       200,711  
Investments held by NDT
    137,032       111,671  
Other investments
    7,473       9,951  
Non-utility property
    976       976  
                 
Total other property and investments
    282,992       323,309  
                 
Utility Plant:
               
Plant in service and plant held for future use
    3,677,974       3,448,218  
Less accumulated depreciation and amortization
    1,260,903       1,204,424  
      2,417,071       2,243,794  
Construction work in progress
    159,793       156,997  
Nuclear fuel, net of accumulated amortization of $19,456 and $16,018
    69,337       58,674  
                 
Net utility plant
    2,646,201       2,459,465  
                 
Deferred Charges and Other Assets:
               
Regulatory assets
    375,131       494,481  
Derivative instruments
    -       17,744  
Goodwill
    51,632       51,632  
Non-current assets of discontinued operations
    -       561,915  
Other deferred charges
    55,841       51,137  
                 
Total deferred charges and other assets
    482,604       1,176,909  
    $ 3,775,166     $ 4,428,735  

The accompanying notes, as they relate to PNM, are an integral part of these financial statements.


 
 
B-18

 

PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED BALANCE SHEETS

   
December 31,
 
   
2009
   
2008
 
   
(In thousands, except share information)
 
LIABILITIES AND STOCKHOLDER’S EQUITY
           
Current Liabilities:
           
Short-term debt
  $ 118,000     $ 340,000  
Current installments of long-term debt
    -       36,000  
Accounts payable
    57,473       90,502  
Affiliate accounts payable
    13,481       17,607  
Accrued interest and taxes
    24,124       50,125  
Regulatory liabilities
    908       1,746  
Derivative instruments
    1,509       7,884  
Current liability of discontinued operations
    -       77,082  
Other current liabilities
    126,273       93,131  
                 
Total current liabilities
    341,768       714,077  
                 
Long-term Debt
    1,055,733       1,019,717  
                 
Deferred Credits and Other Liabilities:
               
Accumulated deferred income taxes
    364,498       414,995  
Accumulated deferred investment tax credits
    20,518       23,834  
Regulatory liabilities
    316,215       292,146  
Asset retirement obligations
    70,099       62,696  
Accrued pension liability and postretirement benefit cost
    265,791       229,683  
Derivative instruments
    556       569  
Non-current liabilities of discontinued operations
    -       94,615  
Other deferred credits
    90,425       124,929  
                 
Total deferred credits and liabilities
    1,128,102       1,243,467  
                 
Total liabilities
    2,525,603       2,977,261  
                 
Commitments and Contingencies (See Note 16)
               
                 
Cumulative Preferred Stock
               
without mandatory redemption requirements ($100 stated value, 10,000,000 authorized:
               
issued and outstanding 115,293 shares)
    11,529       11,529  
                 
Equity:
               
   PNM common stockholder’s equity:
               
Common stock outstanding (no par value, 40,000,000 shares authorized: issued
               
and outstanding 39,117,799 shares)
    1,018,776       932,523  
Accumulated other comprehensive income (loss), net of income tax
    (51,807 )     17,746  
Retained earnings
    181,706       391,170  
Total PNM common stockholder’s equity
    1,148,675       1,341,439  
   Non-controlling interest in Valencia
    89,359       98,506  
Total equity
    1,238,034       1,439,945  
                 
    $ 3,775,166     $ 4,428,735  

The accompanying notes, as they relate to PNM, are an integral part of these financial statements.


 
 
B-19

 

PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED STATEMENTS OF CASH FLOWS

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
Cash Flows From Operating Activities:
                 
Net earnings (loss)
  $ 102,702     $ (24,667 )   $ 38,907  
Adjustments to reconcile net earnings (loss) to net cash flows from operating activities:
                       
Depreciation and amortization
    108,505       101,458       126,255  
Amortization of prepayments on PVNGS firm-sales contracts
    (26,150 )     (16,637 )     -  
Deferred income tax expense (benefit)
    4,648       (7,856 )     16,704  
Net unrealized (gains) losses on derivatives
    (4,487 )     6,629       8,496  
Realized (gains) losses on investments held by NDT
    (4,502 )     15,233       (11,599 )
Gain on sale of PNM Gas
    (98,425 )     -       -  
Impairment of utility plant
    -       -       19,500  
Regulatory disallowances
    26,872       30,248       -  
Settlement of legal proceeding
    31,969       -       -  
Impairment of goodwill
    -       51,143       -  
Other, net
    1,614       4,273       2,945  
Changes in certain assets and liabilities:
                       
Accounts receivable and unbilled revenues
    (50,552 )     (1,289 )     12,022  
Materials, supplies, and fuel stock
    (385 )     (9,319 )     1,292  
Other current assets
    17,679       (21,359 )     13,852  
Other assets
    10,821       20,572       (8,931 )
Accounts payable
    (40,932 )     (3,466 )     (2,688 )
Accrued interest and taxes
    (88,182 )     24,643       (1,683 )
Other current liabilities
    (12,915 )     4,957       (17,903 )
Other liabilities
    (17,588 )     (6,989 )     (8,243 )
Net cash flows from operating activities
    (39,308 )     167,574       188,926  
                         
Cash Flows From Investing Activities:
                       
Utility plant additions
    (256,769 )     (277,087 )     (352,142 )
Proceeds from sales of NDT investments
    124,054       180,295       163,642  
Purchases of NDT investments
    (129,833 )     (185,439 )     (172,327 )
Proceeds from sale of PNM Gas
    652,933       -       -  
Transaction costs for sale of PNM Gas
    (11,162 )     -       -  
Proceeds from sales of utility plant
    -       837       55,041  
Return of principal on PVNGS lessor notes
    30,871       26,077       24,638  
Change in restricted special deposits
    359       7,493       (7,852 )
Other, net
    2,041       419       2,361  
Net cash flows from investing activities
    412,494       (247,405 )     (286,639 )

The accompanying notes, as they relate to PNM, are an integral part of these financial statements.


 
 
B-20

 

PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED STATEMENTS OF CASH FLOWS
   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
Cash Flows From Financing Activities:
                 
Short-term borrowings (repayments), net
    (222,000 )     24,591       70,725  
Long-term borrowings
    36,000       350,000       20,000  
Repayment of long-term debt
    (36,000 )     (300,000 )     -  
Payments received on PVNGS firm-sales contracts
    30,737       88,509       -  
Equity contribution from parent
    86,253       -       -  
Equity transactions with Valencia’s owner
    (13,639 )     -       -  
Dividends paid
    (300,276 )     (40,528 )     (528 )
Other, net
    491       (451 )     (39 )
Net cash flows from financing activities
    (418,434 )     122,121       90,158  
                         
Change in Cash and Cash Equivalents
    (45,248 )     42,290       (7,555 )
Cash and Cash Equivalents at Beginning of Year
    46,621       4,331       11,886  
Cash and Cash Equivalents at End of Year
  $ 1,373     $ 46,621     $ 4,331  
                         
Supplemental Cash Flow Disclosures:
                       
Interest paid, net of capitalized interest
  $ 68,486     $ 80,144     $ 59,413  
Income taxes paid (refunded), net
  $ 126,528     $ 2,050     $ 5,604  
                         
Supplemental schedule of noncash investing and financing activities:
                       
As of January 1, 2007, TNMP transferred its New Mexico operational assets and liabilities to PNMR through a redemption of TNMP’s common stock. PNMR contemporaneously contributed the TNMP New Mexico operational assets and liabilities to PNM. See Note 2.
 
Current assets
                  $ 15,444  
Other property and investments
                    10  
Utility plant, net
                    96,468  
Goodwill
                    102,775  
Deferred charges
                    1,377  
Total assets transferred from TNMP
                    216,074  
                         
Current liabilities
                    17,313  
Long-term debt
                    1,065  
Deferred credits and other liabilities
                    30,673  
Total liabilities transferred from TNMP
                    49,051  
                         
Net assets transferred – increase in common stockholder’s equity
                  $ 167,023  
                         
Activities related to consolidation of Valencia:
                       
     Initial consolidation at May 30, 2008:
                       
          Utility plant additions
          $ 87,310          
          Increase in short-term borrowings
            82,468          
     Non-controlling interest transactions as of July 10, 2008:
                       
          Reduction in short-term borrowings
            88,059          
          Increase in non-controlling interest in Valencia
            90,148          
                         
Utility plant purchased through assumption of long-term debt (see Note 17)
  $ 31,982                  

The accompanying notes, as they relate to PNM, are an integral part of these financial statements.

 
 
B-21

 

PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED STATEMENTS OF CHANGES IN PNM COMMON STOCKHOLDER’S EQUITY

         
Accumulated
         
Total PNM
 
   
Common Stock
   
Other
         
Common
 
   
Number of
   
Aggregate
   
Comprehensive
   
Retained
   
Stockholder’s
 
   
Shares
   
Value
   
Income (Loss)
   
Earnings
   
Equity
 
         
(Dollars in thousands)
 
                               
Balance at December 31, 2006
    39,117,799     $ 765,500     $ 8,761     $ 415,875     $ 1,190,136  
Equity contribution from parent
    -       167,023       -       -       167,023  
Net earnings attributable to PNM
    -       -       -       38,907       38,907  
Total other comprehensive income (loss)
    -       -       (1,181 )     -       (1,181 )
Adoption of amendment to GAAP regarding uncertain tax positions
    -       -       -       (1,132 )     (1,132 )
Dividends on preferred stock
    -       -       -       (528 )     (528 )
Balance at December 31, 2007
    39,117,799       932,523       7,580       453,122       1,393,225  
Adoption of amendment to GAAP regarding fair value measurements
    -       -       -       10,422       10,422  
Net earnings (loss) attributable to PNM
    -       -       -       (31,846 )     (31,846 )
Total other comprehensive income
    -       -       10,166       -       10,166  
Dividends on preferred stock
    -       -       -       (528 )     (528 )
Dividends on common stock
    -       -       -       (40,000 )     (40,000 )
Balance at December 31, 2008
    39,117,799       932,523       17,746       391,170       1,341,439  
Net earnings attributable to PNM
    -       -       -       90,812       90,812  
Total other comprehensive income (loss)
    -       -       (69,553 )     -       (69,553 )
Equity contributions from parent
    -       86,253       -       -       86,253  
Dividends on preferred stock
    -       -       -       (528 )     (528 )
Dividends on common stock
    -       -       -       (299,748 )     (299,748 )
Balance at December 31, 2009
    39,117,799     $ 1,018,776     $ (51,807 )   $ 181,706     $ 1,148,675  

The accompanying notes, as they relate to PNM, are an integral part of these financial statements.

 
 
B-22

 

PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME (LOSS)

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
         
(In thousands)
       
                   
Net Earnings (Loss)
  $ 102,702     $ (24,667 )   $ 38,907  
                         
Other Comprehensive Income (Loss):
                       
                         
Unrealized Gain (Loss) on Investment Securities:
                       
Unrealized holding gains (losses) arising during
                       
the period, net of income tax (expense) benefit
                       
of $(7,462), $1,949, and $(3,029)
    11,386       (2,974 )     4,621  
Reclassification adjustment for (gains) losses included in
                       
net earnings (loss), net of income tax expense (benefit)
                       
of $1,538, $5,433, and $4,913
    (2,348 )     (8,290 )     (7,497 )
                         
Pension liability adjustment, net of income
                       
tax (expense) benefit of $43,510, $2,123, and $(777)
    (66,391 )     (3,239 )     1,186  
                         
Fair Value Adjustment for Designated Cash Flow Hedges:
                       
Change in fair market value, net of income tax (expense)
                       
benefit of $(6,634), $(16,415), and $(972)
    10,123       25,048       1,484  
Reclassification adjustment for (gains) losses included in
                       
net earnings (loss), net of income tax expense (benefit)
                       
of $14,629, $248, and $639
    (22,323 )     (379 )     (975 )
                         
Total Other Comprehensive Income (Loss)
    (69,553 )     10,166       (1,181 )
                         
Comprehensive Income (Loss)
    33,149       (14,501 )     37,726  
                         
Comprehensive Income Attributable to Valencia Non-controlling Interest
    (11,890 )     (7,179 )     -  
                         
Comprehensive Income (Loss) Attributable to PNM
  $ 21,259     $ (21,680 )   $ 37,726  

The accompanying notes, as they relate to PNM, are an integral part of these financial statements.

 
 
B-23

 

TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED STATEMENTS OF EARNINGS (LOSS)

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
                   
Electric Operating Revenues
                 
   Non-affiliates
  $ 151,294     $ 135,068     $ 109,818  
   Affiliate
    41,338       55,214       70,603  
       Total electric operating revenues
    192,632       190,282       180,421  
                         
Operating Expenses:
                       
Cost of energy sold
    34,728       32,671       29,529  
Administrative and general
    33,464       27,354       29,113  
Impairment of goodwill
    -       34,456       -  
Regulatory disallowances
    670       -       -  
Depreciation and amortization
    37,262       38,695       30,401  
Transmission and distribution costs
    22,285       21,069       18,616  
Taxes, other than income taxes
    19,121       18,587       20,092  
Total operating expenses
    147,530       172,832       127,751  
Operating income
    45,102       17,450       52,670  
                         
Other Income and Deductions:
                       
Interest income
    9       63       85  
Other income
    2,622       3,333       1,615  
Other deductions
    238       (171 )     (147 )
Net other income (deductions)
    2,869       3,225       1,553  
                         
Interest Charges
    27,820       18,340       25,168  
                         
Earnings Before Income Taxes
    20,151       2,335       29,055  
                         
Income Taxes
    7,985       11,128       10,647  
                         
Net Earnings (Loss)
  $ 12,166     $ (8,793 )   $ 18,408  

The accompanying notes, as they relate to TNMP, are an integral part of these financial statements.


 
 
B-24

 

TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED BALANCE SHEETS

   
December 31,
 
   
2009
   
2008
 
   
(In thousands)
 
ASSETS
           
Current Assets:
           
Cash and cash equivalents
  $ 138     $ 124  
Special deposits
    50       50  
Accounts receivable
    11,773       11,457  
Unbilled revenues
    7,239       6,421  
Other receivables
    579       480  
Affiliate accounts receivable
    5,151       7,110  
Materials and supplies
    2,591       1,625  
Income taxes receivable
    10,762       9  
Other current assets
    1,012       958  
                 
Total current assets
    39,295       28,234  
                 
Other Property and Investments:
               
Other investments
    270       550  
Non-utility property
    2,111       2,111  
                 
Total other property and investments
    2,381       2,661  
                 
Utility Plant:
               
Plant in service and plant held for future use
    864,260       816,076  
Less accumulated depreciation and amortization
    292,608       291,228  
      571,652       524,848  
Construction work in progress
    9,832       30,948  
                 
Net utility plant
    581,484       555,796  
                 
Deferred Charges and Other Assets:
               
Regulatory assets
    149,005       134,660  
Goodwill
    226,665       226,665  
Other deferred charges
    10,225       23,982  
                 
Total deferred charges and other assets
    385,895       385,307  
                 
    $ 1,009,055     $ 971,998  

The accompanying notes, as they relate to TNMP, are an integral part of these financial statements.


 
 
B-25

 

TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED BALANCE SHEETS

   
December 31,
 
   
2009
   
2008
 
   
(In thousands, except share information)
 
LIABILITIES AND STOCKHOLDER’S EQUITY
           
Current Liabilities:
           
   Short-term debt
  $ -     $ 150,000  
Short-term debt – affiliate
    23,500       14,100  
Current installments of long-term debt
    -       167,690  
Accounts payable
    6,243       11,846  
Affiliate accounts payable
    2,281       1,238  
Accrued interest and taxes
    16,505       35,118  
Other current liabilities
    2,194       3,111  
                 
Total current liabilities
    50,723       383,103  
                 
Long-term Debt
    309,712       -  
                 
Deferred Credits and Other Liabilities:
               
Accumulated deferred income taxes
    136,944       111,193  
Regulatory liabilities
    34,109       35,028  
Asset retirement obligations
    772       711  
Accrued pension liability and postretirement benefit cost
    16,132       16,453  
Other deferred credits
    8,872       1,820  
                 
Total deferred credits and other liabilities
    196,829       165,205  
                 
Total liabilities
    557,264       548,308  
                 
Commitments and Contingencies (See Note 16)
               
                 
Common Stockholder’s Equity:
               
Common stock outstanding ($10 par value, 12,000,000 shares authorized:
               
issued and outstanding 6,358 shares)
    64       64  
Paid-in-capital
    443,187       427,320  
Accumulated other comprehensive income (loss), net of income tax
    (74 )     (142 )
Retained earnings (deficit)
    8,614       (3,552 )
                 
Total common stockholder’s equity
    451,791       423,690  
                 
    $ 1,009,055     $ 971,998  

The accompanying notes, as they relate to TNMP, are an integral part of these financial statements.


 
 
B-26

 

TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED STATEMENTS OF CASH FLOWS

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
Cash Flows From Operating Activities:
                 
Net earnings (loss)
  $ 12,166     $ (8,793 )   $ 18,408  
Adjustments to reconcile net earnings (loss) to
                       
net cash flows from operating activities:
                       
Depreciation and amortization
    42,589       42,418       35,383  
Regulatory disallowances
    670       -       -  
Impairment of goodwill
    -       34,456       -  
Deferred income tax expense (benefit)
    31,855       (7,714 )     (8,727 )
Other, net
    593       (2,506 )     (2,928 )
Changes in certain assets and liabilities:
                       
Accounts receivable and unbilled revenues
    (1,134 )     (4,697 )     (10,092 )
Materials and supplies
    (966 )     (200 )     (46 )
Other current assets
    (712 )     306       3,562  
Other assets
    (3,467 )     (33,434 )     (257 )
Accounts payable
    (5,604 )     6,181       (2,844 )
Accrued interest and taxes
    (29,254 )     938       52,924  
Other current liabilities
    2,147       1       (13,706 )
Other liabilities
    (2,679 )     14,639       (461 )
Net cash flows from operating activities
    46,204       41,595       71,216  
                         
Cash Flows From Investing Activities:
                       
Utility plant additions
    (53,063 )     (51,116 )     (42,725 )
Net cash flows from investing activities
    (53,063 )     (51,116 )     (42,725 )

The accompanying notes, as they relate to TNMP, are an integral part of these financial statements.


 
 
B-27

 

TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED STATEMENTS OF CASH FLOWS

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
Cash Flow From Financing Activities:
                 
Short-term borrowings (repayments), net
    (150,000 )     150,000       -  
Short-term borrowings, net- affiliate
    34,606       10,696       3,404  
Long-term borrowings
    309,242       -       -  
Repayment of long-term debt
    (167,690 )     (148,935 )     (100,500 )
Equity contribution by parent
    -       -       101,249  
Dividends paid
    (9,339 )     -       (35,000 )
Debt issuance costs and other
    (9,946 )     (2,303 )     1  
Net cash flows from financing activities
    6,873       9,458       (30,846 )
                         
Change in Cash and Cash Equivalents
    14       (63 )     (2,355 )
Cash and Cash Equivalents at Beginning of Year
    124       187       2,542  
Cash and Cash Equivalents at End of Year
  $ 138     $ 124     $ 187  
                         
Supplemental Cash Flow Disclosures:
                       
Interest paid, net of capitalized interest
  $ 24,465     $ 17,246     $ 23,625  
Income taxes paid, (refunded) net
  $ 5,887     $ 16,613     $ (15,529 )
                         
Supplemental schedule of noncash investing and financing activities:
 
As of January 1, 2007, TNMP transferred its New Mexico operational assets and liabilities to PNMR through a redemption of TNMP’s common stock. PNMR contemporaneously contributed the TNMP New Mexico operational assets and liabilities to PNM. See Note 2.
 
Current assets
                  $ 15,444  
Other property and investments
                    10  
Utility plant, net
                    96,468  
Goodwill
                    102,775  
Deferred charges
                    1,377  
Total assets transferred to PNM
                    216,074  
                         
Current liabilities
                    17,313  
Long-term debt
                    1,065  
Deferred credits and other liabilities
                    30,673  
Total liabilities transferred to PNM
                    49,051  
                         
Net assets transferred – common stock redeemed
                  $ 167,023  
                         
Equity contribution from parent through forgiveness of
   short-term debt
  $ 25,206                  

The accompanying notes, as they relate to TNMP, are an integral part of these financial statements.

 
 
B-28

 

TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED STATEMENTS OF CHANGES IN COMMON STOCKHOLDER’S EQUITY

               
Accumulated
         
Total
 
   
Common Stock
         
Other
   
Retained
   
Common
 
   
Number of
   
Aggregate
   
Paid-in
   
Comprehensive
   
Earnings
   
Stockholder’s
 
   
Shares
   
Value
   
Capital
   
Income (Loss)
   
(Deficit)
   
Equity
 
            (Dollars in thousands)  
Balance at December 31, 2006
    9,615     $ 96     $ 492,812     $ 562     $ 21,149     $ 514,619  
Redemption of common stock
    (3,257 )     (32 )     (166,991 )     -       -       (167,023 )
Equity contribution from parent
    -       -       101,249       -       -       101,249  
Adoption of amendment to GAAP regarding uncertain tax positions
    -       -       -       -       684       684  
Income taxes on goodwill adjustment
    -       -       250       -       -       250  
Net earnings
    -       -       -       -       18,408       18,408  
Total other comprehensive income
    -       -       -       261       -       261  
Dividends on common stock
    -       -       -       -       (35,000 )     (35,000 )
Balance at December 31, 2007
    6,358       64       427,320       823       5,241       433,448  
Net earnings (loss)
    -       -       -       -       (8,793 )     (8,793 )
Total other comprehensive income (loss)
    -       -       -       (965 )     -       (965 )
Balance at December 31, 2008
    6,358       64       427,320       (142 )     (3,552 )     423,690  
Equity contribution from parent
    -       -       25,206       -       -       25,206  
Net earnings
    -       -       -       -       12,166       12,166  
Total other comprehensive income
    -       -       -       68       -       68  
Dividends on common stock
    -       -       (9,339 )     -       -       (9,339 )
Balance at December 31, 2009
    6,358     $ 64     $ 443,187     $ (74 )   $ 8,614     $ 451,791  
                                                 

The accompanying notes, as they relate to TNMP, are an integral part of these financial statements.


 
 
B-29

 

TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME (LOSS)

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
                   
Net Earnings (Loss)
  $ 12,166     $ (8,793 )   $ 18,408  
                         
Other Comprehensive Income (Loss):
                       
                         
Pension liability adjustment, net of income
                       
tax (expense) benefit of $32, $520, and $(161)
    (57 )     (965 )     261  
                         
Fair Value Adjustment for Designated Cash Flow Hedge:
                       
  Change in fair value, net of income tax (expense)
                       
benefit of $182, $0, and $0
    (329 )     -       -  
  Reclassification adjustment for (gains) losses included in net earnings (loss), net of income tax
                       
expense (benefit) of $(252), $0, and $0
    454       -       -  
                         
Total Other Comprehensive Income (Loss)
    68       (965 )     261  
                         
Comprehensive Income (Loss)
  $ 12,234     $ (9,758 )   $ 18,669  

The accompanying notes, as they relate to TNMP, are an integral part of these financial statements.



 
 
B-30

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


(1)
Summary of the Business and Significant Accounting Policies

Nature of Business

    PNMR is an investor-owned holding company of energy and energy-related businesses.  PNMR’s primary subsidiaries are PNM, TNMP, and First Choice.  PNM is a public utility with regulated operations primarily engaged in the generation, transmission and distribution of electricity and, through January 29, 2009, the transmission, distribution and sale of natural gas.  As described in Note 2, PNM completed the sale of its natural gas operations on January 30, 2009.  PNM began service to TNMP’s New Mexico customers effective January 1, 2007.  TNMP and First Choice are wholly owned subsidiaries of TNP, which is a holding company that is wholly owned by PNMR.  TNMP provides regulated transmission and distribution services in Texas.  First Choice is a competitive retail electric provider operating in Texas.  PNMR owns 50% of Optim Energy (formerly EnergyCo), which is focused on unregulated electric operations, principally within the areas of Texas covered by ERCOT, including the development, operation and ownership of diverse generation assets and wholesale marketing.  PNMR’s common stock trades on the New York Stock Exchange under the symbol PNM.

Financial Statement Preparation and Presentation

The preparation of financial statements in conformity with accounting principles generally accepted in the United States requires management to make estimates and assumptions that affect the reported amounts of assets and liabilities, disclosure of contingent assets and liabilities at the date of the financial statements, and the reported amounts of revenues and expenses during the reporting period.  Actual results could ultimately differ from those estimated.

The Notes to Consolidated Financial Statements include disclosures for PNMR, PNM, and TNMP.  For discussion purposes, this report will use the term “Company” when discussing matters of common applicability to PNMR, PNM and TNMP.  Discussions regarding only PNMR, PNM or TNMP will be indicated as such.

Certain amounts in the 2008 and 2007 Consolidated Financial Statements and Notes thereto have been reclassified to conform to the 2009 financial statement presentation.  At December 31, 2007, PNM Gas, a segment of PNM, became classified as held for sale and is shown as discontinued operations for all periods presented.  See Note 2 and Note 23.

GAAP defines subsequent events as events or transactions that occur after the balance sheet date but before financial statements are issued or are available to be issued.  Based on their nature, magnitude, and timing, certain subsequent events may be required to be reflected at the balance sheet date and/or required to be disclosed in the financial statements.  The Company has evaluated subsequent events as required by GAAP.

Principles of Consolidation

The Consolidated Financial Statements of each of PNMR, PNM, and TNMP include their accounts and those of subsidiaries in which that entity owns a majority voting interest.  PNMR’s primary subsidiaries are PNM, TNMP, First Choice and, through May 31, 2007, Altura.  PNM consolidates the PVNGS Capital Trust and Valencia.  PNM owns undivided interests in several jointly-owned power plants and records its pro-rata share of the assets, liabilities and expenses for those plants.

PNMR shared services’ administrative and general expenses, which represent costs that are primarily driven by corporate level activities, are charged to the business segments, including Optim Energy.  These services are billed at cost, except for Optim Energy, which includes a profit element.  Other significant intercompany transactions between PNMR, PNM, and TNMP include energy purchases and sales, transmission and distribution services, lease payments, dividends paid on common stock, and interest paid by PVNGS Capital Trust to PNM.  All intercompany transactions and balances have been eliminated.  See Note 20.


 
 
B-31

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


Accounting for the Effects of Certain Types of Regulation

The Company maintains its accounting records in accordance with the uniform system of accounts prescribed by FERC and adopted by the NMPRC and PUCT.

Certain of the Company's operations are regulated by the NMPRC, PUCT and FERC and the provisions of GAAP for rate-regulated enterprises are applied to its regulated operations. Regulators may assign costs to accounting periods that differ from accounting methods applied by nonregulated utilities.  When it is probable that regulators will permit recovery of costs through future rates, costs are deferred as regulatory assets that otherwise would be expensed.  Likewise, regulatory liabilities are recognized when it is probable that regulators will require refunds through future rates or when revenue is collected for expenditures that have not yet been incurred.  Regulatory assets and liabilities are amortized into earnings over the authorized recovery period.  Accordingly, the Company has deferred certain costs and recorded certain liabilities pursuant to the rate actions of FERC, the NMPRC and the PUCT.  Information on “regulatory assets” and “regulatory liabilities” is contained in Note 4.

Cash and Cash Equivalents

    Investments in highly liquid investments with original maturities of three months or less at the date of purchase are considered cash equivalents.

Utility Plant

Utility plant is stated at cost, which includes capitalized payroll-related costs such as taxes, pension and other fringe benefits, administrative costs and an allowance for funds used during construction where authorized by rate regulation.

Repairs, including major maintenance activities, and minor replacements of property are expensed when incurred, except as required by regulators for ratemaking purposes.  Major replacements are charged to utility plant.  Gains or losses resulting from retirements or other dispositions of regulated property in the normal course of business are credited or charged to the accumulated provision for depreciation.

Allowance for Funds Used During Construction

As provided by the FERC uniform systems of accounts, an allowance for funds used during construction is charged to utility plant for construction projects included in rate base.  This allowance is a non-cash item designed to enable a utility to capitalize financing costs during periods of construction of property subject to rate regulation.  It represents the cost of borrowed funds (allowance for borrowed funds used during construction) and a return on other funds (allowance for equity funds used during construction).

In 2009, 2008, and 2007, PNM recorded $8.0 million, $7.9 million, and $7.7 million of allowance for funds used during construction on certain projects and TNMP recorded $1.1 million, $1.0 million, and $0.4 million.

Capitalized Interest

PNMR capitalizes interest on its construction projects and major computer software projects not subject to the computation of an allowance for funds used during construction.  Interest was capitalized at the overall weighted average borrowing rate of 6.9%, 6.5%, and 6.0% for 2009, 2008, and 2007.  PNMR’s capitalized interest was $0.7 million, $0.8 million, and $4.1 million in 2009, 2008, and 2007; PNM’s was $0.2 million, $0.5 million, and $3.7 million; and TNMP’s was zero in 2009 and less than $0.1 million in 2008 and 2007.


 
 
B-32

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


Carrying Charges on Stranded Costs

TNMP’s estimate of allowable carrying charges on stranded costs that it may recover from its transmission and distribution customers is based on a Texas Supreme Court ruling, and the PUCT’s application of that ruling.

Materials, Supplies, Fuel Stock, and Natural Gas Stored

Materials and supplies relate to transmission, distribution and generating assets.  Materials and supplies are charged to inventory when purchased and are expensed or capitalized as appropriate when issued.  Materials and supplies are valued using an average costing method.  Obsolete materials and supplies are expensed when identified.

Natural gas in underground storage was valued using a weighted average method.  Withdrawals were charged to sales service customers through the PGAC.

Coal is valued using a rolling weighted average costing method that is updated based on the current period cost per ton.  Periodic aerial surveys are performed on the coal piles and adjustments are made.  In addition to coal delivered and included in inventory, PNM prepays the SJGS coal supplier for coal mined but not yet delivered.  At December 31, 2009 and 2008, prepayments for coal amounted to $32.1 million and $30.7 million

    Inventories consisted of the following at December 31:

   
PNMR
   
PNM
   
TNMP
 
   
2009
   
2008
   
2009
   
2008
   
2009
   
2008
 
   
(In thousands)
 
                                     
Coal
  $ 15,079     $ 16,884     $ 15,079     $ 16,884     $ -     $ -  
Gas in underground storage
    -       9,886       -       9,886       -       -  
Materials and supplies
    35,552       35,362       32,710       33,219       2,591       1,625  
      50,631       62,132       47,789       59,989       2,591       1,625  
Discontinued operations
    -       12,735       -       12,735       -       -  
Continuing operations
  $ 50,631     $ 49,397     $ 47,789     $ 47,254     $ 2,591     $ 1,625  

Investments

In 1985 and 1986, PNM entered into eleven operating leases for interests in certain PVNGS generation facilities (see Note 7).  The remaining 10.3% and 10.15% lessor notes that were issued by the owners of the assets subject to these leases were subsequently purchased by and are now held by the PVNGS Capital Trust, which is consolidated by PNM.  Eight leases continue and are classified as operating leases.  The PVNGS Capital Trust intends to hold the lessor notes until such notes mature.  Similarly, in 1985, PNM entered into two operating leases for the EIP transmission line for which the owners had issued lessor notes.  In 2003, PNM acquired a 60% ownership interest in the EIP, collapsing the lease relating to it, and in 2004 purchased the outstanding lessor note relating to the remaining 40% interest.  The remaining EIP lessor note bears interest at 10.25%, matures in 2012, and is carried on the Consolidated Balance Sheet in other investments at $6.7 million and $8.6 million as of December 31, 2009 and 2008.  Both the PVNGS and EIP lessor notes are carried at amortized cost.

The Company’s other investments, including the NDT, are primarily comprised of United States, state, and municipal government obligations and corporate securities.  All investments are held in the Company’s name and are in the custody of major financial institutions.  The specific identification method is used to determine the cost of securities disposed of, with realized gains and losses reflected in other income and deductions.  At December 31, 2009 and 2008, substantially all of these investments were classified as available for sale.  PNM holds investment securities in the NDT.  PNM evaluates these investment securities for impairment on an on-going basis.  Since third party investment managers have sole discretion over the purchase and sales of the NDT securities, PNM records a
 
 
B-33

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

realized loss as an impairment for any security that has a market value that is less than cost at the end of each quarter.  For the years ended December 31, 2009, 2008 and 2007, PNM recorded impairment losses on securities held in the nuclear decommissioning trust of $8.1 million, $12.3 million, and $1.8 million.  No gains or losses are deferred as regulatory assets or liabilities.  Unrealized gains on these investments are included in other comprehensive income, net of any related tax effect.

Investment in Optim Energy (formerly known as EnergyCo)

 PNMR accounts for its investment in Optim Energy using the equity method of accounting because PNMR’s ownership interest results in significant influence, but not control, over Optim Energy and its operations.  PNMR records as income its percentage share of earnings or loss of Optim Energy and carries its investment at cost, adjusted for its share of undistributed earnings or losses.  The difference between PNMR’s book value of its investment in Optim Energy and its proportionate share of Optim Energy’s equity is being amortized into results of operations over the useful lives of the underlying assets and contractual periods of the liabilities that resulted in the difference. See Note 22.

Goodwill and Other Intangible Assets

Under the provisions of GAAP, the Company does not amortize goodwill.  Certain intangible assets are amortized over their estimated useful lives.  Goodwill and non-amortizable other intangible assets are evaluated for impairment annually, or more frequently if events and circumstances indicate that the goodwill and intangible assets might be impaired.  Amortizable other intangible assets are amortized over the shorter of their economic or legal lives and are evaluated for impairment when events and circumstances indicate that the assets might be impaired.  Impairments recorded in 2008 are discussed in Note 25.

Asset Impairment

Tangible long-lived assets are evaluated in relation to the future undiscounted cash flows to assess recoverability when events and circumstances indicate that the assets might be impaired.  Impairment testing of power generation assets excluded from jurisdictional rates is performed periodically in response to changes in market conditions.

Revenue Recognition

    First Choice, PNM and TNMP record electric and gas operating revenues, as applicable, in the period of delivery, which includes estimated amounts for service rendered but unbilled at the end of each accounting period.

    The determination of the energy sales by PNM, TNMP and First Choice to individual customers is based on the reading of their meters, which occurs on a systematic basis throughout the month.  At the end of each month, amounts of energy delivered to customers since the date of the last meter reading and the corresponding unbilled revenue are estimated.  Unbilled electric revenue is estimated based on the daily generation volumes, estimated customer usage by class, weather factors, line losses and applicable customer rates based on regression analyses reflecting historical trends and experience.

    PNM’s gas operations, which were sold on January 30, 2009 and are reflected as discontinued operations, purchased gas on behalf of its end-use sales-service customers while other marketers or producers purchased gas on behalf of their end-use transportation-service customers.  PNM collected a cost of service revenue for the transportation, delivery, and customer service provided to all on-system end-use customers.  Cost of service tariffs were set by the NMPRC while gas commodity rates were subject to the terms of the PGAC with oversight provided by the NMPRC.

    PNM’s wholesale electricity sales are recorded as operating revenues and the wholesale electricity purchases are recorded as costs of energy sold.  In accordance with GAAP, derivative contracts that are net settled or “booked-out” are recorded net in earnings.  A book-out is the planned or unplanned netting of off-setting purchase and sale
 
 
B-34

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

transactions.  A book-out is a transmission mechanism to reduce congestion on the transmission system or administrative burden (see further discussion below in Derivatives).  For accounting purposes, a book-out is the recording of net revenues upon the settlement of a derivative contract.

    Unrealized gains and losses on contracts that do not qualify for the normal purchases or normal sales exception or are not designated for hedge accounting are classified as trading transactions or economic hedges.  Trading transactions are defined as derivative instruments used to take advantage of existing market opportunities.  Changes in the fair value of trading transactions are reflected on a net basis in operating revenues.  The Company stopped entering into speculative trading transactions during 2008.  Economic hedges are defined as derivative instruments, including long-term power agreements, used to hedge generation assets and purchased power costs.  Changes in the fair value of economic hedges are reflected in results of operations, with changes related to economic hedges on sales included in operating revenues and changes related to economic hedges on purchases included in cost of energy sold.

Depreciation and Amortization

PNM’s provision for depreciation and amortization of utility plant, other than nuclear fuel, is based upon straight-line rates approved by the NMPRC.  Nuclear fuel is based on units-of-production.  TNMP’s provision for depreciation and amortization of utility plant is based upon straight-line rates approved by the PUCT.  Depreciation of non-utility property is computed based on the straight-line method.  The provision for depreciation of certain equipment is allocated between depreciation expense and construction projects based on the use of the equipment.  Average rates used are as follows:

 
2009
 
2008
 
2007
           
PNM
         
Electric plant
2.31%
 
2.35%
 
2.42%
Gas plant (see Note 2)
-
 
-
 
2.82%
Common, intangible, and general plant
4.29%
 
4.24%
 
6.32%
TNMP
3.44%
 
3.44%
 
3.48%

Amortization of Debt Acquisition Costs

Discount, premium and expense related to the issuance of long-term debt are amortized over the lives of the respective issues.  Gains and losses incurred upon the early retirement of long-term debt are recognized in other income or deductions, except for amounts attributable to NMPRC or PUCT regulation, which are amortized over the lives of the respective issues.

Derivatives

The Company records derivative instruments in the balance sheet as either an asset or liability measured at their fair value.  GAAP requires that changes in the derivatives’ fair value be recognized currently in earnings unless specific hedge accounting or normal purchase and sale criteria are met.  Special accounting for qualifying hedges allows derivative gains and losses to offset related change in value of the hedged item in the statement of earnings, and requires that a company must formally document, designate, and assess the effectiveness of transactions that receive hedge accounting.  GAAP provides that the effective portion of the gain or loss on a derivative instrument designated and qualifying as a cash flow hedging instrument be reported as a component of AOCI and be reclassified into earnings in the period during which the hedged forecasted transaction affects earnings.  The results of hedge ineffectiveness and the portion of the change in fair value of a derivative that an entity has chosen to exclude from hedge effectiveness are required to be presented in current earnings.  See Note 8.

The Company treats all forward electric purchases and sales contracts subject to unplanned netting or book-out by the transmission provider as derivative instruments subject to mark-to-market accounting, unless the contract
 
 
 
B-35

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

qualifies for the normal exception by meeting the definition of a capacity contract. Under this definition, the contract cannot permit net settlement, the seller must have the resources to serve the contract and the buyer must be a load serving entity.

    In addition, all energy contracts held for trading purposes are presented on a net margin basis in the statement of earnings.  Energy contracts that do not meet the definition of a derivative are recognized in current earnings and are not marked to market.

GAAP gives guidance on whether realized gains and losses on derivative contracts not held for trading purposes should be reported on a net or gross basis and concludes such classification is a matter of judgment that depends on the relevant facts and circumstances.  PNM nets all realized gains and losses on derivative transactions that do not physically deliver and that are offset by similar transactions during settlement.  For the years ended December 31, 2009, 2008, and 2007, wholesale purchases of $2.8 million, $12.6 million, and $122.0 million were netted with electric revenues in the Consolidated Statements of Earnings (Loss).

Decommissioning Costs

PNM owns and leases nuclear and fossil-fuel generating facilities.  In accordance with GAAP, PNM is only required to recognize and measure decommissioning liabilities for tangible long-lived assets for which a legal obligation exists.  Nuclear decommissioning costs and related accruals are based on site-specific estimates of the costs for removing all radioactive and other structures at PVNGS and are dependent upon numerous assumptions.  PNM’s accruals for PVNGS Units 1, 2 and 3 have been made based on such estimates, the guidelines of the NRC and the probability of a license extension.  PVNGS Unit 3 is excluded from PNM’s retail rates while PVNGS Units 1 and 2 are included.  PNM collects a provision for ultimate decommissioning of PVNGS Units 1 and 2 and its fossil-fueled generation facilities in its rates and recognizes a corresponding expense and liability for these amounts.  See Note 15.

In connection with both the SJGS coal agreement and the Four Corners fuel agreement, the owners are required to reimburse the mining companies for the cost of contemporaneous reclamation as well as the costs for final reclamation of the coal mines.  The reclamation costs are based on site-specific studies that estimate the costs to be incurred in the future and are dependent upon numerous assumptions. PNM considers the contemporaneous reclamation costs part of the cost of its delivered coal costs.  See Note 16 for a discussion of the final reclamation costs.

Pension and Other Postretirement Benefits

See Note 12 for a discussion of pension and postretirement benefits expense, including a discussion of the actuarial assumptions.

Stock-Based Compensation

See Note 13 for a discussion of stock-based compensation expense.

Income Taxes

Income taxes are accounted for using the asset and liability method for accounting for income taxes.  Deferred tax assets and liabilities are recognized for the estimated future tax consequences attributable to differences between the financial statement carrying value of existing assets and liabilities and their respective tax basis.  Current NMPRC and PUCT approved rates include the tax effects of the majority of these differences.  GAAP requires that rate-regulated enterprises record deferred income taxes for temporary differences accorded flow-through treatment at the direction of a regulatory commission.  The resulting deferred tax assets and liabilities are recorded at the expected cash flow to be reflected in future rates.  Because the NMPRC and the PUCT have consistently permitted the recovery of tax effects previously flowed-through earnings, the Company has established regulatory liabilities and assets offsetting such deferred tax assets and liabilities.  Items accorded flow-through
 
 
 
B-36

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

treatment under rate orders, deferred income taxes and the future ratemaking effects of such taxes, as well as corresponding regulatory assets and liabilities, are recorded in the financial statements.

The Company recognizes only the impact of tax positions that, based on their merits, are more likely than not to be sustained upon an IRS audit. See Note 11.

Excise Taxes

The Company pays certain fees or taxes which are either considered to be an excise tax or similar to an excise tax.  Substantially all of these taxes are recorded on a net basis in the Consolidated Statements of Earnings.

 (2)
Acquisitions, Dispositions and Impairments

PNM Gas Sale

On January 12, 2008, PNM reached a definitive agreement to sell its natural gas operations, which comprised the PNM Gas segment, to NMGC, a subsidiary of Continental, for $620.0 million in cash, subject to adjustment based on the actual level of working capital at closing. PNM received an additional $32.9 million related to working capital true-ups. In a separate transaction conditioned upon the sale of the natural gas operations, PNMR proposed to acquire CRHC, Continental's regulated Texas electric transmission and distribution business, for $202.5 million in cash. On July 22, 2008, PNMR and Continental agreed to terminate the agreement for the acquisition of CRHC.  Under the termination agreement, Continental agreed to pay PNMR $15.0 million upon the closing of the PNM Gas transaction.  PNM completed the sale of PNM Gas on January 30, 2009 and recognized a gain of $65.3 million, after income taxes of $33.1 million, in 2009, which is included in discontinued operations on the Consolidated Statements of Earnings (Loss).  This gain reflects the reduction for the increase in the PBO of the PNM pension plan related to the retirement of employees transferred to NMGC.  See Note 12.  PNMR recognized an additional pre-tax gain of $15.0 million ($9.1 million after income taxes) due to the CRHC termination payment, which is included in other income on the Consolidated Statements of Earnings (Loss).  In connection with the sale, PNM retained obligations under the frozen PNM pension and executive retirement plans for employees transferred to NMGC.  PNM had a regulatory asset related to these plans, which was removed from regulatory assets on the date of the sale and transferred to AOCI. The after-tax charge to AOCI was $64.8 million.  PNM also retained obligations for certain contingent liabilities that existed at the date of sale.  PNM recognized $5.4 million in expense related to these liabilities in 2009, which is included in discontinued operations on the Consolidated Statements of Earnings (Loss).

PNM used proceeds from the sale to retire short-term debt and paid a dividend of $220.0 million to PNMR. The remaining funds were used to pay income taxes on the gain from the sale.  PNMR used the dividend from PNM and the $15.0 million from Continental to retire debt. There were no material prior relationships between the PNMR and Continental parties other than in respect of the transactions described herein. PNM and PNMR Services Company provided certain corporate administrative and customer service support at cost to NMGC under a transition services agreement. The agreement term began January 30, 2009 and terminated in July 2009 with the exception of shared meter reading services, which will continue through 2010. See Note 23 for financial information concerning PNM Gas, which is classified as discontinued operations in the accompanying financial statements.

Twin Oaks

On April 18, 2006, PNMR’s wholly owned subsidiary, Altura, purchased the Twin Oaks business, which included a 305 MW coal-fired power plant located 150 miles south of Dallas, Texas for $480.0 million in cash plus the assumption of contracts and liabilities.  Effective June 1, 2007, PNMR contributed Altura, including the Twin Oaks business, to Optim Energy.  See Note 22.  The results of Twin Oaks operations have been included in the Consolidated Financial Statements of PNMR from April 18, 2006 through May 31, 2007.  Beginning June 1, 2007, the Twin Oaks operations are included in Optim Energy, which is accounted for by PNMR using the equity method.

 
 
B-37

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


 The Twin Oaks purchase agreement included the development rights for a possible 600-megawatt expansion of the plant, which PNMR classified as an intangible asset with a value of $25.0 million at the date of acquisition.  PNMR reassessed this valuation as of April 1, 2007 and determined that the asset was impaired, resulting in a pre-tax loss of $3.4 million, which was recorded in energy production costs.  In 2008, Optim Energy made a strategic decision not to pursue the Twin Oaks expansion and wrote off the development rights as an impairment of intangible assets.

As part of the acquisition of Twin Oaks, PNMR determined the fair value of two contractual obligations to sell power.  The first contract obligated PNMR to sell power through September 2007 at which time the second contract began and extends for three years.  In comparing the pricing terms of the contractual obligations against the forward price of electricity in the relevant market, PNMR concluded that the contracts were below market.  In accordance with GAAP, the contracts were recorded at fair value to be amortized as an increase in operating revenue over the contract periods.  The amortization matches the difference between the forward price curve and the contractual obligations for each month in accordance with the contract as of the acquisition date.  For the first contract, $94.9 million was recorded in other current liabilities and $52.4 million was recorded in other deferred credits for a total of $147.3 million.  For the second contract, $29.6 million was recorded in other deferred credits.  As of May 31, 2007, PNMR had amortized $105.9 million for the first contract and nothing for the second contract.

TNMP – New Mexico

In connection with the 2005 acquisition of TNP and its principal subsidiaries, TNMP and First Choice, the NMPRC stipulated that all TNMP’s New Mexico operations would transfer to the ownership of PNM.  This transfer took place on January 1, 2007 when TNMP transferred its New Mexico operational assets and liabilities to PNMR through redemption of TNMP’s common stock.  PNMR contemporaneously contributed the TNMP New Mexico operational assets and liabilities to PNM.

Due to the fact the net assets were distributed to TNMP’s parent, PNMR, the assets and liabilities were considered “held and used” up until the date of transfer.  No gain or loss or impairments were recognized on the disposition due to the fact the transfer was among entities under common control.  Furthermore, the TNMP New Mexico operations are subject to traditional rate of return regulation.  Subsequent to the transfer, the NMPRC regulates these operations in the same manner as prior to the transfer.  Under GAAP for rate-regulated enterprises, the assets and liabilities were recorded by PNM at TNMP’s carrying amounts, which represent their fair value within the regulatory environment.

The asset transfer did not meet the definition of a “change in reporting entity” since PNM’s financial statement composition remained unchanged after the transfer.  The assets and operations transferred from TNMP are in the same line of business as PNM and are immaterial to both PNM’s assets and net earnings.  Information concerning the TNMP New Mexico assets and liabilities transferred to PNM is set forth on their Consolidated Statements of Cash Flows.

Other

See Note 25, for a discussion of impairments of intangible assets recorded in 2008.

In 2006, the NMPRC approved a stipulation to allow PNM to convert its 141-megawatt combustion turbine Afton Generating Station to a combined cycle plant and bring Afton into retail rates in its next rate case, which was anticipated to be effective January 1, 2008.   The Afton costs, including the costs of conversion, allowable for ratemaking were stipulated to be the lower of the actual cost or $187.6 million. The combined cycle plant was declared commercial on October 12, 2007 and was included  in PNM’s retail rates beginning in May 2008.  During the final start-up stages, problems were encountered that required piping modifications and significant problems were encountered with the control software and interfaces.  Furthermore, the new turbine and generator experienced problems that required inspection of all five bearings.  The combination of these issues caused delays and increased costs.  The total Afton costs exceeded the stipulated maximum amount and the excess will not be recoverable in
 
 
B-38

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

rates. Therefore, the Afton asset has been impaired, as defined under GAAP.   A pre-tax impairment charge of $19.5 million ($11.8 million after income taxes) was recorded in 2007 by PNM in energy production costs.

    On June 29, 2007, a wholly-owned subsidiary of PNMR purchased 100% of a trust that owns a 2.27% undivided interest, representing 29.8 MW, in PVNGS Unit 2 and a 0.76% undivided interest in certain PVNGS common facilities, as well as a lease under which such facilities are leased to PNM.  The beneficial interest in the trust was purchased for $44.0 million in cash and the assumption of $41.2 million in long-term debt payable to PVNGS Capital Trust.  This long-term debt offsets a portion of the investment in PVNGS lessor notes and is eliminated in PNMR’s consolidated financial statements.  The funds for the purchase were provided by PNMR.  The lease remained in effect and the transaction had no impact on PNM’s consolidated financial statements.  As described in Note 17, the Resource Stipulation allowed the Unit 2 interest to be transferred to PNM and the acquisition costs to be recovered in PNM’s rates beginning with the 2008 Electric Rate Case.  In July 2009, PNM purchased the trust from the other PNMR subsidiary for $39.1 million in cash.  The purchase price was equal to the book value of the underlying assets less deferred taxes and miscellaneous accruals. The other PNMR subsidiary paid a dividend of that same amount to PNMR.  PNMR then made an equity contribution of that amount to PNM.  The trust had $32.0 million of debt owing to the PVNGS Capital Trust, which is consolidated by PNM.  The transfer had no impact on the financial statements of PNMR. The impacts on the financial statements of PNM were to increase net plant in service by $73.7 million, increase common stock by $39.1 million, reduce investment in the PVNGS lessor notes by $32.0 million, reflecting the elimination of the debt owed by the trust to the PVNGS Capital Trust, and increase deferred income taxes and other accruals by $2.6 million.

