EX-96.1 14 tm2324688d1_ex96-1.htm EXHIBIT 96.1

Exhibit 96.1

 

 

REPORT DATE: 6 SEPTEMBER 2023

 

 

SEC Technical Report Summary – Santa CruzPage ii

 

Date and Signature Page

 

S-K 1300 Initial Assessment & Technical Report Summary, Santa Cruz Project, Arizona

 

Prepared for: Ivanhoe Electric Inc.

 

Report Date: September 6, 2023

 

Prepared by the following Qualified Persons:

 

/s/ SRK Consulting (U.S.), Inc.

 

SRK Consulting (U.S.), Inc.

September 6, 2023

 

/s/ KCB Consultants Ltd.

 

KCB Consultants Ltd.

September 6, 2023

 

/s/ Life Cycle Geo, LLC

 

Life Cycle Geo, LLC

September 6, 2023

 

/s/ M3 Engineering and Technology Corp.

 

M3 Engineering and Technology Corp.

September 6, 2023

 

/s/ Nordmin Engineering Ltd.

 

Nordmin Engineering Ltd.

September 6, 2023

 

/s/ Call & Nicholas, Inc.

 

Call & Nicholas, Inc.

September 6, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage iii

 

/s/ Tetra Tech, Inc.

 

Tetra Tech, Inc.

September 6, 2023

 

/s/ INTERA Incorporated

 

INTERA Incorporated

September 6, 2023

 

/s/ Haley & Aldrich, Inc.

 

Haley & Aldrich, Inc.

September 6, 2023

 

/s/ Met Engineering, LLC

 

Met Engineering, LLC

September 6, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage iv

 

Table of Contents

 

 

1 Executive Summary 28
  1.1 Property Description, Mineral Tenure, Ownership, Surface Rights, Royalties, Agreements, and Permits 28
  1.2 Geology and Mineralization 29
  1.3 Status of Exploration, Development and Operations 30
  1.4 Sample Analysis and Security 30
  1.5 Mineral Processing and Metallurgical Testing 31
  1.6 Mineral Resource Estimate 32
  1.7 Mineral Reserve Estimate 35
  1.8 Mining Methods 35
  1.9 Recovery Methods 37
  1.9.1 Process Design Criteria 39
  1.10 Project Infrastructure 39
  1.11 Market Studies and Contracts 40
  1.12 Environmental, Closure and Permitting 41
  1.13 Capital and Operating Cost Estimates 41
  1.13.1 Mining Capital Cost Estimate 41
  1.13.2 Process Capital Cost Estimate 42
  1.13.3 Tailings Capital Cost Estimate 43
  1.13.4 Mining Operating Cost Estimate 43
  1.13.5 Processing Operating Cost Estimate 44
  1.13.6 G&A Operating Cost Estimate 44
  1.14 Economic Analysis 44
  1.15 Conclusions and Recommendations 48
2 Introduction 51
2.1 Registrant for Whom the Technical Report Summary was Prepared 51
  2.2 Terms of Reference and Purpose of the Report 51
  2.3 Sources of Information 51
  2.4 Details of Inspection 51
  2.5 Report Version Update 52
  2.6 Units of Measure 52
  2.7 Mineral Resource and Mineral Reserve Definitions 53
  2.8 Qualified Person 54
3 Property Description 57
  3.1 Legal Description of Real Property 57
  3.2 Property Location 57
  3.3 Mineral Title, Claim, Mineral Right, Lease or Option Disclosure 58
  3.3.1 Land Tenure and Underlying Agreements 58

  

September 2023

SEC Technical Report Summary – Santa CruzPage v

 

  3.3.2 Private Parcels 58
  3.3.3 Federal Unpatented Mineral Claims 61
  3.3.4 Royalties 61
  3.4 Permits and Authorization 62
  3.5 Environmental Liabilities 63
4 Accessibility, Climate, Local Resources, Infrastructure and Physiography 65
  4.1 Climate 65
  4.2 Local Resources 66
  4.3 Physiography 67
5 History 68
  5.1 Introduction 68
  5.2 Previous Exploration 70
  5.2.1 Sacaton Mine 70
  5.2.2 Santa Cruz and Texaco Deposits 70
  5.3 Previous Reporting 73
  5.3.1 Hanna 1982 73
  5.3.2 In Situ Joint Venture 1997 73
  5.3.3 IMC 2013 73
  5.3.4 Stantec-Mining 2013 74
  5.3.5 Physical Resource Engineering 2014 74
  5.4 Ivanhoe Electric Technical Report Summaries 74
  5.4.1 Mineral Resource Estimate 2021 74
  5.4.2 Mineral Resource Estimate Update 2022 74
  5.5 Historical Production 75
  5.6 QP Opinion 75
6 Geological Setting, Mineralization, and Deposit 76
  6.1 Regional Geology 76
  6.2 Metallogenic Setting 77
  6.3 Santa Cruz Project Geology 77
  6.3.1 Santa Cruz Project Lithologies 78
  6.3.2 Alteration 81
  6.3.3 Structural Geology 81
  6.3.4 Property Mineralization 82
  6.3.5 Mineralization at the Santa Cruz Deposit 83
  6.3.6 Mineralization at the Texaco Deposit 83
  6.3.7 Mineralization at the Texaco Ridge Exploration Area 84
  6.3.8 Mineralization at the East Ridge deposit 84

 

September 2023

SEC Technical Report Summary – Santa CruzPage vi

 

  6.3.9 Mineralization at the Southwest Exploration Area 85
  6.4 Deposit Types 85
  6.5 QP Opinion 88
7 Exploration 89
  7.1 Geophysical Exploration 89
  7.1.1 Ground Gravity Survey 89
  7.1.2 Ground Magnetics Survey 92
  7.1.3 Typhoon™ Survey 94
  7.1.4 2D Seismic Refraction Tomography 95
  7.1.5 Historical Geophysical Exploration 96
  7.2 Historical Data Compilation 100
  7.3 Drilling 101
  7.3.1 Historical Drilling – Santa Cruz and East Ridge Deposits 101
  7.3.2 Historic Drilling – Texaco Deposit 102
  7.3.3 2021 Twin Hole Drilling – IE 103
  7.3.4 2021-2022 Drilling Program – IE 104
  7.3.5 2023 Drilling Program 110
  7.3.6 Geotechnical Drilling 114
  7.3.7 Hydrogeology 114
  7.4 QP Opinion 118
8 Sample Preparation, Analysis and Security 116
  8.1 Sample Preparation Methods and Quality Control Measures 116
  8.2 Sample Preparation, Assaying and Analytical Procedures 116
  8.2.1 Skyline Laboratories 119
  8.2.2 SGS Laboratories 119
  8.2.3 American Assay Laboratories 119
  8.2.4 Historical Core Assay Sample and Analysis 120
  8.3 Specific Gravity Sampling 120
  8.4 Quality Control Procedures/Quality Assurance 120
  8.4.1 IE Santa Cruz Sampling 121
  8.4.2 2022 East Ridge and Texaco Sampling 127
  8.4.3 2021 IE Sampling 136
  8.5 Security and Storage 146
  8.6 QP Opinion 146
9 Data Verification 147
  9.1 Data Verification Procedures 147

 

September 2023

SEC Technical Report Summary – Santa CruzPage vii

 

  9.2 Nordmin Site Visit 2022 147
  9.2.1 Field Collar Validation 148
  9.2.2 Core Logging, Sampling, and Storage Facilities 151
  9.2.3 Independent Sampling 155
  9.2.4 Audit of Analytical Laboratory 162
  9.3 Twin Hole Analysis 162
  9.4 Database Validation 166
  9.5 Review of Company’s QA/QC 166
  9.6 QP Opinion 166
10 Mineral Processing and Metallurgical Testing 167
  10.1 CGCC Studies (1976-1982) 169
  10.1.1 Sample Selection 169
  10.1.2 Grinding Studies 178
  10.1.3 Flotation Studies 179
  10.1.4 Leaching Studies 181
  10.1.5 Copper Measurement 182
  10.1.6 ASARCO Study by Mountain States Engineering (1980) 182
  10.1.7 Santa Cruz In-Situ Study 183
  10.2 2022-2023 Test Work Studies 183
  10.2.1 Sample Selection 183
  10.2.2 Grinding Studies 185
  10.2.3 Leaching Studies 185
  10.2.4 Flotation Studies 185
  10.2.5 Copper Measurement 188
  10.2.6 Thickener Sizing Tests 188
  10.2.7 Solvent Extraction Testing 189
  10.2.8 Column Leach Tests 190
  10.2.9 Sample Mineralogy and Assays 191
  10.3 Process Factors and Deleterious Elements 195
  10.4 QP Opinion 195
11 Mineral Resource Estimates 196
  11.1 Drillhole Database 196
  11.2 Domaining 197
  11.2.1 Geological Domaining 197
  11.2.2 Regression 202
  11.2.3 Mineralization Domaining 204
  11.3 Exploratory Data Analysis 205

 

September 2023

SEC Technical Report Summary – Santa CruzPage viii

 

  11.4 Data Preparation 213
  11.4.1 Assay Intervals at Minimum Detection Limits 213
  11.4.2 Outlier Analysis and Capping 213
  11.4.3 Compositing 214
  11.4.4 Specific Gravity 215
  11.4.5 Block Model Strategy and Analysis 216
  11.4.6 Assessment of Spatial Grade Continuity 216
  11.4.7 Block Model Definition 220
  11.4.8 Interpolation Method 221
  11.4.9 Search Strategy 221
  11.5 Block Model Validation 225
  11.5.1 Visual Comparison 225
  11.5.2 Swath Plots 232
  11.6 Mineral Resource Classification 237
  11.7 Copper Pricing 239
  11.8 Reasonable Prospects of Economic Extraction 240
  11.9 Mineral Resource Estimate 242
  11.9.1 Mineral Resource Estimate 243
  11.9.2 Santa Cruz Mineral Resource Estimate 244
  11.9.3 Texaco Mineral Resource Estimate 245
  11.9.4 East Ridge Mineral Resource Estimate 246
  11.10 Mineral Resource Sensitivity to Reporting Cut-off 247
  11.11 Interpolation Comparison 251
  11.12 Factors That May Affect Mineral Resources 254
  11.13 QP Opinion 254
12 Mineral Reserve Estimates 255
13 Mining Methods 256
  13.1 Cut-Off Grade Calculations 258

 

September 2023

SEC Technical Report Summary – Santa CruzPage ix

 

  13.2 Geotechnical 258
  13.2.1 Dataset 258
  13.2.2 Mine Design Geotechnical Parameters 263
  13.2.3 Risks and Opportunities 265
  13.2.4 Rock Quality, Strength, and Joint Orientations 265
  13.2.5 Engineering Analysis 271
  13.2.6 Primary Ground Support for Development 288
  13.2.7 Boxcut and Decline Access 290
  13.3 Hydrogeology 291
  13.3.1 Surface Water 291
  13.3.2 Hydrogeology Investigations 292
  13.3.3 Hydrogeologic Conceptual Site Model 293
  13.3.4 Groundwater Flow Model 294
  13.4 Mine Dewatering 297
  13.4.1 Ramp Dewatering 297
  13.4.2 Mining Area Dewatering 298
  13.5 Identifying Potentially Minable Areas 301
  13.5.1 Dilution 303
  13.5.2 Stope Recovery Factor 305
  13.5.3 Development Allowance 305
  13.5.4 Block Model Indicator Shells 306
  13.6 Mine Design 306
  13.6.1 Santa Cruz - Longhole Stope 306
  13.6.2 Santa Cruz Exotic and East Ridge, Drift and Fill 307
  13.6.3 Development 308
  13.6.4 Mine Plan Resource 309
  13.7 Production Schedule 311
  13.8 Mining Operations 317
  13.8.1 Stoping 317
  13.8.2 Drift and Fill (DAF) 317
  13.8.3 Underground Material Handling System 317
  13.8.4 Backfill 318
  13.8.5 Grade Control 323
  13.8.6 Ventilation 323
  13.8.7 Mine Services 329
  13.9 QP Opinion 332
14 Processing and Recovery Methods 333
  14.1 Operation Results 333
  14.2 Processing Overview 334
  14.3 Processing Method 334
  14.3.1 Comminution 334
  14.3.2 Whole Ore Leaching 335
  14.3.3 Solvent Extraction / Electrowinning 335
  14.3.4 Leach Residue Neutralization 335
  14.3.5 Flotation Circuit 336
  14.3.6 Tailing 336
  14.3.7 Reagents 336
  14.4 Flowsheet 337

 

September 2023

SEC Technical Report Summary – Santa CruzPage x

 

  14.5 Plant Design and Equipment Design 338
  14.5.1 Plant Layout 338
  14.5.2 Equipment Design 339
  14.6 Consumable Requirements 340
  14.7 QP Opinion 341
15 Infrastructure 342
  15.1 Location & Roads 342
  15.2 Project Layout 343
  15.3 Rail 347
  15.4 Port Facilities 348
  15.5 Tailings Disposal 349
  15.5.1 TSF Siting and Foundation Characterization 349
  15.5.2 Design Basis 352
  15.5.3 Design Features 352
  15.5.4 Embankment Stability 355
  15.5.5 Water Management 355
  15.5.6 Closure Plan 355
  15.6 Power 357
  15.6.1 Power Sources 357
  15.6.2 Power Distribution 358
  15.6.3 Power Consumption 358
  15.7 Water 360
  15.8 Pipelines 361
  15.9 QP Opinion 362
16 Market Studies 363
  16.1 Market Information 363
  16.1.1 Market for Santa Cruz 363
  16.1.2 Copper Demand 363
  16.1.3 Copper Supply 363
  16.1.4 Trailing Price 364
  16.1.5 Study Price and Sales Terms 364
  16.2 Contracts and Status 365
17 Environmental Studies, Permitting, and Plans, Negotiations, or Agreements with Local Individuals or Groups 366
  17.1 Environmental Study Results 366
  17.1.1 Flora and Fauna 366
  17.1.2 Threatened and Endangered Species 366
  17.1.3 Migratory Bird Treaty Act 367

  

September 2023

SEC Technical Report Summary – Santa CruzPage xi

 

  17.1.4 Surface Water Mapping 367
  17.1.5 Cultural Heritage 368
  17.1.6 Air Quality 368
  17.1.7 Carbon Intensity 369
  17.1.8 Surface Water Monitoring 372
  17.1.9 Groundwater Monitoring 372
  17.1.10 Material Characterization 373
  17.2 Permitting and Authorizations 374
  17.3 Requirements and Plans for Waste and Tailings Disposal, Site Monitoring, and Water Management During Operations and After Mine Closure 375
  17.4 Post-Performance or Reclamations Bonds 376
  17.4.1 Arizona State Mine Inspector: Reclamation Plan 376
  17.4.2 Arizona Department Of Environmental Quality: Aquifer Protection Permit 377
  17.5 Status of Permit Applications 377
  17.5.1 Arizona State Mine Inspector: Reclamation Plan 377
  17.5.2 Arizona Department of Environmental Quality: Aquifer Protection Permit 378
  17.5.3 Known Requirements to Post Performance or Reclamation Bonds 378
  17.6 Local Individuals and Groups 378
  17.7 Mine Closure 379
  17.7.1 Waste and Development Rock Closure and Reclamation Approach 379
  17.7.2 Tailings Closure and Reclamation Approach 379
  17.7.3 General Grading and Revegetation Approach 379
  17.7.4 Mill and Process Area Closure and Reclamation Approach 380
  17.7.5 Process and Chemical Ponds Closure and Reclamation Approach 380
  17.7.6 Structural Decommissioning Approach 380
  17.7.7 Underground Operations Closure Approach 380
  17.7.8 Aquifer Restoration and Post Closure Monitoring Approach 381
  17.8 QP Opinion 381
18 Capital and Operating Costs 382
  18.1 Capital Cost Estimates 382
  18.1.1 Mining Capital Cost 382
  18.1.2 Process Capital Cost 385
  18.1.3 Tailings Capital Costs 386
  18.1.4 Basis for Cost Estimates 388
  18.2 Operating Cost Estimates 389
  18.2.1 Mine Operating Cost 389
  18.2.2 Processing Operating Cost 393
  18.2.3 General and Administrative Operating Costs 394
  18.3 QP Opinion 396

 

September 2023

SEC Technical Report Summary – Santa CruzPage xii

 

19 Economic Analysis 397
  19.1 General Description 397
  19.1.1 Basic Model Parameters 397
  19.1.2 External Factors 398
  19.1.3 Technical Factors 399
  19.2 Results 410
  19.3 Sensitivity Analysis 418
20 Adjacent Properties 419
  20.1 Cactus Project 419
21 Other Relevant Data and Information 420
22 Interpretation and Conclusions 421
  22.1 Geology 421
  22.2 Exploration, Drilling, and Analytical Data Collection in Support of Mineral Resource Estimation 422
  22.3 Mineral Resource Estimate 422
  22.4 Mining Methods 424
  22.5 Metallurgy and Processing 425
  22.6 Project Infrastructure 425
  22.7 Environmental, Closure, and Permitting 426
  22.8 Project Economics 427
23 Recommendations 428
  23.1 Resources and Reserves 428
  23.2 Mining Methods 428
  23.2.1 Geotechnical Recommendations 428
  23.2.2 Hydrogeology 429
  23.2.3 Ventilation 429
  23.3 Mineral Processing 429
  23.4 Infrastructure 430
  23.4.1 Power 430
  23.4.2 Water 430
  23.4.3 Tailings Storage 431
  23.5 Environmental and Permitting 431
  23.6 Recommended Work Program Costs 431
24 References 433
25 Reliance on Information Provided by the Registrant 437

 

September 2023

SEC Technical Report Summary – Santa CruzPage xiii

 

List of Tables

 

Table 1-1: December 2022 MRE Drillhole Summary 32
Table 1-2: In situ Santa Cruz Project Mineral Resource Estimates at 0.70% Cu cut-off for Santa Cruz, 0.80% Cu cut-off for Texaco, and 0.90% Cu Cut-off for East Ridge 34
Table 1-3: Mine Plan Summary 37
Table 1-4: Concentrate Terms 41
Table 1-5: Estimated Mining Initial Capital Cost 42
Table 1-6: Estimated Mining Sustaining Capital Cost 42
Table 1-7: Estimated Initial Plant Capital Cost Summary 42
Table 1-8: Estimated TSF Initial Capital Cost 43
Table 1-9: Estimated TSF Sustaining Capital Cost 43
Table 1-10: Mining Operating Costs 43
Table 1-11: Process Plant OPEX Summary by Category 44
Table 1-12: G&A Operating Cost Summary 44
Table 1-13: Indicative Economic Results 45
Table 2-1: Site Visit 52
Table 3-1: Permit Requirements for Exploration Work Required on Private Land 62
Table 4-1: Description of Physiography of the Casa Grande Area, Santa Cruz Property 67
Table 5-1: Sacaton Historical Mine Production (Fiscal Years Ended December 31) 70
Table 5-2: History of Exploration Activities Across the Santa Cruz and Texaco Deposits 71
Table 7-1: Ground Gravity Topographic Survey Coordinate System Parameters 89
Table 7-2: Ground Gravity Base Information 89
Table 7-3: Santa Cruz Typhoon™ 3D PPD IP Survey Specifications 95
Table 7-4: Summary of Historical Exploration on the Santa Cruz Project and Surrounding Area 97
Table 7-5: Summary of Available Data by Region 101
Table 7-6: Drilling History Within the Santa Cruz Deposit and East Ridge Deposit Area 102
Table 7-7: Drilling History within the Texaco Deposit 102
Table 7-8: IE 2021 Twin Hole Drilling on the Santa Cruz Deposit 103
Table 7-9: Santa Cruz Project SG Measurements 105
Table 7-10: 2021-2022 Drilling Summary 107
Table 7-11: 2023 Drilling Summary 111
Table 8-1: IE Submitted Standards Measured at Skyline Laboratories 121
Table 8-2: Skyline Internal QA/QC CRM Samples and Results 121
Table 8-3: IE Inserted CRMs for Texaco Drilling 2022 128
Table 8-4: IE inserted CRMs for East Ridge Drilling 2022, measured at Skyline Laboratories 128
Table 8-5: IE inserted CRMs for East Ridge Drilling 2022, measured at SGS Laboratories 128
Table 8-6: CRMs Inserted by IE into Sample Batches Sent to Skyline Laboratories 137
Table 8-7: CRMs Inserted by IE into Sample Batches Sent to American Assay Laboratories 137
Table 8-8: Skyline Laboratory Submitted CRMs 137
Table 8-9: American Assay Laboratory Submitted CRMs 137

 

September 2023

SEC Technical Report Summary – Santa CruzPage xiv

 

Table 9-1: Check Coordinates for Drilling Within the Santa Cruz, East Ridge, and Texaco Deposits November 9, 2022 149
Table 9-2: Original Assay Values Versus Nordmin Check Sample Assay Values from the March 2022 Site Visit 156
Table 9-3: Original Assay Values versus Nordmin Check Sample Assay Values from the November 2022 Site Visit 157
Table 9-4: Downhole Lithology Logging Comparison of CG-027 versus SCC-001 165
Table 10-1: Upper Ore Body Sample Composite 76-122 for Leach – Float Testing 170
Table 10-2: Analyses of High-grade Supergene Composite No.79-88 (A&B) 170
Table 10-3: Mineralogy of High-grade Supergene Composite No.79-88 170
Table 10-4: Drillholes, Intervals and Sample Weights of High-grade Supergene Composite No. @79-88 (A&B) 171
Table 10-5: Analyses of Supergene Dilution Composite No.79-99 171
Table 10-6: Mineralogy of Supergene Dilution Composite No.79-99 172
Table 10-7: Drillholes, Intervals and Sample Weights of Supergene Dilution Composite No.79-99 172
Table 10-8: Analyses of Low-grade Supergene Composite No.79-128 172
Table 10-9: Mineralogy of Low-grade Supergene Composite No.79-128 173
Table 10-10: Drillholes, Intervals and Sample Weights of Low-grade Supergene Composite No.79-128 173
Table 10-11: Analyses of Mixed Chalcocite / Chalcopyrite Composite No.79-109 173
Table 10-12: Mineralogy of Mixed Chalcocite / Chalcopyrite Composite No.79-109 174
Table 10-13: Drillholes, Intervals and Sample Weights of Mixed Chalcocite / Chalcopyrite Composite No.79-109 174
Table 10-14: Analyses of Chalcopyrite Composite No.79-118 174
Table 10-15: Mineralogy of Chalcopyrite Composite No.79-118 175
Table 10-16: Drillholes, Intervals and Sample Weights of Chalcopyrite Composite No.79-118 175
Table 10-17: Analyses of Exotic Ore and Exotic Dilution Ore Composites Nos. 79-101 and 79-102 175
Table 10-18: Mineralogy of Exotic Ore and Exotic Dilution Ore Composites Nos. 79-101 and 79-102 175
Table 10-19:Drillholes, Intervals and Sample Weights of Exotic Ore Composite No. 79-101 176
Table 10-20: Drillholes, Intervals and Sample Weights of Exotic Dilution Ore Composite No. 79-102 176
Table 10-21: Evaluated Grinds 179
Table 10-22: Open Cycle Leach – Float Test Results Using 50 Grams per Tonne Z-200 Collector 180
Table 10-23: Results of Locked-Cycle Flotation Using 50 grams per tonne Z-200 Collector 181
Table 10-24: Drillholes, Intervals and Sample Lengths of the Mill Composite 183
Table 10-25: Heap Leach Sample No.1 (Lab sample No. 4815-002) 184
Table 10-26: Heap Leach Sample No.2 (Lab sample No. 4815-003) 184
Table 10-27: Confirmatory Bond Mill Work Index Test 185
Table 10-28: Results of Leach – Float Tests at Different Leach Residue Grinds 186
Table 10-29: Combined Metallurgical Results, Whole Ore Acid Leaching, Residue Cleaner Flotation, Composite 4815-001 187
Table 10-30: Base Metal Concentrate Results 188

 

September 2023

SEC Technical Report Summary – Santa CruzPage xv

 

Table 10-31: Chloride Analyses 188
Table 10-32: High-Rate Thickener Sizing Test Results 189
Table 10-33: Sequential Copper Analyses, Santa Cruz Samples 193
Table 10-34: ICP Metals Analysis Results for Santa Cruz Samples 194
Table 11-1: Drillhole Summary 197
Table 11-2: Mineral Resource Estimate Number of Assays by Assay Type 197
Table 11-3: Santa Cruz, Texaco, and East Ridge Geological Domains 198
Table 11-4: Regression Analysis for Acid Soluble Cu 203
Table 11-5: Regression Analysis for Cyanide Soluble Cu 204
Table 11-6: Santa Cruz, East Ridge, and Texaco Deposit Domain Wireframes 205
Table 11-7: Santa Cruz Deposit Domain, Assays by Cu Grade Sub-Domain 206
Table 11-8: Assays at Minimum Detection 213
Table 11-9: Santa Cruz, Texaco, and East Ridge Capping Values 214
Table 11-10: Santa Cruz Deposit Composite Analysis 215
Table 11-11: SG Values Measured for the Santa Cruz Deposit by Geologic Domain 215
Table 11-12: Santa Cruz Deposit Variography Parameters 217
Table 11-13: Santa Cruz, Texaco, and East Ridge Block Model Definition Parameters 220
Table 11-14: Santa Cruz Block Model Search Parameters 222
Table 11-15: Texaco Block Model Search Parameters 223
Table 11-16: East Ridge Block Model Search Parameters 224
Table 11-17: Input Parameter Assumptions 241
Table 11-18: In Situ Santa Cruz Project Mineral Resource Estimates at 0.70% Cu cut-off for Santa Cruz, 0.80% Cu cut-off for Texaco, and 0.90% Cu Cut-off for East Ridge 243
Table 11-19: In Situ Santa Cruz Deposit Mineral Resource Estimate, 0.70% Total Cu CoG 244
Table 11-20: In Situ Texaco Deposit Mineral Resource Estimate, 0.80% Total Cu CoG 245
Table 11-21: In Situ East Ridge Deposit Mineral Resource Estimate, 0.90% Total Cu CoG 246
Table 11-22: Mineral Resource Sensitivity for Santa Cruz Total Cu 248
Table 11-23: Mineral Resource Sensitivity for Texaco Total Cu 249
Table 11-24: Mineral Resource Sensitivity for East Ridge Total Cu - There are no Indicated Resources at East Ridge 250
Table 11-25: Santa Cruz Interpolation Comparison 252
Table 11-26: Texaco Interpolation Comparison 252
Table 11-27: East Ridge Deposit Interpolation Comparison 253
Table 13-1: Cut-Off Grade Assumptions 258
Table 13-2: Drillholes Utilized for 2023 IA 260
Table 13-3: ATV Drillholes by Structural Domain 261
Table 13-4: Summary of Geomechanical Laboratory Testing, 2023 IA 262
Table 13-5: Summary of LHS Geotechnical Design Recommendations 263

 

September 2023

SEC Technical Report Summary – Santa CruzPage xvi

 

Table 13-6: Summary of LHS Dimensions and ELOS by North and South Area, Mineral Domain 264
Table 13-7: Summary of DAF Geotechnical Design Recommendations 265
Table 13-8: Summary of Q’ Rock Quality by Mining Level 266
Table 13-9: Santa Cruz Rock Quality Summary 268
Table 13-10: Santa Cruz Rock Mass Strength by Mineral Domain Summary 270
Table 13-11: Stability Graph Results, North Domain 273
Table 13-12: Stability Graph Results, South Domain 274
Table 13-13: Stope and Production Headings Ground Support 277
Table 13-14: ELOS Design Zones 278
Table 13-15: Sill Pillar Rock Qualities and Carter Classification 284
Table 13-16: Primary Ground Support for Permanent Development 288
Table 13-17: MSO Parameters 301
Table 13-18: Santa Cruz Deposit MSO Summary 301
Table 13-19: Santa Cruz Exotic Deposit MSO Summary 302
Table 13-20: East Ridge Deposit MSO Summary 302
Table 13-21: Dilution Assumptions 304
Table 13-22: Total Dilution 305
Table 13-23: Development Allowance Assumptions 305
Table 13-24: Mine Plan Summary 310
Table 13-25: Productivity Rates 311
Table 13-26: Schedule Parameters for Underground Mining 312
Table 13-27: Material Characteristics 312
Table 13-28: Summarized Production Schedule 313
Table 13-29: Detailed Production Schedule (with inferred) 314
Table 13-30: Detailed Development Schedule (with inferred) 315
Table 13-31: Design Criteria 320
Table 13-32: General Airflow Calculations 325
Table 13-33: Main Fan LoM Operating Points 325
Table 13-34: Overall LoM Equipment Heat Loads 327
Table 13-35: Management and Technical Staff Labor Estimate 330
Table 13-36: Operating and Maintenance Labor Estimate 331
Table 13-37: Santa Cruz Estimated Mobile Equipment 332
Table 14-1: Planned Operating Schedule and Target Throughputs 333
Table 15-1: Starter Dam and Ultimate Embankment Summary 353
Table 15-2: TSF Target and Calculated FoS 355
Table 15-3: Summary of Power Consumption over the LoM for Surface and Underground Facilities 360
Table 16-1: Average Annual and Spot Pricing 364
Table 16-2: Concentrate Terms 364

  

September 2023

SEC Technical Report Summary – Santa CruzPage xvii

 

Table 16-3: Major Contracts 365
Table 17-1: Expected Carbon Intensity of Other Mining Projects 371
Table 17-2: Permitting Table 374
Table 18-1: Estimated Mining Initial Capital Cost 382
Table 18-2: Estimated Mining Sustaining Capital Cost 383
Table 18-3: Mining Capital Spend Schedule 384
Table 18-4: Estimated Initial Plant Capital Cost Summary 385
Table 18-5: Process Plant Capital Cost Expenditure Schedule (US$ Million) 386
Table 18-6: Estimated TSF Initial Capital Cost 387
Table 18-7: Estimated TSF Sustaining Capital Cost 387
Table 18-8: TSF Capital Cost Expenditure Schedule 388
Table 18-9: Mining Operating Costs 390
Table 18-10: Mine Operating Expenditure Schedule 391
Table 18-11: Process Plant OPEX Summary by Category 394
Table 18-12: Process Operating Expenditure Schedule 394
Table 18-13: Life-of Mine General and Administration Cost Detail 395
Table 18-14: G&A Expenditure Schedule 396
Table 19-1: Basic Model Parameters 397
Table 19-2: Mine Development Cost Accelerated Depreciation Schedule 398
Table 19-3: Santa Cruz Mining Summary 401
Table 19-4: Santa Cruz Processing Summary 403
Table 19-5: Santa Cruz Mining Cost Summary 405
Table 19-6: Santa Cruz Processing Cost Summary 406
Table 19-7: G&A Fixed Costs 406
Table 19-8: Santa Cruz G&A Cost Summary 406
Table 19-9: Transport Costs and TC/RCs 406
Table 19-10: Modeled Initial Capital 408
Table 19-11: Modeled Sustaining Capital 408
Table 19-12: Indicative Economic Results 410
Table 19-13: Economic Results - Tabular Data (without Inferred material) 412
Table 19-14: Economic Results - Tabular Data (including Inferred material) 415
Table 22-1: In Situ Mineral Resource Estimate for Santa Cruz, Texaco, and East Ridge Deposits 423
Table 23-1: Summary of Costs for Recommended Work 432
Table 25-1: Reliance on Information Provided by the Registrant 437

 

September 2023

SEC Technical Report Summary – Santa CruzPage xviii

 

List of Figures

 

Figure 1-1: Mine Design, Santa Cruz, Santa Cruz Exotic, and East Ridge 36
Figure 1-2: Process Flow Sheet 38
Figure 1-3: Annual Cash Flow Summary (Tabular data in Table 19-13– Without Inferred material) 46
Figure 1-4: Annual Cash Flow Summary (Tabular data in Table 19-14 – Including Inferred Material) 47
Figure 3-1: Santa Cruz Project Location Map 57
Figure 3-2: Santa Cruz Surface Title 58
Figure 3-3: Santa Cruz Mineral Title 60
Figure 4-1: Location Map 65
Figure 4-2: Average Temperatures and Precipitation 66
Figure 5-1: Historical Drill Collars, Deposit, and Exploration Area Names (white) as well as Current Project Names for IE and Neighboring Project (in yellow) 69
Figure 6-1: Regional Geology of the Southwestern Porphyry Belt and the Cu Porphyry Deposits in the Area around the Santa Cruz Project 76
Figure 6-2: Generalized Cross-section of the Santa Cruz - Sacaton System 78
Figure 6-3: Simplified Stratigraphic Section of Santa Cruz Project Alteration 80
Figure 6-4: Simplified Alteration and Mineralization Zonation Model of a Porphyry Cu Deposit 86
Figure 6-5: Schematic Representation of an Exotic Cu Deposit and its Relative Position to an Exposed Porphyry Cu System 87
Figure 6-6: Typical Cu Porphyry Cross-section Displaying Hypogene and Supergene Mineralization Processes and Associated Minerals 88
Figure 7-1: Gravity Survey Stations (top) and Complete Gravity Survey Results (bottom) 91
Figure 7-2: Ground Magnetics Survey Lines (top) and Ground TMI RTP Ground Magnetics Results (bottom) 93
Figure 7-3: Layout of the Santa Cruz 3D IP Survey 94
Figure 7-4: Refraction Seismic Tomography Survey Results 96
Figure 7-5: ASARCO Map Illustrating Interpreted Ground and Aeromagnetic Data Detailed in Historic Report: “Recommended Drilling Santa Cruz Project,” M.A.970 Pinal County, Arizona, August 21, 1964, by W.E. Saegart 99
Figure 7-6: Plan Map of Historical Drillhole Collars 100
Figure 7-7: Plan Map of the Twinned Drillholes and Historical Drillhole Collars 104
Figure 7-8: Plan Map of Historical and 2021 and 2022 IE Drillhole Collars 109
Figure 7-9: Plan Map of Historical and 2021 and 2022 IE Drillhole Collars 114
Figure 8-1: NTT Diamond Bladed Automatic Core Saw used for Cutting Diamond Drill Core for Sampling 117
Figure 8-2: Tee Street Core Storage Facility 118
Figure 8-3: (Left) samples placed in burlap and inner plastic bags labeled with sample numbers; (Right) sample batches placed in large plastic bags and bins for shipping to lab 118
Figure 8-4: Santa Cruz Deposit, OREAS 501d Standard Total Cu (g/t), Assayed at Skyline Laboratories 122
Figure 8-5: Santa Cruz Deposit, OREAS 906 Standard Total Cu (g/t), Assayed at Skyline Laboratories 122
Figure 8-6: Santa Cruz Deposit, OREAS 907 Standard Total Cu (g/t), Assayed at Skyline Laboratories 123
Figure 8-7: Santa Cruz Deposit, OREAS 908 Standard Total Cu (g/t), Assayed at Skyline Laboratories 123
Figure 8-8: Santa Cruz Deposit, OREAS 901 Standard Total Cu (g/t), Assayed at Skyline Laboratories 124
Figure 8-9: Blank Results from Skyline Laboratory Analyses from the 2021 and 2022 Drill Program 125
Figure 8-10: SGS Blank Results from the 2022 Drill Program 126
Figure 8-11: Field Duplicate Results, in Cu (%), Measured at Skyline Laboratories for the Santa Cruz Deposit 127
Figure 8-12: Texaco Deposit, OREAS 151a Standard Total Cu (g/t), Assayed at Skyline Laboratories 128
Figure 8-13: Texaco Deposit, OREAS 504c Standard Total Cu (%), Assayed at Skyline Laboratories 129
Figure 8-14: Texaco Deposit, OREAS 501d Standard Total Cu (%), Assayed at Skyline Laboratories 129
Figure 8-15 East Ridge Deposit, OREAS 901 Standard Total Cu (%), Assayed at Skyline Laboratories 130
Figure 8-16: East Ridge Deposit, OREAS 906 Standard Total Cu (%), Assayed at SGS Laboratories 130

  

September 2023

SEC Technical Report Summary – Santa CruzPage xix

 

Figure 8-17: Texaco Blanks for Total Cu 131
Figure 8-18: East Ridge Blanks, Total Cu 132
Figure 8-19: East Ridge SGS Laboratories Blanks, Total Cu (%) 133
Figure 8-20: Original Versus Field Duplicate Sample Results for the Texaco Deposit as total Cu (%) from Samples Submitted to Skyline Laboratories 134
Figure 8-21: Original Versus Field Duplicate Sample Results for the East Ridge Deposit as Total Cu (%) from Samples Submitted to Skyline Laboratories 135
Figure 8-22: Original Versus Field Duplicate Sample Results for East Ridge Deposit as Total Cu (%) from Samples Submitted to SGS Laboratories 136
Figure 8-23: Santa Cruz Deposit, OREAS 908 Standard Total Cu (g/t), Assayed at Skyline Laboratories 138
Figure 8-24: Santa Cruz Deposit, OREAS 908 Standard Cyanide Soluble Cu (g/t), Assayed at Skyline Laboratories 138
Figure 8-25: Santa Cruz Deposit, OREAS 908 Standard Cyanide Soluble Cu (g/t), Assayed at Skyline Laboratories 139
Figure 8-26: Santa Cruz Deposit, OREAS 908 Standard Total Cu (g/t), Assayed at American Assay Laboratories 139
Figure 8-27: Santa Cruz Deposit, OREAS 908 Standard Acid Soluble Cu (g/t), Assayed at American Assay Laboratories 140
Figure 8-28: Santa Cruz Deposit, OREAS 908 Standard Cyanide Soluble Cu (g/t), Assayed at American Assay Laboratories 140
Figure 8-29: Blanks Submitted by IE to Skyline Laboratories for QA/QC Process 141
Figure 8-30: Blanks Submitted by IE to American Assay Laboratories for QA/QC Process 142
Figure 8-31: Original Versus Field Duplicate Sample Results as Total Cu (%) from Samples Submitted to Skyline Laboratories 143
Figure 8-32: Original Versus Field Duplicate Sample Results as Total Cu (%) from Samples Submitted to American Assay Laboratories 144
Figure 8-33: Duplicates Completed by Skyline Laboratories for QA/QC Process 145
Figure 8-34: Duplicates Completed by American Assay Laboratories for QA/QC Process 145
Figure 9-1: Map of Check Drillhole Collar Locations from November 2022 Site Visit 150
Figure 9-2: Collars for Historic Diamond Drillholes CG-091 and CG-030 151
Figure 9-3: IE Core Logging Facility Located in Casa Grande, Arizona 152
Figure 9-4: IE’s Core Storage Facilities - Core is Predominantly Stored Outside, Winterized and on Pallets. Further Core Storage is Available in Buildings 1 and 2 153
Figure 9-5: Core Photography Station at IE Core Logging Facility 154
Figure 9-6 Specific Gravity Measuring Station within Core Logging Facility 155
Figure 9-7: Nordmin Independent Sampling Total Cu (%) Assays from Skyline Laboratories, Santa Cruz Deposit 158
Figure 9-8: Nordmin Independent Sampling Acid Soluble Cu (%) Assays from Skyline Laboratories, Santa Cruz Deposit 159
Figure 9-9: Nordmin Independent Sampling of Cyanide Soluble (%) Assays from Skyline Laboratories, Santa Cruz Deposit 160
Figure 9-10: Nordmin Independent Sampling of Total Copper (%) Assays from Skyline Laboratories, Texaco Deposit 160

 

September 2023

SEC Technical Report Summary – Santa CruzPage xx

 

Figure 9-11: Nordmin Independent Sampling of Acid Soluble Copper (%) Assays from Skyline Laboratories, Texaco Deposit 161
Figure 9-12: Nordmin Independent Sampling of Cyanide Soluble Copper (%) Assays from Skyline Laboratories, Texaco Deposit 162
Figure 10-1: Simplified Process Flow Sheet 168
Figure 10-2: Surface Map of the Drillholes Used in the Ore Type Composites 177
Figure 10-3: Mineral Process Testing Sample Drillhole Intercepts in the Minable Material 184
Figure 10-4: Leach – Float Testing Results at Different Leach Residue Grinds 186
Figure 10-5: Copper Recovery vs Organic Extractant Concentration for PLS Extraction of Copper from Santa Cruz PLS 190
Figure 10-6: Summarized Sample Composition 192
Figure 10-7: Copper Deportment (%) of Each Sample 193
Figure 11-1: Plan View of Santa Cruz Project Diamond Drilling by Deposit 196
Figure 11-2: Santa Cruz, Texaco, and East Ridge Geological Domains 198
Figure 11-3: Santa Cruz Deposit Domain Idealized Cross-section 199
Figure 11-4: Texaco Deposit Domain Idealized Cross-section 199
Figure 11-5: East Ridge Deposit Domain Idealized Cross-section with Structural Control, Comprised Solely of Oxide Mineralization 200
Figure 11-6: Revised Santa Cruz High-Grade Domains for Exotic, Oxide, and Primary Mineralization 201
Figure 11-7: Santa Cruz Cross-section Showing Acid Soluble Copper Assay to Total Copper Assay Ratio 202
Figure 11-8: Histogram and Log Probability Plots for Santa Cruz Exotic Cu LG Sub-Domain 207
Figure 11-9: Histogram and Log Probability Plots for Santa Cruz Oxide Cu LG Sub-Domain 208
Figure 11-10: Histogram and Log Probability Plots for Santa Cruz Chalcocite Enriched Cu LG Sub-Domain 209
Figure 11-11: Histogram and Log Probability Plots for Santa Cruz Primary Cu LG Sub-Domain 210
Figure 11-12: Histogram and Log Probability Plots for Texaco Primary Cu LG Sub-Domain 211
Figure 11-13: Histogram and Log Probability Plots for East Ridge Oxide Cu LG Sub-Domain 212
Figure 11-14: Exotic Domain Total Cu Variogram 218
Figure 11-15: Oxide Domain Total Cu Variogram 218
Figure 11-16: Oxide Domain Acid Soluble Cu Variogram 219
Figure 11-17: Chalcocite Enriched Domain Acid Soluble Cu Variogram 219
Figure 11-18: Primary Domain Total Cu Variogram 220
Figure 11-19: Santa Cruz Block Model Validation, Total Cu, Cross-section 226
Figure 11-20: Santa Cruz Block Model Validation, Acid Soluble Cu, Cross-section, +/-50 m Width 226
Figure 11-21: Santa Cruz Block Model Validation, Cyanide Soluble Cu, Cross-section +/-50 m Width 227
Figure 11-22: Santa Cruz Block Model Validation, Total Cu, Cross-section +-/50 m Width 227
Figure 11-23: Santa Cruz Block Model Validation, Acid Soluble Cu, Cross-section +/-50 m Width 228
Figure 11-24: Santa Cruz Block Model Validation, Cyanide Soluble Cu, Cross-section +/-50 m Width 228
Figure 11-25: Texaco Block Model Validation, Total Cu, Cross-section +/-50 m Width 229

