EX-99.1 2 ef20020154_ex99-1.htm EXHIBIT 99.1

 Exhibit 99.1


QUARTERLY ACTIVITIES REPORT
for the period ending 31 December 2023
 
Highlights
 

Permitting
 

o
Key milestone achieved with completion by BLM of the administrative draft EIS.
 

o
The draft EIS will be made available to the public once BLM management and cooperating agency reviews are complete.
 

o
Commencement of the 45-day public comment period expected this quarter (Q1 2024).
 

Project Advancement and Operational Readiness
 

o
Successful geotechnical drilling program completed on time and on budget.
 

o
Drilling program completes coverage of the southern and southeastern sections of the South Basin and provides valuable information for the NEPA evaluation that will also feed into the updated resource and quarry design.
 

o
Work continues on updates for resource/reserve, capital and operating cost estimates and financial model.
 

o
Engineering design now at a mature stage requiring only minimal spend ahead of FID and commencement of construction.
 

Growth Opportunities
 

o
Ioneer and Eco Pro expand existing partnership with MOU covering potential future development of the Rhyolite Ridge lithium clay resource (currently excluded from Project design and economics).
 
Tuesday, 30 January 2024 – Ioneer Ltd (“Ioneer” or “the Company”) (ASX: INR, Nasdaq: IONR), an emerging lithium-boron supplier, is pleased to report on its activities for the quarter ending 31 December 2023 and provide an update on the development of its 100%-owned Rhyolite Ridge Lithium-Boron Project in Esmeralda County, Nevada (“Rhyolite Ridge Project” or “the Project”).

Ioneer Managing Director, Bernard Rowe noted:

“Ioneer made considerable progress toward a Final Investment Decision and commencement of construction at Rhyolite Ridge this past quarter. We are financially well-positioned as we approach being fully permitted with conditional debt and equity commitments of nearly US$1.2 billion.
 
We have largely completed the capital-intensive heavy lifting work required to meet our commitments to Sibanye Stillwater (conditional equity) and the US Department of Energy (conditional debt) and make an informed FID decision later this year. We recently completed an extensive drilling campaign to gain the geotechnical and geological data required to finalize a long-life mine plan that avoids direct impact of Tiehm’s buckwheat.  We are working with Fluor and our other consultants to finish the Class II CAPEX and OPEX estimates, and requisite technical and financial reports required by Sibanye and the DOE.

ioneer Ltd. (ASX: INR)         Suite 16.01, 213 Miller Street, North Sydney, NSW 2060    T: +61 2 9922 5800    W: ioneer.com    ABN: 76 098 564 606

We are pleased to have completed the work to allow the BLM to complete and release the draft EIS for governmental review followed by public comment.”
 
We are excited to be the cornerstone, globally significant Tier 1 lithium project in the United States. We are confident that as the market recognises the continuing reduction in permitting risk as the project advances through the NEPA process, and the major advantages in producing refined lithium and boron chemicals in the United States, compared to spodumene concentrate producers dependent upon Chinese converters, ioneer’s Rhyolite Ridge will be seen as the unique global asset we are confident it is.

 Executive Chairman, James Calaway concluded:
 
“2024 promises to be a momentous year for Ioneer, including the expected conclusion of the federal permitting process and the commencement of construction at Rhyolite Ridge.
 
We look forward to delivering these critical and valuable materials and strengthening domestic EV supply chains.”

Rhyolite Ridge Permitting
 
National Environmental Policy Act (NEPA) Permitting Process
 
A major milestone was reached in mid-January with completion of the administrative draft Environmental Impact Statement (ADEIS).  The Draft EIS will be made public upon completion of review by BLM management and cooperating agencies.  This review is expected to be completed during February and the draft EIS to be published in the Federal Register later in Q1.
 