(3)       Segment Information

The following segment presentation is based on the methodology that management uses for making operating decisions and assessing performance of its various business activities.  A reconciliation of the segment presentation to the GAAP financial statements is provided.

PNM Electric

PNM Electric includes the retail electric utility operations of PNM that are subject to traditional rate regulation by the NMPRC.  PNM Electric provides integrated electricity services that include the generation, transmission and distribution of electricity for retail electric customers in New Mexico as well as the sale of transmission to third parties.  PNM Electric also includes the generation and sale of electricity into the wholesale market.  This includes the asset optimization of PNM’s jurisdictional assets as well as the capacity excluded from retail rates.   FERC has jurisdiction over wholesale rates.

TNMP Electric

TNMP Electric is an electric utility operating in Texas. TNMP’s operations are subject to traditional rate regulation by the PUCT.  TNMP provides regulated transmission and distribution services in Texas under the TECA.

Through December 31, 2006, TNMP provided integrated electric services that included the transmission, distribution, purchase and sale of electricity to its New Mexico customers as well as transmission to third parties and to PNM.  Effective January 1, 2007 TNMP’s New Mexico business was transferred to PNM.  PNM was TNMP’s sole supplier for TNMP’s load in New Mexico prior to the transfer of assets to PNM.

PNM Gas

PNM Gas distributed natural gas to most of the major communities in New Mexico, subject to traditional rate regulation by the NMPRC.  The customer base of PNM Gas included both sales-service customers and transportation-service customers.  PNM Gas purchased natural gas in the open market and sold it at cost to its sales-service customers.  As a result, increases or decreases in gas revenues resulting from gas price fluctuations did not
 
 
B-39

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

impact gross margin or earnings.  As described in Note 2, PNM completed the sale of its gas operations on January 30, 2009.  PNM Gas is reported as discontinued operations in the accompanying financial statements and is not included in the segment information presented below.  Financial information regarding PNM Gas is presented in Note 23.

Altura

The Altura segment includes the results of Twin Oaks from the date of its acquisition by PNMR on April 18, 2006 until its contribution to Optim Energy as of June 1, 2007. See Note 2 and Note 22.

First Choice

First Choice is a certified retail electric provider operating in Texas, which allows it to provide electricity to residential, small commercial, and governmental customers.  Although First Choice is regulated in certain respects by the PUCT, it is not subject to traditional rate regulation.

Optim Energy

Upon the contribution of Altura to Optim Energy, Optim Energy became a separate segment for PNMR effective June 1, 2007.  PNMR’s investment in Optim Energy is held in the Corporate and Other segment and is accounted for using the equity method of accounting. Optim Energy’s revenues and expenses are not included in PNMR’s consolidated revenues and expenses or the following tables.  See Notes 2 and 22.

Corporate and Other

PNMR Services Company is included in the Corporate and Other segment.

 
 
B-40

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The following tables present summarized financial information for PNMR by operating segment. Excluding PNM Gas, which is presented as discontinued operations, PNM has only one operating segment.  TNMP operates in only one reportable segment.  Therefore, tabular segment information is not presented for PNM and TNMP.  Explanations for footnotes follow the tables.


PNMR SEGMENT INFORMATION
   
PNM
   
TNMP
   
First
   
Corporate
       
2009
 
Electric
   
Electric
   
Choice
   
and Other
   
Consolidated
 
               
(In thousands)
             
                               
Operating revenues
  $ 967,998     $ 151,294     $ 528,818     $ (366 )   $ 1,647,744  
Intersegment revenues
    11       41,338       -       (41,349 )     -  
Total revenues
    968,009       192,632       528,818       (41,715 )     1,647,744  
Cost of energy
    378,145       34,728       346,454       (41,338 )     717,989  
Gross margin
    589,864       157,904       182,364       (377 )     929,755  
Other operating expenses
    420,473       75,540       107,354       (13,503 )     589,864  
Depreciation and amortization
    92,140       37,262       1,809       16,738       147,949  
Operating income (loss)
    77,251       45,102       73,201       (3,612 )     191,942  
                                         
Interest income
    30,543       9       56       (2,219 )     28,389  
Equity in net earnings (loss) of Optim Energy
    -       -       -       (30,145 )     (30,145 )
Other income (deductions)
    6,891       2,860       (438 )     17,457       26,770  
Net interest charges
    (69,058 )     (27,820 )     (2,782 )     (22,545 )     (122,205 )
                                         
Earnings (loss) before income taxes
    45,627       20,151       70,037       (41,064 )     94,751  
                                         
Income taxes (benefit)
    13,726       7,985       25,622       (18,515 )     28,818  
Earnings (loss) from continuing operations
    31,901       12,166       44,415       (22,549 )     65,933  
Valencia non-controlling interest
    (11,890 )     -       -       -       (11,890 )
Subsidiary preferred stock dividends
    (528 )     -       -       -       (528 )
                                         
Segment earnings (loss) from continuing
                                       
 operations attributable to PNMR
  $ 19,483     $ 12,166     $ 44,415     $ (22,549 )   $ 53,515  
                                         
Gross property additions (1) (2)
  $ 253,335     $ 53,063     $ 863     $ 16,462     $ 284,597  
At December 31, 2009:
                                       
Total Assets
  $ 3,775,166     $ 1,009,055     $ 197,062     $ 378,638     $ 5,359,921  
Goodwill
  $ 51,632     $ 226,665     $ 43,013     $ -     $ 321,310  


 
 
B-41

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007



 
   
PNM
   
TNMP
   
First
   
Corporate
       
2008
 
Electric
   
Electric
   
Choice
   
and Other
   
Consolidated
 
               
(In thousands)
             
                               
Operating revenues
  $ 1,242,837     $ 135,068     $ 582,224     $ (607 )   $ 1,959,522  
Intersegment revenues
    105       55,214       -       (55,319 )     -  
Total revenues
    1,242,942       190,282       582,224       (55,926 )     1,959,522  
Cost of energy
    698,054       32,671       564,326       (55,197 )     1,239,854  
Gross margin
    544,888       157,611       17,898       (729 )     719,668  
Other operating expenses
    465,681       101,466       238,386       (413 )     805,120  
Depreciation and amortization
    85,724       38,695       2,360       17,583       144,362  
Operating income (loss)
    (6,517 )     17,450       (222,848 )     (17,899 )     (229,814 )
                                         
Interest income
    24,674       63       1,587       (2,228 )     24,096  
Equity in net earnings (loss) of Optim Energy
    -       -       -       (29,687 )     (29,687 )
Other income (deductions)
    (17,613 )     3,162       112       (5,682 )     (20,021 )
Net interest charges
    (69,868 )     (18,340 )     (3,985 )     (40,762 )     (132,955 )
                                         
Earnings (loss) before income taxes
    (69,324 )     2,335       (225,134 )     (96,258 )     (388,381 )
                                         
Income taxes (benefit)
    (10,029 )     11,128       (47,561 )     (44,354 )     (90,816 )
Earnings (loss) from continuing operations
    (59,295 )     (8,793 )     (177,573 )     (51,904 )     (297,565 )
Valencia non-controlling interest
    (7,179 )     -       -       -       (7,179 )
Subsidiary preferred stock dividends
    (528 )     -       -       -       (528 )
                                         
Segment earnings (loss) from continuing
                                       
 operations attributable to PNMR
  $ (67,002 )   $ (8,793 )   $ (177,573 )   $ (51,904 )   $ (305,272 )
                                         
Gross property additions (1)
  $ 240,262     $ 51,116     $ 3,872     $ 12,876     $ 308,126  
At December 31, 2008:
                                       
Total Assets (3)
  $ 3,758,834     $ 971,998     $ 253,048     $ 494,201     $ 5,478,081  
Goodwill
  $ 51,632     $ 226,665     $ 43,013     $ -     $ 321,310  


 
 
B-42

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


2007
 
PNM Electric
   
TNMP Electric
   
Altura
   
First Choice
   
Corporate
and Other
   
Consolidated
 
   
(In thousands)
 
Operating revenues
  $ 1,136,974     $ 109,818     $ 65,395     $ 600,617     $ 1,225     $ 1 ,914,029  
Intersegment revenues
    -       70,603       -       78       (70,681 )     -  
Total revenues
    1,136,974       180,421       65,395       600,695       (69,456 )     1,914,029  
Cost of energy
    638,675       29,529       22,063       500,755       (69,497 )     1,121,525  
Gross margin
    498,299       150,892       43,332       99,940       41       792,504  
Other operating expenses
    381,105       67,821       18,636       57,262       6,943       531,767  
Depreciation and amortization
    83,223       30,401       7,684       1,881       12,506       135,695  
Operating income (loss)
    33,971       52,670       17,012       40,797       (19,408 )     125,042  
                                                 
Interest income
    41,655       85       146       2,137       (869 )     43,154  
Equity in net earnings of Optim Energy
    -       -       -       -       7,581       7,581  
Other income (deductions)
    11,647       1,468       1       (56 )     (5,570 )     7,490  
Net interest charges
    (52,662 )     (25,168 )     (8,523 )     (763 )     (33,039 )     (120,155 )
                                                 
Earnings (loss) before income taxes
    34,611       29,055       8,636       42,115       (51,305 )     63,112  
                                                 
Income taxes (benefit)
    11,220       10,647       3,419       14,929       (36,989 )     3,226  
                                                 
Earnings (loss) from continuing operations
    23,391       18,408       5,217       27,186       (14,316 )     59,886  
                                                 
Subsidiary preferred stock dividends
    (528 )     -       -       -       -       (528 )
                                                 
Segment earnings (loss) from continuing
                                               
  operations attributable to PNMR
  $ 22,863     $ 18,408     $ 5,217     $ 27,186     $ (14,316 )   $ 59,358  
                                                 
Gross property additions (1)
  $ 312,988     $ 42,725     $ 919     $ 184     $ 61,770     $ 418,586  
At December 31, 2007:
                                               
Total Assets (3)
  $ 3,456,800     $ 972,792     $ -     $ 367,838     $ 428,106     $ 5,225,536  
Goodwill
  $ 102,775     $ 261,121     $ -     $ 131,768     $ -     $ 495,664  

Footnote explanations for the above tables are as follows:

(1)  
Excludes gross property additions related to PNM Gas discontinued operations of $3,434, $36,825, and $39,154 for December 31, 2009, 2008, and 2007.
(2)  
Includes PNM’s purchase of an interest in PVNGS Unit 2 from another subsidiary of PNMR of $39,126.
(3)  
Excludes total assets related to PNM Gas discontinued operations of $669,901 and $646,600 at December 31, 2008 and 2007.

Major Customers

No individual customers accounted for more than 10% of the operating revenues of PNMR or PNM.  First Choice is a customer of TNMP and accounted for 21% of its operating revenues from continuing operations in 2009, 29% in 2008, and 39% in 2007.  One unaffiliated customer of TNMP accounted for 20% of its operating revenues from continuing operations in 2009, 22% in 2008, 18% in 2007.  Another unaffiliated customer of TNMP accounted for 13% of its operating revenues from continuing operations in 2009 and less than 10% in 2008 and 2007.

 
 
B-43

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


(4)
Regulatory Assets and Liabilities

Certain of the Company's operations are regulated by the NMPRC, PUCT and FERC and the provisions of GAAP for rate-regulated enterprises are applied to its regulated operations.  Regulatory assets represent probable future recovery of previously incurred costs, which will be collected from customers through the ratemaking process.  Regulatory liabilities represent probable future reductions in revenues associated with amounts that are to be credited to customers through the ratemaking process.  Regulatory assets and liabilities reflected in the Consolidated Balance Sheets are presented below.  On January 30, 2009, PNM completed the sale of its gas operations.  Upon the sale, the regulatory asset of $107.3 million for pension obligations not transferred to NMGC was removed from regulatory assets and charged, net of income taxes, to AOCI.   See Note 2 and Note 23.

PNMR

   
December 31,
 
   
2009
   
2008
 
Assets:
 
(In thousands)
 
Current:
           
Underground rate
  $ 255     $ 1,311  
Fuel and purchased power adjustment clause
    7,195       -  
Rate case expense
    26       230  
      7,476       1,541  
Non-Current:
               
Coal mine reclamation costs
    63,826       69,747  
Deferred income taxes
    57,159       74,902  
Financing costs
    26,449       28,155  
Pension and OPEB
    237,580       329,487  
Loss on reacquired debt
    6,569       11,706  
Stranded costs
    103,616       112,008  
Hurricane recovery costs
    17,707       -  
Rate case expenses
    5,398       2,480  
Other
    5,832       656  
      524,136       629,141  
Total regulatory assets
  $ 531,612     $ 630,682  
                 
Liabilities:
               
Current - other
  $ (908 )   $ (1,746 )
                 
Non-Current:
               
Cost of removal
    (269,864 )     (261,078 )
Deferred income taxes
    (14,220 )     (16,333 )
Asset retirement obligation
    (40,703 )     (40,929 )
SO2 credits
    (19,312 )     -  
Pension and OPEB
    (2,120 )     (1,577 )
Other
    (4,105 )     (7,258 )
      (350,324 )     (327,175 )
Total regulatory liabilities
  $ (351,232 )   $ (328,921 )


 
B-44

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


PNM

   
December 31,
 
   
2009
   
2008
 
   
(In thousands)
 
Assets:
           
Current:
           
Underground rate
  $ 255     $ 1,311  
Fuel and purchased power adjustment clause
    7,195       -  
Rate case expenses
    26       230  
      7,476       1,541  
Non-Current:
               
Coal mine reclamation costs
    63,826       69,747  
Deferred income taxes
    52,166       70,237  
Financing costs
    26,449       28,155  
Loss on reacquired debt
    6,569       11,706  
Pension and OPEB
    219,731       313,484  
Rate case expenses
    1,504       496  
Other
    4,886       656  
      375,131       494,481  
Total regulatory assets
  $ 382,607     $ 496,022  
                 
Liabilities:
               
Current - other
  $ (908 )   $ (1,746 )
                 
Non-Current:
               
Cost of removal
    (238,303 )     (229,733 )
Deferred income taxes
    (14,220 )     (16,333 )
Asset retirement obligation
    (40,703 )     (40,929 )
SO2 credits
    (19,312 )     -  
Other
    (3,677 )     (5,151 )
      (316,215 )     (292,146 )
Total regulatory liabilities
  $ (317,123 )   $ (293,892 )



 
B-45

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


TNMP

   
December 31,
 
   
2009
   
2008
 
   
(In thousands)
 
Assets:
           
Non-Current:
           
Stranded costs
  $ 103,616     $ 112,008  
Deferred income taxes
    4,993       4,665  
Pension and OPEB
    17,850       16,003  
Hurricane recovery costs
    17,707       -  
Rate case expenses
    3,893       1,984  
Other
    946       -  
Total regulatory assets
  $ 149,005     $ 134,660  
                 
Liabilities:
               
Non-Current:
               
Cost of removal
  $ (31,560 )   $ (31,345 )
Pension and OPEB
    (2,120 )     (1,577 )
Other
    (429 )     (2,106 )
Total regulatory liabilities
  $ (34,109 )   $ (35,028 )

The Company’s regulatory assets and regulatory liabilities are reflected in rates charged to customers or have been addressed in a regulatory proceeding.  The Company does not receive or pay a rate of return on the following regulatory assets and regulatory liabilities (and their remaining amortization periods):  coal mine reclamation costs (through 2020); deferred income taxes (over the remaining life of the taxable item, up to the remaining life of utility plant); financing costs (over the life of the related debt, through 2038); pension and OPEB costs (through 2033); asset retirement obligations (to be determined in a future regulatory proceeding); and SO2 credits (through April 2011).

The Company is permitted, under rate regulation, to accrue and record a regulatory liability for the estimated cost of removal and salvage associated with certain of its assets through depreciation expense.  Under GAAP, actuarial losses and prior service costs for pension plans are required to be recorded in AOCI; however, to the extent authorized for recovery through the regulatory process these amounts are recorded as regulatory assets or liabilities.  Based on prior regulatory approvals, the amortization of these amounts will be included in the Company’s rates.  See Note 17 for information related to TNMP’s stranded costs and 2009 regulatory decisions, which resulted in additions to regulatory assets and liabilities.

Based on a current evaluation of the various factors and conditions that are expected to impact future cost recovery, the Company believes that future recovery of its regulatory assets are probable.

(5)
Stockholders’ Equity

Common Stock and Equity Contributions

See Note 6 for details related to PNMR’s issuance of common stock.

As described in Note 2, the New Mexico customers of TNMP were transferred to PNM effective January 1, 2007.  In connection with the transfer, TNMP transferred those operations to TNP by redeeming a portion of its common stock.  TNP then transferred those operations to PNMR, which transferred them to PNM as an equity contribution.  PNMR also made cash equity contributions to PNM of $86.3 million, including the transaction relating to the transfer of an interest in PVNGS Unit 2 as described in Note 2, in 2009.  PNMR made an equity contribution to TNMP by forgiving intercompany borrowings of $25.2 million in 2009 and made a cash equity
 
B-46

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

contribution of $101.2 million in 2007.

Dividends on Common Stock

The declaration of common dividends by PNMR is dependent upon a number of factors including the ability of PNMR’s subsidiaries to pay dividends.  PNMR’s primary sources of dividends are its operating subsidiaries.

Following the sale of PNM Gas, PNM paid a dividend to PNMR of $220.0 million on February 5, 2009 and paid additional cash dividends of $79.7 million in 2009.  PNM paid cash dividends of $40.0 million to PNMR in 2008.  PNM did not pay any cash dividends to PNMR in 2007. TNMP paid cash dividends to PNMR of $9.3 million in 2009 and $35.0 million in 2007. TNMP did not pay any cash dividends to PNMR in 2008.

Each of the PNMR Facility, the PNM Facility, and the TNMP Revolving Credit Facility contain covenants that require the maintenance of debt-to-capital ratios of less than or equal to 65%.  For PNMR and PNM these ratios reflect the present value of payments under the PVNGS and EIP leases as debt.  The NMPRC has placed certain restrictions on the ability of PNM to pay dividends to PNMR, including the restriction that PNM cannot pay dividends that cause its debt rating to fall below investment grade.  The NMPRC provisions allow PNM to pay dividends from equity contributions previously made by PNMR and current earnings, determined on a rolling four quarter basis, without prior NMPRC approval.  The Federal Power Act also imposes certain restrictions on dividends by public utilities.  PNM also has other financial covenants that limit the transfer of assets, through dividends or other means, including a requirement to obtain approval of certain financial counterparties to transfer more than five percent of PNM’s assets.  As of December 31, 2009, none of the numerical tests would restrict the payment of dividends from the retained earnings of PNMR, PNM, or TNMP.  However, PNM would not be able to distribute amounts in excess of its retained earnings and TNMP would not be able to distribute amounts in excess of approximately $176 million without approval of regulators or financial counterparties.  Other PNMR subsidiaries have no restricted net assets.

In addition, the ability of PNMR to declare dividends is dependent upon the extent to which cash flows will support dividends, the availability of retained earnings, the financial circumstances and performance, the NMPRC’s and PUCT’s decisions in various regulatory cases currently pending and which may be docketed in the future, the effect of federal regulatory decisions, Congressional and legislative acts and economic conditions in the United States.  Conditions imposed by the NMPRC or PUCT, future growth plans and the related capital requirements and business considerations may also affect PNMR’s ability to pay dividends.

Preferred Stock

PNMR had no preferred stock outstanding prior to November 17, 2008, when it issued 477,800 shares of Series A convertible preferred stock in connection with the purchase obligation of the holder of PNMR’s private equity-linked units.  See Note 6.  The Series A convertible preferred stock is convertible into PNMR common stock in a ratio of 10 shares of common stock for each share of preferred stock.  The Series A convertible preferred stock is entitled to receive dividends equivalent to any dividends paid on PNMR common stock as if the preferred stock had been converted into common stock.  The Series A convertible preferred stock is entitled to vote on all matters voted upon by common stockholders, except for the election of the Board.  In the event of liquidation of PNMR, preferred holders would receive a preference of $0.10 per common share equivalent.  After that preference, common holders would receive an equivalent liquidation preference per share and all remaining distributions would be shared ratably between common and preferred holders using the number of shares of common stock into which the Series A convertible preferred stock is convertible.  The terms of the Series A convertible preferred stock result in it being substantially equivalent to common stock.  Therefore, for earnings per share purposes the number of common shares into which the Series A convertible preferred stock is convertible is included in the weighted average number of common shares outstanding for periods after the Series A convertible preferred stock was issued.  Similarly, dividends on the Series A convertible preferred stock are considered to be common dividends in the accompanying Consolidated Financial Statements.

 
 
B-47

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

PNM’s cumulative preferred shares outstanding bear dividends at 4.58% per annum.  PNM preferred stock does not have a mandatory redemption requirement but may be redeemed, at PNM’s option, at 102% of the stated value plus accrued dividends.  The holders of the PNM preferred stock are entitled to payment before the holders of
common stock in the event of any liquidation or dissolution or distribution of assets of PNM.  In addition, PNM’s preferred stock is not entitled to a sinking fund and cannot be converted into any other class of stock of PNM.

TNMP has no preferred stock outstanding.  The number of authorized shares of TNMP cumulative preferred stock is 1 million shares.

(6)
Financing

Impacts of Difficulties of Financial Institutions

Disruptions in the credit markets in 2008 and early 2009 had a significant adverse impact on a number of financial institutions, which resulted in certain institutions being restructured or formulating plans to be acquired by other financial institutions.  This includes some financial institutions that are lenders under the PNMR Facility, PNM Facility, and Term Loan Agreement (which was terminated effective January 30, 2009), which are described below.  Other than as described below, the flux in the banking industry has not impacted these credit agreements to date and the Company does not anticipate it will have a significant impact on TNMP’s 2009 Term Loan Agreement, the TNMP Revolving Credit Facility, the PNMR Facility or the PNM Facility, in each case prior to their expirations.

LBB was a lender under the PNMR Facility and the PNM Facility.  LBH, the parent of LBB, has filed for bankruptcy protection.  Subsequent to the bankruptcy filing by LBH, LBB declined to fund a borrowing request under the PNMR Facility amounting to $5.3 million. The PNMR Facility and the PNM Facility agreements contain procedures for substituting another financial institution to take the place of any lender who defaults under the agreements.  A replacement bank has taken the place of LBB under the PNM Facility.  PNMR is discussing with the participants in the PNMR Facility amending the PNMR Facility to remove LBB, which would reduce the total capacity under the PNMR Facility to $568.0 million.  PNMR does not believe amending the PNMR Facility to remove LBB or the LBH bankruptcy will have a significant impact on the liquidity provided by the PNMR Facility.

LBCS, another subsidiary of LBH, has also declared bankruptcy and was a counterparty to various energy transactions with First Choice and Optim Energy.  First Choice had no receivables from LBCS, but as a result of the bankruptcy, First Choice terminated its contract effective September 24, 2008 and recognized a $3.9 million loss as settled purchase power contracts.  These power supply contracts were replaced with other counterparties, which partially offset the $3.9 million loss.  Optim Energy had a receivable from LBCS, which has been written off.  PNMR’s equity share of the write off was $0.6 million.  The bankruptcy of LBCS is not expected to have a significant impact on future operations of the Company.

Financing Activities

On June 26, 2007, the City of Farmington, New Mexico issued $20.0 million of its PCRBs to finance or reimburse PNM for expenditures incurred in connection with pollution control equipment at the SJGS.  PNM is obligated to pay amounts equal to the principal and interest on the PCRBs.  In addition, PNM issued $20.0 million of senior unsecured notes to secure and guarantee the PCRBs. Both the PCRBs and the senior unsecured notes mature in 2037 and bear interest at 5.15%.

Effective June 15, 2007, TNMP redeemed $100.0 million of its 6.125% senior notes due 2008 at a redemption price of 100.5% of the principal amount redeemed, plus accrued interest. To facilitate the redemption, PNMR made a cash contribution, recorded as equity, of $101.2 million to TNP, which then made an equity contribution to TNMP in the same amount. On March 7, 2008, TNMP entered into a $150.0 million short-term bank loan agreement with two lenders.  TNMP borrowed $150.0 million under this agreement on April 9, 2008 and used the proceeds to redeem the remaining $148.9 million of its 6.125% senior unsecured notes prior to the maturity date of June 1, 2008.  The $150.0 million borrowing under this agreement was repaid in October 2008, through
 
B-48

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

borrowing $150.0 million under the TNMP Facility described under Short-term Debt below.
 
   On May 5, 2008, PNM entered into a $300.0 million unsecured delayed draw term loan facility (the “Term Loan Agreement”) with Merrill Lynch Bank USA, Morgan Stanley Senior Funding, Inc. and Wachovia Bank, National Association. The Term Loan Agreement allowed PNM to borrow up to $300.0 million.   The Term Loan Agreement provided that if PNM received net cash proceeds from the sale of certain debt securities or the sale of assets, the amount of the commitments under the Term Loan Agreement would be reduced.  As described below, on May 13, 2008, PNM completed the offering of $350.0 million aggregate principal amount of senior unsecured notes.  On May 28, 2008, PNM was notified that the lenders under the Term Loan Agreement had reduced their commitments to $150.0 million.  As provided by the Term Loan Agreement, upon the closing of the sale of PNM Gas described in Note 2, the Term Loan Agreement terminated.  No borrowings were made under the Term Loan Agreement.
 
On May 8, 2008, PNM entered into a $100.0 million unsecured letter of credit facility pursuant to a reimbursement agreement (as amended, the “Reimbursement Agreement”) with Deutsche Bank AG and Royal Bank of Canada.  The Reimbursement Agreement allowed PNM to obtain, from time to time, standby letters of credit up to the aggregate amount of $100.0 million at any time prior to April 30, 2009.  Upon the sale of PNM Gas on January 30, 2009, PNM voluntarily requested the termination of the Reimbursement Agreement.  No letters of credit were issued under this arrangement.
 
    On May 13, 2008, PNM issued $350.0 million aggregate principal amount of senior unsecured notes. The notes pay interest semi-annually at a rate of 7.95% per year, payable on May 15 and November 15 of each year, beginning November 15, 2008, and mature on May 15, 2018.
 
On May 15, 2008, TNMP entered into a credit agreement with eight lenders for the TNMP Facility, which had a stated maturity of May 13, 2009.  The TNMP Facility provided TNMP with a revolving credit facility for up to $200.0 million.  In connection with entering into the TNMP Facility, TNMP withdrew as a borrower under the PNMR Facility and is no longer a party under the PNMR Facility.   Upon entering into the TNMP Revolving Credit Facility described below, the TNMP Facility was terminated.
 
    On October 31, 2008, TNMP entered into a $100.0 million term loan credit agreement with two lenders (the “TNMP Bridge Facility”) to provide an additional source of funds to repay TNMP’s $167.7 million of senior unsecured notes that matured January 15, 2009.  On January 14, 2009, TNMP borrowed $100.0 million under the TNMP Bridge Facility.  On January 15, 2009, TNMP repaid the entire principal and interest due on the $167.7 million principal amount outstanding of 6.25% senior unsecured notes utilizing the proceeds from the TNMP Bridge Facility and inter-company borrowings from PNMR.
 
    PNM had $300.0 million aggregate principal amount of senior unsecured notes that matured in September 2008.  PNM repaid these notes by utilizing cash on hand and borrowing $240.0 million under the PNM Facility.
 
    PNMR previously issued 4,945,000 6.75% publicly held equity-linked units.  Each of these equity-linked units consisted of a purchase contract and a 5.0% undivided beneficial ownership interest in one of PNMR’s senior notes with a stated amount of $1,000, which corresponded to a $50.00 stated amount of PNMR’s senior notes. The senior notes were scheduled to mature in May 2010 (subject to the remarketing described below) and bore interest at a rate of 4.8% per year.  The purchase contracts entitled their holders to contract adjustment payments of 1.95% per year on the stated amount of $50.00.  Each purchase contract contained a mandatory obligation for the holder to purchase, and PNMR to sell, at a purchase price of $50.00 in cash, shares of PNMR’s common stock on or before May 16, 2008.  Generally, the number of shares each holder of the equity-linked units was obligated to purchase depended on the average closing price per share of PNMR’s common stock over a 20-day trading period ending on the third trading day immediately preceding May 16, 2008, with an adjusted maximum price of $32.08 per share and minimum price of $26.29 per share.  In accordance with the terms of the equity-linked units, the senior note components were remarketed on May 16, 2008.  The proceeds from the remarketed senior notes amounted to $247.3
 
B-49

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

million and were utilized by the holders of the equity-linked units to satisfy their obligations to purchase 9,403,412 shares of PNMR’s common stock for the same aggregate amount on May 16, 2008.  In connection with the remarketing, PNMR sold an additional $102.7 million of senior notes with the same terms for a total offering of $350.0 million.  The senior notes pay interest semi-annually at a rate of 9.25% per year, payable on May 15 and November 15 of each year, beginning November 15, 2008, and mature on May 15, 2015.

    PNMR also had outstanding 4,000,000 privately held 6.625% equity-linked units.  Each of these equity-linked units consisted of a purchase contract and a 2.5% undivided beneficial ownership interest in one of PNMR’s senior notes with a stated amount of $1,000, which corresponds to a $25.00 stated amount of PNMR’s senior notes.  The senior notes aggregating $100.0 million were scheduled to mature in August 2010 (subject to the remarketing described below) and bore interest at the annual rate of 5.1%.  The purchase contracts entitled the holder to quarterly contract adjustment payments of 1.525% per year on the stated amount of $25.00.  Each purchase contract contained a mandatory obligation for the holder to purchase, and PNMR to sell, at a purchase price of $25.00 in cash, shares of PNMR’s common stock (or PNMR preferred stock in a ratio of one preferred share for each 10 shares of common stock) aggregating $100.0 million on November 17, 2008.  Generally, the number of shares the holder was obligated to purchase depended on the average closing price per share of PNMR’s common stock over a 20-day trading period ending on the third trading day immediately preceding November 16, 2008, with a maximum price of $25.12 per share and minimum price of $20.93 per share.  In accordance with the terms of the equity-linked units, PNMR attempted to remarket the senior note components in November 2008, but was unable to complete the remarketing.  As provided in the agreement under which the equity-linked units were originally issued, the holder tendered the $100 million of senior unsecured notes to PNMR to satisfy its obligations under the purchase contracts. The holder chose to receive 477,800 shares of PNMR Series A convertible preferred stock on November 17, 2008 in lieu of 4,778,000 shares of PNMR common stock.  See Note 5.

    On January 5, 2009, PNMR commenced a tender offer whereby it offered to repurchase up to $150.0 million of its 9.25% senior unsecured notes due 2015.  The tender offer requested the holders of the notes to submit the amount of notes they would be willing to sell to PNMR and at the price they would be willing to sell, within the range of 83% to 93% of face value, including additional compensation of 3% of face value for those holders that tendered their notes and did not withdraw them prior to the stated early participation date. Prior to expiration of the offer, $157.5 million of notes were tendered to PNMR for purchase.  Under the applicable rules for this type of arrangement, PNMR was able to purchase $157.0 million of notes at the 93% cap price.  On February 5, 2009, PNMR repurchased and retired these notes for $146.0 million plus accrued interest. On February 26, 2009, PNMR purchased an additional $0.4 million of the 9.25% senior unsecured notes at 93% of face value in a private transaction.  PNMR recognized a pre-tax gain on these transactions of $7.3 million, net of related transaction costs and write-off of the proportionate amount of the deferred costs of the original issuance of the notes, which is included in other income on the Consolidated Statements of Earnings (Loss).

On March 23, 2009, TNMP issued $265.5 million aggregate principal amount of 9.50% First Mortgage Bonds, due 2019, Series 2009A (the “Series 2009A Bonds”) at a price equal to 97.643% of their face value.  The bonds bear interest at the rate of 9.50% per annum of their face value. TNMP may redeem some or all of the bonds at any time at a redemption price that reflects a make-whole provision, plus accrued interest.  The Series 2009A Bonds are secured by a first mortgage on substantially all of TNMP’s property.

On March 25, 2009, TNMP entered into a $50.0 million loan agreement with Union Bank, N. A. (the “2009 Term Loan Agreement”).   TNMP borrowed $50.0 million under this agreement on March 30, 2009.  Borrowings under the 2009 Term Loan Agreement must be repaid by March 25, 2014 and are secured by $50.0 million aggregate principal amount of TNMP first mortgage bonds (the “Series 2009B Bonds”).  Through hedging arrangements, TNMP has established fixed interest rates for the 2009 Term Loan Agreement of 6.05% for the first three years and 6.30% thereafter.  In January 2010, the hedging relationship was modified to reduce the fixed interest rate to 4.80% through March 31, 2012 and to 5.05% thereafter.  The hedging obligations are also secured by the Series 2009B Bonds.  The hedge is accounted for as a cash-flow hedge and its December 31, 2009 pre-tax fair value of $0.2 million is included in other deferred charges and in AOCI on the Consolidated Balance Sheets.  
 
B-50

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

Amounts reclassified from AOCI are included in other interest expense.  The fair value determination was made using Level 2 inputs under GAAP.
 
    TNMP used the proceeds received from the Series 2009A Bonds and the 2009 Term Loan Agreement to repay the $100.0 million borrowed under the TNMP Bridge Facility, which then terminated, and the $150.0 million outstanding under the TNMP Facility.  The remaining proceeds, after offering expenses, were used to reduce intercompany borrowings from PNMR.

On April 30, 2009, TNMP entered into the TNMP Revolving Credit Facility, a new $75.0 million revolving credit facility, and the existing TNMP Facility was terminated.  Borrowings under the TNMP Revolving Credit Facility are secured by $75.0 million aggregate principal amount of TNMP first mortgage bonds (the “Series 2009C Bonds”).  The TNMP Revolving Credit Facility will expire in April 2011.

 
    On May 23, 2003, PNM issued $36.0 million of 4.00% PCRB senior unsecured notes, which had a scheduled maturity in 2038, but were subject to mandatory repurchase and remarketing on July 1, 2009.  PNM repurchased these notes for $36.0 million on July 1, 2009 utilizing available cash balances and borrowings under the PNM Facility.  PNM held these bonds (without legally canceling them) until December 1, 2009, on which date they were remarketed.  The remarketed bonds bear interest at 6.25% and mature on January 1, 2038.

PNMR offers new shares of PNMR common stock through the PNMR Direct Plan.  On July 15, 2009, PNMR began purchasing shares of its common stock on the open market rather than issuing additional shares to satisfy subscriptions under the PNMR Direct Plan.  PNMR had offered new shares of its common stock through an equity distribution agreement, which was terminated in July 2009.

In August 2009, PNMR filed an automatically effective shelf registration statement with the SEC for common stock and in April 2008, PNMR filed an automatically effective shelf registration statement for debt securities.  These registration statements expire three years from the date of filing and can be amended at any time to include additional securities of PNMR.  As a result, these shelf registration statements have unlimited availability, subject to certain restrictions and limitations.

    In April 2008, PNM filed a shelf registration statement for the issuance of $750.0 million of senior unsecured notes that was declared effective on April 29, 2008.  As of February 15, 2010, PNM had $600.0 million of remaining unissued securities registered under this and a prior shelf registration statement.

Borrowing Arrangements Between PNMR and its Subsidiaries

PNMR has one-year intercompany loan agreements with its subsidiaries. Individual subsidiary loan agreements vary in amount from $20.0 million to $100.0 million and have either reciprocal or non reciprocal terms.  Interest charged to the subsidiaries is equivalent to interest paid on the PNMR Facility.  On January 8, 2009, TNMP entered into an agreement for an additional $50.0 million borrowing from PNMR that was subordinated to the TNMP Bridge Facility described above.  The agreement for additional borrowing terminated in April 2009.  As of December 31, 2009 and 2008, TNMP had outstanding borrowings of $23.5 million and $14.1 million from PNMR.  At February 15, 2010, TNMP has borrowings of $26.1 million from PNMR.

    On February 26, 2009, the Finance Committee of the PNMR Board authorized PNMR to provide support for the debt of TNMP by approving one or more additional loans to TNMP as a contingency in the event TNMP was unable to obtain external financing sufficient to pay amounts borrowed under the TNMP Facility and the TNMP Bridge Facility when they came due. With the completion of the financings described above, the PNMR support terminated on April 30, 2009.

Short-term Debt

PNMR and PNM have revolving credit facilities for borrowings up to $600.0 million under the PNMR
 
B-51

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

Facility and $400.0 million under the PNM Facility that primarily expire in 2012.  In addition to the reduction in the PNMR Facility related to LBB discussed above, the PNMR Facility and the PNM Facility will reduce by $26.0 million and $14.0 million in 2010 and an additional $25.0 million and $18.0 million in 2011 according to their terms.  The Company does not believe amending the PNMR Facility to remove LBB or the scheduled reduction in the facilities will have a significant impact on PNMR’s and PNM’s liquidity.

 In addition, PNMR and PNM each have a local line of credit amounting to $5.0 million.  TNMP has a revolving credit facility for borrowings up to $75.0 million under the TNMP Revolving Credit Facility that expires in April 2011.  PNMR and PNM had commercial paper programs under which they could have issued up to $400.0 million and $300.0 million of commercial paper.  No commercial paper has been issued since March 11, 2008 and the programs were terminated on July 2, 2009.

At December 31, 2009, the weighted average interest rate was 1.48% for the PNMR Facility, 0.88% for the PNM Facility.   The TNMP Revolving Credit Facility had no borrowings outstanding at December 31, 2009. Short-term debt outstanding consists of:

   
December 31,
 
Short-term Debt
 
2009
   
2008
 
   
(In thousands)
 
             
PNM
           
Commercial paper
    *     $ -  
Revolving credit facility
  $ 118,000       340,000  
Delayed draw term loan facility
    -       -  
Local lines of credit
    -       -  
      118,000       340,000  
TNMP
               
     Revolving credit facility
    -       150,000  
     Bridge facility
    -       -  
      -       150,000  
PNMR
               
Commercial paper
    *       -  
Revolving credit facility
    80,000       254,667  
Local lines of credit
    -       -  
                 
    $ 198,000     $ 744,667  

* The commercial paper programs were terminated on July 2, 2009.

In addition to the above borrowings, PNMR, PNM, and TNMP had letters of credit outstanding of $61.1 million, $22.3 million and $1.5 million at December 31, 2009 that reduce the available capacity under their respective revolving credit facilities.

At February 15, 2010, PNMR, PNM, and TNMP had $430.4 million, $229.7 million, and $73.5 million of availability under their respective revolving credit facilities and local lines of credit, including reductions of availability due to outstanding letters of credit.  TNMP also had availability of $23.9 million under its intercompany borrowing agreements with PNMR.  Total availability at February 15, 2010, on a consolidated basis, was $733.6 million for PNMR.  Such availability includes $29.9 million that represents the unfunded portion of the PNMR Facility attributable to LBB.  At February 15, 2010, PNMR, PNM, and TNMP had invested cash of $16.4 million, $2.6 million, and none.


 
B-52

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


Long-Term Debt

Information concerning long-term debt outstanding is as follows:

   
December 31,
 
Long-term Debt
 
2009
   
2008
 
   
(In thousands)
 
PNM Debt
           
First Mortgage Bonds, Pollution Control Revenue Bonds:
           
5.70% due 2016
  $ 65,000     $ 65,000  
Senior Unsecured Notes, Pollution Control Revenue Bonds:
               
6.30% due 2016
    77,045       77,045  
5.75% due 2022
    37,300       37,300  
5.80% due 2022
    100,000       100,000  
6.375% due 2022
    90,000       90,000  
6.30% due 2026
    23,000       23,000  
6.60% due 2029
    11,500       11,500  
4.875% due 2033
    46,000       46,000  
4.875% due 2033
    100,000       100,000  
5.15% due 2037
    20,000       20,000  
4.00% due 2038
    -       36,000  
    6.25% due 2038
    36,000       -  
Senior Unsecured Notes:
               
    7.95% due 2018
    350,000       350,000  
    7.50% due 2018
    100,025       100,025  
    Other, including unamortized discounts
    (137 )     (153 )
      1,055,733       1,055,717  
    Less current maturities
    -       36,000  
 
    1,055,733       1,019,717  
TNMP Debt
               
First Mortgage Bonds:
               
   6.05% due 2014, Series 2009B
    50,000       -  
   9.50% due 2019, Series 2009A
    265,500       -  
Senior Unsecured Notes -  6.25% due 2009
    -       167,690  
Other, including unamortized discounts
    (5,788 )     -  
      309,712       167,690  
Less current maturities
    -       167,690  
 
    309,712       -  
PNMR Debt
               
Senior unsecured notes, 9.25% due 2015
    192,592       350,000  
Other
    9,294       11,298  
      201,886       361,298  
Less current maturities
    2,125       2,004  
      199,761       359,294  
                 
Total Consolidated PNMR Debt
    1,567,331       1,584,705  
Less current maturities
    2,125       205,694  
    $ 1,565,206     $ 1,379,011  


 
B-53

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


Interest Rate Swaps

PNMR entered into three fixed-to-floating interest rate swaps with an aggregate notional principal amount of $150.0 million, which matured September 15, 2008.  Under these swaps, PNMR received a 4.40% fixed interest payment on the notional principal amount on a semi-annual basis and paid a floating rate equal to the six month LIBOR plus 58.15 basis points (0.5815%) on the notional amount.  The initial floating rate was 1.91% and was reset to 6.09% on September 15, 2007 and 3.28% on March 17, 2008.  The swaps were accounted for as fair-value hedges.

See Financing Activities above for information concerning a TNMP interest rate swap.

In January 2010, PNM entered into a floating-to-fixed interest rate swap with a notional amount of $100.0 million.  The effect of this swap is to convert $100.0 million of borrowings under the PNM Facility from an interest rate based on the one-month LIBOR rate to a fixed rate of 1.245% through January 14, 2011.  This swap will be accounted for as a cash-flow hedge.

New Mexico Energy Investments LLC

In 2002, PNM entered into an agreement with FPL to develop a 200 MW wind generation facility in New Mexico.  PNM began receiving commercial power from the project in June 2003.  FPL owns and operates the New Mexico Wind Energy Center, which consists of 136 wind-powered turbines on a site in eastern New Mexico.  PNM has a PPA to purchase all the power generated by the New Mexico Wind Energy Center for 25 years.

PNMR entered into purchase and sale agreement with ESI Northeast Energy LP, Inc., an affiliate of FPL, and acquired an interest in the New Mexico Wind Energy Center by the purchase of a 1% membership interest in New Mexico Energy Investments, LLC for $21.2 million.  At closing, PNMR paid $6.2 million in cash and issued a promissory note for $15.0 million at an annual interest rate of 6%. PNMR will make an annual payment of $2.7 million for principal and interest until the final maturity date of the promissory note on December 31, 2013.  PNMR will receive state and federal tax benefits from its ownership interest.  PNMR’s ownership interest terminates on December 31, 2013.

(7)
Lease Commitments

PNMR leases office buildings and other equipment under operating leases. PNM leases interests in Units 1 and 2 of PVNGS, an interest in the EIP transmission line, office buildings, vehicles and other equipment under operating leases.  TNMP leases radio tower antenna space, office buildings, vehicles and other equipment under operating leases.

PNM has a PPA for the entire output of Delta, a gas-fired generating plant in Albuquerque, New Mexico, which is classified as an operating lease with imputed annual lease payments of $6.0 million.  See Note 9 for additional information about the Delta operating lease.  PNM also had a PPA for 40 MW of capacity from Pyramid Unit 4, which was classified as an operating lease and was sold in 2008.  See Note 8.

A portion of PVNGS Unit 2 was leased by PNM from another subsidiary of PNMR from June 2007 until July 2009, at which time the leased assets were transferred to PNM and became subject to rates established by the NMPRC.  See Note 17.  The table below includes lease expense for PNM of $5.4 million in 2009, $9.6 million in 2008, and $4.8 million in 2007 paid to that subsidiary of PNMR.  After the July 2009 transfer, PNM stopped recognizing lease expense for the transferred assets.


 
B-54

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


Operating lease expense was:

   
PNMR
   
PNM
   
TNMP
 
         
(In thousands)
       
                   
2009
  $ 76,301     $ 74,470     $ 2,493  
2008
  $ 83,255     $ 82,101     $ 2,121  
2007
  $ 86,532     $ 80,491     $ 3,233  

    The amounts included in the above table reflect the total amount of expense for the lease payments PNM makes under the PVNGS and EIP leases, excluding payments made related to transferred assets explained above.  As discussed under Investments in Note 1, the PVNGS Capital Trust, which is consolidated by PNM, acquired the lessor notes that were issued by the PVNGS lessors and PNM acquired the remaining lessor note issued by the remaining EIP lessor.  Of the total annual payments of $69.1 million made by PNM under the PVNGS and EIP leases, $55.0 million in 2009, $50.0 million in 2008, and $50.8 million in 2007 was returned in cash to PNM in the form of principal and interest payments on the lessor notes and through its ownership of the PVNGS Unit 2 leased assets.

Future minimum operating lease payments at December 31, 2009 shown below have been reduced by PNM’s lease payments for the owned portion of PVNGS Unit 2 and amounts that will be returned to PNM on the lessor notes, which amounts vary but are approximately $56 million annually thru 2011 reducing thereafter to approximately $33 million annually in 2015:

   
PNMR
   
PNM
   
TNMP
 
         
(In thousands)
       
                   
                   
2010
  $ 27,797     $ 21,268     $ 3,324  
2011
    28,402       21,902       3,311  
2012
    40,543       33,990       3,311  
2013
    45,274       38,685       3,308  
2014
    49,736       43,494       3,302  
Later years
    56,661       55,118       -  
      248,413       214,457       16,556  
Future payments under non-cancelable subleases
    1,902       -       -  
Net minimum lease payments
  $ 246,511     $ 214,457     $ 16,556  

    The PVNGS leases, which expire in 2015 and 2016, contain options to renew the leases at a fixed price or to purchase the property for fair market value at the end of the lease terms.  PNM must give notice to the lessors if it wishes to exercise, or not exercise, these options at dates, varying by lease, through January 15, 2014.  PNM is exploring its alternatives. Covenants in PNM's PVNGS Units 1 and 2 lease agreements limit PNM's ability, without consent of the owner participants in the lease transactions, (i) to enter into any merger or consolidation, or (ii) except in connection with normal dividend policy, to convey, transfer, lease or dividend more than 5% of its assets in any single transaction or series of related transactions.  PNM is exposed to losses under the PVNGS lease arrangements upon the occurrence of certain events that PNM does not consider to be reasonably likely to occur. Under certain circumstances (for example, the NRC issuing specified violation orders with respect to PVNGS or the occurrence of specified nuclear events), PNM would be required to make specified payments to the equity participants, and take title to the leased interests, which, if appropriate, may be required to be written down in value. If such an event had occurred as of December 31, 2009, PNM could have been required to pay the equity participants up to approximately $186.2 million.  In such event, PNM would record the acquired assets at the lower of their fair value or the aggregate of the amount paid and PNM’s carrying value of its investment in PVNGS lessor notes. If PNM exercises its renewal options under the leases, the amount that would be payable to equity participants under the circumstances described above would increase to the fair market value as of the renewal date.
 
B-55

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

 
 (8)
Fair Value of Derivative and Other Financial Instruments

Energy Related Derivative Contracts

Overview

    The Company is exposed to certain risks relating to its ongoing business operations.  The primary objective for the use of derivative instruments, including energy contracts, options, and futures, is to manage price risk associated with forecasted purchases of energy or fuel used to generate electricity, or to manage anticipated generation capacity in excess of forecasted demand from existing customers.  Substantially all of the Company’s energy related derivative contracts are entered into to manage commodity risk and the Company does not currently engage in speculative trading, which it ceased in the second quarter of 2008.  Effective January 1, 2009, the Company adopted amendments to GAAP, which enhanced disclosures for derivative instruments and hedging activities.

Commodity Risk

Marketing and procurement of energy often involve market risks associated with managing energy commodities and establishing open positions in the energy markets, primarily on a short-term basis.  The Company routinely enters into various derivative instruments such as forward contracts, option agreements and price basis swap agreements to economically hedge price and volume risk on power commitments and fuel requirements and to minimize the risk of market fluctuations in wholesale portfolios. The Company monitors the market risk of its commodity contracts using VaR and GEaR calculations to maintain total exposure within management-prescribed limits.

    PNM’s unregulated operations are managed primarily through a net asset-backed marketing strategy, whereby PNM’s aggregate net open forward contract position is covered by its forecasted excess generation capabilities or market purchases.  PNM would be exposed to market risk if its generation capabilities were to be disrupted or if its retail load requirements were to be greater than anticipated.  If all or a portion of the net open contract position were required to be covered as a result of the aforementioned unexpected situations, commitments would have to be met through market purchases.  As discussed in Note 17, effective July 1, 2009, additional resources that had been part of unregulated operations were included in rates subject to the jurisdiction of the NMPRC pursuant to the Resource Stipulation thereby mitigating PNM’s exposure to market risk.

    First Choice is responsible for energy supply related to the sale of electricity to retail customers in Texas.  TECA contains no provisions for the specific recovery of fuel and purchased power costs.  The rates charged to First Choice customers are negotiated with each customer.  As a result, changes in purchased power costs can affect First Choice’s operating results with respect to margins and changes in retail customer load requirements.  First Choice is exposed to market risk to the extent that it has not hedged fixed price load commitments or to the degree that market price movements affect customer retention, customer additions or customer attrition.  Additionally, volumetric fluctuations in First Choice retail load requirements due to weather or other conditions may subject First Choice to market risk.  First Choice’s strategy is to minimize its exposure to fluctuations in market energy prices by matching sales contracts with supply instruments designed to preserve targeted margins.

Accounting for Derivatives

Under derivative accounting and related rules for energy contracts, the Company accounts for its various derivative instruments for the purchase and sale of energy based on the Company’s intent.  Energy contracts that meet the definition of a derivative under GAAP and do not qualify for the normal sales and purchases exception are recorded on the balance sheet at fair value at each period end.  The changes in fair value are recognized in earnings unless specific hedge accounting criteria are met.  Derivatives that meet the normal sales and purchases exception are not marked to market but rather recorded in results of operations when the underlying transactions settle.
 
