We and/or our subsidiaries are party to a number of claims, lawsuits and pending actions, most of which are routine and all of which are incidental to our business. We assess the likelihood of potential losses on an ongoing basis and when losses are considered probable and reasonably estimable, record as a loss an estimate of the outcome. If we can only estimate the range of a possible loss, an amount representing the low end of the range of possible outcomes is recorded. The final consequences of these proceedings are not presently determinable with certainty.
Environmental Matters
Our operations are subject to environmental regulatory laws and environmental remediation laws. Although our operations are occasionally subject to proceedings and orders pertaining to emissions into the environment and other environmental violations, which may result in fines, penalties, damages or other sanctions, we believe that we are in substantial compliance with existing environmental laws and regulations.
We may be identified, along with other entities, as being among parties potentially responsible for contribution to costs associated with the correction and remediation of environmental conditions at disposal sites subject to federal and/or analogous state laws. In certain instances, we may be exposed to joint and several liabilities for remedial action or damages. Our liability in connection with such environmental claims will depend on many factors, including our volumetric share of waste, the total cost of remediation, and the financial viability of other companies that also sent waste to a given site and, in the case of divested operations, the contractual arrangement with the purchaser of such operations.
The potential costs related to the matters described below and the possible impact on future operations are uncertain due in part to the complexity of governmental laws and regulations and their interpretations, the varying costs and effectiveness of cleanup technologies, the uncertain level of insurance or other types of recovery and the questionable level of our responsibility. Although the ultimate outcome and expense of any litigation, including environmental remediation, is uncertain, we believe that the following proceedings will not have a material adverse effect on our condensed consolidated financial position or results of operations.
Lower Passaic River Matter. In August 2004, the United States Environmental Protection Agency (the “EPA”) notified Covanta Essex Company (“Essex”) that it was a potentially responsible party (“PRP”) for Superfund response actions in the Lower Passaic River Study Area, referred to as “LPRSA,” a 17 mile stretch of river in northern New Jersey. Essex’s LPRSA costs to date are not material to its financial position and results of operations; however, to date the EPA has not sought any LPRSA remedial costs or natural resource damages against PRPs. On March 3, 2016, the EPA released the Record of Decision (“ROD”) for its Focused Feasibility Study of the lower 8 miles of the LPRSA; the EPA’s selected remedy includes capping/dredging of sediment, institutional controls and long-term monitoring. The Essex facility started operating in 1990 and Essex does not believe there have been any releases to the LPRSA, but in any event believes any releases would have been de minimis considering the history of the LPRSA; however, it is not possible at this time to predict that outcome or to estimate the range of possible loss relating to Essex’s liability in the matter, including for LPRSA remedial costs and/or natural resource damages.
North Carolina Transformer Site Matter. In December 2012, our subsidiary, Covanta Dade Power Corp. (“Dade”) received a letter from the EPA indicating Dade was named as a PRP, along with numerous other unidentified PRPs, relating to the cleanup of the Ward Transformer Superfund Site in Raleigh, North Carolina (“Ward Site”). Dade's alleged liability as a PRP stems from the 1994 servicing at the Ward Site of a transformer alleged to have contained PCB-contaminated oil. The EPA is seeking reimbursement from PRPs for its oversight costs in connection with ongoing cleanup activities at the Ward Site. While our investigation in this matter is continuing, based on information obtained to date, we believe Dade's responsibility, if any, in connection with this matter to be de minimis; and subject to indemnity by Veolia Environmental Services North America, LLC, from which we acquired Dade in 2010; however, it is not possible at this time to estimate the range of possible loss relating to Dade's ultimate liability, if any, in this matter.
Tulsa Matter. In January 2016, we were informed by the office of the United States Attorney for the Northern District of Oklahoma (“U.S. Attorney”) that our subsidiary, Covanta Tulsa Renewable Energy LLC, is the target of a criminal investigation being conducted by the EPA. We understand that the EPA plans to allege improprieties in the recording and reporting of emissions data during an October 2013 incident involving one of the three municipal waste combustion units at our Tulsa, Oklahoma facility.  We believe that our operations in Tulsa were and are in compliance with existing laws and regulations in all material respects.  While we can provide no assurance as to the outcome of this matter, we do not believe that the investigation or any issues arising therefrom will have a material adverse effect on our financial position or results of operations.
Other Matters
Other commitments as of March 31, 2016 were as follows (in millions):
 
