Environmental Commitments and Contingencies
12 Months Ended
Dec. 31, 2016
Text Block [Abstract]  
Environmental Commitments and Contingencies
ENVIRONMENTAL COMMITMENTS AND CONTINGENCIES
We are subject to federal, state and local laws and regulations governing environmental quality and pollution control. These laws and regulations require us to remove or remediate at current and former operating sites the effect on the environment of the disposal or release of specified substances.

MGP Sites
We have participated in the investigation, assessment or remediation, and have exposures at seven former MGP sites. Those sites are located in Salisbury, Maryland, Seaford, Delaware and Winter Haven, Key West, Pensacola, Sanford and West Palm Beach, Florida. We have also been in discussions with the MDE regarding another former MGP site located in Cambridge, Maryland.
As of December 31, 2016, we had accrued approximately $9.8 million in environmental liabilities related to all of FPU’s MGP sites in Florida, which include the Key West, Pensacola, Sanford and West Palm Beach sites. FPU has approval to recover, from insurance and from customers through rates, up to $14.0 million of its environmental costs related to all of its MGP sites. Approximately $10.6 million of this amount has been recovered as of December 31, 2016, leaving approximately $3.4 million in regulatory assets for future recovery of environmental costs from FPU’s customers.
Environmental liabilities for all of our MGP sites are recorded on an undiscounted basis based on the estimate of future costs provided by independent consultants. We continue to expect that all costs related to environmental remediation and related activities, including any potential future remediation costs for which we do not currently have approval for regulatory recovery, will be recoverable from customers through rates.
West Palm Beach, Florida
Remedial options are being evaluated to respond to environmental impacts to soil and groundwater at and in the immediate vicinity of a parcel of property owned by FPU in West Palm Beach, Florida, where FPU previously operated a MGP. FPU is implementing a remedial plan approved by the FDEP for the east parcel of the West Palm Beach site, which includes installation of monitoring test wells, sparging of air into the groundwater system and extraction of vapors from the subsurface. On January 12, 2016, FDEP conducted a facility inspection and found no problems or deficiencies.
We expect that similar remedial actions will ultimately be implemented for other portions of the site. Estimated costs of remediation for the West Palm Beach site range from approximately $4.5 million to $15.4 million, including costs associated with the relocation of FPU’s operations at this site, which is necessary to implement the remedial plan, and any potential costs associated with future redevelopment of the properties.
Sanford, Florida
FPU is the current owner of property in Sanford, Florida, which was a former MGP site that was operated by several other entities before FPU acquired the property. FPU was never an owner or an operator of the MGP at this site. In January 2007, FPU and the Sanford Group signed a Third Participation Agreement, which provides for the funding of the final remedy approved by the EPA for the site. FPU’s share of remediation costs under the Third Participation Agreement is set at five percent of a maximum of $13.0 million, or $650,000. As of December 31, 2016, FPU has paid $650,000 to the Sanford Group escrow account for its entire share of the funding requirements.
In December 2014, the EPA issued a preliminary close-out report, documenting the completion of all physical remedial construction activities at the Sanford site. Groundwater monitoring and statutory five-year reviews to ensure performance of the approved remedy will continue on this site. The total cost of the final remedy is estimated to be over $20.0 million, which includes long-term monitoring and the settlement of claims asserted by two adjacent property owners to resolve damages that the property owners allege they have incurred and will incur as a result of the implementation of the EPA-approved remediation. In settlement of these claims, members of the Sanford Group, which in this instance does not include FPU, have agreed to pay specified sums of money to the parties. FPU has refused to participate in the funding of the third-party settlement agreements based on its contention that it did not contribute to the release of hazardous substances at the site giving rise to the third-party claims. FPU has advised the other members of the Sanford Group that it is unwilling at this time to agree to pay any sum in excess of the $650,000 committed and paid by FPU in the Third Participation Agreement. The Sanford Group has not requested that FPU contribute to costs beyond the originally agreed upon $650,000 contribution.