B-56

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


    For derivative transactions meeting the definition of a cash flow hedge, the Company documents the relationships between the hedging instruments and the items being hedged.  This documentation includes the strategy that supports executing the specific transaction and the methods utilized to assess the effectiveness of the hedges.  Changes in the fair value of contracts qualifying for cash flow hedge accounting are included in AOCI to the extent effective.  Ineffectiveness gains and losses were immaterial for all periods presented.  The amounts shown as current assets and current liabilities relate to contracts that will be settled in the next twelve months.  Gains or losses related to cash flow hedge instruments are reclassified from AOCI when the hedged transaction settles and impacts earnings.  Based on market prices at December 31, 2009, after-tax gains of $11.2 million for PNMR and $12.7 million for PNM would be reclassified from AOCI into earnings during the next twelve months. However, the actual amount reclassified into earnings will vary due to future changes in market prices.  As of December 31, 2009, the maximum length of time over which the Company is hedging its exposure to the variability in future cash flows is through December 2010.

The contracts recorded at fair value that do not qualify or are not designated for cash flow hedge accounting are classified as either economic hedges or trading transactions.  Economic hedges are defined as derivative instruments, including long-term power agreements, used to economically hedge generation assets, purchased power and fuel costs, and customer load requirements.  Changes in the fair value of economic hedges are reflected in results of operations and are classified between operating revenues and cost of energy according to the intent of the hedge.  Trading transactions include speculative transactions, which the Company ceased in 2008.  Also included in this category are transactions that lock in margin with no forward market risk and are not economic hedges; changes in the fair value of these transactions are reflected on a net basis in operating revenues.

Fair value is defined under GAAP as the price that would be received for an asset or paid to transfer a liability (an exit price) in the principal or most advantageous market for the asset or liability in an orderly transaction between market participants on the measurement date.  Fair value is based on current market quotes as available and is supplemented by modeling techniques and assumptions made by the Company to the extent quoted market prices or volatilities are not available.  External pricing input availability varies based on commodity location, market liquidity, and term of the agreement.  As stated in GAAP, valuations of derivative assets and liabilities must take into account nonperformance risk including the effect of the Company’s own credit standing.  The Company regularly assesses the validity and availability of pricing data for its derivative transactions.  Although management uses its best judgment in estimating the fair value of these instruments, there are inherent limitations in any estimation technique.

At December 31, 2009, amounts recognized for the right to reclaim cash collateral are $4.2 million for PNMR and $1.4 million for PNM.  PNMR and PNM had no obligations to return cash collateral at December 31, 2009.


 
B-57

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The following tables do not include activity related to PNM Gas.  See Note 23.

Commodity Derivatives

Commodity derivative instruments are summarized as follows:

               
Qualified Cash
 
   
Economic Hedges
   
Trading Transactions
   
Flow Hedges
 
   
December 31,
   
December 31,
   
December 31,
 
   
2009
   
2008
   
2009
   
2008
   
2009
   
2008
 
         
(In thousands)
       
PNMR
                                   
Current assets
  $ 15,728     $ 5,699     $ 13,889     $ 19,469     $ 21,002     $ 26,082  
Deferred charges
    2,413       2,060       -       7,594       -       15,966  
      18,141       7,759       13,889       27,063       21,002       42,048  
                                                 
Current liabilities
    (11,375 )     (12,630 )     (12,650 )     (18,142 )     -       (3,179 )
Long-term liabilities
    (4,549 )     (551 )     -       (6,365 )     -       (18 )
      (15,924 )     (13,181 )     (12,650 )     (24,507 )     -       (3,197 )
                                                 
Net
  $ 2,217     $ (5,422 )   $ 1,239     $ 2,556     $ 21,002     $ 38,851  
                                                 
PNM
                                               
Current assets
  $ 3,496     $ 2,976     $ -     $ 347     $ 21,002     $ 25,529  
Deferred charges
    -       2,060       -       -       -       15,684  
      3,496       5,036       -       347       21,002       41,213  
                                                 
Current liabilities
    (1,509 )     (7,785 )     -       (86 )     -       (13 )
Long-term liabilities
    (556 )     (551 )     -       -       -       (18 )
      (2,065 )     (8,336 )     -       (86 )     -       (31 )
     Net
  $ 1,431     $ (3,300 )   $ -     $ 261     $ 21,002     $ 41,182  

In 2007, First Choice entered into a series of forward trades that arbitraged basis differentials among certain ERCOT delivery zones.  During the three months ended March 31, 2008, these trades were negatively affected by extreme transmission congestion within the ERCOT market. This congestion resulted in historically high basis differences between the various delivery zones. As a result, in the first quarter of 2008, First Choice recorded a total pre-tax loss of $47.1 million in the trading margins from these speculative trades that is reflected in electric revenues. Because of continued market volatility and the concern that the forward basis market would continue to deteriorate, First Choice decided to end any further speculative trading and flattened remaining speculative positions.  At December 31, 2009 and 2008, the trading transactions column of the above table includes $13.9 million and $19.1 million of current assets, zero and $7.6 million of deferred charges, $12.7 million and $18.1 million of current liabilities, and zero and $6.4 million of long-term liabilities related to the flattened speculative positions of First Choice.  No significant additional costs are expected related to speculative trading.

 

 
B-58

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The following table presents the effect of PNMR’s and PNM’s commodity derivative instruments, excluding qualified cash flow hedging instruments, on earnings:

     
Year ended December 31, 2009
 
 
 
Location
 
Economic
Hedges
   
Trading Transactions
 
     
(In thousands)
 
PNMR
Electric operating revenues
  $ 4,331     $ 97  
 
Cost of energy
    (16,693 )     -  
 
    Total gain (loss)
  $ (12,362 )   $ 97  
                   
PNM
Electric operating revenues
  $ 4,331     $ 84  
 
Cost of energy
    (11,326 )     -  
 
Total gain (loss)
  $ (6,995 )   $ 84  

The following table presents the impact, excluding tax effects, of PNMR’s and PNM’s qualified commodity cash flow hedge instruments on OCI, as well as the location and amount of income reclassified from AOCI as the hedged transactions settled and impacted earnings:

   
Year ended December 31, 2009
 
   
Gain (Loss)
 
     Recognized   Reclassified from AOCI into Earnings  
    In OCI     Location  
Amount
 
       
(In thousands)
 
 
 
PNMR
  $ (18,762 )  
Electric operating revenues
  $ 36,982  
         
Cost of energy
    (20,354 )
         
    Total
  $ 16,628  
                   
PNM
  $ (20,195 )  
Electric operating revenues
  $ 36,982  
         
Cost of energy
    (29 )
         
    Total
  $ 36,953  
                   

Commodity contract volume positions are presented in Decatherms for gas related contracts and in MWh for power related contracts.  The table below presents PNMR’s and PNM’s net buy (sell) volume positions at December 31, 2009:

   
Decatherms
   
MWh
 
   
Economic
Hedges
   
Trading
Transactions
   
Qualified Cash Flow Hedges
   
Economic
Hedges
   
Trading
Transactions
   
Qualified Cash Flow Hedges
 
                   
PNMR
    17,852,500       (1,963,293 )     -       1,658,101       -       (788,400 )
                                                 
PNM
    6,087,500       -       -       468,525       -       (788,400 )

In connection with managing its commodity risks, the Company enters into master agreements with certain counterparties.  If the Company is in a net liability position under an agreement, some agreements provide that the counterparties can request collateral from the Company if the Company’s credit rating is downgraded; other agreements provide that the counterparty may request collateral to provide it with “adequate assurance” that the Company will perform; and others have no provision for collateral.
 
B-59

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The table below presents information about the Company’s contingent requirements to provide collateral under commodity contracts having an objectively determinable collateral provision that are in net liability positions as of December 31, 2009 and are not fully collateralized with cash.  Contractual liability represents commodity derivative contracts recorded at fair value on the balance sheet, determined on an individual contract basis without offsetting amounts for individual contracts that are in an asset position and could be offset under master netting agreements with the same counterparty.  The table only reflects cash collateral that has been posted under the existing contracts and does not reflect letters of credit under the Company’s revolving credit facilities that have been issued as collateral.  Net exposure is the net contractual liability for all contracts, including those designated as normal purchases and sales, offset by existing cash collateral and by any offsets available under master netting agreements, including both asset and liability positions.

 
Contingent Feature
 
Contractual Liability
   
Existing Cash Collateral
   
Net Exposure
 
 
(In thousands)
 
PNMR
           
       Credit rating downgrade
  $ 17,124     $ 1,000     $ 14,104  
                         
PNM
                       
       Credit rating downgrade
  $ 1,211     $ 1,000     $ 37  

Sale of Wholesale Contracts

On January 18, 2008, PNM entered into an agreement to sell certain wholesale power, natural gas and transmission contracts. These contracts represented a significant portion of the wholesale activity portfolio of PNM Electric, and included several long-term sales and purchase power agreements.  Included in the sales agreement were the Tri-State Pyramid Unit 4 operating lease and certain transmission agreements, which were not considered derivative instruments.  In connection with an amendment to GAAP, pre-tax gains on these contracts amounting to $17.2 million were recorded as an adjustment to January 1, 2008 retained earnings.  On June 19, 2008 PNM completed the sale for $6.1 million.  PNM recognized gains on the sale of these contracts of $5.1 million in the year ended December 31, 2008.

Sale of Power from PVNGS Unit 3

In April 2008, PNM entered into three separate contracts for the sale of capacity and energy related to its entire ownership interest in PVNGS Unit 3, which is 135 MW.  Under two of the contracts, PNM will sell 90 MW of firm capacity and energy.  Under the remaining contract, PNM will sell 45 MW of unit contingent capacity and energy. The term of the contracts is May 1, 2008 through December 31, 2010.  Under the two firm contracts, the two buyers made prepayments of $40.6 million and $30.0 million.  These amounts were recorded as deferred revenue and are being amortized over the life of the contracts.  At December 31, 2009 and 2008, $29.5 million and $29.1 million were included in other current liabilities related to these contracts.  The prepayments received under the firm contracts, as well as required subsequent monthly payments on them, are shown as a financing activity in the Consolidated Statement of Cash Flows as required by GAAP.  The firm contracts are considered energy derivatives and a loss of $4.8 million was recognized at inception.  The firm contracts are accounted for as cash flow hedges and changes in fair value are included in AOCI.  The contingent contract is accounted for as a normal sale.

Non-Derivative Financial Instruments

The carrying amounts reflected on the Consolidated Balance Sheets approximate fair value for cash, temporary investments, receivables, and payables due to the short period of maturity.  Available-for-sale securities are carried at fair value.

 
B-60

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


Available-for-sale securities for PNMR and PNM consist of PNM assets held in trust for its share of decommissioning costs of PVNGS and, in 2008, PNM’s executive retirement program.  The trusts hold equity and fixed income securities.  The carrying value, gross unrealized gains and losses and estimated fair value of investments in available-for-sale securities are as follows:

   
Unrealized Gains
   
Unrealized (Losses)
   
Fair Value
 
         
(In thousands)
       
December 31, 2009
                 
Equity securities:
       
 
       
   Domestic value
  $ 1,684     $ -     $ 21,458  
   Domestic growth
    8,901       -       38,132  
   International and other
    1,558       -       9,985  
Fixed income securities:
                       
   Municipals
    1,715       -       36,901  
   U.S. Government
    25       -       20,451  
   Corporate and other
    309       -       8,006  
Cash investments
    -       -       2,099  
    $ 14,192     $ -     $ 137,032  
December 31, 2008
                       
Equity securities
  $ 1,181     $ -     $ 50,941  
Fixed income securities:
                       
   Municipal bonds
    708       -       31,509  
   U.S. Government
    90       -       14,262  
   Corporate and other
    144       -       6,425  
Cash investments
    -       -       9,345  
    $ 2,123     $ -     $ 112,482  

The proceeds and gross realized gains and losses on the disposition of available-for-sale securities for PNMR and PNM are shown in the following table.  Realized gains and losses are determined by specific identification of costs of securities sold.

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
                   
Proceeds from sales
  $ 124,519     $ 183,616     $ 165,330  
Gross realized gains
  $ 6,009     $ 11,279     $ 19,483  
Gross realized (losses)
  $ (7,359 )   $ (14,206 )   $ (7,016 )

Held-to-maturity securities are those investments in debt securities that the Company has the ability and intent to hold until maturity.  Held-to-maturity securities consist of the investment in PVNGS lessor notes and certain items within other investments, including the EIP lessor note.

The Company has no available-for-sale or held-to-maturity securities for which carrying value exceeds fair value.  There are no impairments considered to be “other than temporary” that are included in AOCI and not recognized in earnings.


 
B-61

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


At December 31, 2009, the available-for-sale and held-to-maturity debt securities had the following final maturities:

   
Fair Value
 
   
Available-for-Sale
   
Held-to-Maturity
 
   
PNMR and PNM
   
PNMR
   
PNM
 
   
(In thousands)
 
Within 1 year
  $ 3,239     $ 69     $ 69  
After 1 year through 5 years
    16,385       70,109       51,946  
After 5 years through 10 years
    7,938       131,192       125,573  
Over 10 years
    37,796       -       -  
    $ 65,358     $ 201,370     $ 177,588  

The carrying amount and fair value of other non-derivative financial instruments (including current maturities) are:

   
December 31, 2009
   
December 31, 2008
 
   
Carrying
Amount
   
Fair Value
   
Carrying
Amount
   
Fair Value
 
   
(In thousands)
 
PNMR
                       
Long-term debt
  $ 1,567,331     $ 1,627,986     $ 1,584,705     $ 1,310,771  
Investment in PVNGS lessor notes
  $ 159,936     $ 169,863     $ 185,637     $ 190,077  
Other investments
  $ 25,528     $ 34,078     $ 32,966     $ 42,459  
                                 
PNM
                               
Long-term debt
  $ 1,055,733     $ 1,044,516     $ 1,055,717     $ 834,157  
Investment in PVNGS lessor notes
  $ 159,936     $ 169,863     $ 221,422     $ 225,987  
Other investments
  $ 7,473     $ 8,457     $ 9,951     $ 10,949  
                                 
TNMP
                               
Long-term debt
  $ 309,712     $ 368,350     $ 167,690     $ 167,690  
Other investments
  $ 270     $ 270     $ 550     $ 550  

The fair value of long-term debt shown above was primarily determined using quoted market values, as were certain items included in other investments.  To the extent market values were not available, fair value was determined by discounting the cash flows for the instrument using quoted interest rates for comparable instruments.

 
Other Fair Value Disclosures

The Company determines the fair values of its derivative and other instruments based on the hierarchy established in GAAP, which requires an entity to maximize the use of observable inputs and minimize the use of unobservable inputs when measuring fair value. GAAP describes three levels of inputs that may be used to measure fair value.  Level 1 inputs are quoted prices (unadjusted) in active markets for identical assets or liabilities that the reporting entity has the ability to access at the measurement date.  Level 2 inputs are inputs other than quoted prices included within Level 1 that are observable for the asset or liability, either directly or indirectly.  Level 3 inputs are unobservable inputs for the asset or liability.  Level 3 inputs used in determining fair values for the Company consist of internal valuation models.

 
B-62

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


Derivatives and Investments

The fair values of derivatives and investments that are recorded at fair value on the Consolidated Balance Sheets at December 31, 2009 and 2008 are as follows:

         
Quoted Prices
   
Significant
       
         
in Active
   
Other
   
Significant
 
         
Market for
   
Observable
   
Unobservable
 
         
Identical Assets
   
Inputs
   
Inputs
 
   
Total(1)
   
(Level 1)
   
(Level 2)
   
(Level 3)
 
December 31, 2009
       
(In thousands)
       
PNMR
                       
Assets
                       
   Commodity derivatives
  $ 53,032     $ 9,097     $ 43,510     $ 320  
   Interest rate swap
    194       -       194       -  
                                 
NDT investments
                               
   Cash and equivalents
    2,099       2,099       -       -  
   Equity securities:
                               
     Domestic value
    21,458       21,458       -       -  
     Domestic growth
    38,132       38,132       -       -  
     International and other
    9,985       9,985       -       -  
   Fixed income securities:
                               
     U.S. government
    20,451       15,135       5,316       -  
     Municipals
    36,901       -       36,901       -  
     Corporate and other
    8,006       -       8,006       -  
Total NDT investments
    137,032       86,809       50,223       -  
      190,258       95,906       93,927       320  
Liabilities
                               
Commodity derivatives
    (28,574 )     (10,534 )     (17,863 )     (72 )
Net
  $ 161,684     $ 85,372     $ 76,064     $ 248  
                                 
PNM
                               
Assets
                               
Commodity derivatives
  $ 24,498     $ -     $ 24,498     $ -  
                                 
NDT investments
                               
   Cash and equivalents
    2,099       2,099       -       -  
   Equity securities:
                               
     Domestic value
    21,458       21,458       -       -  
     Domestic growth
    38,132       38,132       -       -  
     International and other
    9,985       9,985       -       -  
   Fixed income securities:
                               
     U.S. government
    20,451       15,135       5,316       -  
     Municipals
    36,901       -       36,901       -  
     Corporate and other
    8,006       -       8,006       -  
Total NDT investments
    137,032       86,809       50,223       -  
      161,530       86,809       74,721       -  
Liabilities
                               
Commodity derivatives
    (2,065 )     (958 )     (1,090 )     (17 )
Net
  $ 159,465     $ 85,851     $ 73,631     $ (17 )
                                 


 
B-63

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007



December 31, 2008
                 
PNMR
                       
Assets
                       
Commodity derivatives
  $ 76,870     $ 9,390     $ 66,953     $ 13  
NDT
    111,671       69,150       42,521       -  
Rabbi trust
    811       811       -       -  
      189,352       79,351       109,474       13  
Liabilities
                               
Commodity derivatives
    (40,885 )     (12,052 )     (27,897 )     (422 )
Net
  $ 148,467     $ 67,299     $ 81,577     $ (409 )
                                 
PNM
                               
Assets
                               
Commodity derivatives
  $ 46,596     $ -     $ 45,519     $ 13  
NDT
    111,671       69,150       42,521       -  
Rabbi trust
    811       811       -       -  
      159,078       69,961       88,040       13  
Liabilities
                               
Commodity derivatives
    (8,453 )     (510 )     (6,457 )     (422 )
Net
  $ 150,625     $ 69,451     $ 81,583     $ (409 )
 
 
             (1)
The Level 1, 2 and 3 columns in the above table are presented based on the nature of each instrument.  The total column is presented based on the balance sheet classification of the instruments and reflect unit of account reclassifications between commodity derivative assets and commodity derivative liabilities of $0.1 million for PNMR and zero for PNM at December 31, 2009 and $0.5 million for PNMR and $1.1 million for PNM at December 31, 2008.

A reconciliation of the changes in Level 3 fair value measurements is as follows:

   
Year ended December 31, 2009
 
   
PNMR
   
PNM
 
   
(In thousands)
 
Level 3 Fair Value Assets and Liabilities
           
Balance at December 31, 2008
  $ (409 )   $ (409 )
Total gains (losses) included in earnings
    (2,123 )     (2,388 )
Total gains (losses) included in other comprehensive income
    (1,046 )     -  
Purchases, issuances, and settlements(1)
    3,826       2,780  
Balance at December 31, 2009
  $ 248     $ (17 )
Total gains (losses) included in earnings attributable to the change in unrealized gains or losses relating to assets still held at the end of the period
  $ 248     $ (17 )



 
B-64

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007



   
Year ended December 31, 2008
 
   
PNMR
   
PNM
 
   
(In thousands)
 
Level 3 Fair Value Assets and Liabilities
           
Balance at December 31, 2007
  $ 2,061     $ 2,679  
Adoption of amendment to GAAP regarding fair value measurements
    16,407       16,407  
Balance at beginning of period
    18,468       19,086  
Total gains (losses) included in earnings
    (8,555 )     (7,947 )
Total gains (losses) included in other comprehensive income
    (19 )     -  
Purchases, issuances, and settlements(1)
    (11,383 )     (12,628 )
Transfers into Level 3 (2)
    1,080       1,080  
Balance at December 31, 2008
  $ (409 )   $ (409 )
Total gains (losses) included in earnings attributable to the change in unrealized gains or losses relating to assets still held at the end of the period
  $ (409 )   $ (409 )
 
(1)  
Includes fair value reversal of contracts settled, unearned and prepaid option premiums received and paid during the period for contracts still held at end of period and, in 2008, the sale of PNM Electric wholesale contracts.
(2)  
Transfers into Level 3 from Level 2 are at fair values as of July 1, 2008.

Gains and losses (realized and unrealized) for Level 3 fair value measurements included in earnings are reported in operating revenues and cost of energy as follows:

   
Year ended December 31, 2009
 
 
 
Operating
Revenues
   
Cost of
Energy
   
Total
 
PNMR
           (In thousands)         
Total gains (losses) included in earnings
  $ 237     $ (2,360 )   $ (2,123 )
Change in unrealized gains or losses relating to assets still held at reporting date
  $ -     $ 248     $ 248  
                         
PNM
                       
Total gains (losses) included in earnings
  $ 237     $ (2,625 )   $ (2,388 )
Change in unrealized gains or losses relating to assets still held at reporting date
  $ -     $ (17 )   $ (17 )


 
B-65

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007



   
Year ended December 31, 2008
 
 
 
Operating
Revenues
   
Cost of
Energy
   
Total
 
PNMR
           (In thousands)        
Total gains (losses) included in earnings
  $ 11,511     $ (20,066 )   $ (8,555 )
Change in unrealized gains or losses relating to assets still held at reporting date
  $ 13     $ (422 )   $ (409 )
                         
PNM
                       
Total gains (losses) included in earnings
  $ 10,893     $ (18,840 )   $ (7,947 )
Change in unrealized gains or losses relating to assets still held at reporting date
  $ 13     $ (422 )   $ (409 )

Investments Held by Employee Benefit Plans

As discussed in Note 12, PNM and TNMP have trusts that hold investment assets for their pension and other postretirement benefit plans.  The fair value of the assets held by the trusts impacts the determination of the funded status of each plan, but the assets are not reflected on the Consolidated Balance Sheets.  Both the PNM Pension Plan and the TNMP Pension Plan hold units of participation in the PNM Resources, Inc. Master Trust (the "PNMR Master Trust"), which was established for the investment of assets of the pension plans.  Fair value of alternative investments is determined based on net asset value as reported by fund managers.

The fair values of investments held by the employee benefit plans at December 31, 2009 are as follows:

         
Quoted
             
         
Prices in
             
         
Active
   
Significant
       
         
Market for
   
Other
   
Significant
 
         
Identical
   
Observable
   
Unobservable
 
         
Assets
   
Inputs
   
Inputs
 
   
Total
   
(Level 1)
   
(Level 2)
   
(Level 3)
 
         
(In thousands)
       
PNM Pension Plan
                       
Alternative real estate investments
  $ 2,168     $ -     $ -     $ 2,168  
Participation in PNMR Master Trust
    358,762       140,003       144,654       74,105  
Total Assets
  $ 360,930     $ 140,003     $ 144,654     $ 76,273  
                                 
TNMP Pension Plan
                               
Participation in PNMR Master Trust
  $ 57,757     $ 21,629     $ 23,702     $ 12,426  
                                 
PNM OPEB Plan
                               
Cash and equivalents
  $ 6,201     $ 6,201     $ -     $ -  
Equity securities:
                               
   International
    7,849       3,994       3,855       -  
   Domestic value
    3,967       3,967       -       -  
   Domestic growth
    2,745       2,745       -       -  
   Mutual funds
    21,546       -       21,546       -  
Fixed income securities:
                               
   Corporate
    838       -       838       -  
   Mutual funds
    14,893       14,893       -       -  
Total Assets
  $ 58,039     $ 31,800     $ 26,239     $ -  
 
 
B-66

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

                         
TNMP OPEB Plan
                       
Cash and equivalents
  $ 579     $ 579     $ -     $ -  
Equity securities:
                               
   International
    975       975       -       -  
   Domestic value
    471       471       -       -  
   Domestic growth
    493       493       -       -  
   Mutual funds
    2,463       -       2,463       -  
Fixed income securities:
                               
   Corporate
    26       -       26       -  
   Mutual funds
    2,124       2,124       -       -  
Total Assets
  $ 7,131     $ 4,642     $ 2,489     $ -  
                                 

The fair values of investments in the PNMR Master Trust are as follows:

         
Quoted
             
         
Prices in
             
         
Active
   
Significant
       
         
Market for
   
Other
   
Significant
 
         
Identical
   
Observable
   
Unobservable
 
         
Assets
   
Inputs
   
Inputs
 
   
Total
   
(Level 1)
   
(Level 2)
   
(Level 3)
 
          (In thousands)        
PNMR Master Trust
                       
Cash and equivalents
  $ 21,424     $ 21,424     $ -     $ -  
Equity securities:
                               
   International
    44,609       -       44,609       -  
   Domestic value
    69,867       66,197       3,670       -  
   Domestic growth
    70,538       70,538       -       -  
   Mutual funds
    47,742       -       47,742       -  
Fixed income securities:
                               
   Corporate
    17,778       -       17,778       -  
   U.S. government
    3,461       3,461       -       -  
   Municipals
    2,504       -       2,504       -  
   Foreign government and other
    714       12       702       -  
   Mutual funds
    51,351       -       51,351       -  
Alternative investments:
                               
   Private equity funds
    26,883       -       -       26,883  
   Hedge funds
    34,921       -       -       34,921  
   Real estate funds
    24,727       -       -       24,727  
Total Assets
  $ 416,519     $ 161,632     $ 168,356     $ 86,531  
                                 


 
B-67

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


A reconciliation of the changes in Level 3 fair value measurements is as follows:

   
Year ended December 31, 2009
 
   
(In thousands)
 
Level 3 Fair Value Assets and Liabilities
           
             
PNM Pension
 
Master
Trust
   
Real estate funds
 
Balance at December 31, 2008
  $ 95,562     $ 3,129  
Actual return on assets sold during the period
    (2,991 )     -  
Actual return on assets still held at period end
    3,812       (961 )
Purchases, issuances, and settlements
    (22,278 )     -  
Balance at December 31, 2009
  $ 74,105     $ 2,168  
                 
TNMP Pension
               
Balance at December 31, 2008
  $ 16,024          
Actual return on assets sold during the period
    (502 )        
Actual return on assets still held at period end
    640          
Purchases, issuances, and settlements
    (3,736 )        
Balance at December 31, 2009
  $ 12,426          

Additional information concerning changes in Level 3 fair value measurements for the PNMR Master Trust is as follows:

   
Year ended December 31, 2009
 
       
(In thousands)
       
Level 3 Fair Value Assets and Liabilities
               
                     
PNMR Master Trust
 
Private equity funds
   
Hedge
funds
   
Real
estate
funds
   
Total
 
Balance at December 31, 2008
  $ 27,590     $ 49,469     $ 34,527     $ 111,586  
Actual return on assets sold during the period
    (237 )     (3,233 )     (23 )     (3,493 )
Actual return on assets still held at period end
    (3,742 )     8,685       (491 )     4,452  
Purchases, issuances, and settlements
    3,272       (20,000 )     (9,286 )     (26,014 )
Balance at December 31, 2009
  $ 26,883     $ 34,921     $ 24,727     $ 86,531  


(9)
Variable Interest Entities

Under the model for consolidation promulgated by GAAP, a PPA may qualify as a variable interest if its terms expose the purchaser to variability in supply or operating costs and the contract is for a significant portion of the entity’s generating capacity.  PNM evaluated its PPAs and determined that one purchase contract entered into prior to December 31, 2003 qualifies as a variable interest.  PNM has been unable to obtain the necessary information needed to determine if PNM was the primary beneficiary and if consolidation was needed despite ongoing efforts, including formal written requests to the operator of the entity supplying power under the PPA.  The operator cited legal and competitive reasons for refusing to provide the information.


 
B-68

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


This variable interest PPA is a contract expiring in June 2020 to purchase 132 MW of capacity and energy, which is the full output of the Delta generating plant.   The contract is accounted for as an operating lease by PNM.  See Note 7 for more information about the Delta operating lease.  The contract contains a fixed capacity charge, a fixed O&M charge, and a variable energy charge that subject PNM to the changes in the costs to produce energy and operate the plant.  The capacity and O&M charges were $6.4 million in 2009, $9.0 million in 2008, and $8.0 million in 2007.  The energy charges were $0.4 million in 2009, $0.8 million in 2008, and $1.0 million in 2007.  These charges represent all of PNM’s obligations under this PPA, PNM has no other financial exposure related to the Delta operating lease.

On April 18, 2007, PNM entered into a PPA to purchase all of the electric capacity and energy from Valencia, a natural gas-fired power plant near Belen, New Mexico.  Valencia became operational on May 30, 2008.  A third-party built, owns and operates the facility while PNM is the sole purchaser of the electricity generated. The total construction cost for the facility was $90.0 million. The term of the PPA is for 20 years beginning June 1, 2008, with the full output of the plant estimated to be 145 MW.  During the term of the PPA, PNM has the option to purchase and own up to 50% of the plant or the variable interest entity. PNM estimates that the plant will typically operate during peak periods of energy demand in summer (less than 18% of the time on an annual basis).  PNM is obligated to pay fixed O&M and capacity charges in addition to variable O&M charges under this PPA.  For the year ended December 31, 2009 and 2008, PNM paid $16.1 million and $7.5 million for fixed charges as well as $0.6 million and $2.6 million for variable charges.  PNM does not have any other financial obligations related to Valencia and creditors of Valencia do not have any recourse against PNM’s assets.
 
PNM has evaluated the accounting treatment of this arrangement and concluded that the third party entity that owns Valencia is a variable interest entity and that PNM is the primary beneficiary of the entity under GAAP since PNM will absorb the majority of the variability in the cash flows of the plant.  As the primary beneficiary, PNM has consolidated the entity in its financial statements beginning on the commercial operations date.  Accordingly, the assets, liabilities, operating expenses, and cash flows of Valencia are included in the consolidated financial statements of PNM although PNM has no legal ownership interest or voting control of the variable interest entity.  The owner’s equity and net income of Valencia are considered attributable to non-controlling interest.  PNM did not consolidate the variable interest entity prior to May 30, 2008 since PNM had no financial risk.

Summarized financial information for Valencia since May 30, 2008 is as follows:

Results of Operations

     Year ended    
May 30, 2008 to
 
   
December 31, 2009
   
December 31, 2008
 
      (In thousands)  
             
Operating revenues
  $ 18,175     $ 10,400  
Operating expenses
    (6,285 )     (2,996 )
Interest expense
    -       (225 )
    Earnings attributable to non-controlling  interest
  $ 11,890     $ 7,179  

Financial Position

   
December 31,
 
   
2009
   
2008
 
   
(In thousands)
 
             
Current assets
  $ 3,981     $ 9,925  
Net property, plant and equipment
    86,349       89,011  
    Total assets
    90,330       98,936  
Current liabilities
    971       430  
    Owners’ equity – non-controlling interest
  $ 89,359     $ 98,506  
 
 
B-69

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


Changes in Owners’ Equity – Non-controlling Interest

    Year ended
 
  May 30, 2008 to
 
    December 31, 2009
 
December 31, 2008
   
(In thousands)
           
Balance at beginning of period
  $ 98,506     $ (1,155 )
Earnings attributable to non-controlling interest
    11,890       7,179  
Net equity transactions with Valencia’s owner
    (21,037 )     92,482  
    Balance at end of period
  $ 89,359     $ 98,506  


(10)
Earnings Per Share

In accordance with GAAP, dual presentation of basic and diluted earnings (loss) per share has been presented in the Consolidated Statements of Earnings (Loss) of PNMR.  Information regarding the computation of earnings (loss) per share is as follows:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands, except per share amounts)
 
Earnings (Loss) Attributable to PNMR:
                 
Earnings (loss) from continuing operations
  $ 65,933     $ (297,565 )   $ 59,886  
Earnings from continuing operations attributable to Valencia Non-controlling Interest
    (11,890 )     (7,179 )     -  
Preferred stock dividend requirements of subsidiary
    (528 )     (528 )     (528 )
Earnings from continuing operations attributable to
    PNMR
    53,515       (305,272 )     59,358  
Earnings (loss) from discontinued operations
    70,801       34,628       15,516  
Net Earnings (Loss) Attributable to PNMR
  $ 124,316     $ (270,644 )   $ 74,874  
                         
Average Number of Common Shares:
                       
Outstanding during year
    86,634       82,879       76,719  
Equivalents from convertible preferred stock (Note 5)
    4,778       589       -  
Vested awards of restricted stock
    23       -       -  
Average Shares - Basic
    91,435       83,468       76,719  
Dilutive Effect of Common Stock Equivalents (a):
                       
Stock options and restricted stock
    236       -       537  
Equity-linked units
    -       -       672  
Average Shares – Diluted
    91,671       83,468       77,928  
                         
Per Share of Common Stock – Basic:
                       
Earnings (loss) from continuing operations
  $ 0.58     $ (3.66 )   $ 0.77  
Earnings (loss) from discontinued operations
    0.78       0.42       0.21  
Net Earnings (Loss)
  $ 1.36     $ (3.24 )   $ 0.98  
                         
Per Share of Common Stock – Diluted:
                       
Earnings (loss) from continuing operations
  $ 0.58     $ (3.66 )   $ 0.76  
Earnings(loss)  from discontinued operations
    0.78       0.42       0.20  
Net Earnings (Loss)
  $ 1.36     $ (3.24 )   $ 0.96  

 
(a)
Excludes the effect of out-of-the-money options of 3,275,542 shares at December 31, 2009.  Due to losses in the year ended December 31, 2008, no potentially dilutive securities are reflected in the average number of common shares used to compute earnings (loss) per share since any impact would be anti-dilutive.

 
B-70

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


(11)
Income Taxes

PNMR

PNMR’s income taxes (benefit) from continuing operations consist of the following components:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
                   
Current federal income tax
  $ (81,963 )   $ (31,625 )   $ (21,438 )
Current state income tax
    (3,770 )     2,290       (10,112 )
Deferred federal income tax
    112,707       (22,722 )     28,583  
Deferred state income tax
    4,393       (35,855 )     9,517  
Amortization of accumulated investment tax credits
    (2,549 )     (2,904 )     (3,324 )
                         
Total income taxes (benefit)
  $ 28,818     $ (90,816 )   $ 3,226  

PNMR’s provision for income taxes from continuing operations differed from the federal income tax computed at the statutory rate for each of the years shown.  The differences are attributable to the following factors:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
                   
Federal income tax at statutory rates
  $ 33,163     $ (135,933 )   $ 22,089  
Impairment of goodwill
    -       61,024       -  
Investment tax credits
    (2,549 )     (2,904 )     (3,324 )
Flow-through of depreciation items
    3,777       2,682       2,143  
Earnings attributable to non-controlling interest in Valencia
    (4,162 )     (2,513 )     -  
Gains on the sale and leaseback of PVNGS Units 1 and 2
    (55 )     (55 )     (64 )
Reversal of deferred income taxes accrued at prior tax rates
    (1,109 )     (1,109 )     (1,109 )
Research and development credit
    (424 )     (220 )     -  
Affordable housing credit
    (750 )     (750 )     (750 )
Allowance for funds used during construction
    (734 )     (394 )     (523 )
State income tax
    344       (6,238 )     (828 )
Favorable IRS settlement
    -       -       (16,038 )
Texas margin tax and related deferred tax adjustments
    -       (2,494 )     -  
Other
    1,317       (1,912 )     1,630  
                         
Total income taxes (benefit)
  $ 28,818     $ (90,816 )   $ 3,226  
                         
Effective tax rate
    30.41 %     23.38 %     5.11 %


 
B-71

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The components of PNMR’s net accumulated deferred income tax liability were:

   
December 31,
 
   
2009
   
2008
 
   
(In thousands)
 
             
Deferred tax assets:
           
     Pension
  $ 61,280     $ -  
     Other
    114,055       106,717  
        Total deferred tax assets
    175,335       106,717  
                 
Deferred tax liabilities:
               
Depreciation and plant related
    (432,098 )     (394,495 )
Investment tax credit
    (20,518 )     (23,834 )
Regulatory assets related to income taxes
    (57,413 )     (84,067 )
Stranded costs
    (36,266 )     (39,203 )
Optim Energy
    (25,520 )     (39,375 )
Other
    (155,204 )     (122,296 )
Total deferred tax liabilities
    (727,019 )     (703,270 )
Net accumulated deferred income tax liabilities
  $ (551,684 )   $ (596,553 )

The following table reconciles the change in PNMR’s net accumulated deferred income tax liability to the deferred income tax benefit included in the Consolidated Statement of Earnings:

   
Year Ended
 
   
December 31, 2009
 
   
(In thousands)
 
       
Net change in deferred income tax liability per above table
  $ (44,869 )
Change in tax effects of income tax related regulatory assets and liabilities
    3,020  
Tax effect of mark-to-market adjustments
    7,187  
Tax effect of excess pension liability
    43,540  
Adjustment for uncertain income tax positions
    6,022  
Deferred tax expense related to discontinued operations
    99,867  
Other
    (216 )
Deferred income tax (benefit)
  $ 114,551  

The Company defers investment tax credits related to rate regulated assets and amortizes them over the estimated useful lives of those assets.


 
B-72

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


PNM

PNM’s income taxes (benefit) from continuing operations consist of the following components:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
                   
Current federal income tax
  $ (64,342 )   $ 10,449     $ (5,295 )
Current state income tax
    (13,621 )     2,167       (1,225 )
Deferred federal income tax
    77,264       (16,627 )     16,795  
Deferred state income tax
    16,974       (3,305 )     3,850  
Amortization of accumulated investment tax credits
    (2,549 )     (2,713 )     (2,905 )
                         
Total income taxes (benefit)
  $ 13,726     $ (10,029 )   $ 11,220  

PNM’s provision for income taxes from continuing operations differed from the federal income tax computed at the statutory rate for each of the years shown.  The differences are attributable to the following factors:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
                   
Federal income tax at statutory rates
  $ 15,969     $ (24,263 )   $ 12,114  
Impairment of goodwill
    -       17,900       -  
Investment tax credits
    (2,549 )     (2,713 )     (2,905 )
Flow-through of depreciation items
    3,776       2,682       2,143  
Earnings attributable to non-controlling interest in Valencia
    (4,162 )     (2,513 )     -  
Gains on the sale and leaseback of PVNGS Units 1 and 2
    (55 )     (55 )     (64 )
Reversal of deferred income taxes accrued at prior tax rates
    (969 )     (969 )     (969 )
Research and development credit
    -       -       -  
Allowance for funds used during construction
    (733 )     (334 )     (472 )
State income tax
    1,933       (824 )     1,788  
Other
    516       1,060       (415 )
                         
Total income taxes (benefit)
  $ 13,726     $ (10,029 )   $ 11,220  
                         
Effective tax rate
    30.08 %     14.47 %     32.42 %


 
B-73

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The components of PNM’s net accumulated deferred income tax liability were:

   
December 31,
 
   
2009
   
2008
 
   
(In thousands)
 
Deferred tax assets:
           
     Pension
  $ 63,227     $ -  
     Other
    85,935       61,190  
        Total deferred tax assets
  $ 149,162     $ 61,190  
                 
Deferred tax liabilities:
               
Depreciation and plant related
    (340,951 )     (294,025 )
Investment tax credit
    (20,518 )     (23,834 )
Regulatory assets related to income taxes
    (45,960 )     (72,302 )
Pension
    -       (27,131 )
Other
    (126,749 )     (82,727 )
Total deferred tax liabilities
    (534,178 )     (500,019 )
Net accumulated deferred income tax liabilities
  $ (385,016 )   $ (438,829 )

The following table reconciles the change in PNM’s net accumulated deferred income tax liability to the deferred income tax benefit included in the Consolidated Statement of Earnings:

   
Year Ended
 
   
December 31, 2009
 
   
(In thousands)
 
       
Net change in deferred income tax liability per above table
  $ (53,813 )
Change in tax effects of income tax related regulatory assets and liabilities
    3,131  
Tax effect of mark-to-market adjustments
    2,073  
Tax effect of excess pension liability
    43,510  
Adjustment for uncertain income tax positions
    (339 )
Deferred tax expense related to discontinued operations
    99,867  
Other
    (2,740 )
Deferred income tax (benefit)
  $ 91,689  

TNMP

TNMP’s income taxes from continuing operations consist of the following components:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
                   
Current federal income tax
  $ (25,237 )   $ 17,233     $ 18,716  
Current state income tax
    1,584       1,609       973  
Deferred federal income tax
    31,664       11,285       (9,162 )
Deferred state income tax
    (26 )     (18,808 )     538  
Amortization of accumulated investment
                       
tax credits
    -       (191 )     (418 )
                         
Total income taxes
  $ 7,985     $ 11,128     $ 10,647  
 
 
B-74

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


TNMP’s provision for income taxes, from continuing operations differed from the federal income tax computed at the statutory rate for each of the periods shown.  The differences are attributable to the following factors:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
                   
Federal income tax at statutory rates
  $ 7,053     $ 817     $ 10,169  
Impairment of goodwill
    -       12,059       -  
Investment tax credits
    -       (191 )     (418 )
Reversal of deferred income taxes accrued
                       
at prior tax rates
    (141 )     (141 )     (141 )
Allowance for funds used during construction
    -       (10 )     (45 )
State income tax
    1,032       1,045       985  
Texas margin tax and related deferred tax adjustments
    -       (2,494 )     -  
Other
    41       43       97  
                         
Total income taxes
  $ 7,985     $ 11,128     $ 10,647  
                         
Effective tax rate
    39.63 %     476.65 %     36.64 %

The components of TNMP’s net accumulated deferred income tax liability at December 31 were:

   
December 31,
 
   
2009
   
2008
 
   
(In thousands)
 
Deferred tax assets:
           
     Regulatory liabilities related to income taxes
  $ 6,682     $ 7,105  
     Deferred Tax Assets – other
    16,208       29,043  
        Total deferred tax assets
    22,890       36,148  
                 
Deferred tax liabilities:
               
Depreciation and plant related
    (96,627 )     (94,682 )
Stranded costs
    (36,266 )     (39,203 )
Regulatory assets related to income taxes
    (11,453 )     (11,765 )
Other
    (15,488 )     (1,691 )
   Total deferred tax liabilities
    (159,834 )     (147,341 )
Net accumulated deferred income tax liabilities
  $ (136,944 )   $ (111,193 )



 
B-75

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The following table reconciles the change in TNMP’s net accumulated deferred income tax liability to the deferred income tax benefit included in the Consolidated Statement of Earnings:

   
Year Ended
 
   
December 31, 2009
 
   
(In thousands)
 
       
Net change in deferred income tax liability per above table
  $ 25,751  
Change in tax effects of income tax related regulatory assets and liabilities
    (112 )
Tax effect of excess pension liability
    30  
Adjustments for uncertain income tax positions
    6,255  
Other
    (286 )
Deferred income tax (benefit)
  $ 31,638  

As of January 1, 2007, the Company adopted an amendment to GAAP, which requires that the Company recognize only the impact of tax positions that, based on their technical merits, are more likely than not to be sustained upon an audit by the taxing authority.  As a result, PNMR decreased the January 1, 2007 balance of retained earnings by $1.6 million, PNM decreased the January 1, 2007 balance of retained earnings by $1.1 million, and TNMP increased the January 1, 2007 balance of retained earnings by $0.7 million.

As a result of settlements with the IRS, PNMR recognized $16.3 million of income tax benefit during 2007.  Including this benefit, PNMR’s effective tax rate was 5.11% for the year ended December 31, 2007.  This non-recurring benefit reduced PNMR’s effective tax rate by 25.76% for the year ended December 31, 2007.

A reconciliation of unrecognized tax benefits (expenses) is as follows:

   
PNMR
   
PNM
   
TNMP
 
   
(In thousands)
 
                   
Balance at January 1, 2007
  $ 33,895     $ (3,564 )   $ -  
Additions based on tax positions related to 2007
    15,721       (29 )     -  
Reductions for tax positions of prior years
    (15,786 )     -       -  
Settlements
    (15,578 )     3,346       -  
Balance at December 31, 2007
    18,252       (247 )     -  
Additions based on tax positions related to 2008
    (1,111 )     316       541  
Reductions for tax positions of prior years
    (753 )     -       -  
Settlements
    -       -       -  
Balance at December 31, 2008
    16,388       69       541  
Additions based on tax positions related to 2009
    6,633       (287 )     6,255  
Reductions for tax positions of prior years
    (430 )     -       -  
Settlements
    -       -       -  
Balance at December 31, 2009
  $ 22,591     $ (218 )   $ 6,796  

Included in the balance at December 31, 2009 are $3.0 million and $0.1 million of unrecognized tax benefits that, if recognized, would affect the effective tax rate for PNMR and PNM.  None of TNMP’s unrecognized tax benefits at December 31, 2009 would affect the effective tax rate if recognized.  The Company believes that it is reasonably possible that approximately $1.3 million of PNMR’s unrecognized tax benefits, $0.2 million of PNM’s unrecognized tax expenses, and $0.5 million of TNMP’s unrecognized tax benefits will be reduced or settled in 2010 as a result of the conclusion of income tax examinations.

Estimated interest income related to refunds the Company expects to receive is included in Other Income and estimated interest expense and penalties related to potential cash settlements are included in Interest Expense in the Consolidated Statements of Earnings (Loss).
 
 
 
B-76

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

Interest income (expense) related to income taxes is as follows:
 
   
PNMR
   
PNM
   
TNMP
 
         
(In thousands)
       
                   
2009
  $ 6,418     $ 7,746     $ (6 )
2008
  $ (2,450 )   $ (4,874 )   $ 537  
2007
  $ 17,173     $ 10,732     $ (47 )

Accumulated accrued interest receivable (payable) related to income taxes is as follows:

   
PNMR
   
PNM
   
TNMP
 
   
(In thousands)
 
December 31, 2009:
                 
Accumulated accrued interest receivable
  $ 14,267     $ 14,267     $ -  
Accumulated accrued interest payable
  $ (1,105 )   $ (23 )   $ (107 )
December 31, 2008:
                       
Accumulated accrued interest receivable
  $ 6,987     $ 6,521     $ -  
Accumulated accrued interest payable
  $ (244 )   $ (22 )   $ (101 )

The Company files a federal consolidated and several consolidated and separate state income tax returns.  The tax years prior to 2001 are closed to examination by either federal or state taxing authorities.  2001 and 2002 are open for examination only for certain items.  Tax year 2004 is closed to examination by federal taxing authorities, but open for some states.  Other tax years are open to examination by federal and state taxing authorities.

(12)     Pension and Other Postretirement Benefits

PNMR and its subsidiaries maintain qualified defined benefit pension plans, postretirement benefit plans providing medical and dental benefits, and executive retirement programs (“PNM Plans” and “TNMP Plans”).  PNMR maintains the legal obligation for the benefits owed to participants under these plans. As discussed in Note 2, PNM completed the sale of its gas operations to NMGC on January 30, 2009.  PNM retained the obligations under the defined benefit pension plans and executive retirement plans relating to employees that transferred to NMGC upon the sale.  NMGC assumed the postretirement medical and dental obligations for the transferred employees.  The periodic costs or income of the PNM Plans and TNMP Plans are included in regulated rates to the extent attributable to regulated operations.  In addition, PNM receives a regulated return on the amount it has funded for its pension plan in excess of the periodic cost or income.

Participants in the PNM Plans include eligible employees and retirees of PNMR and other subsidiaries of PNMR. Participants in the TNMP Plans include eligible employees and retirees of TNMP, First Choice and other subsidiaries of TNP. The PNM pension plan was frozen at the end of 1997 with regard to new participants, salary levels and benefits. Through December 31, 2007, additional credited service could be accrued under the PNM pension plan up to a limit determined by age and service. The TNMP pension plan was frozen at December 31, 2005 with regard to new participants, salary levels and benefits.

GAAP requires a plan sponsor to (a) recognize in its statement of financial position an asset for a plan’s overfunded status or a liability for a plan’s underfunded status; (b) measure a plan’s assets and its obligations that determine its funded status as of the end of the employer’s fiscal year; and (c) recognize changes in the funded status of a defined benefit postretirement plan in the year in which the changes occur. Such changes are reported in other comprehensive income.

GAAP also requires unrecognized prior service costs and unrecognized gains or losses to be recorded in AOCI and subsequently amortized. The amortization of these incurred costs will ultimately be included as pension and postretirement benefits expenses in subsequent years. To the extent the amortization of these items will
 
B-77

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

ultimately be recovered in future rates, PNM and TNMP records the costs as a regulatory asset or regulatory liability.

The Company has in place, for the PNM Plans and TNMP Plans, a policy that defines the investment objectives, establishes performance goals of the asset managers and provides procedures for the manner in which investments are to be reviewed. The plans implement investment strategies to achieve the following objectives:

  
Maximize the return on assets, commensurate with the risk that the Corporate Investment Committee deems appropriate to:  meet the obligations of the pension plans and other postretirement benefits plans; minimize the volatility of expense; and account for contingencies; and
  
Generate a rate of return for the total portfolio that equals or exceeds the actuarial investment rate assumption.

Management is responsible for the determination of the asset target mix and the expected rate of return.   The target asset allocations are determined based on consultations with external investment advisors.  The expected long-term rate of return on pension and postretirement plan assets is calculated on the market-related value of assets. GAAP requires that actual gains and losses on pension and postretirement plan assets be recognized in the market-related value of assets equally over a period of not more than five years, which reduces year-to-year volatility. For the PNM Plans and TNMP Plans, the market-related value of assets is equal to the prior year’s market related value of assets adjusted for contributions, benefit payments and investment gains and losses that lie within a corridor of plus or minus 4.0% around the expected return on market value. Gains and losses that lie outside the corridor are amortized over five years.  This market-related valuation recognizes the portion of return that is outside the range over a five-year period from the year in which the return occurs. As such, the future value of assets will be impacted as previously deferred returns are recorded.