Ioneer continues to work closely with the U.S. Bureau of Land Management (BLM) and U.S. Fish and Wildlife Service (FWS) to keep both the NEPA and the Section 7 Endangered Species Act (ESA) processes progressing in parallel.  Ioneer is confident the process can be completed in a timely fashion given the amount of preparation and cooperation that has taken place over the past several years.

Construction Water Rights
 
Ioneer’s Construction Water Rights Application Package was approved by the Nevada Department of Water Resources (NDWR) on 15 December 2023.  This approved water right allows Ioneer the ability to pump 474-acre feet per year through the construction period and will also be used to supplement operational water needs once operations commence.  We are pleased to have worked with community members and state officials to complete this process in a timely manner.
Project Advancement and Operational Readiness
 
Focus areas for Project advancement during Q3 have been:
 

Geotechnical drilling (complete)
 

Updated geological model
 

Updated resource/reserves including SK1300 technical report
 

Updated capex/opex estimates
 

Construction strategy and schedule

In November, Ioneer received its third drilling program approval from the BLM to collect additional geotechnical data to support the NEPA analysis of the Mine Plan of Operations.

The drilling targeted the proposed quarry wall locations on the southwestern, southern, and southeastern margins of the deposit.  The drilling was completed in mid-January 2024 and the data is being integrated into geological, geotechnical as resource models.
 
p.2
ioneer Ltd. (ASX: INR)         Suite 16.01, 213 Miller Street, North Sydney, NSW 2060    T: +61 2 9922 5800    W: ioneer.com    ABN: 76 098 564 606

Ioneer also completed development of a 3D magnetic susceptibility model and 3D gravity density-contrast model for the South Basin which was subsequently used in the design of the drill program.

Engineering design is now at a maturity that requires only minimal spend ahead of Final Investment Decision (FID) and commencement of construction. An updated Reliability, Availability, and Maintainability (RAM) analysis was issued following vendors’ engineering updates.

Sales & Marketing
 
Lithium Market and Price
 
Lithium demand from cathode showed a marginal increase this month and improved by 19% year-on-year.  Demand from cathode chemistries rose 4% month-on-month driven by growth in LFP and high-nickel cathode demand.  Overall, demand is forecast to grow 16% annually to 2027.

In the medium term, we expect supply growth to be strong with a compound annual growth rate of ~25% between 2023 to 2027.  Robust growth will come from both spodumene concentrate and lepidolite, but other raw materials and recycling will also contribute towards the strong growth.  According to Benchmark Minerals, the lithium market is expected to be in deficit from 2029 onwards, based on the current project pipeline.

Prices for lithium chemicals and spodumene concentrate continue to decline.  The drop is being facilitated by increased supply and supply chain destocking even though demand is still relatively strong.  We expect prices for spodumene concentrate will be more closely correlated with those of lithium chemicals and less dependent on supply and demand dynamics going forward.
Electric vehicle sales growth slowed in 2023, largely due to lower growth in China.  This was largely due to China’s EV purchase subsidy coming to an end, together with a slowdown in the wider Chinese economy.  There is also a natural drop-off in growth rates as EV adoption rises.

Despite this slow down, according to Wood Mackenzie, global BEV and PHEV sales increased 13% year-on-year in November.

Boric Acid Market and Price
 
Global boric acid demand and supply levels are balanced with prices remaining well above pre-COVID levels and steady during Q4 versus Q3 2023.  The sodium borate market is in slight oversupply creating downward price pressure; however, prices are holding Q3 levels and remain well above pre-COVID levels.  Demand from the consumer electronic market continues to be depressed.

These conditions do not change Rhyolite Ridge’s unique economics or pose any material business risks in the coming years. All current pricing is in excess of boric acid prices assumed in the DFS economic model. Boric acid accounts for approximately one-third of the revenue the project will generate (with two-thirds coming from lithium carbonate).

ESG/EHS Program
 
ISO 14001 Implementation
 
The Company is working on incorporating aspects and impacts of the ISO 14001 system into the company risk registers as discussed last quarter.