 

September 2023

SEC Technical Report Summary – Santa CruzPage xxi

 

Figure 11-26: Texaco Block Model Validation, Acid Soluble Cu, Cross-section +/-50 m Width 229
Figure 11-27: Texaco Block Model Validation, Cyanide Soluble Cu, Cross-section +/-50 m Width 230
Figure 11-28: East Ridge Block Model Validation, Total Cu, Cross-section +/-50 m Width 230
Figure 11-29: East Ridge Block Model Validation, Acid Soluble Cu, Cross-section +/-50 m Width 231
Figure 11-30: East Ridge Block Model Validation, Cyanide Soluble Cu, Cross-section +/- 50 m Width 231
Figure 11-31: Santa Cruz Oxide Domain Swath Plots, Total Cu % in X, Y, and Z Directions 233
Figure 11-32: Santa Cruz Oxide and Chalcocite Domain Swath Plots, Acid Soluble and Cyanide Soluble Cu % 234
Figure 11-33: Texaco Primary Domain Swath Plot, Total Cu % 235
Figure 11-34: East Ridge Oxide Domain Total Cu, Acid Soluble, and Cyanide Soluble Swath Plots 236
Figure 11-35: Plan section Demonstrating Resource Classification,-250 m, -350 m, and -450 m Depth, with North Upward 238
Figure 11-36: Texaco (left) and East Ridge (right) Plan Sections Demonstrating Resources Classification, With North Upward 239
Figure 11-37: Plan View of the Mineral Resource Envelopes 242
Figure 13-1: Location of the Different Zones 257
Figure 13-2: Plan View of Santa Cruz and East Ridge Mining Targets 259
Figure 13-3: Section View (Looking East) of Santa Cruz and East Ridge Mining Targets 260
Figure 13-4: Plan View of Geotechnical Drillhole Collars 261
Figure 13-5: Plan View of Drillhole Collars with ATV Survey 262
Figure 13-6: Cumulative Distribution Plot of All Q’ Data within the Santa Cruz MSO Shapes 267
Figure 13-7: Intact Rock Strength Summary 269
Figure 13-8: North and South Structural Domain Stereonets 270
Figure 13-9: North and South Structural Domains 271
Figure 13-10: North Domain Stability Graph Results (10 m Wide, 30 m High) 275
Figure 13-11: South Domain Stability Graph Results (10 m Wide, 30 m High) 276
Figure 13-12: Cable Bolt Support 277
Figure 13-13: North Domain ELOS Estimates (10 m Wide, 30 m High) 278
Figure 13-14: South Domain ELOS Estimates (10 m Wide, 30 m High) 279
Figure 13-15: PBF Strength Estimates 280
Figure 13-16: Cement in Solids Estimate 281
Figure 13-17: Staggered 1-3-5 Sequence Plan View 282
Figure 13-18: 1-3-5 Sublevel Vertical Sequence Section View 282
Figure 13-19: Haulage Setback Minimum Distances 283
Figure 13-20: Proposed Sill Pillar 284
Figure 13-21: Carter’s Scaled Span Sill Pillar Estimate 284
Figure 13-22: Carter’s Scaled Span Exposure Guidelines 285
Figure 13-23: Critical Span Curve 286
Figure 13-24: Ground Support Chart for DAF Span and Maximum Height 287

  

September 2023

SEC Technical Report Summary – Santa CruzPage xxii

 

Figure 13-25: PST DAF Mining Sequence 288
Figure 13-26: Ground Support Category Estimates Using the Ground Support Chart 289
Figure 13-27: Kinematic Wedge Analysis Results 289
Figure 13-28: Structural Analysis with Dominant Joint Set Orientations 290
Figure 13-29: Isometric View of Most Recent Mine Design with Ground Support Estimates 291
Figure 13-30: Boreholes and Well Locations of Collected Hydrogeology Data used in Groundwater Model 293
Figure 13-31: Mine Residual Passive Inflow (RPI) by Area and Total Mine Plan Combined with Active Dewatering During Years 1 and 2 296
Figure 13-32: Model Estimates of Residual Passive Inflows Mine Workings 297
Figure 13-33: Surface Dewatering Well Locations 298
Figure 13-34: Dewatering System P&ID 300
Figure 13-35: Santa Cruz Oxide and Chalcocite Undiluted MSO Results (Looking to the Northwest) 302
Figure 13-36: Santa Cruz Exotic Undiluted MSO Results (Looking to the Southwest) 303
Figure 13-37: East Ridge Undiluted MSO Results (Looking to the West) 303
Figure 13-38: Typical Stope Cross-Section 306
Figure 13-39: Typical Mining Sequence 307
Figure 13-40: Attack Ramp Access to Stopes 308
Figure 13-41: Typical Stope Cycle 308
Figure 13-42: Railveyor Decline Cross-Section 309
Figure 13-43: Mine Design, Santa Cruz, Santa Cruz Exotic, and East Ridge 310
Figure 13-44: Mine Production Schedule Colored by Year (with Inferred) 316
Figure 13-45: Ore Pass Locations in Red 318
Figure 13-46: Long Section of Paste Distribution System and Maximum Allowable Friction Loss for Gravity Flow (looking East) 320
Figure 13-47: Santa Cruz Paste Process Flow Sheet 322
Figure 13-48: General Ventilation Infrastructure and Layout 324
Figure 13-49: Refrigeration Summary Breakdown 328
Figure 13-50: Seasonal Refrigeration Operation 328
Figure 13-51: Refrigeration Requirements Over the LoM 329
Figure 14-1: Conceptual Flowsheet for the Santa Cruz Process Plant 337
Figure 14-2: Conceptual Santa Cruz Plant Layout 338
Figure 14-3: Santa Cruz Plant Primary Reagents and Consumables 341
Figure 15-1: Project Location and Road Network 342
Figure 15-2: Santa Cruz Site Plan 344
Figure 15-3: Santa Cruz General Arrangement Detail 346
Figure 15-4: UPSP Rail Network Across Western US 347
Figure 15-5: BNSF Rail Network Across Western US 348
Figure 15-6: Ports and Copper Smelters in the Western US and Mexico 349

 

September 2023

SEC Technical Report Summary – Santa CruzPage xxiii

 

Figure 15-7:Site Location, General TSF Layout, and Flood Risk 351
Figure 15-8: TSF Embankment Schematic Cross Section During Operations 354
Figure 15-9: TSF Embankment Schematic Cross Section – Closure 356
Figure 15-10: Transmission lines near the Santa Cruz Project 357
Figure 15-11: Transmission lines near the Santa Cruz Project 361
Figure 17-1: Scope 1 and 2 CO2e Emissions and Avoided Emissions 370
Figure 17-2: Annual CO2e Emissions and Intensities 372
Figure 18-1: Mining Unit Cost Profile 392
Figure 18-2: Longhole Stoping Mining Cost Benchmarking 393
Figure 19-1: Santa Cruz Mining Profile (Tabular Data in Table 19-13 - Without Inferred Material) 400
Figure 19-2: Santa Cruz Mining Profile (Tabular Data in Table 19-14 – Including Inferred Material) 400
Figure 19-3: Santa Crus Processing Profile (Tabular Data in Table 19-13 - Without Inferred Material) 402
Figure 19-4: Santa Cruz Processing Profile (Tabular Data in Table 19-14 – Including Inferred Material) 402
Figure 19-5: LoM Operating Cost Summary (Tabular Data in Table 19-13) 404
Figure 19-6: LoM Operating Cost Contributions 405
Figure 19-7: Santa Cruz Capital Profile (Tabular Data in Table 19-13) 409
Figure 19-8:Annual Cash Flow Summary without Inferred Material (Tabular Data in Table 19-13 – Without Inferred Material) 411
Figure 19-9: Annual Cash Flow Summary with Inferred Material (Tabular Data in Table 19-14 – Including Inferred Material) 411
Figure 19-10: NPV Sensitivity Analysis 418

 

September 2023

SEC Technical Report Summary – Santa CruzPage xxiv

 

List of Abbreviations

 

The metric system has been used throughout this report. Tonnes are metric of 1,000 kg, or 2,204.6 lb. All currency is in U.S. dollars (US$) unless otherwise stated.

 

Abbreviation Unit or Term
% percent
less than
greater than
° degree (degrees)
°C degrees Celsius
°F degrees Fahrenheit
µm micron or microns
2D Two-dimensional
A ampere
A/m2 amperes per square meter
AA atomic absorption
AAS atomic absorption spectrometry
ADEQ Arizona Department of Environmental Quality
ADOT Arizona Department of Transportation
ADWR Arizona Department of Water Resources
ADWS Arizona Drinking Water Standards
Ag silver
AMD acidic and/or metalliferous drainage
ANFO ammonium nitrate fuel oil
APP Aquifer Protection Permit
AR4 Fourth Assessment Report
ASMI Arizona State Mine Inspector
ATV acoustic televiewer
Au gold
AuEq gold equivalent grade
BADCT Best Available Demonstrated Control Technology
BEGPA Bald and Golden Eagle Protection Act
BEV Battery Electric Vehicle
CAP Covered Area Project
CAR Central Arizona Resources
CBA Complete Bouguer Anomaly
CCD Counter Current Decantation
CF cut-and-fill
cfm cubic feet per minute
CIL carbon-in-leach
cm centimeter
cm/s centimeter per second
cm2 square centimeter
cm3 cubic centimeter
cm/y centimeters per year
CNI Call & Nicholas, Inc.
CO2e  carbon dioxide equivalents
CoG cut-off grade
ConfC confidence code
CRec core recovery
CRF cemented rock fill
CSAMT Controlled Source Audio-frequency Magnetotelluric
CSS closed-side setting
CTW calculated true width
CWA Clean Water Act
DAF drift and fill
dia. diameter

 

September 2023

SEC Technical Report Summary – Santa CruzPage xxv

 

Abbreviation Unit or Term
DRHE DR Horton Energy
EIS Environmental Impact Statement
ELOS equivalent length of slough
EMP Environmental Management Plan
EPA Environmental Protection Agency
ESR excavation support ratio
FA fire assay
FEMA Federal Emergency Management Agency
FoS Factor of Safety
FRS fiber-reinforced shotcrete
FS Fast-Static
ft foot (feet)
ft2 square foot (feet)
ft3 cubic foot (feet)
g gram
G&A general and administrative
g/L grams per liter
g/t grams per tonne
gal gallon
GHGs greenhouse gases
GIS Geographic Information System
g-mol gram-mole
gpm gallons per minute
GSI geological strength index
GWPs global warming potentials
ha hectares
HDPE Height Density Polyethylene
HG high-grade
hp horsepower
HTW horizontal true width
IA Initial Assessment
IAS International Accreditation Service
ICP inductively coupled plasma
ICP-OES inductively coupled plasma optical emission spectrometry
ID2 inverse-distance squared
ID3 inverse-distance cubed
IE Ivanhoe Electric Inc.
IFC International Finance Corporation
ILS Intermediate Leach Solution
IPCC Intergovernmental Panel on Climate Change's
kA kiloampere
kg kilogram
km kilometer
km2 square kilometer
koz thousand troy ounce
kPa kilopascal
kt thousand tonnes
kt/d thousand tonnes per day
kt/y thousand tonnes per year
kV kilovolt
kW kilowatt
kWh kilowatt-hour
kWh/t kilowatt-hour per metric tonne
L liter
L/h liters per hour
L/sec liters per second

 

September 2023

SEC Technical Report Summary – Santa CruzPage xxvi

 

Abbreviation Unit or Term
L/sec/m liters per second per meter
lb pound
LG low-grade
LHD long-haul dump truck
LHS longhole stoping
line-km line kilometer
LLDDP Linear Low Density Polyethylene Plastic
LME London Metal Exchange
LOI Loss On Ignition
LoM life-of-mine
m meter
m.y. million years
m/d meters per day
m/s meters per second
m2 square meter
m3 cubic meter
m3/s cubic meters per second
MARN Ministry of the Environment and Natural Resources
masl meters above sea level
MBTA Migratory Bird Treaty Act
MDA Mine Development Associates
MG medium grade
mg/L milligrams/liter
ML Metal Leaching
Mlb million pounds
MLRP Mined Land Reclamation Plan
mm millimeter
mm2 square millimeter
mm3 cubic millimeter
MME Mine & Mill Engineering
Mm3 million cubic meters
Mm3/y million cubic meters per year
Moz million troy ounces
MPa megapascal
MSO mining unit shape optimizer
Mt million tonnes
MTW measured true width
MW million watts
MWh/y megawatt hours per year
MW(R) megawatts of refrigeration
NEPA National Environmental Policy Act
NGO non-governmental organization
NI 43-101 Canadian National Instrument 43-101
NN Nearest Neighbor
NRHP National Register of Historic Places
OHWM ordinary high-water mark
OK ordinary kriging
OSC Ontario Securities Commission
oz troy ounce
PAD Planned Area of Development
PBF paste backfill
PCAQCD Pinal County Air Quality Control District
pCi/L picocuries per liter
PFS prefeasibility study
PLC Programmable Logic Controller
PLS Pregnant Leach Solution
PMF probable maximum flood

 

September 2023

SEC Technical Report Summary – Santa CruzPage xxvii

 

Abbreviation Unit or Term
ppb parts per billion
ppm parts per million
PST primary-seconday-tertiary
QA/QC Quality Assurance/Quality Control
RC reverse circulation
RCRA Resource Conservation Recovery Act
REC  recognized environmental condition
RMR76 Bieniawski’s rock mass rating
ROFO Right of First Offer
ROFR Right of First Refusal
RoM Run-of-Mine
RQD Rock Quality Designation
RTK  Real-Time Kinematic
S.C. Santa Cruz
SCR Selective Catalytic Reduction
SCJV Joint venture between ASARCO Santa Cruz Inc. and Freeport McMoRan Copper & Gold Company
SEC U.S. Securities & Exchange Commission
sec second
SEQ sequential acid leaching
SG specific gravity
SLS  solid-liquid separation
SPT standard penetration testing
SRHA Stockraising Homestead Act
st short ton (2,000 pounds)
SUA Surface Use Agreement
t tonne (metric ton) (2,204.6 pounds)
t/d tonnes per day
t/h tonnes per hour
t/y tonnes per year
TIMA Tescan Integrated Mineral Analyser
TSF tailings storage facility
TSP total suspended particulates
UCS unconfined compressive strength
UIC Underground Injection Control
USACE U.S. Army Corps of Engineers
USCS Unified Soil Classification System
USFWS U.S. Fish and Wildlife Service
V volts
VFD variable frequency drive
VOC Volatile Organic Compounds
VWP vibrating wire piezometer
W watt
WestLand WestLand Engineering & Environmental Services
WOTUS Waters of the United States
XRD x-ray diffraction
XRF x-ray fluorescence
y year

 

September 2023

SEC Technical Report Summary – Santa CruzPage 28

 

1Executive Summary

 

This report was prepared as an initial assessment level Technical Report Summary in accordance with the Securities and Exchange Commission (SEC) S-K regulations (Title 17, Part 229, Items 601 and 1300 through 1305) for Ivanhoe Electric (IE or the Company) by SRK Consulting (U.S.), Inc. (SRK) and other Qualified Persons as identified in section 2.8 on the Santa Cruz Project.

 

Sections of this report pertaining to geology and mineral resources were authored by Nordmin Engineering Ltd. (Nordmin). Sections of this report pertaining processing and infrastructure were authored by M3 Engineering and Technology Corp. (M3). Sections of this report pertaining to tailings storage were authored by KCB Consultants Ltd. (KCB). Sections of this report pertaining to geotechnical studies were authored by Call & Nicholas, Inc. (CNI) Sections of this report pertaining to hydrogeology were authored by INTERA Incorporated (INTERA). Sections of this report pertaining to environmental studies were authored by Tetra Tech, Inc. (Tetra Tech). Sections of this report pertaining to geochemistry and water quality were authored by Life Cycle Geo, LLC (LGC). Sections of this report pertaining to mine closure were authored by Haley & Aldrich, Inc. (H&A). Sections of this report pertaining to power sources and green power were authored by Met Engineering, LLC (Met Engineering). Further detail on the specific sections that were authored by each Qualified Person is set out in section 2.8. None of the Qualified Persons are affiliated with IE or another entity that has an ownership, royalty, or other interest in the property.

 

1.1Property Description, Mineral Tenure, Ownership, Surface Rights, Royalties, Agreements, and Permits

 

The Santa Cruz Project is located 11 kilometers (km) west of the town of Casa Grande, Arizona, and is approximately one hour’s drive south of the capital Phoenix and covers a cluster of deposits about 11 km long and 1.6 km wide. The Santa Cruz Project centroid is approximately -111.88212, 32.89319 (WGS84) in Township 6 S, Range 4E, Section 13, Quarter C.

 

The Santa Cruz Project lies primarily on private land, which is dominantly fee simple (complete and irrevocable ownership). Surface titles and associated rights were acquired by IE in 2022 and 2023 as purchases and options on private parcels. Mineral title for the Project was acquired in 2021 via an agreement with Central Arizona Resources (CAR) for the right to acquire 100% of CAR’s option over the DR Horton Energy (DRHE) mineral title.

 

DRHE also holds 39 Federal unpatented mining claims in T06S R04E in N/2 Section 12, W/2 Section 23 and W/2 Section 24.

 

Royalties

 

Noted royalties on future mineral development of the Project are summarized here:

 

·Royalty interests in favor of the royalty holders of a 5% net smelter return royalty interest for minerals derived from all portions of the property pursuant to terms contained therein recorded in the royalty document.
·Royalty interests in favor of the royalty holder of a 10% net smelter return royalty interest in sections 13, 18, 19, and 24, Township 6 South, Range 4 East, for minerals derived from the property pursuant to terms contained therein recorded in the royalty document.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 29

 

·Rights conveyed to the royalty holder in sections 13, 18, 19, and 24, Township 6 South, Range 4 East, consisting of 10% of one eight-hundredth of Fair Market Value and interest in the Cu and other associated minerals with additional terms, conditions, and matters contained therein, recorded in the royalty documents.
·Rights granted to the royalty holders, as joint tenants with right of survivorship, a royalty in sections 13, 18, 19, and 24, Township 6 South, Range 4 East, consisting of 30% of five tenths of 1% of the net smelter return from all minerals with additional terms, conditions, and matters contained therein, recorded in the royalty documents.
·Rights conveyed to the royalty holder in sections 13, 23, 24, 25, and 26, Township 6 South, Range 4 East and sections 5, 6, 18, 18, 19, and 30, Township 6 South, Range 5 East, consisting of 60% of one eighth-hundredth of Fair Market Value and interest in the Cu and other minerals with additional terms, conditions, and matters contained therein, recorded in the royalty documents.
·Reservation of a 1% royalty interest in favor of the royalty holder recorded in the royalty document, for E1/2 of Section 5, Township 6 South, Range 5 East, south and west of Southern Pacific RR, “that when mined or extracted therefrom shall be equal in value to 1% of the net smelter returns on all ores, concentrated, and precipitates mined, and shipped from said property.
·Reservation of a royalty interest in favor of the royalty holders in the SW1/4 of Section 17, Township 6 South, Range 5 East, for an amount equal to one half of 1% net smelter returns in the sale and disposal of all ores, minerals, and other products mined and removed from the above described parcel and sold to a commercial smelter or chemical hydrometallurgical plant or one half of 1% of 60% of the sales price if the mine product is disposed of other than to a commercial smelter, additional provisions contained therein, recorded in the royalty documents.

 

Permits

 

Current exploration is conducted on private land. State, County, and Municipal permits for exploration, development, and operations are prepared as needed. The ability to operate on private land has the potential to reduce lengthy permitting timelines that result from federal permitting processes. The precise list of permits required to authorize the construction and operation of this Project will be determined as the mining and processing methods are designed.

 

1.2Geology and Mineralization

 

The Santa Cruz Project is located within the Southwestern Porphyry Copper Belt. The Belt includes many productive copper deposits in Arizona such as Mineral Park, Bagdad, Resolution, Miami-Globe, San Manuel-Kalamazoo, Ray, Morenci, Sierrita, Twin Buttes, and the neighboring historical Sacaton Mine. These deposits lie within a broader physiographic region known as the Basin and Range province that covers much of the Southwest United States. . The porphyry copper deposits within the Southwestern Porphyry Copper Belt include the genetic product of igneous activity during the Laramide Orogeny (80 Ma to 50 Ma) when subduction of the Farallon Tectonic Plate beneath the North American Tectonic Plate produced a magmatic arc and associated porphyry copper systems.

 

The Santa Cruz Project is comprised of five separate areas along a southwest-northeast corridor. These areas from southwest to northeast are known as the Southwest Exploration Area, the Santa Cruz deposit, the East Ridge deposit, the Texaco Ridge Exploration Area, and the Texaco deposit, all of which represent portions of one or more large porphyry copper systems separated by extensional Basin and Range normal faults. Each area has experienced variable periods of erosion, supergene enrichment, fault displacement, and tilting into their present positions.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 30

 

Mineralization at the Santa Cruz Project is divided into three main groups:

 

·Primary hypogene sulfide mineralization consists of chalcopyrite, pyrite, and molybdenite hosted within quartz-sulfide stringers, veinlets, veins, vein breccias, and breccias and alteration related to Laramide-aged porphyritic dykes (75 Ma).
·Secondary supergene sulfide mineralization is dominantly chalcocite which rims primary hypogene sulfide and completely replaces hypogene disseminated and vein-hosted sulfides.
·Supergene copper oxide mineralization is comprised dominantly by chrysocolla (copper silicate) with subordinate dioptase, tenorite, cuprite, copper wad, native copper, and as copper-bearing smectite group clays. Superimposed in-situ within the copper oxide zone is atacamite (copper chloride), copper sulfates, antlerite, and chalcanthite.

 

1.3Status of Exploration, Development and Operations

 

Copper mineralization was first discovered in the region in the 1960’s and led to extensive drill programs across the Santa Cruz Project area. Exploration programs by several companies and joint ventures included diamond drilling and several geophysical surveys between the 1960’s through the 1990’s. IE completed an updated mineral resource estimate on December 31, 2022 entitled “Mineral Resource Estimate Update and S-K 1300 Technical Report Summary for the Santa Cruz, Texaco, and East Ridge Deposits, Arizona, USA.”

 

IE exploration in 2021 – 2022 included:

 

·Geophysical surveys – ground gravity, ground magnetics, Typhoon™ three-dimensional Perpendicular Pole Dipole Induced Polarization (3D PPD IP), refraction, and passive seismic.
·Drilling – a combination of diamond drill and rotary drilling totaling 88 holes and approximately 55,291 meters (m)

 

IE exploration in 2023, to June 8, 2023, included:

 

·Drilling – a combination of diamond drill and rotary drilling totaling 36 holes and approximately 29,322.02 m. This data is not part of the mineral resource estimate.
·Exploration is continuing around the Project to identify new zones that may be incorporated into future studies.

 

Combined with the historical exploration, there are over 200 drillholes totaling over 162 km within the Santa Cruz Project area.

 

1.4Sample Analysis and Security

 

From September 2021 to December 2022, IE samples were sent to one of four laboratories: Skyline Laboratories facility located in Tucson, SGS Laboratories located in Burnaby, BC, Canada, SGS Lakefield, ON, Canada for SEQ Copper Analysis, or Arizona, American Assay Laboratories located in Sparks, Nevada. All samples sent to SGS Laboratories were prepared at SGS Burnaby, BC, Canada. At the time, all assay labs were well established and recognized assay and geochemical analytical services companies and are independent of IE.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 31

 

All four laboratories are recognized by the International Standard demonstrating technical competence for a defined scope and the operation of a laboratory quality management system (ISO 17025). Additionally, Skyline Laboratories is recognized by ISO 9001, indicating that the quality management system conforms to the requirements of the international standard. SGS Canada Minerals Burnaby conforms to requirements of ISO/IEC 17025 for specific tests as listed on their scope of accreditation. American Assay Laboratories carries approval from the State of Nevada Department of Conservation and Natural Resources Division of Environmental Protection. Due to QA/QC failures at American Assay Laboratories, IE discontinued work with this lab.

 

Specific gravity (SG) measurements for the Santa Cruz, Texaco, and East Ridge deposits were provided during 2021-2022 on site drill core measurements. SG measurements were taken from representative core sample intervals and measured using a water dispersion method.

 

The Santa Cruz, Texaco, and East Ridge core is stored in wax impregnated core boxes and transported to the core logging shack. After being logged, the core boxes are palletized, weatherized, and stored in IE’s core storage facilities. The core storage is locked behind bay doors or chain link fencing for security purposes. All samples for analyses are transported by courier to the laboratory in Tucson, Arizona, or Burnaby, BC, Canada.

 

1.5Mineral Processing and Metallurgical Testing

 

Metallurgy and processing test work were directed by Met Engineering LLC and conducted at McClelland Labs in Sparks, Nevada. McClelland Labs is recognized by the International Accreditation Service (IAS) for its technical competence and quality of service and has proven that it meets recognized standards. The studies are ongoing. Study focus has been on:

 

·Confirming total copper recovery of the leach-float flow sheet proposed by historical operator, CGCC, circa 1980, on Exotic, Oxide and Chalcocite mineral domains.
·Investigating heap leaching of Exotic, Oxide and Chalcocite mineral domains. The test program for heap leaching is in progress and is reported as such in section 10. Some early results are described below. Column leach testing will complete in the fourth quarter of 2023.

 

Agitation leach tests undertaken in mid-2022 verified historical test results and after adjusting the particle size distribution, acid-soluble copper recovery of 92% was achieved. IE subsequently conducted a leach-float test program in which the same mill composite sample used in prior testing was subjected to the standard leach procedure developed earlier in the year. Three standard leach tests were conducted, each subjected to different grind sizes. IE successfully confirmed that up to 94% total copper recovery with the leach-float circuit was achievable at the Santa Cruz deposit. It was confirmed that a smelter saleable concentrate could be produced without any penalties grading 48% total copper and 23% sulfur.

 

One column cell test has been completed and is in the phase of water rinsing and removing leach residue for analysis. The seven remaining column cell tests are operating normally and are all in the final stage of secondary sulfide leaching. There were no solution flow issues in any of the eight column cells. There were no significant operational issues on any of the column cells. Estimated copper recoveries and extraction rates on the two column cells cured with a chloride dopant were 98% and 94% copper and 70 and 63 days, respectively.

 

There are some factors to follow up on with future testing to ensure all processing factors are effectively investigated. These are confirmation of corrosion resistant materials and linings for the thickeners in the counter-current-decantation system for pregnant leach solution recovery and studying sulfide flotation with expected process water chemistry at the site. Otherwise, there are no deleterious elements that could have a significant effect on economic extraction.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 32

 

1.6Mineral Resource Estimate

 

This IA is based upon the December 31, 2022, Mineral Resource Estimate (MRE) which includes a detailed geological and structural re-examination of the Santa Cruz, East Ridge, and Texaco deposits.

 

The Santa Cruz deposit MRE benefits from approximately 116,388 m of diamond drilling in 129 drillholes, the East Ridge deposit MRE has 18 holes totaling 15,448 m, and the Texaco deposit MRE has 23 drillholes totaling 21,289 m (Table 1-1). All drillholes included in the December 2022 MRE were completed from 1964 to 2022.

 

Diamond drillhole samples were analyzed for total Cu and acid soluble Cu using atomic absorption spectrometry (AAS). A decade after initial drilling, ASARCO re-analyzed select samples for cyanide soluble Cu (AAS) and molybdenum (multi-element ICP). The Company currently analyzes all samples for total Cu, acid soluble Cu, cyanide soluble Cu, and molybdenum. Due to the re-analyses to determine cyanide soluble Cu within historic samples, there are instances where cyanide soluble Cu is greater than total Cu. It has been determined that the historic cyanide soluble assays are valid as they align with recent assays in 2022 drillholes.

 

Table 1-1: December 2022 MRE Drillhole Summary

 

  Total Drilling IE Drilling
Deposit

Number of

Drillholes

Meters
(m)
Meters Intersecting
the Deposit

Number of

Drillholes

Meters
(m)
Meters Intersecting
the Deposit
Santa Cruz 129 116,388 57,326 41 34,769 14,172
East Ridge 18 15,448 1,501 0 0 0
Texaco 23 21,289 2,661 3 3,286 685
Total 170 153,125 61,488 44 38,055 14,857

 

Source: Nordmin, 2023

 

Geological domains were developed within the Santa Cruz Project based upon geographical, lithological, and mineralogical characteristics, along with incorporating both regional and local structural information. Several extensional fault systems are recognized at Santa Cruz with a transport direction towards the south-west of which deformation event 1 (D1) is the oldest, followed by deformation event 2 (D2) faulting. Local D2 fault structures separate the mineralization at the adjacent Santa Cruz, Texaco, and East Ridge deposits. The Santa Cruz, Texaco, and East Ridge deposits were divided into four main geological domains based upon their type of Cu speciation, including primarily acid soluble (Oxide Domain), cyanide soluble (Chalcocite Enriched Domain), primary Cu sulfide (Primary Domain), and exotic Cu (Cu oxides in overlying Tertiary sediments). All four domains are present within the Santa Cruz deposit, whereas all mineralization at East Ridge is within an Oxide Domain, and Texaco is comprised of all but an Exotic Domain.

 

Mineralization wireframes were initially created to reflect the known controls on each mineralization type. Once a geologic interpretation was established, wireframes were created. When not cut-off by drilling, the wireframes terminate at either the contact of the Cu-oxide boundary layer, the Tertiary sediments/Oracle Granite (as defined below) contact, or the D2 fault structure. There is an overlap of the Chalcocite Enriched Domain with both the Oxide Domain in the weathered supergene and with the Primary Domain in the primary hypogene mineralization. Otherwise, no wireframe overlapping exists within a given grade domain. Implicit modeling was completed in Leapfrog Geowhich produced reasonable mineral domains that appropriately represent the known controls on grade mineralization.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 33

 

A block model for each deposit was created that incorporated lithological, structural, and mineralization trends and selection of the block modeling parameters. Each block model validation process included visual comparisons between block estimates and composite grades in plan and section views, local versus global estimates for NN, ID2, ID3, and OK when available, and swath plots. The Santa Cruz deposit block model was estimated using Nearest Neighbor (NN), inverse distance squared (ID2), inverse distance cubed (ID3), and ordinary kriging (OK) interpolation methods for global comparisons and validation purposes. The OK method was used for the Mineral Resource Estimate; it was selected over ID2, ID3, and NN as the OK method was the most representative approach to controlling the smoothing of grades. The Texaco and East Ridge block models were estimated using NN, ID2, and ID3, and the ID3 method was used for the mineral estimate for the Texaco and East Ridge deposits.

 

Nordmin considers that the interpreted geological and mineralization domains produced accurately represent the deposit style of the Santa Cruz, Texaco, and East Ridge deposits.

 

The MRE was classified in accordance with S-K 1300 definitions. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. This estimate of Mineral Resources may be materially affected by environmental permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

 

Mineral Resource Classification was assigned to regions of the block model based on the Nordmin QP’s confidence and judgment related to geological understanding, continuity of mineralization in conjunction with data quality, spatial continuity based on variography, estimation pass, data density, and block model representativeness.

 

The areas of greatest uncertainty are attributed to Inferred Mineral Resources, which are areas with limited drilling and/or large drill spacing (greater than (>) 100 m). Indicated Mineral Resources are resources derived from adequately detailed and reliable exploration, sampling, and testing, and are sufficient to assume geological and grade or quality continuity between points of observation. In the Santa Cruz deposit, the drill spacing that supports the Indicated Mineral Resource classification constitutes approximately 80 m to 100 m. There is the possibility for Indicated Mineral Resources to be upgraded to Measured Mineral Resources via additional infill drilling that would reduce the drill spacing to less than (<) 25 m. Currently none of the deposits have a Measured Mineral Resource.

 

The 2021 twin drilling program conducted by IE, outlined in Sections 7.3.3 and 9.3, has demonstrated overall grade continuity, location, and continuity between intercepts. There is the potential for unknown errors within the database which could affect the size and quantity of Measured, Indicated, and Inferred Mineral Resources.

 

While most of the Texaco deposit is classified as Inferred, there is a small portion of Indicated Mineral Resource. The East Ridge deposit is currently classed as Inferred, as the area is defined by historic drilling which has yet to be validated with modern drilling. This work is forthcoming and will help to improve resource class confidence in subsequent iterations.

 

To demonstrate reasonable prospects for economic extraction for the Santa Cruz, Texaco, and East Ridge Mineral Resource Estimates, representational minimum mining unit shapes were created using Deswik’s minimum mining unit shape optimizer (MSO) tool.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 34

 

The Santa Cruz Project Mineral Resource Estimate, which is exclusive of mineral reserves, is presented in Table 1-2.

 

Table 1-2: In situ Santa Cruz Project Mineral Resource Estimates at 0.70% Cu cut-off for Santa Cruz, 0.80% Cu cut-off for Texaco, and 0.90% Cu Cut-off for East Ridge

 

Classification Deposit

Mineralized

Material

(kt)

Mineralized

Material

(k ton)

Total

Cu

(%)

Total

Soluble Cu

(%)

Acid

Soluble Cu

(%)

Cyanide

Soluble

Cu (%)

Total Cu

(kt)

Total

Soluble Cu

(kt)

Acid

Soluble Cu

(kt)

Cyanide

Soluble Cu

(kt)

Total Cu

(Mlb)

Indicated

Santa Cruz

(0.70% CoG)

223,155 245,987 1.24 0.82 0.58 0.24 2,759 1,824 1,292 533 6,083

Texaco

(0.80% CoG)

3,560 3,924 1.33 0.97 0.25 0.73 47 35 9 26 104

East Ridge

(0.90% CoG)

0 0 0.00 0.00 0.00 0.00 0 0 0 0 0
Inferred

Santa Cruz

(0.70% CoG)

62,709 69,125 1.23 0.92 0.74 0.18 768 576 462 114 1,694

Texaco

(0.80% CoG)

62,311 68,687 1.21 0.56 0.21 0.35 753 348 132 215 1,660

East Ridge

(0.90% CoG)

23,978 26,431 1.36 1.26 0.69 0.57 326 302 164 137 718
Total
Indicated All Deposits 226,715 249,910 1.24 0.82 0.57 0.25 2,807 1,859 1,300 558 6,188
Inferred All Deposits 148,998 164,242 1.24 0.82 0.51 0.31 1,847 1,225 759 466 4,072

 

Source: Nordmin, 2023

Mlb = million pounds 

kt = thousand tonnes

 

Notes on Mineral Resources

 

The Mineral Resources in this Estimate were independently prepared, including estimation and classification, by Nordmin Engineering Ltd. and in accordance with the definitions for Mineral Resources in S-K 1300.
Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. This estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.
Verification included multiple site visits to inspect drilling, logging, density measurement procedures and sampling procedures, and a review of the control sample results used to assess laboratory assay quality. In addition, a random selection of the drillhole database results was compared with the original records.
The Mineral Resources in this estimate for the Santa Cruz, East Ridge, and Texaco deposits used Datamine Studio RMTM software to create the block models.
The Mineral Resources are current to December 31, 2022.
Underground-constrained Mineral Resources for the Santa Cruz deposit are reported at a cut-off grade (CoG) of 0.70% total copper, Texaco deposit are reported at a CoG of 0.80% total copper and East Ridge deposit are reported at a CoG of 0.90% total copper. The CoG reflects total operating costs to define reasonable prospects for eventual economic extracted by conventional underground mining methods with a maximum production rate of 15,000 tonnes per day (t/d). All material within mineable shape-optimized wireframes has been included in the Mineral Resource
Underground mineable shape optimization parameters include a long-term copper price of US$3.70/lb, process recovery of 94%, direct mining costs between US$24.50-$40.00/processed tonne reflecting various mining method costs (long hole or room and pillar), mining general and administration cost of US$4.00/t processed, onsite processing and SX/EW costs between US$13.40-$14.47/t processed, offsite costs between US$3.29 to US$4.67/t processed, along with variable royalties between 5.00% to 6.96% NSR and a mining recovery of 100%.
Specific Gravity was applied using weighted averages by deposit Sub-Domain.
All figures are rounded to reflect the relative accuracy of the estimates, and totals may not add correctly.
Excludes unclassified mineralization located along edges of the Santa Cruz, East Ridge, and Texaco deposits where drill density is poor.
Reported from within a mineralization envelope accounting for mineral continuity.
Total soluble copper means the addition of sequential acid soluble copper and sequential cyanide soluble copper assays. Total soluble copper is not reported for the Primary Domain

 

September 2023

SEC Technical Report Summary – Santa CruzPage 35

 

Areas of uncertainty that may materially impact the Mineral Resource Estimate include:

 

·Changes to long term metal price assumptions
·Changes to the input values for mining, processing, and general and administrative (G&A) costs to constrain the estimate
·Changes to local interpretations of mineralization geometry and continuity of mineralized zones
·Changes to the density values applied to the mineralized zones
·Changes to metallurgical recovery assumptions
·Changes in assumption of marketability of the final product
·Variations in geotechnical, hydrogeological, and mining assumptions
·Changes to assumptions with an existing agreement or new agreements
·Changes to environmental, permitting, and social license assumptions
·Logistics of securing and moving adequate services, labor, and supplies could be affected by epidemics, pandemics and other public health crises including COVID-19 or similar viruses

 

These risks and uncertainties may cause delays in economic resource extraction and/or cause the resource to become economically non-viable.

 

1.7Mineral Reserve Estimate

 

This section is not relevant to this Technical Report.

 

1.8Mining Methods

 

The Project is currently not being mined. Mineral resources are stated for three deposits: Santa Cruz, Texaco, and East Ridge. For mine planning work, only the Santa Cruz and East Ridge deposits were evaluated.

 

Santa Cruz is located approximately 430 to 970 m below the surface. Based on the mineralization geometry and geotechnical information, an underground longhole stoping (LHS) method is suitable for the Oxide and Chalcocite-enriched domains within the deposit. The Santa Cruz deposit will be mined in blocks where mining within a block occurs from bottom to top with paste backfill (PBF) for support. A sill pillar is left in situ between blocks.

 

Within the Santa Cruz deposit, there is an Exotic Domain located approximately 500 to 688 m below the surface and to the east of the main deposit. The Exotic Domain consists of flatter lenses that are more amenable to drift and fill (DAF) mining. Cemented waste rockfill will be used for support. The backfill will have sufficient strength to allow mining of adjacent drifts without leaving pillars.

 

The East Ridge deposit is approximately 380 to 690 m below the surface and to the north of the main Santa Cruz deposit. The East Ridge deposit consists of two tabular lenses and will be mined using DAF with cemented waste rock backfill for support.

 

The mine will be accessed by dual decline drifts from surface, with one drift serving as the main access and the other as a railveyor drift for material handling. Mineralization is transported from stopes via loader to an ore pass system and then to surface by the railveyor. Main intake and exhaust raises will be developed with conventional shaft sinking methods to provide air to the mine workings. The mine will target a combined production of 15,000 t/d from Santa Cruz and East Ridge.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 36

 

Portal box cut is assumed to start in 2026. Decline and railveyor activities begin in 2027 through to 2028 to access the top portion of the mine. Decline and railveyor resumes in 2033 to access the bottom of the mine. Stoping begins in 2029 with a 1 year ramp-up period until the mine and plant are operating at full capacity. The currently defined mine life is approximately 3 years of construction and 20 years of production.

 

Using historical data and the results of recent hydrogeologic testing, the hydrogeological conceptual site model was updated and the groundwater flow model was developed and finalized. The groundwater flow model was used to evaluate multiple passive and active dewatering scenarios for the proposed mine plan. With an active dewatering scenario pumping approximately 3,000 gallons per minute (gpm) for the first two years of life of mine (LoM), the model shows that the annual average residual passive inflows for the first 10 years of the mine are at or below 12,000 gpm. From year 11 through 25 of LoM, the residual passive inflows range from approximately 15,000 to 18,000 gpm.

 

Figure 1-2 shows the completed mine plan. Table 1-3 summarizes the total tonnage and grades within the mine plan by area.