Pension Plans

For defined benefit pension plans, including the executive retirement plans, the PBO represents the actuarial present value of all benefits attributed by the pension benefit formula to employee service rendered prior to that date using assumptions regarding future compensation levels. The accumulated benefit obligation represents the PBO without considering future compensation levels.  Since the plans are frozen, the PBO and accumulated benefit obligation are equal.  The following table presents information about the PBO, fair value of plan assets, and funded status of the plans:

   
PNM Plan
   
TNMP Plan
 
   
Year Ended December 31,
   
Year Ended December 31,
 
   
2009
   
2008
   
2009
   
2008
 
   
(In thousands)
 
                         
PBO at beginning of year
  $ 491,758     $ 498,859     $ 64,028     $ 66,619  
   Service cost
    -       -       -       -  
   Interest cost
    34,439       33,268       4,396       4,243  
   Actuarial (gain) loss
    55,492       (8,284 )     6,181       279  
   Benefits paid
    (35,942 )     (32,085 )     (5,969 )     (7,113 )
PBO at end of year
    545,747       491,758       68,636       64,028  
Fair value of plan assets at beginning of year
    332,768       501,718       53,424       81,538  
Actual return on plan assets
    64,028       (136,865 )     10,289       (21,001 )
Benefits paid
    (35,942 )     (32,085 )     (5,969 )     (7,113 )
Fair value of plan assets at end of year
    360,854       332,768       57,744       53,424  
Funded status-asset (liability) for pension benefits
  $ (184,893 )   $ (158,990 )   $ (10,892 )   $ (10,604 )


 
B-78

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The following table presents pre-tax information about prior service cost and net actuarial (gain) loss in AOCI as of December 31, 2009.

   
PNM Plan
   
TNMP Plan
 
   
December 31, 2009
   
December 31, 2009
 
   
Prior service cost
   
Net actuarial (gain) loss
   
Net actuarial
(gain) loss
 
   
(In thousands)
 
                   
Amounts in AOCI not yet recognized in net periodic cost (income) at beginning of year
  $ 93     $ 11,348     $ 294  
Experience loss (gain)
    -       20,591       1,985  
Regulatory asset (liability) adjustment
    -       89,929       (1,889 )
Amortization recognized in net periodic cost
    (143 )     (1,729 )     -  
Amounts in AOCI not yet recognized in net periodic cost (income) at end of year
  $ (50 )   $ 120,139     $ 390  
                         
Amortization expected to be recognized in AOCI in 2010
  $ (143 )   $ (2,921 )   $ -  
 
The following table presents the components of net periodic cost (income) recognized in the Consolidated Statements of Earnings:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
PNM Plan
                 
Service cost
  $ -     $ -     $ 144  
Interest cost
    34,439       33,268       31,811  
Long-term rate of return on plan assets
    (38,763 )     (41,345 )     (40,780 )
Amortization of net (gain) loss
    3,818       1,924       3,890  
Amortization of prior service cost
    317       317       317  
     Net periodic benefit (income) cost
  $ (189 )   $ (5,836 )   $ (4,618 )
                         
TNMP Plan
                       
Service cost
  $ -     $ -     $ -  
Interest cost
    4,396       4,243       4,229  
Long-term rate of return on plan assets
    (6,093 )     (6,635 )     (6,840 )
Amortization of net (gain) loss
    -       (146 )     (7 )
Amortization of prior service cost
    -       -       -  
     Net periodic benefit (income) cost
  $ (1,697 )   $ (2,538 )   $ (2,618 )

The following significant weighted-average assumptions were used to determine the PBO and net periodic cost (income).  Should actual experience differ from actuarial assumptions, the PBO and net periodic cost (income) would be affected.


 
B-79

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007



 
Year Ended December 31,
PNM Plan
2009
 
2008
 
2007
Discount rate for determining projected benefit obligation
         
at December 31
6.47%
 
7.25%
 
6.88%
Discount rate for determining net periodic cost (income)
7.25%
 
6.88%
 
6.10%
Long-term rate of return on plan assets
8.75%
 
8.50%
 
8.75%
Rate of compensation increase
N/A
 
N/A
 
N/A
           
TNMP Plan
         
Discount rate for determining projected benefit obligation
         
 at December 31
6.31%
 
7.25%
 
6.72%
Discount rate for determining net periodic cost (income)
7.25%
 
6.72%
 
6.10%
Long-term rate of return on plan assets
8.75%
 
8.50%
 
8.75%
Rate of compensation increase
N/A
 
N/A
 
N/A

    The assumed discount rate for determining the PBO was determined based on a review of long-term high-grade bonds and management’s expectations. The change in discount rate resulted in an increase in the PNM and TNMP PBO of $38.4 million and $4.7 million at December 31, 2009, which are reflected as actuarial (gain) loss above. The PNM PBO also increased in 2009 by $16.3 million, reflected as actuarial (gain) loss, due to changes in demographics, including $9.6 million associated with early retirement of PNM Gas employees transferred to NMGC.  Although the transferred employees do not result in a significant reduction in the expected years of future service of present employees covered by the pension plan and, therefore, under GAAP, a curtailment does not occur, GAAP requires measuring the effects of the reduction in the work force in the same manner as a curtailment for purposes of determining the gain or loss on the sale of gas operations.   This $9.6 million, which is not included in net periodic benefit (income) cost above, was recognized as a loss reducing the gain on the sale of PNM Gas.

    The expected long-term rate of return on plan assets reflects the average rate of earnings expected on the funds invested, or to be invested, to provide for the benefits included in the PBO.  Factors that are considered include, but are not limited to, historic returns on plan assets, current market information on long-term returns (e.g., long-term bond rates) and current and target asset allocations between asset categories. The expected long-term rate of return assumption for the PNM and TNMP pension plans compares to the actual return (loss) of 20.3% and 20.4% for the year ended December 31, 2009. If all other factors were to remain unchanged, a 1% decrease in the expected long-term rate of return would cause PNM’s and TNMP’s 2010 net periodic cost to increase $4.3 million and $0.7 million (analogous changes would result from a 1% increase).

The Company’s overall pension investment strategy is to invest in a portfolio that is diversified by asset class and style strategies. The targeted asset allocation is 57.5% equities, 22.5% fixed income, and 20% alternative investments. The objective is over the long term to achieve the actuarial rate of return. Equity securities primarily include investments in large, mid, and small cap domestic companies. The pension has a targeted allocation of 10% to equities of companies domiciled primarily in developed countries outside of the United States. This category comprises of actively managed international and domestic equity securities that are benchmarked against a variety of style indices. Equity mutual funds are enhanced index funds that attempt to beat the S&P 500 index.  Fixed income investments are primarily corporate bonds of companies from diversified industries and government securities. Fixed income mutual funds are funds that attempt to match the duration of the pension liability.  Alternative investments include investments in hedge funds and private equity funds. These funds are structured as multi-strategy multi-manager fund-of-funds to achieve a diversified position in these asset classes. The plans have invested in funds that have investments in a diversified portfolio of assets including timber, commercial property, and multi-family housing.  The hedge funds pursue various absolute return strategies such as relative value, long-short equity, and event driven. Private equity fund strategies include mezzanine financing, venture capital and buy-outs.

See Note 8 for fair value information concerning assets held by the pension plans.
 
B-80

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

The following pension benefit payments, which reflect expected future service, are expected to be paid:

   
PNM
   
TNMP
 
   
Plan
   
Plan
 
   
(In thousands)
 
             
2010
  $ 38,230     $ 6,490  
2011
  $ 39,079     $ 6,414  
2012
  $ 40,028     $ 6,582  
2013
  $ 41,002     $ 6,029  
2014
  $ 41,903     $ 6,151  
Years 2014 – 2018
  $ 218,074     $ 27,113  

There has been a significant decline in the general price levels of marketable equity securities held by the pension plans in late 2008 and in early 2009.  PNM and TNMP made no contributions to the pension plans in 2009. Based on current law and estimates of portfolio performance, PNM anticipates making contributions to its pension plan trust of approximately $19.5 million in 2010 and a total of $185.7 million for 2011-2013 and TNMP anticipates making contributions to its pension plan trust of approximately $0.3 million in 2010 and a total of $8.0 million for 2011-2013.  These anticipated contributions were developed using a probabilistically weighted average discount rate of 6.2% to determine the projected benefit obligation under the pension plan.  Actual amounts to be funded in the future will be dependent on the actuarial assumptions at that time, including the appropriate discount rate.

Other Postretirement Benefit Plans

    For postretirement benefit plans, the APBO is the actuarial present value as of a date of all future benefits attributed under the terms of the postretirement benefit plan to employee service rendered to that date.

    The following table presents information about the APBO, the fair value of plan assets, and the funded status of the plans:

   
PNM Plan
   
TNMP Plan
 
   
Year Ended December 31,
   
Year Ended December 31,
 
   
2009
   
2008
   
2009
   
2008
 
   
(In thousands)
 
                         
APBO at beginning of year
  $ 120,843     $ 123,672     $ 10,565     $ 10,779  
Service cost
    418       713       259       284  
Interest cost
    7,388       8,344       733       715  
Participant contributions
    1,706       1,579       388       348  
Actuarial (gain) loss
    16,766       (5,233 )     268       (869 )
Benefits paid
    (9,050 )     (8,232 )     (659 )     (692 )
   Liability transferred with sale of PNM Gas
    (15,654 )     -       -       -  
APBO at end of year
    122,417       120,843       11,554       10,565  
Fair value of plan assets at beginning of year
    49,480       71,567       5,692       7,907  
   Actual return on plan assets
    12,044       (20,637 )     1,378       (2,299 )
   Employer contributions
    2,946       5,203       294       428  
   Participant contributions
    1,706       1,579       388       348  
   Benefits paid
    (9,050 )     (8,232 )     (659 )     (692 )
Fair value of plan assets at end of year
    57,126       49,480       7,093       5,692  
Funded status-APBO net (liability)
  $ (65,291 )   $ (71,363 )   $ (4,461 )   $ (4,873 )
 
 
B-81

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

As a result of the sale of gas operations on January 30, 2009, $15.7 million of the APBO liability was transferred to the purchaser and PNM recognized unamortized prior service costs resulting in a $2.9 million gain, which is not included in net periodic benefit cost below.

The following table presents pre-tax information about prior service cost and net actuarial (gain) loss in AOCI as of December 31, 2009.

   
PNM Plan
   
TNMP Plan
 
   
December 31, 2009
   
December 31, 2009
 
   
Prior service cost/(credit)
   
Net actuarial (gain)/loss
   
Prior
service cost
   
Net actuarial (gain)/loss
 
   
(In thousands)
 
                         
Amount in AOCI not yet recognized in net periodic cost (income) at beginning of year
  $ (971 )   $ 4,016     $ 15     $ (89 )
Experience loss (gain)
    -       10,555       -       (616 )
Regulatory asset (liability) adjustment
    -       (10,209 )     -       602  
Amortization recognized in net periodic cost
    140       (108 )     (2 )     6  
Amounts in AOCI not yet recognized in net periodic cost (income) at end of year
  $ (831 )   $ 4,254     $ 13     $ (97 )
                                 
Amortization expected to be recognized in AOCI in 2010
  $ 136     $ (177 )   $ (1 )   $ 4  

The following table presents the components of net periodic cost recognized in the Consolidated Statements of Earnings:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
PNM Plan
                 
Service cost
  $ 417     $ 713     $ 2,530  
Interest cost
    7,388       8,344       7,712  
Long-term rate of return on plan assets
    (5,832 )     (6,128 )     (5,856 )
Amortization of net (gain) loss
    3,290       4,816       5,842  
Amortization of prior service credit
    (4,262 )     (5,687 )     (5,687 )
     Net periodic benefit cost
  $ 1,001     $ 2,058     $ 4,541  
TNMP Plan
                       
Service cost
  $ 260     $ 284     $ 394  
Interest cost
    733       716       661  
Long-term rate of return on plan assets
    (495 )     (486 )     (456 )
Amortization of prior service cost
    60       60       60  
Amortization of net (gain) loss
    (265 )     (271 )     (156 )
     Net periodic benefit cost
  $ 293     $ 303     $ 503  

The following significant weighted-average assumptions were used to determine the accumulated postretirement benefit obligation and postretirement benefit cost.  Should actual experience differ from actuarial assumptions, the APBO and postretirement benefit cost would be affected.


 
B-82

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007



 
Year Ended December 31,
PNM Plan
2009
 
2008
 
2007
Discount rate for determining accumulated postretirement
         
benefit obligation at December 31
6.42%
 
7.25%
 
6.91%
Discount rate for determining postretirement benefit cost
7.25%
 
6.91%
 
6.10%
Long-term rate of return on plan assets
8.75%
 
8.50%
 
8.75%
Rate of compensation increase
N/A
 
N/A
 
N/A
TNMP Plan
         
Discount rate for determining accumulated postretirement
         
   benefit obligation at December 31
6.42%
 
7.25%
 
6.91%
Discount rate for determining postretirement benefit cost
7.25%
 
6.91%
 
6.10%
Long-term rate of return on plan assets
6.70%
 
6.50%
 
6.70%
Rate of compensation increase
N/A
 
N/A
 
N/A

The assumed discount rate for determining the APBO was determined based on a review of long-term high-grade bonds and management’s expectations.  The change in discount rate resulted in an increase in the PNM and TNMP APBO obligation of $8.8 million and $0.8 million.

The expected long-term rate of return on plan assets reflects the average rate of earnings expected on the funds invested, or to be invested, to provide for the benefits included in the APBO. Factors that are considered include, but are not limited to, historic returns on plan assets, current market information on long-term returns (e.g., long-term bond rates) and current and target asset allocations between asset categories. The expected long-term rate of return assumption for the PNM and TNMP postretirement benefit plans compares to the actual return (loss) of 25.5% and 24.2% for the year ended December 31, 2009. If all other factors were to remain unchanged, a 1% decrease in the expected long-term rate of return would cause PNM’s and TNMP’s 2010 postretirement benefit cost to increase $0.6 million and $0.1 million (analogous changes would result from a 1% increase).

TNMP’s exposure to cost increases in the postretirement benefit plan is minimized by a provision that limits TNMP’s share of costs under the plan. Costs of the plan in excess of the limit are wholly borne by the participants. TNMP reached the cost limit at the end of 2001. As a result, a one-percentage-point change in assumed health care cost trend rates would have no effect on either the net periodic expense or the year-end APBO.

The following table shows the assumed health care cost trend rates:

   
PNM Plan
 
   
December 31,
 
   
2009
   
2008
 
             
Health care cost trend rate assumed for next year
    8.5 %     9.0 %
Rate to which the cost trend rate is assumed
               
to decline (the ultimate trend rate)
    5.0 %     5.0 %
Year that the rate reaches the ultimate trend rate
    2017       2014  


 
B-83

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The following table shows the impact of a one-percentage-point change in assumed health care cost trend rates:
 
   
PNM Plan
 
   
1-Percentage-
   
1-Percentage-
 
   
Point Increase
   
Point Decrease
 
   
(In thousands)
 
             
Effect on total of service and interest cost
  $ 680     $ (586 )
Effect on APBO
  $ 9,304     $ (8,108 )

The Company’s other postretirement benefit plans invest in a portfolio that is diversified by asset class and style strategies. The other postretirement benefit plans use the same pension fixed income and equity investment managers and utilize the same overall investment strategy as described above for the pension plans, except there is no allocation to alternative investments. The other postretirement benefit plans have an asset allocation of 70% equities and 30% fixed income.  See Note 8 for fair value information concerning assets held by the other postretirement benefit plans.

The following other postretirement benefit payments, which reflect expected future service, are expected to be paid:
   
PNM
   
TNMP
 
   
Plan
   
Plan
 
   
(In thousands)
 
             
2010
  $ 8,279     $ 958  
2011
  $ 8,734     $ 960  
2012
  $ 9,102     $ 938  
2013
  $ 9,331     $ 919  
2014
  $ 9,735     $ 908  
Years 2015 – 2019
  $ 52,012     $ 4,747  

PNM expects to make contributions totaling $2.5 million to the PNM postretirement benefit plan in 2010. TNMP expects to make contributions totaling $0.4 million to the TNMP postretirement benefit plan in 2010.

Executive Retirement Programs

For the executive retirement programs, the following table presents information about the PBO and funded status of the plans:

   
PNM Plan
   
TNMP Plan
 
   
Year Ended
December 31,
   
Year Ended
December 31,
 
   
2009
   
2008
   
2009
   
2008
 
   
(In thousands)
 
                         
PBO at beginning of year
  $ 16,388     $ 17,262     $ 1,125     $ 1,199  
Service cost
    59       57       -       -  
Interest cost
    1,135       1,135       76       75  
Actuarial gain
    914       (555 )     (183 )     14  
Benefits paid
    (1,492 )     (1,511 )     (151 )     (163 )
PBO at end of year-funded status
    17,004       16,388       867       1,125  
Less current liability
    1,396       1,404       88       149  
Non-current liability
  $ 15,608     $ 14,984     $ 779     $ 976  
 
 
B-84

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

PNM has an irrevocable grantor “Rabbi” trust established in connection with the executive retirement program.  Under the terms of the trust, PNM may, but is not obligated to, provide funds to the trust, which was established with an independent trustee, to aid it in meeting its obligations under the program.  The trust is recorded as an asset of PNM. Marketable securities with a fair value of $0.8 million were in the trust at December 31, 2008 and cash equivalents of $0.7 million were held at December 31, 2009.  Amounts shown as benefits paid in the above table are considered to be contributions to the executive retirement programs.
 
The following table presents pre-tax information about prior service cost and net actuarial loss in AOCI as of December 31, 2009.

   
PNM Plan
   
TNMP Plan
 
   
December 31, 2009
   
December 31, 2009
 
   
Prior
service cost
   
Net actuarial loss
   
Net actuarial loss
 
   
(In thousands)
 
                   
Amount in AOCI not yet recognized in net periodic cost (income) at beginning of year
  $ 2     $ 165     $ -  
Experience loss (gain)
    -       914       183  
Regulatory asset (liability) adjustment
    -       (38 )     (183 )
Amortization recognized in net periodic cost
    -       (1 )     -  
Amount in AOCI not yet recognized in net periodic cost (income) at end of year
  $ 2     $ 1,040     $ -  
                         
Amortization expected to be recognized in AOCI in 2010
  $ -     $ (32 )   $ -  

The following table presents the components of net periodic cost recognized in the Consolidated Statements of Earnings:

   
Pension Benefits
 
   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
PNM Plan
                 
Service cost
  $ 59     $ 56     $ 57  
Interest cost
    1,135       1,136       1,088  
Amortization of net loss
    27       52       93  
Amortization of prior service cost
    10       13       13  
     Net periodic benefit cost
  $ 1,231     $ 1,257     $ 1,251  
TNMP Plan
                       
Service cost
  $ -     $ -     $ -  
Interest cost
    76       75       76  
Amortization of actuarial loss
    -       -       -  
Amortization of prior service cost
    -       -       -  
     Net periodic benefit cost
  $ 76     $ 75     $ 76  


 
B-85

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The following significant weighted-average assumptions were used to determine the projected benefit obligation and net periodic cost (income).  Should actual experience differ from actuarial assumptions, the projected benefit obligation and net periodic cost would be affected.

 
Year Ended December 31,
PNM Plan
2009
 
2008
 
2007
Discount rate for determining projected benefit obligation
         
  at December 31
6.47%
 
7.25%
 
6.88%
Discount rate for determining net pension cost
7.25%
 
6.88%
 
6.10%
Long-term rate of return on plan assets
N/A
 
N/A
 
N/A
Rate of compensation increase
N/A
 
N/A
 
N/A
TNMP Plan
         
Discount rate for determining projected benefit obligation
         
  at December 31
6.31%
 
7.25%
 
6.72%
Discount rate for determining net periodic cost
7.25%
 
6.72%
 
6.10%
Long-term rate of return on plan assets
N/A
 
N/A
 
N/A
Rate of compensation increase
N/A
 
N/A
 
N/A

The assumed discount rate for determining the PBO was determined based on a review of long-term high-grade bonds and management’s expectations. The change in discount rate resulted in a decrease in the PNM and TNMP PBO of $1.0 million and less than $0.1 million at December 31, 2009.

The following executive retirement plan payments, which reflect expected future service, are expected:

   
PNM
   
TNMP
 
   
Plan
   
Plan
 
   
(In thousands)
 
             
             
2010
  $ 1,442     $ 91  
2011
  $ 1,422     $ 90  
2012
  $ 1,404     $ 89  
2013
  $ 1,384     $ 88  
2014
  $ 1,362     $ 86  
Years 2014 – 2018
  $ 6,381     $ 392  

Other Retirement Plans

PNMR sponsors a 401(k) defined contribution plan for eligible employees, including those of its subsidiaries.  PNMR’s contributions to the 401(k) plan consist of a discretionary matching contribution equal to 75% of the first 6% of eligible compensation contributed by the employee on a before-tax basis.   PNMR also makes a non-matching contribution ranging from 3% to 10% of eligible compensation based on the eligible employee’s age.

PNMR also provides executive deferred compensation benefits through an unfunded, non-qualified plan. The purpose of this plan is to permit certain key employees of PNMR who participate in the 401(k) defined contribution plan to defer compensation and receive credits without reference to the certain limitations on contributions. In December of 2008, an earlier version of this plan, which was frozen in 2004, was merged into this plan. Effective January 1, 2009, PNMR allowed eligible employees to save on an after-tax basis.


 
B-86

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


A summary of expenses for these other retirement plans is as follows:

   
Year ended December 31,
 
   
2009
   
2008
   
2007
 
         
(In thousands)
       
PNMR
                 
     401(k) plan
  $ 16,743     $ 16,766     $ 17,050  
     Non-qualified plan
    2,073       (1,444 )     1,722  
PNM
                       
     401(k) plan
    11,698       10,844       11,803  
     Non-qualified plan
    1,299       (979 )     525  
TNMP
                       
     401(k) plan
    3,323       2,869       3,061  
     Non-qualified plan
    405       (288 )     157  

 

(13)    Stock-Based Compensation Plans

PNMR has various types of stock-based compensation programs, including stock options, restricted stock and performance shares granted under the Performance Equity Plan (“PEP”).  All stock-based compensation is granted through stock-based employee compensation plans maintained by PNMR.  Although certain PNM and TNMP employees participate in the PNMR plans, PNM and TNMP do not have separate employee stock-based compensation plans.

Performance Stock Plan

PNMR’s Performance Stock Plan (“PSP”) expired in December 2000.  The PSP was a non-qualified stock option plan, covering a group of management employees.  Options to purchase shares of PNMR’s common stock were granted at the fair value of the shares at the close of business on the date of the grant.  Although the authority to grant options under the PSP expired on December 31, 2000, the options that were granted continue to be effective according to their terms.

Performance Equity Plan

The PEP provides for the granting of non-qualified stock options, restricted stock rights, performance shares, performance units, and stock appreciation rights to officers, key employees, and non-employee board members.  Generally, the awards vest ratably over three years from the grant date of the award.  However, plan provisions provide that upon retirement, participants become 100% vested in stock awards.  The total number of shares of PNMR common stock subject to all awards under the PEP may not exceed 12.32 million, subject to adjustment under certain circumstances defined in the PEP.  The number of shares of PNMR common stock subject to the grant of restricted stock rights, performance shares and units and stock appreciation rights is limited to 1.56 million shares.  Re-pricing of stock options is prohibited unless specific shareholder approval is obtained.

Source of Shares

The source of shares for exercised stock options, delivery of vested restricted stock, and performance shares is shares acquired on the open market, rather than newly issued shares.

Accounting for Stock Awards

The Company accounts for stock awards utilizing the modified prospective approach for all new awards and awards that were outstanding on January 1, 2006 that are subsequently modified, repurchased or cancelled.  Compensation expense recognized after January 1, 2006 is based on the grant-date fair value estimated in
 
B-87

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

accordance with GAAP and includes compensation cost for all share-based payments granted prior to, but not yet vested as of January 1, 2006, and for all share-based payments granted subsequent to January 1, 2006.

The unearned stock-based compensation related to stock options and restricted stock awards is being amortized to compensation expense over the requisite vesting period, which is generally equally over three years.  However, compensation expense for stock options and restricted stock awards to participants that are retirement eligible on the grant date is recognized immediately at the grant date and is not amortized over the vesting period. The Company records compensation cost for performance stock awards based upon periodic estimates of the levels that the performance targets will be achieved.

Total compensation expense for stock-based payment arrangements recognized by PNMR for the years ended December 31, 2009, 2008 and 2007 was $2.2 million, $3.3 million, and $7.6 million.  Of this total expense, $1.4 million, $2.4 million, and $6.1 million were charged to PNM and $0.5 million, $0.6 million, and $1.1 million were charged to TNMP.

PNMR receives a tax deduction for certain stock option exercises during the period the options are exercised, generally for the excess of the price at which the options are sold over the exercise prices of the options and a tax deduction for increases in the value of equity instruments issued under stock-based payment arrangements.  PNMR’s Consolidated Statements of Cash Flows presentation reports the tax benefits from the exercise of stock options and stock-based payments as financing cash flows.

At December 31, 2009, PNMR had $1.8 million of unrecognized compensation expense related to stock-based payments that is expected to be recognized over a weighted-average period of 1.7 years.

Stock Options

The Company uses the Black-Scholes option pricing model to estimate the fair value of stock-based awards with the following weighted-average assumptions for the indicated periods:


   
2009
   
2008
   
2007
 
                   
Dividend yield
    6.27 %     6.99 %     3.02 %
Expected volatility
    42.03 %     28.33 %     18.68 %
Risk-free interest rates
    1.56 %     2.69 %     4.72 %
Expected life (years)
                       4.5                           4.2                           4.2  

The assumptions above are based on multiple factors, including historical exercise patterns of employees in relatively homogeneous groups with respect to exercise and post-vesting employment termination behaviors, expected future exercising patterns for these same homogeneous groups and both the implied and historical volatility of PNMR’s stock price.


 
B-88

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The following table summarizes activity in stock option plans:

         
Weighted
     
Weighted
   
Stock
   
Average
 
Aggregate
 
Average
   
Option
   
Exercise
 
Intrinsic
 
Remaining
   
Shares
   
Price
 
Value
 
Contract Life
                   
Outstanding at December 31, 2006
    2,999,606     $ 21.02        
Granted
    766,400     $ 30.47        
Exercised
    (442,252 )   $ 20.32        
Forfeited
    (40,177 )   $ 27.45        
Expired
    (18,679 )   $ 20.48        
Outstanding at December 31, 2007
    3,264,898     $ 23.26        
Granted
    558,261     $ 11.90        
Exercised
    (5,001 )   $ 16.13        
Forfeited
    (19,075 )   $ 26.49        
Expired
    (73,176 )   $ 22.04        
Outstanding at December 31, 2008
    3,725,907     $ 21.54        
Granted
    790,064     $ 8.23        
Exercised
    (6,236 )   $ 10.22        
Forfeited
    (69,200 )   $ 16.40        
Expired
    (166,516 )   $ 21.32        
Outstanding at December 31, 2009
    4,274,019     $ 19.19  
$3,966,376*
 
5.97 years
Exercisable at December 31, 2009
    3,054,849     $ 26.85  
$  269,646
 
4.93 years
Options available for future grant**
    5,133,798                

*  At December 31, 2009, the exercise price of 3,275,542 outstanding stock options is greater than the closing price of PNMR common stock on that date so those options have no intrinsic value.
**    Includes shares available for grants of restricted stock.

The following table summarizes stock option activity for the years ended December 31:

Stock Options
 
2009
   
2008
   
2007
 
 
   
(In thousands,
except per share amounts)
               
Weighted-average grant date fair value of options granted
  $ 1.63     $ 1.39     $ 4.70  
Total fair value of options that vested during the period
  $ 1,179     $ 4,003     $ 4,670  
Total intrinsic value of options exercised during the period
  $ 15     $ 15     $ 4,931  


 
B-89

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


Restricted Stock and Performance Shares

The PEP allows for the issuance of restricted stock awards.  As noted above, “restricted stock” is the name of these awards provided for in the PEP and refers to awards of stock subject to vesting.  It does not refer to restricted shares with contractual post-vesting restrictions as defined in GAAP.  Compensation expense for restricted stock and performance stock awards was determined based on the market price of PNMR stock on the date of grant reduced by the present value of future dividends applied to the total number of shares that were anticipated to fully vest with the following weighted-average assumptions for the indicated periods:

   
2009
 
2008
 
2007
Expected quarterly dividends per share
 
$0.125
 
$0.23
 
$0.23
Risk-free interest rate
 
3.11%
 
2.93%
 
4.71%

The following table summarizes nonvested restricted stock activity for the year ended December 31, 2009:

         
Weighted-
 
         
Average
 
         
Grant-Date
 
Nonvested Restricted Stock
 
Shares
   
Fair Value
 
             
Nonvested at beginning of period
    195,626     $ 17.43  
Granted
    102,000     $ 7.81  
Vested
    (99,349 )   $ 19.13  
Forfeited
    (4,336 )   $ 12.24  
Nonvested at end of period
    193,941     $ 11.62  

The following table summarizes restricted stock activity for the year ended December 31:

Nonvested Restricted Stock
 
2009
   
2008
   
2007
 
   
(In thousands,
except per share amounts)
 
Weighted-average grant date fair value of shares granted
  $ 7.81     $ 11.50     $ 28.79  
Total fair value of shares that vested during the period
  $ 1,900     $ 2,365     $ 1,961  

During 2009, the Company issued performance share agreements to certain executives that are based upon the Company achieving specified performance targets, partly for 2009 and partly for the 2009 through 2011 period.  The determination of the number of shares ultimately issued depends on the levels at which the performance criteria are achieved and cannot be determined until after the performance periods end. For the targets based only on 2009 performance, the optimal level was attained and 106,969 shares were earned and will vest through 2013.  The Company would issue an additional maximum of 46,317 shares if all of the performance criteria based on the 2009 through 2011 period are achieved at the maximum level and all the executives remain eligible.

ESPP

PNMR terminated the ESPP effective June 30, 2009.  Under the ESPP, employees were allowed to purchase shares of PNMR’s common stock at a 5% discount from the market price.  The ESPP was not considered to be a compensatory plan.  Under the ESPP, 48,202, 92,224, and 55,885 were issued during the years ended December 31, 2009, 2008, and 2007.  The source of shares for the ESPP was newly issued shares.


 
B-90

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


(14)
Construction Program and Jointly-Owned Electric Generating Plants

Joint Projects

PNMR’s construction expenditures for 2009 were $288.0 million, including expenditures on PNM’s jointly-owned projects and including $3.4 million for PNM Gas.  TNMP does not participate in the ownership or operation of any generating plants, but incurred construction expenditures of $53.1 million during 2009.

PNM’s construction expenditures for 2009 were $256.8 million, including expenditures on jointly-owned projects, including $39.1 million for the purchase of an interest in PVNGS Unit 2 from another subsidiary of PNMR (see Note 17).  Under the agreements for the jointly-owned projects, PNM has an undivided interest in each asset and liability of the project and records its pro-rata share of each item in the corresponding asset and liability account on PNM’s Consolidated Balance Sheets.  Likewise, PNM records its pro-rata share of each item of operating and maintenance expenses for its jointly-owned plants within the corresponding operating expense account in its Consolidated Statements of Earnings.

At December 31, 2009, PNM’s interests and investments in jointly-owned generating facilities are:


 
 
Station (Fuel Type)
 
Plant in
Service
   
Accumulated
Depreciation
   
Construction
Work in
Progress
   
Composite
Interest
 
              (In thousands)           
                                 
SJGS (Coal)
  $ 926,580     $ (424,429 )   $ 26,990       46.30 %
PVNGS (Nuclear) *
    423,586       (110,049 )     41,178       10.20 %
Four Corners Units 4 and 5 (Coal)
    144,428       (103,530 )     7,735       13.00 %
Luna (Gas)
    56,822       (8,183 )     274       33.33 %

* Includes interest in PVNGS Unit 3, interest in common facilities for all PVNGS units, and owned interests in PVNGS Units 1 and 2.


San Juan Generating Station

PNM operates and jointly owns the SJGS.  SJGS Units 1 and 2 are owned on a 50% shared basis with Tucson.  SJGS Unit 3 is owned 50% by PNM, 41.8% by SCPPA, and 8.2% by Tri-State.  SJGS Unit 4 is owned 38.457% by PNM, 28.8% by M-S-R Public Power Agency, 10.04% by the City of Anaheim, California, 8.475% by the City of Farmington, New Mexico, 7.2% by the County of Los Alamos, New Mexico, and 7.028% by UAMPS.

Palo Verde Nuclear Generating Station

PNM is a participant in the three units of PVNGS, also known as the Arizona Nuclear Power Project, with APS (the operating agent), SRP, EPE, SCE, SCPPA and The Department of Water and Power of the City of Los Angeles.  PNM has a 10.2% undivided interest in PVNGS, with portions of its interests in Units 1 and 2 held under leases.


 
B-91

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


    Operation of each of the three PVNGS units requires an operating license from the NRC.  The NRC issued full power operating licenses for Unit 1 in June 1985, Unit 2 in April 1986 and Unit 3 in November 1987.  The full power operating licenses are valid for a period of approximately 40 years.  APS, on behalf of the PVNGS participants, applied for renewed operating licenses for each unit on December 15, 2008 for a period of 20 years beyond the expirations of the current licenses.  The NRC is currently reviewing the application. The current NRC schedule for the applications estimates a final decision in the fall of 2011.  The PVNGS participants do not anticipate any problems renewing these licenses.  However, as a result of potential terrorist threats and increased public scrutiny of utilities, the licensing process could result in increased licensing or compliance costs that are difficult or impossible to predict.
 
Four Corners Power Plant

PNM is a participant in two units of Four Corners with APS (the operating agent), EPE, SRP, SCE, and Tucson.  PNM has a 13.0% undivided interest in Units 4 and 5 of Four Corners.  The Four Corners plant site is leased from the Navajo Nation and is also subject to an easement from the federal government.

Luna Energy Facility

Luna is a combined-cycle power plant near Deming, New Mexico.  Luna is owned 33.3% by PNM, 33.3% by Tucson and 33.3% by Freeport McMoran, (formerly Phelps Dodge).  Prior to July 2009, Luna was operated as a PNM wholesale facility and PNM’s 190-megawatt share of its power was sold to wholesale electric customers in the Southwest.  Beginning in July 2009, Luna is included in rates subject to the jurisdiction of the NMPRC.  See Note 17.  The operation and maintenance of the facility has been contracted to North American Energy Services.


Construction Program

The Company anticipates making substantial capital expenditures for the construction and acquisition of utility plant and other property and equipment.  A summary of the budgeted construction expenditures, including expenditures for jointly-owned projects, renewable energy projects, and nuclear fuel, is as follows:


   
2010
   
2011
   
2012
   
2013
   
2014
   
Total
 
   
(In millions)
       
PNM
  $ 228.8     $ 412.6     $ 190.9     $ 183.9     $ 167.4     $ 1,183.6  
TNMP
    41.4       60.4       45.0       41.4       55.5       243.7  
Other
    14.9       16.2       16.1       18.1       17.2       82.5  
Total PNMR
  $ 285.1     $ 489.2     $ 252.0     $ 243.4     $ 240.1     $ 1,509.8  


 
B-92

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


(15)
Asset Retirement Obligations

    The ARO is recorded based on the determination of underlying assumptions, such as the Company’s discount rate, estimates of the future costs for decommissioning, and the timing of the removal activities to be performed.  Any changes in these assumptions underlying the required calculations may require revisions to the estimated ARO when identified.  A reconciliation of ARO is as follows:

   
PNMR
   
PNM
   
TNMP
 
   
(In thousands)
 
                   
Liability at December 31, 2006
  $ 61,338     $ 60,493     $ 686  
Liabilities incurred
    204       205       -  
Liabilities settled
    (8 )     -       (8 )
Accretion expense
    5,204       5,142       52  
Asset transferred with TNMP New Mexico asset transfer to PNM
    -       68       (68 )
Asset transferred with Twin Oaks contribution to Optim Energy
    (89 )     -       -  
Liability at December 31, 2007 (1)
    66,649       65,908       662  
Liabilities incurred
    548       548       -  
Liabilities settled
    (49 )     (42 )     (7 )
Accretion expense
    4,928       4,866       56  
Revisions to estimated cash flows(2)
    (8,401 )     (8,401 )     -  
Liability at December 31, 2008(1)
    63,675       62,879       711  
   Liabilities incurred
    3,464       3,464       -  
   Liabilities settled
    (8 )     (8 )     -  
   Accretion expense
    5,751       5,683       60  
   Revisions to estimated cash flows (2)
    (1,919 )     (1,919 )     -  
Liability at December 31, 2009
  $ 70,963     $ 70,099     $ 771  

 
(1)
ARO for PNMR and PNM includes $0.2 million and $0.2 million at December 31, 2008 and 2007 for PNM Gas, which is reflected as discontinued operations.
 
(2)
Based on studies to estimate amount and timing of future ARO expenditures.

(16)
Commitments and Contingencies

Overview

There are various claims and lawsuits pending against the Company.  The Company is also subject to federal, state and local environmental laws and regulations, and is currently participating in the investigation and remediation of numerous sites.  In addition, the Company periodically enters into financial commitments in connection with its business operations.  The Company is also involved in various legal proceedings in the normal course of its business.  It is not possible at this time for the Company to determine fully the effect of all litigation and other legal proceedings on its results of operations or financial position.  It is the Company’s policy to accrue for expected liabilities in accordance with GAAP when it is probable that a liability has been incurred and the amount to be incurred is reasonably estimable.  The Company cannot make any assurances that the amount of reserves or potential insurance coverage will be sufficient to cover the cash obligations that might be incurred as a result of litigation or regulatory proceedings.   Outside legal costs for these and regulatory matters are recorded when the expenses are incurred.  The Company does not expect that any known lawsuits, environmental costs, and commitments will have a material adverse effect on its financial condition, results of operations, or cash flows, although the outcome of litigation, investigations, and other legal proceedings is inherently uncertain.
 
B-93

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


With respect to some of the items listed below, the Company has determined that a loss is not probable or that, to the extent probable, is not reasonably estimable.  In some cases, the Company is not able to predict with any degree of certainty the range of possible loss that could be incurred.  Notwithstanding these facts, the Company has assessed these matters based on current information and made judgments concerning their potential outcome, giving due consideration to the nature of the claim, the amount and nature of damages sought, and the probability of success.  Such judgments are made subject to the known uncertainty of litigation.  The Company has established appropriate reserves for matters where it is probable a loss has been incurred and the amount of loss is reasonably estimable.  The actual outcomes of the items listed below could ultimately differ from the judgments made and the differences could be material.

Commitments and Contingencies Related to the Environment

PVNGS Decommissioning Funding

PNM has a program for funding its share of decommissioning costs for PVNGS. The nuclear decommissioning funding program is invested in equities and fixed income instruments in qualified and non-qualified trusts.

PNM provided an additional $3.0 million, $3.5 million, and $7.9 million funding for the years ended December 31, 2009, 2008, and 2007 into the qualified and non-qualified trust funds.  The estimated market value of the trusts at December 31, 2009 and 2008 was $137.0 million and $111.7 million.

Nuclear Spent Fuel and Waste Disposal

Nuclear power plant operators are required to enter into spent fuel disposal contracts with the DOE, and the DOE is required to accept and dispose of all spent nuclear fuel and other high-level radioactive wastes generated by domestic power reactors.  Although the Nuclear Waste Policy Act required the DOE to develop a permanent repository for the storage and disposal of spent nuclear fuel by 1998, the DOE has announced that the repository cannot be completed before at least 2017.  In November 1997, the U.S. Court of Appeals for the District of Columbia Circuit issued a decision preventing the DOE from excusing its own delay, but refused to order the DOE to begin accepting spent nuclear fuel.  Based on this decision and the DOE’s delay, a number of utilities, including APS (on behalf of itself and the other PVNGS owners including PNM), filed damages actions against the DOE in the Court of Federal Claims and are currently pursuing those damages claims. In August 2008, the United States Court of Appeals for the Federal Circuit issued decisions in three damages actions brought by other nuclear utilities that could result in a decrease in the amount of PNM’s recoverable damages; however, additional appeals in those actions are possible and APS continues to monitor the status of those actions.  The trial in the APS matter began on January 28, 2009 and closing arguments were heard in late May.  The court has not indicated when it will reach its decision in the matter.  In January 2010, on appeal of another utility’s damages case in which the DOE successfully raised the unavoidable delays defense, the U.S. Court of Appeals for the Federal Circuit reversed the lower court’s decision and concluded that the U.S. Court of Federal Claims, which is the court handling the APS matter, is bound by the November 1997 District of Columbia Circuit Court decision that prevents the DOE from excusing its delay in performance.  PNM currently estimates that it will incur approximately $46.1 million (in 2007 dollars) over the current life of PVNGS for its share of the fuel costs related to the on-site interim storage of spent nuclear fuel during the operating life of the plant.  PNM accrues these costs as a component of fuel expense, meaning that the charges are accrued as the fuel is burned.  At December 31, 2009 and 2008, PNM had $15.0 million and $14.5 million recorded as a liability on its Consolidated Balance Sheets for interim storage costs.


 
B-94

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The Clean Air Act

Regional Haze

The EPA has established rules addressing regional haze and guidelines for BART determinations. The rule calls for all states to establish goals and emission reduction strategies for improving visibility in national parks and wilderness areas.   In particular, the alternatives rule defines how an SO2 emissions trading program developed by the Western Regional Air Partnership, a voluntary organization of western states, tribes and federal agencies, can be used by western states.  New Mexico will be participating in the SO2 program, which is a trading program that will be implemented if SO2 reduction milestones, which are still being developed, are not met.

In November 2006, the NMED requested a BART analysis for NOX and particulates for each of the four units at SJGS.  PNM submitted the analysis to the NMED in early June 2007, recommending against installing additional pollution control equipment on any of the SJGS units beyond those planned at that time, the installation of which was recently completed.  PNM has provided additional data in response to requests from the NMED.  The NMED is presently reviewing the analysis and supplemental data.  Potentially, additional NOX emission reductions could be required.  The nature and cost of compliance with these potential requirements cannot be determined at this time.
 
 The EPA previously requested APS to perform a BART analysis for Four Corners.  APS submitted an analysis to the EPA concluding that certain combustion control equipment constitutes BART for Four Corners.  Based on the analyses and comments received through EPA’s rulemaking process, the EPA will determine what it believes constitutes BART for Four Corners.  The EPA recently issued an Advanced Notice of Proposed Rulemaking (“ANPR”) seeking public comments on its BART determination.  The public comment period initially expired in October 2009, but the EPA has extended the comment period until March 20, 2010.  APS anticipates the EPA will issue proposed and final BART determinations for Four Corners in 2010.  The participant owners of Four Corners will have five years after the EPA issues its final determination to achieve compliance with their respective BART requirements.  In addition, on February 16, 2010, a group of environmental organizations filed a petition with the U.S. Departments of Interior and Agriculture requesting those agencies to certify to the EPA that visibility impairment in sixteen national park and wilderness areas is reasonably attributable to emissions from Four Corners.  If the agencies certify impairment, the EPA is required to evaluate and, if necessary, determine BART for Four Corners. APS’ recommended plan for Four Corners includes the installation of combustion control equipment with an estimated cost to PNM, based on preliminary engineering estimates, of approximately $6.8 million.  If the EPA determines that post-combustion controls are required, PNM’s total costs could be up to approximately $69.0 million for Four Corners.  The obligation to comply with the EPA’s final BART determinations, coupled with the financial impact of future climate change legislation, other environmental regulations, and other business considerations, could jeopardize the economic viability of the Four Corners plant or the ability of individual participants to continue their participation in it.  In order to coordinate with Four Corners’ other scheduled activities, APS is currently implementing portions of its recommended plan on a voluntary basis.  Costs related to the implementation of these portions of the recommended plan are included in PNM’s 2009, 2010 and 2011 construction expenditure estimates.
 
While the Company continues to monitor these matters, at the present time, the Company cannot predict whether the agencies will agree with either PNM’s or APS’ BART recommendations.  If the agencies disagree with those recommendations for SJGS or Four Corners, the Company cannot predict the nature of the BART controls the agencies may ultimately mandate or the resulting financial or operational impact.

Citizen Suit Under the Clean Air Act

The operations of the SJGS are covered by a consent decree with the Grand Canyon Trust and Sierra Club and with the NMED that includes a provision whereby stipulated penalties are assessed for non-compliance with specified emissions limits.  Stipulated penalty amounts are placed in escrow on a quarterly basis pending review of SJGS’s emissions performance for each quarter.  As of December 31, 2008, PNM’s share of the total amount of stipulated penalties was $3.4 million, which had been deposited into the escrow account and was paid in 2009.  Subsequent penalties have been insignificant.
 
B-95

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

Ozone Non-Attainment

In March 2009, the NMED published its draft recommendation of area designations for the 2008 revised ozone national ambient air quality standard.  The draft recommended that San Juan County, New Mexico be designated as non-attainment for ozone.  SJGS is situated in San Juan County.  However, the NMED subsequently determined that the monitor indicating high ozone levels was not reliable and did not recommend to the EPA that San Juan County be designated as non-attainment.  On January 6, 2010, EPA announced it would strengthen the 8-hour ozone standard by setting the standard in a range of 0.060-0.070 parts per million (“ppm”).  The EPA will make its final determination of the exact number by August 31, 2010.  If EPA sets the standard at 0.070 ppm, it is projected that San Juan County and Dona Ana County will be designated as non-attainment for ozone.  If the standard is set lower than 0.070 ppm, other counties in the state, including Bernalillo County, may be designated as non-attainment.  A non-attainment designation for San Juan County could result in the requirement to reduce NOx emissions from San Juan Generating Station by 2014.  The Company cannot predict the outcome of this matter or if additional NOX controls would be required as a result of ozone non-attainment designation.

Navajo Nation Environmental Issues

Four Corners is located on the Navajo Reservation and is held under an easement granted by the federal government as well as a lease from the Navajo Nation.  The Navajo Acts, enacted in 1995 by the Navajo Nation, purport to give the Navajo Nation Environmental Protection Agency authority to promulgate regulations covering air quality, drinking water, and pesticide activities, including those activities that occur at Four Corners.  In October 1995, the Four Corners participants filed a lawsuit in the District Court of the Navajo Nation, Window Rock District, challenging the applicability of the Navajo Acts as to Four Corners.  The District Court stayed these proceedings pursuant to a request by the parties and the parties are seeking to negotiate a settlement.

In 2000, the Navajo Tribal Council approved operating permit regulations under the Navajo Nation Air Pollution Prevention and Control Act.  The Four Corners participants believe that the regulations fail to recognize that the Navajo Nation did not intend to assert jurisdiction over Four Corners.  Each of the Four Corners participants filed a petition with the Navajo Nation Supreme Court for review of the operating permit regulations.  Those proceedings have been stayed, pending the outcome of the settlement negotiations mentioned above.

In May 2005, APS and the Navajo Nation signed a Voluntary Compliance Agreement (“VCA”) resolving the dispute regarding the Navajo Nation Air Pollution Prevention and Control Act portion of the lawsuit.  On March 21, 2006, the EPA determined that the Navajo Nation was eligible for “treatment as a state” for the purpose of entering into a supplemental delegation agreement with the EPA to administer the Clean Air Act Title V, Part 71 federal permit program over Four Corners.  The EPA entered into the supplemental delegation agreement with the Navajo Nation on the same day.  Because the EPA’s approval was consistent with the requirements of the VCA, APS sought dismissal of the pending litigation in the Navajo Nation Supreme Court, as well as the pending litigation in the Navajo Nation District Court to the extent the claims relate to the Clean Air Act, and the Courts have dismissed the claims accordingly. The agreement does not address or resolve any dispute relating to other aspects of the Navajo Acts.
 
The Company cannot currently predict the outcome of these matters.
 
Four Corners Federal Implementation Plan Litigation
 
On April 30, 2007, the EPA adopted a source specific FIP to set air quality standards at Four Corners.  The FIP essentially federalizes the requirements contained in the New Mexico State Implementation Plan, which Four Corners has historically followed.  The FIP also includes a requirement to maintain and enhance dust suppression methods.  APS filed a petition for review in the U.S. District Court of Appeals for the Tenth Circuit seeking revisions to the FIP to clarify certain requirements and allow operational flexibility.  The Sierra Club intervened in this action and with other parties filed a petition for review with the same court challenging the FIP’s compliance with the Clean Air Act.  APS intervened in that action.  In APS’ lawsuit, APS challenged two key provisions of the
 
B-96

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

FIP:  a 20% opacity limit on certain fugitive dust emissions and a 20% stack opacity limit on Units 4 and 5.  During 2008, the EPA voluntarily moved to vacate the fugitive dust provisions of the FIP, and on April 14, 2009, the court granted EPA’s motion.  The court also rejected the Sierra Club’s challenges to the FIP and ruled in favor of the 20% stack opacity limit.  APS filed a petition for rehearing related to the stack opacity limit finding because APS did not believe that EPA properly established that limit.  The court denied APS’s petition on July 24, 2009, and APS does not intend to appeal the matter further.  The Company does not believe that compliance with this limit will have a material adverse impact on the Company’s financial position, results of operations or cash flows.
 
Section 114 Request
 
On April 6, 2009, APS received a request from the EPA under Section 114 of the Clean Air Act seeking detailed information regarding projects at and operations of Four Corners.  This request is part of an enforcement initiative that the EPA has undertaken under the Clean Air Act.  The EPA has taken the position that many utilities have made certain physical or operational changes at their plants that should have triggered additional regulatory requirements under the NSR provisions of the Clean Air Act.  Other electric utilities have received and responded to similar Section 114 requests, and several of them have been the subject of notices of violation and lawsuits by the EPA.  APS has responded to the EPA’s request.  The Company is currently unable to predict the timing or content of EPA’s response or any resulting actions.
 
Santa Fe Generating Station

PNM and the NMED conducted investigations of gasoline and chlorinated solvent groundwater contamination detected beneath the site of the former Santa Fe Generating Station to determine the source of the contamination pursuant to a 1992 settlement agreement between PNM and the NMED.

PNM believes that the data compiled indicates observed groundwater contamination originated from off-site sources.  However, to avoid a prolonged legal dispute, PNM entered into settlement agreements with the NMED under which PNM agreed to install a remediation system to treat water from a City of Santa Fe municipal supply well and install an additional extraction well and two new monitoring wells to address gasoline contamination in the groundwater at and in the vicinity of the site.  PNM will continue to operate the remediation facilities until the groundwater meets applicable federal and state standards or until such time as the NMED determines that additional remediation is not required, whichever is earlier.  The well continues to operate and meets federal drinking water standards.  PNM is not able to assess the duration of this project.

The Superfund Oversight Section of the NMED has conducted multiple investigations into the chlorinated solvent plume in the vicinity of the site of the former Santa Fe Generating Station   In February 2008, a NMED site inspection report was submitted to the EPA, which states that neither the source nor extent of contamination has been determined and also states that the source may not be the former Santa Fe Generating Station.  The NMED investigation is ongoing.  The Company is unable to predict the outcome of this matter.

