COMMITMENTS AND CONTINGENCIES
We and/or our subsidiaries are party to a number of claims, lawsuits and pending actions, most of which are routine and all of which are incidental to our business. We assess the likelihood of potential losses on an ongoing basis to determine whether losses are considered probable and reasonably estimable prior to recording an estimate of the outcome. If we can only estimate the range of a possible loss, an amount representing the low end of the range of possible outcomes is recorded. The final consequences of these proceedings are not presently determinable with certainty. As of June 30, 2021 and December 31, 2020, accruals for our loss contingencies recorded in Accrued expenses and other current liabilities in our condensed consolidated balance sheets were $3 million and $4 million, respectively.

Environmental Matters
Our operations are subject to environmental regulatory laws and environmental remediation laws. Although our operations are occasionally subject to proceedings and orders pertaining to emissions into the environment and other environmental violations, which may result in fines, penalties, damages or other sanctions, we believe that we are in substantial compliance with existing environmental laws and regulations.

We may be identified, along with other entities, as being among parties potentially responsible for contribution to costs associated with the correction and remediation of environmental conditions at disposal sites subject to federal and/or analogous
state laws. In certain instances, we may be exposed to joint and several liabilities for remedial action or damages. Our liability in connection with such environmental claims will depend on many factors, including our volumetric share of waste, the total cost of remediation, and the financial viability of other companies that also sent waste to a given site and, in the case of divested operations, the contractual arrangement with the purchaser of such operations.

The potential costs related to the matters described below and the possible impact on future operations are uncertain due in part to the complexity of governmental laws and regulations and their interpretations, the varying costs and effectiveness of cleanup technologies, the uncertain level of insurance or other types of recovery and the questionable level of our responsibility. Although the ultimate outcome and expense of any litigation, including environmental remediation, is uncertain, we believe that the following proceedings will not have a material adverse effect on our consolidated results of operations, financial position or cash flows.

Lower Passaic River Matter. In August 2004, the U.S. Environmental Protection Agency (the “EPA”) notified our subsidiary, Covanta Essex Company (“Essex”) that it was a potentially responsible party (“PRP”) for Superfund response actions in the Lower Passaic River Study Area (“LPRSA”), a 17 mile stretch of river in northern New Jersey. Essex’s LPRSA costs to date are not material to its financial position and results of operations; however, to date the EPA has not sought any LPRSA remedial costs or natural resource damages against PRPs. In March 2016, the EPA released the Record of Decision (“ROD”) for its Focused Feasibility Study of the lower 8 miles of the LPRSA; the EPA’s selected remedy includes capping/dredging of sediment, institutional controls and long-term monitoring. In June 2018, PRP Occidental Chemical Corporation (“OCC”) filed a federal Superfund lawsuit against 120 PRPs including Essex with respect to past and future response costs expended by OCC with respect to the LPRSA. The Essex facility started operating in 1990 and Essex does not believe there have been any releases to the LPRSA, but in any event believes any releases would have been de minimis considering the history of the LPRSA; however, it is not possible at this time to predict that outcome or to estimate the range of possible loss relating to Essex’s liability in the matter, including for LPRSA remedial costs and/or natural resource damages.

Other Commitments
Other commitments as of June 30, 2021 were as follows (in millions):
Letters of credit issued under the Revolving Credit Facility$229 
Letters of credit — other80 
Surety bonds137 
Total other commitments — net$446 

We issue letters of credit to secure our performance under various contractual undertakings related to our domestic and international projects or to secure obligations under our insurance programs. We believe that we will be able to fully perform under our contracts to which these existing letters of credit relate, and that it is unlikely that letters of credit would be drawn because of a default of our performance obligations. If any of these letters of credit were to be drawn by the beneficiary, the amount drawn would be immediately repayable by us to the issuing bank. If we do not immediately repay such amounts drawn under letters of credit issued under the Revolving Credit Facility, unreimbursed amounts would be treated under the Credit Facilities as either additional term loans or as revolving loans.

The surety bonds listed in the table above relate primarily to construction and performance obligations and support for other obligations, including closure requirements of various energy projects when such projects cease operating. Were these bonds to be drawn upon, we would have a contractual obligation to indemnify the surety company. The bonds do not have stated expiration dates. Rather, we are released from the bonds as the underlying performance is completed.

We have certain contingent obligations related to our Senior Notes and Tax-Exempt Bonds. Holders may require us to repurchase their Senior Notes and Tax-Exempt Bonds if a fundamental change occurs. Under the taxable note indentures, a Change of Control Offer to purchase the Bonds at a purchase price in cash equal to 101% of the principal amount of the Notes would need to be made if (a) a Change of Control (“CoC”) occurs and (b) the Notes are downgraded by either Rating Agency on any date during the period commencing 60 days prior to the consummation of such CoC and ending 60 days following consummation of such CoC. Under the tax-exempt indentures, a Change of Control Offer to purchase the Bonds at a purchase price in cash equal to 101% of the principal amount of the Notes would need to be made, if, inter alia, the long-term credit rating on the tax-exempt bonds is lower than the rating on the Bonds immediately prior to such transaction.
For specific criteria related to the redemption features of the Senior Notes and Tax-Exempt Bonds, see Item 8. Financial Statements And Supplementary Data — Note 16. Consolidated Debt of our 2020 Annual Report on Form 10-K.

We have issued or are party to guarantees and related contractual support obligations undertaken pursuant to agreements to construct and operate waste and energy facilities. For some projects, such performance guarantees include obligations to repay certain financial obligations if the project revenue is insufficient to do so, or to obtain or guarantee financing for a project. With respect to our businesses, we have issued guarantees to municipal clients and other parties that our subsidiaries will perform in accordance with contractual terms, including, where required, the payment of damages or other obligations. Additionally, damages payable under such guarantees for our WtE facilities could expose us to recourse liability on project debt. If we must perform under one or more of such guarantees, our liability for damages upon contract termination would be reduced by funds held in trust and proceeds from sales of the facilities securing the project debt and is presently not estimable. Depending upon the circumstances giving rise to such damages, the contractual terms of the applicable contracts, and the contract counterparty’s choice of remedy at the time a claim against a guarantee is made, the amounts owed pursuant to one or more of such guarantees could be greater than our then-available sources of funds. To date, we have not incurred material liabilities under such guarantees.

We have entered into certain guarantees of performance in connection with our recent divestiture activities. Under the terms of the arrangements, we guarantee performance should the guaranteed party fail to fulfill its obligations under the specified arrangements.