Montana Rate Review

On July 10, 2024, we filed a Montana electric and natural gas rate review with the Montana Public Service Commission (MPSC). The filing requests a base rate annual revenue increase of $156.5 million ($69.4 million net with Property Tax and Power Cost and Credit Adjustment Mechanism (PCCAM) tracker adjustments) for electric and $28.6 million for natural gas. Our request is based on a return on equity of 10.80 percent with a capital structure including 46.81 percent equity, and forecasted 2024 electric and natural gas rate base of $3.45 billion and $731.9 million, respectively. The electric rate base investment includes the 175-megawatt natural gas-fired Yellowstone County Generating Station ("YCGS"), which is expected to be in service during the third quarter of 2024. We requested interim base rates to be effective October 1, 2024.

South Dakota Natural Gas Rate Review

On June 21, 2024, we filed a natural gas rate review (2023 test year) with the South Dakota Public Utilities Commission. The filing requests a base rate annual revenue increase of $6.0 million. Our request is based on a return on equity of 10.70 percent, a capital structure including 53.13 percent equity, and rate base of $95.6 million. If a final order is not received by December 21, 2024, interim base rates may go into effect.

Nebraska Natural Gas Rate Review

On June 6, 2024, we filed a natural gas rate review (2023 test year) with the Nebraska Public Service Commission. The filing requests a base rate annual revenue increase of $3.6 million. Our request is based on a return on equity of 10.70 percent, a capital structure including 53.13 percent equity, and rate base of $47.4 million. Interim base rates are not anticipated to be implemented prior to October 1, 2024.