As of December 31, 2016, FPU’s remaining remediation expenses, including attorneys’ fees and costs, are estimated to be $24,000. However, we are unable to determine, to a reasonable degree of certainty, whether the other members of the Sanford Group will accept FPU’s asserted defense to liability for costs exceeding $13.0 million to implement the final remedy for this site, as provided in the Third Participation Agreement, or will pursue a claim against FPU for a sum in excess of the $650,000 that FPU has paid under the Third Participation Agreement. No such claims have been made as of December 31, 2016.
Winter Haven, Florida
The Winter Haven site is located on the eastern shoreline of Lake Shipp, in Winter Haven, Florida. Pursuant to a consent order entered into with FDEP, we are obligated to assess and remediate environmental impacts at this former MGP site. Groundwater monitoring results have shown a continuing reduction in contaminant concentrations from the sparging system, which has been in operation since 2002. On September 12, 2014, FDEP issued a letter approving shutdown of the sparging operations on the northern portion of the site, contingent upon continued semi-annual monitoring.
Groundwater monitoring results on the southern portion of this site indicated that natural attenuation default criteria continue to be exceeded. Plans to modify the monitoring network on the southern portion of the site in order to collect additional data to support the development of a remedial plan were specified in a letter sent to FDEP in October 2014. The well installation and abandonment program was implemented in October 2014, and documentation was reported in the next semi-annual RAP implementation status report, submitted in January 2015. FDEP approved the plan to expand the bio-sparging operations in the southern portion of the site, and additional sparge points were installed and connected to the operating system in the first quarter of 2016. Groundwater monitoring results from testing conducted in October 2016 indicated that natural attenuation default criteria were met at all wells.
We estimate that future remediation costs for the subsurface soils and groundwater at the site should not exceed $425,000, which includes an estimate of $100,000 to implement additional actions, such as institutional controls, at the site.
FDEP previously indicated that we could also be required to remediate sediments along the shoreline of Lake Shipp, immediately west of the site. Based on studies performed to date, and our recent meeting with FDEP, we believe that corrective measures for lake sediments are not warranted and will not be required by FDEP. We therefore have not recorded a liability for sediment remediation.
Seaford, Delaware
In December 2013, the DNREC notified us that it would be conducting a facility evaluation of a former MGP site in Seaford, Delaware. In a report issued in January 2015, DNREC provided the evaluation, which found several compounds within the groundwater and soil that required further investigation. In September 2015, DNREC approved our application to enter this site into the voluntary cleanup program. A remedial investigation was conducted in December 2015, which resulted in DNREC requesting additional investigative work be performed prior to approval of potential remedial actions.
In December 2016, additional on-site wells were installed, developed and sampled pursuant to a September 2016 request from DNREC. The results of the sampling event and proposed future activities are anticipated to be available by the end of the second quarter of 2017. We estimate the cost of potential remedial actions, based on the findings of the DNREC report, to be between $273,000 and $465,000.
Cambridge, Maryland
We are discussing with the MDE a former MGP site located in Cambridge, Maryland. The outcome of this matter cannot be determined at this time; therefore, we have not recorded an environmental liability for this location.
Ohio
We have also completed the investigation, assessment and remediation of eight natural gas pipeline facilities in Ohio that Aspire Energy acquired from Gatherco pursuant to the merger. Under the merger agreement, we are entitled to be indemnified from an escrow fund created at closing for certain matters, including certain claims related to environmental remediation. The costs incurred to date associated with remediation activities for these eight facilities is approximately $1.6 million. In September 2016, we and the Gatherco shareholder agent resolved certain disputes associated with our claims for indemnification, including claims for environmental matters. After deducting the amount of anticipated tax benefits related to our claims and an indemnification deductible in the amount of $431,250 in accordance with the merger agreement, we received approximately $500,000 from the indemnification escrow as final settlement of our claims related to these environmental matters.  We do not anticipate submitting any additional environmental claims for indemnification.