Coal Combustion Waste Disposal

Regulation

SJGS does not operate any CCB impoundments.  SJCC currently disposes of CCBs consisting of fly ash, bottom ash, and gypsum from SJGS in the surface mine pits adjacent to the plant.  APS currently disposes of CCBs in ash ponds and dry storage areas at Four Corners, and also sells a portion of its fly ash for beneficial uses, such as a constituent in concrete production.  The Mining and Minerals Division of the New Mexico Energy, Minerals and Natural Resources Department currently regulates mine placement of ash at the mine with federal oversight by the U.S. Department of Interior’s Office of Surface Mining (“OSM”).  The OSM has developed draft proposed regulations for the mine placement of CCBs.  OSM’s rulemaking effort is currently tabled by the Obama Administration.
 
B-97

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

    The EPA is considering a proposal to regulate CCBs, but the timing of the release of EPA’s proposal is unclear.   It is possible that the EPA could classify CCBs as a hazardous waste.  PNM continues to advocate for the non-hazardous regulation of CCBs, believing the proper place for oversight of mine placement of CCBs is through the OSM and state mining and mining reclamation agencies. PNM cannot predict the outcome of the EPA’s actions regarding CCB regulation and whether such actions will have a material adverse impact on its operations or financial position.  However, if the regulation ultimately prevents the CCBs from SJGS to be disposed of in the adjacent mine, the increased costs of disposal could be significant, which would negatively impact PNM.  The Company’s results of operations would be negatively impacted unless the costs are recovered in PNM’s customer rates.

Sierra Club Allegations

In December 2009, PNM received a Notice of Intent to Sue (“RCRA Notice”) under the Resource Conservation and Recovery Act ("RCRA") from the Sierra Club.  The RCRA Notice was also sent to all SJGS owners and to SJCC, which operates the San Juan Mine.  The Sierra Club alleges that activities at SJGS and the San Juan Mine are causing imminent and substantial harm to the environment, including ground and surface water in the region, and that placement of CCBs at the San Juan Mine constitute "open dumping" in violation of RCRA.  Additionally, PNM has been informed that SJCC has received a separate Notice of Intent to Sue (“SMCRA Notice”) under the Surface Mine Control and Reclamation Act ("SMCRA") from the Sierra Club.  The SMCRA Notice alleges similar damage to the environment due to activities at the San Juan Mine, including the placement of CCBs from SJGS in the surface pits at the mine.  Both Notices state Sierra Club's intent to file citizens’ suits to pursue these claims upon expiration of the statutory notice period.  If suits are filed, potential remedies include the imposition of civil penalties and injunctive relief.  PNM plans an aggressive defense of the RCRA claims and cannot predict the outcome of these matters at this time. 

Gila River Indian Reservation Superfund Site
 
In April 2008, the EPA informed PNM that it may be a PRP in the Gila River Indian Reservation Superfund Site in Maricopa County, Arizona.  PNM, along with SRP, APS and EPE, owns a parcel of property on which a transmission pole and a portion of a transmission line are located.  The property abuts the Gila River Indian Community boundary and, at one time, may have been part of an airfield where crop dusting took place.  Currently, the EPA is only seeking payment from PNM and other PRPs for past cleanup-related costs involving contamination from the crop dusting.  Based upon the total amount of cleanup costs reported by the EPA in its letter to PNM, the resolution of this matter is not expected to have a material adverse impact on PNM’s financial position, results of operations, or cash flows.
 
Other Commitments and Contingencies

Coal Supply

Twin Oaks

Altura is the owner of Twin Oaks, a coal-fired power plant, which is being supplied by a long-term coal supply agreement.  Altura is not responsible under this agreement for the decommissioning or reclamation costs of this mine.  PNMR originally guaranteed Altura’s performance under this agreement.  On June 1, 2007, when PNMR contributed its ownership interest of Altura to Optim Energy, the guarantee obligation of PNMR was released.


 
B-98

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


PNM

The coal requirements for SJGS are being supplied by SJCC, a wholly owned subsidiary of BHP Billiton.  SJCC holds certain federal, state and private coal leases under an underground coal sales agreement pursuant to which it will supply processed coal for operation of the SJGS through 2017.  The coal agreement is a cost plus contract.  SJCC is reimbursed for all costs for mining and delivering the coal plus an allocated portion of administrative costs.  In addition, SJCC receives a return on its investment.  BHP Minerals International, Inc. has guaranteed the obligations of SJCC under the coal agreement.  The coal agreement contemplates the delivery of approximately 61 million tons of coal during its remaining term, which would supply substantially all the requirements of the SJGS through approximately 2017.  The coal agreement replaced two surface mining operations with a single underground mine located adjacent to the plant.

    APS purchases all of Four Corners’ coal requirements from a supplier with a long-term lease of coal reserves with the Navajo Nation.  The Four Corners coal contract runs through 2016, with options on APS’ part to extend the contract for five to fifteen additional years.  The Four Corners plant site is leased from the Navajo Nation and is also subject to an easement from the federal government.

    In 2003, PNM completed a comprehensive review of the final reclamation costs for both the surface mines that previously provided coal to SJGS and the current underground mine providing coal.  Based on this study, PNM revised its estimates of the final reclamation costs.  In addition, the mining contract for Four Corners has been renewed until 2016 and the estimate for decommissioning the Four Corners mine was also revised.  In 2009, these studies were updated.  Based on the most recent estimates, the total final cost of surface and underground mine reclamation are estimated to be $141.1 million and $23.3 million in future dollars excluding contract buyout costs paid to SJCC.  During the year ended December 31, 2009, 2008 and 2007, PNM made payments of $7.6 million, $12.7 million, and $11.4 million against the surface mine liability.  As of December 31, 2009, and 2008, obligations of $26.6 million and $33.8 million for surface mine reclamation and $2.3 million and $1.6 million for underground mining activities were recognized on PNM’s Consolidated Balance Sheets using the fair value method to determine the liability.

    In 2003, the NMPRC granted PNM permission to collect as a part of its rates up to $100.0 million of surface mine final reclamation costs.  In the 2007 Electric Rate Case, PNM requested recovery of increased surface mine decommissioning costs, as well as underground mine reclamation costs. Recovery of the final underground mine reclamation costs was allowed; however, the NMPRC denied recovery of amounts for surface mine decommissioning in excess of $100.0 million. PNM appealed this decision to the New Mexico Supreme Court, which on September 1, 2009 issued its ruling that the NMPRC had properly denied recovery of these costs.  PNM filed a motion with the court seeking rehearing of this issue, which was denied in November 2009 concluding this matter.

PVNGS Liability and Insurance Matters
 
    The PVNGS participants have insurance for public liability resulting from nuclear energy hazards to the full limit of liability under federal law.  This potential liability is covered by primary liability insurance provided by commercial insurance carriers in the amount of $375 million and the balance by an industry-wide retrospective assessment program.  If losses at any nuclear power plant covered by the program exceed the accumulated funds, PNM could be assessed retrospective premium adjustments.  The maximum assessment per reactor under the program for each nuclear incident is $117.5 million, subject to an annual limit of $17.5 million per incident, to be periodically adjusted for inflation.  Based on PNM’s 10.2% interest in the three PVNGS units, PNM’s maximum potential assessment per incident for all three units is $36.0 million, with an annual payment limitation of $5.4 million.

    The PVNGS participants maintain “all risk” (including nuclear hazards) insurance for property damage to, and decontamination of, property at PVNGS in the aggregate amount of $2.75 billion, a substantial portion of which must first be applied to stabilization and decontamination.  The participants have also secured insurance against
 
B-99

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

portions of any increased cost of generation or purchased power and business interruption resulting from a sudden and unforeseen accidental outage of any of the three units.  The property damage, decontamination, and replacement power coverages are provided by Nuclear Electric Insurance Limited (“NEIL”).  PNM is subject to retrospective assessments under all NEIL policies if NEIL’s losses in any policy year exceed accumulated funds.  The maximum amount of retrospective assessments PNM could incur under the current NEIL policies totals $6.7 million.  The insurance coverage discussed in this and the previous paragraph is subject to policy conditions and exclusions.

Natural Gas Supply

    PNM Gas contracted for the purchase of gas primarily to serve its retail customers.  The majority of these contracts were short-term in nature, supplying the gas needs for the current heating season and the following off-season months.  The price of gas was a pass-through, whereby PNM recovered 100% of its cost of gas.  There was also occasion for PNM Gas to purchase gas to source off-system sales.  As discussed in Note 2, PNM completed the sale of PNM Gas on January 30, 2009 at which time all commitments for PNM Gas future gas purchases were assumed by the buyer.

    PNM Electric procures gas supplies for its power plants from third-party sources and contracts with third party transportation providers, including NMGC, and PNM Gas (through January 29, 2009).

Water Supply

    Because of New Mexico’s arid climate and periodic drought conditions, there is a growing concern in New Mexico about the use of water for power plants.  PNM has secured water rights in connection with the existing plants at Afton, Luna and Lordsburg.  Water availability does not appear to be an issue for these plants at this time.

    The “four corners” region of New Mexico, in which SJGS and Four Corners are located, experienced drought conditions during 2002 through 2004 that could have affected the water supply for PNM’s generation plants.  In future years, if adequate precipitation is not received in the watershed that supplies the four corners region, the plants could be impacted.  Consequently, PNM, APS and BHP Billiton have undertaken activities to secure additional water supplies for SJGS, Four Corners and related mines.  PNM has reached an agreement for a voluntary shortage sharing agreement with tribes and other water users in the San Juan Basin for a term ending December 31, 2012.  Further, PNM and BHP Billiton have reached agreement on a long-term supplemental contract relating to water for SJGS with the Jicarilla Apache Nation that ends in 2016.  APS and BHP Billiton have entered into a similar contract for Four Corners.  Although the Company does not believe that its operations will be materially affected by the drought conditions at this time, it cannot forecast the weather situation or its ramifications, or how regulations and legislation may impact the Company’s situation in the future, should the shortages occur in the future.

PVNGS Water Supply Litigation
 
A summons was served on APS in 1986 that required all water claimants in the Lower Gila River Watershed of Arizona to assert any claims to water on or before January 20, 1987, in an action pending in the Maricopa County Superior Court.  PVNGS is located within the geographic area subject to the summons.  APS’ rights and the rights of the other PVNGS participants to the use of groundwater and effluent at PVNGS are potentially at issue in this action.   APS filed claims that dispute the court’s jurisdiction over PVNGS’ groundwater rights and their contractual rights to effluent relating to PVNGS and, alternatively, seek confirmation of those rights.  In 1999, the Arizona Supreme Court issued a decision finding that certain groundwater rights may be available to the federal government and Indian tribes.  In addition, the Arizona Supreme Court issued a decision in 2000 affirming the lower court’s criteria for resolving groundwater claims.  Litigation on both these issues has continued in the trial court.  No trial dates have been set in these matters.  PNM does not expect that this litigation will have a material adverse impact on its results of operation, financial position, or cash flows.
 
B-100

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

NRC Matters
 
    Because of several NRC findings relating to situations at PVNGS Unit 3 in 2004 and 2006, PVNGS was subject to a heightened level of oversight by the NRC.  On March 24, 2009, the NRC informed APS that it was removing PVNGS Unit 3 from the "multiple/repetitive degraded cornerstone" column of the NRC's Action Matrix (“Column 4”), removing PVNGS Units 1 and 2 from the “one degraded cornerstone” column (“Column 3”), and returning all three units of the plant to routine inspection and oversight by the NRC.  This notification follows the NRC's completion of its inspections of the corrective actions taken by PVNGS to address performance deficiencies that caused the NRC to place Unit 3 into Column 4 and Units 1 and 2 into Column 3.  The NRC has closed the confirmatory action letter that outlined the performance deficiencies and associated corrective actions.
 
San Juan River Adjudication

In 1975, the State of New Mexico filed an action entitled “State of New Mexico v. United States, et al.”, in the District Court of San Juan County, New Mexico, to adjudicate all water rights in the San Juan River Stream System.  The Company was made a defendant in the litigation in 1976.  The action is expected to adjudicate water rights used at Four Corners and at SJGS.  In 2005, the Navajo Nation and various parties announced a settlement of the Nation’s reserved surface water rights.  On March 30, 2009, President Obama signed legislation confirming the settlement with the Navajo Nation.  The Company cannot determine the effect, if any, of any water rights adjudication on the present arrangements for water at SJGS and Four Corners.  Final resolution of the case cannot be expected for several years. The Company is unable to predict the ultimate outcome of this matter.  An agreement reached with the Navajo Nation in 1985, however, provides that if Four Corners loses a portion of its rights in the adjudication, the Navajo Nation will provide, for an agreed upon cost, sufficient water from its allocation to offset the loss.

Conflicts at San Juan Mine Involving Oil and Gas Leaseholders

SJCC, through leases with the federal government and the State of New Mexico, owns coal interests with respect to the San Juan underground mine.  Certain gas producers have leases in the area of the underground coal mine and have asserted claims against SJCC that its coal mining activities are interfering with gas production.  SJCC has reached settlement with several gas leaseholders and has other claimants and potential claimants.  PNM cannot predict the outcome of existing or future disputes between SJCC and gas leaseholders.

Rights-of-Way Matters

Many of PNM’s electric transmission and distribution facilities are located on lands that require the grant of rights-of-way from governmental entities, Native American tribes, or private parties.  Several of the agreements granting the rights-of-way have expired or will expire within the next few years.  PNM is actively reviewing these matters and negotiating with certain parties, as appropriate, for the renewal of these rights-of-way.  However, there can be no assurance that all of these rights-of-way will be renewed.  If PNM is not successful in renewing the rights-of-way on Native American lands, it could be forced to remove its facilities from or abandon its facilities on the property covered by the rights-of-way and seek alternative routes for its transmission or distribution facilities.  If rights-of-way on Native American lands are renewed, it is likely they will be renewed at prices that are higher than historical levels, based on current renewal experience.  With respect to non-tribal government land and private land, PNM may have condemnation rights. Rights-of-way costs have historically been recovered in rates charged to customers.  PNM will seek to recover such costs in future rates.

Republic Savings Bank Litigation

In 1992, Meadows Resources, Inc. (“MRI”), an inactive subsidiary of PNMR, and its subsidiaries (“Plaintiffs”) filed suit against the Federal government in the United States Court of Claims, alleging breach of contract arising from the seizure of Republic Savings Bank (“RSB”).  RSB was seized and liquidated after Federal legislation prohibited certain accounting practices previously authorized by contracts with the Federal government.  
 
B-101

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

The Federal government filed a counterclaim alleging breach of obligation to maintain RSB’s net worth and moved to dismiss Plaintiffs’ claims for lack of standing.

    Plaintiffs filed a motion for summary judgment in December 1999 on the issue of liability and on the issue of damages.  The Federal government filed a cross motion for summary judgment and opposed Plaintiffs’ motion.

On January 25, 2008, the court entered its opinion granting the Federal government’s motion to dismiss MRI, denying the Federal government’s motion for summary judgment and granting the remaining Plaintiffs’ motion for summary judgment on the issues of liability and damages, awarding the Plaintiffs damages in the amount of $14.9 million. MRI had previously received payment from the FDIC in the amount of $0.3 million.  This payment reduces the amount of damages owed to $14.6 million.

The federal government appealed this matter to the U.S. Court of Appeals for the Federal Circuit and Plaintiffs cross-appealed.  On October 21, 2009, the Federal Circuit issued its opinion, affirming in part and reversing in part the decision of the Court of Claims, resulting in an award to the Plaintiffs of $9.7 million.  The period for requesting rehearing and for filing a petition for certiorari in the United States Supreme Court expired in January 2010, and the Circuit Court has issued its mandate, returning the case to the Court of Claims.  The government and Plaintiffs intend to file a Joint Motion for Entry of Final Judgment, after which the Court of Claims will issue its final judgment for $9.7 million and the claim should be paid shortly thereafter.  Because the procedural posture of this case eliminates the possibility of further review, the amount will be recorded, net of legal expenses, in the first quarter of 2010.

Western United States Wholesale Power Market

Various circumstances, including electric power supply shortages, weather conditions, gas supply costs, transmission constraints and alleged market manipulation by certain sellers, resulted in the well-publicized California and Western markets energy crisis of 2000-2001 and the bankruptcy filings of the Cal PX and PG&E.  As a result of the conditions in the Western markets during this time period, between late-2000 and mid-2003, FERC, the California Attorney General and private parties (collectively, the “California Parties”) initiated investigations, litigation, and other proceedings relevant to PNM and other sellers in the Western markets at FERC and in both California State and Federal District Courts, seeking a determination whether sellers of wholesale electric energy during the crisis period, including PNM, should be ordered to pay monetary refunds to buyers of such energy.  These proceedings were pending at FERC as well as before the U.S. Court of Appeals for the Ninth Circuit.  PNM participated in these proceedings at FERC, the Federal District Courts and the Ninth Circuit, including filing appeals to that court. 

In December 2009, PNM and the California Parties reached an agreement in principle to settle all remaining claims against PNM in these proceedings and on February 11, 2010, PNM entered into a “Settlement and Release of Claims Agreement” (the “Settlement Agreement”), which was filed with FERC on February 12, 2010.   The settlement contemplated by this agreement is subject to FERC approval.  The terms of the Agreement provide, among other things, for PNM to pay to the California Parties the amount of $45.0 million, consisting of the assignment of PNM receivables plus interest as of December 31, 2009 from the Cal ISO and the Cal PX in the amount of $13.1 million plus a cash payment of $31.9 million and for the California Parties to release PNM from claims arising from the California energy crisis of 2000 and 2001.  To account for the settlement, PNM recorded a pre-tax aggregate of $32.0 million ($19.3 million after income taxes) as reductions of operating revenue in 2009.  PNM’s liability for the settlement is included in other current liabilities at December 31, 2009.  PNM expressly denies any wrongdoing or culpability with respect to the claims against it that are released by the Settlement Agreement and, in entering into the settlement, does not admit any fault or liability.

On January 15, 2010, PNM transferred the cash payment to an escrow account established by the California Parties, pending entry into the Settlement Agreement.  Pursuant to the Settlement Agreement, upon approval by FERC satisfactory to the parties, the receivables and the cash payment will be distributed to the California Parties
 
B-102

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

and other entities that purchased electricity through the Cal ISO and Cal PX during the relevant time period as settlement funds in accordance with the terms and conditions of the Settlement Agreement.

In certain circumstances the Settlement Agreement may be terminated, in which case, the receivables and accrued interest will not be transferred into the Escrow Account and the Cash Payment together returned to PNM.  The Agreement may be terminated a) by its own terms if FERC by final order rejects the settlement; b) by any party adversely affected by a FERC order approving the settlement but imposing a material condition or modification that adversely affects such party; c) by the California Parties based on the failure of FERC to approve the settlement on or before April 30, 2010; or d) by PNM based on the failure of FERC to approve the settlement on or before September 30, 2010.

Complaint Against Southwestern Public Service Company

In September 2005, PNM filed a complaint under the Federal Power Act against SPS. PNM argued that SPS’ rates for sale of interruptible energy were excessive and that SPS had been overcharging PNM for deliveries of energy through its fuel cost adjustment clause practices.  PNM also intervened in a complaint proceeding brought by other customers raising similar arguments relating to SPS’ fuel cost adjustment clause practices (the “Golden Spread complaint proceeding”).  Additionally, in November 2005, SPS filed an electric rate case at FERC proposing to unbundle and raise rates charged to customers effective July 2006. PNM intervened in the case and objected to the proposed rate increase. In September 2006, PNM and SPS filed a settlement agreement providing for resolution of issues relating to rates for sales of interruptible energy, but not resolving the fuel clause issues. In September 2008, FERC issued its order approving the settlement between PNM and SPS.

In April 2008, FERC issued its order in the Golden Spread complaint proceeding.  FERC affirmed in part and reversed in part an ALJ’s initial decision, which had, among other things, ordered SPS to pay refunds to PNM with respect to the fuel clause issues.  FERC affirmed the decision of the ALJ that SPS violated its fuel cost adjustment clause tariffs.   However, FERC shortened the refund period applicable to the violation of the fuel cost adjustment clause issues. PNM and SPS have filed petitions for rehearing and clarification of the scope of the remedies that were ordered and reversal of various rulings in the order. FERC has not yet acted upon the requests for rehearing or clarification and they remain pending further decision.  PNM cannot predict the final outcome of the case at FERC.

Begay v. PNM et al

A putative class action was filed against PNM and other utilities on February 11, 2009 in the United States District Court in Albuquerque.  Plaintiffs claim to be allottees, members of the Navajo Nation, who pursuant to the Dawes Act of 1887, were allotted ownership in land carved out of the Navajo Nation. Plaintiffs, including an allottee association, make broad, general assertions that defendants, including PNM, are right-of-way grantees with rights-of-way across the allotted lands and are either in trespass or have paid insufficient fees for the grant of rights-of-way or both.  The plaintiffs, who have sued the defendants for breach of fiduciary duty, seek a constructive trust.  They have also included a breach of trust claim against the United States and its Secretary of the Interior.  PNM and the other defendants have filed motions to dismiss this action.  PNM is unable to determine the outcome of this case but intends to defend it vigorously.

(17)
Regulatory and Rate Matters

PNMR

First Choice Price-to-Beat Base Rate Reset

Based on the terms of the Texas stipulation related to the acquisition of TNP, First Choice made a filing to reset its price-to-beat base rates in 2005. First Choice’s price-to-beat base rate case was consolidated with TNMP’s 60-day rate review (see “60-Day Rate Review” below). First Choice requested that the PUCT recognize in its new price-to-beat base rates the TNMP rate reduction and the synergy savings credit provided for in the TNP acquisition
 
B-103

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

stipulation. In 2006, TNMP, First Choice, the PUCT staff and other parties filed a non-unanimous settlement agreement (“NUS”).  The PUCT unanimously approved the NUS on November 2, 2006 and made First Choice’s new price-to-beat base rates effective on December 1, 2006, as First Choice had requested.  As price-to-beat rates expired on December 31, 2006, the approved rates are no longer applicable.  In January 2007, TNMP’s 60-Day Rate Review proceeding and the underlying NUS were appealed by various Texas cities to a Texas District Court.  TNMP and First Choice had intervened in this appeal.   On August 31, 2009, the Texas District Court dismissed this matter for lack of prosecution thereby affirming the PUCT decision as requested by First Choice and TNMP.

First Choice Request for ERCOT Alternative Dispute Resolution

In June 2008, First Choice filed a request for alternative dispute resolution with ERCOT alleging that ERCOT incorrectly applied its protocols with respect to congestion management during the first quarter of 2008.  First Choice requested that ERCOT resolve the dispute by restating certain elements of its first quarter 2008 congestion management data and by refunding to First Choice allegedly overstated congestion management charges.  The amount at issue in First Choice’s claim can only be determined by running ERCOT market models with corrected inputs but First Choice believes that the amount is significant.  ERCOT protocols provide that ERCOT will notify potentially impacted market participants and subsequently consider the merits of First Choice’s allegations.  The Company is unable to predict the outcome of this matter.

PNM

Gas Rate Case

In May 2006, PNM filed a general gas rate case that asked the NMPRC to approve an increase in the service fees charged to its 481,000 natural gas customers, including the set monthly fee, the charge tied to monthly usage, and miscellaneous on-demand service fees.  Those fees are separate from the cost of gas charged to customers, which would not be affected by the fee increase.  The petition requested an increase in base gas service rates of $22.6 million and an increase in miscellaneous on-demand service rates of $0.2 million.  In June 2007 the NMPRC unanimously approved an increase in annual revenues of approximately $9 million for PNM.  PNM and the AG filed appeals on various issues with the New Mexico Supreme Court.  In connection with the acquisition of PNM’s gas assets by NMGC, PNM and the AG moved to dismiss their respective gas rate case appeals, which motions were granted on February 6, 2009.

2007 Electric Rate Case

On February 21, 2007, PNM filed a general electric rate case (“2007 Electric Rate Case”) requesting the NMPRC approve an increase in service fees to all of PNM’s retail customers except those formerly served by TNMP.  The request was designed to provide PNM’s electric utility an opportunity to earn a 10.75 percent return on equity.  The application also requested authorization to implement a FPPAC through which changes in the cost of fuel and purchased power, above or below the costs included in base rates, will be passed through to customers on a monthly basis.  On April 24, 2008, the NMPRC issued a final order that resulted in a revenue increase of $34.4 million.  The rate increase provides for a 10.1 percent return on equity.  New rates reflecting the $34.4 million increase were effective for bills rendered on and after May 1, 2008.  In its final order, the NMPRC disallowed recovery of costs associated with the RECs used to meet the New Mexico Renewable Energy Portfolio Standards that were being deferred as regulatory assets. The NMPRC also ruled that recovery of surface coal mine decommissioning costs be capped at $100 million.  The order resulted in PNM being unable to assert it is probable, as defined under GAAP, that the costs previously deferred on PNM’s balance sheet will be recoverable through future rates charged to its customers.  Accordingly, as of March 31, 2008, PNM recorded regulatory disallowances for pre-tax write offs of $19.6 million for coal mining decommissioning costs and $10.6 million for deferred REC costs.  PNM appealed the NMPRC’s treatment of coal mine decommissioning and the RECs to the New Mexico Supreme Court.  Under the terms of the stipulation in the 2008 Electric Rate Case described below, PNM dismissed its appeal of the treatment of the REC costs.  The New Mexico Supreme Court affirmed the NMPRC order on coal
 
 
B-104

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

mine decommissioning in September 2009.  PNM filed a motion for rehearing, which was denied in November 2009 concluding this matter.

Emergency FPPAC

    On March 20, 2008, PNM and the IBEW filed a joint motion in the 2007 Electric Rate Case requesting NMPRC authorization to implement an Emergency FPPAC on an interim basis. On May 22, 2008, the NMPRC issued a final order that approved the Emergency FPPAC with certain modifications.  PNM implemented the Emergency FPPAC from June 2, 2008 through the effective date of the 2008 Electric Rate Case order described below.

The Albuquerque Bernalillo County Water Utility Authority and the New Mexico Industrial Energy Consumers Inc. filed notices of appeal to the New Mexico Supreme Court, which seek to have vacated the NMPRC order approving the Emergency FPPAC. The appeals have been consolidated and PNM has been granted party status.  Oral argument was held October 13, 2009.  PNM is unable to predict the outcome of these appeals.

    The NMPRC order approving the Emergency FPPAC required PNM to pay for an audit of PNM’s monthly FPPAC reports and a prudence review of PNM’s fuel and purchased power costs, to be conducted by auditors selected by the NMPRC.  Costs of the audit incurred by PNM will be recoverable through future rate proceedings.  The NMPRC has selected an auditor and the audit has begun.  On February 19, 2010, the audit report of findings and recommendations was submitted to the NMPRC.  The report recommended improvements in several areas but did not identify any imprudent activities or find that PNM’s fuel or purchased costs were unreasonable. These findings and recommendations are subject to NMPRC review and approval.  PNM is unable to predict the outcome of this matter.
 
    The Emergency FPPAC provided that if PNM’s base load generating units subject to NMPRC jurisdiction did not operate at or above a specified capacity factor and PNM was required to obtain replacement power to serve jurisdictional customers, PNM would be required to make a filing with the NMPRC seeking approval of the replacement power costs.  In its required filing, PNM stated that the costs of the replacement power amounting to $8.0 million were prudently incurred and made a motion that they be approved.  The NMPRC staff filed opposition to PNM’s motion and recommended that PNM be required to refund the amount collected.  On January 12, 2010, the NMPRC directed the Emergency FPPAC auditor to investigate whether the replacement power costs were prudently incurred. The order also directed PNM to file a response to the auditors’ report, to provide certain additional information, and to show cause why it should not be fined for recovering replacement power costs without prior NMPRC approval.  PNM filed its response to the show cause order on February 12, 2010.  On February 19, 2010, the auditor’s report on replacement power costs was submitted to the NMPRC. The report concludes that the methodology used to estimate the cost of replacement power was reasonable, that PNM purchased power at the lowest reasonable cost, and that outage planning  and scheduling and plant operations were reasonable.  These findings are subject to NMPRC review and approval. PNM intends to file a response to the report and will continue to assert that its recovery of replacement power costs was proper and did not violate the NMPRC’s order.  PNM is unable to predict the outcome of this matter.

2008 Electric Rate Case

On September 22, 2008, PNM filed a general rate case (“2008 Electric Rate Case”) requesting the NMPRC to approve an increase in electric service rates to all PNM retail customers except those formerly served by TNMP. The proposed rates were designed to increase annual operating revenue by $123.3 million, based on a March 31, 2008 test period and calculating base fuel costs using a projection of costs for the 12 months ending March 31, 2009. PNM also proposed a FPPAC in the general form authorized by the NMPRC, but with PNM retaining 25% of off-system sales margins and crediting 75% against fuel and purchased power costs.

On March 6, 2009, PNM, the NMPRC staff and most of the intervening parties filed a stipulation to resolve all issues in the case, including the approval of the Resource Stipulation described below. No party opposed the
 
B-105

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

stipulation.   The stipulation provided for an increase in annual non-fuel revenues of $77.3 million, of which 65% ($50.2 million) would be implemented for bills beginning on July 1, 2009 and the remaining 35% ($27.1 million) to be implemented in rates as of April 1, 2010.  The stipulation was amended to reduce the rate increase to $77.1 million and was approved by the NMPRC on June 18, 2009. The new rates went into effect for bills rendered beginning July 1, 2009.  As an offset to the non-fuel revenue increase, PNM implemented a credit to customers totaling $26.3 million, representing the amount of revenues from past sales of SO2 allowances.  This amount will be credited to ratepayers over 21 months beginning July 1, 2009. The crediting mechanism will also be used to credit customers with revenues received by PNM from future sales of SO2 allowances.  PNM recorded a regulatory disallowance expense and a regulatory liability for the $26.3 million to be credited to ratepayers. The stipulation also provides that a traditional FPPAC go into effect with the new rates.  The stipulation provides that 100% of off-systems sales margins be credited against fuel and purchased power costs in the FPPAC.  PNM implemented the new FPPAC on July 1, 2009.  The new FPPAC does not include a recovery cap or the capacity factor target of the Emergency FPPAC. The FPPAC factor will be set annually beginning July 1, 2010.

Resource Stipulation

In anticipation of the 2008 Electric Rate Case, on September 10, 2008, a stipulation (the “Resource Stipulation”) executed by PNM, the NMPRC staff, the AG and the Coalition for Clean Affordable Energy, and later joined by the New Mexico Industrial Energy Consumers Inc., was filed with the NMPRC. The NMPRC approved the Stipulation on May 26, 2009.  The Resource Stipulation allowed recovery in rates of costs related to and resolves all issues in the proceedings regarding 1) the Valencia PPA, 2) PNM’s acquisition of an ownership interest in Unit 2 of PVNGS that was being leased, including carrying costs, and 3) the application to own and operate Lordsburg and PNM’s interest in Luna as jurisdictional assets.

    In June 2007, a wholly-owned subsidiary of PNMR purchased 100% of a trust, which owns a 2.26% undivided interest, representing 29.8 MW, in PVNGS Unit 2 and a 0.76% undivided interest in certain PVNGS common facilities, as well as a lease under which such facilities were leased to PNM.  The Resource Stipulation allowed the Unit 2 interest to be transferred to PNM and the acquisition costs to be recovered beginning with the 2008 Electric Rate Case.  On July 24, 2009, PNM purchased the trust from the other PNMR subsidiary for $39.1 million in cash.  The purchase price was equal to the book value of the underlying assets less deferred taxes and miscellaneous accruals. The other PNMR subsidiary paid a dividend of that same amount to PNMR.  PNMR then made an equity contribution of that amount to PNM.  The trust has $32.0 million of debt owing to the PVNGS Capital Trust, which is consolidated by PNM.  The transfer had no impact on the financial statements of PNMR. The impacts on the financial statements of PNM were to increase net plant in service by $73.7 million, increase common stock by $39.1 million, reduce investment in the PVNGS lessor notes by $32.0 million, reflecting the elimination of the debt owed by the trust to the PVNGS Capital Trust, and increase deferred income taxes and other accruals by $2.6 million.

Renewable Portfolio Standard

The Renewable Energy Act of 2004 was enacted to encourage the development of renewable energy in New Mexico.  The act, as amended, establishes a mandatory renewable energy portfolio standard requiring a utility to acquire a renewable energy portfolio equal to 5% of retail electric sales by January 1, 2006, increasing to 10% by 2011, 15% by 2015 and 20% by 2020.  The NMPRC requires renewable energy portfolios to be “fully diversified” beginning in 2011 when no less than 20% of the renewable portfolio requirement must be met by wind energy, no less than 20% by solar energy, no less than 10% by other renewable technologies, and no less than 1.5% by distributed generation. The act provides for streamlined proceedings for approval of utilities’ renewable energy procurement plans, assures utilities recovery of costs incurred consistent with approved procurement plans and requires the NMPRC to establish a RCT for the procurement of renewable resources to prevent excessive costs being added to rates. The NMPRC has established a RCT that began at 1% of all customers’ aggregated overall annual electric charges, increasing by 0.2% annually until 2011, at which time it will be 2%, and then increasing by 0.25% annually until reaching 3% in 2015.
 
B-106

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


On July 1, 2009, PNM filed its annual Renewable Energy Portfolio Procurement Plan for 2010 with the NMPRC.  Under the plan, PNM proposed to rely on a mixture of solar, wind, and biogas resources and the purchase of RECs to meet its renewable energy requirements for 2010 and 2011.  The plan described that PNM could meet its renewable energy requirements in 2010 with existing resources, but required additional resources for 2011 compliance.  The plan also stated that PNM would not be able to fully meet the NMPRC’s resource diversity requirements without exceeding the RTC and the plan proposed to cap to certain previously approved net-metered, PV distributed generation programs.  The plan also committed PNM to file for additional projects later in the year.

In September 2009, PNM entered into settlement discussions with various parties to address issues related to the distributed generation programs, the RCT, and PNM’s prospective additional projects.  In recognition of these settlement negotiations, the NMPRC issued an order on September 22, 2009 that rejected PNM’s July 1st plan, with the exception of two procurements concerning the acquisition of RECs from a wind resource and from biogas resources, and ordered that PNM file a revised plan.  A public hearing on the acquisition of RECs from the wind resource and the biogas program was held in October and an order approving these projects was issued on December 17, 2009.  On January 9, 2010, PNM announced that the negotiations had concluded and a settlement had been reached.  PNM filed the settlement and its revised plan with the NMPRC on January 25, 2010.  Under the revised 2010 procurement plan, PNM would invest approximately $205.7 million on solar PV facilities through the first quarter of 2012 and implement a customer-sited PV distributed generation program to replace current PV programs.  On February 1, 2010, motions were filed to dismiss the revised plan and to extend the time period for NMPRC action on the revised plan. PNM and other settling parties filed their joint response in opposition to these motions on February 15, 2010. Under a previous NMPRC order, proceedings on the revised plan are to be completed within six months from the date of filing. PNM cannot predict the outcome of the NMPRC’s proceedings on the revised plan.

NMPRC Inquiry on Fuel and Purchased Power Adjustment Clauses

In October 2007, the NMPRC issued a NOI that could lead to the adoption of an amended rule for the implementation of FPPACs for all investor-owned utilities and electric cooperatives in New Mexico.  The investor-owned utilities and electric cooperatives have responded to a series of questions and the NMPRC staff made a filing dealing with the need for consistency of FPPACs, streamlining FPPACs, and whether a single FPPAC methodology should be applied to all utilities.  Workshops have been held to discuss the comments filed by PNM and others and the proposed changes. The workshop process has concluded and the Hearing Examiner presented proposed rule amendments to the NMPRC for its consideration.  The NMPRC has not taken action on the proposed amendments.

NMPRC Rulemaking on Disincentives to Energy Efficiency Programs

In January 2008, the NMPRC issued a NOI to identify disincentives in utility expenditures on energy efficiency and measures to address those disincentives, including specific rate making alternatives, and appointed a Hearing Examiner to conduct workshops to develop proposals for possible rule changes.  Based on the workshops, amendments were proposed to the NMPRC energy efficiency rule that would allow utilities to collect $0.01 per KWh for energy savings and $10 per kilowatt for demand savings related to energy efficiency programs and an alternative proposal that would add a decoupling mechanism to the rule.  PNM filed comments and testimony addressing the proposed rule.  A public hearing was held on June 26, 2009 and a decision is pending.  PNM is unable to predict the outcome of this proceeding.

PNM Electric Energy Efficiency and Load Management Programs

The NMPRC requires public utilities to obtain approval to implement energy efficiency and load management programs. Costs to implement approved programs are recovered through a rate rider. On September 15, 2008, PNM filed a plan, which included new programs, modifications to existing programs and a request to recover program costs.  After proceedings before the NMPRC, a final order approving the programs was issued on May 19, 2009.  In August 2009, PNM began recovering the costs of the programs through a rate rider amounting to 1.881% of
 
B-107

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

customers’ bills, before taxes and franchise fees based on program costs of $14.1 million. The new programs are being implemented.

    On July 7, 2009, the NMPRC ordered an investigation into whether it is prudent for PNM to continue certain load management programs initiated in 2008 with NMPRC approval, considering its recent addition of supply-side resources.  PNM offers these programs through contracts with third-party vendors that contain substantial fees for early termination.  PNM and the NMPRC staff filed testimony recommending continuing these programs and a public hearing was held on January 12, 2010.  A recommended decision, which recommended continuation of the programs, was issued by the Hearing Examiner on February 15, 2010.  The recommended decision is subject to the approval of the NMPRC.  PNM is unable to predict the outcome of this proceeding.

Investigation on Establishing a Policy Linking Utility Earnings to Quality of Customer Service

On May 28, 2009, the NMPRC ordered an investigation to consider the development of a service quality incentive mechanism for utilities in New Mexico, including PNM. The parties were to look at quality of service mechanisms established in other NMPRC orders, as well as the mechanisms that have been implemented in other states. A workshop process concluded with the filing of a report that concludes that present circumstances do not warrant the implementation of a performance based ratemaking mechanism to either reward or penalize utilities for quality of service. The workshop participants agreed that enhanced reporting requirements would allow the NMPRC to monitor important customer service metrics to determine if service quality is deteriorating so that the Commission can identify and address any adverse trends before they become a problem. The report recommends that utilities be required to file customer service reports no later than April 30th of each year for a three-year period commencing April 30, 2011.  A timetable for the NMPRC to act on this recommendation has not been established.  PNM is unable to predict the outcome of this proceeding.

Rates for Former TNMP Customers in New Mexico

    PNM serves the former New Mexico customers of TNMP (“TNMP-NM”) under rates approved by the NMPRC in its order approving PNMR’s acquisition of TNMP.  Under that order, rates charged to customers were set through December 31, 2010.  In January 2009, the NMPRC directed PNM to estimate the revenue requirement increase that would be reflected in a TNMP-NM rate application for rates effective January 2011.  PNM estimated that the rate increase could be between 40% and 56% depending on fuel costs. In April 2009, the NMPRC directed PNM, the NMPRC staff, and other parties to attempt to reach consensus on ways to mitigate the impact of this potential rate increase and appointed a mediator.  Several mediations have been held and discussions are ongoing.  No date has been set for completion of this process.  PNM cannot predict the outcome of this matter.

Third-Party Arrangements for Renewable Distributed Generation

On June 16, 2009, the NMPRC initiated a proceeding and requested legal briefs on the topic of whether third-party arrangements for the sale of renewable energy from customer-sited distributed generation facilities are permissible under New Mexico law.  Initial briefs and response briefs were filed by utilities, the NMPRC staff and intervenors.  In its initial brief, PNM stated that such arrangements that involve the sale of electricity to retail customers in the service territory of existing utilities were not legally permissible.  Other utilities’ and the NMPRC staff’s briefs reached similar conclusions.  Certain intervenors argued in their briefs that such arrangements were generally permissible.  The Hearing Examiner issued a recommended decision on October 23, 2009 analyzing a number of different scenarios.  Among her findings, the Hearing Examiner recommended that the NMPRC determine that developers who sell electricity to a single host or to multiple hosts from different systems each located on the host’s premises, without transporting electricity from one location to another, are not public utilities under New Mexico law.  On December 31, 2009, the NMPRC issued an order that declared that a third party that owns renewable generation equipment that is installed on a utility customer’s premises, pursuant to a long term contract with the customer to supply a portion of that customer’s electricity use, payments for which are based on a kilowatt-hour charge, is not a public utility subject to regulation by the NMPRC.  The order also declared that a third party developer that owns renewable generation equipment installed on a utility customer’s premises, which is used
 
B-108

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

to serve multiple customers for a portion of each customer’s electricity use is not a public utility subject to regulation by the NMPRC.  However, the order declares that a third party developer may not use a public utility’s distribution lines or equipment in order to route electricity to multiple customers.  On January 21, 2010 PNM filed a notice of appeal of this order in the New Mexico Supreme Court.  Other parties have also appealed.  Although PNM believes there are substantial bases for reversal of the NMPRC order, it cannot predict the outcome of this proceeding.

In early 2010, both houses of the New Mexico Legislature passed a bill that would supersede the NMPRC order.  The Governor of New Mexico has not acted on the bill.  If signed by the Governor, the bill would allow non-utility power generators to be excluded from classification as public utilities under state law provided that such generators use renewable energy resources, that the generators are located on the site of the power consumer, do not involve retail wheeling of power, and that any adverse cost affects to other utility customers are minimized. The bill encourages the development and use of renewable energy, but will safe guard against unreasonable cost shifting to other utility customers while protecting the financial integrity of utilities.
 
Application to Hedge Fuel and Purchased Power Costs

In August 2009, PNM filed an application for approval of a plan to manage fuel and purchased power costs by entering into certain forward market transactions relating to the procurement of fuel and purchased power and the sale of excess electrical energy in the wholesale market.  PNM’s application seeks NMPRC authorization to conduct these activities, which involve hedging practices, and to pass through the costs and benefits of the transactions to jurisdictional customers using PNM’s FPPAC.  The NMPRC staff filed testimony recommending approval of PNM’s application with minor modifications. PNM filed rebuttal testimony agreeing with the proposed modifications. A hearing was held on February 23, 2010.  PNM cannot predict the outcome of this proceeding.

TNMP

TNMP Competitive Transition Charge True-Up Proceeding

    The purpose of the true-up proceeding was to quantify and reconcile the amount of stranded costs that TNMP may recover from its transmission and distribution customers.  A 2004 PUCT decision established $87.3 million as TNMP’s stranded costs.  TNMP and other parties have made a series of appeals on the ruling and it is currently before the Texas Supreme Court. TNMP is unable to predict if the Texas Supreme Court will review the decision or the ultimate outcome of this matter.
 
Interest Rate for Calculating Carrying Charges on TNMP’s Stranded Cost

The PUCT approved an amendment to the true-up rule in 2006, which results in a lower interest rate that TNMP is allowed to collect on the unsecuritized true-up balance through a CTC. The PUCT concluded that the correct rate at which a utility should accrue carrying costs through a CTC is the weighted average of an adjusted form of its marginal cost of debt and its unadjusted historical cost of debt, with the weighting based on the utility’s most recently authorized capital structure.  The revised rate affects TNMP by lowering the previously approved carrying cost rate of 10.93%.  After regulatory proceedings, the PUCT issued an order approving the 8.31% rate proposed by TNMP and the PUCT staff. Various municipal intervenors (“Cities”) appealed the PUCT’s order to the District Court in Austin, Texas, with TNMP as an intervenor.  The District Court affirmed the PUCT’s decision and the Cities filed an appeal in the Texas 3rd Court of Appeals.  On May 1, 2009, the Court of Appeals affirmed the decisions of the lower court as requested by TNMP. No party appealed the matter to the Texas Supreme Court and it is now concluded.


 
B-109

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


Interest Rate Compliance Tariff

Following the revision of the interest rate on TNMP’s carrying charge, TNMP filed a compliance tariff to implement the new 8.31% rate. TNMP’s filing proposed to put the new rates into effect on February 1, 2008.  Intervenors asserted objections to the compliance filing.  PUCT staff urged that the PUCT make the new rate effective as of December 27, 2007 when the PUCT’s order establishing the correct rate became final.  After regulatory proceedings, the PUCT issued an order making the new rate retroactive to July 20, 2006.  TNMP filed an appeal of this order in the District Court in Austin, Texas.  While there is inherent uncertainty in this type of proceeding, TNMP believes it will ultimately be successful in overturning any ruling that the effective date should be prior to December 27, 2007.

60-Day Rate Review

In 2005, TNMP made a required 60-day rate review filing.  TNMP’s case establishes a CTC for recovery of the true-up balance.  As noted above, TNMP’s 60-day rate review, along with First Choice’s price-to-beat rate reset filing, were consolidated.  In 2006, the PUCT issued a signed order which would allow TNMP to begin collecting its true-up balance, which includes carrying charges, over a 14-year period.  The order also allows TNMP to collect expenses associated with several cases over a three-year period.  TNMP began collecting its CTC and its rate case expenses on December 1, 2006.  In January 2007, this proceeding was appealed by various Texas cities to the District Court, in Austin, Texas.  TNMP and First Choice have intervened.  On August 31, 2009, the Texas District Court dismissed this matter for lack of prosecution thereby affirming the PUCT decision as requested by First Choice and TNMP.

2008 Rate Case

On August 29, 2008, TNMP filed with the PUCT for an $8.7 million increase in revenues, requesting that new rates go into effect in September 2009.  In its request, TNMP also asked for permission to implement a catastrophe reserve fund similar to those approved for other transmission and distribution companies in Texas. Catastrophe funds help pay for a utility system’s recovery from natural disasters and acts of terrorism.  On October 10, 2008, the PUCT issued a preliminary order permitting TNMP to file supplemental testimony on costs caused by Hurricane Ike.
 
In December 2008, the parties in the TNMP rate case requested that the case be abated and the ALJ granted the request.  The abatement suspended procedural deadlines until after the submittal of supplemental testimony by TNMP relating to costs incurred during Hurricane Ike and anticipated increased financing costs.  In March 2009, TNMP filed its supplemental testimony, requesting an additional revenue increase of $15.7 million annually. In June 2009, TNMP and the other parties in the rate case announced that a unanimous settlement had been reached. The settlement resolves all issues in the rate case and permits TNMP to increase revenues by $12.7 million annually.  This increase reflects interest and other costs associated with its March 2009 debt refinancing and the settlement adjusts the interest rate TNMP is allowed to collect on its CTC to reflect those costs.  The rate increase includes recovery of $17.6 million of Hurricane Ike restoration costs plus carrying costs over five years although $0.7 million of the costs incurred by TNMP were not included and were written off in the three months ended June 30, 2009.  The settlement authorizes a catastrophe reserve of $1.0 million funded over an eight year period. The settlement was approved by the PUCT in August 2009 and rates went into effect for bills rendered on or after September 1, 2009. No party appealed the decision and the matter is concluded.
 
TNMP now has the ability to update its transmission rates annually to reflect changes in its invested capital.  Updated rates would reflect the addition and retirement of transmission facilities, including appropriate depreciation, federal income tax and other associated taxes, and the approved rate of return on such facilities.
 

 
B-110

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


Senate Bill 769

            On April 16, 2009, Senate Bill 769 (“SB 769”) concerning the recovery of hurricane costs by utilities was enacted.  SB 769 authorizes the PUCT, after a full review, to permit an electric utility to obtain timely recovery of system restoration costs, and permits utilities to use securitization financing for the recovery of such costs. Appropriately incurred costs can be approved in any future proceeding.

Energy Efficiency

On October 28, 2009, TNMP filed an application for approval of its 2010 energy efficiency programs and requested recovery through an energy efficiency cost recovery factor. TNMP’s estimated the costs of its 2010 energy efficiency programs to be $2.6 million and requested to collect this amount based on a per customer charge over 11 months. The PUCT staff and intervenors took no issue with TNMP’s application. TNMP implemented the factor effective February 1, 2010.

(18)
Environmental Issues

The normal course of operations of the Company necessarily involves activities and substances that expose the Company to potential liabilities under laws and regulations protecting the environment.  Liabilities under these laws and regulations can be material and in some instances may be imposed without regard to fault, or may be imposed for past acts, even though the past acts may have been lawful at the time they occurred.  Sources of potential environmental liabilities include the Federal Comprehensive Environmental Response Compensation and Liability Act of 1980 and other similar statutes.

The Company records its environmental liabilities when site assessments or remedial actions are probable and a range of reasonably likely cleanup costs can be estimated.  The Company reviews its sites and measures the liability quarterly, by assessing a range of reasonably likely costs for each identified site using currently available information, including existing technology, presently enacted laws and regulations, experience gained at similar sites, and the probable level of involvement and financial condition of other potentially responsible parties. These estimates include costs for site investigations, remediation, operations and maintenance, monitoring and site closure.  Unless there is a probable amount, the Company records the lower end of such reasonably likely range of costs (classified as other deferred credits at undiscounted amounts).

The Company’s recorded liability estimated to remediate its identified sites was as follows:

PNMR
 
PNM
 
TNMP
December 31,
 
December 31,
 
December 31,
2009
 
2008
 
2009
 
2008
 
2009
 
2008
(In thousands)
                     
$1,894
 
$5,308
 
$1,894
 
$5,308
 
$  -
 
$ -

The Company expended the following for remediation, including payments related to the Citizen Suit under the Clean Air Act described in Note 16:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
                   
PNMR
  $ 3,638     $ 190     $ 469  
PNM
  $ 3,638     $ 190     $ 469  
TNMP
  $ -     $ -     $ -  

 
B-111

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The ultimate cost to clean up the Company’s identified sites may vary from its recorded liability due to numerous uncertainties inherent in the estimation process, such as the extent and nature of contamination, the scarcity of reliable data for identified sites, and the time periods over which site remediation is expected to occur.  The Company expects that the majority of the December 31, 2009 environmental liability will be paid over the next five years, funded by cash generated from operations.  Future environmental obligations are not expected to have a material impact on the results of operations or financial condition of the Company.