Sustainability Road Mapping /External Disclosure Alignment
 
Ioneer has completed reporting and/or report feedback to ISS-ESG, Sustainalytics, and S&P to demonstrate transparency in our sustainability practices.  This work has already delivered a marked improvement in our ESG risk ratings.

We anticipate continued improvements in our ESG risk rating scores due to our ongoing commitment and implementation of a comprehensive ESG strategy, which includes sustainable practices, responsible governance, community engagement.
 
p.3
ioneer Ltd. (ASX: INR)         Suite 16.01, 213 Miller Street, North Sydney, NSW 2060    T: +61 2 9922 5800    W: ioneer.com    ABN: 76 098 564 606

Ioneer developed a three-year Sustainability Plan which was approved by the Board Committee in November 2023.  The Plan reflects a concerted effort to establish long-term sustainability goals and strategies.

Ioneer is participating in the International Lithium Association’s working group to standardize life cycle analysis for carbon across the various extraction methods including sedimentary, spodumene, and brines.

Towards Sustainable Mining (TSM) Implementation
 
Work is ongoing to develop document registers for the TSM Action Plans and to complete self-assessments to gauge readiness of the programs for a TSM audit.

Environmental Regulatory Compliance
 
Ioneer continues to maintain compliance with the issued State of Nevada Water pollution Control and Class II Air Permits.  No compliance issues were noted during the quarter and ioneer continues to report ongoing monitoring and compliance related activities as required under these obligations.

Health & Safety
 
During the quarter, no lost time incidents, first aid incidents, or fatalities were reported for Ioneer staff.  However, two drilling contractors were involved in a driving accident resulting in property damage.

Ioneer has worked on the following H&S activities this quarter:
 

1.
Bloodborne Pathogens Training
 

2.
Safety Culture Training
 

3.
Workplace Violence Training
 

4.
MSHA/OSHA Program & Training Development


1 See ASX announcement titled “Mineral Resource increases by 168% to 3.4 Mt lithium carbonate - Underscores growth potential for U.S. supply chain” dated 26 April 2023.
Tiehm’s Buckwheat Conservation Center Propagation
 
Ioneer marked the close of a successful year at the Tiehm’s Buckwheat Conservation Center, which opened in May 2023.  Ioneer’s full-time botanist concluded seed cleaning efforts yielding a total of 3,600 seeds from the plants at the greenhouse.  These seeds are currently under refrigeration until their designated germination period (March –April 2024).

In addition, we worked with the Rae Selling Berry Seed Bank to complete its seed collection work at Rhyolite Ridge, with a total of 8,000 seeds collected.

We anticipate further increasing the overall number of plants housed in the greenhouse for the coming year due to higher seed production success in 2023.

In 2024, Ioneer hopes to raise the germination rate due to improved conditions resulting from the greenhouse construction and the wet winter at Rhyolite Ridge in 2023.

Organic Growth Projects
 
Ioneer continues to evaluate future growth potential at the Rhyolite Ridge project with concept-level studies of both the South Basin, where mine permitting is in progress, and the North Basin (located 5km north), which is at a pre-resource stage.

The Rhyolite Ridge deposit hosts three main types of mineralisation, however, only one of these (high-boron) is included in the current project design and DFS economics.

The three distinct styles of mineralisation are described in the April 2023 Mineral Resource Estimate (MRE)1. They are:
 

Type 1 Mineralisation: Lithium with high boron and low clay content
 152Mt Mineral Resource containing 1.2Mt of lithium carbonate equivalent (LCE).
 
p.4
ioneer Ltd. (ASX: INR)         Suite 16.01, 213 Miller Street, North Sydney, NSW 2060    T: +61 2 9922 5800    W: ioneer.com    ABN: 76 098 564 606


Type 2 Mineralisation: Lithium with high clay content
75Mt Mineral Resource containing 1.0Mt of LCE.
 