 
Commitments Expiring by Period

 
Total
 
Less Than
One Year
 
More Than
One Year
Letters of credit issued under the Revolving Credit Facility
 
$
157

 
$
11

 
$
146

Letters of credit - other
 
66

 

 
66

Surety bonds
 
157

 

 
157

Total other commitments — net
 
$
380

 
$
11

 
$
369


The letters of credit were issued to secure our performance under various contractual undertakings related to our domestic and international projects or to secure obligations under our insurance program. Each letter of credit relating to a project is required to be maintained in effect for the period specified in related project contracts, and generally may be drawn if it is not renewed prior to expiration of that period.
We believe that we will be able to fully perform under our contracts to which these existing letters of credit relate, and that it is unlikely that letters of credit would be drawn because of a default of our performance obligations. If any of these letters of credit were to be drawn by the beneficiary, the amount drawn would be immediately repayable by us to the issuing bank. If we do not immediately repay such amounts drawn under letters of credit issued under the Revolving Credit Facility, unreimbursed amounts would be treated under the Credit Facilities as either additional term loans or as revolving loans.
The surety bonds listed in the table above relate primarily to construction and performance obligations and support for other obligations, including closure requirements of various energy projects when such projects cease operating. Were these bonds to be drawn upon, we would have a contractual obligation to indemnify the surety company. 
We have certain contingent obligations related to the 7.25% Notes, 6.375% Notes, 5.875% Notes, and Tax-Exempt Bonds. Holders may require us to repurchase their 7.25% Notes, 6.375% Notes, 5.875% Notes and Tax-Exempt Bonds if a fundamental change occurs. For specific criteria related to the redemption features of the 5.875% Notes, 7.25% Notes or 6.375% Notes, see Item 8. Financial Statements And Supplementary Data — Note 11. Consolidated Debt of our Annual Report on Form 10-K.
We have issued or are party to guarantees and related contractual support obligations undertaken pursuant to agreements to construct and operate waste and energy facilities. For some projects, such performance guarantees include obligations to repay certain financial obligations if the project revenue is insufficient to do so, or to obtain or guarantee financing for a project. With respect to our businesses, we have issued guarantees to municipal clients and other parties that our subsidiaries will perform in accordance with contractual terms, including, where required, the payment of damages or other obligations. Additionally, damages payable under such guarantees for our energy-from-waste facilities could expose us to recourse liability on project debt. If we must perform under one or more of such guarantees, our liability for damages upon contract termination would be reduced by funds held in trust and proceeds from sales of the facilities securing the project debt and is presently not estimable. Depending upon the circumstances giving rise to such damages, the contractual terms of the applicable contracts, and the contract counterparty’s choice of remedy at the time a claim against a guarantee is made, the amounts owed pursuant to one or more of such guarantees could be greater than our then-available sources of funds. To date, we have not incurred material liabilities under such guarantees.
Benefit Obligations - Defined Contribution Plans
Substantially all of our employees in the United States are eligible to participate in defined contribution plans we sponsor. Our costs related to defined contribution plans were $4 million for both the three months ended March 31, 2016 and 2015.
Dublin EfW Facility
In connection with the financing of the Dublin EfW facility, Covanta Energy has made commitments for contingent support as follows: (1) lending commitments up to €25 million to fund working capital shortfalls in the project company under certain circumstances during operations; and (2) up to €75 million commitment in the aggregate to provide support payments to the project company, under certain circumstances, in the event waste revenue falls below minimum levels (set far below anticipated levels).

Essex County EfW Facility
We are implementing significant operational improvements at our Essex County EfW facility at a total estimated cost of approximately $90 million. Construction commenced in 2014 and is expected to be completed in 2016. As of March 31, 2016, we have approximately $35 million of capital expenditures remaining to be incurred related to these improvements.
New York City Waste Transport and Disposal Contract
In 2013, New York City awarded us a contract to handle waste transport and disposal from two marine transfer stations located in Queens and Manhattan. Service for the Manhattan marine transfer station is expected pending approval from New York City. As of March 31, 2016, we expect to incur approximately $35 million of additional capital expenditures, primarily for transportation equipment.