Note 10 - Commitments and Contingencies
As of June 30, 2024, there were no commitment
and contingency other than those stated below:
| | | | June 30, | | Commitments and Contingencies | | Terms | | 2024 | | Rental of premises | | Rental expense from July 2024 to January 2025 | | $ | 75 | | Electrical installation for HL wire & cable in Kampung Baru Subang factory | | 60% upon installation | | | 13 | | Installation of New Cooling Tower in Kampung Baru Subang factory | | 30% upon piping work, 20% upon installation and 10% after 3 months warranty | | | 15 | | Rental of factory | | Rental expense for July 2024 | | | 4 | | | | | | $ | 107 | |
|