Type 3 Mineralisation: Lithium with low boron and low clay content
128Mt Mineral Resource containing 1.1Mt of LCE.
 
On 31 October 2023 Ioneer announced a Research and Development (“R&D”) Memorandum of Understanding (“MOU”) with EcoPro Innovation Co Ltd (“EcoPro”), a global leader in battery grade high purity lithium hydroxide conversion.

Under the MOU, EcoPro will conduct research and development on the lithium clay resource.  The lithium-clay type mineralisation is currently excluded from the project design and economics.  The goal is to develop a process to commercialise Rhyolite Ridge lithium clay to produce refined lithium materials for the U.S. EV battery supply chain.

EcoPro will endeavour to develop a commercially feasible process for the extraction of lithium from lithium clays at Rhyolite Ridge considering location constraints provided by Ioneer.  If a commercially feasible process is developed by EcoPro, EcoPro intends to develop a commercial-scale refining plant to process lithium clay supplied from Rhyolite Ridge and produce Battery Grade Lithium Hydroxide (the "Product").  Subject to Ioneer's financing and contractual arrangements the lithium clay raw material would be supplied at no cost by Ioneer to EcoPro, but the profits referable to the sale of the Product produced by the commercial scale refining plant will be equally shared between EcoPro and Ioneer based on an index price formula to be agreed, less costs.


2 A conditional commitment is offered by DOE prior to issuing a loan and indicates that DOE expects to support the Rhyolite Ridge Project, subject to the satisfaction of certain conditions including fulfilling remaining legal, contractual, and financial requirements.
The R&D project will be managed by a jointly developed Project Committee, which will meet quarterly to evaluate progress of the project and to determine in good faith if progress justifies continuation of the agreement.

North Basin Growth Project
 
The North Basin is located 5km north of the South Basin.  No work was undertaken at North Basin during the quarter.
 
Project Debt Funding
 
The end of 2023 allowed Ioneer to reflect on its
important conditional financing commitment that began the year. Following 18 months of work and a rigorous application process, the U.S. Department of Energy Loan Programs Office (DOE LPO)2 and Ioneer announced finalisation of a term sheet and offer of a Conditional Commitment for a loan from the DOE for financing the construction of the Rhyolite Ridge processing facility.

Under the term sheet, the proposed loan is up to US$700 million3 with a term of approximately 10 years. The loan will be at interest rates fixed from the date of each advance for the term of the loan at applicable U.S. Treasury rates.

The proposed loan amount remains subject to negotiation and documentation of long-form agreements and various conditions and may be subsequently revised to appropriately match updated project economics leading up to financial close and upon satisfaction of several conditions outlined in the market release4.

During the quarter, Ioneer continued to work to progress satisfaction of conditions for the DOE loan.

3 Excludes estimated capitalised interest costs. Approximately US$700 million in advances from DOE loan is proposed to be available to fund eligible costs of the Rhyolite Ridge Project including reserve accounts.
4 See ASX release dated 16 January 2023 titled, “US Dept of Energy Loan Offer of US$700m for Rhyolite Ridge.”


 


































 

p.5
ioneer Ltd. (ASX: INR)         Suite 16.01, 213 Miller Street, North Sydney, NSW 2060    T: +61 2 9922 5800    W: ioneer.com    ABN: 76 098 564 606

Upcoming Work Program

The work program over the coming months includes:
 

Advancing federal permitting through participation in the NEPA process in concurrence with the Section 7 ESA Consultation.
 

Preparing for the DEIS public comments.
 

Updated resource/reserve estimate including SK1300 technical report
 

Updated Class II capex and opex estimates
 

Continuing to close CP’s required for Sibanye’s FID and the DOE loan
 

Evaluation of growth opportunities including leach testwork on low-boron non-clay mineralisation.
 