(19)
Accumulated Other Comprehensive Income (Loss)

AOCI reports a measure for accumulated changes in equity that result from transactions and other economic events other than transactions with shareholders.  The following table sets forth each component of AOCI, net of income taxes:

               
Mark-to-
       
   
Unrealized
         
market for
   
Accumulated
 
   
gain (loss)
   
Pension
   
cash-flow
   
other
 
   
on
   
liability
   
hedge
   
comprehensive
 
   
securities
   
adjustment
   
transactions
   
income (loss)
 
   
(In thousands)
 
PNMR
                       
Balance at December 31, 2008
  $ 1,721     $ (8,998 )   $ 38,225     $ 30,948  
Balance at December 31, 2009
  $ 10,759     $ (75,444 )   $ 18,628     $ (46,057 )
                                 
PNM
                               
Balance at December 31, 2008
  $ 1,721     $ (8,854 )   $ 24,879     $ 17,746  
Balance at December 31, 2009
  $ 10,759     $ (75,245 )   $ 12,679     $ (51,807 )
                                 
TNMP
                               
Balance at December 31, 2008
  $ -     $ (142 )   $ -     $ (142 )
Balance at December 31, 2009
  $ -     $ (199 )   $ 125     $ (74 )

(20)
Related Party Transactions

PNMR, PNM, TNMP, and Optim Energy are considered related parties as defined under GAAP.  PNMR Services Company provides corporate services to PNMR, its subsidiaries, and Optim Energy in accordance with shared services agreements.  These services are billed on a monthly basis to the business units.  Billings are at cost, except for Optim Energy, which includes a profit element. There is also a services agreement for Optim Energy to provide services to PNMR.

PNMR files a consolidated federal income tax return with its affiliated companies.  A tax allocation agreement exists between PNMR and each of its affiliated companies.  These agreements provide that the subsidiary company will compute its taxable income on a stand-alone basis.  If the result is a net tax liability, such amount shall be paid to PNMR.  If there are net operating losses and/or tax credits, the subsidiary shall receive payment for the tax savings from PNMR to the extent that PNMR is able to utilize those benefits.

See Note 6 for information on intercompany borrowing arrangements and Note 7 for intercompany lease arrangements.
 
 
B-112

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


See Note 22 for information concerning Optim Energy.  See Note 23 for information concerning the transfer of operations from TNMP to PNM and the sale of PNM Gas.  The table below summarizes the nature and amount of related party transactions of PNMR, PNM and TNMP:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
         
(In thousands)
       
                   
Electricity, transmission and distribution related services billings:
                 
PNM to TNMP
  $ -     $ -     $ 126  
TNMP to PNMR
    41,338       55,214       72,578  
                         
Services billings:
                       
PNMR to PNM*
    80,141       81,726       93,910  
PNMR to TNMP
    22,919       19,043       23,833  
PNM to TNMP
    698       129       235  
TNMP to PNMR
    636       994       872  
PNMR to Optim Energy
    6,516       8,972       8,316  
Optim Energy to PNMR
    305       672       116  
                         
PNMR Services capital expenditures fees:
                       
PNM to (from) PNMR
    -       -       99  
TNMP to (from) PNMR
    -       -       18  
                         
Income tax sharing payments:
                       
PNM to PNMR
    126,527       2,050       5,604  
TNMP to PNMR
    4,322       15,079       -  
PNMR to TNMP
    -       -       (15,529 )
                         
Interest payments:
                       
PNM to PNMR
    8       -       3  
TNMP to PNMR
    849       133       1,165  

* PNM Shared services include billings to PNM Gas of $0.9 million, $16.1 million, and $31.6 million in 2009, 2008, and 2007.

 (21)
New Accounting Pronouncements

Information regarding recently issued accounting pronouncements, including those that have not been adopted by the Company could have a material impact, is set forth below.

Accounting Standard Update 2009-01 -- Generally Accepted Accounting Principles: amendments based on—Statement of Financial Accounting Standards No. 168—The FASB Accounting Standards CodificationTM and the Hierarchy of Generally Accepted Accounting Principles

Effective September 15, 2009, the FASB Accounting Standards Codification (“ASC”) combined all of the FASB’s, and its predecessors’, technical accounting pronouncements into a single source of authoritative GAAP.  As a result, references are no longer made to technical accounting pronouncements but instead to GAAP or the ASC topic.  The ASC will be updated thru an Accounting Standard Update (“ASU”).  ASU’s that affect the current reporting period or may affect the Company’s future financial statements or disclosure requirements are described in this section.
 
B-113

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

Accounting Standard Update 2009-17 -- Consolidation: Improvements to Financial reporting by Enterprises Involved with Variable Interest Entities

The FASB amended GAAP through ASU 2009-17 to require entities to perform an analysis of a company’s variable interest entities to determine whether a controlling interest exists and therefore require consolidation.  This amendment provides additional guidance and ongoing reassessments of the status of variable interest entities and is effective for interim and annual reporting periods beginning after November 15, 2009.  The Company is evaluating the impact of  the amendment on the Company’s financial statements.

Accounting Standard Update 2010-06 -- Fair Value Measurements and Disclosures: Improving Disclosures about Fair Value Measurements

The FASB released amended guidance related to disclosures of fair value measurements.  The update requires entities to enhance interim and annual disclosures about fair value measurements, specifically:
-Further disaggregate the level presented for debt and equity securities (i.e. U.S. Treasuries, municipals, etc.)
-Disclose the amount and reason for significant transfers between fair value categories level 1 and level 2
-Disclose information about the purchases, sales, issuances, and settlements for items in level 3 of the fair value measurements on a gross basis rather than net

The enhanced disclosure will be effective for the interim period ended March 31, 2010 for the first two items.  The third item regarding level 3 information will be effective for the interim period ended March 31, 2011.  The Company will comply with the disclosure requirements as they become effective.

 (22)
Optim Energy

In January 2007, Optim Energy was created by PNMR and ECJV, a wholly owned subsidiary of Cascade to serve expanding U.S. markets, principally the areas of Texas covered by ERCOT.  PNMR and ECJV each have a 50 percent ownership interest in Optim Energy, a limited liability company.  Optim Energy’s name was changed from EnergyCo on February 2, 2009.

On June 1, 2007, Optim Energy entered into a bank financing arrangement with a term of five years, which includes a revolving line of credit.  This facility also provides for bank letters of credit to be issued as credit support for certain contractual arrangements entered into by Optim Energy.  Cascade and ECJV have guaranteed Optim Energy’s obligations on this facility and, to secure Optim Energy’s obligation to reimburse Cascade and ECJV for any payments made under the guaranty, have a first lien on all assets of Optim Energy and its subsidiaries.  In June 2007, Optim Energy distributed $87.5 million to each of PNMR and ECJV from a long-term borrowing under this facility.

In January 2010, Optim Energy entered into floating-to-fixed interest rate swaps with an aggregate notional amount of $650.0 million.  The effect of these swaps is to convert $650.0 million of borrowings under Optim Energy’s credit facility from an interest rate based on the one-month LIBOR rate to a fixed rate of 1.33% through January 7, 2011, exclusive of loan guaranty fees.  These swaps will be accounted for as cash-flow hedges.

On June 1, 2007, PNMR contributed its ownership of Altura to Optim Energy at fair value of $549.6 million (after the working capital adjustment described below). ECJV made a cash contribution to Optim Energy equal to 50% of the fair value amount, and Optim Energy distributed that cash to PNMR.  PNMR accounted for this transaction by (1) removing the assets and liabilities transferred to Optim Energy from its consolidated financial statements; (2) recording an additional investment in Optim Energy for an amount equal to 50% of the net carrying value of the Altura assets and liabilities transferred, reflecting that 50% of the items transferred are in effect still owned by PNMR; and (3) reflecting in results of operations the difference between the cash received and 50% of the net carrying value of the items transferred that in effect were sold to ECJV, which resulted in a pre-tax loss of $3.1 million being reflected in energy production costs.  As provided under the contribution agreement, subsequent to
 
B-114

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

June 1, 2007, an adjustment to the contribution amounts was made for changes in  June 1, 2007, an adjustment to the contribution amounts was made for changes in components of working capital between the date for which fair value was determined and closing.  The result of this adjustment was a payment by PNMR of $2.1 million.

Effective August 1, 2007, Optim Energy completed the acquisition of Altura Cogen, a 614 MW natural gas-fired cogeneration electric and steam plant, located near Houston, Texas.  The purchase price of $477.9 million, after working capital adjustments, was funded through cash contributions of $42.5 million from each of PNMR and ECJV and the remaining amount was financed through borrowings under Optim Energy’s credit facility.

In June 2009, Optim Energy and NRG Cedar Bayou completed a jointly developed 550 MW combined-cycle natural gas unit at the existing NRG Cedar Bayou Generating Station near Houston.   Optim Energy’s share of this unit is 275 MW and its share of the construction costs was $209.6 million.  Optim Energy financed its portion of the Cedar Bayou construction with borrowings under its existing credit facility and operating cash flows.

PNMR has no commitments or guarantees with respect to Optim Energy.

Summarized financial information for Optim Energy is as follows:

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
Operating revenues
  $ 319,507     $ 472,665     $ 224,339  
Cost of sales
    201,547       366,477       147,312  
Gross margin
    117,960       106,188       77,027  
Non-fuel operations and maintenance expenses
    33,118       26,053       13,253  
Administrative and general expenses
    27,910       26,232       15,445  
Impairment of intangible assets
    -       21,794       -  
Write down of emission allowances
    51,586       31,739       -  
Depreciation and amortization expense
    37,171       30,545       15,665  
Taxes other than income tax
    11,089       11,954       4,804  
   Operating income (loss)
    (42,914 )     (42,129 )     27,860  
Other income (deductions)
    (318 )     740       635  
Net interest charges
    (13,755 )     (19,183 )     (17,907 )
Earnings (loss) before income taxes
    (56,987 )     (60,572 )     10,588  
Income taxes (benefit)(1)
    (161 )     (88 )     434  
Net earnings (loss)
  $ (56,826 )   $ (60,484 )   $ 10,154  
                         
50 percent of net earnings (loss)
  $ (28,413 )   $ (30,242 )   $ 5,077  
Amortization of basis difference in Optim Energy
    (1,732 )     555       2,504  
PNMR equity in net earnings (loss) of Optim Energy
  $ (30,145 )   $ (29,687 )   $ 7,581  

(1)  Represents the Texas Margin Tax, which is considered an income tax.

 
B-115

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007



   
December 31,
 
   
2009
   
2008
 
   
(In thousands)
 
Current assets
  $ 128,619     $ 151,677  
Net property plant and equipment
    951,757       946,420  
Deferred assets
    137,384       224,776  
Total assets
    1,217,760       1,322,873  
                 
Current liabilities
    66,190       104,826  
Long-term debt
    755,000       730,778  
Other long-term liabilities
    5,710       7,763  
Total liabilities
    826,900       843,367  
                 
Owners’ equity
  $ 390,860     $ 479,506  
                 
50 percent of owners’ equity
    195,430       239,753  
Unamortized PNMR basis difference in Optim Energy
    236       197  
PNMR equity investment in Optim Energy
  $ 195,666     $ 239,950  

Revenue related to power sales and purchases is included net in operating revenues.  Costs related to fuel purchases and sales are recorded net in cost of sales.

The contribution of Altura created a basis difference between PNMR’s recorded investment in Optim Energy and 50 percent of Optim Energy’s equity.  While the portion of the basis difference related to contract amortization will only continue through 2010, other basis differences, including a difference related to emission allowances, will continue to exist through the life of the Altura plant.  The basis difference adjustment detailed above relates mainly to contract amortization with insignificant offsets related to the other minor basis difference components.

 Optim Energy individually valued each asset and liability received in the Altura (Twin Oaks) and Altura Cogen transactions and initially record them on its balance sheet at the determined fair value.  For both transactions, this accounting results in amortization since contracts acquired were out of market and emission allowances, while acquired from government programs without cost to Optim Energy, have market value.  During 2009, 2008, and 2007, Optim Energy recorded, as a increase (decrease) to operating revenues, income from amortization of contracts acquired of $(6.7) million, $2.2 million, and $36.4 million and amortization expense on emission allowances of $4.7 million, $11.2 million, and $2.3 million, which is recorded in cost of sales.

In July 2008, a federal appeals court ruling by the U.S. Court of Appeals for the District of Columbia Circuit Court invalidated CAIR.  This ruling appears to remove the need for emissions allowance credits under the CAIR program. However, in December 2008, CAIR was temporarily reinstated by the courts.  Optim Energy has inventory of emissions allowances from the purchase of the Altura Cogen plant and contribution of the Twin Oaks plant.  During 2008, Optim Energy recorded a pre-tax write off of $31.7 million for all inventory under the CAIR program.  Optim Energy values its remaining emission allowances at the lower of cost or market.  In December 2009, Optim Energy reduced the value of its held for sale NOx emission allowances by $51.6 million because of significant price declines in an illiquid market.  At December 31, 2009, Optim Energy has $4.9 million remaining held for sale allowances in inventory. As of December 31, 2009, Optim Energy also has $54.6 million in inventory for emission allowances that are held to meet the emission requirements of its generating facilities.

The assets of Altura transferred to Optim Energy included the development rights for a possible 600-megawatt expansion of the Twin Oaks plant, which was classified as an intangible asset.  Optim Energy made a strategic decision not to pursue the Twin Oaks expansion and, in 2008, wrote off the development rights as an
 
B-116

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

impairment of intangible assets amounting to $21.8 million.  In addition $1.2 million of deferred costs related to this project were written off as administrative and general expense.

Optim Energy has a multi-year hedging program.  The level of hedging at any given time varies depending on current market conditions and other factors.  Economic hedges that do not qualify for or are not designated as cash flow hedges or normal purchases/sales are derivative instruments that are required to be marked to market.  Due to the extreme market volatility experienced in the first quarter of 2008 in the ERCOT market, Optim Energy made the decision to exit the speculative trading business and close out the speculative trading positions.  Optim Energy incurred $2.4 million of speculative trading losses in 2008 and has since settled all speculative positions.

See Note 6 for a discussion of the impacts of the bankruptcy of LBCS.

 LCC is Optim Energy’s counterparty in several agreements for power and steam sales. In addition, LCC leases Optim Energy the land for the Altura Cogen facility and provides other services, including water, to that facility.  On January 6, 2009, LCC filed for bankruptcy protection under Chapter 11 of the US Bankruptcy Code.  The pre-petition amount due from LCC is immaterial and was fully reserved as of December 31, 2008.  LCC has continued to perform under the existing contracts.

(23)
Discontinued Operations

PNM Gas

As discussed in Note 2, PNM sold its gas operations, which comprised the PNM Gas segment, on January 30, 2009.  Under GAAP, the assets and liabilities of PNM Gas are considered to be held-for-sale as of December 31, 2007 and presented as discontinued operations on the accompanying balance sheets and statements of earnings.  In accordance with GAAP, no depreciation is recorded on assets held for sale in 2009 and 2008. PNM also retained obligations for certain contingent liabilities that existed at the date of sale.  PNM recognized $5.4 million in expense related to these liabilities in the 2009 Results of Operations for PNM Gas.  Summarized financial information for PNM Gas is as follows:

Financial Position

   
December 31, 2008
 
   
(In thousands)
 
ASSETS
     
Cash and cash equivalents
  $ 25  
Accounts receivable and unbilled revenues, net
    64,022  
Regulatory and other current assets
    43,939  
Total current assets
    107,986  
Gas plant in service
    775,836  
Accumulated depreciation and amortization
    (239,280 )
Construction work in progress
    22,574  
Net utility plant
    559,130  
Regulatory and other assets
    2,785  
    $ 669,901  
         

 
B-117

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007



LIABILITIES AND EQUITY
     
Accounts payable and accrued expenses
  $ 44,995  
Regulatory and other current liabilities
    32,087  
Total current liabilities
    77,082  
Regulatory liabilities
    75,296  
Deferred credits and other liabilities
    19,319  
Total deferred credits and other liabilities
    94,615  
Equity
    498,204  
    $ 669,901  

Results of Operations

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
         
(In thousands)
       
Operating revenues
  $ 65,695     $ 506,953     $ 508,546  
Cost of energy
    44,698       346,571       352,807  
Gross margin
    20,997       160,382       155,739  
Operating expenses
    11,264       92,177       97,102  
Depreciation and amortization
    -       -       21,649  
Operating income
    9,733       68,205       36,988  
Other income (deductions)
    292       2,590       1,147  
Net interest charges
    (962 )     (13,210 )     (12,225 )
Gain on disposal
    98,425       -       -  
Segment earnings before income taxes
    107,488       57,585       25,910  
Income taxes (benefit)
    36,687       22,957       10,394  
Segment Earnings
  $ 70,801     $ 34,628     $ 15,516  

Information on the regulatory assets and liabilities of PNM Gas is as follows:

   
December 31, 2008
 
   
(In thousands)
 
Assets:
     
Current:
     
PGAC
  $ 13,165  
Other
    9,670  
      22,835  
Non-Current:
       
OPEB
    -  
Other
    1,435  
      1,435  
Total regulatory assets
  $ 24,270  
         

 
B-118

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007



Liabilities:
     
Current:
     
PGAC
  $ -  
Off-system sales margin
    (303 )
Other
    (579 )
      (882 )
Non-Current:
       
Cost of Removal
    (75,295 )
Total regulatory liabilities
  $ (76,177 )

PNM Gas’s cost-of-gas revenues collected from sales-service customers were recovered in accordance with NMPRC regulations through the PGAC and represented a pass-through of the cost of natural gas to the customer.  The NMPRC approved an agreement regarding the hedging strategy of PNM Gas and the implementation of a price management fund program which included a continuous monthly balancing account with a carrying charge.  This carrying charge had the effect of keeping PNM Gas whole on purchases of gas since it was compensated for the time value of money that existed due to any delay in collections from customers.

PNM Gas used a variety of hedging instruments including fixed price contracts, call options and financial swaps to facilitate the hedge strategy. PNM Gas also entered into physical gas contracts to meet the needs of its retail sales-service customers.  Due to the agreement to sell PNM Gas, the contracts that extended beyond December 31, 2008 no longer qualified for the normal purchases exception pursuant to GAAP as of December 31, 2007 and were marked-to-market. Costs and gains and losses for the above instruments are deferred and recovered through the PGAC with no income statement effect.  At December 31, 2008, PNM Gas had $7.0 million of current assets and current liabilities and no long-term assets and long-term liabilities related to these instruments.
 
 (24)
Business Improvement Plan

In 2007, the Company began a business improvement process that included a comprehensive cost structure analysis of its operations and a benchmarking analysis to similar-sized utilities.  During 2007 and 2008, the Company implemented a series of initiatives designed to manage future operational costs, maintain financial strength and strengthen its regulated utilities.   The multi-phase process included a business improvement plan to streamline internal processes and reduce the Company’s work force.  The utility-related process enhancements were designed to improve and centralize business functions. Activities contemplated under the business improvement plan have been completed and no significant costs were incurred during 2009.

 The Company has existing plans providing severance benefits to employees who are involuntarily terminated due to elimination of their positions.  Severance benefits payable under the Company’s existing plans are recorded when it is probable that a liability has been incurred and the amount can be reasonably estimated.  At December 31, 2008 and 2007, the Company assessed the status of the business improvement process and the positions that were probable of being eliminated.  The Company calculated the severance benefits associated with those positions and recorded pre-tax expense of $3.4 million in 2008 and $10.5 million in 2007.  In 2008 and 2007, severance expenses of zero and $5.0 million were recorded by PNM and $0.1 million and $0.6 million were recorded by TNMP.  The Company also incurred other costs, primarily consulting fees, related to the business improvement plan of $7.5 million and $2.1 million in 2008 and 2007.

(25)
Goodwill and Other Intangible Assets; Impairments

The excess purchase price over the fair value of the assets acquired and the liabilities assumed by PNMR for its June 6, 2005 acquisition of TNP was recorded as goodwill and was pushed down to the businesses acquired.  In 2007, the TNMP assets that were included in its New Mexico operations, including goodwill of $102.8 million, were transferred to PNM.  See Note 2.  Of the $79.3 million of other intangible assets acquired in the TNP acquisition, $68.8 million related to the trade name “First Choice.”  The trade name is considered to have an indefinite useful
 
B-119

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007

life; therefore, no amortization is recorded.  The other $10.5 million intangible asset related to the First Choice customer list.  The useful life of the customer list was estimated to be approximately eight years.

The Company evaluates its goodwill and non-amortizing intangible assets for impairment annually at the reporting unit level or more frequently if circumstances indicate that the goodwill or intangible assets may be impaired.  Application of the impairment test requires judgment, including the identification of reporting units, assignment of assets and liabilities to reporting units and determination of the fair value of each reporting unit.  The fair value of each reporting unit is estimated using a discounted cash flow methodology.  This analysis requires significant judgments, including estimation of future cash flows, which is dependent on internal forecasts, estimation of long-term growth rates for the business and determination of appropriate weighted average cost of capital for each reporting unit.  Changes in these estimates and assumptions could materially affect the determination of fair value and the conclusion of impairment for each reporting unit.

For non-amortizing intangibles other than goodwill, the Company compares the fair value of the intangible asset to its recorded value.  For goodwill, the first step of the impairment test requires that the Company compare the fair value of each reporting unit with its carrying value, including goodwill.  If as a result of this analysis, the Company concludes there is an indication of impairment in a reporting unit having goodwill, the Company is required to perform the second step of the impairment analysis, determining the amount of goodwill impairment to be recorded.  The amount is calculated by comparing the implied fair value of the goodwill to its carrying amount.  This exercise requires the Company to allocate the fair value determined in step one to the individual assets and liabilities of the reporting unit.  Any remaining fair value would be the implied fair value of goodwill on the testing date.  To the extent the recorded amount of goodwill of a reporting unit exceeds the implied fair value determined in step two, an impairment loss is reflected in results of operations.

The market capitalization of PNMR’s common stock was significantly below book value during 2008, which is an indicator that intangible assets may be impaired.  In addition, changes in the ERCOT market significantly impacted the results of operations of First Choice. The Company performed its annual testing of intangible assets as of April 1, 2008.  As a result of this analysis, the Company concluded there was an indication of impairment in the reporting units having goodwill and that the First Choice trade name was impaired and recorded impairments of $135.0 million for goodwill and $9.0 million for the First Choice trade name.  The financial challenges facing First Choice continued throughout 2008 and were exacerbated by the impacts of Hurricane Ike and depressed economic conditions resulting in significant increases in the levels of uncollectible accounts.  Due to these conditions, additional impairment testing was performed for First Choice as of December 31, 2008.  As a result, the Company recorded additional impairment losses of $39.4 million for First Choice goodwill and $33.6 million for the First Choice trade name at December 31, 2008.  Although the impairments of goodwill, aggregating $174.4 million, have no income tax effects, the impairment of the First Choice trade name amounting to $42.6 million does have an income tax effect and results in an after-tax impact of $27.7 million. The impairments do not impact the Company’s cash flows.  Other than the 2008 impairments, the Company has not recorded any impairments of goodwill.

The 2009 annual evaluation did not indicate impairments of any of PNMR’s reporting units.  While the market capitalization of PNMR’s common stock was still significantly below book value at April 1, 2009, PNMR’s stock price has increased since that date.  In addition, improved regulatory treatment has been experienced by PNM in New Mexico and by TNMP in Texas.  Furthermore, the First Choice business has stabilized in 2009, primarily due to more predictable power and fuel price patterns in the ERCOT market.  These factors have resulted in more predictable earnings and increased fair values of the reporting units. Since the annual evaluation, there have been no indications that the fair values of the reporting units with recorded goodwill have decreased below the carrying values.


 
B-120

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


The changes in the carrying amount of goodwill by reportable segment for the years ended December 31, 2009, 2008, and 2007 were as follows:

   
PNM
   
TNMP
Electric
   
First
Choice
   
Total
PNMR
 
   
(In thousands)
 
                         
Balance as of December 31, 2006
  $ -     $ 363,764     $ 131,974     $ 495,738  
Adjustments during 2007
    102,775       (102,643 )     (206 )     (74 )
Balance as of December 31, 2007
    102,775       261,121       131,768       495,664  
Impairments during 2008
    (51,143 )     (34,456 )     (88,755 )     (174,354 )
Balance as of December 31, 2008 and 2009
  $ 51,632     $ 226,665     $ 43,013     $ 321,310  


The components of PNMR’s other identifiable intangible assets are as follows:

   
December 31,
 
   
2009
   
2008
 
   
(In thousands)
 
             
First Choice trade name
  $ 26,157     $ 26,157  
First Choice customer list
    5,682       5,682  
Total other intangible assets
    31,839       31,839  
Accumulated amortization
    5,272       4,672  
    $ 26,567     $ 27,167  

The Company evaluates its amortizing intangible assets for impairment only when circumstances indicate that the intangible assets may be impaired.  Due to conditions at First Choice described above, the Company performed an impairment test of the First Choice customer list asset as of December 31, 2008 and as a result, recorded a pre-tax impairment of $4.8 million ($3.1 million after-tax) for this asset.

See Note 22 for a discussion of impairments recorded by Optim Energy.

(26)
Quarterly Operating Results (Unaudited)

Unaudited operating results by quarters for 2009 and 2008 are presented below. In the opinion of management of the Company, all adjustments (consisting of normal recurring accruals) necessary for a fair statement of the results of operations for such periods have been included.  On January 30, 2009, PNM completed the sale of PNM Gas, which is considered discontinued operations and excluded from continuing operations in the tables below.  See Note 2 and Note 23.

 
B-121

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007



         
Quarter Ended
       
   
March 31
   
June 30
   
September 30
   
December 31
 
   
(In thousands, except per share amounts)
 
PNMR
     
2009
                       
Operating revenues
  $ 385,865     $ 401,110     $ 477,727     $ 383,042  
Operating income
    29,903       24,878       101,536       35,625  
Earnings from continuing operations
    16,407       3,419       58,223       (12,116 )
Earnings from continuing operations attributable to PNMR
    13,696       512       55,555       (16,248 )
Net earnings
    92,260       808       56,861       (13,195 )
Net earnings (loss) attributable to PNMR
    89,549       (2,099 )     54,193       (17,327 )
Earnings from Continuing Operations Attributable to PNMR per Common Share:
                               
Basic
    0.15       0.01       0.61       (0.18 )
Diluted
    0.15       0.01       0.60       (0.18 )
Net Earnings (Loss) Attributable to PNMR per Common Share:
                               
Basic
    0.98       (0.02 )     0.59       (0.19 )
Diluted
    0.98       (0.02 )     0.59       (0.19 )
2008
                               
Operating revenues
  $ 364,503     $ 580,310     $ 607,076     $ 407,633  
Operating income (loss)
    (58,971 )     (122,760 )     33,664       (81,747 )
Earnings (loss) from continuing operations
    (71,003 )     (145,115 )     (1,264 )     (80,183 )
Earnings (loss) from continuing operations attributable to PNMR
    (71,135 )     (146,248 )     (4,847 )     (83,042 )
Net earnings (loss)
    (48,504 )     (142,353 )     (1,902 )     (70,178 )
Net earnings (loss) attributable to PNMR
    (48,636 )     (143,486 )     (5,485 )     (73,037 )
Earnings (Loss) from Continuing Operations Attributable to PNMR per Common Share:
                               
Basic
    (0.93 )     (1.79 )     (0.06 )     (0.94 )
Diluted
    (0.93 )     (1.79 )     (0.06 )     (0.94 )
Net Earnings (Loss) Attributable to PNMR per Common Share:
                               
Basic
    (0.63 )     (1.76 )     (0.06 )     (0.82 )
Diluted
    (0.63 )     (1.76 )     (0.06 )     (0.82 )
PNM
                               
2009
                               
Operating revenues
  $ 231,955     $ 226,541     $ 275,025     $ 234,488  
Operating income (loss)
    10,486       (10,441 )     58,952       18,254  
Earnings (loss) from continuing operations
    (2,344 )     (5,146 )     33,447       5,944  
Net earnings (loss)
    73,509       (7,757 )     32,085       4,865  
Net earnings (loss) attributable to PNM
    70,930       (10,532 )     29,549       865  
2008
                               
Operating revenues
  $ 252,664     $ 386,058     $ 356,397     $ 247,823  
Operating income (loss)
    (30,582 )     (29,637 )     47,385       6,317  
Earnings (loss) from continuing operations
    (26,977 )     (46,007 )     19,385       (5,696 )
Net earnings (loss)
    (4,478 )     (43,245 )     18,747       4,309  
Net earnings (loss) attributable to PNM
    (4,478 )     (44,246 )     15,296       1,582  
TNMP
                               
2009
                               
Operating revenues
  $ 41,225     $ 46,819     $ 55,665     $ 48,923  
Operating income (loss)
    6,085       10,432       16,732       11,853  
Net earnings (loss)
    1,421       1,766       6,151       2,828  
2008
                               
Operating revenues
  $ 42,228     $ 47,118     $ 51,097     $ 49,839  
Operating income (loss)
    10,583       (21,563 )     15,506       12,924  
Net earnings (loss)
    3,730       (28,753 )     8,093       8,137  

 
B-122

 
PNM RESOURCES, INC. AND SUBSIDIARIES
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARIES
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
December 31, 2009, 2008 and 2007


As discussed in Note 12, the actuarial determination of the PBO for the PNM pension plan at December 31, 2009 revealed that there had been an increase in the PBO of $9.6 million due to the retirement of employees transferred to NMGC following the sale of PNM Gas in January 2009.  This increase was expensed, similar to a plan curtailment, as required by GAAP and reduced the gain recognized on the sale.  The expense for the PBO increase is reflected through a retroactive adjustment of the March 31, 2009 quarter in the above table and PNMR and PNM will restate that quarter on its Form 10-Qs during 2010.  The retroactive adjustment is part of discontinued operations for PNMR and PNM and does not impact earnings from continuing operations or earnings per share from continuing operations.  The retroactive adjustment had the following impact on the March 31, 2009 amounts presented above:

 
   
Quarter Ended March 31, 2009
 
   
As previously
       
   
Reported
   
As Restated
 
   
(In thousands, except per share amounts)
 
             
PNMR
           
Net earnings (loss)
  $ 98,082     $ 92,260  
Net earnings (loss) attributable to PNMR
    95,371       89,549  
Net Earnings (Loss) Attributable to PNMR per Common Share:
               
Basic
    1.04       0.98  
Diluted
    1.04       0.98  
                 
PNM
               
Net earnings (loss)
    79,331       73,509  
Net earnings (loss) attributable to PNM
    76,752       70,930  

 
B-123

 


REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM

To the Board of Directors and Stockholders of
PNM Resources, Inc. and Public Service Company of New Mexico
Albuquerque, New Mexico

We have audited the consolidated financial statements of PNM Resources, Inc. and subsidiaries and Public Service Company of New Mexico and subsidiaries (collectively, the “Companies”) as of December 31, 2009 and 2008, and for each of the three years in the period ended December 31, 2009, and have issued our reports thereon dated February 27, 2010 (which reports express an unqualified opinion and include an explanatory paragraph regarding changes in the method of accounting for fair value measurements in 2008) and internal control over financial reporting as of December 31, 2009 and have issued our reports theron dated February 27, 2010; such consolidated financial statements and reports are included elsewhere in this Form 10-K. Our audits also included the financial statement schedules of the Companies listed in Item 15. The financial statement schedules are the responsibility of the Companies’ management. Our responsibility is to express an opinion based on our audits. In our opinion, such financial statement schedules, when considered in relation to the basic consolidated financial statements taken as a whole, present fairly, in all material respects, the information set forth therein.
 
/s/ DELOITTE & TOUCHE LLP
 
Dallas, Texas
February 27, 2010



 
B-124

 

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM

To the Board of Directors and Stockholder of
Texas-New Mexico Power Company
Lewisville, Texas

We have audited the consolidated financial statements of Texas-New Mexico Power Company and subsidiaries (collectively, the “Company”) as of December 31, 2009 and 2008, and for each of the three years in the period ended December 31, 2009, and have issued our report thereon dated February 27, 2010; such consolidated financial statements and report are included elsewhere in this Form 10-K.  Our audit also included the financial statement schedule of the Company listed in Item 15.  The financial statement schedule is the responsibility of the Company's management.  Our responsibility is to express an opinion based on our audit.  In our opinion, such financial statement schedule, when considered in relation to the basic consolidated financial statements taken as a whole, presents fairly, in all material respects, the information set forth therein.
 
/s/ DELOITTE & TOUCHE LLP
 
Dallas, Texas
February 27, 2010



 
B-125

 

SCHEDULE I

PNM RESOURCES, INC.
CONDENSED FINANCIAL INFORMATION OF PARENT COMPANY
BALANCE SHEETS

   
December 31,
 
   
2009
   
2008
 
   
(In thousands)
 
Assets
           
Cash and cash equivalents
  $ 6,652     $ 75,095  
Intercompany receivables
    98,599       102,511  
Income taxes receivable
    57,859       64,984  
Other current assets
    -       1,266  
Total current assets
    163,110       243,856  
                 
Property, plant and equipment, net of accumulated
               
depreciation of $10,916 and $9,731
    22,216       23,459  
Long-term investments
    16,400       21,153  
Investment in subsidiaries (including discontinued operations)
    1,648,336       1,805,046  
Equity investment in Optim Energy
    195,666       239,950  
Other long-term assets
    3,439       6,831  
Total long-term assets
    1,886,057       2,096,439  
                 
    $ 2,049,167     $ 2,340,295  
                 
Liabilities and Stockholders' Equity
               
Short-term debt
  $ 40,000     $ 154,667  
Short-term debt-affiliate
    6,800       3,600  
Current maturities of long-term debt
    2,125       2,004  
Current liabilities
    17,073       16,842  
Total current liabilities
    65,998       177,113  
Long-term debt
    199,761       359,294  
Other long-term liabilities
    33,691       57,482  
Total liabilities
    299,450       593,889  
                 
  Convertible preferred stock (no stated value, 10,000,000 shares authorized:
               
      issued and outstanding 477,800 shares)
    100,000       100,000  
                 
Common stock outstanding (no par value, 120,000,000 shares authorized:
               
issued and outstanding 86,673,174 and 86,531,644 shares
    1,289,890       1,288,168  
Accumulated other comprehensive income, net of tax
    (46,057 )     30,948  
Retained earnings
    405,884       327,290  
Total common stockholders' equity
    1,649,717       1,646,406  
                 
    $ 2,049,167     $ 2,340,295  




 
B-126

 

SCHEDULE I
PNM RESOURCES, INC.
CONDENSED FINANCIAL INFORMATION OF PARENT COMPANY
STATEMENTS OF EARNINGS

   
Year ended December 31,
 
   
2009
   
2008
   
2007
 
         
(In thousands)
       
                   
Operating Revenues
  $ -     $ -     $ -  
Operating Expenses
    8,156       23,819       22,434  
Operating income (loss)
    (8,156 )     (23,819 )     (22,434 )
Other Income and Deductions:
                       
Equity in earnings (loss) of subsidiaries
    76,492       (254,093 )     78,580  
Equity in net earnings (loss) of Optim Energy
    (30,145 )    
(29,687)
      7,581  
Other income
    22,916       3,355       2,766  
Other deductions
    (26,850 )     (45,782 )     (47,217 )
  Net other income (deductions)
    42,413       (326,207 )     41,710  
                         
Income (Loss) Before Income Taxes
    34,257       (350,026 )     19,276  
Income Tax Expense (Benefit)
    (19,258 )     (44,754 )     (40,082 )
                         
Earnings (Loss) from Continued Operations
    53,515       (305,272 )     59,358  
                         
Earnings from Discontinued Operations, net of income
                       
taxes of $36,687,  $22,957, and $10,394
    70,801       34,628       15,516  
                         
Net Earnings (Loss)
  $ 124,316     $ (270,644 )   $ 74,874  



 
B-127

 

SCHEDULE I
PNM RESOURCES, INC.
CONDENSED FINANCIAL INFORMATION OF PARENT COMPANY
STATEMENTS OF CASH FLOWS

   
Year Ended December 31,
 
   
2009
   
2008
   
2007
 
   
(In thousands)
 
Cash Flows From Operating Activities:
                 
Net earnings (loss)
  $ 124,316     $ (270,644 )   $ 74,874  
Adjustments to reconcile net earnings (loss) to net cash flows
                       
from operating activities:
                       
Depreciation and amortization
    4,893       4,249       4,942  
Deferred income tax expense
    (16,957 )     (13,787 )     (416 )
Equity in (earnings) loss of subsidiaries
    (147,293 )     219,465       (94,096 )
Equity in net (earnings) loss of Optim Energy
    30,145       29,687       (7,581 )
Impairment of intangible assets
    -       -       3,380  
Gain on reacquired debt
    (7,317 )                
Realized loss on Altura contribution
    -       -       3,089  
Stock based compensation expense
    2,188       3,261       7,557  
Other, net
    -       -       -  
Changes in certain assets and liabilities:
                       
Other current assets
    8,391       10,991       (1,366 )
Other assets
    634       33       3,375  
Accounts payable
    (97 )     71       (641 )
Accrued interest and taxes
    (1,080 )     (3,704 )     (73,376 )
Other current liabilities
    1,387       (3,009 )     42,150  
Other liabilities
    (22,359 )     (29,288 )     (10,099 )
Net cash flows from operating activities
    (23,149 )     (52,675 )     (48,208 )
Cash Flows From Investing Activities:
                       
Additions to property, plant and equipment
    -       -       (8 )
Investments in subsidiaries
    (86,253 )     -       (148,349 )
Investments in Optim Energy
    -       -       (45,040 )
Distributions from Optim Energy
    -       -       362,282  
Cash dividends from subsidiaries
    347,012       40,042       101,300  
Other, net
    3       -       592  
Net cash flows from investing activities
    260,762       40,042       270,777  
Cash Flows From Financing Activities:
                       
Short-term borrowings (repayments), net
    (114,667 )     (202,224 )     (158,086 )
Short-term borrowings (repayments – affiliate)
    3,200              
Long-term debt repayments
    (148,422 )            
Long-term debt borrowings
    -       102,750                                 -  
Issuance of common stock
    1,245       250,956       4,281  
Exercise of employee stock options
    (951 )     (1,315 )     (7,266 )
Excess tax benefit from stock-based payment arrangements
    (760 )     (560 )     12  
Dividends paid
    (45,701 )     (56,970 )     (69,807 )
Other, net
    -       (5,253 )     (404 )
Net cash flows from financing activities
    (306,056 )     87,384       (231,270 )
Change in Cash and Cash Equivalents
    (68,443 )     74,751       (8,701 )
Cash and Cash Equivalents at Beginning of Period
    75,095       344       9,045  
Cash and Cash Equivalents at End of Period
  $ 6,652     $ 75,095     $ 344  
Supplemental Cash Flow Disclosures:
                       
Interest paid
  $ 32,092     $ 54,746     $ 39,938  
Income taxes paid (refunded), net
  $ 116,593     $ (5,936 )   $ (2,903 )
                         
Supplemental schedule of non cash investing and financing activities:
                       
Convertible preferred stock issued under forward purchase contract
                       
   upon tender of senior unsecured notes
          $ 100,000          


 
B-128

 

SCHEDULE II
PNM RESOURCES, INC. AND SUBSIDIARIES
VALUATION AND QUALIFYING ACCOUNTS

         
Additions
   
Deductions
       
                               
   
Balance at
   
Charged to
   
Charged to
             
   
beginning of
   
costs and
   
other
         
Balance at
 
Description
 
year
   
expenses
   
accounts
   
Write-offs
   
end of year
 
         
(In thousands)
       
(a)    Allowance for doubtful accounts,
                             
year ended December 31:
                             
2007
  $ 5,840     $ 17,044     $ -     $ 16,863     $ 6,021  
                                         
2008
  $ 6,021     $ 56,136     $ -     $ 40,691     $ 21,466  
                                         
2009
  $ 21,466     $ 43,937     $ -     $ 52,620     $ 12,783  
                                         


(a)  
Totals reflect continuing operations.






 
B-129

 

SCHEDULE II
PUBLIC SERVICE COMPANY OF NEW MEXICO AND SUBSIDIARY
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
VALUATION AND QUALIFYING ACCOUNTS

         
Additions
   
Deductions
       
                               
   
Balance at
   
Charged to
   
Charged to
             
   
beginning of
   
costs and
   
other
         
Balance at
 
Description
 
year
   
expenses
   
accounts
   
Write-offs
   
end of year
 
         
(In thousands)
       
(a)    Allowance for doubtful accounts,
                             
year ended December 31:
                             
2007
  $ 729     $ 1,967     $ -     $ 1,967     $ 729  
                                         
2008
  $ 729     $ 4,186     $ -     $ 3,570     $ 1,345  
                                         
2009
  $ 1,345     $ 2,534     $ -     $ 2,396     $ 1,483  
                                         


(a)  
Totals reflect continuing operations.


 
B-130

 

SCHEDULE II
TEXAS-NEW MEXICO POWER COMPANY AND SUBSIDIARIES
A WHOLLY OWNED SUBSIDIARY OF PNM RESOURCES, INC.
VALUATION AND QUALIFYING ACCOUNTS

         
Additions
   
Deductions
       
                               
   
Balance at
   
Charged to
   
Charged to
             
   
beginning of
   
costs and
   
other
         
Balance at
 
Description
 
year
   
expenses
   
accounts
   
Write-offs
   
end of year
 
         
(In thousands)
       
Allowance for doubtful accounts,
                             
year ended December 31:
                             
                               
2007
  $ 31     $ 3     $ -     $ 34     $ -  
                                         
2008
  $ -     $ 144     $ -     $ 144     $ -  
                                         
2009
  $ -     $ 238     $ -     $ 238     $ -  





 
B-131

 

ITEM 9.
CHANGES IN AND DISAGREEMENTS WITH ACCOUNTANTS ON ACCOUNTING AND FINANCIAL DISCLOSURE

None.

ITEM 9A.
CONTROLS AND PROCEDURES

PNMR

(a) Evaluation of disclosure controls and procedures.

As of the end of the period covered by this annual report, PNMR conducted an evaluation under the supervision and with the participation of PNMR’s management, including the Chief Executive Officer and the Chief Financial Officer, of the effectiveness of the design and operation of the disclosure controls and procedures (as defined in Regulation 13A, Sections 13a-15(e) and 15d-15(e) of the Securities Exchange Act of 1934).  Based upon this evaluation, the Chief Executive Officer and the Chief Financial Officer concluded that the disclosure controls and procedures are effective.

(b) Management’s report on internal control over financial reporting.

    “Management’s Annual Report on Internal Control Over Financial Reporting” appears on page B-2. This report is incorporated by reference herein.

(c) Changes in internal controls.

    There have been no changes in PNMR’s internal control over financial reporting (as such term is defined in Rules13a-15(f) and 15d-15(f) under the Securities Exchange Act of 1934) during the quarter ended December 31, 2009 that have materially affected, or are reasonably likely to materially affect, PNMR’s internal control over financial reporting.

PNM

(a) Evaluation of disclosure controls and procedures.

    As of the end of the period covered by this annual report, PNM conducted an evaluation under the supervision and with the participation of PNM’s management, including the Chief Executive Officer and the Chief Financial Officer, of the effectiveness of the design and operation of the disclosure controls and procedures (as defined in Regulation 13A, Sections 13a-15(e) and 15d-15(e) of the Securities Exchange Act of 1934).  Based upon this evaluation, the Chief Executive Officer and the Chief Financial Officer concluded that the disclosure controls and procedures are effective.

(b) Management’s report on internal control over financial reporting.

    “Management’s Annual Report on Internal Control Over Financial Reporting” appears on page B-3. This report is incorporated by reference herein.

(c) Changes in internal controls.

    There have been no changes in PNM’s internal control over financial reporting (as such term is defined in Rules13a-15(f) and 15d-15(f) under the Securities Exchange Act of 1934) during the quarter ended December 31, 2009 that have materially affected, or are reasonably likely to materially affect, PNM’s internal control over financial reporting.


C-1
 
 

 

TNMP

(a) Evaluation of disclosure controls and procedures.

    As of the end of the period covered by this annual report, TNMP conducted an evaluation under the supervision and with the participation of TNMP’s management, including the Chief Executive Officer and the Chief Financial Officer, of the effectiveness of the design and operation of the disclosure controls and procedures (as defined in Regulation 13A, Sections 13a-15(e) and 15d-15(e) of the Securities Exchange Act of 1934).  Based upon this evaluation, the Chief Executive Officer and the Chief Financial Officer concluded that the disclosure controls and procedures are effective.

(b) Management’s report on internal control over financial reporting.

    “Management’s Annual Report on Internal Control Over Financial Reporting” appears on page B-4. This report is incorporated by reference herein.

(c) Changes in internal controls.

    There have been no changes in TNMP’s internal control over financial reporting (as such term is defined in Rules13a-15(f) and 15d-15(f) under the Securities Exchange Act of 1934) during the quarter ended December 31, 2009 that have materially affected, or are reasonably likely to materially affect, TNMP’s internal control over financial reporting.

ITEM 9B.
OTHER INFORMATION

None.

PART III

ITEM 10.
DIRECTORS, EXECUTIVE OFFICERS OF PNMR AND CORPORATE GOVERNANCE

Reference is hereby made to “Proposal 1:  Elect Ten Directors” in PNMR’s Proxy Statement relating to the annual meeting of stockholders to be held on May 18, 2010 (the “2010 Proxy Statement”), to PART I, SUPPLEMENTAL ITEM - “EXECUTIVE OFFICERS OF THE COMPANY” in this Form 10-K, “Other Matters” - “Section 16(a) Beneficial Ownership Reporting Compliance”, “Code of Ethics” and “Board Committees and Their Functions”-“Audit and Ethics Committee” in the 2010 Proxy Statement.  The Company intends to satisfy the disclosure requirements of Form 8-K relating to amendments to the Company’s code of ethics applicable to its senior executive and financial officers by posting such information on its Internet website.  Information about the Company’s website is included under Part I, Item 1 - “Company Website.”

PNMR’s common stock is listed on the New York Stock Exchange. As a result, PNMR’s Chief Executive Officer is required to make an annual certification to the New York Stock Exchange stating that he was not aware of any violations by PNMR of the New York Stock Exchange corporate governance listing standards.  PNMR’s Chief Executive Officer made the most recent certification to the New York Stock Exchange on May 28, 2009.


C-2
 
 

 

ITEM 11.       EXECUTIVE COMPENSATION

Reference is hereby made to “Executive Compensation”, and all subheadings thereunder from “Compensation Discussion and Analysis” to “Potential Payments Upon Termination or Change in Control”, “Director Compensation”, and “Board Committees and Their Functions”-“Board Governance and Human Resources Committee”-“Interlocks” in the 2010 Proxy Statement.

ITEM 12.
SECURITY OWNERSHIP OF CERTAIN BENEFICIAL OWNERS AND MANAGEMENT AND RELATED STOCKHOLDER MATTERS

Reference is hereby made to “PNM Resources Common Stock Owned by Executive Officers and Directors,” “Ownership of More Than Five Percent of PNM Resources Common Stock” and “Equity Compensation Plan Information” in the 2010 Proxy Statement.

ITEM 13.
CERTAIN RELATIONSHIPS AND RELATED TRANSACTIONS AND DIRECTOR INDEPENDENCE

Reference is hereby made to “Related Person Transactions” and “Director Independence” in the 2010 Proxy Statement.

ITEM 14.
PRINCIPAL ACCOUNTING FEES AND SERVICES

Reference is hereby made to “Audit and Ethics Committee Report” and “Independent Auditor Fees” in the 2010 Proxy Statement.  Independent auditor fees for PNM and TNMP are reported in the 2010 Proxy Statement for PNMR.  All such fees are fees of PNMR.


C-3
 
 

 


 
PART IV

ITEM 15.
EXHIBITS, FINANCIAL STATEMENT SCHEDULES

(a) - 1. See Index to Financial Statements under Item 8.
(a) - 2. Financial Statement Schedules for the years 2009, 2008, and 2007 are omitted for the reason that they are not required or the information is otherwise supplied under Item 8.
(a) - 3-A. Exhibits Filed:

Exhibit
No.
 
Description
     
10.1**
PNMR
Changes in Director Compensation
     
12.1
PNMR
Ratio of Earnings to Fixed Charges
     
12.2
PNM
Ratio of Earnings to Fixed Charges
     
12.3
TNMP
Ratio of Earnings to Fixed Charges
     
21
PNMR
Certain subsidiaries of PNM Resources, Inc.
     
23.1
PNMR
Consent of Deloitte & Touche LLP for PNM Resources, Inc.
     
23.2
PNM
Consent of Deloitte & Touche LLP for Public Service Company of New Mexico
     
31.1
PNMR
Chief Executive Officer Certification Pursuant to Section 302 of the Sarbanes-Oxley Act of 2002
     
31.2
PNMR
Chief Financial Officer Certification Pursuant to Section 302 of the Sarbanes-Oxley Act of 2002
     
31.3
PNM
Chief Executive Officer Certification Pursuant to Section 302 of the Sarbanes-Oxley Act of 2002
     
31.4
PNM
Chief Financial Officer Certification Pursuant to Section 302 of the Sarbanes-Oxley Act of 2002
     
31.5
TNMP
Chief Executive Officer Certification Pursuant to Section 302 of the Sarbanes-Oxley Act of 2002
     
31.6
TNMP
Chief Financial Officer Certification Pursuant to Section 302 of the Sarbanes-Oxley Act of 2002
     
32.1
PNMR
Chief Executive Officer Certification Pursuant to Section 906 of the Sarbanes-Oxley Act of 2002
     
32.2
PNMR
Chief Financial Officer Certification Pursuant to Section 906 of the Sarbanes-Oxley Act of 2002
     
32.3
PNM
Chief Executive Officer Certification Pursuant to Section 906 of the Sarbanes-Oxley Act of 2002
     
32.4
PNM
Chief Financial Officer Certification Pursuant to Section 906 of the Sarbanes-Oxley Act of 2002
     
32.5
TNMP
Chief Executive Officer Certification Pursuant to Section 906 of the Sarbanes-Oxley Act of 2002
     
32.6
TNMP
Chief Financial Officer Certification Pursuant to Section 906 of the Sarbanes-Oxley Act of 2002

Note:  Separate financial statements of 50 percent or less owned persons will be filed by amendment to PNMR’s Form 10-K to the extent required by Article 3.09 of SEC Regulation S-X.

 
D-1

 
(a) - 3-B.  Exhibits Incorporated By Reference:

The documents listed below are being filed (as shown above) or have been previously filed on behalf of PNM Resources, PNM or TNMP and are incorporated by reference to the filings set forth below pursuant to Exchange Act Rule 12b-32 and Regulation S-K section 10, paragraph (d).