 

 

 

Source: SRK, 2023

 

Figure 1-1: Mine Design, Santa Cruz, Santa Cruz Exotic, and East Ridge

 

September 2023

SEC Technical Report Summary – Santa CruzPage 37

 

Table 1-3: Mine Plan Summary

 

Classification Domain Tonnage
(kt)

Total

Soluble
Cu (%)

Acid

Soluble
Cu (%)

Cyanide

Soluble Cu
(%)

Indicated Santa Cruz 73,582 1.62 1.05 0.39
East Ridge - - - -
Santa Cruz Exotic 1,131 2.79 2.28 0.22
Inferred Santa Cruz 14,991 1.45 0.98 0.32
East Ridge 9,799 1.76 0.95 0.75
Santa Cruz Exotic 741 2.47 1.83 0.17
Indicated + Inferred Santa Cruz 88,573 1.60 1.04 0.38
East Ridge 9,799 1.76 0.95 0.75
Santa Cruz Exotic 1,872 2.66 2.09 0.20
Indicated Total 74,713 1.64 1.07 0.39
Inferred Total 25,530 1.60 0.99 0.48
Indicated + Inferred Total 100,244 1.63 1.05 0.41

 

Source: SRK, 2023

 

Note:4.94 Mt of marginal material at a grade of 0.56% is not included in this table.

 

This work is preliminary in nature, it includes inferred mineral resources that are considered too speculative geologically to have modifying factors applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that this economic assessment will be realized.

 

1.9Recovery Methods

 

The Santa Cruz processing facility will recover copper by conventional weak sulfuric acid agitated leaching of the oxide mineralized material, and by sulfide flotation of the residue produced after leaching. Leached oxide copper will be processed through solvent extraction and electrowinning (SX-EW) to produce high purity copper cathodes. Sulfide copper and by-product precious metals will be recovered in copper flotation mineral concentrate. Copper concentrates will be of suitable quality to be sold to a domestic or international copper smelters.

 

The process design is based on metallurgical tests results from The Hanna Mining Company’s research center (circa 1980) and new IA-level mineral process testing initiated by IE in 2022 and 2023.

 

The process flow diagram in Figure 1-3 illustrates sequence of operations to recover copper in the Santa Cruz plant. This flowsheet provides the basis for the process description that follows.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 38

 

 

 

Source: M3, 2023

 

Figure 1-2: Process Flow Sheet

 

September 2023

SEC Technical Report Summary – Santa CruzPage 39

 

1.9.1Process Design Criteria

 

The nominal capacity of the mill process is 5.475 million tonnes per year (Mt/y). Process availability factors include both the mechanical availability and the use of this mechanical availability. For the design, an availability factor of 92% is used throughout the plant because the primary and secondary grinding lines have a single ball mill in each.

 

The current mine plan developed for the Project is based on a 365-day calendar year. The yearly mine production tonnage will vary from 4.0 million tonnes (Mt) at the start of production to a high of 5.9 Mt in Year 5 of production.

 

The mass balance was developed for the Santa Cruz process using MetSim mass balance software. The process simulation used overall recoveries of 96% for the acid soluble copper as cathode copper and 93% for the sulfide copper into concentrate. These recoveries are based on 1980 studies and confirmed by mineral process testing in 2023 on recent drill core samples and include process losses attributed to PLS wash efficiency (2023 liquid solid separation test results) and cleaner scavenger flotation losses (1980 and 2023 test programs).

 

1.10Project Infrastructure

 

The Santa Cruz project has excellent existing infrastructure including access to roads and interstate highways, railroads, power lines, and an abundant supply of water from dewatering operations and water rights associated with the private land acquired by IE. The Project owns sufficient fee simple land to allow for all surface infrastructure including the process facility, Tailings Storage Facility (TSF), offices borrow pit, and other related mine structures.

 

Interstate highways near the Project (<10 km) are Interstate 8 and Interstate 10. The Union Pacific/Southern Pacific (UPSP) rail borders the northern edge of the Santa Cruz property and the BNSF rail has a spur and terminal in Phoenix, Arizona.

 

Tailings Storage Facility

 

A significant portion of the mined material will be returned underground as backfill in the mine. Backfill is used to fill voids created during mining. By returning tailings as paste backfill underground, the size and impact of the surface TSF will be reduced.

 

The TSF is proposed to be located on relatively flat terrain directly east of the plant site and sited to avoid: the underground ore body outline; mine’s infrastructure; and the 1% annual exceedance probability (AEP) (1 in 100-yr return period) floodplain from Federal Emergency Management Agency (FEMA) (2007) flood hazard mapping. The TSF is sized to store all the tailings estimated to be produced over the mine life and not used for underground backfill (56.7 Mt, without additional contingency) on surface. The tailings will be retained by a perimeter embankment (up to 50 m high) constructed primarily of compacted, structural fill sourced from on-site borrow areas. The TSF impoundment will be lined with a low-permeability liner, which will be raised within the perimeter embankment for seepage control. During operations, tailings slurry water and precipitation which collects in the TSF will be reclaimed to the mine for use in the mining process or treated (if required) and discharged. At closure, the TSF impoundment will be regraded to prevent ponding and covered with a soil cover and vegetated to limit infiltration and resist erosion. Closure channels will be constructed to shed water off the impoundment surface and over the embankment slopes.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 40

 

Power

 

Power consumption for the Santa Cruz site is anticipated to average 450,000 MWh/y. Initially the source of power for the Project will be provided from a 69 kV power line operated by Pinal County Electric District 3 (ED3). Several other higher voltage transmission lines border the property within close proximity.

 

Power for the Project could be provided from a number of sources, or combination of sources, ranging from grid supply to microgrid renewable energy supply. The goal of the mine development is to achieve much of the energy supply from renewable sources, such as solar or geothermal, either at the start or through a phased in approach during the mine operation. The base case of the project is that the mine will operate using 70% renewable power within the first three years of operations.

 

Water

 

The water balance for the Santa Cruz Project indicates that there will be a surplus of water from the Project from dewatering of the underground operations. The mining and processing operations will consume approximately 3.5 million cubic meters (Mm3) of water per year, while water supplies from dewatering will range from 20 million to over 30 million cubic meters per year (Mm3/y). The amount of water for distribution to local stakeholders during operations will average 27 Mm3/y. The water balance excludes the water rights associated with the surface title of the Project.

 

1.11Market Studies and Contracts

 

The Santa Cruz project is envisioned to produce both copper cathode and copper concentrate into its regional market. Copper demand is driven by both developing and developed locations in the drive towards electrification. Expectations for long term copper demand are positive over the next several decades. This is somewhat tempered in the near term should significant economic headwinds materialize that slow global growth.

 

Global mined copper production in 2022 was estimated at 22 Mt. Long lead times for mine development result in a slow supply response to changes in demand. This dynamic is likely to result in price volatility.

 

A flat copper price of US$3.80/lb has been selected for this study. In the opinion of SRK, this price is generally in-line with pricing over the last 3 years and forward-looking pricing is appropriate for use during an Initial Assessment of the Project with an estimated mine life of 20 years. As the Project progresses, more detailed market work in the form of market studies will be completed to support further study efforts. SRK cautions that price forecasting is an inherently forward-looking exercise dependent upon numerous assumptions. The uncertainty around timing of supply and demand forces has the potential to create a volatile price environment and SRK fully expects that the price will move significantly above and below the selected price over the expected life of the Project.

 

Cathode is assumed to be 100% payable with no premium or discount applied for the purposes of the study. This approach assumes that the cathode has not received registration or certification that would result in a premium; nor is the cathode assumed to contain any deleterious or penalty elements.

 

Concentrate terms for the study are generic terms and do not reflect the presence of any deleterious or penalty elements within the concentrate. Table 1-4 presents the concentrate terms applied for this study.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 41

 

Table 1-4: Concentrate Terms

 

  Item Unit Value
  Payability % 96.5
  Treatment Charge US$/dmt 65
  Refining Charge US$/lb 0.065
  Transport Cost US$/wmt 90

 

Source: SRK, 2023

 

As the Project is an early-stage greenfield project, there are a large number of contracts required for the development and operation of the site. None of the major required contracts have been executed at the time of this study.

 

1.12Environmental, Closure and Permitting

 

The Project is located on private land. Permitting is primarily with the State of Arizona, Pinal County, and City of Casa Grande. While the Project will be required to obtain several permits to operate it is on private land and is not anticipated to be subject to lengthy federal permitting timelines.

 

Baseline studies are underway for resources of concern and studies will continue as the Project develops. There are no known occurrences of federally listed threatened and endangered species and there are no planned impacts to potential federally regulated waters of the US. Portions of the Project site is a known nesting area for burrowing owls protected under the Migratory Bird Treaty Act and US Fish and Wildlife beneficial practices to avoid and minimize impacts to birds have been and will continue to be implemented as the Project develops.

 

The utilization of a renewable microgrid will allow the Santa Cruz Project to produce copper with one of the industry's lowest carbon intensities. Such intensities highlight IE commitment to implementing cutting-edge mining techniques, conserving energy, and utilizing renewable energy.

 

Aside from the pending reclamation plan for exploration activities at the Project, IE has no current obligations to tender post mining performance or reclamation bonds for the Project. Once the facility achieves the level of design necessary to advance to mine development and operation, IE will need to submit and gain approval of an Arizona Department of Environmental Quality (ADEQ)-approved Aquifer Protection Permit (APP) and an Arizona State Mine Inspector (ASMI)-approved Reclamation Plan. The closure approach and related closure cost estimates must be submitted following approval and before facility construction and operation.

 

IE plans to create an all-encompassing environmental, social, and governance framework designed to effectively address any community concerns and ensure that the Santa Cruz Project operates in a socially responsible manner.

 

1.13Capital and Operating Cost Estimates

 

1.13.1Mining Capital Cost Estimate

 

The mining capital cost estimate is based on first principal cost model build-up and budgetary quotes. The total capital estimate is US$960.48 million, this includes an estimated capital of US$878.08 million plus 9.4% contingency of US$82.40 million.

 

Development costs are derived from the mining schedule prepared by SRK. The prepared mining schedule includes meters of development during pre-production, this schedule of meters was combined with unit costs, based on site specific data, to estimate the cost of this development operation. The breakdown of the estimated initial capital costs is shown in Table 1-5.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 42

 

Table 1-5: Estimated Mining Initial Capital Cost

 

  Item US$ Million
  Capital Development Cost 166.99
  Equipment Purchase and Rebuilds 241.24
  Mine Services 17.96
  Owner Cost 32.75
  Contingency 38.76
  Total 497.70

 

Source: SRK, 2023

 

The Santa Cruz Project will require sustaining capital to maintain the equipment and all supporting infrastructure necessary to continue operations until the end of its projected production schedule. The sustaining capital cost estimate developed includes the costs associated with the engineering, procurement, construction and commissioning.

 

The estimate indicates that the Project requires sustaining capital of US$462.78 million to support the projected production schedule through the LoM. The sustaining capital cost is shown in Table 1-6.

 

Table 1-6: Estimated Mining Sustaining Capital Cost

 

  Item US$ Million
  Capital Development Cost 60.79
  Equipment Purchase and Rebuilds 322.64
  Mine Services 0.00
  Owner Cost 35.71
  Contingency 43.63
  Total 462.78

 

Source: SRK, 2023

 

1.13.2Process Capital Cost Estimate

 

The initial capital cost for the Santa Cruz plant and infrastructure facilities totals US$563.7 million as summarized in Table 1-7. This capital cost includes all process areas facilities in the Santa Cruz plant proper starting with the primary crushing, and continuing through grinding, agitated leaching, solvent extraction and electrowinning, leach residue neutralization, leach residue grinding, rougher flotation, concentrate regrinding, cleaner flotation, concentrate dewatering and tailing dewatering and pumping to the TSF. The initial capex includes the ventilation chiller for the underground mine, the main plant substation, fresh and process water ponds, and the batch plant, and the surface ancillary buildings.

 

Table 1-7: Estimated Initial Plant Capital Cost Summary

 

  Description Hours

Total Cost

(US$ million)

% of Total Capital Cost
  Directs 1,290,000 345.4 61.3
  Indirects   72.0 12.8
  Contingency   111.3 19.7
  Owner's Costs   35.0 6.2
  Escalation   - 0.0
  Total Capital Cost (TCC)   563.7 100.0

 

Source: M3, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 43

 

No sustaining capital costs have been included for the Santa Cruz process plant. The mine life is 20 years, and the capital equipment will be designed to last for the duration of the Project. Preventative maintenance and periodic rebuilds/relining is captured in the annual maintenance cost estimation. The only place where sustaining capital is expected is in the TSF for annual embankment enlargement which was estimated separately.

 

1.13.3Tailings Capital Cost Estimate

 

The initial capital cost for the Santa Cruz tailings facilities totals US$75.1 million as shown in Table 1-8. The estimated sustaining capital costs total US$486.8 million as shown in Table 1-9. The key elements of the tailings capital cost estimation methodology include:

 

Material take offs by year were provided by KCB

 

Earthworks, lining, and piping rates from standard schedule

 

Borrow-to-fill provided by budgetary quotation – Turner Mining Group

 

Table 1-8: Estimated TSF Initial Capital Cost

 

  Item US$ Million
  Directs 48.8
  Indirects 11.3
  Contingency 15.0
  Total 75.1

 

Source: M3, 2023

 

Table 1-9: Estimated TSF Sustaining Capital Cost

 

  Item US$ Million
  Sustaining 382.2
  Closure 104.6
  Total 486.8

 

Source: M3, 2023

 

1.13.4Mining Operating Cost Estimate

 

The required mining equipment fleet, required production operating hours, and manpower to arrive at an estimate of the mining costs that the mining operations would incur was estimated. The mining costs were developed from first principles and compared to recent actual costs.

 

A maintenance cost was allocated to each category that required equipment maintenance. A summary of the LoM unit mine operating costs is presented in Table 1-10.

 

Table 1-10: Mining Operating Costs

 

  LoM Tonnes Mined (000)  107,134*
  Category US$000 US$/t Mined
  Operating Development 481,021 4.49
  Production (Drilling, Blasting, Loading, Hauling and Backfill) 1,139,843 10.64
  Other mining costs (Services, Maintenance, Rehab and Definition Drilling) 458,564 4.28
  Mine engineering and administration 592,085 5.54
  Contingency (9.5%) 254,664 2.39
  Total 2,926,177 27.33

 

* LoM Tonnes mined includes 100,244 kt of process material, 4,942 kt of marginal material and 1,948 kt of waste.

Source: SRK, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 44

 

1.13.5Processing Operating Cost Estimate

 

The process plant operating costs are summarized by the categories of labor, electric power, liners (wear steel), grinding media, reagents, maintenance parts, and supplies and services, as presented in Table 1-11.

 

Table 1-11: Process Plant OPEX Summary by Category

 

  Operating and Maintenance

Average Annual Cost

(US$000)

$/t Processed

(US$)

LoM Operating Cost

(US$000)

%
  Labor 11,119 2.11 222,383 16.8%
  Electrical Power 23,297 4.43 465,939 35.1%
  Reagents 18,447 3.51 368,947 27.8%
  Wear Parts (Liners & grinding media) 6,811 1.30 136,221 10.3%
  Maintenance Parts 5,993 1.14 119,865 9.0%
  Supplies and Services 628 0.12 12,557 0.9%
  Total (US$000) $66,296 $12.61 $1,325,912 100.0%

 

Source: M3, 2023

 

TSF operating costs are included in the processing operating costs and include labor, power, reagents, and maintenance.

 

1.13.6G&A Operating Cost Estimate

 

The G&A and laboratory costs are summarized in Table 1-12.

 

Table 1-12: G&A Operating Cost Summary

 

   

US$/t processed

(US$)

LoM Operating Cost

(US$000)

  Lab Opex 0.24 24,798
  G&A Opex 2.39 251,543
  Total $2.63 $276,341

 

Source: M3, 2023

 

1.14Economic Analysis

 

Economic analysis, including estimation of capital and operating costs is inherently a forward-looking exercise. These estimates rely upon a range of assumptions and forecasts that are subject to change depending upon macroeconomic conditions, operating strategy and new data collected through future study or operations and therefore actual economic outcomes often deviate significantly from forecasts.

 

The Santa Cruz Project consists of an underground mine and processing facility producing both copper concentrate and copper cathode.

 

The economic analysis metrics are prepared on annual after-tax basis in US$. The results of the analysis are presented in Table 1-13. The results indicate that, at a copper price of US$3.80/lb, the Project without inferred material returns an after-tax net present value (NPV) at 8% of US$0.5 billion calculated from the start of construction, an after tax internal rate of return (IRR) of 14% and a payback period from the start of construction of 10 years. When the inferred material is included in the economic analysis, the after tax NPV at 8% increases to US$1.3 billion, the after tax IRR increases to 23% and the payback period decreases to 7 years from the start of construction.

  

This assessment is preliminary in nature and is based on mineral resources. Unlike mineral reserves, mineral resources do not have demonstrated economic viability. This assessment also includes inferred mineral resources that are considered too speculative geologically to have modifying factors applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that this economic assessment will be realized.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 45

 

The economic model is based on mine plans that were prepared as outlined in previous sections. Inferred resources account for approximately 21% of the tonnage contained within the mine plan. The economic results of the Project both without inferred resources and including inferred resources are presented within this section. However, the removal of the inferred material from the mine plan is a gross adjustment and no recalculation of fixed capital and operating costs has been completed for the scenario without inferred mineral resources.

 

As the stage of study for the Santa Cruz Project is Initial Assessment, no reserves are estimated for use in this analysis. The economic evaluation was completed using resource material that includes material in the Inferred category. To evaluate the risk associated with the use of Inferred material in the mine plan, a model was completed where the Inferred material was removed from the mine plan. SRK notes that this model result should be viewed with caution as the removal of the Inferred material is a gross adjustment and no corresponding adjustments to capital, operating cost or mill performance were made.

 

Table 1-13: Indicative Economic Results

 

  LoM Cash Flow (Unfinanced) Units Value (without Inferred) Value (with Inferred)
  Total Revenue US$ million 10,031.6 12,865.9
  Total Opex US$ million (4,616.9) (4,617.0)
  Operating Margin US$ million 5,414.7 8,248.9
  Operating Margin Ratio % 54% 64%
  Taxes Paid US$ million (426.6) (984.8)
  Free Cash Flow US$ million 3,241.1 5,350.1
  Before Tax  
  Free Cash Flow US$ million 2,549.5 5,216.7
  NPV at 8% US$ million 583.4 1,642.5
  IRR % 15% 25%
  After Tax  
  Free Cash Flow US$ million 2,122.9 4,231.9
  NPV at 8% US$ million 457.7 1,316.6
  IRR % 14% 23%
  Payback years 10 7

 

Source: SRK, 2023

 

Within the constraints of this analysis, the Project appears to be most sensitive to material classification, mined grades, commodity prices and recovery assumptions within the processing plant.

 

A summary of the cash flow on an annual basis is presented in Figure 1-4 and Figure 1-5.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 46

 

 

Source: SRK, 2023

 

Figure 1-3: Annual Cash Flow Summary (Tabular data in Table 19-3 – Without Inferred material)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 47

 

 

 

Source: SRK, 2023

 

Figure 1-4: Annual Cash Flow Summary (Tabular data in Table 19-14 – Including Inferred Material)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 48

 

1.15Conclusions and Recommendations

 

Under the assumptions presented in this Technical Report Summary, and based on the available data, the Mineral Resource Estimates show reasonable prospects of economic extraction.

 

The recommended program is for the company to complete a pre-feasibility study (PFS) level Technical Report. The work program required to complete a PFS will consist of associated infill and exploration drilling, analytical and metallurgical test work, hydrogeological and geotechnical drilling, geological modeling, mine planning, and environmental baseline studies to support permitting efforts.

 

Specific conclusions and recommendations by discipline are as follows:

 

Process Facilities

 

Processing technologies used in this study have been proven at large scales in the industry (mill ores):

 

Agitation leaching of copper oxide minerals with sulfuric acid followed by SX-EW to produce salable copper cathodes.

 

Sulfide flotation to produce salable copper chalcocite/chalcopyrite concentrate.

 

The milling and process facilities can be expanded within the current process area footprint to accommodate processing additional ore as needed. In the next stage of analysis, some process trade-off studies should be evaluated with regards to optimizing process capital and operating costs.

 

Economics

 

The Santa Cruz Project consists of an underground mine and processing facility producing both copper concentrate and copper cathode. The operation is expected to have a 20 year mine life. Under the forward-looking assumptions modeled and documented in this report, the operation is forecast to generate positive cash flow. This estimated cash flow is inherently forward-looking and dependent upon numerous assumptions and forecasts, such as macroeconomic conditions, mine plans and operating strategy, that are subject to change.

 

The economic analysis metrics are prepared on annual after-tax basis in US$. The results indicate that, at a copper price of US$3.80/lb, the Project without inferred material returns an after-tax NPV at 8% of US$0.5 billion calculated from the start of construction, an after tax IRR of 14% and a payback period from the start of construction of 10 years. When the inferred material is included in the economic analysis, the after tax NPV at 8% increases to US$1.3 billion, the after tax IRR increases to 23% and the payback period decreases to 7 years from the start of construction.

 

This assessment is preliminary in nature and is based on mineral resources. Unlike mineral reserves, mineral resources do not have demonstrated economic viability. This assessment also includes inferred mineral resources that are considered too speculative geologically to have modifying factors applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that this economic assessment will be realized.

 

The economic model is based on mine plans that were prepared as outlined in previous sections. Inferred resources account for approximately 21% of the tonnage contained within the mine plan. The economic results of the Project both without inferred resources and including inferred resources are presented within this section. However, the removal of the inferred material from the mine plan is a gross adjustment and no recalculation of fixed capital and operating costs has been completed for the scenario without inferred mineral resources.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 49

 

The analysis performed for this report indicates that the operation’s NPV is most sensitive to the classification of material, the commodity price received, processing plant performance and variations in the grade of ore mined.

 

Geotechnical

 

The Project is amenable to mining using conventional LHS and DAF methods depending on the ore geometries and rock qualities within the geotechnical domains. Access to the orebody will be achievable using roadheader development and drill and blast techniques using industry standard ground support methodologies. To advance the geotechnical understanding of the Project to a PFS level of study the following investigations are recommended:

 

Incorporate additional drill data to further characterize rock quality domains, rock strengths, and geological structure. East Ridge and Texaco should be targeted for additional drilling.

 

Update the geotechnical block model with additional drill data and lithology interpretation.

 

Update all stability analyses using new rock characterization data. This includes stope optimization studies and sill pillar recovery techniques.

 

Continue exploration drilling along potential decline routes to improve decline placement within better rock qualities.

 

Conduct in-situ stress measurements to better understand the current stress field at site. These learnings can be applied to stability analyses and used in numerical modeling.

 

Conduct numerical modeling of the mine sequence to better understand redistributions of mining induced stresses which could be detrimental to stability.

 

An underhand DAF method should be considered for mining at East Ridge and the Exotics at Santa Cruz. An underhand method might allow wider DAF spans but would require additional cement binder and a higher minimum compressive strength requirement.

 

A study should be conducted to evaluate whether mine waste aggregate is suitable for CRF.

 

Hydrogeology

 

The groundwater flow model developed for the Santa Cruz Project shows that with an active dewatering scenario of pumping from the surface approximately 3,000 gpm for the first 2 years of LoM that the annual average residual passive inflows for the first 10 years of the mine are at or below 12,000 gpm. To advance the understanding of the site hydrogeology to the PFS stage, the following investigations are recommended:

 

Additional characterization of the conglomerates and non-mineralized Oracle Granite around the proposed decline.

 

Additional characterization of the variability of hydraulic parameters of the mineralized Oracle Granite, along with the porphyry and diabase intrusions, around the Santa Cruz, East Ridge, and Texaco deposits.

 

Characterization of the hydraulic parameters of the conglomerate within the Exotics at the Santa Cruz deposit.

 

Hydrogeological characterization of the impact of faulting on groundwater movement. Installation of monitoring wells to collect baseline groundwater data.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 50

 

Environmental & Permitting

 

Recommendations for Environmental and Permitting would include the following:

 

Continued environmental baseline data collection to support major local county and state permitting programs.

 

Continue permitting activities and agency engagement for Pinal County Class II air permit, City of Casa Grande General Plan amendment and zoning changes, Arizona Department of Environmental Quality Aquifer Protection and Reclaim Water Discharge permits, and Arizona Department of Water Resources dewatering permit.

 

As the facility engineering progresses, advance the closure and reclamation design and engage Arizona State Mining Inspector to obtain an approved Mined Land Reclamation Plan.

 

Develop and implement a community working group to keep local stakeholders informed about the Project’s potential economic and community benefits, as well as the Company’s commitment to safety and the environment.

 

TSF Design

 

The key risks identified for the TSF design are:

 

Unknown risks related to limited site-specific information for characterizing the TSF foundation and geotechnical/geochemical properties of the tailing

 

Natural flood inundation

 

Seepage management/geochemical control requirements

 

Suitability of on-site borrow areas for construction fill

 

Dust management

 

Recommendations to advance the TSF design to the next design stage are:

 

Conduct a tailings alternatives assessment following a multiple accounts analysis (MAA) framework. The alternatives assessment must consider technical, environmental, and social objectives, and engage a range of Project stakeholders.

 

Conduct a site investigation to evaluate the geotechnical, hydrogeological and geochemical properties of the TSF foundation, and suitability of potential borrow sources. The investigation should comprise drilling, test pitting, geophysics, in-situ hydrogeological testing, sampling and associated laboratory testing.

 

Perform additional test work (geotechnical, rheological and geochemical) on the tailings. Geochemical testing should include static and kinetic testing to understand long-term acid rock drainage and metal leaching potential, to inform geochemical management strategy.

 

Conduct site-specific flood-routing modeling to assess TSF and borrow area flood risk.

 

Perform a TSF staging assessment and review the embankment design approach. This assessment should evaluate beach wetting as a viable approach for dust suppression and serve as key input to the TSF water balance.

 

Develop a TSF water balance as an input to the site-wide water balance. If warranted, investigate TSF configurations with smaller impoundment footprints to limit evaporation loss.

 

Evaluate the design of the TSF liner system based on modeling and consider changes to seepage management strategy based on findings of the tailings characterization.

 

Consider tailings processing methods (e.g., filtration, cycloning) to produce construction materials and offset borrow requirements.

 

Conduct a site-specific seismic hazard assessment.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 51

 

2Introduction

 

2.1Registrant for Whom the Technical Report Summary was Prepared

 

This report was prepared as an initial assessment level Technical Report Summary in accordance with the Securities and Exchange Commission (SEC) S-K regulations (Title 17, Part 229, Items 601 and 1300 through 1305) for Ivanhoe Electric Inc. (IE or the Company).

 

2.2Terms of Reference and Purpose of the Report

 

The quality of information, conclusions, and estimates contained herein are based on: i) information available at the time of preparation and ii) the assumptions, conditions, and qualifications set forth in this report. This report is intended for use by IE subject to the terms and conditions of its contract with SRK and relevant securities legislation. The contract permits IE to file this report as a Technical Report Summary with United States securities regulatory authorities pursuant to the SEC S-K regulations, more specifically Title 17, Subpart 229.600, item 601(b)(96) - Technical Report Summary and Title 17, Subpart 229.1300 - Disclosure by Registrants Engaged in Mining Operations. Except for the purposes legislated under provincial securities law, any other uses of this report by any third party is at that party’s sole risk. The responsibility for this disclosure remains with IE.

 

This Initial Assessment is a preliminary technical and economic study of the economic potential of all or parts of mineralization to support the disclosure of mineral resources.

 

The Initial Assessment is preliminary in nature. It includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the Initial Assessment will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

 

2.3Sources of Information

 

This report is based in part on internal Company technical reports, previous studies, maps, published government reports, Company letters and memoranda, and public information as cited throughout this report and listed in the References Section 24.

 

Reliance upon information provided by the registrant is listed in the Section 25 when applicable.

 

2.4Details of Inspection

 

Table 2-1 summarizes the details of the personal inspections on the property by each qualified person or, if applicable, the reason why a personal inspection has not been completed.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 52

 

Table 2-1: Site Visit

 

Expertise Company Date(s) of Visit Details of Inspection
Mining/Reserves SRK Consulting (U.S.), Inc (SRK) 2/23/2023 Site examination, visited core shed, reviewed select core samples. Discussion on mining strategy, geotech, infrastructure locations.

Metallurgical Testwork

Mineral Recovery

Infrastructure

M3 Engineering and Technology Corp. (M3) 2/23/2023 Site examination, visited core shed, reviewed select core samples. Visited Project site; assessed infrastructure, Discussion on site layout, floodplain, utilities, infrastructure locations.
Tailings Facility KCB Consultants Ltd. (KCB) 7/13/2023 Visited locations near the perimeter of the TSF footprint for visual observation. Discussion on site layout and available geotechnical information.
Geotechnical Call & Nicholas, Inc. (CNI) 12/16/2022 Site examination, core shed visit, discussion of geotechnical characterization, and provided summaries of CNI’s geotechnical studies.
Geology/Mineral
Resources
Nordmin Engineering Ltd. (Nordmin)

3/2/2022 – 3/6/2022

 

11/7/2022 – 11/10/2022

Site examination; inspection of logging, geological setting, mineralization, and structural controls; review of chain of custody; review of drilling, logging, sampling, analytical testing, and QA/QC; facility inspection; drillhole collar confirmation; structural validation; and partial drillhole database validation.
Hydrogeology INTERA Incorporated (INTERA) 8/10/2023 Site examination, observed vibrating wire piezometer installation, visited core shed, reviewed select core samples, discussion of formation properties.
Environmental Tetra Tech, Inc. (Tetra Tech) 8/24/2023 Site examination, visited core facility, and reviewed environmental components of the proposed Project.
Geochemistry/
Water Quality
Life Cycle Geo, LLC (LCG) 7/12/2023 – 7/13/2023 Site examination, visited the core facility, reviewed core and it’s environmental and geochemical components, discussed historic water quality, and received an overview of the proposed Project.
Closure Haley & Aldrich, Inc. (H&A) 3/22/2023 Site examination, visited core facility, received an overview of the Project and discussed reclamation and closure components of the proposed Project.
Power Sources - Green Power Met Engineering, LLC (Met Engineering)

3/26/2022

 

2/24/2023

Visited the core facilities (2) and the probable surface facility sites for processing, maintenance, substation, warehousing, administration and PV solar energy

Source: All Companies, 2023

 

2.5Report Version Update

 

This Technical Report Summary supersedes the previous report, Mineral Resources Estimate Update and S-K 1300 Technical Report Summary for the Santa Cruz, Texaco, and East Ridge deposits, Arizona, USA, dated 31 December 2022, which had previously been filed pursuant to 17 CFR §§ 229.1300 through 229.1305 (subpart 229.1300 of Regulation S-K)

 

This is the third Technical Report Summary prepared under regulation S-K 1300 for IE for the Santa Cruz Project.

 

2.6Units of Measure

 

The metric system has been used throughout this report unless otherwise stated. Tonnes are metric of 1,000 kg, or 2,204.6 lb. All currency is in U.S. dollars (US$) unless otherwise stated.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 53

 

2.7Mineral Resource and Mineral Reserve Definitions

 

The terms “Mineral Resource” and “Mineral Reserves” as used in this Technical Report Summary have the following definitions.

 

Mineral Resources

 

17 CFR § 229.1300 defines a “Mineral Resource” as a concentration or occurrence of material of economic interest in or on the Earth's crust in such form, grade or quality, and quantity that there are reasonable prospects for economic extraction. A mineral resource is a reasonable estimate of mineralization, taking into account relevant factors such as cut-off grade, likely mining dimensions, location or continuity, that, with the assumed and justifiable technical and economic conditions, is likely to, in whole or in part, become economically extractable. It is not merely an inventory of all mineralization drilled or sampled.

 

A “Measured Mineral Resource” is that part of a mineral resource for which quantity and grade or quality are estimated on the basis of conclusive geological evidence and sampling. The level of geological certainty associated with a measured mineral resource is sufficient to allow a qualified person to apply modifying factors, as defined in this section, in sufficient detail to support detailed mine planning and final evaluation of the economic viability of the deposit. Because a measured mineral resource has a higher level of confidence than the level of confidence of either an indicated mineral resource or an inferred mineral resource, a measured mineral resource may be converted to a proven mineral reserve or to a probable mineral reserve.

 

An “Indicated Mineral Resource” is that part of a mineral resource for which quantity and grade or quality are estimated on the basis of adequate geological evidence and sampling. The level of geological certainty associated with an indicated mineral resource is sufficient to allow a qualified person to apply modifying factors in sufficient detail to support mine planning and evaluation of the economic viability of the deposit. Because an indicated mineral resource has a lower level of confidence than the level of confidence of a measured mineral resource, an indicated mineral resource may only be converted to a probable mineral reserve.

 

An “Inferred Mineral Resource” is that part of a mineral resource for which quantity and grade or quality are estimated on the basis of limited geological evidence and sampling. The level of geological uncertainty associated with an inferred mineral resource is too high to apply relevant technical and economic factors likely to influence the prospects of economic extraction in a manner useful for evaluation of economic viability. Because an inferred mineral resource has the lowest level of geological confidence of all mineral resources, which prevents the application of the modifying factors in a manner useful for evaluation of economic viability, an inferred mineral resource may not be considered when assessing the economic viability of a mining project and may not be converted to a mineral reserve.

 

Mineral Reserves

 

17 CFR § 229.1300 defines a “Mineral Reserve” as an estimate of tonnage and grade or quality of indicated and measured mineral resources that, in the opinion of the qualified person, can be the basis of an economically viable project. More specifically, it is the economically mineable part of a measured or indicated mineral resource, which includes diluting materials and allowances for losses that may occur when the material is mined or extracted. A “Proven Mineral Reserve” is the economically mineable part of a measured mineral resource and can only result from conversion of a measured mineral resource. A “Probable Mineral Reserve” is the economically mineable part of an indicated and, in some cases, a measured mineral resource.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 54

 

2.8Qualified Person

 

This report was compiled by SRK, with contributions from Nordmin, M3, CNI, KCB, INTERA, Tetra Tech, H&A, LCG, and Met Engineering. All ten firms are third-party firms comprising mining experts in accordance with 17 CFR § 229.1302(b)(1). IE has determined that all ten firms meet the qualifications specified under the definition of qualified person in 17 CFR § 229.1300.

 

Nordmin prepared the following sections of the report:

 

·Section 4 (Accessibility, Climate, Local Resources, Infrastructure & Physiography)

 

·Section 5 (History)

 

·Section 6 (Geological Setting, Mineralization, and deposit)

 

·Section 7 (Exploration)

 

·Section 8 (Sample Preparations, Analysis, and Security)

 

·Section 9 (Data Verification)

 

·Section 11 (Mineral Resource Estimates)

 

·Related contributions to Section 1 (Executive Summary), Section 22 (Interpretation and Conclusions), Section 23 (Recommendations) and Section 24 (References)

 

In sections of this report prepared by Nordmin, references to the Qualified Person or QP are references to Nordmin and not to any individual employed at Nordmin.

 

M3 prepared the following sections of the report:

 

·Section 10 (Mineral Processing and Metallurgical Testing.)

 

·Section 14 (Processing and Recovery Methods)

 

·Section 15 (Infrastructure), with the exception of 15.5 (Tailings) and 15.6.1 (Power Sources)

 

·Section 18 (Capital and Operating Costs), portions relating to process, infrastructure, and G&A

 

·Related contributions to Section 1 (Executive Summary), Section 22 (Interpretation and Conclusions), Section 23 (Recommendations) and Section 24 (References)

 

In sections of this report prepared by M3, references to the Qualified Person or QP are references to M3 and not to any individual employed at M3.

 

CNI prepared the following sections of the report:

 

·Section 13.2 (Geotechnical)

 

·Related contributions to Section 1 (Executive Summary), Section 22 (Interpretation and Conclusions), Section 23 (Recommendations) and Section 24 (References)

 

In sections of this report prepared by CNI, references to the Qualified Person or QP are references to CNI and not to any individual employed at CNI.

 

KCB prepared the following sections of the report:

 

·Section 15.5 Tailings Disposal

 

·Related contributions to Section 1 (Executive Summary), Section 22 (Interpretation and Conclusions), Section 23 (Recommendations) and Section 24 (References)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 55

 

In sections of this report prepared by KCB references to the Qualified Person or QP are references to KCB and not to any individual employed at KCB.

 

INTERA prepared the following sections of the report:

 

·Section 13.3 (Hydrogeology)

 

·Section 13.4.1 (Ramp Dewatering)

 

·Related contributions to Section 1 (Executive Summary), Section 22 (Interpretation and Conclusions), Section 23 (Recommendations) and Section 24 (References)

 

In sections of this report prepared by INTERA, references to the Qualified Person or QP are references to INTERA and not to any individual employed at INTERA.

 

Tetra Tech prepared the following sections of the report:

 

·Section 17.1 (Environmental Studies, Permitting, and Plans, Negotiations, or Agreements with Local Groups or Individuals), with the exception of Section 17.1.9 (Groundwater Monitoring) and 17.1.10 (Material Characterization)

 

·Sections 17.2 (Permitting and Authorizations) and 17.6 (Local Individuals and Groups)

 

Related contributions to Section 1 (Executive Summary), Section 17.8 (QP Opinion), Section 22 (Interpretation and Conclusions), Section 23 (Recommendations) and Section 24 (References)

 

In sections of this report prepared by Tetra Tech, references to the Qualified Person or QP are references to Tetra Tech and not to any individual employed at Tetra Tech.

 

H&A prepared the following sections of the report:

 

·Sections 17.4 (Post-Performance or Reclamations Bonds), 17.5 (Status of Permit Applications), and 17.7 (Mine Closure)

 

·Related contributions to Section 1 (Executive Summary), Section 17.8 (QP Opinion), Section 22 (Interpretation and Conclusions), Section 23 (Recommendations) and Section 24 (References)

 

In sections of this report prepared by H&A, references to the Qualified Person or QP are references to H&A and not to any individual employed at H&A.

 

LCG prepared the following sections of the report:

 

·Sections 17.1.9 (Groundwater Monitoring), 17.1.10 (Material Characterization), and 17.3 (Requirements and Plans for Waste and Tailings Disposal, Site Monitoring, and Water Management During Operations and After Mine Closure)

 

·Related contributions to Section 1 (Executive Summary), Section 17.8 (QP Opinion), Section 22 (Interpretation and Conclusions), Section 23 (Recommendations) and Section 24 (References)

 

In sections of this report prepared by LCG, references to the Qualified Person or QP are references to LCG and not to any individual employed at LCG.

 

Met Engineering prepared the following sections of the report:

 

·Section 15.6.1 (Power Sources)

 

·Related contributions to Section 1 (Executive Summary), Section 22 (Interpretation and Conclusions), Section 23 (Recommendations) and Section 24 (References)

 

In sections of this report prepared by Met Engineering, any references to the Qualified Person or QP are references to Met Engineering and not to any individual employed at Met Engineering.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 56

 

SRK prepared all sections of the report that are not identified in this Section 2.8 as being prepared by Nordmin, M3, CNI, KCB, INTERA, LCG, H&A, Tetra Tech, and Met Engineering. In sections of this report prepared by SRK, references to the Qualified Person or QP are references to SRK and not to any individual employed at SRK.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 57

 

3Property Description

 

3.1Legal Description of Real Property

 

The property and rights owned by IE, through IE’s fully-owned subsidiary Mesa Cobre Holding Corp., are described in Appendix A. These rights and titles have been provided by IE and have not been independently verified by Nordmin. The Title Opinion and Reliance letter by Marian Lalonde dated August 30, 2023, of Fennemore Law, Tucson, Arizona, has been relied upon by the QP for this section of the Technical Report.

 

3.2Property Location

 

The Santa Cruz Project is located 11 km west of Casa Grande, Arizona, which is approximately a one-hour drive south of the capital, Phoenix as shown in Figure 3-1. It is approximately 9 km southwest of the Sacaton deposit which was previously mined by ASARCO. The Santa Cruz Project covers a cluster of deposits and exploration areas approximately 11 km long and 1.6 km wide. Access to the Project from Casa Grande is west on West Gila Bend Highway for 7.5 km and then north on unpaved Midway Road for 1.5 km. The Santa Cruz Project centroid is approximately -111.88212, 32.89319 (WGS84) in Township 6 S, Range 4E, Section 13, Quarter C.

 

 

Source: IE, 2023

 

Figure 3-1: Santa Cruz Project Location Map

 

September 2023

SEC Technical Report Summary – Santa CruzPage 58

 

3.3Mineral Title, Claim, Mineral Right, Lease or Option Disclosure

 

3.3.1Land Tenure and Underlying Agreements

 

In 2021, IE executed an agreement with Central Arizona Resources (CAR) for the right to acquire 100% of CAR’s option over the DR Horton Energy (DRHE) mineral title. In May 2023, IE acquired 5,974.57 acres of surface title to Legend Property Group land (now known as Wolff-Harvard Ventures). The Santa Cruz exploration area covers 47.71 km2, including 25.79 km2 of private land, 2.6 km2 of Stockraising Homestead Act (SRHA) lands, and 238 unpatented claims, or 19.32 km2 of BLM land.

 

3.3.2Private Parcels

 

The Santa Cruz Project lies primarily on private land, which is dominantly fee simple. Surface titles and associated rights were acquired by IE as purchases and options on private parcels as shown in Figure 3-2. Mineral title for the Project has been acquired via an option with CAR and staking unpatented federal lode mining claims.