Estimated Project Timeline
 
Our current best estimate for timing of key milestones is as follows:

 
Milestone
 
Targeted timing5
 
Anticipated ROD
 
3Q 2024
 
Construction Period
 
24 Months
 
First Production
 
2026

Corporate Activities
 
The Annual General Meeting was held on Friday, 3 November 2023. Shareholders were able to attend either in person or virtually.  All resolutions were carried without amendment.

During the quarter, Ioneer participated in several industry and investor events, including:
 

LME Week, 9-12 October.
 

IMARC conference 2023, 31 October – 2 November.
 

Bell Potter non-deal roadshow with institutional investors in Sydney, 23 November.
 

5 Note: all dates are estimates only and are subject to change.

Canaccord Genuity non-deal roadshow with institutional investors in Sydney, 6 November & New York 6 December.

ASX Additional Information
 
The Company provides the following information pursuant to ASX Listing Rule requirements.


1.
ASX LR 5.3.1: Exploration and Evaluation Expenditure during the quarter was US$8.2 million. Details of the exploration activity are set out in this report. A breakdown of the expenditure is shown below:

 
Expenditure
US$’000
 
 
Exploration
-
 
 
Engineering
5,322
 
 
Environmental
1,662
 
 
Sales & Marketing
160
 
 
Other
1,026
 
 
Total
8,171
 


2.
ASX LR 5.3.2: The Company confirms there were no production or development activities during the quarter.


3.
ASX LR 5.3.5: Related party payments for the quarter totalled US$272,000, comprising salaries and fees for the Company’s executive and non-executive directors. No other payments were made to any related parties of the entity or their associates.


4.
ASX LR 5.3.3: INR confirms that it has not acquired tenements during the quarter (see appendix 1).


























 


























p.6
ioneer Ltd. (ASX: INR)         Suite 16.01, 213 Miller Street, North Sydney, NSW 2060    T: +61 2 9922 5800    W: ioneer.com    ABN: 76 098 564 606

Capital Structure
 
Total cash and cash equivalents as of 31 December 2023 was US$28.0 million of which 60.9% was held in USD with the balance held in AUD.  There was a planned significant reduction in Exploration and Evaluation expenditure compared to the previous quarter (US$8.2 million this quarter compared to US$16.3 million in the September quarter).  This planned reduction reflects the maturity of the project particularly around engineering and mine design.  Further reductions in expenditure are anticipated in the March quarter as geotechnical drilling was completed in January 2024.
At the end of the quarter, Ioneer had on issue:


2.1 billion ordinary shares
 

2.9 million options, and
 

34.5 million performance rights.

This ASX release has been authorised by Ioneer Managing Director, Bernard Rowe.

--ENDS--

Media Contact
 
Chad Yeftich
Ioneer USA Corporation
Ian Bucknell
Ioneer Limited
Investor Relations (USA)
Investor Relations (AUS)
T: +1 775 993 8563
T: +61 434 567 155
E: ir@ioneer.com
E: ibucknell@ioneer.com

About Ioneer
 
Ioneer Ltd is an emerging lithium–boron producer and the 100% owner of the Rhyolite Ridge Lithium-Boron Project located in Nevada, USA. Rhyolite Ridge is the only known lithium-boron deposit in North America and one of only two known such deposits in the world. Once operational, the low-cost, world-class project is expected to power upward of 50 million electric vehicles and will instantly become a globally significant source of critical materials vital to the clean energy transition.

Upon anticipated completion of the U.S. federal permitting process, construction at Rhyolite Ridge, largely funded through the combination of $490 million USD in equity from Sibanye-Stillwater and a $700 million USD in debt from the U.S. Department of Energy’s Loan Programs Office, will begin in 2024. Production and on-site processing are expected to follow in 2026.

To date, Ioneer has major offtake agreements with Ford Motor Company, Prime Planet Energy & Solutions (PPES), a joint venture between Toyota Motor Company and Panasonic, and EcoPro Innovation.

p.7
ioneer Ltd. (ASX: INR)         Suite 16.01, 213 Miller Street, North Sydney, NSW 2060    T: +61 2 9922 5800    W: ioneer.com    ABN: 76 098 564 606

Recent Announcements
 
The table below lists announcements made by the Company during the quarter.
 