Exhibit No.
Description of Exhibit
 
Filed as Exhibit:
Registrant(s)
File No:
         
Plan of Acquisition
     
2.0
Asset Purchase Agreement dated January 12, 2008 among PNM, Continental Energy Systems, LLC and New Mexico Gas Company, Inc.
 
 
2.0 to PNM’s Annual Report on Form 10-K for the year ended December 31, 2007
1-6986
PNM
2.1
Agreement and Plan of Merger among PNM Resources, PNM Merger Sub LLC, Continental Energy Systems, LLC and Cap Rock Holding Corporation dated as of January 12, 2008
 
 
2.1 to the Company’s Annual Report on Form 10-K for the year ended December 31, 2007
1-32462
PNMR
2.2
Contribution Agreement, dated as of June 1, 2007, among EnergyCo, LLC, PNM Resources, and ECJV Holdings, LLC
 
 
2.1 to the Company’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2007
1-32462
PNMR
2.3
Purchase and Sale Agreement, dated as of January 14, 2006 among Twin Oaks Power LP, Twin Oaks Power III, LP, Sempra Energy, Altura Power L.P. and PNM Resources (Confidential treatment was requested for portions of the exhibit, and such portions were omitted from this exhibit filed and were filed separately with the Securities and Exchange Commission)
 
2.1 to the Company’s Annual Report on Form 10-K for the year ended December 31, 2005
1-32462
PNMR
         
Articles of Incorporation and By-laws
     
3.1
Articles of Incorporation of PNM Resources, as amended to date (Certificate of Amendment dated October 27, 2008 and Restated Articles of Incorporation dated August 3, 2006)
 
3.1 to the Company’s Current Report on Form 8-K filed November 21, 2008
1-32462
PNMR
         
3.2
Restated Articles of Incorporation of PNM, as amended through May 31, 2002
 
3.1.1 to the Company’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2002
1-6986
PNM
         
3.3
Articles of Incorporation of TNMP, as amended through July 7, 2005
 
3.1.2 to the Company’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2005
2-97230
TNMP
         
3.4
Bylaws of PNM Resources, Inc. with all amendments to and including December 8, 2009
 
3.1 to the Company’s Current Report on Form 8-K filed December 11, 2009
1-32462
PNMR
         
3.5
Bylaws of PNM with all amendments to and including May 31, 2002
 
3.1.2 to the Company’s Report on Form 10-Q for the fiscal quarter ended June 30, 2002
1-6986
PNM
 
 
D-2

 
 
Exhibit No.
Description of Exhibit
 
Filed as Exhibit:
Registrant(s)
File No:
3.6
Bylaws of TNMP as adopted on August 4, 2005
 
3.2.3 to the Company’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2005
2-97230
TNMP
         
         
Indentures
       
PNMR
       
         
4.1
Indenture, dated as of March 15, 2005, between PNMR and JPMorgan Chase Bank, N.A., as Trustee
 
10.2 to PNMR’s Current Report on Form 8-K filed March 31, 2005
1-32462
PNMR
         
4.2
Supplemental Indenture No. 1, dated as of March 30, 2005, between the Company and JPMorgan Chase Bank, N.A. as Trustee, with Form of Senior Note included as Exhibit A thereto
 
10.3 to PNMR’s Current Report on Form 8-K filed March 31, 2005
333-32170
PNMR
         
4.3
Supplemental Indenture No. 2, dated as of May 16, 2008 between PNMR and The Bank of New York Trust Company, N.A. (successor to JPMorgan Chase Bank, N.A.), as trustee
 
4.3 to PNMR’s Current Report on Form 8-K filed May 21, 2008
1-32462
PNMR
         
4.4
Underwriting Agreement dated May 9, 2008 among PNMR and Lehman Brothers Inc. and Merrill Lynch, Pierce, Fenner & Smith Incorporated, as representatives of the Underwriters named therein
 
1.3 to the Company’s Current Report on Form 8-K filed May 12, 2008
 
         
4.5
Amended and Restated Purchase Contract Agreement dated as of August 4, 2008, between PNMR and U.S. Bank National Association, as purchase contract agent
 
4.1 to the Company’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2008
1-32462
PNMR
         
4.6
Amended and Restated Pledge Agreement, dated as of August 4, 2008, between PNMR and U.S. Bank National Association
 
4.2 to the Company’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2008
2-43573
PNMR
         
4.7
Indenture, dated as of October 7, 2005, between PNMR and U.S. Bank National Association, as trustee
 
4.11 to the Company’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2005
1-32462
PNMR
         
4.8
Supplemental Indenture, dated as of October 7, 2005, between PNMR and U.S. Bank National Association, as trustee, with Form of Senior Note included as Exhibit A thereto
 
4.12 to the Company’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2005
1-32462
PNMR
         
4.9
Supplemental Indenture No. 2, dated as of August 4, 2008 between PNMR and U.S. Bank National Association, as trustee
 
4.3 to PNMR’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2008
1-32462
PNMR
 
 
D-3

 
 
Exhibit No.
Description of Exhibit
 
Filed as Exhibit:
Registrant(s)
File No:
4.10
Remarketing Agreement, dated as of October 7, 2005, among PNMR, Banc of America Securities LLC, as remarketing agent and U.S. Bank National Association as purchase contract agent.
 
4.9 to the Company’s Annual Report on Form 10-K for the year ended December 31, 2005
1-32462
PNMR
         
4.11
Supplemental Remarketing Agreement dated November 7, 2008 among PNMR, remarketing agents named therein and U.S. Bank National Association, as purchase contract agent
 
10.1 to PNMR’s Current Report on Form 8-K filed November 13, 2008
1-32462
PNMR
         
4.12
Registration Rights Agreement, dated as of October 7, 2005, between PNMR, as issuer and Cascade Investment, LLC, as initial holder.
 
4.10 to the Company’s Annual Report on Form 10-K for the year ended December 31, 2005
1-32462
PNMR
         
PNM
       
4.13
Indenture of Mortgage and Deed of Trust dated as of June 1, 1947, between PNM and The Bank of New York (formerly Irving Trust Company), as Trustee, together with the Ninth Supplemental Indenture dated as of January 1, 1967, the Twelfth Supplemental Indenture dated as of September 15, 1971, the Fourteenth Supplemental Indenture dated as of December 1, 1974 and the Twenty-Second Supplemental Indenture dated as of October 1, 1979 thereto relating to First Mortgage Bonds of PNM
 
4-(d) to PNM’s Registration Statement No. 2-99990
2-99990
PNM
         
4.14
Fifty-third Supplemental Indenture, dated as of March 11, 1998, supplemental to Indenture of Mortgage and Deed of Trust, dated as of June 1, 1947, between PNM and The Bank of New York(formerly Irving Trust Company), as trustee
 
4.3 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1998
1-6986
PNM
         
4.15
Indenture (for Senior Notes), dated as of March 11, 1998, between PNM and The Chase Manhattan Bank, as Trustee
 
4.4 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1998
1-6986
PNM
         
4.16
First Supplemental Indenture, dated as of March 11, 1998, supplemental to Indenture, dated as of March 11, 1998, Between PNM and The Chase Manhattan Bank, as Trustee
 
4.5 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1998
1-6986
PNM
         
4.17
Second Supplemental Indenture, dated as of March 11, 1998, supplemental to Indenture, dated as of March 11, 1998, Between PNM and The Chase Manhattan Bank, as Trustee
 
4.6 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1998
1-6986
PNM
 
 
D-4

 
 
Exhibit No.
Description of Exhibit
 
Filed as Exhibit:
Registrant(s)
File No:
4.18
Third Supplemental Indenture, dated as of October 1, 1999 to Indenture dated as of March 11, 1998, between PNM and The Chase Manhattan Bank, as Trustee
 
4.6.1 to PNM’s Annual Report on Form 10-K for the fiscal year ended December 31, 1999
1-6986
PNM
         
4.19
Fourth Supplemental Indenture, dated as of May 1, 2003 to Indenture dated as of March 11, 1998, between PNM and JPMorgan Chase Bank (formerly The Chase Manhattan Bank), as Trustee
 
4.6.2 to PNM’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2003
1-6986
PNM
         
4.20
Fifth Supplemental Indenture, dated as of May 1, 2003 to Indenture dated as of March 11, 1998, between PNM and JPMorgan Chase Bank, as Trustee
 
4.6.3 to PNM’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2003
1-6986
PNM
 
4.21
Sixth Supplemental Indenture, dated as of May 1, 2003 to Indenture dated as of March 11, 1998, between PNM and JPMorgan Chase Bank, as Trustee
 
4.6.4 to PNM’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2003
1-6986
PNM
         
4.22
Seventh Supplemental Indenture, dated as of June 1, 2007 to Indenture dated as of March 11, 1998, between PNM and The Bank of New York Trust Company, N.A. (successor to JPMorgan Chase Bank), as Trustee
 
4.23 to PNM’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2007
1-6986
PNM
         
4.23
Indenture (for Senior Notes), dated as of August 1, 1998, between PNM and The Chase Manhattan Bank, as Trustee
 
4.1 to PNM’s Registration Statement No. 33-53367
333-53367
PNM
         
4.24
First Supplemental Indenture, dated August 1, 1998, supplemental to Indenture, dated as of August 1, 1998, between PNM and The Chase Manhattan Bank, as Trustee
 
4.3 to PNM’s Current Report on Form 8-K Dated August 7, 1998
1-6986
PNM
         
4.25
Second Supplemental Indenture, dated September 1, 2003, supplemental to Indenture, dated as of August 1, 1998, between PNM and JPMorgan Chase Bank (formerly, The Chase Manhattan Bank), as Trustee
 
4.7.1 to PNM’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2003
1-6986
PNM
         
4.26
Third Supplemental Indenture, dated as of May 13, 2008 between PNM and The Bank of New York Trust Company, N.A. as trustee
 
4.2 to PNM’s Current Report on Form 8-K filed May 15, 2008
1-6986
PNM
         
4.27
Underwriting Agreement dated May 8, 2008 among PNM and Lehman Brothers Inc. and Merrill Lynch, Pierce, Fenner & Smith Incorporated, as representatives of the Underwriters named therein
 
1.2 to the Company’s Current Report on Form 8-K filed May 12, 2008
 
 
 
D-5

 
         
TNMP
       
         
4.28
The First Mortgage Indenture dated as of March 23, 2009, between TNMP and The Bank of New York Mellon Trust Company, N.A., as Trustee
 
4.1 to TNMP’s Current Report on Form 8-K filed March 27, 2009
2-97230
TNMP
         
4.29
The First Supplemental Indenture dated as of March 23, 2009, between TNMP and The Bank of New York Mellon Trust Company, N.A., as Trustee
 
4.2 to TNMP’s Current Report on Form 8-K filed March 27, 2009
2-97230
TNMP
         
4.30
The Second Supplemental Indenture dated as of March 25, 2009, between TNMP and The Bank of New York Mellon Trust Company, N.A., as Trustee
 
4.3 to TNMP’s Current Report on Form 8-K filed March 27, 2009
2-97230
TNMP
         
4.31
The Third Supplemental Indenture dated as of April 30, 2009 between TNMP and The Bank of New York Mellon Trust Company, N.A., as Trustee
 
4.1 to TNMP’s current Report on Form 8-K filed May 6, 2009
2-97230
TNMP
         
4.32
Indenture, dated January 1, 1999 between TNMP and JPMorgan Chase Bank (successor to The Chase Bank of Texas, N. A.), as Trustee
 
4(w) to TNMP’s Annual Report on Form 10-K for the year ended December 31, 1998
2-97230
TNMP
         
4.33
First Supplemental Indenture, dated January 1, 1999, to Indenture, dated January 1, 1999, between TNMP and JPMorgan Chase Bank (successor to The Chase Bank of Texas, N. A.), as Trustee
 
4(x) to TNMP’s Annual Report on Form 10-K for the year ended December 31, 1998
2-97230
TNMP
         
4.34
Second Supplemental Indenture, dated June 1, 2003, to Indenture, dated January 1, 1999, between TNMP and JPMorgan Chase Bank (successor to The Chase Bank of Texas, N. A.), as Trustee
 
4 to TNMP’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2003
2-97230
TNMP
         
Material Contracts
       
         
10.1
Amended and Restated Credit Agreement, dated as of August 15, 2005, among PNM Resources, Inc. and First Choice Power, L.P., as borrowers, the lenders party thereto, Bank of America, N.A., as administrative agent and Wachovia Bank, National Association, as syndication agent.
 
10.1 to the Company’s Current Report on Form 8-K filed August 19, 2005 as Exhibit 10.1 (refiled with exhibits thereto as Exhibit 10.1 to Form 8-K/A filed January 5, 2010)
1-32462
PNMR
         
10.2
First Amendment to Credit Agreement dated as of November 3, 2006 among PNM Resources, First Choice Power, L.P. and TNMP, as borrowers, the lenders party thereto and Bank of America, N.A., as administrative agent
 
10.2 to the Company’s Annual Report on Form 10-K for the year ended December 31, 2006
1-32462
PNMR
 
 
D-6

 
         
10.3
Second Amendment to Credit Agreement dated as of December 20, 2006 among PNM Resources, First Choice Power, L.P. and TNMP, as borrowers, the lenders party thereto and Bank of America, N.A., as administrative agent
 
10.3 to the Company’s Quarterly Report on Form 10-Q for the quarter ended March 31, 2007
1-32462
PNMR
         
10.4
Third Amendment to Credit Agreement, dated as of March 11, 2009, among PNMR, First Choice Power, L.P., the lenders party thereto, and Bank of America, N.A., as administrative agent.
 
10.1 to PNMR’s Current Report on Form 8-K filed March 13, 2009
1-32462
PNMR
         
10.5
Consent Agreement, dated as of August 11, 2008, among PNMR, First Choice Power, L.P., the lenders party thereto and Bank of America, N.A., as administrative agent for the lenders named therein
 
10.1 to PNMR’s Current Report on 8-K filed August 13, 2008
1-32462 Form
         
10.6
Amended and Restated Guaranty Agreement, dated as of August 15, 2005, executed by PNM Resources, Inc., as Guarantor
 
10.1 to the Company’s Current Report on Form 8-K filed August 19, 2005
1-32462
PNMR
         
10.7
Joinder Agreement, dated as of September 30, 2005, between TNMP, as borrower and Bank of America, as administrative agent
 
10.3 to the Company’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2005
2-97230
TNMP
         
10.8
Term Loan Agreement, dated April 17, 2006, among PNM Resources, as borrower, the lenders identified therein and Lehman Commercial Paper, Inc., as administrative agent
 
10.4 to PNM Resource’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2006
1-32462
PNMR
         
10.9
Unit Purchase Agreement dated as of August 13, 2004 between PNM Resources and Cascade Investment, L.L.C.
 
99 to PNM Resources’ Current Report on Form 8-K filed August 19, 2004
333-32170
PNMR
         
10.10
First Supplement to Unit Purchase Agreement, dated as of June 4, 2005, between PNMR and Cascade
 
99.2 to the Company’s Current Report on Form 8-K filed June 10, 2005
1-32462
PNMR
         
10.11
Second Supplement to Unit Purchase Agreement, dated as of July 1, 2005, between PNMR and Cascade
 
99.1 to the Company’s Current Report on Form 8-K filed July 8, 2005
1-32462
PNMR
 
         
10.12
Third Supplement to Unit Purchase Agreement, dated as of August 12, 2005, between PNMR and Cascade and Fourth Supplement to Unit Purchase Agreement, dated as of September 30, 2005, between PNMR and Cascade
 
 
10.4 and 10.5 to the Company’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2005
1-32462
PNMR
 
 
D-7

 
         
10.13
Credit Agreement dated as of August 17, 2005, among PNM, the lenders party thereto, Wachovia Bank, National Association, as administrative agent and Union Bank of California, N.A., as syndication agent
 
10.3 to the Company’s Current Report on Form 8-K filed August 19, 2005 (refiled with exhibits thereto as Exhibit 10.3 to Form 8-K/A filed January 5, 2010)
1-6986
PNM
         
10.14
Consent Agreement, dated as of August 12, 2008, among PNM, the lenders party thereto, and Wachovia Bank, National Association, as Administrative Agent for the lenders named therein
 
10.2 to PNM’s Current Report on Form 8-K filed August 13, 2008
1-6986
PNM
         
10.15
Delayed Draw Term Loan Agreement, dated as of May 5, 2008, among PNM, as borrower, the lenders party thereto and Merrill Lynch Capital Corporation, as administrative agent (terminated January 30, 2009)
 
 
10.1 to PNM’s Current Report on Form 8-K filed May 7, 2008
1-6986
PNM
         
10.16
First Amendment to the Delayed Draw Term Loan Agreement, dated as of August 7, 2008, among PNM, the lenders party thereto and certain other parties
 
10.3 to PNM’s Current Report on Form 8-K filed August 13, 2008
1-6986
PNM
         
10.17
Reimbursement Agreement, dated as of May 8, 2008, among PNM, as borrower, the lenders party thereto, Deutsche Bank AG New York Branch, as administrative agent and RBC Capital Markets as syndication agent (terminated January 30, 2009)
 
 
10.1 to PNM’s Current Report on Form 8-K filed May 9, 2008
1-6986
PNM
         
10.18
First Amendment to the Reimbursement Agreement, dated as of August 7, 2008, among PNM, the lenders party thereto and Deutsche Bank AG New York Branch as Administrative Agent
 
10.4 to PNM’s Current Report on Form 8-K filed August 13, 2008
1-6986
PNM
         
10.19
Transitional Services Agreement among PNM, PNMR Services Company and New Mexico Gas Company, Inc. dated as of January 12, 2008
 
10.12 to PNM’s Annual Report on Form 10-K for the year ended December 31, 2007
1-6986
PNM
         
10.20
Credit Agreement, dated as of April 30, 2009, among TNMP, the lenders identified therein and JPMorgan Chase Bank, N.A.., as administrative agent
 
10.1 to TNMP’s Currentt Report on Form 8-K filed May 6, 2009
1-32462
PNMR
         
10.21
Term Loan Credit Agreement, dated as of March 25, 2009, among TNMP, the lenders identified therein and Union Bank, N.A., as administrative agent
 
10.1 to TNMP’s Current Report on Form 8-K filed March 27, 2009
1-32462
PNMR
 
 
D-8

 
         
10.22
Term Loan Agreement, dated as of March 7, 2008, among TNMP, as borrower, the lenders named therein, and JPMorgan Chase Bank, N.A., as administrative agent, as amended by Amendment No. 1 dated May 15, 2008 (terminated March 23, 2009)
 
10.1 to TNMP’s Quarterly Report on Form 10-Q for the quarter ended March 31, 2008 (and 10.1 to TNMP’s Current Report on Form 8-K filed October 16, 2008 for Amendment No. 1 thereto)
2-97230
TNMP
         
10.23
Credit Agreement, dated as of May 15, 2008, among TNMP, the lenders named therein, JPMorgan Chase Bank, N.A., as administrative agent, and Union Bank of California, N.A., as syndication agent, as amended by Amendment No. 1 dated October 31, 2008 and Amendment No. 2 dated March 10, 2009 (terminated April 30, 2009)
 
4.4 to TNMP’s Current Report on Form 8-K filed May 21, 2008 (and 10.2 to Form 8-K filed November 4, 2008 for Amendment No. 1 thereto and 10.2 to Form 8-K filed March 13, 2009 for Amendment No. 2 thereto)
2-97230
TNMP
         
10.24
 Credit Agreement, dated as of October 31, 2008, among TNMP, as borrower, Union Bank of California, N.A., as administrative agent and as a lender, and JPMorgan, as a lender (terminated March 23, 2009)
 
10.1 to TNMP’s Current report on Form 8-K filed November 3, 2008
2-97230
TNMP
         
10.25**
PNM Resources, Inc. Second Amended and Restated Omnibus Performance Equity Plan dated May 19, 2009 (“PEP”)
 
4.1 to PNM Resources’ Form S-8 Registration Statement filed May 20, 2009
333-159361
PNMR
         
10.26**
Form of Stock Option Award Agreement for non-qualified stock options granted under PEP in 2010 and later
 
10.3 to PNMR’s Current Report on form 8-K filed May 26, 2009
1-32462
PNMR
         
10.27**
Form of Performance Restricted Stock Rights Award Agreement for performance-based, time-vested restricted stock rights awards based on adjusted cash earnings granted under PEP in 2009
 
10.4 to PNMR’s Current Report on form 8-K filed May 26, 2009
1-32462
PNMR
         
10.28**
Form of Performance Cash Award Agreement for performance cash awards based on adjusted cash earnings granted under PEP in 2009
 
10.5 to PNMR’s Current Report on form 8-K filed May 26, 2009
1-32462
PNMR
         
10.29**
Form of Performance Share Award Agreement for performance share awards based on special purpose performance criteria granted under the PEP in 2009
 
10.6 to PNMR’s Current Report on form 8-K filed May 26, 2009
1-32462
PNMR
         
10.30**
Form of Performance Cash Award Agreement for performance cash awards based on special purpose performance criteria granted under the PEP in 2009
 
10.7 to PNMR’s Current Report on form 8-K filed May 26, 2009
1-32462
PNMR
         
10.31**
Form of Restricted Stock Rights Award Agreement for time-vested stock rights awards granted under PEP in May 2009
 
10.8 to PNMR’s Current Report on form 8-K filed May 26, 2009
1-32462
PNMR
 
 
D-9

 
         
10.32**
Form of the award agreement for non-qualified stock options granted under the PEP in 2007-2009
 
10.2 to the Company's Current Report on Form 8-K filed February 16, 2007
1-32462
PNMR
         
10.33**
Form of award agreement for restricted stock rights granted under the PEP in 2007, 2008 and February 2009
 
10.3 to the Company’s Current Report on Form 8-K filed February 16, 2007
 
1-32462
PNMR
         
10.34**
Form of award agreement for performance shares granted for the 2004-2006 performance period under the PEP and a description of the Long-Term Performance Share Program Amended Effective January 1, 2004
 
 10.4 to PNM Resources' Current Report on Form 8-K filed February 16, 2007
1-32462
PNMR
         
10.35**
Long-Term Performance Cash Program description effective January 1, 2004
 
10.5 to PNM Resources' Current Report on Form 8-K filed February 16, 2007
333-125010
PNMR
         
10.36**
First Amendment to Long-Term Performance Loan Plan Program executed December 8, 2008
 
10.2 to PNMR’s Annual Report on Form 10-K for fiscal year ended December 31, 2008
1-32462
PNMR
         
10.37**
Changes in Director Compensation
 
10.1 to the Company’s Annual Report on Form 10-K for the fiscal year ended December 31, 2009
1-32462
PNMR
         
10.38**
PNM Resources, Inc. Executive Savings Plan dated December 29, 2003
 
10.75 to PNM Resources and PNM’s Annual Report on Form 10-K for the fiscal year ended December 31, 2003
333-32170
PNMR
         
10.39**
First Amendment to PNMR’s Executive Savings Plan executed December 17, 2008
 
10.6 to PNMR’s Annual Report on Form 10-K for he fiscal year ended December 31, 2008
1-32462
PNMR
         
10.40**
PNM Resources, Inc. Executive Savings Plan II (amended and restated effective January 1, 2009)
 
4.1 to PNMR’s Registration Statement on Form S-8 (333-156243) filed December 17, 2008
333-156243
PNMR
         
10.41**
PNM Resources, Inc. After-Tax Retirement Plan effective January 1, 2009
 
10.5 to PNMR’s Annual Report on Form 10-K for he fiscal year ended December 31, 2008
1-32462
PNMR
         
10.42**
2009 Officer Incentive Plan
 
 
10.2 to PNM Resources' Current Report on Form 8-K filed May 26, 2009
1-32462
PNMR
         
10.43**
2008 Officer Incentive Plan (as amended December 16, 2008)
 
10.1 to the Company’s Annual Report on Form 10-K for the fiscal year ended December 31, 2008
1-32462
PNMR
         
10.44**
Performance Cash Program for the Utilities President (Patricia K. Collawn)
 
10.2 to the Company’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2008
1-32462
PNMR
         
10.45**
Summary of Executive Time Off Policy Effective January 1, 2006
 
10.31 to the Company’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2005
1-32462
PNMR
         
10.46**
Restated and Amended Public Service Company of New Mexico Accelerated Management Performance Plan (1988) (August 16, 1988) (refiled)
 
10.23 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1998
1-6986
PNM
 
 
D-10

 
         
10.47**
First Amendment to Restated and Amended Public Service Company of New Mexico Accelerated Management Performance Plan (1988) (August 30, 1988) (refiled)
 
10.23.1 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1998
1-6986
PNM
         
10.48**
Second Amendment to Restated and Amended Public Service Company of New Mexico Accelerated Management Performance Plan (1988) (December 29, 1989) (refiled)
 
10.23.2 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1998
1-6986
PNM
         
10.49**
Second  [Third] Amendment to the Restated and Amended Public Service Company of New Mexico Accelerated Management Performance Plan (1988) dated December 8, 1992
 
10.22.1 to PNM's Annual Report on Form 10-K for fiscal year ended December 31, 2004.
1-6986
PNM
         
10.50**
Fourth Amendment to the Restated and Amended Public Service Company of New Mexico Accelerated Management Performance Plan, as amended effective December 7, 1998
 
10.23.4 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1999
1-6986
PNM
         
10.51**
Fifth Amendment dated November 27, 2002 to the Restated and Amended PNM Resources, Inc. Accelerated Performance Management Plan
 
10.23.5 to the Company’s Annual Report on Form 10-K for the fiscal year ended December 31, 2002
333-32170
PNMR
         
10.52**
Sixth Amendment dated December 9, 2003 to the PNM Resources, Inc. Restated and Amended Accelerated Performance Management Plan
 
10.23.6 to the Company’s Annual Report on Form 10-K for the fiscal year ended December 31, 2003
333-32170
PNMR
         
10.53**
Seventh Amendment dated November 21, 2008 to the PNM Resources, Inc. Accelerated Management Performance Plan
 
10.4 to PNMR’s Annual Report on Form 10-K for the fiscal year ended December 31, 2008
1-32462
PNMR
         
10.54**
PNM Resources, Inc. Non-Union Severance Pay Plan effective August 1, 2007 (amended and restated)
 
10.3 to the Company's Quarterly Report on Form 10-Q for the quarter ended September 30, 2007
1-32462
PNMR
 
         
10.55**
First Amendment to the PNM Resources Non-Union Severance Pay Plan executed November 20, 2008
 
10.3 to PNMR’s Annual Report on Form 10-K for the fiscal year ended December 31, 2008
1-32462
PNMR
         
10.56**
PNM Service Bonus Plan dated October 23, 1984
 
19.4 to PNM’s Quarterly Report on Form 10-Q or the quarter ended September 30, 1988
1-6986
PNM
         
10.57**
First Amendment dated November 20, 1985 to PNM Service Bonus Plan
 
10.11.1 to PNM’s Annual Report on Form 10-K for the fiscal year ending December 31, 1985
1-6986
PNM
         
10.58**
Second Amendment dated December 29, 1989 to PNM Service Bonus Plan
 
10.27.2 to PNM’s Annual Report on Form 10-K for the fiscal year ending December 31, 1989
1-6986
PNM
 
 
D-11

 
         
10.59**
Second  [Third] Amendment dated December 7, 1998 to PNM Service Bonus Plan
 
10.45 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1999
1-6986
PNM
         
10.60**
Fourth Amendment dated November 27, 2002 to PNM Resources, Inc. Service Bonus Plan
 
10.45.4 to the Company’s Annual Report on Form 10-K for the fiscal year ended December 31, 2002
333-32170
PNMR
         
10.61**
Fifth Amendment dated December 9, 2003 to PNM Resources, Inc. Service Bonus Plan
 
10.45.5 to the Company’s Annual Report on Form 10-K for the fiscal year ended December 31, 2003
333-32170
PNMR
         
10.62**
Public Service Company of New Mexico OBRA ‘93 Retirement Plan
effective November 15, 1993
 
10.4 to PNM’s Quarterly Report on Form 10-Q for the quarter ended September 30, 1993
1-6986
PNM
         
10.63**
First Amendment to the Public Service Company of New Mexico OBRA ’93 Retirement Plan, as amended effective December 7, 1998
 
10.48.1 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1999
1-6986
PNM
         
10.64**
Second Amendment dated November 27, 2002 to the PNM Resources, Inc. OBRA ’93 Retirement Plan
 
10.48.2 to the Company’s Annual Report on Form 10-K for the year ended December 31, 2002
333-32170
PNMR
         
10.65**
Third Amendment dated December 9, 2003 to the PNM Resources, Inc. OBRA ’93 Retirement Plan
 
10.48.3 to the Company’s Annual Report on Form 10-K for the year ended December 31, 2003
333-32170
PNMR
         
10.66**
Public Service Company of New Mexico Section 415 Plan dated January 1, 1994
 
10.50 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1993
1-6986
PNM
         
10.67**
First Amendment dated December 7, 1998 and Second Amendment dated August 7, 1999 to PNM Section 415 Plan and Third Amendment dated November 27, 2002 to the PNM Resources, Inc. Section 415 Plan
 
10.50.1 to the Company’s Annual Report in Form 10-K for the fiscal year ended December 31, 2002
333-32170
PNMR
         
10.68**
Fourth Amendment dated December 9, 2003 to the PNM Resources, Inc. Section 415 Plan
 
10.50.2 to the Company’s Annual Report in Form 10-K for the fiscal year ended December 31, 2003
333-32170
PNMR
         
10.69**
PNM Resources, Inc. Officer Retention Plan executed September 2, 2008 (amended and restated effective January 1, 2009)
 
10.1 to the Company’s Quarterly Report in Form 10-Q for the quarter ended September 30, 2008
1-32462
PNMR
 
         
10.70**
First Amendment to PNM Resources, Inc. Officer Retention Plan executed November 20, 2008
 
10.8 to the Company’s Annual Report in Form 10-K for the fiscal year ended December 31, 2008
1-32462
PNMR
         
10.71**
PNM Resources Executive Spending Account Plan dated December 9, 2003
 
10.52 to the Company’s Annual Report on Form 10-K for fiscal year ended December 31, 2003
333-32170
PNMR
         
10.72**
First Amendment to PNM Resources Executive Spending Account Plan effective January 1, 2004
 
10.52.1 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 2004
333-32170
PNMR
 
 
D-12

 
         
10.73**
Second Amendment to PNMR’s Executive Spending Account Plan executed August 28, 2008
 
10.2 to PNMR’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2008
 
         
10.74**
Third Amendment to PNMR’s Executive Spending Account Plan effective January 1, 2009
 
10.7 to PNMR’s Annual Report on Form 10-K for the year ended December 31, 2008
1-32462
PNMR
         
10.75**
Third Restated and Amended Public Service Company of New Mexico Performance Stock Plan effective March 10, 1998
 
10.74 to PNM's Quarterly Report on Form 10-Q for the quarter ended March 31, 1998
1-6986
PNM
         
10.76**
First Amendment to the Third Restated and Amended Public Service Company of New Mexico Performance Stock Plan Dated February 7, 2000
 
10.74.1 to PNM's Quarterly Report on Form 10-Q for the quarter ended March 31, 2000
1-6986
PNM
         
10.77**
Second Amendment to the Third Restated and Amended Public Service Company of New Mexico Performance Stock Plan, effective December 7, 1998
 
10.74.2 to PNM's Annual Report on Form 10-K for the fiscal year ended December 31, 2000
1-6986
PNM
         
10.78**
Third Amendment to the Third Restated and Amended Public Service Company of New Mexico Performance Stock Plan, effective December 10, 2000
 
10.74.3 to PNM’s Annual Report on Form 10-K for the fiscal year ended December 31, 2000
1-6986
PNM
         
10.79**
Fourth Amendment to Third Restated and Amended Public Service Company of New Mexico Performance Stock Plan dated December 31, 2001
 
4.3.5 to PNM Resources’ Post-Effective Amendment No. 1 to Form S-8 Registration Statement filed December 31, 2001
333-03303
PNMR
         
10.80**
Fifth Amendment to the Third Restated and Amended PNM Resources, Inc. Performance Stock Plan dated September 6, 2002
 
10.74.5 to the Company’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2002
333-32170
PNMR
         
10.81**
PNM Resources, Inc.
Director Retainer Plan,
dated December 31, 2001
 
4.3 to PNM Resources, Inc.
Post-Effective Amendment No. 1 to Form S-8 Registration Statement filed December 31, 2001
333-03289
PNMR
         
10.82**
First Amendment dated
February 17, 2003 to
PNM Resources, Inc. Director Retainer Plan
 
10.40.1 to the Company’s Quarterly Report on Form 10-Q for the quarter ended March 31, 2003
333-32170
PNMR
         
10.83**
Supplemental Employee Retirement Agreement for Patrick T. Ortiz (amended and restated effective January 1, 2009)
 
10.3 to the Company’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2008
1-32462
PNMR
         
10.84**
Retainer Agreement between the Company and Patrick T. Ortiz dated July 28, 2009 (assigned on December 10, 2009, for billing and collection purposes only, to Cuddy & McCarthy, LLP)
 
10.1 to PNMR’s Current Report on Form 8-K filed July 30, 2009
1-32462
PNMR
 
 
D-13

 
 
         
10.85**
Executive Transition Agreement between the Company and Patrick T. Ortiz dated July 28, 2009
 
10.2 to PNMR’s Current Report on Form 8-K filed July 30, 2009
1-32462
PNMR
         
10.86**
Supplemental Employee Retirement Agreement for Jeffry E. Sterba (amended and restated effective January 1, 2009)
 
10.9 to the Company’s Annual Report on Form 10-K for the fiscal year ended December 31, 2008
1-32462
PNMR
         
10.87**
Amended and Restated Retention Bonus Agreement for Jeffry E. Sterba executed September 7, 2007
 
10.4 to the Company’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2007
1-32462
PNMR
         
10.88**
First Amendment to the Retention Bonus Agreement between PNMR and Jeffrey E. Sterba effective January 1, 2009
 
10.11 to the Company’s Annual Report on Form 10-K for the fiscal year ended December 31, 2008
1-32462
PNMR
         
10.89**
PNM Resources Officer Life Insurance Plan dated April 28, 2004
 
10.24.1 to the Company’s Quarterly Report on Form 10-Q for the quarter ended March 31, 2004
333-32170
PNMR
         
10.90**
First Amendment to PNM Resources Officer Life Insurance Plan dated December 16, 2004
 
10.27 to the Company’s Annual Report on Form 10-K for the fiscal year ended December 31, 2004.
333-32170
PNMR
         
10.91**
Second Amendment to PNM Resources Officer Life Insurance Plan executed April 15, 2007
 
10.5 to the Company’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2007
1-32462
PNMR
         
10.92**
Third Amendment to the PNMR Officer Life Insurance Plan effective January 1, 2009
 
10.10 to PNMR’s Annual Report on Form 10-K for the fiscal year ended December 31, 2008
1-32462
PNMR
         
10.93**
Fourth Amendment to the PNMR Officer Life Insurance Plan effective January 1, 2009
 
10.15 to PNMR’s Annual Report on Form 10-K for the fiscal year ended December 31, 2008
1-32462
PNMR
         
10.94**
Long Term Care Insurance Plan effective January 1, 2003
 
10.87 to the Company’s Annual Report on Form 10-K for the year ended December 31, 2002
333-32170
PNMR
         
10.95**
Executive Long Term Disability effective January 1, 2003
 
10.88 to the Company’s Annual Report on Form 10-K for the year ended December 31, 2002
333-32170
PNMR
         
10.96
Supplemental Indenture of Lease dated as of July 19, 1966 between PNM and other participants in the Four Corners Project and the Navajo Indian Tribal Council
 
4-D to PNM’s Registration Statement No. 2-26116
2-26116
PNM
 
 
D-14

 
 
         
10.97
Amendment and Supplement No. 1 to Supplemental and Additional Indenture of Lease dated April 25, 1985 between the Navajo Tribe of Indians and Arizona Public Service Company, El Paso Electric Company, Public Service Company of New Mexico, Salt River Project Agricultural Improvement and Power District, Southern California Edison Company, and Tucson Electric Power Company (refiled)
 
10.1.1 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1995
1-6986
PNM
         
10.98
Water Supply Agreement between the Jicarilla Apache Tribe and Public Service Company of New Mexico, dated July 20, 2000
 
10.5 to PNM’s Quarterly Report of Form 10-Q for the quarter ended September 30, 2001
1-6986
PNM
         
10.99
Arizona Nuclear Power Project Participation Agreement among PNM and Arizona Public Service Company, Salt River Project Agricultural Improvement and Power District, Tucson Gas & Electric Company and El Paso Electric Company, dated August 23, 1973
 
5-T to PNM’s Registration Statement No. 2-50338
2-50338
PNM
         
10.100
Amendments No. 1 through No. 6 to Arizona Nuclear Power Project Participation Agreement
 
10.8.1 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1991
1-6986
PNM
         
10.101
Amendment No. 7 effective April 1, 1982, to the Arizona Nuclear Power Project Participation Agreement (refiled)
 
10.8.2 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1991
1-6986
PNM
         
10.102
Amendment No. 8 effective September 12, 1983, to the Arizona Nuclear Power Project Participation Agreement (refiled)
 
10.58 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1993
1-6986
PNM
         
10.103
Amendment No. 9 to Arizona Nuclear Power Project Participation Agreement dated as of June 12, 1984 (refiled)
 
10.8.4 to PNM’s Annual Report of the Registrant on Form 10-K for fiscal year ended December 31, 1994
1-6986
PNM
         
10.104
Amendment No. 10 dated as of November 21, 1985 and Amendment No. 11 dated as of June 13, 1986 and effective January 10, 1987 to Arizona Nuclear Power Project Participation Agreement (refiled)
 
10.8.5 to PNM’s Annual Report of the Registrant on Form 10-K for fiscal year ended December 31, 1994
1-6986
PNM
         
10.105
Amendment No. 12 to Arizona Nuclear Power Project Participation Agreement dated June 14, 1988, and effective August 5, 1988
 
19.1 to PNM's Quarterly Report on Form 10-Q for the quarter ended September 30, 1990
1-6986
PNM
         
10.106
Amendment No. 13 to the Arizona Nuclear Power Project Participation Agreement dated April 4, 1990, and effective June 15, 1991
 
10.8.10 to PNM’s Annual Report on Form 10-K for the fiscal year ended December 31, 1990
1-6986
PNM
 
 
D-15

 
 
10.107
Amendment No. 14 to the Arizona Nuclear Power Project Participation Agreement effective June 20, 2000
 
10.8.9 to PNM’s Annual Report on Form 10-K for the fiscal year ended December 31, 2000
1-6986
PNM
         
10.108
Underground Coal Sales Agreement, dated August 31, 2001 among San Juan Coal Company, PNM and Tucson Electric Power Company
 
10.85 to PNM’s Quarterly Report on Form 10-Q for the quarter ending September 31, 2001  (Confidential treatment was requested for portions of this exhibit, and such portions were omitted from this exhibit filed and were filed separately with the Securities and Exchange Commission)
1-6986
PNM
         
10.109
Amendment One to Underground Coal Sales Agreement dated December 15, 2003 among San Juan Coal Company, PNM and Tucson Electric Coal Company
 
10.9.1 to PNM’s Amended Report on Form 10-K for fiscal year ended December 31, 2003 (Confidential treatment was requested for portions of this exhibit, and such portions were omitted from this exhibit filed and were filed separately with the Securities and Exchange Commission)
1-6986
PNM
         
10.110
Amendment Two to Underground Coal Sales Agreement effective September 15, 2004 among San Juan Coal Company, PNM and Tucson Electric Coal Company
 
10.9.2 to PNM’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2004
1-6986
PNM
         
10.111
Amendment Three to Underground Coal Sales Agreement executed April 29, 2005 among San Juan Coal Company, PNM and Tucson Electric Coal Company (Confidential treatment was requested for portions of this exhibit, and such portions were omitted from this exhibit filed and were filed separately with the Securities and Exchange Commission)
 
10.86.1 to the Company’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2005
1-6986
PNM
         
10.112
Amendment Four to Underground Coal Sales Agreement effective March 7, 2007 among San Juan Coal Company, PNM and Tucson Electric Coal Company
 
10.89 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 2007
1-6986
PNM
         
10.113
Amendment Five to Underground Coal Sales Agreement executed December 21, 2007 among San Juan Coal Company, PNM and Tucson Electric Power Company (Confidential treatment was requested for portions of this exhibit, and such portions were omitted from this exhibit filed and were filed separately with the Securities and Exchange Commission)
 
10.95 to PNM’s Annual Report on Form 10-K for the year ended December 31, 2007
1-6986
PNM
 
 
D-16

 
         
10.114
San Juan Unit 4 Early Purchase and Participation Agreement dated as of September 26, 1983 between PNM and M-S-R Public Power Agency, and Modification No. 2 to the San Juan Project Agreements dated December 31, 1983 (refilled)
 
10.11 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1994
1-6986
PNM
         
10.115
Amendment No. 1 to the Early Purchase and Participation Agreement between Public Service Company of New Mexico and M-S-R Public Power Agency, executed as of December 16, 1987, for San Juan Unit 4 (refiled)
 
10.11.1 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1997
1-6986
PNM
         
10.116
Amendment No. 3 to the San Juan Unit 4 Early Purchase and Participation Agreement between Public Service Company of New Mexico and M-S-R Public Power Agency, dated as of October 27, 1999
 
10.11.3 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1999
1-6986
PNM
         
10.117
Amended and Restated San Juan Unit 4 Purchase and Participation Agreement dated as of December 28, 1984 between PNM and the Incorporated County of Los Alamos (refiled)
 
10.12 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1994
1-6986
PNM
         
10.118
Amendment No. 1 to the Amended and Restated San Juan Unit 4 Purchase and Participation Agreement between Public Service Company of New Mexico and M-S-R Public Power Agency, dated as of October 27, 1999
 
10.12.1 to PNM’s Annual Report Form 10-K for fiscal year ended December 31, 1999
1-6986
PNM
         
10.119
Amendment No. 2 to the San Juan Unit 4 Purchase Agreement and Participation Agreement between Public Service Company of New Mexico and The Incorporated County of Los Alamos, New Mexico, dated October 27, 1999
 
10.13 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1999
1-6986
PNM
         
10.120
Participation Agreement among PNM, Tucson Electric Power Company and certain financial institutions relating to the San Juan Coal Trust dated as of December 31, 1981 (refiled)
 
10.14 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1992
1-6986
PNM
         
10.121
San Juan Unit 4 Purchase and Participation Agreement Public Service Company of New Mexico and the City of Anaheim, California dated April 26, 1991
 
19.2 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1991
1-6986
PNM
         
10.122
Amendment No. 1 to the San Juan Unit 4 Purchase and Participation Agreement between Public Service Company of New Mexico and The City of Anaheim, California, dated October 27, 1999
 
10.36.1 to Annual Report PNM’s on Form 10-K for fiscal year ended December 31, 1999
1-6986
PNM
 
 
D-17

 
         
10.123
Restated and Amended San Juan Unit 4 Purchase and Participation Agreement between Public Service Company of New Mexico and Utah Associated Municipal Power Systems
 
10.2.1 to PNM’s Quarterly Report on Form 10-Q for the quarter ended September 30, 1993
1-6986
PNM
         
10.124
Amendment No. 1 to the Restated and Amended San Juan Unit 4 Purchase And Participation Agreement between Public Service Company of New Mexico And Utah Associated Municipal Power Systems, dated October 27, 1999
 
10.38.1 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1999
1-6986
PNM
         
10.125
Participation Agreement dated as of June 30, 1983 among Security Trust Company, as Trustee, PNM, Tucson Electric Power Company and certain financial institutions relating to the San Juan Coal Trust (refiled)
 
10.61 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1993
1-6986
PNM
         
10.126
Amended and Restated San Juan Project Participation Agreement dated as of March 3, 2006, among Public Service Company of New Mexico, Tucson Electric Power Company, The City of Farmington, New Mexico, M-S-R Public Power Agency, The Incorporated County of Los Alamos, New Mexico, Southern California Public Power Authority, City of Anaheim, Utah Associated Municipal Power System and Tri-State Generation and Transmission Association, Inc.
 
10.119 to PNM's Quarterly Report on Form 10-Q for the quarter ended March 30, 2006
1-6986
PNM
         
10.127*
Facility Lease dated as of December 16, 1985 between The First National Bank of Boston, as Owner Trustee, and Public Service Company of New Mexico together with Amendments No. 1, 2 and 3 thereto (refiled)
 
10.18 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1995
1-6986
PNM
         
10.128*
Amendment No. 4 dated as of March 8, 1995, to Facility Lease between Public Service Company of New Mexico and the First National Bank of Boston, dated as of December 16, 1985
 
10.18.5 to the PNM's Quarter Report on Form10-Q for the quarter ended March 31, 1995
1-6986
PNM
         
10.129
Facility Lease dated as of July 31, 1986, between the First National Bank of Boston, as Owner Trustee, and Public Service Company of New Mexico together with Amendments No. 1, 2 and 3 thereto (refiled)
 
10.19 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
         
10.130
Facility Lease dated as of August 12, 1986, between The First National Bank of Boston, as Owner Trustee, and Public Service Company of New Mexico together with Amendments No. 1 and 2 thereto (refiled)
 
10.20 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
 
 
D-18

 
         
10.131
Amendment No. 2 dated as of April 10, 1987 to Facility Lease dated as of August 12, 1986, as amended, between The First National Bank of Boston, not in its individual capacity, but solely as Owner Trustee under a Trust Agreement, dated as of August 12, 1986, with MFS Leasing Corp., Lessor and Public Service Company of New Mexico, Lessee (refiled)
 
10.20.2 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1998
1-6986
PNM
         
10.132
Amendment No. 3 dated as of March 8, 1995, to Facility Lease between Public Service Company of New Mexico and the First National Bank of Boston, dated as of August 12, 1986
 
10.20.4 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1995
1-6986
PNM
         
10.133
Facility Lease dated as of December 15, 1986, between The First National Bank of Boston, as Owner Trustee, and Public Service Company of New Mexico (Unit 1 Transaction) together with Amendment No. 1 thereto (refiled)
 
10.21 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
         
10.134
Facility Lease dated as of December 15, 1986, between The First National Bank of Boston, as Owner Trustee, and Public Service Company of New Mexico Unit 2 Transaction) together with Amendment No. 1 thereto (refiled)
 
10.22 to PNM’s Annual Report of the Registrant on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
         
10.135
Amendment No. 2 dated as of April 10, 1987 to the Facility Lease dated as of August 12, 1986 between The First National bank of Boston, as Owner Trustee, and PNM. (Unit 2 transaction.) (This is an amendment to a Facility Lease which is substantially similar to the Facility Lease filed as Exhibit 28.1 to the Company’s Current Report on Form 8-K dated August 18, 1986)
 
10.53 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1987
1-6986
PNM
 
10.136
Master Decommissioning Trust Agreement for Palo Verde Nuclear Generating Station dated March 15, 1996, between Public Service Company of New Mexico and Mellon Bank, N.A.
 
10.68 to PNM's Quarterly Report on Form 10-Q for the quarter ended March 31, 1996
1-6986
PNM
         
10.137
Amendment Number One to the Master Decommissioning Trust Agreement for Palo Verde Nuclear Generating Station dated January 27, 1997, between Public Service Company of New Mexico and Mellon Bank, N.A.
 
10.68.1 to PNM's Annual Report on Form 10-K for fiscal year ended December 31, 1997
1-6986
PNM
         
10.138
Amendment Number Two to the Master Decommissioning Trust Agreement for Palo Verde Nuclear Generating Station between Public Service Company of New Mexico and Mellon Bank, N.A.
 
