XML 64 R49.htm IDEA: XBRL DOCUMENT v3.20.1
Regulatory Matters (Regulatory Matters Narrative - Duke Energy Progress) (Details) - Duke Energy Progress
customer in Thousands, $ in Millions
3 Months Ended
Jan. 29, 2020
USD ($)
MW
Oct. 30, 2019
USD ($)
May 21, 2019
USD ($)
Nov. 08, 2018
USD ($)
Nov. 22, 2017
Jun. 01, 2017
USD ($)
Mar. 31, 2020
USD ($)
Feb. 07, 2020
USD ($)
Dec. 31, 2019
USD ($)
Sep. 30, 2019
USD ($)
customer
Mar. 28, 2016
USD ($)
2017 North Carolina Rate Case | NCUC                      
Public Utilities, General Disclosures [Line Items]                      
Requested rate increase (decrease), amount           $ 477          
Requested rate increase, percentage           14.90%          
Requested rate increase (decrease), amended amount           $ 420          
Requested rate increase (decrease) amended, percentage           13.00%          
Requested return on equity, percent         9.90%            
Public utilities, requested equity capital structure, percentage         52.00%            
Public utilities, requested debt capital structure, percentage         48.00%            
2019 North Carolina Rate Case | NCUC                      
Public Utilities, General Disclosures [Line Items]                      
Requested rate increase (decrease), amount   $ 464                  
Requested rate increase, percentage   12.30%                  
Requested rate increase (decrease), gross amount   $ 586                  
Rider reduction   122                  
Requested rate increase (decrease), rider reduction   $ 120                  
Hurricane Dorian storm damage                      
Public Utilities, General Disclosures [Line Items]                      
Estimated storm costs - O&M                   $ 177  
Estimated storm costs - capital investments                   $ 4  
Storm deferral - O&M               $ 22      
South Carolina Rate Case 2018 | PSCSC                      
Public Utilities, General Disclosures [Line Items]                      
Requested rate increase (decrease), amount       $ 59              
Requested rate increase, percentage       10.30%              
Change in tax rate, deferred tax liability, income tax benefit     $ 17 $ 17              
Measurement period adjustment, income tax expense (benefit)     $ 12 10              
Approved return on equity percentage     9.50%                
Public utilities, approved equity capital structure, percentage     53.00%                
Public utilities, approved debt capital structure, percentage     47.00%                
Western Carolinas Modernization Plan | NCUC                      
Public Utilities, General Disclosures [Line Items]                      
Regulatory asset, amortization period             10 years        
Estimated capital cost                     $ 893
NORTH CAROLINA | Hurricane Dorian storm damage                      
Public Utilities, General Disclosures [Line Items]                      
Customers experiencing outages | customer                   270  
SOUTH CAROLINA | Hurricane Dorian storm damage                      
Public Utilities, General Disclosures [Line Items]                      
Customers experiencing outages | customer                   30  
Storm Costs [Member] | Hurricane Dorian storm damage                      
Public Utilities, General Disclosures [Line Items]                      
Regulatory assets             $ 151   $ 179    
Asset retirement obligations - coal ash | South Carolina Rate Case 2018 | PSCSC                      
Public Utilities, General Disclosures [Line Items]                      
Regulatory assets     $ 4 $ 51              
Recovery costs denied     $ 65                
Regulatory asset, amortization period     5 years 5 years              
Asset retirement obligations - unprotected EDIT, Property, Plant and Equipment | South Carolina Rate Case 2018 | PSCSC                      
Public Utilities, General Disclosures [Line Items]                      
Regulatory asset, amortization period     20 years                
Asset retirement obligations - unprotected EDIT | South Carolina Rate Case 2018 | PSCSC                      
Public Utilities, General Disclosures [Line Items]                      
Regulatory asset, amortization period     5 years                
Asset retirement obligations - deferred revenue | South Carolina Rate Case 2018 | PSCSC                      
Public Utilities, General Disclosures [Line Items]                      
Regulatory asset, amortization period     3 years                
State and local jurisdiction | North Carolina Department of Revenue | South Carolina Rate Case 2018 | PSCSC                      
Public Utilities, General Disclosures [Line Items]                      
State and local taxes reduction amount     $ (12) $ (12)              
Asheville Plant                      
Public Utilities, General Disclosures [Line Items]                      
Capacity (in MW) | MW 376                    
Generation facilities retired, net $ 214