Date Released
 
Title
03/10/2023
 
Notification regarding unquoted securities - INR
03/10/2023
 
Application for quotation of securities - INR
30/10/2023
 
September 2023 – Quarterly Activities Report
30/10/2023
 
September 2023 – Quarterly Cash Flow Report
31/10/2023
 
Investor Presentation – IMARC Conference
01/11/2023
 
Partnership with EcoPro to bolster U.S. lithium production
02/11/2023
 
Expanded EcoPro partnership _ Further details
03/11/2023
 
2023 AGM – Chairman’s Address
03/11/2023
 
2023 AGM – Managing Director Presentation
03/11/2023
 
2023 AGM – Results of Meeting
13/11/2023
 
Application for quotation of securities - INR
13/11/2023
 
Notification of cessation of securities - INR
13/11/2023
 
Proposed issue of securities - INR
14/11/2023
 
Notification regarding unquoted securities - INR
14/11/2023
 
Notification regarding unquoted securities - INR
14/11/2023
 
Change of Director’s Interest Notice – Bernard Rowe
14/11/2023
 
Change of Director’s Interest Notice – Alan Davies
14/11/2023
 
Change of Director’s Interest Notice – James Calaway
14/11/2023
 
Change of Director’s Interest Notice – Margaret Walker
14/11/2023
 
Change of Director’s Interest Notice – Rose McKinney-James
14/11/2023
 
Change of Director’s Interest Notice – Stephen Gardiner
15/11/2023
 
Notification of cessation of securities - INR
20/11/2023
 
Response to ASX Query Letter
08/12/2023
 
Change of Director’s Interest Notice – Alan Davies
 
p.8
ioneer Ltd. (ASX: INR)         Suite 16.01, 213 Miller Street, North Sydney, NSW 2060    T: +61 2 9922 5800    W: ioneer.com    ABN: 76 098 564 606

Appendix 1 - Schedule of Tenements
 
ASX listing rule 5.3.3

 
Country
 
Project
 
Tenement ID
 
Tenement Name
 
Area
(km2)
 
Interest at beginning of
quarter
 
Interest at end of quarter
 
Note
 
USA
 
Rhyolite Ridge
 
NMC1118666
 
NLB claims (160)
 
13
 
100%
 
100%
 
No change
 
USA
 
Rhyolite Ridge
 
NV106310781
 
NLB claims (41)
 
1.2
 
100%
 
100%
 
No change
 
USA
 
Rhyolite Ridge
 
NMC1117360
 
SLB claims (199)
 
16.5
 
100%
 
100%
 
No change
 
USA
 
Rhyolite Ridge
 
NMC1117360
 
SLB claims (18)
 
1.5
 
100%
 
100%
 
No change
 
USA
 
Rhyolite Ridge
 
NMC1171536
 
SLM claims (122)
 
9.7
 
100%
 
100%
 
No change
 
USA
 
Rhyolite Ridge
 
NMC 1179516
 
RR claims (65)
 
5.4
 
100%
 
100%
 
No change
 
USA
 
Rhyolite Ridge
 
NMC 1179516
 
RR claims (14)
 
1.1
 
100%
 
100%
 
No change
 
USA
 
Rhyolite Ridge
 
NMC 1129523
 
BH claims (81)
 
7
 
100%
 
100%
 
No change
 
USA
 
Rhyolite Ridge
 
NV105272779
 
RMS claims (23)
 
0.5
 
100%
 
100%
 
No change
 
USA
 
Rhyolite Ridge
 
NMC1147932
 
SLP claims (120)
 
9.7
 
100%
 
100%
 
No change
 
USA
 
Rhyolite Ridge
 
NV105272053
 
PR claims (11)
 