 

 

 

Source: IE, 2023

 

Figure 3-2: Santa Cruz Surface Title

 

September 2023

SEC Technical Report Summary – Santa CruzPage 59

 

The three surface titles are summarized as follows:

 

Surface Title – Legend/Wolff-Harvard

 

In May 2023, IE acquired the surface title and associated water rights to 5,975 acres encompassing the entire Santa Cruz Project. At closing of the purchase, IE paid a total of $34.3 million to the seller, which includes $5.1 million of previously paid deposits. IE has also issued a secured promissory note to the seller in the principal amount of approximately $82.6 million over a period of 4.5 years. The promissory note includes an annual interest rate of prime plus 1%.

 

Surface Title – CG100

 

In May 2022, IE acquired the surface title to 100.33 acres in the northeast area of the Santa Cruz Project. IE has made or shall make the following payments:

 

·On the closing date, IE paid the “Initial Payment” of $300,000

 

·On the first anniversary of the closing date, IE paid $300,000

 

·On the second anniversary of the closing date, IE shall pay $300,000; and

 

·On the third anniversary of the closing date, IE shall pay the final installment of $600,000 to release the deed from escrow.

 

Surface Title – Skull Valley

 

In February 2022, IE acquired the surface title to 20 acres in the southeast area of the Santa Cruz Project.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 60

 

The mineral rights are shown in Figure 3-3.

 

 

 

Source: IE, 2023

 

Figure 3-3: Santa Cruz Mineral Title

 

Mineral Title - DRHE Option

 

The agreement with DRHE provides that IE, by way of assignment from CAR, has the right, but not the obligation, to earn 100% of the mineral title in the fee simple mineral estate, 39 Federal Unpatented mining claims, and three small approximately 10-acre surface parcels, in cash or IE shares at DRHE’s election, over the course of three years as follows:

 

·On the Effective Date, IE paid the “Initial Payment”

 

·Within five (5) days following of the expiration of the Due Diligence Period, IE paid “Due Diligence Payment”

 

·On or before the first anniversary of the Effective Date, IE paid “First Payment”

 

·On or before the second anniversary of the Effective Date, IE paid collectively with the Initial Payment, the Due Diligence Payment, and the First Payment, the “Option Payments”; and

 

September 2023

SEC Technical Report Summary – Santa CruzPage 61

 

·Following the exercise of the option on 16 August 2024 and upon the closing date on 21 August 2024, IE shall pay the “Closing Payment”.

 

These mineral rights will be formally acquired upon the completion of scheduled payments by IE to the current mineral title holder in August of 2024. At that time, IE will have a unified land and mineral package encompassing the entire Santa Cruz Project.

 

Mineral Title – CG100

 

The mineral rights to CG100 were acquired in May 2022 along with the surface title to 100.33 acres in the northeast area of the Santa Cruz Project

 

Mineral Title - Skull Valley

 

The mineral rights to Skull Valley were acquired in February 2022 along with the surface title to 20 acres in the southeast area of the Santa Cruz Project.

 

3.3.3Federal Unpatented Mineral Claims

 

IE, by way of assignment and deed from CAR, holds 238 unpatented Federal Mining claims (Appendix A).

 

DRHE also holds 39 Federal unpatented mining claims in T06S R04E in N/2 Section 12, W/2 Section 23 and W/2 Section 24, which are subject to the option described in Section 3.3.2.

 

3.3.4Royalties

 

Noted royalties on future mineral development of the Project are summarized here:

 

·Royalty interests in favor of the royalty holders of a 5% net smelter return royalty interest for minerals derived from all portions of the property pursuant to terms contained therein recorded in the royalty document.

 

·Royalty interests in favor of the royalty holder of a 10% net smelter return royalty interest in sections 13, 18, 19, and 24, Township 6 South, Range 4 East, for minerals derived from the property pursuant to terms contained therein recorded in the royalty document.

 

·Rights conveyed to the royalty holder in Sections 13, 18, 19, and 24, Township 6 South, Range 4 East, consisting of 10% of one eight-hundredth of Fair Market Value and interest in the Cu and other associated minerals with additional terms, conditions, and matters contained therein, recorded in the royalty documents.

 

·Rights granted to the royalty holders, as joint tenants with right of survivorship, a royalty in sections 13, 18, 19, and 24, Township 6 South, Range 4 East, consisting of 30% of five tenths of 1% of the net smelter return from all minerals with additional terms, conditions, and matters contained therein, recorded in the royalty documents.

 

·Rights conveyed to the royalty holder in sections 13, 23, 24, 25, and 26, Township 6 South, Range 4 East and sections 5, 6, 18, 18, 19, and 30, Township 6 South, Range 5 East, consisting of 60% of one eighth-hundredth of Fair Market Value and interest in the Cu and other minerals with additional terms, conditions, and matters contained therein, recorded in the royalty documents.

 

·Reservation of a 1% royalty interest in favor of the royalty holder recorded in the royalty document, for E1/2 of Section5, Township 6 South, Range 5 East, south and west of Southern Pacific RR, “that when mined or extracted therefrom shall be equal in value to 1% of the net smelter returns on all ores, concentrated, and precipitates mined, and shipped from said property.”

 

September 2023

SEC Technical Report Summary – Santa CruzPage 62

 

·Reservation of a royalty interest in favor of the royalty holders in the SW1/4 of Section 17, Township 6 South, Range 5 East, for an amount equal to one half of 1% net smelter returns in the sale and disposal of all ores, minerals, and other products mined and removed from the above described parcel and sold to a commercial smelter or chemical hydrometallurgical plant or one half of 1% of 60% of the sales price if the mine product is disposed of other than to a commercial smelter, additional provisions contained therein, recorded in the royalty documents.

 

3.4Permits and Authorization

 

Current exploration is conducted on private land. Current permits are listed in Table 3-1.

 

Table 3-1: Permit Requirements for Exploration Work Required on Private Land

 

Permit Name Agency Status Renewal
Date
Requirements Violations

Dust Control Permit DUSTW-23-0362

Pinal County Air Quality Control District (PCAQCD) Approved 05/11/2024 Bi-weekly inspections; limit vehicle access to work areas; reduce vehicle speeds; water disturbed areas; apply stabilizers as needed; concurrent reclamation; install track-out devices as needed. No Violations
NOI AZPDES Stormwater General Construction Permit AZCN96111 Arizona Dept. of Environmental Quality Approved 06/30/2025 Stormwater Pollution Prevention Plan in place; monthly inspections. No Violations
Temporary Use Permit DSA-22-00200 City of Casa Grande Approved 11/08/2025 N/A No Violations
Floodplain Use Permit FUP2206-165 Pinal County Approved N/A Existing grades within the area of disturbance shall be restored per the reclamation plan. No Violations
Special Flood Hazard Area Permit – CDP-23-01296 City of Casa Grande Approved N/A Existing grades within the area of disturbance shall be restored per the reclamation plan. Stormwater shall be managed per the Stormwater Pollution Prevention Plan. No Violations

Temporary Use Permit – (Non-SFHA) – DSA-23-00116

City of Casa Grande Approved 11/08/2025 Existing grades within the area of disturbance shall be restored per the reclamation plan. Stormwater shall be managed per the Stormwater Pollution Prevention Plan. No Violations
Exploration Drilling Reclamation Plan Arizona State Mine Inspector (ASMI) In Review TBD Maximum extent of surface disturbance to be left unreclaimed at any one time during exploration operations is 20.0 acres. N/A

 

Source: IE, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 63

 

The Migratory Bird Treaty Act prohibits “Take” without prior authorization by the U.S. Fish and Wildlife Service (USFWS). This includes “Incidental Take” which is harming or killing that results from, but is not the purpose of, carrying out an otherwise lawful act. Santa Cruz has implemented beneficial practices in accordance with USFWS Nationwide Standard Conservation Measures which include employee education, preconstruction surveys, nest monitoring, and avoidance of active nests. This may affect access points and the ability to perform work on the property.

 

Existing and past land uses in the Project area and immediately surrounding areas include agriculture, residential home development, light industrial facilities, and mineral exploration and development. Some dispersed recreation occurs in the area. The climate is dry, and most of the Project area is flat, sandy, and sparsely vegetated. Portions of the Project area are in the 100-year flood plain. Within the Project area, approximately 85 acres of land located 1.2 km north of the intersection of N. Spike Road and W. Clayton Road was used during an in situ leaching project in 1991. A Phase 1 Environmental Site Assessment (ESA) was conducted on the Project area (Environmental Site Assessments, Inc. 2023).

 

There is a large private land package covering the Project area and area of known mineralization. The ability to operate on private land has the potential to reduce lengthy permitting timelines that result from federal permitting processes. The precise list of permits required to authorize the construction and operation of this Project will be determined as the mining and processing methods are designed.

 

The permit approval process for some permits includes review and approval of the process design. Thus, the project design must be substantially advanced to support the application for those permits. These technical permits typically represent the “longest lead” permits. Technical permits with substantial technical design are needed as part of the applications. The anticipated issuing agencies include:

 

·Mined Land Reclamation Plan (ASMI)

 

·45-513 Groundwater Withdrawal Permit (Arizona Department of Water Resources (ADWR))

 

·Recycled Water Discharge Permit (Arizona Department of Environmental Quality (ADEQ))

 

·Aquifer Protection Permit(s) (ADEQ)

 

·Air Quality Operating Permit (PCAQCD)

 

·General Plan Amendment (City of Casa Grande)

 

·Zone Change or Planned Area of Development (PAD) Amendment (City of Casa Grande)

 

·Site Plan Approval (City of Casa Grande)

 

3.5Environmental Liabilities

 

The 2023 Phase I ESA, completed by Environmental Site Assessments, Inc. found the following environmental liabilities associated with the Santa Cruz Project:

 

·An ASARCO/Freeport McMoRan joint venture operated an In Situ Leach Pilot Test from circa 1980s until late 1990s. Operations were mainly within Section 13 of the subject site. As part of a Class III Underground Injection Control permit for the In Situ Leach Pilot Test there is a special warranty deed and an aquifer exemption in place for a portion of the site stating, in general, that no drinking water wells shall be completed in the subsurface zone over the interval from approximately 800-ft to 4,000-ft below the ground surface over an approximate aerial extent of 960 acres. The aquifer exemption is under the jurisdiction of the U.S. Environmental Protection Agency (EPA) Region 9 and shall remain on the property in perpetuity. This limitation of the site is representative of a controlled recognized environmental condition (REC). The Santa Cruz Project will comply with this regulatory limitation during all phases of the Project.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 64

 

·Screening of former crop fields at the site evaluated as part of the 2008 Phase II ESA identified agrochemical contaminate concentrations in excess of Soil Remediation Limits (SRLs). Surficial crop field agrochemical contamination represents a recognized environmental condition for the site.

 

·The Santa Cruz Project recognizes that agrochemical contamination of soils will need to be further assessed prior to any earthwork for redevelopment of former crop fields, in order to verify that agrochemical contaminate levels are below ADEQ SRL’s for the intended use.

 

·Previous evaluations identified elevated concentrations of the pesticides DDE, DDT, dieldrin, and toxaphene in the surficial soils surrounding a concrete loading pad in the southeast portion of Section 24 just northwest of the intersection of Highway 84 and Midway Road.

 

The Santa Cruz Project currently has no plans for development in this area, however, the team recognizes that agrochemical contamination of soils will need to be further assessed prior to any earthwork for redevelopment of this portion of the property, in order to verify that agrochemical contaminate levels are below ADEQ SRL’s for the intended use.

 

In summary, the Santa Cruz Project acknowledges and fully comprehends the environmental liabilities identified in the 2023 Phase I Environmental Site Assessment (ESA). The Project team is committed to adhering to all regulatory limitations associated with the site and will ensure all necessary measures to address the recognized environmental concerns associated with the site are taken prior to development.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 65

 

4Accessibility, Climate, Local Resources, Infrastructure and Physiography

 

The Santa Cruz Project is located 60 km south-southwest of the greater Phoenix metropolitan area and is accessed from the Gila Bend highway, 9 km west from the city of Casa Grande (population of 57,699 persons). The Santa Cruz Project, as shown in Figure 4-1, is surrounded by current and past-producing copper mines and processing facilities. The greater Phoenix area is a major population center (approximately 4.8 million persons) with a major international airport (Phoenix Sky Harbor International Airport), and well-developed infrastructure and services that support the mining industry. The cities of Casa Grande, Maricopa, and Phoenix can supply sufficient electricity, water, skilled labor, and supplies for the Santa Cruz Project.

 

 

 

Source: IE, 2023

 

Figure 4-1: Location Map

 

4.1Climate

 

The climate at the Santa Cruz Project is typical of the Sonoran Desert, with temperatures ranging from -7 degrees Celsius (°C) (19 degrees Fahrenheit (°F)) to 47°C (117°F) and average annual precipitation ranging from 76˚ to 500 millimeters (mm) (3 to 30 inches) per year. Precipitation occurs as frequent low-intensity winter (December/January) rains and violent summer (July/August) “monsoon” thunderstorms (Figure 4-2). The Santa Cruz Project site contains no surface water resources. Storm runoff waters from the site are drained toward the Santa Cruz River by minor tributaries to the Santa Rosa and North Santa Cruz washes. Operations at the Santa Cruz Project site can continue year-round as there are no limiting weather or accessibility factors.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 66

 

 

 

Source: IE, 2023

 

Figure 4-2: Average Temperatures and Precipitation

 

The wind is usually calm. The windiest month is May, followed by April and July. May’s average wind speed of around 5.5 knots (6.4 mph or 10.3 km/h) is considered a light breeze. IE has instituted measures to reduce dust that could be produced at the Santa Cruz Project site.

 

4.2Local Resources

 

IE is in the process of transferring Irrigation Grandfathered Rights and Type 1 Non-Irrigation Grandfathered Water Rights in association with the private land purchased in 2023. To date, water for exploration drilling has been sourced from the City of Casa Grande. IE is planning on sourcing water from wells on the Project property in the future.

 

Electrical power is available along Midway Road with a high voltage line along the Maricopa-Casa Grande Highway along the northern edges of the Santa Cruz Project area. Also, an east-west rail line parallels the Highway and passes through Casa Grande. A natural gas line is available along Clayton Road on the southern side of the Project area.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 67

 

IE is securing water rights and additional lands surrounding the Santa Cruz and Texaco deposits to allow for future mine development activities including potential tailings storage, potential waste disposal, and processing plant areas, as well as space for ramps for underground development.

 

4.3Physiography

 

The Santa Cruz Project is in the Middle Gila Basin, entirely within the Sonoran Desert Ecoregion of Basin and Range Physiographic Province. The area is characterized by low, jagged mountain ranges separated by broad alluvial-filled basins. This portion of the Sonoran Desert is sparsely vegetated with greater variability near washes and in areas that have long lain fallow. Near washes and longer abandoned areas, catclaw acacia, mesquite, creosote bush, bursage, and salt cedar are common. The Santa Cruz Project area is flat and featureless with an elevation of 403±5 masl and sloping gently to the northwest. Much of the Santa Cruz Project area has been used for irrigated agriculture, with decaying remnants of an extensive system of wells and concrete lined ditches still present. The alignments of furrows are still visible despite decades of lying fallow. Efforts at real estate development in the 1990s and 2000s have also left visible remnants with preliminary roadworks and some planting (palm trees) overlying the previous agricultural remains. Soils proximal to washes tend to be more sand and gravel-rich, while soils in old agricultural areas are more silt and clay-rich. The physiography is further described in Table 4-1.

 

Table 4-1: Description of Physiography of the Casa Grande Area, Santa Cruz Property

 

General Physiographic Area Intermontane Plateaus
Physiographic Province Basin and Range
Physiographic Section Sonoran Desert
Alteration Potassic, Phyllic, and Argillic – more intense in mineralized areas
Associated Rocks

Breccia

Conglomerate

Schist

Porphyry

Granite

Diabase

Rock Unit Names

Gila Conglomerate

Laramide Porphyry

Oracle Granite

Pinal Schist

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 68

 

5History

 

5.1Introduction

 

Historically, there were three main deposit areas that are part of the current Santa Cruz Project: Texaco (to the northeast), Santa Cruz North (southwest of Texaco), and Casa Grande West/Santa Cruz South which is the southernmost deposit (Figure 5-1). ASARCO owned and drilled the Texaco and Santa Cruz North deposits. Hanna-Getty owned and drilled the Casa Grande/Santa Cruz South deposit. In 1990, ASARCO entered a joint venture with Freeport McMoRan Copper & Gold Inc. on the Texaco land position. Hanna-Getty continued to own and operate the Casa Grande West/Santa Cruz South deposit.

 

The first discovery of copper mineralization in the area occurred in February 1961 by geologists from ASARCO. They discovered a small outcrop of leached capping composed of granite cut by a thin monzonite porphyry dyke. The outcrop was altered to quartz-sericite-clay with weak but pervasive jarosite-goethite and a few specks of hematite after chalcocite, particularly in the dyke.

 

ASARCO proceeded with preliminary geophysical surveys that same year, including IP, resistivity, seismic reflection, and magnetics. Upon positive results from the geophysical surveys, a small drill program of six holes was funded, with the last hole being the first to intersect the significant mineralization that became known as the West Orebody and, in time, the Sacaton open pit mine (Figure 5-1).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 69

 

 

 

Source: IE, 2023

 

Figure 5-1:   Historical Drill Collars, Deposit, and Exploration Area Names (white) as well as Current Project Names for IE and Neighboring Project (in yellow)

 

Encouraged by the discovery at Sacaton, ASARCO expanded exploration efforts across the Casa Grande Valley and in 1964 the first hole was drilled on the Santa Cruz Project. By May 1965, seventeen drillholes were completed without similar success, and ASARCO reduced its land position. Subsequent reviews in 1970-1971 deemed the Santa Cruz Project worth renewed exploration activity. Following the initiation of the Santa Cruz Joint Venture (SCJV) between ASARCO Santa Cruz, Inc. and Freeport McMoRan Copper & Gold Inc. in 1974, additional ground was acquired around the Santa Cruz North deposit. By this time, various joint ventures, as below, had staked considerable ground over and around what would eventually be the Casa Grande West (now Santa Cruz) deposit.

 

In 1973, David Lowell put together an exploration program called the Covered Area Project (CAP) that was funded first by Newmont Mining, then, in succession, by a joint venture between Newmont and Hanna Mining, then Hanna with Getty Oil Corp. and Quintana Corp.; though both Quintana and Newmont would pull out of the project before any discoveries were made. In 1974, after having systematically drilled over 120 holes at 20 projects across Southwestern Arizona, David Lowell and his team focused their attention on the Santa Cruz system (which Lowell and his team called the Casa Grande project). ASARCO had just put the Sacaton operation into production and Lowell and associates were aware of the evidence for shallow angle faulting and potential for dissected porphyry mineralization that might have been displaced undercover in the Casa Grande Valley (Lowell, unpublished personal communication). Furthermore, the CAP program had compiled historic data of the area that indicated several water wells drilled had returned pebbles of Cu-oxide mineralization. Careful stream mapping and drainage analysis revealed that the Santa Cruz River had reversed flow directions at least twice in recent history, and it was this revelation that allowed Lowell to trace the exogenous oxide-Cu pebbles back to the Santa Cruz deposit area. They discovered evidence for porphyry mineralization in their first drillhole, which intersected leached capping, and by their seventh hole (CG-7), they had intersected significant supergene enriched Cu mineralization at what they called the Casa Grande West deposit. Drilling under the CAP program continued through to 1977, at which point Hanna Mining took over as operator under a joint venture with operation funding from Getty Oil Corp. Between 1977 and 1982, Hanna-Getty advanced a tight spaced drill program that delineated an estimated 500 Mt of 1% Cu at Casa Grande West, and countless exploration holes in the surrounding Casa Grande Valley (Lowell unpublished personal communication). The decision to go underground and mine the Casa Grande West deposit was never made, and the combination of encroaching real estate, the growing environmental movement, and potential mismanagement by Hanna-Getty followed by the fall of Cu commodity prices all resulted in the Casa Grande West project becoming inactive in the early 80s.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 70

 

5.2Previous Exploration

 

5.2.1Sacaton Mine

 

ASARCO went on to mine the Sacaton deposit from 1974 to 1984. The Sacaton deposit was mined using open pit methods with the beginnings of underground workings initiated but depressed Cu prices resulted in the halt of all mining at Sacaton. Table 5-1 shows the historical mine production from Sacaton.

 

Table 5-1: Sacaton Historical Mine Production (Fiscal Years Ended December 31)

 

Year Ore Milled Short Tons Mill Grade Cu% Cu Short Tons Au Troy Oz. Ag Troy Oz.
1974 2,020,000 0.63 9,516 N/A N/A
1975 3,630,000 0.74 21,918 3,153 N/A
1976 3,782,000 0.71 22,021 3,151 N/A
1977 3,471,000 0.70 19,872 3,103 N/A
1978 4,153,000 0.67 23,042 3,691 N/A
1979 4,006,000 0.65 21,367 3,558 142,000
1980 3,819,000 - 16,097 2,504 124,000
1981 4,103,000 - 21,015 3,334 172,000
1982 4,165,000 - 20,892 2,499 154,000
1983 4,003,000 - 18,794 1,983 134,000
1984 1,000,000 - 4,496 479 33,000
Total 38,152,000 0.69 199,030 27,455 759,000

 

Source: Nordmin, 2023

 

5.2.2Santa Cruz and Texaco Deposits

 

Several deposits, including Santa Cruz South (also known as Casa Grande West), Santa Cruz North (the Santa Cruz North and South deposits are collectively referred to as the “Santa Cruz deposit”), Texaco, and Parks-Salyer were identified during ASARCO drilling in the 1960s and subsequent drilling in the 1970s and 1980s by numerous exploration companies including Newmont Mining, Hanna, Hanna-Getty, and a joint venture between ASARCO Santa Cruz Inc. and Freeport McMoRan Copper & Gold Company (SCJV). In total, 362 drillholes totaling 229,577 m have been drilled by previous owners delineating the cluster of deposits. Table 5-2 presents a summarized history of exploration on the property. There are no records of work by Texaco, but the company held land over what is now called the Texaco deposit.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 71

 

Table 5-2: History of Exploration Activities Across the Santa Cruz and Texaco Deposits

 

Dates Activities Company(s) Description Notes
1961 Prospecting and discovery ASARCO ASARCO geologists Kinnison and Blucher identify Sacaton Discovery Outcrop An outcrop of granite with a thin dyke of porphyry was discovered.
1961 Geophysical Surveying ASARCO ASARCO Geophysical Dept. report Geophysical surveys including IP, resistivity, magnetics.
1962 Drilling ASARCO Six exploration drillholes at Sacaton The first five holes cut sulfides, but only a few short runs of ore grade rock. The sixth hole was the first hole within the West Orebody.
1964 Drilling ASARCO Five holes were drilled near the Santa Cruz deposit by ASARCO (SC-2 to SC-6) These were exploration drillholes, none of which intersected the main mineralization at Santa Cruz. SC-5 was drilled nearly 3 km SW of the main deposit.
1965 Drilling ASARCO 11 holes were drilled near the Santa Cruz deposit by ASARCO (SC-7 to SC-17) These were exploration drillholes, SC-1 was drilled along the western margin of the subsequent Independent Mining Consultants, Inc. (IMC) block model. And SC-16 was just to the East of the future Santa Cruz North deposit. SC-17 was drilled approximately 4 km SW of the Casa Grande deposit (furthest step out exploration hole in the database).
1974 Drilling and Discovery Hanna-Getty Five holes were drilled around Santa Cruz North and one at Casa Grande by Hanna-Getty (CG-1 to CG-6) Six holes drilled by Hanna-Getty under the CAP led by Lowell, one of which (CG-3) intersected near ore grade mineralization along the western boundary of what would become the Santa Cruz North and Casa Grande deposits.
1974 Drilling and Discovery ASARCO SC-18,19 and 20 are drilled at Santa Cruz North by ASARCO Following the initiation of exploration in the Santa Cruz area by the CAP initiative, led by Lowell, ASARCO re-initiated exploration drilling in the area. All three holes intersected porphyry-style mineralization at what would be called the Santa Cruz North deposit.
1975 Drilling Hanna-Getty Two holes were drilled at Casa Grande, two holes drilled at Santa Cruz North and one hole drilled at Texaco by Hanna-Getty (CG-7 to CG-11) Hole CG-7 was the first intersection of ore grade mineralization, as reported by Lowell.
1975 Drilling and Discovery ASARCO Four holes were drilled at Santa Cruz North and one at Texaco by ASARCO (SC-21 to SC-24) ASARCO drilled five holes, three nearby 1974 drilling that intersected mineralization at Santa Cruz North, and two exploration step out holes each 1.5 km to the NE of the Santa Cruz North area, SC-21, and SC-23 which intersected the Texaco deposit mineralization.
1976 Drilling and land position expansion Hanna-Getty Two holes were drilled at Santa Cruz North and 14 holes were drilled at Casa Grande by Hanna-Getty (CG-12 to CG-33) Bolstered by success in CG-7, and led by Lowell, key ground over what would eventually be the Casa Grande deposit was picked up, and exploration drilling advanced through 1976.
1976 Drilling ASARCO One hole was drilled approximately 1 km NE of the Casa Grande deposit (SC-25), and six holes were drilled at Texaco (SC-27, -28, -29, -30, -31, and -34)  
1977 Drilling and Operatorship change Hanna-Getty One hole was drilled at Texaco (CG-48), and 45 holes were drilled at Casa Grande (CG-34-CG-79) Hanna-Getty took over operatorship from Lowell and the CAP team and began a close-spaced drill program to delineate the ore body at Casa Grande.
1977 Drilling ASARCO Six holes were drilled at Texaco and 12 holes were drilled at Santa Cruz North by ASARCO (SC-35 to SC-52)  
1978 Drilling Hanna-Getty One hole was drilled north of Santa Cruz North and 31 holes drilled at Casa Grande by Hanna-Getty (CG-80 to CG-122)  

 

September 2023

SEC Technical Report Summary – Santa CruzPage 72

 

Dates Activities Company(s) Description Notes
1979 Drilling Hanna-Getty Six holes drilled by Hanna-Getty approximately 1 km west of the Casa Grande and Santa Cruz North deposits  
1979 Drilling ASARCO Four holes were drilled at Santa Cruz North by ASARCO (SC-55 to SC-58)  
1980 Drilling ASARCO Six holes were drilled at Santa Cruz North by ASARCO (SC-59 to SC-64)  
1981 Drilling Hanna-Getty Two holes were drilled north and west of Santa Cruz North  
1982 Drilling Hanna-Getty Two holes were drilled north and west of Santa Cruz North  
1990-1991 Land Consolidation SCJV (ASARCO, Santa Cruz Inc., and Freeport McMoRan Copper & Gold Inc.) – Texaco Texaco approached SCJV (ASARCO-Freeport) regarding the sale of the Texaco land position A series of internal memos from SCJV discussed the opportunity and holding costs and why they should acquire the lands from Texaco.
1994 In situ Cu Mining Research Project US Bureau of Reclamation (USBR) and SCJV   Permits received to begin injection of sulfuric acid.
1995 In situ Cu Mining Research Project USBR – SCJV   Pilot plant completed.
1996 Drilling SCJV 11 holes drilled at and around Texaco by ASARCO (SC-65 to SC-74)  
1996 In situ Cu Mining Research Project USBR-SCJV   Mining test started In February.
1997 Drilling SCJV Four holes were drilled by ASARCO at Texaco (SC-75 to SC-78)  
1997 In situ Cu Mining Research Project USBR-SCJV Lost funding – closure started USBR lost Congressional funding in October. Injection continued until December.
1998 In situ CU Mining Research Project USBR-SCJV State required closure activities – final report to Bureau of Reclamation Pumping continued until the end of February. Plant to care and maintenance. The final research report was never made public.

 

Source: IE, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 73

 

5.3Previous Reporting

 

5.3.1Hanna 1982

 

Watts Griffis McOuat Ltd. (Watts Griffis McOuat) calculated a historical mineral inventory for Hanna Mining in 1982. Mineralization was determined from sections by calculating areas from drillhole intercepts and distance between holes, and by assigning the weighted average grade of the neighboring holes to each area. In the case of a single hole in a section, the grade of that hole was assigned to that area.

 

Watts Griffis McOuat recommended additional consideration be given to a more flexible mining method such as sublevel caving.

 

5.3.2In Situ Joint Venture 1997

 

In 1986, the Bureau of Mines obtained Congressional approval and funding to study in situ copper mining. In 1988, the Santa Cruz deposit was selected for this research project sponsored by a joint venture program between landowners ASARCO Santa Cruz Inc. and Freeport McMoRan Copper & Gold Inc., and the US Department of the Interior, Bureau of Reclamation, who funded most of the program.

 

Field testing began in 1988, and the test wells were constructed in 1989 in a 5-point pattern with one injection well centered between four extraction wells. Salt tracer tests were conducted in 1991, permits for the use of sulfuric acid were received in 1994, and the solvent extraction-electrowinning (SX-EW) pilot plant was completed in 1995.

 

The in-situ testing began in February 1996, but research funding was halted in October 1997 due to a change from Congress. Utilizing the carryover funds from previous years of the program, injections continued until December 1997 and pumping until mid-February 1998. At this point, the remaining fluids in the leach zone were less acidic, and metals remaining in the solution were redeposited into the ore body through precipitation. A final report was not made publicly available. However, a newsletter from the project was circulated in March 1998 and noted that 35,000 lbs of Cu were extracted.

 

5.3.3IMC 2013

 

IMC constructed a block model for the Santa Cruz South deposit, the Texaco deposit, and the Parks-Salyer deposit for Russell Mining and Minerals in 2013. The block model for the Santa Cruz South deposit was based on 116 drillholes with 18,034 assay intervals for a total of approximately 342,338 feet (ft) (104,344 m) of drilling, in which 90.7% of the intervals were assayed for Cu. 40% of the drill intervals were assayed for acid soluble Cu and 5% for cyanide soluble Cu.

 

The block model for the Texaco deposit was based on all Cu drilling data available as of April 5, 2013. The block model was based on 29 drillholes with 2,281 assay intervals for a total of approximately 82,696 ft (25,205 m) of drilling, in which 92.5% of the intervals were assayed for Cu. Less than 9% of the drill intervals were assayed for acid soluble Cu or cyanide soluble Cu.

 

The block model for the Parks-Salyer deposit was based on seven drillholes with 7,398 ft (2,254 m) of drilling. The model incorporated the topography, the bottom of the conglomerate, and the top of the bedrock, as well drillhole collars, and downhole information, plus additional drillhole data from outside the model limits. These surfaces are a rough approximation based on the limited amount of information available.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 74

 

5.3.4Stantec-Mining 2013

 

Stantec completed a conceptual study for Presidio Capital in August 2013 on the Santa Cruz South, Texaco, and Sacaton exploration properties.

 

5.3.5Physical Resource Engineering 2014

 

In 2014 Physical Resource Engineering completed a conceptual study, “Mining Study Exploitation of the Santa Cruz South deposit by Undercut Caving” for Casa Grande Resources LLC.

 

5.4Ivanhoe Electric Technical Report Summaries

 

5.4.1Mineral Resource Estimate 2021

 

Nordmin produced a Mineral Resource Estimate for IE dated December 8, 2021 included within the Technical Report Summary dated June 8, 2022.

 

5.4.2Mineral Resource Estimate Update 2022

 

Nordmin produced a Mineral Resource Estimate for IE dated December 31, 2022 entitled “Mineral Resource Estimate Update and S-K 1300 Technical Report Summary for the Santa Cruz, Texaco, and East Ridge Deposits, Arizona, USA.” The Mineral Resource Estimates for the Santa Cruz and East Ridge Deposits from this report are used for this IA and are available in Section 11.9.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 75

 

5.5Historical Production

 

No historical production has been carried out on the property.

 

5.6QP Opinion

 

The Nordmin QP is of the opinion that the historical exploration, as described above, are reasonable indicators of what IE could expect to encounter with continued exploration. The reader is cautioned that the historical reports listed above vary between different sources and therefore should be considered as an indicative only.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 76

 

6Geological Setting, Mineralization, and Deposit

 

6.1Regional Geology

 

The Santa Cruz Project is located within an approximately 600 km long northwest to southeast trending metallogenic belt known as the Southwestern Porphyry Belt, which extends from northern Mexico into the southwestern United States. The belt includes many productive copper deposits in Arizona such as Mineral Park, Bagdad, Resolution, Miami-Globe, San Manuel-Kalamazoo, Ray, Morenci, and the neighboring Sacaton Mine (Figure 6-1). These deposits lie within a broader physiographic region known as the Basin and Range province that covers and defines most of the southwestern United States and northwestern Mexico. This region is characterized by linear sub-parallel mountain chains separated by broad flat valleys formed by regional tectonic extension during the mid- to late-Cenozoic Period.

 

 

 

Source: IE, 2023

 

Figure 6-1: Regional Geology of the Southwestern Porphyry Belt and the Cu Porphyry Deposits in the Area around the Santa Cruz Project

 

September 2023

SEC Technical Report Summary – Santa CruzPage 77

 

Basement geologic units of Arizona consist of formations developed during the Paleoproterozoic collisional orogeny that were subsequently stitched together by anorogenic granitic plutonic suites within the Mesoproterozoic. Basement Proterozoic lithologies at the Santa Cruz Project are represented by three primary units: Pinal Schist, Oracle Granite, and Diabase dykes.

 

The Pinal Schist is a metasedimentary to metavolcanic basal schist which spans much of southern Arizona. Proterozoic anorogenic granitic complexes were emplaced into the schist between 1450-1350 Ma. Continental rifting in the Mesoproterozoic brought both Paleo- and early Mesoproterozoic granitic complexes to the surface where they were subsequently buried beneath early Neoproterozoic rocks of the Apache Group, which represents a very shallow intracontinental basin. Around 1100 Ma, these rocks were intruded by Diabase intrusions related to the break-up of the Rodinia supercontinent. Throughout the Paleozoic Era, Arizona was located within a craton with major disconformities in the stratigraphy interpreted to represent relative sea level changes. Continental shortening throughout the Cretaceous period is contemporaneous with diachronous magmatism within the same location (Tosdal and Wooden, 2015). Cessation of magmatic activity in the Paleocene Period marked the onset of erosion of the uplifted arc, which lay southwest of the Colorado Plateau.

 

6.2Metallogenic Setting

 

The porphyry copper deposits within the Southwestern Porphyry Copper Belt are the genetic product of igneous activity during the Laramide Orogeny (80 Ma to 50 Ma). Laramide porphyry systems near the Santa Cruz Project define a southwest to northeast linear array orthogonal to the trend of magmatic arc environment.

 

During the tectonic extension of the mid-Cenozoic Period, the Laramide arc and related porphyry copper systems were variably dismembered, tilted, and buried beneath basin alluvium and conglomeratic deposits that fill the Casa Grande Valley. Prior to concealment, many of the Laramide porphyry systems of Arizona experienced supergene enrichment events that make them such economically significant deposits.

 

Supergene alunite from the Sacaton porphyry copper deposit, located approximately 8.5 km from the Santa Cruz deposit, was K-Ar dated at 41 Ma (Cook, 1994). At the Santa Cruz Project, evidence for multiple cycles of supergene enrichment is represented by multiple chalcocite and oxide-copper ”blankets”. These “blankets” were developed oblique to each other as a result of rotation and subsequent overprinting by new supergene blankets. This enrichment has been shown to occur throughout the Tertiary Period and ceased with the deposition of overlying sedimentary packages, comprised predominantly of conglomerates, which changed the hydrology near the deposits. The earliest supergene enrichment is interpreted to have occurred in the Eocene Epoch (Tosdal and Wooden, 2015).

 

6.3Santa Cruz Project Geology

 

The Santa Cruz Project is comprised of five separate areas along a southwest-northeast corridor. These areas from southwest to northeast are known as the Southwest Exploration Area, the Santa Cruz deposit, the East Ridge deposit, the Texaco Ridge Exploration Area, and the Texaco deposit. Each of these deposits represent portions of one or more large porphyry copper systems separated by extensional Basin and Range normal faults. Each area has variably experienced periods of erosion, supergene enrichment, fault displacement and tilting into their present positions due to Basin and range extensional faulting (Figure 6-3).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 78

 

 

 

Source: IE, 2023

 

Figure 6-2: Generalized Cross-section of the Santa Cruz - Sacaton System

 

6.3.1Santa Cruz Project Lithologies

 

The bedrock geology at the Santa Cruz Project is dominated by Oracle Granite (1450 to 1350 Ma) with lesser proportions of Proterozoic Diabase intrusions (1100 Ma), dipping at ~40 degrees (°) to 50° to the south-southwest, and Laramide porphyry intrusions (75 Ma), dipping at ~30° to 40° to the southwest.

 

The Oracle Granite is prevailingly a coarse-grained hypidiomorphic biotite granite with large pink or salmon-colored orthoclase feldspars 32 mm to 38 mm across that gives rock a pink or gray mottled appearance on fresh surfaces. Groundmass composed of uniformly sized, 5 mm, grains of clear white feldspar and glassy quartz with greenish-black masses of biotite and magnetite. Composition suggests that rock should be classed as quartz monzonite rather than granite. Surface exposures of light-buff color. Age is interpreted to be 1450 Ma to 1350 Ma (Tosdal and Wooden, 2015). Alteration minerals are dominated by secondary orthoclase and sericite.

 

Proterozoic diabase is Holocrystalline, medium- to coarse-grained ophitic to subophitic textures with plagioclase and clinopyroxene (augite) as the dominant primary phases. Magnetite, oligoclase, sulfide (pyrite and chacopyrite) mineralization are reported as minor phases within the diabase. These diabase intrusions were dominantly emplaced as horizontal to sub-horizontal sills, though rare dykes are recognized. These dykes are associated with local discrete increases in observed hypogene sulfide mineralization – interpreted as being a more reactive and receptive host rock for hydrothermal fluid deposition of sulfide mineralization. Historic petrographic thin section analysis indicates diabase is dominantly associated with hydrothermal biotite and epidote.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 79

 

Laramide porphyry intrusions are strongly associated with primary hypogene mineralization. The porphyry has a quartz monzonite composition (35% quartz, 6% biotite, 29% feldspar, 30% K-feldspar, and plagioclase) with 40% phenocrysts averaging 1.5 mm and 60% aplitic to aphanitic groundmass. Quartz phenocrysts are less than 10 mm, sub-spherical, and comprise approximately 25% of the phenocrysts. Biotite makes up 15% of the phenocrysts and are less than 5 mm. Subhedral plagioclase phenocrysts, 60%, are generally less than 7 mm. There are two distinct groups of Laramide-aged porphyry intrusions. One contains quartz phenocrysts <5% by volume, and is generally associated with increased biotite phenocrysts as well as increased biotite content in the groundmass, typically giving this unit a darker color. The other variant contains more quartz phenocrysts (>5%), and is often described as being more siliceous and lighter in color.

 

A later late biotite-quartz feldspar monzonite porphyry is composed of 15% biotite, 25% K-feldspar, 40% plagioclase and 20% quartz with 15% phenocrysts consisting of 20% biotite, 70% plagioclase and 10% quartz in an aphanitic 15% biotite, 30% K-feldspar, 35% plagioclase, 20% and quartz groundmass with 0.06 mm average crystal size.

 

Alteration minerals in mineralized Laramide dykes are dominated by hydrothermal biotite, sericite, and lesser orthoclase feldspar.

 

Directly overlying the erosional surface of the basement rocks is a series of sedimentary and volcanic units. These consist of predominantly syn-extensional sediments and conglomerates, airfall volcanic tuffs, and andesitic basalts associated with dykes or flows. Sediments and conglomerate units include the Alluvium, Gila Conglomerate, Whitetail Conglomerate, and Basal Conglomerate. The Gila Conglomerate and Whitetail Conglomerate are separated stratigraphically and conformably by a thin marker bed of rhyolitic Apache Leap Tuff (20 Ma) usually of no greater thickness than 1 m. Basaltic dykes or flows include the Mafic Conglomerate unit which exists variably above, below, or intercalated within the Basal Conglomerate.

 

The syn-extensional sedimentary and volcanic units are well understood across the Santa Cruz Project and have all been intersected in numerous drilling intersections through coring from surface. A general stratigraphic cross-section can be viewed in Figure 6-4. Quaternary alluvium consists of poorly sorted silt and sand spread out in a thin veneer across the entirety of the Casa Grande Valley, reaching up to 70 m thick near the Santa Cruz River and displays a conformable relationship with underlying Gila Conglomerate. Dissected alluvial fans flank the Tabletop Mountain area to the southwest of the Santa Cruz Project and are largely comprised of volcanic rubble.

 

The Tertiary Gila Conglomerate consists of alternating valley beds most of which are sub-rounded to sub-angular cobble to boulder conglomerates with periodically interbedded layers of moderately sorted sand and gravel, collectively averaging 150 to 300 m thick across the Santa Cruz Project, reaching thickest intersections over paleo-valleys controlled by buried extensional structural block configurations and displays a conformable relationship with the underlying Apache Leap Tuff.

 

The Tertiary Apache Leap Tuff is defined as a single rhyolitic airfall tuff layer. The tuff layer consists primarily of devitrified quartzofeldspathic cryptocrystalline groundmass and displays a conformable relationship with the underlying Whitetail Conglomerate.