10.68.2 to PNM's Annual Report on Form 10-K for fiscal year ended December 31, 2003
1-6986
PNM
 
 
D-19

 
 
         
10.139
Refunding Agreement No. 8A, dated as of December 23, 1997, among PNM, the Owner Participant Named Therein, State Street Bank and Trust Company, as Owner Trustee, The Chase Manhattan Bank, as Indenture Trustee, and First PV Funding Corporation
 
10.73 to PNM's Quarterly Report on Form 10-Q for the quarter ended March 31, 1998
1-6986
PNM
       
10.140
PVNGS Capital Trust—Variable Rate Trust Notes—PVNGS Note Agreement dated as of July 31, 1998
 
10.76 to PNM's Quarterly Report on Form 10-Q for the quarter ended September 30, 1998
1-6986
PNM
         
10.141
New Mexico Public Service Commission Order dated July 30, 1987, and Exhibit I thereto, in NMPUC Case No. 2004, regarding the PVNGS decommissioning trust fund (refiled)
 
10.67 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1997
1-6986
PNM
         
10.142
Stipulation in the matter of PNM’s transition plan Utility Case No. 3137, dated October 10, 2002 as amended by Amendment to Stipulated Agreement dated October 18, 2002
 
10.86 to the Company’s Annual Report on Form 10-K for the year ended December 31, 2002
1-6986
PNM
         
10.143
Settlement Agreement between Public Service Company of New Mexico and Creditors of Meadows Resources, Inc. dated November 2, 1989 (refiled)
 
10.34 to PNM’s Quarterly Report on Form 10-Q for quarter ended June 30, 2000
1-6986
PNM
         
10.144
First Amendment dated April 24, 1992 to the Settlement Agreement dated November 2, 1989 among Public Service Company of New Mexico, the lender parties thereto and collateral agent (refiled)
 
10.34.1 to PNM’s Quarterly Report on Form 10-Q for quarter ended June 30, 2000
1-6986
PNM
         
10.145
Amendment dated April 11, 1991 among Public Service Company of New Mexico, certain banks and Chemical Bank and Citibank, N.A., as agents for the banks
 
19.1 to PNM’s Quarterly Report on Form 10-Q for the quarter ended September 30, 1991
1-6986
PNM
         
10.146
Stipulation dated February 28, 2005 in NMPRC Case No. 04-00315-UT regarding the application of PNM Resources and TNMP for approval of the TNP acquisition
 
10.134 to the Company’s Quarterly Report on Form 10-Q for the quarter ended March 31, 2005
1-32462
PNMR/
TNMP
         
10.147
Settlement Agreement dated February 3, 2005, between PNM Resources, Inc. and Texas-New Mexico Power Company, the cities of Dickenson, Lewisville, La Marque, Ft. Stockton and Friendswood, Texas, the Legal and Enforcement Division of the Public Utility Commission of Texas, the Office of Public Utility Counsel, the Texas Industrial Energy Consumers and the Alliance for Retail Markets
 
10.1-10.1.7 to the Company’s Current Report on Form 8-K filed February 7, 2005
1-32462
PNMR/
TNMP
 
 
D-20

 
 
         
10.148
Consent Decree entered into by PNM on March 9, 2005 relating to the citizen suit under the Clean Air Act and the excess emissions report matter for SJGS
 
10.135 to the Company’s Quarterly Report on Form 10-Q for the quarter ended March 31, 2005
1-6986
PNM
         
10.149
Stipulation in the matter of PNM’s application for approval of a certificate of public convenience and necessity for the Afton Generating Station, Case No. 05-00275-UT, dated November 30, 2005
 
10.132 to the Company’s Annual report on Form 10-K for the year ended December 31, 2005
1-6986
PNM
 
 
         
21
Certain subsidiaries of PNM Resources
 
21 to the Company’s Annual Report on Form 10-K for the year ended December 31, 2008
1-32462
PNMR
         
99.2*
Participation Agreement dated as of December 16, 1985, among the Owner Participant named therein, First PV Funding Corporation. The First National Bank of Boston, in its individual capacity and as Owner Trustee (under a Trust Agreement dated as of December 16, 1985 with the Owner Participant), Chemical Bank, in its individual capacity and as Indenture Trustee (under a Trust Indenture, Mortgage, Security Agreement and Assignment of Rents dated as of December 16, 1985 with the Owner Trustee), and Public Service Company of New Mexico, including Appendix A definitions together with Amendment No. 1 dated July 15, 1986 and Amendment No. 2 dated November 18, 1986 (refiled)
 
99.2 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1995
1-6986
PNM
         
99.3
Trust Indenture, Mortgage, Security Agreement and Assignment of Rents dated as of December 16, 1985, between the First National Bank of Boston, as Owner Trustee, and Chemical Bank, as Indenture Trustee together with Supplemental Indentures Nos. 1 and 2 (refiled)
 
99.3 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1996
1-6986
PNM
 
99.3.3
Supplemental Indenture No. 3 dated as of March 8, 1995, to Trust Indenture Mortgage, Security Agreement and Assignment of Rents between The First National Bank of Boston and Chemical Bank dated as of December 16, 1985
 
99.3.3 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1995
1-6986
PNM
         
99.4*
Assignment, Assumption and Further Agreement dated as of December 16, 1985, between Public Service Company of New Mexico and The First National Bank of Boston, as Owner Trustee (refiled)
 
99.4 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1995
1-6986
PNM
 
 
D-21

 
 
         
99.5
Participation Agreement dated as of July 31, 1986, among the Owner Participant named herein, First PV Funding Corporation, The First National Bank of Boston, in its individual capacity and as Owner Trustee (under a Trust Agreement dated as of July 31, 1986, with the Owner Participant), Chemical Bank, in its individual capacity and as Indenture Trustee (under a Trust Indenture, Mortgage, Security Agreement and Assignment of Rents dated as of July 31, 1986, with the Owner Trustee), and Public Service Company of New Mexico, including Appendix A definitions together with Amendment No. 1 thereto (refiled)
 
99.5 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
         
99.6
Trust Indenture, Mortgage, Security Agreement and Assignment of Rents dated as of July 31, 1986, between The First National Bank of Boston, as Owner Trustee, and Chemical Bank, as Indenture Trustee together with Supplemental Indenture No. 1 thereto (refiled)
 
99.6 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
         
99.7
Assignment, Assumption, and Further Agreement dated as of July 31, 1986, between Public Service Company of New Mexico and The First National Bank of Boston, as Owner Trustee (refiled)
 
99.7 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
         
99.8
Participation Agreement dated as of August 12, 1986, among the Owner Participant named therein, First PV Funding Corporation. The First National Bank of Boston, in its individual capacity and as Owner Trustee (under a Trust Agreement dated as of August 12, 1986, with the Owner Participant), Chemical Bank, in its individual capacity and as Indenture Trustee (under a Trust Indenture, Mortgage, Security Agreement and Assignment of Rents dated as of August 12, 1986, with the Owner Trustee), and Public Service Company of New Mexico, including Appendix A definitions (refiled)
 
99.8 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1997
1-6986
PNM
         
99.8.1*
Amendment No. 1 dated as of November 18, 1986, to Participation Agreement dated as of August 12, 1986 (refiled)
 
99.8.1 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1997
1-6986
PNM
 
 
 
D-22

 
         
99.9*
Trust Indenture, Mortgage, Security Agreement and Assignment of Rents dated as of August 12, 1986, between the First National Bank of Boston, as Owner Trustee, and Chemical Bank, as Indenture Trustee together with Supplemental Indenture No. 1 thereto (refiled)
 
99.9 to PNM’s Annual Report of the Registrant on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
         
99.9.2
Supplemental Indenture No. 2 dated as of March 8, 1995, to Trust Indenture, Mortgage, Security Agreement and Assignment of Rents between The First National Bank of Boston and Chemical Bank dated as of August 12, 1986
 
99.9.1 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1995
1-6986
PNM
         
99.10*
Assignment, Assumption, and Further Agreement dated as of August 12, 1986, between Public Service Company of New Mexico and The First National Bank of Boston, as Owner Trustee (refiled)
 
99.10 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1997
1-6986
PNM
         
99.11*
Participation Agreement dated as of December 15, 1986, among the Owner Participant named therein, First PV Funding Corporation, The First National Bank of Boston, in its individual capacity and as Owner Trustee (under a Trust Agreement dated as of December 15, 1986, with the Owner Participant), Chemical Bank, in its individual capacity and as Indenture Trustee (under a Trust Indenture, Mortgage, Security Agreement and Assignment of Rents dated as of December 15, 1986, with the Owner Trustee), and Public Service Company of New Mexico, including Appendix A definitions (Unit 1 Transaction) (refiled)
 
99.1 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1997
1-6986
PNM
         
99.12
Trust Indenture, Mortgage, Security Agreement and Assignment of Rents dated as of December 15, 1986, between The First National Bank of Boston, as Owner Trustee, and Chemical Bank, as Indenture Trustee (Unit 1 Transaction) (refiled)
 
99.12 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1997
1-6986
PNM
         
99.13
Assignment, Assumption and Further Agreement dated as of December 15, 1986, between Public Service Company of New Mexico and The First National Bank of Boston, as Owner Trustee (Unit 1 Transaction) (refiled)
 
99.13 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1997
1-6986
PNM
 
 
 
D-23

 
         
99.14
Participation Agreement dated as of December 15, 1986, among the Owner Participant named therein, First PV Funding Corporation, The First National Bank of Boston, in its individual capacity and as Owner Trustee (under a Trust Agreement dated as of December 15, 1986, with the Owner Participant), Chemical Bank, in its individual capacity and as Indenture Trustee (under a Trust Indenture, Mortgage, Security Agreement and Assignment of Rents dated as of December 15, 1986, with the Owner Trustee), and Public Service Company of New Mexico, including Appendix A definitions (Unit 2 Transaction) (refiled)
 
99.14 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1997
1-6986
PNM
         
99.15
Trust Indenture, Mortgage, Security Agreement and Assignment of Rents dated as of December 31, 1986, between the First National Bank of Boston, as Owner Trustee, and Chemical Bank, as Indenture Trustee (Unit 2 Transaction) (refiled)
 
99.15 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
         
99.16
Assignment, Assumption, and Further Agreement dated as of December 15, 1986, between Public Service Company of New Mexico and The First National Bank of Boston, as Owner Trustee (Unit 2 Transaction) (refiled)
 
99.16 to PNM’s Quarterly Report on Form 10-Q for the quarter ended March 31, 1997
1-6986
PNM
         
99.17*
Waiver letter with respect to “Deemed Loss Event” dated as of August 18, 1986, between the Owner Participant named therein, and Public Service Company of New Mexico (refiled)
 
99.17 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
         
99.18*
Waiver letter with respect to Deemed Loss Event” dated as of August 18, 1986, between the Owner Participant named therein, and Public Service Company of New Mexico (refiled)
 
99.18 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
         
99.19
Agreement No. 13904 (Option and Purchase of Effluent), dated April 23, 1973, among Arizona Public Service Company, Salt River Project Agricultural Improvement and Power District, the Cities of Phoenix, Glendale, Mesa, Scottsdale, and Tempe, and the Town of Youngtown (refiled)
 
99.19 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
         
99.20
Agreement for the Sale and Purchase of Wastewater Effluent, dated June 12, 1981, Among Arizona Public Service Company, Salt River Project Agricultural Improvement and Power District and the City of Tolleson, as amended (refiled)
 
99.20 to PNM’s Annual Report on Form 10-K for fiscal year ended December 31, 1996
1-6986
PNM
 
 
D-24

 
         
99.21*
1996 Supplemental Indenture dated as of September 27, 1996 to Trust Indenture, Mortgage, Security Agreement and Assignment of Rents dated as of December 16, 1985 between State Street Bank and Trust Company, as Owner Trustee, and The Chase Manhattan Bank, as Indenture Trustee
 
99.21 to PNM’s Quarterly Report on Form 10-Q for the quarter ended September 30, 1996
1-6986
PNM
         
99.22
1997 Supplemental Indenture, dated as of December 23, 1997, to Trust Indenture, Mortgage, Security Agreement and Assignment of Rents, dated as of August 12, 1986, between State Street Bank and Trust, as Owner Trustee, and The Chase Manhattan Bank, as Indenture Trustee
 
99.22 to the Company’s Annual Report on Form 10-K for the year ended December 31, 2006
1-6986
PNM


___________
 *        One or more additional documents, substantially identical in all material respects to this exhibit, have been entered into, relating to one or more additional sale and leaseback transactions. Although such additional documents may differ in other respects (such as dollar amounts and percentages), there are no material details in which such additional documents differ from this exhibit.

**       Designates each management contract or compensatory plan or arrangement required to be identified pursuant to paragraph 3 of Item 15(a) of Form 10 -K.


‡   Certain instruments defining the rights of holders of long-term debt of the registrants included in the financial statements of registrants filed herewith have been omitted because the total amount of securities authorized thereunder does not exceed 10% of the total assets of registrants. The registrants hereby agree to furnish a copy of any such omitted instrument to the SEC upon request.



 

 
D-25

 

SIGNATURES

Pursuant to the requirements of Section 13 or 15(d) of the Securities Exchange Act of 1934, the Registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.


   
PNM RESOURCES, INC.
   
(Registrant)
     
Date:  February 27, 2010
By
/s/ J. E. Sterba
   
J. E. Sterba
   
Chairman and
Chief Executive Officer

Pursuant to the requirements of the Securities Exchange Act of 1934, this report has been signed below by the following persons on behalf of the Registrant and in the capacities and on the dates indicated.

Signature
 
Capacity
Date
       
/s/ J. E. Sterba
 
  Principal Executive Officer and
February 27, 2010
J. E. Sterba
Chairman and
Chief Executive Officer
 
Chairman of the Board
 
/s/ C. N. Eldred
 
  Principal Financial Officer
February 27, 2010
C. N. Eldred
Executive  Vice President and
Chief Financial Officer
     
/s/ T. G. Sategna
 
  Principal Accounting Officer
February 27, 2010
T. G. Sategna
Vice President and
Corporate Controller
     
/s/ A. E. Archuleta
 
  Director
February 27, 2010
A. E. Archuleta
     
/s/ J. A. Dobson
 
  Director
February 27, 2010
J. A. Dobson
     
/s/ R. R. Nordhaus
 
  Director
February 27, 2010
R. R. Nordhaus
     
/s/ M. T. Pacheco
 
  Director
February 27, 2010
M. T. Pacheco
     
/s/ R. M. Price
 
  Director
February 27, 2010
R. M. Price
     
/s/ B. S. Reitz
 
  Director
February 27, 2010
B. S. Reitz
     
/s/ D. K. Schwanz
 
  Director
February 27, 2010
D. K. Schwanz
     
/s/ J. B. Woodard
 
  Director
February 27, 2010
J. B. Woodard
     


E-1
 
 

 

SIGNATURES

Pursuant to the requirements of Section 13 or 15(d) of the Securities Exchange Act of 1934, the Registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.


   
PUBLIC SERVICE COMPANY OF NEW MEXICO
   
(Registrant)
     
Date:  February 27, 2010
By
/s/ P. K. Collawn
   
P. K. Collawn
   
President and
   
Chief Executive Officer

Pursuant to the requirements of the Securities Exchange Act of 1934, this report has been signed below by the following persons on behalf of the Registrant and in the capacities and on the dates indicated.


Signature
 
Capacity
Date
       
/s/ P. K. Collawn
 
  Principal Executive Officer and
February 27, 2010
P. K. Collawn
President and
 Chief Executive Officer
 
Director
 
/s/ C. N. Eldred
 
  Principal Financial Officer and
February 27, 2010
C. N. Eldred
Executive Vice President and
Chief Financial Officer
 
Director
 
/s/ T. G. Sategna
 
  Principal Accounting Officer
February 27, 2010
T. G. Sategna
Vice President and
Corporate Controller
     
/s/ A. A. Cobb
 
  Director
February 27, 2010
A. A. Cobb
     
/s/ E. J. Ferland
 
  Director
February 27, 2010
E. J. Ferland
     
/s/ J. E. Sterba
 
  Chairman of the Board
February 27, 2010
J. E. Sterba
     

 


E-2

 
 

 

SIGNATURES

Pursuant to the requirements of Section 13 or 15(d) of the Securities Exchange Act of 1934, the Registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.


   
TEXAS-NEW MEXICO POWER COMPANY
   
(Registrant)
     
Date:  February 27, 2010
By
/s/ P. K. Collawn
   
P. K. Collawn
   
President and
   
Chief Executive Officer

Pursuant to the requirements of the Securities Exchange Act of 1934, this report has been signed below by the following persons on behalf of the Registrant and in the capacities and on the dates indicated.

Signature
 
Capacity
Date
       
/s/ P. K. Collawn
 
  Principal Executive Officer and
February 27, 2010
P. K. Collawn
President and
Chief Executive Officer
 
Director
 
/s/ T. G. Sategna
 
  Principal Financial Officer and
February 27, 2010
T. G. Sategna
Vice President and
Controller
 
Principal Accounting Officer
 
/s/ A. A. Cobb
 
  Director
February 27, 2010
A. A. Cobb
     
/s/ J. E. Sterba
 
  Chairman of the Board
February 27, 2010
J. E. Sterba
     


























E-3

 
 

 


EX-10.1 2 exh10-1_123109.htm EXHIBIT 10.1 exh10-1_123109.htm

Exhibit 10.1
  
Change in Director Compensation
  
Non-employee directors of PNM Resources, Inc. (the “Company”) receive their annual retainer in the form of cash and stock-based compensation as determined by the Company’s Board of Directors.   At the December 2009 Board meeting, the Board approved increasing the 2010 annual retainer for non-employee directors from the 2009 annual retainer reported in the Company’s 2009 Proxy Statement by increasing the amount of time-vested restricted stock rights from 2,500 to 4,000.  No other changes were made to the amount of stock options, amount of annual cash retainer, or meeting and chair fees.  Thus, except as described below for Mr. Sterba (who retires as the Company’s Chief Executive Officer (“CEO”) effective March 1, 2010), the 2010 annual retainer for non-employee directors is as follows:
 
Annual Retainer:
 
$35,000, 1,000 stock options* and 4,000 restricted stock rights*
     
Annual Committee Chair Fee:
 
$  5,000 paid in quarterly installments (in addition to meeting attendance fees), except that the Annual Audit and Ethics Committee Chair Fee is $10,000
     
Attendance Fees:
(no attendance fee for teleconference meetings less than 1 hour in duration)
 
$    1,750  per Board meeting
$    1,500 per Board Committee meeting
 
* Stock options and restricted stock rights granted under the Company’s Omnibus Performance Equity Plan (“PEP”) each vest in three equal annual installments beginning on the first anniversary of the grant date.  These awards are typically made at the annual meeting of directors, unless the meeting occurs during a black-out period for trading in the Company’s securities as specified in the Company’s Insider Trading Policy.  As set forth under the Company’s Stock Option Grant Policy, under those circumstances, the Board will either (a) schedule a special meeting after the expiration of the black-out period, (b) make awards pursuant to a unanimous written consent executed after the expiration of the black-out period, or (c) pre-approve the equity awards with an effective date after the expiration of the black-out period.  The date of the awards is the date on which the Board approves the awards, unless (i) the approval date is a non-trading day, in which case the date is the immediately preceding trading date or (ii) in the case of pre-approval during a black-out period, in which case the grant date is the first trading date after the expiration of the black-out period.  The exercise price of the stock option is equal to the closing price of the common stock on the New York Stock Exchange on the date of the grant.   The PEP prohibits option re-pricing.
  
Directors are also reimbursed for any Board-related expenses, such as travel expenses incurred to attend Board and Board committee meetings and director educational programs.

While employed as CEO, Mr. Sterba receives no additional compensation for serving as a director or as the Chairman of the Board and is only reimbursed for any travel related expenses to Board meetings.  As reported in a Current Report on Form 8-K filed February 19, 2010, in February 2010, the Board asked Mr. Sterba to continue to serve as Chairman following his retirement as CEO.  In his role as Chairman, Mr. Sterba will, among other things, provide support on strategic and public policy issues to the Company.  He will also continue to serve as the Chairman of the First Choice Power board of managers and as a PNMR representative on the board of Optim Energy, LLC and as its Chairman.  As compensation, Mr. Sterba will receive a separate annual retainer of $250,000.    Mr. Sterba will not receive any separate Board attendance fees but is eligible to receive the annual equity award of 1,000 stock options and 4,000 restricted stock rights typically made at the annual meeting of directors.  In addition, Mr. Sterba will be reimbursed for any Board-related expenses, such as travel expenses incurred to attend Board meetings. 


 
 

 

EX-12.1 3 exh12-1_123109.htm EXHIBIT 12.1 exh12-1_123109.htm
 
Exhibit 12.1

PNM RESOURCES, INC. AND SUBSIDIARIES
 
Ratio of Earnings to Fixed Charges
 
(In thousands, except ratio)
 
                               
                               
   
Year Ended December 31,
 
   
2009
   
2008
   
2007
   
2006
   
2005
 
Fixed charges, as defined by the Securities and Exchange
                             
Commission:
                             
                               
Interest on long-term debt (including interest capitalized)
  $ 113,574     $ 98,455     $ 85,757     $ 87,755     $ 67,463  
Amortization of debt premium, discount and expenses
    5,430       6,386       6,566       4,729       3,962  
Other interest (including interest capitalized)
    10,259       36,503       38,542       48,064       15,939  
Interest from discontinued operations (including capitalized interest)
    1,027       13,758       12,546       11,790       10,658  
Estimated interest factor of lease rental charges
    7,034       7,894       8,804       7,124       7,568  
Preferred dividend requirements of subsidiary
    759       689       556       798       4,063  
     Total Fixed Charges
  $ 138,083     $ 163,685     $ 152,771     $ 160,260     $ 109,653  
                                         
                                         
                                         
Earnings, as defined by the Securities and Exchange
                                       
Commission:
                                       
                                         
Earnings from continuing operations before income taxes and non-controlling interest
  $ 94,751     $ (388,381 )   $ 63,112     $ 164,018     $ 76,502  
(Earnings) loss of equity investee
    30,145       29,687       (7,581 )     -       -  
Earnings from continuing operations before income taxes, non-controlling interest,  and investee earnings
    124,896       (358,694 )     55,531       164,018       76,502  
Fixed charges as above
    138,083       163,685       152,771       160,260       109,653  
Interest capitalized
    (7,743 )     (8,849     (10,740 )     (6,503 )     (4,025 )
Non-controlling interest in earnings of Valencia
    (11,890 )     (7,179     -       -       -  
Preferred dividend requirements of subsidiary
    (759 )     (689     (556 )     (798 )     (4,063 )
                                         
Earnings Available for Fixed Charges
  $ 242,587     $ (211,726   $ 197,006     $ 316,977     $ 178,067  
                                         
Ratio of Earnings to Fixed Charges
    1.76       N/M   *   1.29       1.98       1.62  
                                         
 
 
 
                                       
* The ratio of earnings to fixed charges for the year ended December 31, 2008 is not meaningful since earnings available for fixed charges is negative. The shortfall in the earnings available for fixed charges to achieve a ratio of earnings to fixed charges of 1.00 amounted to $375.4 million for the year ended December 31, 2008.
 
                   
                                         
                                         

 
 

 

EX-12.2 4 exh12-2_123109.htm EXHIBIT 12.2 exh12-2_123109.htm

                           
Exhibit 12.2
 
PUBLIC SERVICE COMPANY OF NEW MEXICO
 
Ratio of Earnings to Fixed Charges
 
(In thousands, except ratio)
 
                               
                               
   
Year Ended December 31,
 
   
2009
   
2008
   
2007
   
2006
   
2005
 
Fixed charges, as defined by the Securities and Exchange
                             
Commission:
                             
                               
Interest on long-term debt (including interest capitalized)
  $ 70,575     $ 58,003     $ 42,272     $ 42,487     $ 40,462  
Amortization of debt premium, discount and expenses
    1,336       4,345       4,618       2,871       2,856  
Other interest (including interest capitalized)
    2,529       14,424       15,773       6,892       3,980  
Interest from discontinued operations (including capitalized interest)
    1,027       13,758       12,546       11,790       10,658  
Estimated interest factor of lease rental charges
    4,517       4,553       4,661       4,337       4,588  
     Total Fixed Charges
  $ 79,984     $ 95,083     $ 79,870     $ 68,377     $ 62,544  
                                         
Earnings, as defined by the Securities and Exchange
                                       
Commission:
                                       
                                         
Earnings from continuing operations before income taxes and non-controlling interest
  $ 45,627     $ (69,324 )   $ 34,611     $ 89,657     $ 51,034  
Fixed charges as above
    79,984       95,083       79,870       68,377       62,544  
Non-controlling interest in earnings of Valencia
    (11,890 )     (7,179 )     -       -       -  
Interest capitalized
    (6,067 )     (7,363 )     (10,033 )     (5,257 )     (3,512 )
                                         
Earnings Available for Fixed Charges
  $ 107,654     $ 11,217 *   $ 104,448     $ 152,777     $ 110,066  
                                         
Ratio of Earnings to Fixed Charges
    1.35       0.12       1.31       2.23       1.76  
                                         
 
 
                                         
* The shortfall in the earnings available for fixed charges to achieve a ratio of earnings to fixed charges of 1.00 amounted to $83.9 million for the year December 31, 2008.
 
                                         

 
 

 

EX-12.3 5 exh12-3_123109.htm EXHIBIT 12.3 exh12-3_123109.htm

                           
Exhibit 12.3
 
TEXAS-NEW MEXICO POWER COMPANY
 
Ratio of Earnings to Fixed Charges
 
(In thousands, except ratio)
 
                               
                               
   
Year Ended December 31,
 
         
 
                   
   
2009
   
2008
   
2007
   
2006
   
2005
 
Fixed charges, as defined by the Securities and Exchange
                         
Commission:
                             
                               
Interest on long-term debt (including interest capitalized)
  $ 22,232     $ 12,427     $ 22,394     $ 25,728     $ 25,727  
Amortization of debt premium, discount and expenses
    3,355       1,504       1,925       1,695       2,111  
Other interest (including interest capitalized)
    3,377       5,434       1,129       1,646       179  
Estimated interest factor of lease rental charges
    831       571       844       367       377  
                                         
Total Fixed Charges
  $ 29,795     $ 19,936     $ 26,292     $ 29,436     $ 28,394  
                                         
                                         
Earnings, as defined by the Securities and Exchange
                                       
Commission:
                                       
                                         
Earnings from continuing operations before income taxes
  $ 20,151     $ 2,335     $ 29,055     $ 17,905     $ 25,183  
Fixed charges as above
    29,795       19,936       26,292       29,436       28,394  
Interest capitalized
    (1,144 )     (1,025 )     (332 )     (209 )     (200 )
                                         
Earnings Available for Fixed Charges
  $ 48,802     $ 21,246     $ 55,015     $ 47,132     $ 53,377  
                                         
Ratio of Earnings to Fixed Charges
    1.64       1.07       2.09       1.60       1.88  
                                         

 
 

 

EX-21 6 exh21_123109.htm EXHIBIT 21 exh21_123109.htm

EXHIBIT 21
 
 
Subsidiaries of PNM Resources, Inc.
 
 
As of December 31, 2009, PNM Resources, Inc. directly or indirectly owns all of the voting securities of the following subsidiaries:
 
Public Service Company of New Mexico, a New Mexico corporation that does business under the names “Public Service Company of New Mexico” and “PNM”.
 
Texas-New Mexico Power Company, a Texas corporation that does business under the name “Texas-New Mexico Power Company” and “TNMP”.
 
First Choice Power Special Purpose, LP, a Texas limited partnership that does business under its partnership name.
 
First Choice Power, LP, a Texas limited partnership that does business under its partnership name.
 
FCP Enterprises Inc., a Delaware corporation that does business under its corporate name.
 
TNP Enterprises, Inc., a Texas corporation that does business under its corporate name.

The remaining subsidiaries of PNM Resources, Inc. considered in the aggregate as a single subsidiary, do not constitute a "significant subsidiary" (as defined in Rule 1-02(w) of Regulation S-X) as of the end of the year covered by this report.
 


 
 

 

EX-23.1 7 exh23-1_123109.htm EXHIBIT 23.1 exh23-1_123109.htm

EXHIBIT 23.1


CONSENT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM
 
 
We consent to the incorporation by reference in Registration Statement Nos. 333-150101 and 333-161218 on Form S-3ASR and Registration Statement Nos. 333-76288, 333-139108, 333-129454, 333-03303, 333-03289, 333-88372, 333-121371, 333-125010, 333-141282, 333-156243, 333-159361, and 333-159362 on Form S-8 of our reports dated February 27, 2010  relating to the consolidated financial statements (which report expresses an unqualified opinion and includes an explanatory paragraph regarding the change in method of accounting for fair value measurements in 2008), financial statement schedules, and internal control over financial reporting of PNM Resources, Inc. and subsidiaries, appearing in this Annual Report on Form 10-K of PNM Resources, Inc. and subsidiaries for the year ended December 31, 2009.
 
/s/ DELOITTE & TOUCHE LLP
 
Dallas, Texas
February 27, 2010


 
 

 

EX-23.2 8 exh23-2_123109.htm EXHIBIT 23.2 exh23-2_123109.htm

EXHIBIT 23.2


CONSENT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM
 
 
We consent to the incorporation by reference in Registration Statement No. 333-150024 on Form S-3 of our reports dated February 27, 2010   relating to the consolidated financial statements (which report expresses an unqualified opinion and includes an explanatory paragraph regarding the change in method of accounting for fair value measurements in 2008), financial statement schedule, and internal controls over financial reporting of Public Service Company of New Mexico and subsidiaries, appearing in this Annual Report on Form 10-K of Public Service Company of New Mexico and subsidiaries for the year ended December 31, 2009.
  
/s/ DELOITTE & TOUCHE LLP
 
Dallas, Texas
February 27, 2010
 


 
 

 

EX-31.1 9 exh31-1_123109.htm EXHIBIT 31.1 exh31-1_123109.htm

PNM Resources
Alvarado Square
Albuquerque, NM  87158
www.pnmresources.com



EXHIBIT 31.1

CERTIFICATION


I, Jeffry E. Sterba, certify that:

1.  
I have reviewed this Annual Report on Form 10-K of PNM Resources, Inc.;

2.  
Based on my knowledge, this report does not contain any untrue statement of a material fact or omit to state a material fact necessary to make the statements made, in light of the circumstances under which such statements were made, not misleading with respect to the period covered by this report;

3.  
Based on my knowledge, the financial statements, and other financial information included in this report, fairly present in all material respects the financial condition, results of operations and cash flows of the registrant as of, and for, the periods presented in this report;

4.  
The registrant’s other certifying officer and I are responsible for establishing and maintaining disclosure controls and procedures (as defined in Exchange Act Rules 13a-15(e) and 15d-15(e)) and internal control over financial reporting (as defined in Exchange Act Rules 13a-15(f) and 15d-15(f)) for the registrant and have:

          a)  
Designed such disclosure controls and procedures, or caused such disclosure controls and procedures to be designed under our supervision, to ensure that material information relating to the registrant, including its consolidated subsidiaries, is made known to us by others within those entities, particularly during the period in which this report is being prepared;

          b)  
Designed such internal control over financial reporting, or caused such internal control over financial reporting to be designed under our supervision, to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles;

          c)  
Evaluated the effectiveness of the registrant’s disclosure controls and procedures and presented in this report our conclusions about the effectiveness of the disclosure controls and procedures, as of the end of the period covered by this report based on such evaluation; and

          d)  
Disclosed in this report any change in the registrant’s internal control over financial reporting that occurred during the registrant’s most recent fiscal quarter (each registrant’s fourth fiscal quarter in the case of an annual report) that has materially affected, or is reasonably likely to materially affect, the registrant’s internal control over financial reporting; and


 
 

 

5.  
The registrant’s other certifying officer and I have disclosed, based on our most recent evaluation of internal control over financial reporting, to the registrant’s auditors and the audit committee of the registrant’s board of directors (or persons performing the equivalent functions):

          a)  
All significant deficiencies and material weaknesses in the design or operation of internal controls over financial reporting which are reasonably likely to adversely affect the registrant’s ability to record, process, summarize and report financial information; and

          b)  
Any fraud, whether or not material, that involves management or other employees who have a significant role in the registrant’s internal control over financial reporting.




Date:   February 27, 2010




/s/ Jeffry E. Sterba                            
Jeffry E. Sterba
Chairman and Chief Executive Officer
PNM Resources, Inc.



 
 

 

EX-31.2 10 exh31-2_123109.htm EXHIBIT 31.2 exh31-2_123109.htm

PNM Resources
Alvarado Square
Albuquerque, NM  87158
www.pnmresources.com



EXHIBIT 31.2

CERTIFICATION


I, Charles N. Eldred, certify that:

1.  
I have reviewed this Annual Report on Form 10-K of PNM Resources, Inc.;

2.  
Based on my knowledge, this report does not contain any untrue statement of a material fact or omit to state a material fact necessary to make the statements made, in light of the circumstances under which such statements were made, not misleading with respect to the period covered by this report;

3.  
Based on my knowledge, the financial statements, and other financial information included in this report, fairly present in all material respects the financial condition, results of operations and cash flows of the registrant as of, and for, the periods presented in this report;

4.  
The registrant’s other certifying officer and I are responsible for establishing and maintaining disclosure controls and procedures (as defined in Exchange Act Rules 13a-15(e) and 15d-15(e)) and internal control over financial reporting (as defined in Exchange Act Rules 13a-15(f) and 15d-15(f)) for the registrant and have:

          a)  
Designed such disclosure controls and procedures, or caused such disclosure controls and procedures to be designed under our supervision, to ensure that material information relating to the registrant, including its consolidated subsidiaries, is made known to us by others within those entities, particularly during the period in which this report is being prepared;

          b)  
Designed such internal control over financial reporting, or caused such internal control over financial reporting to be designed under our supervision, to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles;

          c)  
Evaluated the effectiveness of the registrant’s disclosure controls and procedures and presented in this report our conclusions about the effectiveness of the disclosure controls and procedures, as of the end of the period covered by this report based on such evaluation; and

          d)  
Disclosed in this report any change in the registrant’s internal control over financial reporting that occurred during the registrant’s most recent fiscal quarter (each registrant’s fourth fiscal quarter in the case of an annual report) that has materially affected, or is reasonably likely to materially affect, the registrant’s internal control over financial reporting; and


 
 

 

5.  
The registrant’s other certifying officer and I have disclosed, based on our most recent evaluation of internal control over financial reporting, to the registrant’s auditors and the audit committee of the registrant’s board of directors (or persons performing the equivalent functions):

          a)  
All significant deficiencies and material weaknesses in the design or operation of internal controls over financial reporting which are reasonably likely to adversely affect the registrant’s ability to record, process, summarize and report financial information; and

          b)  
Any fraud, whether or not material, that involves management or other employees who have a significant role in the registrant’s internal control over financial reporting.




Date:   February 27, 2010




/s/ Charles N. Eldred                            
Charles N. Eldred
Executive Vice President and
Chief Financial Officer
PNM Resources, Inc.



 
 

 

EX-31.3 11 exh31-3_123109.htm EXHIBIT 31.3 exh31-3_123109.htm

PNM Resources
Alvarado Square
Albuquerque, NM  87158
www.pnmresources.com



EXHIBIT 31.3

CERTIFICATION


I, Patricia K. Collawn, certify that:

1.  
I have reviewed this Annual Report on Form 10-K of Public Service Company of New Mexico;

2.  
Based on my knowledge, this report does not contain any untrue statement of a material fact or omit to state a material fact necessary to make the statements made, in light of the circumstances under which such statements were made, not misleading with respect to the period covered by this report;

3.  
Based on my knowledge, the financial statements, and other financial information included in this report, fairly present in all material respects the financial condition, results of operations and cash flows of the registrant as of, and for, the periods presented in this report;

4.  
The registrant’s other certifying officer and I are responsible for establishing and maintaining disclosure controls and procedures (as defined in Exchange Act Rules 13a-15(e) and 15d-15(e)) and internal control over financial reporting (as defined in Exchange Act Rules 13a-15(f) and 15d-15(f)) for the registrant and have:

          a)  
Designed such disclosure controls and procedures, or caused such disclosure controls and procedures to be designed under our supervision, to ensure that material information relating to the registrant, including its consolidated subsidiaries, is made known to us by others within those entities, particularly during the period in which this report is being prepared;

          b)  
Designed such internal control over financial reporting, or caused such internal control over financial reporting to be designed under our supervision, to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles;

          c)  
Evaluated the effectiveness of the registrant’s disclosure controls and procedures and presented in this report our conclusions about the effectiveness of the disclosure controls and procedures, as of the end of the period covered by this report based on such evaluation; and

          d)  
Disclosed in this report any change in the registrant’s internal control over financial reporting that occurred during the registrant’s most recent fiscal quarter (each registrant’s fourth fiscal quarter in the case of an annual report) that has materially affected, or is reasonably likely to materially affect, the registrant’s internal control over financial reporting; and


 
 

 

5.  
The registrant’s other certifying officer and I have disclosed, based on our most recent evaluation of internal control over financial reporting, to the registrant’s auditors and the audit committee of the registrant’s board of directors (or persons performing the equivalent functions):

          a)  
All significant deficiencies and material weaknesses in the design or operation of internal controls over financial reporting which are reasonably likely to adversely affect the registrant’s ability to record, process, summarize and report financial information; and

          b)  
Any fraud, whether or not material, that involves management or other employees who have a significant role in the registrant’s internal control over financial reporting.




Date: February 27, 2010




/s/  Patricia K. Collawn                   
Patricia K. Collawn
President and Chief Executive Officer
Public Service Company of New Mexico



 
 

 

EX-31.4 12 exh31-4_123109.htm EXHIBIT 31.4 exh31-4_123109.htm

PNM Resources
Alvarado Square
Albuquerque, NM  87158
www.pnmresources.com



EXHIBIT 31.4

CERTIFICATION


I, Charles N. Eldred, certify that:

1.  
I have reviewed this Annual Report on Form 10-K of Public Service Company of New Mexico;

2.  
Based on my knowledge, this report does not contain any untrue statement of a material fact or omit to state a material fact necessary to make the statements made, in light of the circumstances under which such statements were made, not misleading with respect to the period covered by this report;

3.  
Based on my knowledge, the financial statements, and other financial information included in this report, fairly present in all material respects the financial condition, results of operations and cash flows of the registrant as of, and for, the periods presented in this report;

4.  
The registrant’s other certifying officer and I are responsible for establishing and maintaining disclosure controls and procedures (as defined in Exchange Act Rules 13a-15(e) and 15d-15(e)) and internal control over financial reporting (as defined in Exchange Act Rules 13a-15(f) and 15d-15(f)) for the registrant and have:

          a)  
Designed such disclosure controls and procedures, or caused such disclosure controls and procedures to be designed under our supervision, to ensure that material information relating to the registrant, including its consolidated subsidiaries, is made known to us by others within those entities, particularly during the period in which this report is being prepared;

          b)  
Designed such internal control over financial reporting, or caused such internal control over financial reporting to be designed under our supervision, to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles;

          c)  
Evaluated the effectiveness of the registrant’s disclosure controls and procedures and presented in this report our conclusions about the effectiveness of the disclosure controls and procedures, as of the end of the period covered by this report based on such evaluation; and

          d)  
Disclosed in this report any change in the registrant’s internal control over financial reporting that occurred during the registrant’s most recent fiscal quarter (each registrant’s fourth fiscal quarter in the case of an annual report) that has materially affected, or is reasonably likely to materially affect, the registrant’s internal control over financial reporting; and


 
 

 

5.  
The registrant’s other certifying officer and I have disclosed, based on our most recent evaluation of internal control over financial reporting, to the registrant’s auditors and the audit committee of the registrant’s board of directors (or persons performing the equivalent functions):

          a)  
All significant deficiencies and material weaknesses in the design or operation of internal controls over financial reporting which are reasonably likely to adversely affect the registrant’s ability to record, process, summarize and report financial information; and

          b)  
Any fraud, whether or not material, that involves management or other employees who have a significant role in the registrant’s internal control over financial reporting.




Date:   February  27, 2010




/s/ Charles N. Eldred                            
Charles N. Eldred
Executive Vice President and
Chief Financial Officer
Public Service Company of New Mexico



 
 

 

EX-31.5 13 exh31-5_123109.htm EXHIBIT 31.5 exh31-5_123109.htm

PNM Resources
Alvarado Square
Albuquerque, NM  87158
www.pnmresources.com



EXHIBIT 31.5

CERTIFICATION


I, Patricia K. Collawn, certify that:

1.  
I have reviewed this Annual Report on Form 10-K of Texas-New Mexico Power Company;

2.  
Based on my knowledge, this report does not contain any untrue statement of a material fact or omit to state a material fact necessary in order to make the statements made, in light of the circumstances under which such statements were made, not misleading with respect to the period covered by this report;

3.  
Based on my knowledge, the financial statements, and other financial information included in this report, fairly present in all material respects the financial condition, results of operations and cash flows of the registrant as of, and for, the periods presented in this report;

4.  
The registrant’s other certifying officer and I are responsible for establishing and maintaining disclosure controls and procedures (as defined in Exchange Act Rules 13a-15(e) and 15d-15(e)) and internal control over financial reporting (as defined in Exchange Act Rules 13a-15(f) and 15d-15(f)) for the registrant and have:

          a)  
Designed such disclosure controls and procedures, or caused such disclosure controls and procedures to be designed under our supervision, to ensure that material information relating to the registrant, including its consolidated subsidiaries, is made known to us by others within those entities, particularly during the period in which this report is being prepared;

          b)  
Designed such internal control over financial reporting, or caused such internal control over financial reporting to be designed under our supervision, to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles;

          c)  
Evaluated the effectiveness of the registrant’s disclosure controls and procedures and presented in this report our conclusions about the effectiveness of the disclosure controls and procedures, as of the end of the period covered by this report based on such evaluation; and

          d)  
Disclosed in this report any change in the registrant’s internal control over financial reporting that occurred during the registrant’s most recent fiscal quarter (the registrant’s fourth fiscal quarter in the case of an annual report) that has materially affected, or is reasonably likely to materially affect, the registrant’s internal control over financial reporting; and

 
 

 
5.  
The registrant’s other certifying officer and I have disclosed, based on our most recent evaluation of internal control over financial reporting, to the registrant’s auditors and the audit committee of the registrant’s board of directors (or persons performing the equivalent functions):

          a)  
All significant deficiencies and material weaknesses in the design or operation of internal controls over financial reporting which are reasonably likely to adversely affect the registrant’s ability to record, process, summarize and report financial information; and

          b)  
Any fraud, whether or not material, that involves management or other employees who have a significant role in the registrant’s internal control over financial reporting.




Date:   February 27, 2010
 

 


/s/ Patricia K. Collawn                         
Patricia K. Collawn
President and Chief Executive Officer
Texas-New Mexico Power Company




 
 

 

EX-31.6 14 exh31-6_123109.htm EXHIBIT 31.6 exh31-6_123109.htm

PNM Resources
Alvarado Square
Albuquerque, NM  87158
www.pnmresources.com



EXHIBIT 31.6

CERTIFICATION


I, Thomas G. Sategna, certify that:

1.  
I have reviewed this Annual Report on Form 10-K of Texas-New Mexico Power Company;

2.  
Based on my knowledge, this report does not contain any untrue statement of a material fact or omit to state a material fact necessary in order to make the statements made, in light of the circumstances under which such statements were made, not misleading with respect to the period covered by this report;

3.  
Based on my knowledge, the financial statements, and other financial information included in this report, fairly present in all material respects the financial condition, results of operations and cash flows of the registrant as of, and for, the periods presented in this report;

4.  
The registrant’s other certifying officer and I are responsible for establishing and maintaining disclosure controls and procedures (as defined in Exchange Act Rules 13a-15(e) and 15d-15(e)) and internal control over financial reporting (as defined in Exchange Act Rules 13a-15(f) and 15d-15(f)) for the registrant and have:

          a)  
Designed such disclosure controls and procedures, or caused such disclosure controls and procedures to be designed under our supervision, to ensure that material information relating to the registrant, including its consolidated subsidiaries, is made known to us by others within those entities, particularly during the period in which this report is being prepared;

          b)  
Designed such internal control over financial reporting, or caused such internal control over financial reporting to be designed under our supervision, to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles;

          c)  
Evaluated the effectiveness of the registrant’s disclosure controls and procedures and presented in this report our conclusions about the effectiveness of the disclosure controls and procedures, as of the end of the period covered by this report based on such evaluation; and

          d)  
Disclosed in this report any change in the registrant’s internal control over financial reporting that occurred during the registrant’s most recent fiscal quarter (the registrant’s fourth fiscal quarter in the case of an annual report) that has materially affected, or is reasonably likely to materially affect, the registrant’s internal control over financial reporting; and

 
 

 
5.  
The registrant’s other certifying officer and I have disclosed, based on our most recent evaluation of internal control over financial reporting, to the registrant’s auditors and the audit committee of the registrant’s board of directors (or persons performing the equivalent functions):

          a)  
All significant deficiencies and material weaknesses in the design or operation of internal controls over financial reporting which are reasonably likely to adversely affect the registrant’s ability to record, process, summarize and report financial information; and

          b)  
Any fraud, whether or not material, that involves management or other employees who have a significant role in the registrant’s internal control over financial reporting.




Date:   February 27, 2010





/s/ Thomas G. Sategna                        
Thomas G. Sategna
Vice President and Controller
Texas-New Mexico Power Company



 
 

 

EX-32.1 15 exh32-1_123109.htm EXHIBIT 32.1 exh32-1_123109.htm

PNM Resources
Alvarado Square
Albuquerque, NM  87158
www.pnmresources.com




EXHIBIT 32.1


CERTIFICATION PURSUANT TO 18 U.S.C. § 1350, AS ADOPTED PURSUANT TO § 906 OF THE SARBANES-OXLEY ACT OF 2002


In connection with the Annual Report on Form 10-K for the period ended December 31, 2009, for PNM Resources, Inc. (“Company”), as filed with the Securities and Exchange Commission on February 27, 2010 (“Report”), I, Jeffry E. Sterba, Chairman and Chief Executive Officer of the Company, certify pursuant to 18 U.S.C. §1350, as adopted pursuant to § 906 of the Sarbanes-Oxley Act of 2002, that:

 
(1)
the Report fully complies with the requirements of § 13(a) or 15(d) of the Securities Exchange Act of 1934, as amended; and

 
(2)
the information contained in the Report fairly presents, in all material respects, the financial condition and results of operations of the Company.


Date:   February 27, 2010
By:
/s/ Jeffry E. Sterba                            
   
Jeffry E. Sterba
   
Chairman and Chief Executive Officer
   
PNM Resources, Inc.
     


 
 

 

EX-32.2 16 exh32-2_123109.htm EXHIBIT 32.2 exh32-2_123109.htm

PNM Resources
Alvarado Square
Albuquerque, NM  87158
www.pnmresources.com




EXHIBIT 32.2


CERTIFICATION PURSUANT TO 18 U.S.C. § 1350, AS ADOPTED PURSUANT TO § 906 OF THE SARBANES-OXLEY ACT OF 2002


In connection with the Annual Report on Form 10-K for the period ended December 31, 2009, for PNM Resources, Inc. (“Company”), as filed with the Securities and Exchange Commission on February 27, 2010 (“Report”), I, Charles N. Eldred, Executive Vice President and Chief Financial Officer of the Company, certify pursuant to 18 U.S.C. §1350, as adopted pursuant to § 906 of the Sarbanes-Oxley Act of 2002, that:

 
(1)
the Report fully complies with the requirements of § 13(a) or 15(d) of the Securities Exchange Act of 1934, as amended; and

 
(2)
the information contained in the Report fairly presents, in all material respects, the financial condition and results of operations of the Company.


Date:   February 27, 2010
By:
/s/ Charles N. Eldred                         
   
Charles N. Eldred
   
Executive Vice President and
   
Chief Financial Officer
   
PNM Resources, Inc.



 
 

 

EX-32.3 17 exh32-3_123109.htm EXHIBIT 32.3 exh32-3_123109.htm

PNM Resources
Alvarado Square
Albuquerque, NM  87158
www.pnmresources.com




EXHIBIT 32.3


CERTIFICATION PURSUANT TO 18 U.S.C. § 1350, AS ADOPTED PURSUANT TO § 906 OF THE SARBANES-OXLEY ACT OF 2002


In connection with the Annual Report on Form 10-K for the period ended December 31, 2009, for Public Service Company of New Mexico (“Company”), as filed with the Securities and Exchange Commission on February 27, 2010 (“Report”), I, Patricia K. Collawn, President and Chief Executive Officer of the Company, certify pursuant to 18 U.S.C. §1350, as adopted pursuant to § 906 of the Sarbanes-Oxley Act of 2002, that:

 
(1)
the Report fully complies with the requirements of § 13(a) or 15(d) of the Securities Exchange Act of 1934, as amended; and

 
(2)
the information contained in the Report fairly presents, in all material respects, the financial condition and results of operations of the Company.


Date:   February  27, 2010
By:
/s/ Patricia K. Collawn                         
   
Patricia K. Collawn
   
President and Chief Executive Officer
   
Public Service Company of New Mexico


 
 

 

EX-32.4 18 exh32-4_123109.htm EXHIBIT 32.4 exh32-4_123109.htm

PNM Resources
Alvarado Square
Albuquerque, NM  87158
www.pnmresources.com




EXHIBIT 32.4


CERTIFICATION PURSUANT TO 18 U.S.C. § 1350, AS ADOPTED PURSUANT TO § 906 OF THE SARBANES-OXLEY ACT OF 2002


In connection with the Annual Report on Form 10-K for the period ended December 31, 2009, for Public Service Company of New Mexico (“Company”), as filed with the Securities and Exchange Commission on February 27, 2010 (“Report”), I, Charles N. Eldred, Executive Vice President and Chief Financial Officer of the Company, certify pursuant to 18 U.S.C. §1350, as adopted pursuant to § 906 of the Sarbanes-Oxley Act of 2002, that:

 
(1)
the Report fully complies with the requirements of § 13(a) or 15(d) of the Securities Exchange Act of 1934, as amended; and

 
(2)
the information contained in the Report fairly presents, in all material respects, the financial condition and results of operations of the Company.


Date:  February 27, 2010
By:
/s/ Charles N. Eldred                           
   
Charles N. Eldred
   
Executive Vice President and
   
Chief Financial Officer
   
Public Service Company of New Mexico



 
 

 

EX-32.5 19 exh32-5_123109.htm EXHIBIT 32.5 exh32-5_123109.htm

PNM Resources
Alvarado Square
Albuquerque, NM  87158
www.pnmresources.com




EXHIBIT 32.5


CERTIFICATION PURSUANT TO 18 U.S.C. § 1350, AS ADOPTED PURSUANT TO § 906 OF THE SARBANES-OXLEY ACT OF 2002


In connection with the Annual Report on Form 10-K for the period ended December 31, 2009, for Texas-New Mexico Power Company (“Company”), as filed with the Securities and Exchange Commission on February 27, 2010 (“Report”), I, Patricia K. Collawn, President and Chief Executive Officer of the Company, certify pursuant to 18 U.S.C. §1350, as adopted pursuant to § 906 of the Sarbanes-Oxley Act of 2002, that:

 
(1)
the Report fully complies with the requirements of § 13(a) or 15(d) of the Securities Exchange Act of 1934, as amended; and

 
(2)
the information contained in the Report fairly presents, in all material respects, the financial condition and results of operations of the Company.


Date:   February 27, 2010
By:
/s/ Patricia K. Collawn                          
   
Patricia K. Collawn
   
President and Chief Executive Officer
   
Texas-New Mexico Power Company



 
 

 

EX-32.6 20 exh32-6_123109.htm EXHIBIT 32.6 exh32-6_123109.htm

PNM Resources
Alvarado Square
Albuquerque, NM  87158
www.pnmresources.com




EXHIBIT 32.6


CERTIFICATION PURSUANT TO 18 U.S.C. § 1350, AS ADOPTED PURSUANT TO § 906 OF THE SARBANES-OXLEY ACT OF 2002


In connection with the Annual Report on Form 10-K for the period ended December 31, 2009, for Texas-New Mexico Power Company (“Company”), as filed with the Securities and Exchange Commission on February 27, 2010 (“Report”), I, Thomas G. Sategna, Vice President, Controller of the Company, certify pursuant to 18 U.S.C. §1350, as adopted pursuant to § 906 of the Sarbanes-Oxley Act of 2002, that:

 
(1)
the Report fully complies with the requirements of § 13(a) or 15(d) of the Securities Exchange Act of 1934, as amended; and

 
(2)
the information contained in the Report fairly presents, in all material respects, the financial condition and results of operations of the Company.


Date:   February 27, 2010
By:
/s/ Thomas G. Sategna                         
   
Thomas G. Sategna
   
Vice President, Controller
   
Texas-New Mexico Power Company


 
 

 

-----END PRIVACY-ENHANCED MESSAGE-----