0.9
 
100%
 
100%
 
No change
 
USA
 
SM
 
NMC1166813
 
SM claims (96)
 
7.7
 
100%
 
100%
 
No change
 
USA
 
GD
 
NMC1166909
 
GD claims (13)
 
1.1
 
100%
 
100%
 
No change
 
USA
 
CLD
 
NMC1167799
 
CLD claims (65)
 
5.2
 
100%
 
100%
 
No change

On 16 September 2021, the Company announced a strategic investment by Sibanye-Stillwater6 in the Rhyolite Ridge Project. Under the terms of the agreement, Sibanye-Stillwater will contribute US$490 million for a 50% interest in the Joint Venture, with Ioneer to maintain a 50% interest and retain operatorship. Ioneer has also agreed to provide Sibanye-Stillwater with an option to participate in 50% of the North Basin, upon the election of Sibanye-Stillwater to contribute up to an additional US$50 million, subject to certain terms and conditions. Establishment of the Joint Venture and Sibanye-Stillwater’s funding commitment is subject to certain terms and conditions precedent, including receipt of final permits, commitments for remaining debt financing, and other customary approvals.


6 Refer ASX release titles ‘Sibanye-Stillwater to invest US$490M in Rhyolite Ridge’ announced on 16 September 2021.

p.9
ioneer Ltd. (ASX: INR)         Suite 16.01, 213 Miller Street, North Sydney, NSW 2060    T: +61 2 9922 5800    W: ioneer.com    ABN: 76 098 564 606


Rule 5.5

Appendix 5B
 
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
 
Name of entity
ioneer Ltd
ABN
Quarter ended (“current quarter”)
76 098 564 606
December 2023
 
Consolidated statement of cash flows
Current quarter
$US’000
Year to date
(6 months)
$US’000
1.
Cash flows from operating activities
-
-
1.1
Receipts from customers
1.2
Payments for
-
-
 
(a)
exploration & evaluation (if expensed)
 
(b)
development
-
-
 
(c)
production
-
-
 
(d)
staff costs
(1,627)
(1,737)
 
(e)
administration and corporate costs
(813)
(3,593)
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
358
883
1.5
Interest and other costs of finance paid
-
-
1.6
Income taxes paid
   
1.7
Government grants and tax incentives
-
-
1.8
Other (provide details if material)
-
-
1.9
Net cash from / (used in) operating activities
(2,082)
(4,447)
 
2.
Cash flows from investing activities
-
-
2.1
Payments to acquire:
 
(a)
entities
 
(b)
tenements
-
-
 
(c)
property, plant and equipment
(3)
(3)
 
(d)
exploration & evaluation (if capitalised)
(8,417)
(21,871)
 
(e)
investments
-
-
 
(f)
other non-current assets
-
-

ASX Listing Rules Appendix 5B (01/12/19)
Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.


Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
Current quarter
$US’000
Year to date
(6 months)
$US’000
2.2
Proceeds from the disposal of:
-
-
 
(a)
entities
 
(b)
tenements
-
-
 
(c)
property, plant and equipment
-
-
 
(d)
investments
-
-
 
(e)
other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
-
2.6
Net cash from / (used in) investing activities
(8,420)
(21,874)
 
3.
Cash flows from financing activities
-
-
3.1
Proceeds from issues of equity securities (excluding convertible debt securities)
3.2
Proceeds from issue of convertible debt securities
-
-
3.3
Proceeds from exercise of options
-
54
3.4
Transaction costs related to issues of equity securities or convertible debt securities
-
(9)
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
-
-
3.7
Transaction costs related to loans and borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
(29)
(65)
3.10
Net cash from / (used in) financing activities
(29)
(20)
 
4.
Net increase / (decrease) in cash and cash equivalents for the period
   
4.1
Cash and cash equivalents at beginning of period
36,536
52,709
4.2
Net cash from / (used in) operating activities (item 1.9 above)
(2,082)
(4,447)
4.3
Net cash from / (used in) investing activities (item 2.6 above)
(8,420)
(21,874)
4.4
Net cash from / (used in) financing activities (item 3.10 above)
(29)
(20)

ASX Listing Rules Appendix 5B (01/12/19)
Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.


Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
Current quarter
$US’000
Year to date
(6 months)
$US’000
4.5
Effect of movement in exchange rates on cash held
1,983
1,620
4.6
Cash and cash equivalents at end of period
27,988
27,988

5.
Reconciliation of cash and cash equivalents
at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accounts
Current quarter
$US’000
Previous quarter
$US’000
5.1
Bank balances
12,466
14,253
5.2
Call deposits
15,522
22,283
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
   
5.5
Cash and cash equivalents at end of quarter (should equal item 4.6 above)
27,988
36,536

6.
Payments to related parties of the entity and their associates
Current quarter
$US'000
6.1
Aggregate amount of payments to related parties and their associates included in item 1
272
6.2
Aggregate amount of payments to related parties and their associates included in item 2
 
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an explanation for, such payments

Directors’ fees – 97.5
Executive salary component of chairman’s fee – 78
Wages – 96.3

ASX Listing Rules Appendix 5B (01/12/19)
Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.


Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of financing arrangements available to the entity.
Add notes as necessary for an understanding of the sources of finance available to the entity.
Total facility
amount at quarter
end
$US’000
Amount drawn at
quarter end
$US’000
7.1
Loan facilities
-
-
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
     
7.5
Unused financing facilities available at quarter end
-
7.6
Include in the box below a description of each facility above, including the lender, interest rate, maturity date and whether it is secured or unsecured. If any additional financing facilities have been entered into or are proposed to be entered into after quarter end, include a note providing details of those facilities as well.
 
8.
Estimated cash available for future operating activities
$US’000
8.1
Net cash from / (used in) operating activities (Item 1.9)
(2,082)
8.2
Capitalised exploration & evaluation (Item 2.1(d))
(8,417)
8.3
Total relevant outgoings (Item 8.1 + Item 8.2)
(10,499)
8.4
Cash and cash equivalents at quarter end (Item 4.6)
27,988
8.5
Unused finance facilities available at quarter end (Item 7.5)
-
8.6
Total available funding (Item 8.4 + Item 8.5)
27,988
8.7
Estimated quarters of funding available (Item 8.6 divided by Item 8.3)
2.7
8.8
If Item 8.7 is less than 2 quarters, please provide answers to the following questions:
 
1.
Does the entity expect that it will continue to have the current level of net operating cash flows for the time being and, if not, why not?
 
Answer: N/A
   
 
2.
Has the entity taken any steps, or does it propose to take any steps, to raise further cash to fund its operations and, if so, what are those steps and how likely does it believe that they will be successful?
 
Answer: N/A
   
 
3.
Does the entity expect to be able to continue its operations and to meet its business objectives and, if so, on what basis?
 
Answer: N/A

ASX Listing Rules Appendix 5B (01/12/19)
Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.


Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Compliance statement
 
1
This statement has been prepared in accordance with accounting standards and policies which comply with Listing Rule 19.11A.
 
2
This statement gives a true and fair view of the matters disclosed.
 

30 January 2024
Date:


 

Bernard Rowe – Managing Director

Authorised by:

   (Name of body or officer authorising release – see note 4)  
 
Notes
 
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is encouraged to do so.
 
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
 
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on the accounting policy of the entity.
 
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”. If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the [name of board committeeeg Audit and Risk Committee]”. If it has been authorised for release to the market by a disclosure committee, you can insert here: “By the Disclosure Committee”.
 
5.
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial records of the entity have been properly maintained, that this report complies with the appropriate accounting standards and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a sound system of risk management and internal control which is operating effectively.
 

ASX Listing Rules Appendix 5B (01/12/19)
Page 5
+ See chapter 19 of the ASX Listing Rules for defined terms.