 

The Tertiary Whitetail Conglomerate is temporally and characteristically regarded as the stratigraphically lower and older equivalent of Gila Conglomerate. It consists of alternating valley beds of mostly angular to subangular cobble to boulder conglomerates with periodically interbedded layers of moderately to poorly sorted sand and gravel. It is interpreted to represent a period of higher intensity erosion. The unit collectively averages 100 m to 400 m thick across the Santa Cruz Project. The thickest intersections are found over paleo-valleys controlled by extensional structural block configurations. It displays a conformable relationship with the underlying Basal Conglomerate or Mafic Conglomerate.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 80

 

Tertiary Mafic Conglomerate consists of tightly compacted monomictic conglomerate composed of angular cobble to boulder sized clasts of andesitic to basaltic composition and is distinguished by the abrupt change in clast composition and coloration. The unit collectively averages 10 to 50 m thickness across the Santa Cruz Project but displays layers at the edges of occurrences as narrow as 1 m. The unit displays a conformable relationship with the underlying Basal Conglomerate or Whitetail Conglomerate or an unconformable relationship with the underlying Oracle Granite or Laramide Porphyry.

 

Tertiary Basal Conglomerate is characterized as a tightly compacted, monomictic conglomerate consisting of angular cobble to boulder sized clasts of Oracle Granite. The unit is also distinguished by a sharp and significant introduction or increase in total hematitic iron oxidation throughout the rock mass. The unit averages 25 m to 100 m thickness across the Santa Cruz Project, reaching the thickest intersections at the base of paleo-valleys due to slope erosion and sedimentation. The unit displays a conformable relationship with the underlying Mafic Conglomerate or an unconformable relationship with the underlying Oracle Granite.

 

The Santa Cruz Project lithologies are shown in the simplified stratigraphic column (Figure 6-4).

 

 

 

Source: IE, 2023

 

Figure 6-3: Simplified Stratigraphic Section of Santa Cruz Project Alteration

 

September 2023

SEC Technical Report Summary – Santa CruzPage 81

 

6.3.2Alteration

 

Alteration at the Santa Cruz Project is variable across the property based on host lithology and mineralization type. Hypogene hydrothermal alteration assemblages consist predominantly of quartz, secondary biotite, orthoclase, magnetite, sericite, phengite. Low-temperature broad overprints are present consisting of illite and smectite, lesser kaolinite (which occurs primarily in the oracle granite), and late low-temperature chlorite and calcite. Rare subordinate phases such as epidote, albite, and tremolite may also occur. Supergene alteration related to the weathering and oxidation of primary hypogene sulfides. It is also important to note it can be difficult to discriminate from retrograde intermediate-argillic hypogene alteration. Supergene clays occur dominantly in the weathering environment where the breakdown of primary hypogene sulfides results in sulfuric acid and the formation of limonites, alunite, jarosite, and kaolinite-bearing assemblages. Supergene alteration also includes alteration due to heated meteoric groundwater resulting from Miocene igneous activity. This includes late propylitic overprints, smectite clay alteration of mafic to intermediate-composition igneous rocks, smectite alteration along Miocene Basin-and-Range faults, and broad pervasive illite-smectite alteration overprints.

 

6.3.3Structural Geology

 

The Santa Cruz Project lies within the Basin and Range Province, within a domain that has experienced some of the greatest degrees of extensional tectonism Figure 6-2. The Santa Cruz Project, including the Southwest Exploration Area, Santa Cruz deposit, East Ridge deposit, Texaco Ridge Exploration Area, and Texaco deposit represents portions of one or more large porphyry copper systems that have been dismembered and displaced during Tertiary extensional faulting. As such, faulting at the Santa Cruz Project is intimately associated with mineralization and the current deposit configuration in several ways. The extensional fault systems are recognized at Santa Cruz with a transport direction towards the south-west of which D1 is the oldest, followed by D2 faulting.

 

Firstly, major deep-seated northeast-southwest striking basement structures that run from Colorado to Mexico (i.e., The Jemez Lineament) likely controlled or constrained Laramide age intrusive emplacement and metal endowment during transpressional arc magmatism. These structures have been reactivated multiple times, potentially serving as transfer faults for dextral offset during basin and range extension. Secondly, post-mineral faulting is recognized at Santa Cruz Project, and it is evident that at least three different generations of approximately northeast-southwest striking normal faulting have developed during basin and range extension. This has resulted in significant rotation and offset of fault blocks with the earliest generation of D1 faults exhibiting a sub-horizontal configuration. This rotation and offset of faults and fault blocks during basin and range extension is well documented in Arizona.

 

Additionally, it is evident within the Santa Cruz Project that post emplacement faulting has controlled and affected groundwater dynamics and the subsequent mobilization and deposition of copper in supergene enrichment processes. These faults also played a role in shaping the paleotopographic landscape and had a controlling influence on the development and distribution of exotic copper mineralization in paleodrainages that are recognized at the Santa Cruz Project.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 82

 

6.3.4Property Mineralization

 

The Santa Cruz Project is comprised of five separate areas known as the Southwest Exploration Area, Santa Cruz deposit, East Ridge deposit, Texaco Ridge Exploration Area, and Texaco deposit which represent portions of one or more large porphyry copper systems. Each deposit contains porphyry-style hypogene sulfide mineralization and subsequent tertiary-supergene oxide copper and chalcocite enrichment. Intensity varies by deposit along with speciation, and characteristics depending on spatial and vertical positions and the timing and total amount of overlying post-mineral tertiary sediment deposition.

 

Mineralization at the Santa Cruz Project is generally divided into three main groups:

 

1.Primary hypogene sulfide mineralization: chalcopyrite, pyrite, and molybdenite hosted within quartz-sulfide stringers, veinlets, veins, vein breccias, and breccias as well as fine to coarse disseminations within vein envelopes associated with hydrothermal porphyry-style mineralization. Hypogene mineralization appears to be the most concentrated within the Southwest Exploration Area, Texaco Ridge Exploration Area, and Texaco deposit areas based on IE drillholes. Hypogene mineralization at these locations is defined by elevated amounts of pyrite and chalcopyrite mineralization compared to the other project areas with equal or lesser amounts of molybdenite mineralization.

 

2.Secondary supergene sulfide mineralization: dominantly chalcocite which rims primary hypogene sulfides and completely replaces hypogene mineralization. Other sulfides that fall within this category include lesser bornite and covellite as well as djurleite and digenite which have been identified by historic XRD analyses. Supergene sulfide mineralization developed as sub-horizontal domains, known as “chalcocite blankets”, within the phreatic zone (below the paleo water table). They result from the weathering, oxidation, and leaching of sulfides under oxidizing conditions in the vadose zone (above the water table) and the transport and re-precipitation of copper sulfides in a more reducing environment below the water table. Basin and range extension dissected and tilted older chalcocite blankets to the southeast, younger chalcocite blankets may have formed after the bulk of miocene tilting.

 

3.Supergene copper oxide mineralization: Supergene oxide mineralization is dominantly comprised of chrysocolla (copper silicate) with lesser dioptase, tenorite, cuprite, copper wad, and native copper, and as copper-bearing smectite group clays. This mineralization style resides immediately above supergene sulfide mineralization near the paleo water table. Superimposed in-situ within the copper oxide zone is atacamite (copper chloride) and copper sulfates (e.g., antlerite, chalcanthite). Atacamite accounts for much of the copper grades within the oxide zone and requires formation of a brine to precipitate. The timing and mechanism for brine formation and atacamite precipitation remains poorly understood. One possibility is that atacamite may reconstitute copper from supergene copper oxides. As a consequence of this model, atacamite distribution may be controlled by the distribution of readily leachable copper oxides and permeability generated by Miocene faulting. Exogenous, or “exotic” copper occurrences also occur, including copper-oxide cemented gravels, sediments, and conglomerates; copper incorporation into ferricrete and smectite-group clays in the volcaniclastic tephra of the mafic conglomerate and in diabase sills; and finally, reworked clasts containing copper oxide mineralization.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 83

 

6.3.5Mineralization at the Santa Cruz Deposit

 

Hypogene Mineralization

 

Lithologies hosting hypogene mineralization in and around the Santa Cruz deposit include precambrian oracle granite, laramide porphyry, and precambrian diabase.

 

Primary hypogene sulfide mineralization consists of chalcopyrite, pyrite, molybdenite, and minor bornite hosted within quartz-sulfide stringers, veinlets, veins, vein breccias, and breccias as well as fine to coarse disseminations within vein envelopes associated with hydrothermal porphyry-style mineralization. Lateral and vertical continuity of highest hypogene grades locally varies within the deposit due to clustering of laramide porphyry dike intrusions.

 

Supergene Mineralization

 

Prior to burial by Tertiary sediments, hypogene sulfide mineralization near the paleo ground surface was subjected to multiple cycles of oxidation and enrichment resulting in locally abundant atacamite, chrysocolla, and chalcocite mineralization that form a supergene zone with complex geometries up to 600 m thick in vertical drillholes. Supergene mineralization is generally subdivided into supergene sulfide and -oxide mineralization with minor quantities of exotic copper mineralization. Atacamite and associated copper sulfate mineralization occurs dominantly within the copper oxide zone, although the relative timing and mechanism for formation is less well understood. The exotic Cu mineralization is dominantly hosted in the overlying clastic and volcanic rocks at the Santa Cruz deposit. Supergene mineralization at the Santa Cruz deposit reflects a mature, long lived supergene system (nearly complete chalcocite replacement of hypogene sulfides) with a well-developed supergene stratigraphy consisting of distinctly zoned mineralization with chrysocolla overlying chrysocolla-atacamite, overlying atacamite, overlying chalcocite. There is also abundant evidence for post rotational development of multiple supergene enrichment horizons that shows two or more distinct supergene sulfide events. During the tertiary (no later than 15 Ma), the rapid burial of the Santa Cruz deposit led to the cessation of supergene enrichment processes.

 

6.3.6Mineralization at the Texaco Deposit

 

Hypogene Mineralization

 

Hypogene mineralization at the Texaco deposit has been intersected with over a dozen widely spaced drillholes, historical and modern. However, the hypogene system has not been systematically tested and remains open in several directions. Hypogene mineral assemblages consist of chalcopyrite, pyrite, and molybdenite hosted within sulfide and quartz-sulfide veins, veinlets, vein breccias, and breccias, as well as fine to coarse disseminations within vein envelopes (dominantly replacing mafic minerals biotite and hornblende). Chalcopyrite and pyrite mineralization also occur locally as chemical cements in breccias similar to those found in the Southwest Exploration Area that occur with quartz and gypsum minerals. Hypogene mineralization is related to Laramide-aged quartz-biotite-feldspar granodiorite and latite porphyry dikes. At the Texaco deposit these sulfide minerals are interpreted to exhibit a distinct zoning pattern with a core zone of chalcopyrite-molybdenite, a chalcopyrite zone, and a pyrite zone. The core and chalcopyrite zone host rocks are altered by biotite-orthoclase-sericite and represent a potassic core transitionally overprinted by retrograde phyllic-style veins and alteration. Host rocks in the outer chalcopyrite zone and pyrite zone are altered by quartz-sericite (Kreis, 1978).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 84

 

Supergene Mineralization

 

Drilling by ASARCO at Texaco deposit delineated supergene copper mineralization that remains open in several directions. The supergene mineralization at the Texaco deposit consists of a similar geochemical stratigraphy to that observed at the Santa Cruz deposit. Supergene mineralization contains a well-developed leached cap with abundant limonite consisting of hematite over goethite and minor jarosite. The limonite leached cap zone overlies a chalcocite enrichment blanket of variable thickness. However, supergene mineralization at the Texaco deposit contains much less copper-oxide and copper-chloride mineralization compared to the Santa Cruz deposit. Brochantite (copper sulfate) was also noted as the dominant copper-bearing phase in historic hole SC-23, where it is overprinting chalcocite (Kreis, 1978). Chalcocite mineralization was historically interpreted by previous operators as having been developed in an originally thick sub-horizontal blanket and subsequently thinned due to faulting and extension.

 

6.3.7Mineralization at the Texaco Ridge Exploration Area

 

Recent drilling of the Texaco Ridge Exploration Area has identified some of the highest quartz-sulfide vein densities within the various deposits which may reflect proximity to one of the main hypogene hydrothermal centers. Hypogene mineralization includes quartz vein-hosted and disseminated chalcopyrite, pyrite, and molybdenite. Hypogene mineralization is associated with Laramide-aged biotite granodiorite porphyries, biotite latite porphyries, and rare amphibole-biotite latite porphyry dikes.

 

As with the Santa Cruz and East Ridge deposits, the Texaco Ridge Exploration Area contains a laterally extensive mafic conglomerate sequence within the basal conglomerates. Classic supergene chalcocite, chrysocolla, and atacamite are absent from the Texaco Ridge Exploration Area either due to erosion or poor development well below the paleo water table. Exogeneous mineralization, however, occurs as narrow bands of copper-bearing vermiculite and smectite-group clays within finely laminated lacustrine sediments above the mafic conglomerate and at the upper contact of the mafic conglomerate. Calcite and siderite occur commonly throughout the mafic conglomerate. The interior and basal sections of the mafic conglomerate are relatively unaltered or weakly altered by low-temperature weathering clays. Below the bedrock contact, the only noteworthy supergene mineralization identified is chalcocite rimming and partial replacement of primary hypogene chalcopyrite. The relatively thick sequence of mafic conglomerates in this exploration area may have acted as a significant reductant diminishing the weathering of hypogene sulfides and/or the supergene enrichment may have been eroded away by denudation prior to the deposition of the mafic conglomerate locally. It is important to note that supergene enrichment does occur within the Texaco deposit, located immediately east of the Texaco Ridge Exploration Area, at lower elevations of the paleotopography. If supergene enrichment of the Texaco Ridge Exploration Area was eroded, then there is still potential for supergene enrichment to exist laterally or at lower elevations to the east within the same structural block.

 

6.3.8Mineralization at the East Ridge deposit

 

Hypogene Mineralization

 

Hypogene mineralization in the East Ridge deposit is correlative and displaced from the Santa Cruz deposit. Hypogene mineralization includes broad zones of low to moderate-density quartz-sulfide veins consisting of pyrite, chalcopyrite, molybdenite, and rare bornite mineralization. Lithologies hosting hypogene mineralization in and around the East Ridge deposit include Precambrian Oracle Granite, Laramide Porphyry, and Precambrian Diabase.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 85

 

Supergene Mineralization

 

Supergene mineralization in the East Ridge deposit is also correlative and partially displaced from the Santa Cruz deposit. Supergene sulfides are present as thin, stacked intervals displaced from those in the Santa Cruz deposit by D2 faulting. Chrysocolla and atacamite mineralization is more broadly distributed, especially near the fault-controlled paleo-valley formed between the Santa Cruz deposit and the East Ridge deposit. Supergene mineralization tends to thin to the east and south within the East Ridge deposit.

 

6.3.9Mineralization at the Southwest Exploration Area

 

Hypogene Mineralization

 

Hypogene mineralization within the Southwest Exploration Area is characterized by a single drill intercept that encountered bedrock at approximately 1000 m depth. The hypogene sulfides include pyrite and chalcopyrite that occur dominantly as a chemical cement within a magmatic-hydrothermal breccia. The breccia may resemble collapse breccias observed as late-stage features in many porphyry copper deposits. The breccia clasts are dominated by a Laramide-aged porphyritic diorite with lesser oracle granite and Laramide-age aplite, each with sparse quartz-sulfide veining; the clasts have been moderately to intensely potassically altered. Gangue minerals within the breccia cement include quartz, gypsum, and locally, anhydrite.

 

Supergene Mineralization

 

Supergene mineralization has not been encountered in the Southwest Exploration Area with diamond drilling. The bedrock contact was a faulted contact, and thus any supergene mineralization was displaced. Supergene mineralization may occur higher within the structural block.

 

6.4Deposit Types

 

The Santa Cruz Project consists of a series of porphyry copper systems exhibiting typical features of porphyry copper deposits. Porphyry copper deposits form in areas of shallow magmatism within subduction-related tectonic environments (Sillitoe, 2010). The Santa Cruz Project has typical characteristics of a porphyry copper deposit defined by Berger et al. (2008) as follows (Figure 6-5):

 

·Copper-bearing sulfides are localized in a network of fracture-controlled stockwork veinlets and as disseminated grains in the adjacent altered rock matrix.

·Alteration and mineralization at 1 km to 4 km depth are genetically related to magma reservoirs emplaced into the shallow crust (6 km to over 8 km), predominantly intermediate to silicic in composition, in magmatic arcs above subduction zones.

·Intrusive rock complexes associated with porphyry Cu mineralization and alteration are predominantly in the form of upright-vertical cylindrical stocks and/or complexes of dykes.

·Zones of phyllic-argillic and marginal propylitic alteration overlap or surround a potassic alteration assemblage.

·Cu may also be introduced during overprinting phyllic-argillic alteration events.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 86

 

 

 

Source: Modified after Lowell and Guilbert, 1970

 

Figure 6-4: Simplified Alteration and Mineralization Zonation Model of a Porphyry Cu Deposit

 

Hypogene (or primary) mineralization occurs as disseminations and in stockworks of veins, in hydrothermally altered, shallow intrusive complexes and their adjacent country rocks (Berger, Ayuso, Wynn, & Seal, 2008). Sulfides of the hypogene zone are dominantly chalcopyrite and pyrite, with minor bornite. The hydrothermal alteration zones and vein paragenesis of porphyry copper deposits is well known and provide an excellent tool for advancing exploration. Schematic cross sections of typical alteration zonations and associated minerals are presented in Figure 6-6.

 

Supergene enrichment processes are a common feature of many porphyry copper systems located in certain physiogeographical regions (semi-arid). It can result in upgrading of low-grade porphyry copper sulfide mineralization into economically significant accumulations of supergene copper species (copper oxides, halides, carbonates, etc.). This is particularly important in the southwestern United States. Supergene enrichment occurs when a porphyry system is uplifted to shallow depths and is exposed to surface oxidation processes. This leads to the copper being leached from the hypogene mineralization during weathering of primarily pyrite, which generates significant sulfuric acid in oxidizing conditions, and redeposits the copper below the water table as supergene copper sulfides such as chalcocite and covellite. Figure 6-6 illustrates a schematic section through a secondary enriched porphyry copper deposit, identifying the main mineral zones formed as an overprint from weathering of the hypogene system.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 87

 

 

 

Source: Fernandez-Mote et al., 2018; modified after Münchmeyer 1996; Sillitoe 2005

 

Figure 6-5: Schematic Representation of an Exotic Cu Deposit and its Relative Position to an Exposed Porphyry Cu System

 

The Santa Cruz Project has a history of oxidation and leaching that resulted in the formation of enriched chalcocite horizons, and later stages of oxidation and leaching, which modified the supergene Cu mineralization by oxidizing portions of it in place and mobilizing some of the chalcocite to a greater depth (Figure 6-7). This process is associated with descending water tables and or erosion and uplift of the system, or changes in climate, or hydrogeological systematics.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 88

 

 

 

Source: modified from Asmus, B., 2013

 

Figure 6-6: Typical Cu Porphyry Cross-section Displaying Hypogene and Supergene Mineralization Processes and Associated Minerals

 

These processes are also known to be associated with the generation of exotic copper deposits. Exotic copper mineralization is a complex hydrochemical process linking supergene enrichment, lateral copper transport, and precipitation of copper-oxide minerals in the drainage network of a porphyry copper deposit (Mote et al., 2001).

 

6.5QP Opinion

 

The Nordmin QP is of the opinion that the structure, geology, and mineralization of the Santa Cruz Project is well understood and has been derived from the interpretation of drilling and the work of several authors over multiple decades.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 89

 

7Exploration

 

7.1Geophysical Exploration

 

IE has completed several geophysical exploration surveys over the Santa Cruz Project area including ground gravity, ground magnetics, seismic, and proprietary Typhoon™ 3D PPD IP. The geophysical datasets have been used to assist with geological interpretation and improved drill targeting.

 

7.1.1Ground Gravity Survey

 

Phase 1 of the Santa Cruz ground gravity survey was completed in January 2022. 615 stations were collected within the property boundaries. Phase 2 of the survey was done in August 2022 with 307 more gravity stations collected (Figure 7-1).

 

Topographic surveying was performed simultaneously with gravity data acquisition. The gravity stations were surveyed in WGS84 UTM Zone 12 North coordinates in meters. The GEOID18 geoid model was used to calculate North American Vertical Datum of 1988 (NAVD88) elevations from ellipsoid heights. The coordinate system parameters used on this survey are summarized in Table 7-1.

 

Table 7-1: Ground Gravity Topographic Survey Coordinate System Parameters

 

Datum Name WGS84
Ellipsoid World Geodetic System 1984
Semi-Major Axis 6378137.000 m
Inverse Flattening 298.257223563
Transformation None
Projection Type Universal Transverse Mercator
Zone UTM 12 North
Origin Latitude 00º 00' 00.00000" N
Central Meridian 111º 00' 00.00000" W
Scale Factor 0.9996
False Northing 0
False Easting 500000 m
Geoid Model GEOID18 (CONUS)

 

Source: Nordmin, 2023

 

Relative gravity measurements were made with Scintrex CG-5 Autograv gravity meters. Topographic surveying was performed with Trimble Real-Time Kinematic (RTK) and Fast-Static (FS) GPS. The gravity survey is tied to a gravity base established in January 2022 and was designated “CASA”. The CASA base is tied to the U.S. Department of Defense gravity base in Florence, AZ; designated “FLORENCE” (DoD reference number 3213-1). The integer value 9999 was used in the CG-5 gravity meters as the identifier for CASA and 8888 was used for Florence. The coordinates in WGS84/NAVD88 on these bases is in Table 7-2.

 

Table 7-2: Ground Gravity Base Information

 

Base ID CG5 ID Absolute Gravity Latitude Longitude Elevation (m)
FLORENCE 8888 979 393.50 mGal 33.03114 -111.37930 459.3
CASA 9999 979 393.522 mGal 32.87787 -111.70788 399.59

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 90

 

Gravity data processing was performed with the Gravity and Terrain Correction module of Seequent’s Oasis montaj (Version 2021.2 [20211201.32]) The raw ASCII text files were edited to remove unwanted records prior to data processing in Oasis montaj. Editing consisted of:

 

Removal of incomplete integration records (i.e., <90 sec).

Removal of assumed additional low frequency noise likely associated with elastic relaxation, instabilities in the sensor and/or high tilt susceptibility introduced during transport between stations.

 

Local slope measurements were also entered into the Line column of the ASCII text file during this stage. A residual drift correction was then applied to produce observed gravity. Gravity data were then processed to Complete Bouguer Anomaly (CBA) over a range of densities from 2.00 g/cc through 3.00 g/cc at steps of 0.05 g/cc using standard procedures and formulas.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 91

 

 

 

 

 

Source: Nordmin, 2023

 

Figure 7-1: Gravity Survey Stations (top) and Complete Gravity Survey Results (bottom)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 92

 

7.1.2Ground Magnetics Survey

 

A 243 line-kilometer (line-km) ground magnet survey was carried out between January 22-27, 2022. Data was collected on lines spaced 50 m apart with an orientation of 33° from true north. Results and lines used can be seen in Figure 7-2. The survey was completed by Magee Geophysical services of Reno, Nevada, using geometrics G858 Cesium vapor magnetometers for both base station and rover data collection. G858 magnetometers can sample the earth's magnetic field at a 10Hz frequency. GPS data is collected synchronously during data acquisition at a rate of 1Hz and is embedded in the data for accurate positioning of the transects. Data from the rover and base were downloaded daily and diurnal variations were corrected for in Geometric’s own MagMap software. Final data processing was completed in Seequent’s Oasis montaj software. Artifacts from cultural noise were removed and a narrow non-linear filter was used to smooth very short wavelength near surface features.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 93

 

 

 

 

 

Source: Nordmin, 2023

 

Figure 7-2: Ground Magnetics Survey Lines (top) and Ground TMI RTP Ground Magnetics Results (bottom)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 94

 

7.1.3Typhoon™ Survey

 

The Santa Cruz Project Typhoon™ 3D PPD IP survey was conducted by IE using the Typhoon™ 2 high power geophysical system. Acquisition of 50 line-km of 3D PPD time domain IP data was completed over an area of 27 km2 from May to July 2022 (Figure 7-3).

 

The survey was designed as a 3D PPD array with 32 East-West receiver lines spaced 200 m apart with electrodes spaced at 100 m intervals along the lines. Current injections were performed at 136 transmitter pits spaced 500 m apart East-West and 400 m apart North-South (Figure 7-3). The remote electrode was installed approximately 4 km south of the center of the grid for the first half of the survey and then moved to a pit at the Northwest corner of the survey for receiver lines south of Clayton Road.

 

 

 

Source: Nordmin, 2023

Note: Green dots are receiver electrodes and red dots are transmitter points.

 

Figure 7-3: Layout of the Santa Cruz 3D IP Survey

 

September 2023

SEC Technical Report Summary – Santa CruzPage 95

 

Table 7-3: Santa Cruz Typhoon™ 3D PPD IP Survey Specifications

 

Survey type Time domain 3D IP
Survey design Pole-dipole IP 200m receiver line spacing; 100m electrode spacing
Survey area 27 km2
Transmitter Typhoon™ 2
Planned number of Tx poles 154
Transmit frequencies 1/12 Hz (= 0.0833 Hz)
Injected current 8-26 Amps
Receiver sampling rate 150 Hz
Recording time 12 minutes
Number of cycles for stacking 100
Receiver Type DIAS 32
Number of receiver dipoles 5,000-7,000 unique dipoles per injection, 1011000 total dipole recordings
Line km 128.6 line-km of receivers
Receiver dipole lengths 100 m to 1,000 m
Receiver electrode station spacing Grid: 200 m north-south, 100 m east-west
Recovered frequency range 0.0833 Hz
IP integration window 450 -2,940 ms
IP conversion factor None applied
Sensor N/A
GPS datum WGS84
GPS projection UTM Zone 12N
GPS heights WGS84

 

Source: Nordmin, 2023

 

7.1.42D Seismic Refraction Tomography

 

Two-dimensional (2D) surface seismic refraction tomography surveys were conducted at the Santa Cruz Project. The purpose of the survey was to determine bedrock depth and topography. Surface seismic data were acquired along four lines by Bird Seismic Services, Inc., Globe, Arizona, in a manner suitable for 2D tomographic analyses using a Seistronix EX-6 seismograph, configured with sufficient channels to extend the entire length of each line, in 32-bit floating-point format data, 2 second record length and 0.5 ms sample rate. Geospace SM24 geophones (one per takeout) with 10-Hz natural frequencies were placed at intervals of 12.2 m along each line and source points were located between geophones at intervals of 36.6 m. A United Service Alliance AF-450 nitrogen gas accelerated weight-drop seismic source with a 450 lb weight was used. For this Project, the seismic data were stacked nominally five to ten times at each source point to increase the signal-to-noise ratio. Stacking, or signal enhancement, involved repeated source impacts at the same point into the same set of geophones.

 

The seismic tomography data for this Project were processed using the Rayfract (version 3.36) computer software program developed by Intelligent Resources Inc. of Vancouver, BC, Canada. The models produced by the Rayfract tomography program use multiple signal propagation paths (e.g., refraction, reflection, transmission, and diffusion) that comprise a first break. See Figure 7-4.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 96

 

 

 

Source: Nordmin, 2023

 

Figure 7-4: Refraction Seismic Tomography Survey Results

 

7.1.5Historical Geophysical Exploration

 

IE has historical documents that detail historical geophysical exploration efforts and results over the Santa Cruz – Sacaton system (Table 7-4). To date, none of the original data has been located, but historic interpretations and results remain valuable.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 97

 

Table 7-4: Summary of Historical Exploration on the Santa Cruz Project and Surrounding Area

 

Year Activities Company(s) Prospect/Deposit Description Notes
1961 Prospecting and discovery ASARCO Sacaton ASARCO geologists Kinnison and Blucher identify Sacaton Discovery Outcrop, consisting of weak Cu-oxide mineralization on what will eventually be the margin of the Sacaton pit. Based on Asarco's recognition that porphyry Cu deposits often have little or no associated Cu staining and on information from surrounding porphyry Cu deposits, Asarco's geologists were looking for other prospects in the area by driving and walking around. There was a faint trace of Cu-stain but not enough to have attracted previous exploration or prospecting. The outcrop was granite with a thin dyke of porphyry – both altered to quartz-sericite-clay with weak but pervasive jarosite-goethite and a few specks of hematite after chalcocite, particularly in the dyke. The outcrop was expected to have originally contained about 2% sulfides as pyrite/chalcocite/chalcopyrite.
1961 Geophysical Surveying ASARCO Sacaton ASARCO Geophysical Dept. report. Geophysical survey results were used to improve the interpretations of bedrock depth in the Sacaton area.
1967 Ground IP geophysics ASARCO   1967 Internal report indicates eight holes were drilled over a large 13.2 mv/v IP anomaly around 15 miles SW of Sacaton. None of the drillholes intersected primary sulfides, and the chargeability response was interpreted to have been caused by water-saturated clays in the overlying conglomerate.
1988-1991 Borehole Geophysics SCJV Santa Cruz Downhole geophysical data was collected during the in situ leach test program. During the SCJV In Situ leach tests (approximately 1988-1991), an undisclosed number of holes were subjected to downhole/borehole geophysical surveying that implemented the collection of caliper, density, resistivity, gamma-ray spectrometer, neutron activation spectrometry, dipmeter, sonic waveform, IP, and magnetic susceptibility data collection methods.
1988 In situ Cu Mining Research Project USBR, SCJV (ASARCO Santa Cruz Inc., and Freeport McMoRan Copper & Gold Inc.) Santa Cruz Santa Cruz selected over other deposits for research site; Field testing begins. The Santa Cruz deposit was 1,250 ft to 3,200 ft below the surface and contains 1.0 billion tons of potentially leachable grading 0.55% total Cu. The joint venture owns 7,000 surface acres, with the Cu mineralization under approximately 250 acres.

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 98

 

Historical ASARCO documents detail multiple IP surveys over the Sacaton and Santa Cruz deposits, as well as the historic Santa Rosa Prospect. Historic IP survey reports indicate that extraneous responses in IP surveys at Sacaton and Santa Cruz resulted from groundwater present in the valley fill conglomerates (i.e., W.G. Farley “ASARCO, 1967, Induced Polarization Pinal County” report documents IP response correlating with the water table at Santa Cruz and Sacaton, within the overlying gravels, and well above the basement contact). In 1991, the ASARCO-Hanna-Getty-Bureau of Mines joint venture contracted Zonge Geophysical to implement Controlled Source Audio-frequency Magnetotelluric (CSAMT) tests evaluating the potential to use the application to non-invasively monitor in situ leachate plume activity during in situ leach tests. Results from phase one and two testing from May 1990 through June 1991 were considered promising for tracking leachate detectability with salt doping/tracing. Historic airborne and ground magnetic interpretations are also available, though of lesser value than modern magnetic datasets (Figure 7-5).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 99

 

 

Source: Nordmin, 2023

 

Figure 7-5: ASARCO Map Illustrating Interpreted Ground and Aeromagnetic Data Detailed in Historic Report: “Recommended Drilling Santa Cruz Project,” M.A.970 Pinal County, Arizona, August 21, 1964, by W.E. Saegart

 

September 2023

SEC Technical Report Summary – Santa CruzPage 100

 

7.2Historical Data Compilation

 

IE has obtained geological information in the form of historical maps, sections, drill reports, drill logs, and assay result reports. As a significant component of the exploration program, the historical drill logs were interpreted and used to create a 3D (Leapfrog Geo™) geologic model of the Santa Cruz Project. Three-dimensional geological interpretations were derived from historical drill logs and 2D sections containing geologic interpretations. The drill core data was compiled by IE geologists.

 

The historical drilling within the Project area can be separated into several series: CG (Hanna-Getty), SC (ASARCO), and T and HC drilling (related to the In Situ program described in Section 5.3.2). A plan view map of collar locations is in Figure 7-6 and a summary is provided in Table 7-5.

 

 

 

Source: IE, 2023

 

Figure 7-6: Plan Map of Historical Drillhole Collars

 

September 2023

SEC Technical Report Summary – Santa CruzPage 101

 

The CG series drilling comprised 122 drillholes (CG-001 to CG-122) with 102,563 m drilled. Twenty-nine original drill cross-sections from 1978 to 1980 covering 92 holes were digitized. Information collected included elevation, total and rotary depths, basic lithology, assays from the three most predominant Cu minerals (total Cu, acid soluble Cu, and molybdenum), and survey depth. The archived data was originally recorded using a series of numerical codes documented in the “Casa Grande Copper Company Ore Reserves Study” for the Hanna Mining Company (Watts Griffis McOuat, 1982).

 

The SC series drilling, by ASARCO, comprised 80 drillholes (SC-001 to SC-078) with 62,754 m drilled. The archived data was originally logged using a series of numerical codes documented in the Casa Grande Copper Company Ore Reserves Study for the Hanna Mining Company (Watts Griffis McOuat, 1982).

 

The T and HC drilling were related to the In Situ testing in the 1990’s described in Section 5.3.2. The T series drilling comprised five holes (T-1 to T-5) with 2,295 m drilled. The HC series drillings comprised five holes (HC-1 to HC-5) with 3,622 m drilled. A summary of data available by each of the drill sets is shown in Table 7-5.

 

Table 7-5: Summary of Available Data by Region

 

  Dataset Region Total
CG SC HC T
Total number of holes 121 80 5 5 211
Total drilled (m) 102,563 62,754 3,622 2,295 165,317
% Collar Survey (holes) 100 100 0 0 100
% Downhole Survey (m drilled) 62.1 65.9     63.4
% Assay (m drilled) 96.5 34.4     73.0

 

Source: Nordmin, 2023

 

7.3Drilling

 

7.3.1Historical Drilling – Santa Cruz and East Ridge Deposits

 

Santa Cruz deposit diamond drilling consists of 108,301 m of core from 126 NQ drillholes completed between 1965 to 1996. Historically, these two deposits were undifferentiated, thus drilling totals are cumulative for both deposits. The historic diamond drill core is currently unavailable for review. Table 7-6 provides a summary of the drill campaigns by year and operator.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 102

 

Table 7-6: Drilling History Within the Santa Cruz Deposit and East Ridge Deposit Area

 

Year Operator Total (m)
Unknown Casa Grande Copper Company, Hanna-Getty Mining 9,083
ASARCO/Freeport McMoRan Gold Co. JV 744
1965 ASARCO/Freeport McMoRan Gold Co. JV 2,698
1974 2,068
1975 Casa Grande Copper Company, Hanna-Getty Mining 2,348
ASARCO/Freeport McMoRan Gold Co. JV 682
1976 Casa Grande Copper Company, Hanna-Getty Mining 16,633
ASARCO/Freeport McMoRan Gold Co. JV 513
1977 Casa Grande Copper Company, Hanna-Getty Mining 28,147
ASARCO/Freeport McMoRan Gold Co. JV 9,184
1978 Casa Grande Copper Company, Hanna-Getty Mining 22,301
1979 ASARCO/Freeport McMoRan Gold Co. JV 2,468
1980 5,516
1989 In Situ Testing 2,630
1996 3,286

 

Source: Nordmin, 2023

 

During the initial site assessment, it was determined that historical collar coordinates had variable errors. A program was conducted to check the collar locations of a selection from the drillhole database using a professionally licensed surveying company, D2 land surveying. Based on the transformation for these spot-checked drillholes, nearby hole collar locations were adjusted. All historical drilling is conducted with a vertical dip. For the Santa Cruz deposit, the drilling has been completed along 100 m spaced section lines with drillholes spaced 90 to 100 m apart on each section line.

 

Holes are reverse circulation (RC) drilled through Tertiary sediments until the approximate depth of the Oracle Granite is reached by Major Drilling. Drilling is then switched to diamond drilling through the crystalline basement rocks, and again drilling is executed by Major Drilling.

 

7.3.2Historic Drilling – Texaco Deposit

 

The historic Texaco deposit diamond drilling consists of 23,848 m of core from 27 diamond NQ drillholes completed between 1975 to 1997. The drillholes in this deposit area consist of the SC drillhole series. The historic diamond drill core is currently unavailable for review. Table 7-7 provides a summary of the drill campaigns by year and operator.

 

Table 7-7: Drilling History within the Texaco Deposit

 

Year Operator Total (m)
1975 ASARCO and Freeport McMoRan Gold JV 1,719
1976 ASARCO and Freeport McMoRan Gold JV 5,207
1977 Casa Grande Copper Co., Hanna-Getty Mining 2,883
ASARCO and Freeport McMoRan Gold JV 5,906
1996 ASARCO and Freeport McMoRan Gold JV 5,086
1997 3,043

 

Source: Nordmin, 2023

 

During the initial site assessment, it was determined that historical collar coordinates had variable errors. A program was conducted to check the collar locations of a selection from the drillhole database using a professionally licensed surveying company, D2 land surveying. Based on the transformation for these spot-checked drillholes, nearby hole collar locations were adjusted. All historical drilling is conducted with a vertical dip. For the Texaco deposit, historical drilling has been completed along 100 m to 200 m spaced section lines with drillholes spaced 200 m apart on each section line. The average drill section and spacing in the Texaco deposit is approximately 200 m and varies between approximately 90 m and 250 m.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 103

 

7.3.32021 Twin Hole Drilling – IE

 

The company completed five diamond drillholes totaling 4,739 m within the Santa Cruz deposit at the time of this Technical Report (Table 7-8). The five diamond drillholes were twins of the historical drillholes. All drilling was a mix of rotary and diamond drilling where the first 300 m to 500 m of drilling was rotary to get past the barren tertiary sediments. All samples from within the interpreted mineralized zone were assayed for total Cu (%), acid soluble Cu (%), cyanide soluble Cu (%), and molybdenum (ppm). The collar locations, downhole surveys, logging (lithology, alteration, and mineralization), sampling and assaying between the two sets of drillholes were used to determine if the historical holes had valid information and would not be introducing a bias within the geological model or Mineral Resource Estimate. The comparison included a QA/QC analysis of the historical drillholes (Section 9.2). Plans for infill drilling and drilling of angled holes have been made to test the continuity of mineralization and gain more information.

 

Table 7-8: IE 2021 Twin Hole Drilling on the Santa Cruz Deposit

 

Year Operator Total (m)
2021 IE 4,739

 

Source: Nordmin, 2023

 

A total of five historical holes were reviewed with the following outcomes (Figure 7-7):

 

·All five historical hole assays aligned with the 2021 diamond drilling assays.

·The 2021 diamond drilling assays were of higher resolution due to smaller sample sizes.

·The recent drilling validated the ASARCO cyanide soluble assays.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 104

 

 

 

Source: IE, 2023

 

Figure 7-7: Plan Map of the Twinned Drillholes and Historical Drillhole Collars

 

7.3.42021-2022 Drilling Program – IE

 

Core Logging

 

Initially, IE Geologists enter information into several tabs within MX Deposit™ while logging, including lithology, alteration, veining, structural zone, structure point, and mineralization. Optional characterizers, including color and grain size, are available for further identification.

 

The current database has five major rock types, including 47 major lithologies in line with historically logged lithologies, 21 lithological textures, 17 alteration types, and 15 lithological structures. There are 28 unique economic minerals recorded in the current database, including chalcocite, chrysocolla, chalcopyrite, cuprite, molybdenum, and atacamite. X-ray fluorescence (XRF) measurements are taken by IE wherever mineralization of interest is present for internal use.

 

Surveying

 

During 2021-2022 drilling, downhole surveying was conducted using an EZ Gyro single shot taken from the collar and every 30 m afterwards as the tool is being pulled from the hole.

 

After hole completion, all drillholes were surveyed using borehole geophysics and video through Southwest Exploration Service, LLC. Each borehole was surveyed for 4RX Sonic-Gamma (sampled every 0.06 m), Acoustic Televiewer (sampled every 0.003 m), E-Logs-Gamma (sampled every 0.06 m), and a Gamma Caliper test for fluid temperature conduction (sampled every 0.06 m). This downhole surveying allowed for the calibration of drillhole information post-drilling to ensure that surveying was correct and lithological and mineralogical contacts were logged properly. The downhole surveying has collected very accurate structural measurements.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 105

 

Specific Gravity

 

At both the Santa Cruz and Texaco deposits, no specific gravity (SG) measurements were taken from historical diamond drill core. The 2021 diamond drilling was aimed at twinning CG historical drilling to confirm the historical logging and assays. The 2022 diamond drilling program was aimed at expanding and defining the mineral resource. IE collected 2,639 SG measurements over 74 diamond drillholes across the Santa Cruz Project (Table 7-9). SG measurements are taken every 3 m or at each new lithology to ensure a well-established database of measurements for each rock type. Measurements are taken using a water dispersion method. The samples are weighed in air, and then the uncoated sample is placed in a basket suspended in water and weighed again.

 

Table 7-9: Santa Cruz Project SG Measurements

 

Lithology Average SG
Alluvium 1.88
Whitetail Conglomerate 2.28
Apache Leap Tuff 2.25
Gila Conglomerate 2.29
Mafic Conglomerate 2.37
Basal Conglomerate 2.43
Diabase 2.61
Laramide Porphyry 2.56
Oracle Granite 2.52
Pinal Schist 2.65
Unspecified 2.36

 

Source: Nordmin, 2023

 

Due to the overall low SG values, multiple styles of SG measurement were tested, all of which indicated that these values are correct. The low SG values are interpreted to be due to the high porosity from leaching, faulting, and brecciation throughout the mineralized rock.

 

2021-2022 Drilling Program Summary

 

Drilling performed by IE over the 2021-2022 calendar years included 6005.18 m from 6 completed drillholes in 2021 and 60,116.54 m from 106 completed drillholes completed in 2022. Drilling during the 2021-2022 drilling campaigns was focused on multiple areas at the Santa Cruz Project including the Southwest Exploration Area, Santa Cruz Deposit, East Ridge Deposit, Texaco Ridge Exploration Area, and Texaco Deposit. Much of the drilling was focused on mineral resource definition within the Santa Cruz Deposit with secondary exploration drilling in the other project Areas.

 

Drilling was performed using a variety of drilling equipment and methodologies including reverse circulation, diamond coring, tricone rotary, and shallow sonic boring. Drilling methodology varied across the Santa Cruz Project depending on objective and target depth. The majority of drilling was standard PQ diamond coring from surface to maximize the amount of core sample recovered for use in multiple sampling and testing programs. Non-resource related drilling, particularly focused outside the Santa Cruz Deposit itself was performed using tricone rotary surface as pre-collar parent holes for subsequent HQ size coring at target depths. Tricone rotary with HQ tails was utilized when targets did not require large-diameter coring from surface, allowing for this more cost-efficient technique.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 106

 

Reverse circulation and sonic drilling were also used in 2022 for rapid characterization of: bedrock interface underneath sedimentary cover, soil and clay, and overburden sediments and conglomerate units, respectively.

 

Abandonment procedures for all drilling performed during the 2021 and 2022 campaigns were designed and held to meet or exceed State mandated requirements. The majority of drilling reaching or exceeding depths over 100 m utilized borehole abandonment of State approved methods involving: abandonite to approximately 20 m below the geological contact between bedrock and overburden sediments, if present, then the installation of appropriately sized Bradley plugs, labeled with the associated borehole ID, as the base for pumping and curing State approved cement across the geological contact to seal the interface, followed by additional abandonite to approximately 20 m below the topographic surface, with an approximately 20 m cement cap, with the hole tagged and labeled for collar demarcation. Shallow drillholes, particularly those drilled utilizing only reverse circulation or sonic drilling methods, were abandoned using cement from total depth to surface with cap, with the hole tagged and labeled for collar demarcation.

 

A drillhole summary complete to December 31, 2022 can be seen in Table 7-10. A map of drillhole collar locations can be seen in Figure 7-8. Cross sections and further geological discussion is presented in Section 11.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 107

 

Table 7-10: 2021-2022 Drilling Summary

 

Drillhole Depth (m) Azimuth (˚) Dip (˚) Assay Status/Comment
SCC-001 1274.98 0 -90 All Assays Received
SCC-002 965.30 0 -90 All Assays Received
SCC-003 778.46 0 -90 All Assays Received
SCC-004 926.91 0 -90 All Assays Received
SCC-005 793.70 0 -90 All Assays Received
SCC-006 1344.17 235 -50 All Assays Received
SCC-007 1220.27 0 -90 All Assays Received
SCC-008 945.79 225 -75 All Assays Received
SCC-009 664.46 0 -90 All Assays Received
SCC-010 1099.41 225 -90 All Assays Received
SCC-011 379.78 0 -90 All Assays Received
SCC-012 855.27 0 -90 Hole Abandoned, No Assays Taken
SCC-013 1023.52 190 -84 All Assays Received
SCC-014 548.94 0 -90 All Assays Received
SCC-015 931.16 0 -90 Hole Abandoned, No Assays Taken
SCC-016 1139.34 0 -90 All Assays Received
SCC-017 848.87 0 -90 All Assays Received
SCC-018 1123.34 0 -90 All Assays Received
SCC-019 284.07 0 -90 All Assays Received
SCC-020 822.35 230 -80 All Assays Received
SCC-021 446.83 241 -80 All Assays Received
SCC-022 446.80 241 -80 All Assays Received
SCC-022A 406.50 241 -80 All Assays Received
SCC-023 897.94 207 -75 All Assays Received
SCC-024 309.82 0 -90 All Assays Received
SCC-025 858.77 228 -82 In Lab, Assays Pending for 494-570;739.5-858.77 m
SCC-026 741.88 209 -80 In Lab, Assays Pending for 396-688 m
SCC-027 550.47 259 -82 All Assays Received
SCC-028 369.72 230 -75 All Assays Received
SCC-029 917.91 227 -78 In Lab, Assays Pending for 402-453.69; 855-906 m
SCC-030 280.26 230 -75 All Assays Received
SCC-031 904.34 222 -85 In Lab, Assays Pending for 749-900 m
SCC-032 811.68 220 -78 In Lab, Assays Pending for 557.63-811.68
SCC-033 455.07 230 -60 All Assays Received
SCC-034 201.17 230 -60 All Assays Received
SCC-035 161.54 230 -75 All Assays Received
SCC-036 181.36 230 -60 All Assays Received
SCC-037 379.78 230 -80 All Assays Received
SCC-038 311.81 230 -75 All Assays Received
SCC-039 252.98 230 -60 All Assays Received
SCC-040 292.60 230 -75 All Assays Received
SCC-041 323.09 230 -60 All Assays Received
SCC-042 360.58 230 -60 All Assays Received
SCC-043 127.10 230 -60 Hole Abandoned, No Assays Taken
SCC-044 304.80 230 -60 All Assays Received
SCC-045 883.76 225 -73 All Assays Received
SCC-046 210.31 230 -60 All Assays Received
SCC-047 474.57 230 -60 All Assays Received
SCC-048 915.47 259 -82 In Lab, Assays Pending for 587-781; 808-829; 869-915.47 m
SCC-049 274.32 230 -60 All Assays Received
SCC-050 398.22 230 -60 All Assays Received

 

 

September 2023

SEC Technical Report Summary – Santa CruzPage 108

 

Drillhole Depth (m) Azimuth (˚) Dip (˚) Assay Status/Comment
SCC-051 114.30 230 -60 All Assays Received
SCC-052 880.87 224 -75 All Assays Received
SCC-053 1041.80 224 -85 In Lab, Assays Pending for 471-656; 756-951 m
SCC-054 686.71 248 -85 In Lab, All Assays Pending
SCC-055 304.80 224 -85 RC pre-collar, No Assays Taken
SCC-056 846.73 224 -78 In Lab, Assays Pending for 561-846.73 m
SCC-057 996.70 221 -74 In Lab, All Assays Pending
SCC-058 889.25 226 -69 In Lab, All Assays Pending
SCC-059 977.18 212 -80 In Lab, All Assays Pending
SCC-060 304.80 224 -75 RC pre-collar, No Assays Taken
SCC-061 304.80 238 -75 RC pre-collar, No Assays Taken
SCC-062 304.80 250 -82 RC pre-collar, No Assays Taken
SCC-063 932.99 200 -80 In Lab, Assays Pending for 390.31-405; 475-932.99 m
SCC-064 204.22 0 -90 RC Hole - Not Sampled, No Assays Taken
SCC-065 577.90 0 -90 In lab, Assays Pending for 576-577.9 m
SCC-066 228.60 0 -90 RC Hole - Not Sampled, No Assays Taken
SCC-067 243.84 0 -90 RC Hole - Not Sampled, No Assays Taken
SCC-068 1019.09 231 -75 In Lab, Assays Pending 487-556; 807-890; 917-1,019.1 m
SCC-069 228.65 0 -90 RC Hole - Not Sampled, No Assays Taken
SCC-070 246.89 0 -90 RC Hole - Not Sampled, No Assays Taken
SCC-071 243.84 0 -90 RC Hole - Not Sampled, No Assays Taken
SCC-072 274.32 0 -90 RC Hole - Not Sampled, No Assays Taken
SCC-073 916.38 0 -90 In Lab, All Assays Pending
SCC-074 259.08 0 -90 RC Hole - Not Sampled, No Assays Taken
SCC-075 280.41 0 -90 RC Hole - Not Sampled, No Assays Taken
SCC-076 152.40 0 -90 RC Hole - Not Sampled, No Assays Taken
SCC-077 320.04 0 -90 RC Hole - Not Sampled, No Assays Taken
SCC-078 100.00 0 -90 Sonic Hole - Not Sampled, No Assays Taken
SCC-079 454.15 232 -75 RC pre-collar, No Assays Taken
SCC-080 759.56 205 -85 In Lab, Assays Pending
SCC-081 525.17 0 -90 In Lab, All Assays Pending
SCC-082 112.70 0 -90 Sonic Hole - Not Sampled, No Assays Taken
SCC-083 399.28 222 -85 RC pre-collar, No Assays Taken
SCC-084 915.92 214 -80 All Assays Received
SCC-085 388.00 254 -78 RC pre-collar, No Assays Taken
SCC-086 149.96 0 -90 Sonic Hole - Not Sampled, No Assays Taken
SCC-087 426.72 234 -80 RC pre-collar, No Assays Taken
SCC-088 579.73 0 -90 In Lab, All Assays Pending
SCC-089 100.28 0 -90 Sonic Hole - Not Sampled, No Assays Taken
SCC-090 712.01 0 -90 Currently Sampling, All Assays Pending
SCC-091 457.20 0 -90 All Assays Received
SCC-092 666.60 0 -90 In Lab, All Assays Pending
SCC-093 546.81 0 -90 In Lab, All Assays Pending
SCC-093A 959.20 0 -90 In Lab, All Assays Pending
SCC-094 99.06 0 -90 Sonic Hole - Not Sampled, No Assays Taken
SCC-095 457.20 0 -90 All Assays Received
SCC-096 981.76 0 -90 Currently Sampling, All Assays Pending
SCC-097 457.20 0 -90 All Assays Received
SCC-098 ACTIVE 0 -90 Actively Drilling
SCC-099 884.38 0 -90 In Lab, All Assays Pending
SCC-100 259.08 0 -90 RC Hole - Not Sampled, No Assays Taken
SCC-101 413.00 0 -90 In Lab, All Assays Pending
SCC-102 827.37 0 -90 In Lab, Assays Pending for 270-468; 638.5-827.38m
SCC-103 60.96 0 -90 Hole Abandoned, No Assays Taken
SCC-105 1029.30 0 -90 In Lab, Assays Pending for 554-637; 756-1,029.31 m
SCC-106 583.84 0 -90 Currently Sampling, All Assays Pending

 

September 2023

SEC Technical Report Summary – Santa CruzPage 109

 

Drillhole Depth (m) Azimuth (˚) Dip (˚) Assay Status/Comment
SCC-107 1074.12 0 -90 In Lab, All Assays Pending
SCC-108 858.62 0 -90 Currently Sampling, All Assays Pending
SCC-109 859.08 0 -90 Currently Sampling, All Assays Pending
SCC-110 864.71 0 -90 Currently Sampling, All Assays Pending
SCC-111 ACTIVE 270 -80 Actively Drilling
SCC-112 ACTIVE 0 -90 Actively Drilling

 

Source: Nordmin, 2023

 

 

 

Source: IE, 2023

 

Figure 7-8: Plan Map of Historical and 2021 and 2022 IE Drillhole Collars

 

September 2023

SEC Technical Report Summary – Santa CruzPage 110

 

7.3.52023 Drilling Program

 

Drilling performed by IE over the 2023 calendar year to-date includes 29,322.02 m from 36 completed drillholes. Drilling during the 2023 campaign focused on exploration, mineral resource infill and definition, and geotechnical and hydrogeological infill and definition. Exploration is continuing around the Project to identify new zones that may be incorporated into future studies.

 

Drilling was performed using tricone or polycrystalline diamond compact rotary drilling and diamond core drilling. The drilling methodology used depended on the objective and target depth. The majority of drilling was polycrystalline diamond compact or rotary drilling through the overburden sediments to a pre-planned depth, followed by standard PQ or HQ diamond coring through the bedrock complex for data collection and use in multiple sampling and testing programs. Some drilling was performed as core from surface to provide drill core material of the overburden for certain sampling and testing programs.

 

Abandonment procedures for all drilling performed during 2023 were designed to meet or exceed State mandated requirements. The majority of drilling reaching or exceeding depths over 100 m utilized State approved borehole abandonment methods involving: abandonite to approximately 20 m below the geological contact between bedrock and overburden sediments, if present, then the installation of appropriately sized Bradley plugs, labeled with the associated borehole ID, as the base for pumping and curing State approved cement across the geological contact to seal the interface, followed by additional abandonite to approximately 20 m below the topographic surface, with an approximately 20 m cement cap, with the hole tagged and labeled for collar demarcation.

 

A drillhole summary complete to June 8th, 2023, can be seen in Table 7-11. A map of drillhole collar locations can be seen in Figure 7-9.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 111

 

Table 7-11: 2023 Drilling Summary

 

Drillhole Depth (m) Azimuth (˚) Dip (˚) Assay Status/Comment
SCC-001 1,274.98 0 -90 All Assays Received
SCC-002 965.30 0 -90 All Assays Received
SCC-003 778.46 0 -90 All Assays Received
SCC-004 926.91 0 -90 All Assays Received
SCC-005 793.70 0 -90 All Assays Received
SCC-006 1,265.83 225 -56 All Assays Received
SCC-007 1,344.17 235 -50 All Assays Received
SCC-008 1220.27 0 -90 All Assays Received
SCC-009 945.79 225 -75 All Assays Received
SCC-011 1,099.41 0 -90 All Assays Received
SCC-012 379.78 0 -90 Hole Abandoned, No Assays Taken
SCC-013 855.27 0 -90 All Assays Received
SCC-014 1023.52 190 -84 All Assays Received
SCC-015 548.94 0 -90 Hole Abandoned, No Assays Taken
SCC-016 931.16 0 -90 All Assays Received
SCC-017 1,139.34 0 -90 All Assays Received
SCC-018 848.87 0 -90 All Assays Received
SCC-019 1,123.34 0 -90 All Assays Received
SCC-021 822.35 230 -80 All Assays Received
SCC-022 446.80 241 -80 All Assays Received
SCC-022A 813.36 241 -80 All Assays Received
SCC-023 897.94 207 -75 All Assays Received
SCC-025 858.77 228 -82 All Assays Received
SCC-026 741.88 209 -80 All Assays Received
SCC-027 550.47 259 -82 All Assays Received
SCC-029 917.91 227 -78 All Assays Received
SCC-031 904.34 222 -85 All Assays Received
SCC-032 811.68 220 -78 All Assays Received
SCC-045 883.76 225 -73 All Assays Received
SCC-048 915.47 259 -82 All Assays Received
SCC-052 880.87 224 -75 All Assays Received
SCC-053 1,041.80 224 -85 All Assays Received
SCC-054 686.71 248 -85 All Assays Received
SCC-055 304.80 224 -85 Hole Abandoned, No Assays Taken
SCC-056 846.73 224 -78 All Assays Received
SCC-057 996.70 221 -74 All Assays Received
SCC-058 889.25 226 -69 All Assays Received
SCC-059 980.24 212 -80 All Assays Received
SCC-060 274.32 224 -75 Hole Abandoned, No Assays Taken
SCC-061 304.80 238 -75 Hole Abandoned, No Assays Taken
SCC-062 304.80 250 -82 Hole Not Sampled, No Assays Pending
SCC-063 932.99 200 -80 All Assays Received
SCC-064 204.22 0 -90 Hole Not Sampled, No Assays Pending
SCC-065 577.90 0 -90 All Assays Received
SCC-066 228.60 0 -90 Hole Not Sampled, No Assays Pending
SCC-067 243.84 0 -90 Hole Not Sampled, No Assays Pending
SCC-068 1,019.09 231 -75 All Assays Received
SCC-069 228.60 0 -90 Hole Abandoned, No Assays Taken
SCC-070 246.89 0 -90 Hole Abandoned, No Assays Taken
SCC-071 243.84 0 -90 Hole Abandoned, No Assays Taken
SCC-072 274.32 0 -90 Hole Abandoned, No Assays Taken
SCC-073 916.38 0 -90 All Assays Received
SCC-074 259.08 0 -90 Hole Not Sampled, No Assays Pending
SCC-075 289.56 0 -90 Hole Not Sampled, No Assays Pending
SCC-076 152.40 0 -90 Hole Not Sampled, No Assays Pending
SCC-077 320.04 0 -90 Hole Not Sampled, No Assays Pending

 

September 2023

SEC Technical Report Summary – Santa CruzPage 112

 

Drillhole Depth (m) Azimuth (˚) Dip (˚) Assay Status/Comment
SCC-078 100.00 0 -90 Hole Not Sampled, No Assays Pending
SCC-079 454.15 232 -75 Hole Not Sampled, No Assays Pending
SCC-080 759.56 205 -85 All Assays Received
SCC-081 525.17 0 -90 All Assays Received
SCC-082 112.70 0 -90 Hole Not Sampled, No Assays Pending
SCC-083 457.20 222 -85 Hole Abandoned, No Assays Taken
SCC-084 915.92 214 -80 All Assays Received
SCC-085 387.10 254 -78 Hole Not Sampled, No Assays Pending
SCC-086 149.96 0 -90 Hole Not Sampled, No Assays Pending
SCC-087 426.72 234 -80 Hole Not Sampled, No Assays Pending
SCC-088 579.73 0 -90 All Assays Received
SCC-089 100.28 0 -90 Hole Not Sampled, No Assays Pending
SCC-090 712.01 0 -90 All Assays Received
SCC-091 457.20 0 -90 All Assays Received
SCC-092 666.60 0 -90 All Assays Received
SCC-093 546.81 0 -90 All Assays Received
SCC-093A 959.21 0 -90 All Assays Received
SCC-095 457.20 0 -90 All Assays Received
SCC-096 981.76 0 -90 All Assays Received
SCC-097 457.20 0 -90 All Assays Received
SCC-098 1274.52 0 -90 All Assays Received
SCC-099 884.38 0 -90 All Assays Received
SCC-101 413.00 0 -90 All Assays Received
SCC-102 827.38 0 -90 All Assays Received
SCC-103 60.96 0 -90 Hole Abandoned, No Assays Taken
SCC-105 1,029.30 0 -90 All Assays Received
SCC-106 583.84 0 -90 All Assays Received
SCC-107 1,074.12 0 -90 All Assays Received
SCC-108 858.62 0 -90 All Assays Received
SCC-109 859.08 0 -90 All Assays Received
SCC-110 864.72 0 -90 All Assays Received
SCC-111 660.50 270 -80 All Assays Received
SCC-112 1,025.96 0 -90 All Assays Received
SCC-113 994.26 0 -90 All Assays Received
SCC-114 808.33 0 -90 All Assays Received
SCC-115 931.77 0 -90 All Assays Received
SCC-116 726.80 0 -90 All Assays Received
SCC-117 865.02 0 -90 All Assays Received
SCC-118 381.30 140 -65 All Assays Received
SCC-119 998.83 0 -90 All Assays Received
SCC-120 980.54 140 -65 Currently cutting and sampling
SCC-121 760.48 0 -90 All Assays Received
SCC-122 921.56 0 -90 In Lab, All Assays Pending
SCC-123 819.00 0 -90 In Lab, All Assays Pending
SCC-124 710.79 0 -90 In Lab, Assays Pending
SCC-125 890.78 0 -90 In Lab, All Assays Pending
SCC-126 404.93 320 -67 Hole Not Sampled, No Assays Pending
SCC-127 922.02 0 -90 In Lab, Assays Pending
SCC-128 692.96 0 -90 In Lab, Assays Pending
SCC-129 832.10 0 -90 In Lab, All Assays Pending
SCC-130 779.37 0 -90 In Lab, All Assays Pending
SCC-131 873.86 0 -90 Currently cutting and Sampling
SCC-132 898.70 0 -90 In Lab, All Assays Pending
SCC-133 890.93 0 -90 Cutting and sampling
SCC-134 931.62 0 -90 Cutting and sampling
SCC-135 829.05 0 -90 Cutting and sampling
SCC-136 803.76 46 -65 Cutting and sampling

 

September 2023

SEC Technical Report Summary – Santa CruzPage 113

 

Drillhole Depth (m) Azimuth (˚) Dip (˚) Assay Status/Comment
SCC-137 865.94 0 -90 Cutting and sampling
SCC-138 698.44 0 -90 Cutting and sampling
SCC-139 738.68 0 -90 Cutting and sampling
SCC-140 882.70 0 -90 Cutting and sampling
SCC-141 790.80 0 -90 Cutting and sampling
SCC-142 670.71 0 -90 Actively Drilling
SCC-143 590.09 0 -90 Actively Drilling
SCC-144 ACTIVE 0 -90 Actively Drilling
SCC-145 ACTIVE 0 -90 Actively Drilling
SCC-146 ACTIVE 143 -65 Actively Drilling
SCC-147 ACTIVE 0 -90 In Lab, All Assays Pending
SCC23-GT-001 1,141.78 100 -70 In Lab, All Assays Pending
SCC23-GT-002 874.01 140 -75 Currently cutting and sampling
SCC23-GT-003 733.65 45 -80 Actively Drilling

 

Source: IE, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 114

 

 

 

Source: IE, 2023

 

Figure 7-9: Plan Map of Historical and 2021 and 2022 IE Drillhole Collars

 

7.3.6Geotechnical Drilling

 

See Section 13.2.

 

7.3.7Hydrogeology

 

See Section 13.3.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 115

 

7.4QP Opinion

 

In the opinion of the Nordmin QP, the quantity and quality of the historical data compilation and twin hole drilling programs, geophysical surveys, geologic logging, are sufficient to support the MRE.

 

Core logging completed by IE and previous operators meet industry standards for exploration on replacement and porphyry deposits:

 

·Collar surveys and downhole surveys were performed using industry-standard instrumentation

·Drillhole orientations are appropriate for the mineralized style

·Drillhole intercepts demonstrate that sampling is representative

 

Ongoing collection of geotechnical and hydrogeologic data will be pertinent for future studies.

 

No other factors were identified with the data collected from the drill programs that could significantly affect the mineral resource estimate.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 116

 

8Sample Preparation, Analysis and Security

 

8.1Sample Preparation Methods and Quality Control Measures

 

From September 2021 to December 2022, IE samples were sent to one of four independent laboratories: Skyline Laboratories located in Tucson, AZ, USA; SGS Laboratories located in Burnaby, BC, Canada, SGS Lakefield, ON, Canada for SEQ Analysis; or American Assay Laboratories located in Sparks, NV, USA. All samples sent through SGS Laboratories were prepped at SGS Burnaby, BC, Canada. At the time, all assay labs were well established and recognized assay and geochemical analytical services companies and are independent of IE.

 

All four laboratories are recognized by the International Standard demonstrating technical competence for a defined scope and the operation of a laboratory quality management system (ISO 17025). Additionally, Skyline Laboratories is recognized by ISO 9001, indicating that the quality management system conforms to the requirements of the international standard. SGS Canada Minerals Burnaby conforms to requirements of ISO/IEC 17025 for specific tests as listed on their scope of accreditation. American Assay Laboratories carries approval from the State of Nevada Department of Conservation and Natural Resources Division of Environmental Protection. Due to QA/QC failures at American Assay Laboratories, IE discontinued work with this lab.

 

8.2Sample Preparation, Assaying and Analytical Procedures

 

The diamond drill core from the Santa Cruz and Texaco Deposits were sampled by IE in 2021 under the direct supervision of Santa Cruz Geology Manager Christopher Seligman, MAusIMM CP(Geo) and Eric Castleberry, PG, US Operations Manager. Diamond drill core from the Santa Cruz, East Ridge, and Texaco Deposits sampled by IE in 2022 were completed under the direct supervision of Santa Cruz Geology Manager Christopher Seligman and Santa Cruz Exploration Manager Arron Jergenson.

 

Samples were cut lengthwise, either in half or in four quarters, using an NTT brand diamond bladed saw or a Husqvarna table saw (Figure 8-1). The sample consisted of one half or one quarter of the core which was placed in a plastic sample bag labeled with the sample number and the sample bag was sealed with a zip tie. That bag was then placed in a burlap sample bag labeled with the sample number and a sample tag added between the plastic and burlap bags. The sample tag corresponded with the tag stapled to the core box where the remaining half or three-quarters of the core was placed for catalog and storage (Figure 8-2). The burlap sample bags were then placed in labeled large plastic bags in batches of 25, that bag was sealed with a zip tie, and those bags were placed in large fold-out plastic bins for transport to the lab facility (Figure 8-3).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 117

 

 

Source: Nordmin, 2023

 

Figure 8-1: NTT Diamond Bladed Automatic Core Saw used for Cutting Diamond Drill Core for Sampling

 

September 2023

SEC Technical Report Summary – Santa CruzPage 118

 

 

 

Source: Nordmin, 2023

 

Figure 8-2: Tee Street Core Storage Facility

 

 

Source: Nordmin, 2023

 

Figure 8-3: (Left) samples placed in burlap and inner plastic bags labeled with sample numbers; (Right) sample batches placed in large plastic bags and bins for shipping to lab

 

September 2023

SEC Technical Report Summary – Santa CruzPage 119

 

8.2.1Skyline Laboratories

 

Half of the total drill core samples taken during the 2021 and 2022 diamond drilling program were prepared and analyzed at Skyline Laboratories, Tucson, Arizona. The samples were crushed from the split core to prepare a total sample of up to 5 kilograms (kg) at 75% passing 6 mm. Samples were then riffle split, and a 250 g sample was pulverized with a standard steel to plus 95% passing at 150 µm. After sample pulp preparation, the samples were analyzed in the following manner:

 

·All samples were analyzed for total Cu using multi-acid digestions with an atomic absorption spectrometry (AAS) finish. The lower limit of detection is 0.01% for total Cu, with an upper detection limit of 10%.

 

·Sequential Analysis for cyanide soluble and acid soluble Cu were conducted via multi-acid leaching with an AAS finish. For sequential acid leaching (SEQ) Cu analyses, the lower limit of detection is 0.005%, with an upper detection limit of 10%.

 

·Molybdenum was prepared using multi-acid digestion and analyzed using inductively coupled plasma optical emission spectrometry (ICP-OES). This analysis has a lower detection limit of 0.001%.

 

·Samples greater than 10% Cu, with a 20% threshold, were analyzed again using a Long Iodine method.

 

8.2.2SGS Laboratories

 

Half of the total drill core samples taken during the 2022 diamond drilling program were prepared and analyzed at SGS Laboratories in Burnaby, BC, Canada or SGS Lakefield, ON, Canada. The samples were crushed from the split core to prepare a total sample of up to 5 kg at 6 mm. Samples were then riffle split, and a 250 g sample was crushed to 75% passing at 2 mm. The sample was then pulverized with a standard steel to plus 85% passing at 75 µm. After sample pulp preparation, the samples were analyzed in the following manner:

 

·All samples were analyzed for total Cu using a sodium peroxide fusion with an inductively coupled plasma atomic emission spectroscopy (ICP-AES) finish. The lower limit of detection is 0.001% for total Cu, with an upper detection limit of 5%.

 

·Sequential analysis for cyanide soluble and acid soluble Cu were conducted via multi-acid leaching with an AAS finish. For SEQ Cu analyses, the lower limit of detection is 0.005%, with an upper detection limit of 100%.

 

·Molybdenum was prepared using multi-acid digestion and analyzed using ICP-OES. This analysis has a lower detection limit of 0.05 ppm and an upper detection of 10,000 ppm.

 

·Samples greater than 5% Cu, with a 30% threshold, were analyzed again using sodium peroxide fusion overlimit with an ICP-OES finish.

 

8.2.3American Assay Laboratories

 

A single drillhole from the 2021 drill campaign was prepared and analyzed at American Assay Laboratories in Sparks, Nevada. The samples were crushed from the split core to prepare a total sample of up to 5 kg at 75% passing 10 mm. Samples were then riffle split and pulverized with a standard steel to plus 95% passing at 150 µm. After sample pulp preparation, the samples were analyzed in the following manner:

 

September 2023

SEC Technical Report Summary – Santa CruzPage 120

 

·All samples were analyzed for total Cu using AAS, total molybdenum with an inductively coupled plasma mass spectrometer (ICP-MS), and acid soluble and cyanide soluble Cu with sequential leaching with an AAS finish. A measurement for residual Cu was also taken; this is essentially the Cu that is measured that cannot be attributed to cyanide soluble, acid soluble, or total Cu. The lower detection limit is 0.001%, with an upper limit of 10%. Samples greater than or equal to 10% were alternatively measured using Long Iodine analysis, which has an upper detection limit of 20%.

 

·The detection limit at American Assay Laboratories is an order of magnitude less than at Skyline Laboratories; therefore, there is a lower resolution, but during a comparison between the two labs, it was found that the results were similar.

 

·Due to QA/QC failures at American Assay Laboratories, IE discontinued work with this lab.

 

8.2.4Historical Core Assay Sample and Analysis

 

Historically, samples for both the Texaco and Santa Cruz Deposit drilling were sent to Skyline Laboratories to be assayed for standard total Cu and non-sulfide Cu methods. Samples were crushed and split; a 250 to 500 mg sample was then prepared in the following ways:

 

·Total Cu analysis samples were dissolved using a mixture of hydrochloric acid (HCl), nitric acid (HNO3) and perchloric acid (HClO4) over low heat. The mixture was then measured using AAS.

 

·Non-sulfide Cu was dissolved using a mixture of sulfuric acid (H2SO4) and sulfurous acid (H2SO3) over moderate to high heat. This mixture was then filtered, diluted, and measured using AAS.

 

8.3Specific Gravity Sampling

 

A combined total of 2,637 SG measurements for the Santa Cruz, East Ridge, and Texaco Deposits were provided during 2021-2022 on site drill core measurements. SG measurements were taken from representative core sample intervals (approximately 0.1 m to 0.2 m long). SG was measured using a water dispersion method. The samples were weighed in air, and then the uncoated sample was placed in a basket suspended in water and weighed again. SG is calculated by using the weight in air versus the weight in water method (Archimedes), by applying the following formula:

 

Specific Gravity =   Weight in Air
(Weight in Air − Weight in Water)

 

8.4Quality Control Procedures/Quality Assurance

 

Quality assurance and quality control (QA/QC) measures were set in place to ensure the reliability and trustworthiness of exploration data. These measures include written field procedures and independent verifications of aspects such as drilling, surveying, sampling, assaying, data management, and database integrity. Appropriate documentation of QC measures and regular analysis of QC data is essential as a safeguard for project data and form the basis for the QA program implemented during exploration.

 

Analytical QC measures involve internal and external laboratory procedures implemented to monitor the precision and accuracy of the sample preparation and assay data. These measures are also important to identify potential sample sequencing errors and to monitor for contamination of samples.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 121

 

The Company submitted a blank, standard, or duplicate sample on every seventh sample. Sampling and analytical QA/QC protocols typically involve taking duplicate samples and inserting QC samples (certified reference material [CRM] and blanks) to monitor the assay results' reliability throughout the drill program.

 

8.4.1IE Santa Cruz Sampling

 

Standards

 

During the 2022 drilling campaign, IE submitted eight different CRMs as a part of their QA/QC protocol across the Santa Cruz, East Ridge, and Texaco Deposits. OREAS 905 was archived by OREAS and was replaced with OREAS 901 by the Company as the new low-grade copper standard. The review of the CRM results identified no laboratory failures at Skyline Laboratories or SGS Laboratories. Table 8-1 shows the eight standards submitted to Skyline by IE and their mean measured values. At the time of writing, not enough results for CRMs measured at SGS Laboratories had been returned to adequately track their progress. Table 8-2 shows the seven internal standards used by Skyline as quality control and tracking of their average results. Figure 8-4 to Figure 8-8 are charts which track the progress of CRM measurements over time. Few measurements go above or below three standard deviations, which is followed by a recalibration at the lab and a re-analysis of the sample.

 

Table 8-1: IE Submitted Standards Measured at Skyline Laboratories

 

Standard Count Best
Cu
Total
Mean
Value
Cu Total
(%)
Bias
(%)
Best
Value CuAs-
SEQ
(%)
Mean
Value
CuAS-
SEQ
(%)
Bias
(%)
Best
Value CuCN-
SEQ
(%)
Mean
Value
CuCN-
SEQ
(%)
Bias
(%)
OREAS 908 64 1.26 1.25 0.01 1.078 1.08 -0.002 0.023 0.023 0.002
OREAS 907 28 0.6 0.649 0.049 0.531 0.55 0.019 0.018 0.012 0.006
OREAS 906 19 0.31 0.322 0.012 - - - - - -
OREAS 905 21 0.155 0.159 0.004 - - - - - -
OREAS 901 55 0.141 0.140 -0.71 - - - - - -
OREAS 501d 51 0.27 0.273 0.003 - - - - - -
OREAS 503d 35 0.53 0.528 0.002 - - - - - -
OREAS 504c 44 1.13 1.108 0.022 - - - - - -

 

Source: Nordmin, 2023

 

Table 8-2: Skyline Internal QA/QC CRM Samples and Results

 

Standard Count Best
Value
CuT
(%)
Mean
Value
CuT
(%)
Bias
(%)
Best
Value Cu-AS-
SEQ
(%)
Mean
Value
Bias
(%)
Best
Value Cu-CN-
SEQ
(%)
Mean
Value
Bias
(%)
SKY5 801 - - - 0.18 0.18 0.0 0.155 0.153 0.658
SKY6 783 - - - 0.42 0.4 -4.1 0.076 0.083 6.410
CDN-CM-21 221 0.54 0.53 0 - - - - - -
CDN-CM-14 442 1.06 1.06 0 - - - - - -
CDN-CM-29 187 0.74 0.74 0 - - - - - -
CDN-CM-33 185 0.35 0.35 0 - - - - - -
CDN-W-4 220 0.14 0.14 0.00 - - - - - -

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 122

 

 

Source: Nordmin, 2023

 

Figure 8-4: Santa Cruz Deposit, OREAS 501d Standard Total Cu (g/t), Assayed at Skyline Laboratories

 

 

Source: Nordmin, 2023

 

Figure 8-5: Santa Cruz Deposit, OREAS 906 Standard Total Cu (g/t), Assayed at Skyline Laboratories

September 2023

SEC Technical Report Summary – Santa CruzPage 123

 

 

Source: Nordmin, 2023

 

Figure 8-6: Santa Cruz Deposit, OREAS 907 Standard Total Cu (g/t), Assayed at Skyline Laboratories

 

 

Source: Nordmin, 2023

 

Figure 8-7: Santa Cruz Deposit, OREAS 908 Standard Total Cu (g/t), Assayed at Skyline Laboratories

 

September 2023

SEC Technical Report Summary – Santa CruzPage 124

 

 

Source: Nordmin, 2023

 

Figure 8-8: Santa Cruz Deposit, OREAS 901 Standard Total Cu (g/t), Assayed at Skyline Laboratories

 

Blanks

 

The Company submitted 725 coarse granite blanks to Skyline Laboratories and 147 coarse granite blanks to SGS Laboratories for the Santa Cruz Deposit drilling in 2022 as part of its QA/QC process. No significant carryover of elevated metals is evident in blanks measured at Skyline Laboratories nor SGS Laboratories. A threshold of +/- 0.02% Cu was accepted for blank samples, if samples did not initially pass. Samples which failed were reanalyzed. Figure 8-9 illustrates the blank performance of Skyline and Figure 8-10 displays the performance of SGS.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 125

 

 

Source: Nordmin, 2023

 

Figure 8-9: Blank Results from Skyline Laboratory Analyses from the 2021 and 2022 Drill Program

 

September 2023

SEC Technical Report Summary – Santa CruzPage 126

 

 

Source: Nordmin, 2023

 

Figure 8-10: SGS Blank Results from the 2022 Drill Program

 

Duplicates

 

The Company submitted 737 field duplicates to Skyline Laboratories during the 2021 and 2022 drill campaigns as a part of its QA/QC process. Duplicates were also submitted to SGS Laboratories for the 2022 drill program, but not enough samples had been returned to track results at the time of writing. Original versus duplicate sample results for total Cu (%) are present in Figure 8-11. The results of the field duplicates are in good agreement for total Cu (%), acid soluble Cu (%) and cyanide soluble Cu (%).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 127

 

 

 

Source: Nordmin, 2023

 

Figure 8-11: Field Duplicate Results, in Cu (%), Measured at Skyline Laboratories for the Santa Cruz Deposit

 

8.4.22022 East Ridge and Texaco Sampling

 

Standards

 

During the 2022 drilling campaign IE submitted 5 CRMs for drilling conducted within the Texaco exploration property and 5 CRMs for the drilling within East Ridge. Results for two submitted CRMs were available for East Ridge at the time of writing. A review of the CRM results identified no failures from Skyline Laboratories or SGS laboratories for samples submitted from either deposit. Table 8-3 and Table 8-4 show the CRMs submitted to Skyline and a comparison of the average grade for different measured elements for Texaco and East Ridge, respectively. Figure 8-12 to Figure 8-14 are charts tracking submitted standard results to Skyline Laboratories for the Texaco Deposit. Figure 8-15 and Figure 8-16 are charts tracking submitted standard results to Skyline Laboratories for the East Ridge Deposit. Table 8-5 and Figure 8-16 show the CRM results submitted to SGS Laboratories for East Ridge drilling. Not enough assays were received for standard OREAS 906 or OREAS 503d to create a chart tracking progress. In the rare instance of failure (outside three standard deviations), the lab re-calibrated equipment and re-analyzed the batch.

 

Table 8-5 contains Skyline internal CRM measurements and their results.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 128

 

Table 8-3: IE Inserted CRMs for Texaco Drilling 2022

 

Standard Count Best Value Cu (%) Mean Value Cu (%) Bias (%)
Oreas 906 3 0.32 0.31 0.00
Oreas 501d 12 0.27 0.27 0.18
Oreas 503d 3 0.53 0.53 1.32
Oreas 504c 28 1.13 1.082 -2.54
OREAS 151a 12 0.166 0.171 2.91

 

Source: Nordmin, 2023

 

Table 8-4: IE inserted CRMs for East Ridge Drilling 2022, measured at Skyline Laboratories

 

Standard Count Best Value
Cu (%)
Mean Value
Cu (%)
Bias
(%)
Best Value
SEQ (%)
Mean Value
SEQ (%)
Bias
(%)
OREAS 901 9 0.141 0.144 2.13 - - -
OREAS 906 2 0.31 0.31 -0.13 0.259 0.263 1.54

 

Source: Nordmin, 2023

 

Table 8-5: IE inserted CRMs for East Ridge Drilling 2022, measured at SGS Laboratories

 

Standard Count Best Value
CuT (%)
Mean Value
CuT (%)
Bias
(%)
Best Value SEQ
Cu (%)
Mean
Value
Bias
(%)
OREAS 906 3 0.31 0.309 0.32 0.259 0.266 -2.63

 

Source: Nordmin, 2023

 

 

 

Source: Nordmin, 2023

 

Figure 8-12: Texaco Deposit, OREAS 151a Standard Total Cu (g/t), Assayed at Skyline Laboratories

 

September 2023

SEC Technical Report Summary – Santa CruzPage 129

 

 

Source: Nordmin, 2023

 

Figure 8-13: Texaco Deposit, OREAS 504c Standard Total Cu (%), Assayed at Skyline Laboratories

 

 

Source: Nordmin, 2023

 

Figure 8-14: Texaco Deposit, OREAS 501d Standard Total Cu (%), Assayed at Skyline Laboratories

 

September 2023

SEC Technical Report Summary – Santa CruzPage 130

 

 

Source: Nordmin, 2023

 

Figure 8-15 East Ridge Deposit, OREAS 901 Standard Total Cu (%), Assayed at Skyline Laboratories

 

 

Source: Nordmin, 2023

 

Figure 8-16: East Ridge Deposit, OREAS 906 Standard Total Cu (%), Assayed at SGS Laboratories

 

September 2023

SEC Technical Report Summary – Santa CruzPage 131

 

Blanks

 

The Company submitted 70 coarse granite blanks for the Texaco Deposit drilling and 13 for East Ridge during the 2022 drill campaign to Skyline Laboratories, at the time of this report, as part of its QA/QC process. Additionally, four blanks were sent to SGS Laboratories for the East Ridge Deposit during the 2022 drill campaign. No significant carryover of elevated metals is evident in blanks measured at Skyline Laboratories. A threshold of +/- 0.02% Cu was accepted for blank samples, if samples did not initially pass. Samples which failed were reanalyzed. Figure 8-17 and Figure 8-18 are charts for blanks inserted into Texaco and East Ridge drilling measured at Skyline Laboratories. Figure 8-19 is a chart for blanks inserted into East Ridge drilling, measured by SGS Laboratories.

 

 

Source: Nordmin, 2023

 

Figure 8-17: Texaco Blanks for Total Cu

 

September 2023

SEC Technical Report Summary – Santa CruzPage 132

 

 

 Source: Nordmin, 2023

 

 Figure 8-18: East Ridge Blanks, Total Cu

 

September 2023

SEC Technical Report Summary – Santa CruzPage 133

 

 

Source: Nordmin, 2023

 

Figure 8-19: East Ridge SGS Laboratories Blanks, Total Cu (%)

 

Duplicates

 

The Company submitted 14 field duplicates to Skyline Laboratories and five to SGS Laboratories for East Ridge and 74 to Skyline Laboratories for Texaco during the 2022 drilling campaign, at the time of this report, as a part of its QA/QC process. Original versus duplicate sample results for total Cu (%) are present in Figure 8-20 to Figure 8-22. All samples appear to be in reasonable agreement. Slight to moderate differences can be explained by a “nugget” effect and geological inconsistencies in mineralization.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 134

 

 

Source: Nordmin, 2023

 

Figure 8-20: Original Versus Field Duplicate Sample Results for the Texaco Deposit as total Cu (%) from Samples Submitted to Skyline Laboratories

 

September 2023

SEC Technical Report Summary – Santa CruzPage 135

 

 

Source: Nordmin, 2023

 

Figure 8-21: Original Versus Field Duplicate Sample Results for the East Ridge Deposit as Total Cu (%) from Samples Submitted to Skyline Laboratories

 

September 2023

SEC Technical Report Summary – Santa CruzPage 136

 

 

Source: Nordmin, 2023

 

Figure 8-22: Original Versus Field Duplicate Sample Results for East Ridge Deposit as Total Cu (%) from Samples Submitted to SGS Laboratories

 

8.4.32021 IE Sampling

 

Standards

 

During the 2021 drilling campaign IE submitted six different CRMs as a part of their QA/QC protocol, with 33 submitted in total. The review of the CRM results identified no laboratory failures at Skyline Laboratories and seven failures at American Assay Laboratories. OREAS 908 falls within the range of +/- two standard deviations for Cu Total (%) and acid soluble Cu (%) (Table 8-6 and Table 8-7 and Figure 8-23 to Figure 8-28). Skyline Laboratories submitted seven different CRMs, including two inhouse CRMs, as a part of their QA/QC process (Table 8-8), and American Assay Laboratories submitted three different CRMs as a part of their QA/QC process (Table 8-9).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 137

 

Table 8-6: CRMs Inserted by IE into Sample Batches Sent to Skyline Laboratories

 

Standard Count Best
Value
Cu
(%)
Mean
Value
Cu
(%)
Bias
(%)
Best
Value
Cu-AS-
SEQ
(%)
Mean
Value
Cu-AS-
SEQ
(%)
Bias
(%)
Best
Value
CuCN-
SEQ
(%)
Mean
Value
CuCN-
SEQ
(%)
Bias
(%)
OREAS 908 9 1.26 1.256 0.004 1.078 1.067 0.011 0.022 0.024 0.002
OREAS 907 6 0.6 0.652 0.052 0.531 0.54 0.009 0.018 0.015 0.003
OREAS 906 4 0.31 0.31 0 0.269 1.126 -0.86 0.01 0.019- -0.009
OREAS 501 d 6 0.27 0.27 0 - - - - - -
OREAS 503 d 4 0.53 0.524 0.006 - - - - - -
OREAS 504c 1 1.13 1.09 0.04 - - - - - -

 

Source: Nordmin, 2023

 

Table 8-7: CRMs Inserted by IE into Sample Batches Sent to American Assay Laboratories

 

Standard Count Best
Value
Cu
(%)
Mean
Value
Cu
(%)
Bias
(%)
Best
Value
CuAS-
SEQ
(%)
Mean
Value
CuAS-
SEQ
(%)
Bias
(%)
Best
Value
CuCN-
SEQ
(%)
Mean
Value
CuCN-
SEQ
(%)
Bias
(%)
OREAS 908 10 1.26 1.299 0.039 1.078 1.067 0.64 0.022 0.023 0.001
OREAS 907 5 0.6 0.643 0.043 0.531 0.54 1.31 0.018 0.009 0.009
OREAS 906 2 0.31 0.33 0.02 - - - - - -
OREAS 503c 1 0.27 0.545 0.275 - - - - - -
OREAS 504c 3 1.13 1.11 0.02 - - - - - -

 

Source: Nordmin, 2023

 

Table 8-8: Skyline Laboratory Submitted CRMs

 

Standard Count Best
Value
CuT
(%)
Mean
Value
CuT
(%)
Bias
(%)
Best
Value
Cu-AS-
SEQ
(%)
Mean
Value
Bias
(%)
Best
Value Cu-
CN-SEQ
(%)
Mean
Value
Bias
(%)
SKY5 48 - - - 0.18 0.18 0.00 0.155 0.156 0.00
SKY6 48 - - - 0.42 0.41 0.01 0.076 0.077 0.00
CDN-CM-21 14 0.54 0.54 0.00 - - - - - -
CDN-CM-14 34 1.06 1.07 -0.01 - - - - - -
CDN-CM-29 12 0.74 0.74 0.00 - - - - - -
CDN-CM-33 12 0.35 0.36 -0.01 - - - - - -
CDN-W-4 20 0.14 0.14 0.00 - - - - - -

 

Source: Nordmin, 2023

 

Table 8-9: American Assay Laboratory Submitted CRMs

 

Standard Count

Best
Value Cu
(%)

Mean
Value Cu
(%)

Bias
(%)

Best Value
CuAS-SEQ
(%)

Mean Value
Cu-AS-SEQ
(%)

Bias
(%)

OREAS 600b 3 0.05 0.051 0.00 - - -
OREAS 602b 3 0.494 0.495 0.00 - - -
OREAS 905 3 0.157 0.158 0.00 0.128 0.127 0.001

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 138

 

 

 

Source: Nordmin, 2023

 

Figure 8-23: Santa Cruz Deposit, OREAS 908 Standard Total Cu (g/t), Assayed at Skyline Laboratories

 

 

Source: Nordmin, 2023

 

Figure 8-24: Santa Cruz Deposit, OREAS 908 Standard Cyanide Soluble Cu (g/t), Assayed at Skyline Laboratories

 

September 2023

SEC Technical Report Summary – Santa CruzPage 139

 

 

 

Source: Nordmin, 2023

 

Figure 8-25: Santa Cruz Deposit, OREAS 908 Standard Cyanide Soluble Cu (g/t), Assayed at Skyline Laboratories

 

 

 

Source: Nordmin, 2023

 

Figure 8-26: Santa Cruz Deposit, OREAS 908 Standard Total Cu (g/t), Assayed at American Assay Laboratories

 

September 2023

SEC Technical Report Summary – Santa CruzPage 140

 

 

 

Source: Nordmin, 2023

 

Figure 8-27: Santa Cruz Deposit, OREAS 908 Standard Acid Soluble Cu (g/t), Assayed at American Assay Laboratories

 

 

 

Source: Nordmin, 2023

 

Figure 8-28: Santa Cruz Deposit, OREAS 908 Standard Cyanide Soluble Cu (g/t), Assayed at American Assay Laboratories

 

September 2023

SEC Technical Report Summary – Santa CruzPage 141

 

Blanks

 

The Company submitted 50 coarse blanks during the 2021 drill campaign, at the time of this report, as part of its QA/QC process. The Company used local granite blanks during the 2021 drill campaign as part of its QA/QC process. One blank was used labeled as Blank. The blank has been tested by Skyline Laboratories to ensure that there is no trace of Cu present. No significant carryover of elevated metals is evident in blanks measured at Skyline Laboratories (Figure 8-29). There is a carryover of metals evident in blanks measured at American Assay Laboratories related to dust control issues at this lab (Figure 8-30). The samples from these batches were re-analyzed by the lab, as set out in the QA/QC protocol.

 

 

 

Source: Nordmin, 2023

 

Figure 8-29: Blanks Submitted by IE to Skyline Laboratories for QA/QC Process

 

September 2023

SEC Technical Report Summary – Santa CruzPage 142

 

 

 

Source: Nordmin, 2023

 

Figure 8-30: Blanks Submitted by IE to American Assay Laboratories for QA/QC Process

 

Duplicates

 

The Company submitted 64 field duplicates during the 2021 drill campaign, at the time of this report, as a part of its QA/QC process. Original versus duplicate sample results for total Cu (%) are present in Figure 8-31 and Figure 8-32. The results of the field duplicates are in good agreement for total Cu (%), acid soluble Cu (%) and cyanide soluble Cu (%). Skyline Laboratories submitted 175 lab duplicates (119 total Cu, 125 Acid Soluble, 125 Cyanide Soluble and 119 Mo) during the 2021 drill campaign as a part of their QA/QC process. The results of the laboratory duplicates versus the original sample measurements for total Cu (%) are presented in Figure 8-33. The results of the laboratory duplicates are in good agreement for total Cu (%), acid soluble Cu (%) and cyanide soluble Cu (%). American Assay Laboratories submitted 21 Lab duplicates (all measured for total Cu, acid soluble Cu, cyanide soluble Cu and molybdenum) during the 2021 drill campaign as a part of their QA/QC process. The results of the laboratory duplicates are in good agreement for total Cu (%), acid soluble Cu (%) and cyanide soluble Cu (%) and molybdenum (ppm). The results of the duplicates versus the original sample measurements for total Cu (%) can be viewed in Figure 8-34.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 143

 

 

 

Source: Nordmin, 2023

 

Figure 8-31: Original Versus Field Duplicate Sample Results as Total Cu (%) from Samples Submitted to Skyline Laboratories

 

September 2023

SEC Technical Report Summary – Santa CruzPage 144

 

 

 

Source: Nordmin, 2023

 

Figure 8-32: Original Versus Field Duplicate Sample Results as Total Cu (%) from Samples Submitted to American Assay Laboratories

 

September 2023

SEC Technical Report Summary – Santa CruzPage 145

 

 

 

Source: Nordmin, 2023

 

Figure 8-33: Duplicates Completed by Skyline Laboratories for QA/QC Process

 

 

 

Source: Nordmin, 2023

 

Figure 8-34: Duplicates Completed by American Assay Laboratories for QA/QC Process

 

September 2023

SEC Technical Report Summary – Santa CruzPage 146

 

8.5Security and Storage

 

The Santa Cruz East Ridge, and Texaco core is stored in wax impregnated core boxes and transported to the core logging shack. After being logged, the core boxes are palletized, weatherized, and stored in IE’s core storage facilities. The core storage is locked behind bay doors or chain link fencing for security purposes. All samples for analyses are transported by courier to the laboratory in Tucson, Arizona, or Burnaby, BC, Canada.

 

8.6QP Opinion

 

Nordmin has been supplied with all raw QA/QC data and has reviewed and completed an independent check of the results for all the Santa Cruz Project sampling programs. Nordmin has completed a lab inspection of Skyline Laboratories, and IE has completed a lab inspection of SGS Laboratories and American Assay Laboratories. It is Nordmin’s opinion that the sample preparation, security, and analytical procedures used by all parties are consistent with standard industry practices and that the data is suitable for the Mineral Resource Estimate.

 

Nordmin recommends that IE acquire higher grade standards, and/or create their own standard, to better reflect the grade profile of the expected mineable material. Currently, the highest grade standard in use is OREAS 908 at 1.26% TCu, which is insufficient for QA/QC assurance of the highest grade material (which is closer to ~2% TCu) that is expected to be mined at the three Deposits Nordmin has also identified further recommendations to IE to ensure the continuation of a robust QA/QC program, and has noted that there are no material concerns with the geological or analytical procedures used, or the quality of the resulting data.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 147

  

9Data Verification

 

9.1Data Verification Procedures

 

Nordmin completed several data verification checks throughout the duration of the Mineral Resource Estimate. The verification process included two site visits to the Santa Cruz Project by Nordmin to review surface geology, drill core geology, geological procedures, QA/QC procedures, chain of custody of drill core, and the collection of independent samples for assay verification. The site visits occurred from March 2nd to 6th, 2022 and November 7th to 10th, 2022. The data verification included:

 

·Survey spot check of drill collars

 

·Spot check comparison of assays from the drillhole database against original assay records (lab certificates)

 

·Spot check of drill core lithologies recorded in the database versus the core located in the core processing and storage facilities

 

·Spot check of drill core lithologies in the database versus the lithological model

 

·Review of the QA/QC performance of the drill programs

 

Nordmin has also completed additional data analysis and validation, as outlined in Section 8.

 

9.2Nordmin Site Visit 2022

 

Nordmin completed a site visit to the Santa Cruz Project from March 2nd to March 6th, 2022. Nordmin was accompanied by IE management team members and project geologists. Additionally, Nordmin also visited the site on November 7th through November 10th, 2022.

 

Activities during the site visits included:

 

·Review of the geological and geographical setting of the Santa Cruz Project

 

·Review and inspection of the site geology, mineralization, and structural controls on mineralization

 

·Review of the drilling, logging, sampling, analytical, and QA/QC procedures

 

·Review of the chain of custody of samples from the field to the assay lab

 

·Review of the drill logs, drill core, storage facilities, and independent assay verification on selected core samples

 

·Confirmation of several drillhole collar locations

 

·Review of the structural measurements recorded within the drill logs and how they are utilized within the 3D structural model

 

·Verification of a portion of the drillhole database

 

IE geologists completed the geological mapping, core logging, and sampling associated with each drill location, therefore, Nordmin relied on IE’s database to review the core logging procedures, collection of samples, and chain of custody associated with the drilling programs. IE provided Nordmin with digital copies of the logging and assay reports, all drilling data, including collars, logs, and assay results, prior to the site visit.

 

No significant issues were identified during the site visit.

 

IE employs a rigorous QA/QC protocol, including the routine insertion of field duplicates, blanks, and certified reference standards. Nordmin was provided with an excerpt from the database for review.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 148

 

Currently, IE’s core logging scope includes measured sections of fractures, faults, shears, and other structures. Downhole televiewer data is collected and compiled with the logging information. This allows for the accurate measurement of structures.

 

The geological data collection procedures and the chain of custody were found to be consistent with industry standards and following IE’s internal procedural documentation. Nordmin was able to verify the quality of geological and sampling information and develop an interpretation of Cu (primary, acid soluble and cyanide soluble) grade distributions appropriate for the MRE.

 

9.2.1Field Collar Validation

 

Nordmin and a senior IE geologist verified several collar locations during the November site visit using a Garmin GPSMAP 64sx handheld GPS unit. The collars taken by Nordmin are very similar, if not exact, to what IE had for collar locations. Table 9-1 and Figure 9-1 demonstrate the comparison between the collected collar locations for select historical and 2021/2022 IE drillholes to the IE collar locations used in the MRE.

 

Photos of drillhole collars for historic holes CG-091 and CG-030 can be seen in Figure 9-2.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 149

 

Table 9-1: Check Coordinates for Drilling Within the Santa Cruz, East Ridge, and Texaco Deposits November 9, 2022

 

  Original Coordinates Check Coordinates
Hole ID Easting Northing Easting Northing
CG-021 417,681.0 3,640,646.1 417,692.2 3,640,646.4
CG-030 417,838.1 3,640,036.4 417,838.5 3,640,036.4
CG-047 419,086.6 3,643,143.5 419,086.5 3,643,144.2
CG-055 417,832.8 3,639,424.9 417,833.4 3,639,420.8
CG-061 417,833.9 3,639,581.1 417,834.5 3,639,579.8
CG-065 417,844.7 3,640,488.8 417,844.1 3,640,490.1
CG-068 417,894.1 3,639,506.3 417,893.1 3,639,504.3
CG-083 417,897.0 3,640,118.5 417,898.2 3,640,118.6
CG-091 417,861.4 3,639,958.8 417,862.3 3,639,957.2
CG-092 417,768.0 3,640,117.3 417,768.7 3,640,117.6
CG-099 417,898.7 3,639,661.0 417,898.5 3,639,660.8
CG-100 417,758.8 3,639,654.9 417,758.3 3,639,654.3
CG-101 417,759.1 3,640,427.4 417,758.4 3,640,427.4
SC-024 417,494.1 3,641,007.9 417,496.6 3,641,006.9
SC-029 419,648.6 3,643,194.8 419,648.0 3,643,196.2
SC-036 417,491.3 3,641,157.6 417,492.9 3,641,149.2
SC-039 417,640.6 3,640,854.2 417,645.0 3,640,860.3
SC-041 419,369.7 3,643,301.1 419,369.7 3,643,302.5
SC-042 419,636.1 3,643,254.0 419,638.0 3,643,246.7
SC-043 419,174.8 3,643,173.9 419,176.4 3,643,173.8
SC-067 419,422.9 3,642,948.3 419,420.1 3,642,947.9
SCC-001 417,838.0 3,639,741.0 417,837.1 3,639,741.1
SCC-002 417,683.0 3,640,043.0 417,696.1 3,640,053.3
SCC-004 417,536.0 3,640,350.0 417,534.6 3,640,348.6
SCC-005 417,837.7 3,640,344.0 417,840.7 3,640,342.8
SCC-006 417,863.6 3,640,199.8 417,864.8 3,640,201.7
SCC-007 418,341.0 3,639,977.0 418,342.3 3,639,974.7
SCC-008 417,937.0 3,639,914.0 417,937.4 3,639,914.4
SCC-012 419,564.0 3,643,172.0 419,562.1 3,643,175.6
SCC-014 419,175.1 3,643,173.6 419,176.4 3,643,173.8
SCC-015 419,378.5 3,643,167.5 419,379.2 3,643,169.5
SCC-017 419,378.0 3,643,172.7 419,378.2 3,643,174.1

 

Source: Nordmin, 2023

 

Note: Drillholes beginning with “SCC” are recent holes drilled by IE. All other hole ID’s represent historical drillholes throughout the property.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 150

 

 

 

Source: Nordmin, 2023

 

Figure 9-1: Map of Check Drillhole Collar Locations from November 2022 Site Visit

 

September 2023

SEC Technical Report Summary – Santa CruzPage 151

 

 

 

Source: Nordmin, 2023

 

Figure 9-2: Collars for Historic Diamond Drillholes CG-091 and CG-030

 

9.2.2Core Logging, Sampling, and Storage Facilities

 

The Company drillholes are logged, photographed, and sampled on site at the core logging facility (Figure 9-3 to Figure 9-5). No historical core is available. Recently drilled core is palletized, winterized, stored at IE’s core storage facilities (Figure 9-3). The core samples, pulps, and coarse rejects are kept at the core logging facility or at IE’s core storage facilities.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 152

 

 

 

Source: Nordmin, 2023

 

Figure 9-3: IE Core Logging Facility Located in Casa Grande, Arizona

 

September 2023

SEC Technical Report Summary – Santa CruzPage 153

 

 

 

Source: Nordmin, 2023

 

Figure 9-4: IE’s Core Storage Facilities - Core is Predominantly Stored Outside, Winterized and on Pallets. Further Core Storage is Available in Buildings 1 and 2

 

September 2023

SEC Technical Report Summary – Santa CruzPage 154

 

 

 

Source: Nordmin, 2023

 

Figure 9-5: Core Photography Station at IE Core Logging Facility

 

MX DepositTM logging software is used for the drill program. The software has been extensively customized, and all core loggers have been very well trained. As a result, the QP found great consistency of logging across all personnel, a rarity in the industry. Geotechnical measurements are also taken in MX Deposit and are equally robust and consistent across personnel.

 

Documented drilling, logging, and sampling SOPs, including a standardized drill inspection checklist are used to standardize and enforce procedures. QA/QC samples, including blanks, duplicates, and standards, are appropriately selected and applied to the assaying.

 

Prior to the November site visit by the QP, anomalous SG values were observed in database exports. This included negative values and values less than or close to the SG of water (1.0). Upon inspection of the SG station (Figure 9-6), it was noted that the vessel used for weight in water was not of adequate size and the water contained large amounts of sediment, likely causing erroneous measurements. The QP discussed how to rectify these issues with the on-site team and will be closely monitoring SG values going forward. All suggested changes have since been implemented. The existing SG database was subsequently corrected and validated to the satisfaction of the QP, all incoming SG measurements have been reviewed and were acceptable.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 155

 

 

 

Source: Nordmin, 2023

 

Figure 9-6 Specific Gravity Measuring Station within Core Logging Facility

 

Historical drill core has not been preserved; several core dumps can be found around the property, but it is not available for review.

 

9.2.3Independent Sampling

 

Nordmin selected intervals from two Santa Cruz Deposit holes. A total of 14 verification samples were collected (Table 9-2) from the Santa Cruz available diamond drillholes. During the November 2022 site visit an additional 50 samples were selected for verification from the Texaco Deposit diamond drillholes (Table 9-3). Diamond drill core previously sampled (halved) was re-sampled by having the labs re-analyze the coarse reject material. Two assay laboratories were used during the 2021 drill campaign; therefore, the decision was made by Nordmin to send the independent samples to both laboratories to check for any lab bias.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 156

 

Table 9-2: Original Assay Values Versus Nordmin Check Sample Assay Values from the March 2022 Site Visit

 

  Original Sample Check Sample
Sample Number From To TCu
(%)
ASCu-
SEQ
CNCu-
SEQ
Mo
(%)
TCu
(%)
ASCu-
SEQ
CNCu-
SEQ
Mo
(%)
SKY5022508 582.35 583.70 0.12 0.041 0.005 0.013 0.12 0.045 0.007 0.011
SKY5022513 587.70 588.70 6.05 4.535 0.014 0.012 6.03 5.544 0.012 0.012
SKY5022517 590.70 591.70 2.02 1.756 0.007 0.008 2.17 2.134 0.007 0.007
SKY5022525 591.70 600.70 1.2 1.069 0.011 0.009 1.23 1.207 0.012 0.006
SKY5022601 600.70 687.23 3.99 3.803 0.039 0.005 4.05 3.947 0.039 0.005
SKY5022604 600.70 690.23 6.89 1.472 3.742 0.011 6.95 1.527 5.31 0.01
SKY5022585 664.23 666.23 1.98 1.818 0.007 0.012 1.99 1.98 0.007 0.011
SKY5022565 666.23 642.10 2.63 2.348 0.012 0.007 2.62 2.621 0.014 0.005
SKY5022730 816.00 817.00 0.61 0.0025 0.068 0.005 0.62 0.005 0.075 0.003
SKY5022754 836.00 837.00 1.99 0.0025 0.204 0.012 2.05 0.0025 0.214 0.011
SKY5022823 939.00 941.00 0.62 0.007 0.064 0.002 0.64 0.009 0.066 0.002
SKY5022824 941.00 943.00 0.55 0.0025 0.031 0.006 0.55 0.005 0.031 0.006
SKY5022823 939.00 941.00 0.62 0.007 0.064 0.002 0.65 0.0025 0.06 0.002
SKY5022824 941.00 943.00 0.55 0.0025 0.031 0.006 0.55 0.0025 0.032 0.002

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 157

 

Table 9-3: Original Assay Values versus Nordmin Check Sample Assay Values from the November 2022 Site Visit

 

  Original Sample Check Sample
Sample Number From To TCu
%
ASCu
%
CNCu
%
Mo
%
TCu
%
ASCu
%
CNCu
%
Mo
%
695481 774.4 775 0.91 0.901 0.005 0.001 1.18 1.169 0.009 0.001
695482 775 776 2.72 2.686 0.016 0.006 2.74 2.684 0.022 0.007
695483 776 777 0.74 0.707 0.032 0.005 0.74 0.702 0.038 0.005
695484 777 778 1.61 1.576 0.026 0.006 1.66 1.618 0.03 0.007
695514 802 803 3.55 0.164 3.189 0.015 3.33 0.228 3.048 0.013
695517 805 806 3.08 0.148 2.876 0.029 3.14 0.167 2.833 0.032
695518 806 807 2.15 0.058 1.89 0.012 2.09 0.084 1.822 0.011
695670 937 938 0.98 0.013 0.191 0.003 0.99 0.02 0.223 0.003
695671 938 939 1.13 0.005 0.092 0.015 1.31 0.014 0.142 0.018
695672 939 940 1.66 0.0025 0.403 0.009 1.71 0.019 0.418 0.01
695673 940 941 1.34 0.005 0.21 0.009 1.36 0.013 0.254 0.009
695687 952 953 0.25 0.0025 0.01 0.017 0.22 <0.005 0.017 0.013
695689 953 954 0.29 0.0025 0.017 0.004 0.31 0.008 0.03 0.004
695690 954 955 0.37 0.0025 0.014 0.003 0.39 0.008 0.025 0.003
695691 955 956 0.18 0.0025 0.009 0.003 0.16 0.005 0.017 0.002
695692 956 957 0.2 0.0025 0.009 0.002 0.2 <0.005 0.016 0.003
694625 793 794 0.95 0.029 0.799 0.02 0.95 0.04 0.844 0.02
694626 794 795 0.65 0.019 0.494 0.033 0.66 0.038 0.515 0.03
694627 795 796 1.1 0.028 0.957 0.067 1.15 0.04 0.916 0.066
694629 796 797 0.58 0.035 0.441 0.007 0.58 0.038 0.452 0.006
694630 797 798 0.99 0.027 0.736 0.045 0.98 0.043 0.824 0.045
694631 798 799 1.55 0.026 1.018 0.035 1.46 0.042 1.171 0.034
694639 805 806 1.05 0.013 0.383 0.022 1.06 0.023 0.41 0.023
694640 806 807 1.37 0.033 0.828 0.016 1.42 0.036 0.831 0.019
694641 807 808 0.97 0.025 0.546 0.036 0.99 0.032 0.571 0.039
694643 808 809 0.87 0.015 0.512 0.028 0.89 0.032 0.524 0.03
694644 809 810 0.8 0.025 0.453 0.01 0.81 0.028 0.454 0.009
694645 810 811 1.06 0.021 0.474 0.011 1.13 0.02 0.475 0.011
694646 811 812 1.28 0.014 0.72 0.032 1.25 0.022 0.73 0.027
694647 812 813 1.21 0.024 0.707 0.026 1.14 0.032 0.706 0.023
694648 813 814 0.85 0.016 0.498 0.031 0.89 0.023 0.582 0.032
694650 814 815 0.72 0.019 0.408 0.051 0.54 0.01 0.03 0.003
694651 815 815.9 1.13 0.022 0.467 0.037 1.15 0.025 0.448 0.036
694712 867 868 0.82 0.006 0.038 0.074 0.82 0.012 0.034 0.061
694713 868 869 0.41 0.0025 0.016 0.006 0.39 0.01 0.016 0.005
694714 869 870 0.72 0.007 0.033 0.014 0.77 0.013 0.036 0.017
694715 870 871 1.31 0.026 0.104 0.126 1.45 0.027 0.107 0.105
694716 871 872 1 0.038 0.178 0.053 1.13 0.043 0.203 0.048
694717 872 873 1.22 0.016 0.38 0.019 1.29 0.018 0.384 0.017
694718 873 874 3.07 0.008 0.44 0.168 3.13 0.021 0.462 0.163
694720 874 875 1.67 0.015 0.386 0.033 1.72 0.026 0.381 0.026
694721 875 876 2.01 0.017 0.514 0.054 1.96 0.02 0.502 0.047
694722 876 877 1.59 0.022 0.702 0.046 1.68 0.026 0.702 0.046
694723 877 878 2.15 0.023 1.015 0.017 2.09 0.034 0.871 0.014
694724 878 879 2.12 0.026 0.855 0.044 2 0.028 0.812 0.042
694949 1070 1071 1.25 0.0025 0.091 0.008 1.26 0.007 0.075 0.007
694950 1071 1072 0.59 0.006 0.041 0.003 0.74 0.029 0.421 0.056
694952 1072 1073 0.25 0.0025 0.022 0.001 0.24 0.006 0.02 0.001
694953 1073 1074 0.25 0.006 0.046 0.004 0.22 0.006 0.023 0.003
694954 1074 1075 0.5 0.005 0.028 0.003 0.44 0.008 0.026 0.002

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 158

 

IE uses unmineralized material (an alkaline granite from the area), where values of ore minerals are below detection limits or quartz gravel as sample blanks. The blank material was analyzed at Skyline Laboratories to ensure that there was no significant amount of Cu present. Coarse blanks are crushed as normal samples within the sample stream so that contamination during sample preparation can be detected. Blanks are used to assess proper instrument cleaning and instrument detection limits and contaminations within the lab.

 

The Nordmin assay results for verification samples from the Santa Cruz Deposit were compared to IE’s database and summarized in the scatter plots for total Cu (%), acid soluble Cu (%), and cyanide soluble Cu (%) (Figure 9-7, Figure 9-8 and Figure 9-9). Assay results for verification samples from the Texaco Deposit are summarized in Figure 9-10 to Figure 9-12. Despite some significant sample variances in a few samples, most assays compared within reasonable tolerances for the deposit type and no material bias was evident. No bias was evident among lab analyses.

 

 

 

Source: Nordmin, 2023

 

Figure 9-7: Nordmin Independent Sampling Total Cu (%) Assays from Skyline Laboratories, Santa Cruz Deposit

 

September 2023

SEC Technical Report Summary – Santa CruzPage 159

 

 

 

Source: Nordmin, 2023

 

Figure 9-8: Nordmin Independent Sampling Acid Soluble Cu (%) Assays from Skyline Laboratories, Santa Cruz Deposit

 

September 2023

SEC Technical Report Summary – Santa CruzPage 160

 

 

 

Source: Nordmin, 2023

 

Figure 9-9: Nordmin Independent Sampling of Cyanide Soluble (%) Assays from Skyline Laboratories, Santa Cruz Deposit

 

 

 

Source: Nordmin, 2023

 

Figure 9-10: Nordmin Independent Sampling of Total Copper (%) Assays from Skyline Laboratories, Texaco Deposit

 

September 2023

SEC Technical Report Summary – Santa CruzPage 161

 

 

 

Source: Nordmin, 2023

 

Figure 9-11: Nordmin Independent Sampling of Acid Soluble Copper (%) Assays from Skyline Laboratories, Texaco Deposit

 

September 2023

SEC Technical Report Summary – Santa CruzPage 162

 

 

 

Source: Nordmin, 2023

 

Figure 9-12: Nordmin Independent Sampling of Cyanide Soluble Copper (%) Assays from Skyline Laboratories, Texaco Deposit

 

9.2.4Audit of Analytical Laboratory

 

On September 17, 2021, the Nordmin QP and representatives from IE audited the sample preparation and analysis facilities of Skyline Laboratories in Tucson, Arizona. Recommendations from the audit were provided to Skyline Laboratories and follow up was completed by IE representatives to ensure that the recommendations were implemented. An additional audit of Skyline Laboratories, Tucson, AZ was conducted on June 29, 2022 by members of IE. Recommendations from the 2021 visit were found to have improved (i.e., dust control, air quality). Overall, the lab was found to be clean and organized for sample preparation and analysis. Recommendations from the audit were shared with the lab, follow up audits by IE representatives will be completed to ensure that recommendations were implemented. Another audit of Skyline is planned for 2023.

 

9.3Twin Hole Analysis

 

In the 2021 MRE, Nordmin completed a twin hole analysis between the historical Hanna-Getty and ASARCO diamond drilling versus the 2021 IE drilling to determine if the historical information could be used in the geologic model and Resource Estimate. The analysis compared the collar locations, downhole surveys, logging (lithology, alteration, and mineralization), sampling and assaying between the two groups to determine if the historical holes had valid information and would not be introducing a bias within the geological model or Resource Estimate. The comparison included a QA/QC analysis of the historical drillholes.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 163

 

A total of five historical holes were reviewed with the following outcomes:

 

·All five historical hole assays aligned with 2021 diamond drilling assays.

 

·2021 diamond drilling assays were of higher resolution due to smaller sample sizes.

 

·Recent drilling validated the ASARCO cyanide soluble assays.

 

Figure 9-13 demonstrates that grade variability and location were insignificant between CG-027 and SCC-001 and demonstrated overall grade continuity between the intercepts. Resolution is higher in SCC-001 downhole due to smaller sample sizes compared to historic drilling. Table 9-4 demonstrates good agreement between historic logging and current logging using the same regional lithology types. This provides confidence in the accuracy of the geologic model and that associations made between mineralization and lithology are valid. Similar patterns are observed within the other three historical drillholes used within the Resource Estimate, which included reliable QA/QC data.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 164

 

 

 

Source: Nordmin, 2023

A) shows the direct comparison of total Cu assays as Cu (%).

B) SCC-001 and CG-027 showing downhole charts of acid soluble Cu assays (%) on the left and total Cu (%) assays on the right.

 

Figure 9-13: Comparison of Assays From SCC-001 Versus CG-027

 

September 2023

SEC Technical Report Summary – Santa CruzPage 165

 

Table 9-4: Downhole Lithology Logging Comparison of CG-027 versus SCC-001

 

Hole ID FROM (m) TO (m) Lithology Hole ID FROM (m) TO (m) Lithology
CG-027 0 24.38 Tert. Sediments SCC-001 0 514.78 Conglomerate
24.38 85.34 Tert. Sediments Conglomerate
85.34 195.07 Tert. Sediments Conglomerate
195.07 347.47 Tert. Sediments Conglomerate
347.47 542.54 Tert. Sediments 514.78 544.03 Conglomerate
542.54 563.88 Tert. Sediments 544.03 551.28 Conglomerate
563.88 566.92 No data 551.28 556.26 Fault
566.92 576.07 Tert. Sediments 556.26 578.76 Breccia
576.07 579.12 Tert. Sediments 578.76 600.93 Quartz Monzonite
579.12 585.52 No data 600.93 603.35 Quartz Monzonite
585.52 603.5 Mixed      
603.5 606.55 Tert. Sediments 603.35 615.03 Quartz Monzonite
606.55 612.64 Mixed      
612.64 615.69 Tert. Sediments      
615.69 621.79 Mixed 615.03 660.24 Granodiorite
621.79 640.08 Laramide Int.      
640.08 643.12 Tert. Sediments      
643.12 658.36 Laramide Int.      
658.36 694.94 Granite 660.24 705.39 Granite
694.94 697.99 Granite 705.39 707.83 Granodiorite
697.99 710.18 Granite      
710.18 713.23 Laramide Int. 707.83 724.47 Granite
713.23 719.32 Granite 724.47 732.03 Granodiorite
719.32 731.52 Laramide Int.      
731.52 734.56 Laramide Int. 732.03 751.71 Granite
734.56 807.72 Granite 751.71 769.62 Granite
      769.62 802.66 Granite
      802.66 807.511 Gabbro
807.72 816.86 Laramide Int. 807.511 818.39 Granite
816.86 923.54 Granite 818.39 820.23 Fault
      820.23 845.75 Granite
      845.75 849.17 Fault
      849.17 891.7 Granite
      891.7 897.94 Granite
      897.94 910 Granite
      910 921.22 Fault
923.54 926.59 Laramide Int. 921.22 928.75 Granodiorite
926.59 929.64 Granite 928.75 946.09 Fault

 

Source: Nordmin, 2023 

TgcU = Tertiary unconsolidated sediments, TgcL = Tertiary Lithified Sediments, Mixed = breccias 

LI = Laramide Intrusives, pC = Precambrian Granites/Diabase Dykes and Aplites

 

Several holes have been twinned over the course of the exploration work conducted on the Santa Cruz Deposit. Nordmin was able to match most of the intervals for each of the pairs and plotted the grades for Cu, Cu-SEQ, and Mo. In Nordmin’s opinion, for most of the pairs, the assay results compared reasonably well; the high-grade (HG) and low-grade (LG) zones were similar, and the grades tended to cluster in the same ranges. In Nordmin’s opinion, the twinning has provided a reasonably consistent verification of the earlier Hanna-Getty and ASARCO drill results, particularly considering the differences in the assay, survey methods and QA/QC protocols.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 166

 

9.4Database Validation

 

The Nordmin QP completed a spot check verification of the following drillholes:

 

Santa Cruz Deposit – Five drillholes which included 89 lithology entries (19%), 388 geotechnical measurements (55%), and 328 assay entries (70%)

Texaco Deposit – Two drillholes were checked which included 78 lithology entries (47%), 441 geotechnical measurements (44%), and 1059 assays (56%)

East Ridge Deposit – One drillhole was checked which included 27 lithology entries (12.7%), 176 geotechnical measurements (11%), and 306 assays (23%)

 

The historical geology was validated for lithological units from handwritten logs transcribed into excel tables and historical logs compiled into a database. Lithological units being implemented in current logging were based on the historical description. Detail and interpretation of the lithologic units have developed along with the 2021-2022 drilling and are more robust than earlier descriptions. The geological contacts and lithology aligned with the core contacts and lithology and are acceptable for use. Two assay depth errors from 2021 drilling were brought to the attention of the on-site geologists. These errors were rectified, and the database was updated. The entire database was run through the QGIS validity check to look for errors. No significant errors were found in the database.

 

Within the database, a portion of historic drillholes is missing the downhole survey and assay data. Holes drilled by Casa Grande Copper Co. have 62.1% of the survey data and 96.5% of the assay data. Holes drilled by ASARCO have 65.9% of the downhole survey data and only 34.4% of the assay data available. Missing data has been well documented by IE, and vertical twins of historic drillholes have been and continue to be drilled to confirm lithology, assay, and geotechnical data (Section 9.1.4).

 

9.5Review of Company’s QA/QC

 

Nordmin conducted an independent review of IE’s QA/QC procedures as part of the validation process and believes that the Company has a robust QA/QC process in place, as previously described in Section 8.

 

9.6QP Opinion

 

Upon completion of the data verification process, it is the Nordmin QP’s opinion that the geological data collection and QA/QC procedures used by IE are consistent with standard industry practices and that the geological database is of suitable quality to support the Mineral Resource Estimate.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 167

 

10Mineral Processing and Metallurgical Testing

 

Metallurgy and processing test work were directed by Met Engineering LLC and conducted at McClelland Labs in Sparks, Nevada. McClelland Labs is recognized by the International Accreditation Service (IAS) for its technical competence, is independent of the Issuer, and quality of service and has proven that it meets recognized standards. The studies are ongoing. Study focus has been on:

 

Confirming total copper recovery of the leach-float flow sheet proposed by historical operator, Casa Grande Copper, circa 1980, on Exotic, Oxide, and Chalcocite mineral domains. IA level testing studies have finished for this flow sheet.

Investigating heap leaching of Exotic, Oxide, and Chalcocite mineral domains. The test program for heap leaching is in the latter stages of the secondary copper sulfide column cell leach and will be completed in the fourth quarter of 2023. A progress report is presented below in section 10.2.8.

 

The preferred flow sheet reported in the IA is the Leach-Float Process, developed by Casa Grande Copper Corp. in 1980. A simplified flow sheet is illustrated in Figure 10-1.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 168

  

 

Source: Met Engineering, 2023

 

Figure 10-1: Simplified Process Flow Sheet

 

September 2023

SEC Technical Report Summary – Santa CruzPage 169

 

10.1CGCC Studies (1976-1982)

 

The Casa Grande Copper Corp. (CGCC) studies were conducted by the Hanna Mining Company’s internal Research Centre in Minnesota, USA. Hanna Mining Company was the first mining company to try to advance the Santa Cruz deposit. They evaluated the three distinct processing routes listed below. Detailed reports were prepared for each process. There is a fourth process, heap leach, that was investigated with conceptual studies, but no detailed study was pursued for this process. Approximately 90 mineral processing and metallurgical test programs were conducted. The number of tests conducted in each program ranged from 6 to 40. Three different processes were considered by CGCC:

 

All Agitated Tank Leach Approach (91% total Cu recovery to cathodes)

All-Float Approach (92% total Cu recovery to cathodes or a mixture of cathodes and saleable Cu concentrates)

Leach – Float Process (94% Cu recovery to cathodes or to a mixture of cathodes and saleable Cu concentrates)

 

10.1.1Sample Selection

 

Historical testing in 1979-1980 was performed on drill core coarse rejects. Grinding tests, open cycle and closed cycle bench level flotation tests, and bottle roll leach tests were performed.

 

Composite samples of seven “ore” types (listed below) were prepared from drill core intervals based on the estimate of mineralized material in the Santa Cruz Deposit developed by Hanna, dated November 15, 1978. The purpose of these ore type composites was to have material readily available for blending to represent different mine plans for various flow sheet development:

 

High-grade Supergene

Supergene Dilution

Low-grade Supergene

Mixed Chalcocite/Chalcopyrite

Primary Chalcopyrite

Exotic Ore

Exotic Dilution Ore

 

Mineral processing and metallurgical tests were conducted on blends of each ore type representing the ore expected in each mine plan related to the three flow sheets mentioned in Section 10.1.1

 

Table 10-1 through Table 10-20 are the drillholes, intervals, and sample quantities blended for each ore type composite along with the analyses and copper mineralization. Note that some of the tables lack section data as these were not present in the historical data source. The QP is of the opinion that industry accepted practices were applied in regard to preparing sample blends for each ore type composite, and that the composite samples represent the ore type indicated.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 170

 

Table 10-1: Upper Ore Body Sample Composite 76-122 for Leach – Float Testing

 

Drillhole From (m) To (m) % Wt. % CuTot % ASCu % S_Cu % Mo
CG-11 494 533 10.64 1.04 0.95 0.09 0.0075
CG-11 533 579 12.27 1.70 0.26 1.44 0.0181
CG-11 579 616 9.82 2.26 2.05 0.21 0.0099
CG-12 596 623 9.78 1.81 1.75 0.06 0.0045
CG-13 597 628 6.19 2.19 1.90 0.20 0.013
CG-13 655 747 18.46 1.08 0.18 0.90 0.015
CG-16 NR NR 13.09 0.72 0.52 0.20 0.006
CG-16 NR NR 19.76 1.86 0.19 1.67 0.010
Calc. Assay     100.00 1.52 0.762 0.747 0.0108
Comp. Assay     1.565 1.565 0.777 0.788  

 

Source: Met Engineering, 2023

 

Table 10-2: Analyses of High-grade Supergene Composite No.79-88 (A&B)

 

  Analyses
Composite No. Total Cu (%) ASCu (%) Chloride (%)
79-88A (-3/8") 1.50 1.14 0.191
79-88B (-10 Mesh) 1.47 1.14 0.185

 

 Source: Met Engineering, 2023

 

Table 10-3: Mineralogy of High-grade Supergene Composite No.79-88

 

  Mineralogy
Mineral % Cu % Cu Dist.
Atacamite 0.62 41.6
Chrysocolla, Cuprite 0.45 30.2
Copper Clay 0.07 4.7
Copper Sulfides 0.35 23.5
Total 1.49 100.0

 

Source: Met Engineering, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 171

 

Table 10-4: Drillholes, Intervals and Sample Weights of High-grade Supergene Composite No. @79-88 (A&B)

 

  Feet Meters Sample Weight (g)
Section Drillhole ID From To ft From To m -3/8 inch -10 Mesh
14500 11 1,620 2,010 390 494 613 119 15,080 15,077
14500 12 1,965 2,075 110 599 632 34 6,260 6,260
14250 81 1,934 2,068 134 589 630 41 9,782 9,782
14250 96 1,537 1,801 264 468 549 80 11,129 11,129
14250 96 1,640 1,801 161 500 549 49
14250 106 1,937 2,127 190 590 648 58 7,810 7,810
14000 13 1,960 2,450 490 597 747 149 17,760 17,760
14000 29 1,520 1,570 50 463 479 15 795 795
14000 40 2,006 2,049 43 611 625 13 366 366
13750 98 1,633 1,805 172 498 550 52 8,186 8,186
13750 84 1,827 2,118 291 557 646 89 15,128 15,128
13750 77 2,041 2,150 109 622 655 33 9,392 9,392
13750 77 2,199 2,279 80 670 695 24
13500 20 1,680 1,860 180 512 567 55 10,433 10,437
13500 18 2,000 2,190 190 610 667 58 5,371 5,378
13500 60 1,592 1,638 46 485 499 14 1,894 1,894
13250 78 1,802 1,927 125 549 587 38 8,913 8,913
12750 93 1,712 1,820 108 522 555 33 5095 5,095
12750 90 1,682 1,877 195 513 572 59 14,657 14,657
12750 82 1,472 1,566 94 449 477 29 19,725 19,725
12750 82 1,807 1,947 140 551 593 43
12400 23 1,840 2,010 170 561 613 52 10,948 10,936
12400 37 1,710 2,270 560 521 692 171 25,922 25,933
12400 38 2,050 2,646 596 625 806 182 24,132 24,063
12400 16 2,410 2,550 140 735 777 43 12,898 12,799
12400 16 2,770 3,170 400 844 966 122
12250 88 1,867 2,178 311 569 664 95 13,350 13,350
12250 94 2,225 2,342 117 678 714 36 10,447 10,447
12250 94 2,565 2,758 193 782 841 59
12250 87 1,899 1,977 78 579 603 24 874 874
12000 27A 1,953 2,667 714 595 813 218 47,272 47,269
12000 57 2,219 2,336 117 676 712 36 14,833 14,833
12000 57 2,582 2,627 45 787 801 14    
12000 57 2,753 2,870 117 839 875 36
12000 24 1,990 2,060 70 607 628 21 2,548 2,548
12000 62 1,972 2,021 49 601 616 15 3,402 3,402
11750 89 2,051 2,104 53 625 641 16 3,494 3,494
11500 31 2,420 2,440 20 738 744 6 1,296 1,296
11500 61 2,484 2,609 125 757 795 38 10,574 10,574
  32 Drillholes     7,437     2,267 349,766 349,602

 

Source: Met Engineering, 2023

 

Table 10-5: Analyses of Supergene Dilution Composite No.79-99

 

  Analyses
Composite No. Total Cu (%) ASCu (%) Chloride (%) Sulfur (%) Total Iron (%)
79-99 0.31 0.278 0.037 0.22 2.71

 

Source: Met Engineering, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 172

 

Table 10-6: Mineralogy of Supergene Dilution Composite No.79-99

 

  Mineralogy
Mineral % Cu % Cu Dist.
Atacamite 0.079 25.5
Chrysocolla, Cuprite 0.136 44.1
Copper Clay 0.063 20.4
Copper Sulfides 0.031 10.0
Total 0.309 100.0

 

Source: Met Engineering, 2023

 

Table 10-7: Drillholes, Intervals and Sample Weights of Supergene Dilution Composite No.79-99

 

Supergene Dilution Composite No. 79-99
  Feet Meters Sample Weight (g)
Section Drillhole ID From To ft From To m -3/8 inch -10 Mesh
14500N 11 1,550 1,620 70 472 494 21 10,150 10,155
14250N 76 1,876 1,893 17 572 577 5 2,465 2,470
14250N 106 1,916 1,937 21 584 590 6 3,045 3,050
14250N 81 1,919 1,934 15 585 589 5 2,175 2,177
14000N 13 1,910 1,953 43 582 595 13 6,235 6,250
13750N 98 1,605 1,633 28 489 498 9 4,060 4,080
13750N 84 1,798 1,827 29 548 557 9 4,205 4,205
13750N 77 2,011 2,041 30 613 622 9 4,350 4,355
13500N 20 1,670 1,700 30 509 518 9 4,350 4,355
13500N 18 1,970 2,000 30 600 610 9 4,350 4,365
13500N 18A 1,970 2,000 30 600 610 9 4,350 4,359
13250N 78 1,772 1,802 30 540 549 9 4,350 4,352
12750N 93 1,697 1,712 15 517 522 5 2,175 2,078
12750N 82 1,446 1,472 26 441 449 8 3,770 3,777
12750N 82 1,781 1,807 26 543 551 8 3,770 3,770
12400N 23 1,800 1,840 40 549 561 12 5,800 5,800
12400N 37 1,590 1,710 120 485 521 37 17,400 17,596
12400N 38 2,004 2,050 46 611 625 14 6,670 6,668
12400N 16 2,380 2,410 30 725 735 9 4,350 4,352
12400N 16 2,700 2,770 70 823 844 21 10,150 4,601
12250N 88 1,747 1,867 120 532 569 37 17,400 17,397
12250N 94 2,198 2,225 27 670 678 8 3,915 3,910
12250N 94 2,504 2,565 61 763 782 19 8,845 8,830
12000N 57 2,168 2,219 51 661 676 16 7,395 7,385
11500N 61 2,464 2,484 20 751 757 6 2,900 2,915
  22 drillholes     1,025     312 148,625  143,252

 

Source: Met Engineering, 2023

 

Table 10-8: Analyses of Low-grade Supergene Composite No.79-128

 

  Analyses
Composite No. Total Cu (%) ASCu (%) Mo (%) Chloride (%) Sulfur (%) Total Iron (%)
79-128 0.486 0.140 0.011 0.020 0.24 1.45

 

Source: Met Engineering, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 173

 

Table 10-9: Mineralogy of Low-grade Supergene Composite No.79-128

 

  Mineralogy
Mineral % Cu % Cu Dist.
Atacamite 0.018 3.7
Chrysocolla, Cuprite 0.091 18.7
Copper Clay 0.031 6.4
Copper Sulfides 0.346 71.2
Total 0.486 100.0

 

Source: Met Engineering, 2023

 

Table 10-10: Drillholes, Intervals and Sample Weights of Low-grade Supergene Composite No.79-128

 

  Feet Meters Sample Weight (g)
Drillhole ID From To ft From To m -3/8 inch
12 2,075 2,185 110 632 666 34 12,720
78 1,927 1,954 27 587 596 8 3,140
80 1,925 2,173 248 587 662 76 28,710
98 1,797 2,041 244 548 622 74 28,190
13 2,500 2,670 170 762 814 52 18,520
96 1,801 2,061 260 549 628 79 29,770
81 2,068 2,411 343 630 735 105 39,560
11 2,010 2,260 250 613 689 76 28,920
23 2,010 2,310 300 613 704 91 34,690
16 2,550 2,770 220 777 844 67 11,370
90 1,877 1,917 40 572 584 12 12,670
90 1,956 2,025 69 596 617 21
82 1,947 2,084 137 593 635 42 15,910
109 2,505 2,598 93 763 792 28 10,810
91 2,691 2,781 90 820 848 27 21,975
91 2,896 2,995 99 883 913 30
61 2,609 2,679 70 795 817 21 6,605
100 2,338 2,463 125 713 751 38 14,540
57 2,486 2,582 96 758 787 29 37,625
57 2,666 2,733 67 813 833 20
57 2,907 3,064 157 886 934 48
88 2,178 2,236 58 664 681 18 6,740
94 2,342 2,565 223 714 782 68 25,225
19 drillholes     3496     1066 387,690

 

Source: Met Engineering, 2023

 

Table 10-11: Analyses of Mixed Chalcocite / Chalcopyrite Composite No.79-109

 

  Analyses
Composite No. Total Cu (%) ASCu (%) Mo (%) Chloride (%) Sulfur (%) Total Iron (%)
79-109 0.824 0.073 0.024 0.024 0.94 1.73

 

Source: Met Engineering, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 174

 

Table 10-12: Mineralogy of Mixed Chalcocite / Chalcopyrite Composite No.79-109

 

  Mineralogy
Mineral % Cu % Cu Dist.
Atacamite 0.032 3.9
Chrysocolla, Cuprite 0.009 1.1
Copper Clay 0.032 3.9
Copper Sulfides 0.751 91.1
Total 0.824 100.0

 

Source: Met Engineering, 2023

  

Table 10-13: Drillholes, Intervals and Sample Weights of Mixed Chalcocite / Chalcopyrite Composite No.79-109

 

  Feet Meters Sample
Weight (g)
Drillhole ID From To ft From To m -3/8 inch
81 2,411 2,663 252 735 812 77 22,750
78 1,954 2,225 271 596 678 83 24,495
80 2,284 2,355 71 696 718 22 6,435
20 2,020 2,080 60 616 634 18 5,440
84 2,118 2,681 563 646 817 172 50,950
37 2,270 2,699 429 692 823 131 17,180
38 2,646 3,041 395 806 927 120 13,840
90 2,025 2,287 262 617 697 80 23,725
82 2,084 2,277 193 635 694 59 17,440
109 2,598 3,003 405 792 915 123 36.585
91 2,995 3,043 48 913 927 15 4,350
61 2,679 2,808 129 817 856 39 11,650
100 2,463 2,702 239 751 824 73 21,585
99 3,079 3,143 64 938 958 20 5,805
27A 2,667 2,715 48 813 827 15 4,325
57 3,123 3,180 57 952 969 17 5,170
88 2,236 2,306 70 681 703 21 6,360
94 2,832 3,030 198 863 923 60 17,915
18 Drillholes     3,754     1,144 296,000

 

Source: Met Engineering, 2023

 

Table 10-14: Analyses of Chalcopyrite Composite No.79-118

 

  Analyses
Composite No. Total Cu (%) ASCu (%) Mo (%) Chloride (%) Sulfur (%) Total Iron (%)
79-118 0.740 0.020 0.01 0.015 1.23 2.34

 

Source: Met Engineering, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 175

 

Table 10-15: Mineralogy of Chalcopyrite Composite No.79-118

 

  Mineralogy
Mineral % Cu % Cu Dist.
Atacamite 0.0 0.0
Chrysocolla, Cuprite 0.012 1.6
Copper Clay 0.008 1.1
Copper Sulfides 0.720 97.3
Total 0.74 100.0

 

Source: Met Engineering, 2023

  

Table 10-16: Drillholes, Intervals and Sample Weights of Chalcopyrite Composite No.79-118

 

  Feet Meters Sample
Weight (g)
Drillhole ID From To ft From To m -3/8 inch
20 2,080 2,570 490 634 783 149 27,600
98 2,118 2,390 272 646 728 83 16,320
78 2,225 2,987 762 678 910 232 45,720
80 2,355 3,147 792 718 959 241 46,980
38 3,041 3,193 152 927 973 46 6,080
90 2,287 3,119 832 697 951 254 49,920
82 2,227 2,908 681 679 886 208 37,860
91 3,043 3,215 172 927 980 52 10,320
57 3,180 3,419 239 969 1,042 73 14,340
88 2,306 2,607 301 703 795 92 18,060
87 2,275 2,636 361 693 803 110 21,660
94 3,030 3,389 359 923 1,033 109 21,540
61 2,808 3,577 769 856 1,090 234 46,140
100 2,702 3,250 548 824 991 167 32,340
99 3,143 3,437 294 958 1,048 90 17,640
50 2,915 3,459 544 888 1,054 166 32,280
16 Drillholes     7,568     2,307 444,800

 

Source: Met Engineering, 2023

 

Table 10-17: Analyses of Exotic Ore and Exotic Dilution Ore Composites Nos. 79-101 and 79-102

 

  Analyses
Composite Total Cu (%) ASCu (%) Chloride (%)
Exotic Ore Composite No. 79-101 2.210 1.980 0.365
Exotic Dilution Ore Composite No. 79-102 0.379 0.227 0.015

 

Source: Met Engineering, 2023

 

Table 10-18: Mineralogy of Exotic Ore and Exotic Dilution Ore Composites Nos. 79-101 and 79-102

 

  Mineralogy
Exotic Ore No. 79-101 Exotic Dilution Ore No.79-102
Mineral % Cu % Cu Dist. % Cu % Cu Dist.
Atacamite 1.25 54.3 0.0 0.0
Chrysocolla, Cuprite 0.73 31.4 0.23 59.9
Copper Clay 0.23 10.0 0.11 28.8
Copper Sulfides 0.10 4.3 0.04 11.3
Total 2.31 100.0 0.38 100.0

 

Source: Met Engineering, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 176

 

Table 10-19:Drillholes, Intervals and Sample Weights of Exotic Ore Composite No. 79-101

 

    Feet Meters Sample Weight (g)
Section Drillhole ID From To ft From To m -3/8 inch
13500N 52 2,101 2,230 129 640 680 39 11,665
13500N 18 1,830 1,930 100 558 588 30 9,060
13750N 77 1,677 1,740 63 511 530 19 5,700
13750N 85 1,971 2,095 124 601 639 38 11,225
14000N 22 1,970 2,270 300 600 692 91 27,155
  5 Drillholes     716     218 64,805
                       

 

Source: Met Engineering, 2023

 

Table 10-20: Drillholes, Intervals and Sample Weights of Exotic Dilution Ore Composite No. 79-102

 

  Feet Meters Sample Weight (grams)
Section Drillhole ID From To ft From To m -3/8 inch
13500N 52 2,088 2,101 13 636 640 4 2,610
13500N 18A 1,820 1,840 20 555 561 6 4,010
13750N 77 1,658 1,677 19 505 511 6 3,810
13750N 85 1,952 1,971 19 595 601 6 3,805
  4 Drillholes     71     22 14,235

 

Source: Met Engineering, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 177

 

Figure 10-2 is a surface map of the locations of 43 drillholes used in the ore type composites and their relative positions in the projected outline of the Mineral Resource of the Santa Cruz Deposit. The distribution of drillholes indicates that the holes selected represent the current defined resource.

 

Map

Description automatically generated

 

Source: Met Engineering, 2023

 

Figure 10-2: Surface Map of the Drillholes Used in the Ore Type Composites

 

September 2023

SEC Technical Report Summary – Santa CruzPage 178

 

10.1.2Grinding Studies

 

Grinding studies were conducted using laboratory size ball mills on 1,000 g samples. The initial sample types from the early drilling programs were tested, as were the major composite samples of the Santa Cruz Deposit. Grinding for leaching was investigated separately from grinding for flotation purposes.

 

Ground samples for flotation were subjected to rougher flotation and standard Cu recovery (non-acid soluble Cu) and concentrate grade relationships were developed to determine the best primary grind P80. Ground samples for leaching were subjected to bottle roll leaching with sulfuric acid or sulfuric acid and ferric sulfate as lixiviant.

 

The results of the grinding studies (leaching and flotation) on the major composite sample representing the entire deposit were used to test later blended composites of the listed ore types, to develop a flow sheet. The optimum grind size for whole ore agitated tank leaching, with either type lixiviant mixture, was determined to P80 800 µ. The optimum primary grinding size for rougher copper sulfide flotation was P80 74 µ. The estimated specific energy of the ball mill for leaching was 1.2 kWh/t. The estimated specific energy of the ball mill for flotation was 9.8 kWh/t. The estimated energy of the SAG mill was 2.2 kWh/t.

 

These grinding studies were applied to blended composites for flow sheet development of ore types listed under Sample Selection. There was no variability testing conducted, therefore the test results would be acceptable for an IA-level study program under regulation S-K 1300. A prefeasibility level study would require 30 to 40 variability tests of selected drillholes and drill intervals and a feasibility level study would require 100 intervals or more.

 

Bond Mill Work Index Analysis

 

Six laboratory ball mill grinding studies were conducted on the upper ore body samples labeled Composite Sample 78-17 and 78-77 utilizing a calibrated 7.75-inch diameter by 7-inch Galigher batch ball mill. These samples had head grades of 1.54% and 1.61% total copper and represented approximately 118 and 90 Mt of mineralized material in the 1979 study, respectively.

 

Procedure

 

This mill had been calibrated so that specific grinding energies could be reported for batch grinds. The level of accuracy was estimated to be +/-20%. Grinds were performed wet at 60% solids by weight using tap water and 35% ball charge.

 

Ore was ground for a fixed time and the energy input could be calculated for this grind time. The ground solids were wet screened at 150 µ, 74 µ and 37 µ. The screen fractions were then filtered, dried and weighed. The screen dried solids were repulped and ground for additional time. The energy input, screening and drying procedure was repeated until the desired grind was obtained.

 

A number of final grind sizes (80% passing a grind size) were evaluated. Table 10-21 shows the results. Specific grinding energy varied with the fineness of the grind from 3.96 to 10.01 KWh/t of material. Theoretically, the Bond Ball Mill Index should be approximately the same in each test. Bond Ball Mine Index varied from 9.79 to 11.38 KWh/t of material and increased as the fineness of the grind increased. Bond Ball Mill Index was back calculated using Bond’s Third Theory or Law of Comminution:

 

E = 10 Wi (1/P801/2 – 1/F801/2)

 

Where:

E = Specific Energy Consumption, kWh/t ground. 

F80 = 80% passing size in the Fresh Ore Feed Stream, microns. 

P80 = 80% passing size in the Final Ground Product, microns. 

Wi = Bond's Work Index, indicative of the hardness of the ore, kWh/t

 

September 2023

SEC Technical Report Summary – Santa CruzPage 179

 

Table 10-21: Evaluated Grinds

 

Sample
Description
Sample ID Particle Size, µ
(80% passing)
Specific
Energy,
KWh/t
Bond Work Index,
kWh/t
Unground material 78-17 1,131    
Ground material 78-17 223 3.96 10.64
Ground material 78-17 93 8.03 10.84
Ground material 78-17 72 10.01 11.38
Unground material 78-17 1,101    
Ground material 78-17 201 3.96 9.79
Ground material 78-17 89 8.03 10.59
Ground material 78-17 68 10.01 11.03
Average Bond Work Index 10.71

 

Source: Met Engineering, 2023

 

10.1.3Flotation Studies

 

The flotation equipment described is still in use today. All tests were documented as they would be today, with such information as: P80’s, float times, reagent names, and consumptions, notes on froth appearance, etc. The regrind test program for the cleaner circuit flotation was vague. However, copper sulfide concentrate grade and overall copper recovery (non-acid soluble copper) results were typical based on the rougher flotation recoveries reported in the mid-90% range, so, the regrind was performed correctly. Copper recovery after cleaning was in the low 90% range and the concentrate grade varied from 25% to 50% copper depending on copper sulfide ore mineralogy.

 

Flotation of atacamite together with copper sulfides was evaluated and found to be successful in producing a 12% concentrate at recoveries in the mid 90% range for atacamite and copper sulfide minerals. The chloride in this concentrate was leached out almost completely with a patented NaOH leach leaving behind copper sulfides and copper hydroxide. The Copper hydroxide was leached out with weak sulfuric acid solution producing a pregnant leach solution (PLS) for solvent extraction-electrowinning (SX-EW), and remaining copper sulfides were pH adjusted, reground, and upgraded in a cleaner flotation circuit. Copper recovery of the copper oxides (excluding atacamite) was poor. Thus, total Cu recovery was in the mid 80% range. An all-float process was developed later where the copper oxides were economically recovered, and total copper recovery was raised to the low 90% range in the flow sheet. Concentrate products were not suitable for sale to a copper smelter and needed to be processed on site by a roast-leach-electrowinning process.

 

Flotation test programs were applied to all the composite blends samples for flow sheet development as described in Sample Selection. The test programs would be acceptable for an IA-level program today but not for a PFS or FS level study due to the lack of any significant variability flotation testing of the Santa Cruz Deposit.

 

Sulfide Flotation Test Work Results

 

Open Cycle Flotation Test Results

 

Table 10-22 shows the open cycle leach – float results for sample composite 76-122, which is material from the upper orebody. Two tests were run utilizing a grind to approximately 80% passing 74 micron, rougher flotation with Z-200 collector at 50 grams per tonne (g/t) (isopropyl ethyl thiocarbonate collector). Total leach-float recovery was 91.06% for test 10 and 94.17% for test 11. These recoveries were calculated without credit for the copper in the middling material from the cleaner circuit which is usually treated in a cleaner scavenger flotation circuit in a commercial plant achieving 50-90% copper recovery. Assuming a worst case of 50% recovery of the cleaner tailing copper brings the total recovery to 92.79% and 95.07%, respectively. Total copper recovery to the pregnant leach solution (PLS) was 44.17% for test 10 and 46.67% for test 11. Total copper recovery to cleaner concentrate was 46.89% for test 10 and 47.50% for test 11. The cleaner concentrate grade was 28.34% copper and 25.15% copper, respectively. Cleaner concentrate grade and total copper recovery could have been significantly improved with regrinding the rougher concentrate to 80% passing 50 µ.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 180

 

Table 10-22: Open Cycle Leach – Float Test Results Using 50 Grams per Tonne Z-200 Collector

 

  Assay Distribution
Test No. Description Mass,
Grams
%
Weight
% Total
Copper
% Acid
Soluble
Copper
%
Sulfide
Copper
%
Molyb-
denum
% Sulfur % Total
Copper
% Acid
Soluble
Copper
%
Sulfide
Copper
%
Molyb-
denum
% Sulfur
10 Composite 76-122                        
Head Assay     1.565 0.777 0.788 0.0133 0.43          
Calculated Head Assay 1000 100 1.508 0.777 0.731 0.0158            
                         
Agitated Leach                        
PLS 2000   0.333         44.17 84.72 1.05    
Residue 975.1 97.51           55.83 15.28 98.95    
                         
Sulfide Flotation                        
Cleaner Concentrate 24.95 2.495 28.34 1.22 27.12 0.127 15.06 46.89 3.91 92.56 20.62 87.4
Cleaner Circuit Middlings 122.95 12.295 0.425 0.308 0.117 0.032   3.46 4.88 1.97 25.58  
Tailings 827.2 82.72 0.100 0.061 0.039 0.01   5.48 6.49 4.42 53.79  
11 Composite 76-122   100                    
Head Assay     1.565 0.777 0.788 0.0133            
Calculated Head Assay 1000   1.504 0.777 0.727 0.0158            
                         
Agitated Leach                        
PLS 2000   0.351         46.67 87.82 2.68    
Residue 973.4 97.34           53.33 12.18 97.32    
                         
Sulfide Flotation                        
Cleaner Concentrate 28.4 2.84 25.15 1.13 24.02 0.123 13.52 47.5 4.13 93.83 22.11 89.3
Cleaner Circuit Middlings 111.4 11.4 0.255 0.181 0.074     1.89 2.6 1.13    
Tailings 833.6 83.36 0.0712 0.0507 0.0205     3.94 5.45 2.36    

 

Source: Met Engineering, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 181

 

Locked-Cycle Flotation Test Results

 

Three lock-cycle sulfide flotation tests were run on the upper ore zone material utilizing the composite sample identified as 78-77. These tests were numbered 181-183. The circuit configuration consisted of grinding the ore to approximately 80% passing 74 microns, conditioning, rougher flotation with collectors Z-200 followed by two stages of cleaner flotation. Underflow from the first cleaner stage was recycled to rougher flotation and underflow from the second stage of cleaning was recycled to the first stage of flotation. The number of lock-cycles was six. Results were reported for the last three cycles of each locked-float float test. Results of the tests are shown in Table 10-23.

 

Table 10-23: Results of Locked-Cycle Flotation Using 50 grams per tonne Z-200 Collector

 

  Assay Distribution
Test No. Description %
Weight
% Total
Copper
% Acid
Soluble
Copper
%
Sulfide
Copper
% Total
Copper
% Acid
Soluble
Copper
%
Sulfide
Copper
181 Composite 78-77              
Calculated Head Assay 100 1.615 1.102 0.513      
Sulfide Flotation              
Cleaner Concentrate 1.62 33.24 3.85 29.39 33.41 5.67 92.98
Tailings 98.38 1.093 1.057 0.037 66.59 94.33 7.02
182 Composite 78-77              
Calculated Head Assay 100 1.591 1.083 0.508      
Sulfide Flotation              
Cleaner Concentrate 1.71 30.42 4.18 26.24 32.72 6.60 88.40
Tailings 98.29 1.089 1.029 0.060 67.28 93.40 11.60
183 Composite 78-77              
Calculated Head Assay 100 1.606 1.186 0.420      
Sulfide Flotation              
Cleaner Concentrate 1.28 34.00 0.828 33.17 26.27 0.89 90.26
Tailings 98.72 1.199 1.191 0.041 73.73 99.11 9.74

 

Source: Met Engineering, 2023

 

10.1.4Leaching Studies

 

Leaching test programs were applied to a composite sample blend representing the whole resource, from the samples of the ore types described above under Sample Selection. They were also applied to another ore deposit composite blend that represented mineralization containing principally acid soluble copper minerals and secondary sulfide copper minerals, composite sample 78-77.

 

Industry accepted practices for bottle roll tests were used where PLS samples were withdrawn at timed intervals, and copper, acid, ferric, and pH levels were measured. Acid was added to maintain pH. Optimum leach time, ferric level, and pH were determined based on plots of copper extraction rate, acid consumption rate, and ferric consumption rate.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 182

 

Acid leach test results on the tested composites were generally consistent. Acid soluble copper recovery was in the mid 90% range for a four hour leach time. Acid consumption ranged from 18.5 to 23 kg of acid per tonne of ore without the SX-EW acid credit on copper electrowon. The best pH was 1.5.

 

Acidic ferric sulfate leaching on a composite of acid soluble copper minerals and secondary sulfide minerals was successful. The best agitated tank leach conditions were determined to be:

 

·24-hour leach time

 

·40oC leach temperature

 

·10 grams per liter (gpl) ferric concentration

 

Acid soluble copper recovery was 95%. Non-acid soluble copper recovery was 90%. Total copper recovery was 90-91%.

 

Test procedures described meet current industry accepted practices for determining the leachability of an ore with sulfuric acid or acidic ferric sulfate at the IA level. Once again, lack of any variability test program prevents use for PFS and FS levels.

 

Sulfuric acid heap leaching was evaluated on one hole, 27 A, across most of its length using the column cell test method. Nine column cell tests were conducted from selected intervals of core. The calculated head grade was 1.4% total copper and 1.2% acid soluble copper. Total copper extraction was 77% and acid soluble copper was 89%. Gangue acid consumption (including SX-EW acid credit) was 9.2 kilograms per tonne (kg/t) ore.

 

The QP is of the opinion that procedures applied during the tests were acceptable industry practices.

 

10.1.5Copper Measurement

 

An important aspect of the test programs described above are the analytical techniques used for measuring total copper and acid soluble copper in ores, and total copper in concentrates. The sequential copper assaying method had yet to be developed for the CGCC test programs from 1976 to 1982. Thus, secondary sulfide concentrations in the test composite samples were estimated from mineralogy studies on the composites and from drill core mineral logging records. The analytical methods used by CGCC for total copper assaying are still in use today. The method used digestion by aqua regia and measurement after dilution with DI-water with atomic adsorption. The method described by Hanna for oxide copper determination is in use today minus the addition of 10 ml of sulfurous acid (digestion at boiling temperature for 5 minutes with 100 ml of 5% sulfuric acid and 10 ml of sulfurous acid) and is considered satisfactory for determination of acid soluble copper content in the sample.

 

10.1.6ASARCO Study by Mountain States Engineering (1980)

 

This study evaluated leaching in place of fragmented acid soluble copper ore from block cave mining. There were no mineral processing and metallurgical tests associated with this study. Copper recovery factor and column of ore caving factors are used from nearby underground block cave mines and/or that were leaching block cave rubblized ore with dilute sulfuric acid. This study could not be used today at an IA-level study due to the lack of testwork. This work can be considered conceptual and is referenced as such.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 183

 

10.1.7Santa Cruz In-Situ Study

 

The Santa Cruz in-situ project was a research project between the Department of the Interior Bureau of Mines (subsequently Bureau of Reclamation) and the landowners, the SCJV, consisting of ASARCO Santa Cruz Inc. and Freemont McMoRan Copper & Gold Inc (Mountain States Engineering, 1980).

 

Metallurgical studies of core (2-inch diameter by 2.5-inch-long), from the proposed in situ leach zone in the pilot program reported copper recoveries ranging from 57% to 90%. Total Cu ranged from 2.3% to 9%. Tests were run for 3,000 hours to 3,800 hours (125 days to 158 days), and no extraction rate versus time data was reported, which is unusual because it is critical for the process design and for the well development schedule. Flow volumes varied from two milliliters per day to several liters per day, and pressures ranged from 0 psi to 1,000 psi. The studies reported the acid consumption would be 1.2 lbs per 1.0 lb of Cu recovered on atacamite samples and ranged between three to eight pounds per pound of Cu for chrysocolla samples (with some very high consumption rates initially of, 10+ lbs/lb Cu). The initial acid concentration in the feed solution varied from 5 to 40 gpl H2SO4.

 

Leach tests on the core showed that initial permeability rates were very low when the solution initially contacted the core in the test apparatus. Later, as copper-oxide minerals dissolved from the filled fractures acceptable permeability rates were achieved.

 

The In Situ leach test program used industry accepted practices. Total copper and acid soluble analytical methods were satisfactory for the measurement of the core samples. Identification of the core sample by drillhole and interval was performed. Cross sections of the sample location in the proposed ore area for the five-spot injection and test well design were provided. Samples were representative of the proposed test region.

 

10.22022-2023 Test Work Studies

 

The IE studies were directed by Met Engineering LLC and conducted at McClelland Labs in Sparks, Nevada. McClelland Labs is recognized by the IAS for its technical competence and quality of service and has proven that it meets recognized standards. The studies are in progress currently at an IA level. Study focus has been on:

 

·Confirming total copper recovery of the leach-float flow sheet proposed by CGCC in circa 1980 on Oxide and Chalcocite mineral domains.

 

·Investigating heap leaching of Oxide and Chalcocite mineral domains. The test program for heap leaching is at the slow chalcocite leach stage and will not be completed until the fourth quarter 2023. A progress report is presented in section 10.2.8 below later stage of the Project.

 

10.2.1Sample Selection

 

Testing was performed on a composite of drill core (1/2 core) samples from the 2021 - 2022 drilling program, designated as the mill composite. Details of the mill composite are listed in Table 10-24. The composite generally characterizes minerals found in the Oxide and Chalcocite mineral domains.

 

Table 10-24: Drillholes, Intervals and Sample Lengths of the Mill Composite

 

Drillhole ID From (m) To (m) Number of Samples
SCC-002 615 765 60
SCC-004 595 637 33
SCC-006 665 681 13

 

Source: Met Engineering, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 184

 

Column cell testing was performed on two composites of drill core (1/2 core) samples from the 2021 - 2022 drilling program, designated as heap leach No.1 (4815-002) and No.2 (4815-003). Details of the heap leach composites are listed in Table 10-25 and Table 10-26. The composites generally characterize minerals found in the oxide and chalcocite mineral domains.

 

Table 10-25: Heap Leach Sample No.1 (Lab sample No. 4815-002)

 

Hole ID From (m) To (m) Number of Samples
SCC-007 811.12 1089 145
SCC-008 752.39 791.44 40

 

Source: Met Engineering, 2023

 

Table 10-26: Heap Leach Sample No.2 (Lab sample No. 4815-003)

 

Hole ID From (m) To (m) Number of Samples
SCC-048 580.27 774.51 135
SCC-068 577.82 697.6 113

 

Source: Met Engineering, 2023

 

Figure 10-3 illustrates the location of the drillholes and their intervals used in each composite. All the drill intercepts are positioned inside the minable portion of the mineralized material depicted in the figure. Drillholes SCC-002, -004 and -006 represent the Mill Composite sample (McClelland Labs sample identification 4815-001). Drillholes SCC-007 and -008 represent the No. 1 Heap Leach Composite sample (McClelland Labs sample identification 4815-002). Drillholes SCC-048 and -068 represent the No. 2 Heap Leach Composite sample (McClelland Labs sample identification 4815-003).

 

 

Source: Met Engineering, 2023

 

Figure 10-3: Mineral Process Testing Sample Drillhole Intercepts in the Minable Material

 

September 2023

SEC Technical Report Summary – Santa CruzPage 185

 

10.2.2Grinding Studies

 

The Bond Mill Work Index (10.71 kWh/t) estimated for the upper body of mineralized material in 1980 by CGCC was applied for predicting the energy consumption per tonne of ore for the flow sheet proposed. The proposed flow sheet employs a SAG and ball mill to grind ore for agitation leaching purposes, followed by a second ball mill to grind the leach residue in preparation for copper sulfide flotation. Finer grinds were determined from the IE studies on the mill composite described above compared to the CGCC studies to achieve the same total copper recovery for the leach-float process flow sheet. The grinding flow sheet reduces primary crushed product at a P80 of 150,000 µ to P80 300 µ for leaching, requiring an estimated 7.17 kWh/t. Leached residue needs to be reduced from P80 300 µ to P80 106 µ to achieve optimal rougher flotation recovery, requiring 4.22 kWh/t. Combined grinding circuit energy requirements are 11.39 kWh/t.

 

A confirmatory bond mill work index test was performed on the mill sample (4815-001). Results are shown in Table 10-27. The Bond Mill Work Index was 13.82 KWh/t of material, which is somewhat larger than the CGCC work found, and places the material in the medium hard category. For process design the CGCC results were used because they represent the minable area better than the mill sample (4815-001).

 

Table 10-27: Confirmatory Bond Mill Work Index Test

 

Results
Ball Mill Work Index 12.53 kW-hr/st
Ball Mill Work Index & Classification Medium 13.82 kW-hr/mt
       

Source: Met Engineering, 2023

 

10.2.3Leaching Studies

 

Testing was conducted in the summer of 2022 to confirm that high ASCu recovery (plus 93% recovery) achieved in the circa 1980 test programs by the Case Grande Copper Corporation (CGCC) were achievable on the mill composite described above. After some experimentation with particle size distribution, similar results were achieved to those reported by CCGC. ASCu recovery of 92% was achieved consistently at a grind size of P80 300 µ and leach conditions of pH 1.6, ambient temperature and four hours of residence time. The next step was to confirm that 94% total copper recovery of the CGCC test program was achievable by the leach – float circuit. Table 10-28 in the flotation section shows the combined copper recoveries for the leach-float test on sample 4815-001.

 

10.2.4Flotation Studies

 

In December 2022, the same mill composite sample as used above was subjected to the standard leach procedure developed in the summer of 2022 (leach after P80 300 µ grind). Neutralized residue was then subjected to conventional froth floatation (rougher flotation stage, only) utilizing parameters and reagents utilized in the CGCC studies. However, because some experimentation on particle size distribution was needed earlier in the leach phase of testing, three standard leach tests were run and the neutralized residue from each was subject to different grind sizes. The results are illustrated in Figure 10-4. Table 10-28 that shows total copper recovery for each test. These test results are also shown in more detail in Table 10-29.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 186

 

 

Source: Met Engineering, 2023

 

Figure 10-4: Leach – Float Testing Results at Different Leach Residue Grinds

 

Table 10-28: Results of Leach – Float Tests at Different Leach Residue Grinds

 

Test Description Head
Grade
(% Cu)
Calculated
Head Grade (%
Cu)
Leach
Recovery
(%)
Flotation
Recovery
(%)
Total
Copper
Recovery
(%)

Rougher
Con
(% Cu)

Rougher
Con
(%S)

Test, standard leach, grind residue to P80 212 microns 1.41 1.38 54.3 38.6 92.9 9.91 4.71
Test 2, standard leach, grind residue to P80 150 microns 1.41 1.36 59.7 34.4 94.1 10 5.36
Test 3, standard leach, grind residue to P80 106 microns 1.41 1.38 58.8 36.7 95.5 6.83 3.09

 

 

Source: Met Engineering, 2023

 

The test program demonstrated that total copper recovery increases with finer grinding of the leach residue. Grinding the leach residue to P80 106 µ seems optimal with the current data, producing a total copper recovery of 95.5%. Total copper recovery the flotation test improved to 89.1% for the P80 106 µ grind from 85.3% for the P80 150 µ grind. Recovery of non-ASCu copper in the P80 copper grind was the highest at approximately 93.9%. Factoring in process losses a total copper recovery of 94% is possible. This total copper recovery at the P80 106 grind confirms the total copper recovery results predicted by GCC test programs.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 187

 

Cleaner Stage Flotation Results

 

A larger bulk leach and flotation sample was treated by the standard leach on material from sample 4815-001 followed by flotation of the leach residue after re-grinding to 80% passing 106 microns. This procedure created a large enough rougher concentrate sample to use in a cleaner circuit test utilizing two stages of cleaning, which was the configuration that worked effectively in the CCGC test programs. The new circuit design included a regrind of the rougher concentrate, which is effectively used at most copper concentrators, to 100% passing 74 microns. The cleaner test produced a final concentrate of 42% total copper and 96% of the copper in the rougher concentrate reported to the cleaner concentrate product. A scavenger cleaner circuit on the tailings from the second cleaner would likely result in 98 to 99% recovery of copper from the rougher concentrate to the cleaner concentrate. Table 10-29 illustrates the results from agitation leach through to final concentrate.

 

Table 10-29: Combined Metallurgical Results, Whole Ore Acid Leaching, Residue Cleaner Flotation, Composite 4815-001

 

  Feed Weight Cu Grade Cu Distribution Units
Product Size % % Cu % of Total % Cu
Whole Ore Acid Leach 80%-300 µm 100.0      
Extraction     0.79 58.6 0.79
           
Residue Cleaner Flotation 80%-106 µm 93.6*      
Cleaner Concentrate   1.1 41.50 34.6 0.47
Recleaner Tail   1.7 1.01 1.3 0.02
Cleaner Tail   0.2 2.7 0.4 0.01
Residue Rougher Flotation          
Rougher Tails   90.6 0.08 5.2 0.07
Total Recovered     1.26 93.2 1.35
Tail     0.07 6.8  
Composite   93.6 1.33 100.0  

 

Source: Met Engineering, 2023

 

*Weight percent reporting to flotation, reflects weight loss during leaching

 

There were other metals of interest in the cleaner concentrate. Gold and silver were at smelter payable levels of 2.71 ppm gold (fire assay and AA finish) and 57.4 ppm silver (ICP). Molybdenum was present at 11,300 ppm (4 acid digestion and ICP), which could warrant evaluating recovery of a separate molybdenite concentrate on-site for sale.

 

There were no deleterious smelter penalty elements for compounds in the final cleaner concentrate. See Table 10-30 and Table 10-31 for the full suite of assays on the final copper concentrate.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 188

 

Table 10-30: Base Metal Concentrate Results

 

Santa Cruz
Analyte Unit F-5 Cleaner
Al2O3 % 1.26
As % 0.01
Ba % 0.04
Bi % <0.01
CaO % 0.09
Co % 0.02
Cr % 0.01
Cu % 45.4
Fe % 15.10
K2O % 0.36
MgO % 0.06
Mn % <0.01
Mo % 0.988
Nb % <0.01
Ni % 0.02
P % 0.04
Pb % 0.04
S % 26.5
Sb % <0.01
SiO2 % 6.03
Sn % <0.01
Ta % 0.01
TiO2 % 0.08
LOI1 % 11.52
Total % >110
V % 0.01
WO3 % 0.01
Zn % <0.01
Zr % 0.02

 

Source: Met Engineering, 2023

 

1. Loss of ignition

ALS Report No. RE23055348

 

Table 10-31: Chloride Analyses

 

Santa Cruz
  Sample
Analyte Unit F-5 Cleaner Concentrate
Cl mg/kg 280

 

Source: Met Engineering, 2023

ALS Report No. RE23055348

 

10.2.5Copper Measurement

 

McClelland Labs used modern copper measurement methods on ore grade material for total copper and sequential copper assaying, assays are acceptable in the QP’s opinion.

 

10.2.6Thickener Sizing Tests

 

Pocock Industrial (Salt Lake City) was commissioned to conduct solid-liquid separation (SLS) tests on Santa Cruz material to generate data for thickener design and sizing criteria. Tests were conducted on samples of pre-leach ground feed material, leach residue tails, and flotation tails. The resulting data was used to size the ground ore dewatering thickener (treating pre-leach). Counter current decantation (CCD) thickeners (treating leach residue) and flotation tailing dewatering thickener. A 32 m diameter design was found to be effective for each situation.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 189

 

This work produced the following high-rate thickener design parameter recommendations (Table 10-32):

 

Table 10-32: High-Rate Thickener Sizing Test Results

 

Material pH Feed Solids %  Max Underflow Solids, %

Unit Feed Rate

m3/m2∙hr

Pre-leach 7.15 24.11 72.7 3.62
Leach residue 2.2 23.48 70.2 3.45
Tailings 10.5 18.72 63.0 2.90

 

Source: Met Engineering, 2023

 

m3 = cubic meters

m2 = square meters

 

Flocculant screening was conducted on small pulp samples in static settling tests to determine the effectiveness of each flocculant. Pocock selected SNF FA920SH a widely used flocculant of medium high molecular weight, nonionic polyacrylamide, for best overall performance for thickening the pre-leach ground feed, for the CCD thickeners (leach residue) and for the tailings thickener. The non-ionic flocculant will avoid phase disengagement problems in the downstream solvent extraction process. Flocculant consumption rate will be 18-23 g/t for pre-leach material. The first CCD thickener will use 19 to 26 g/t flocculant and subsequent CCD thickeners will decline steadily due to flocculant carry over; overall usage for the CCD circuit will be 70 to 80 g/t. The finer material reporting to the tailing thickener will require 40 to 50 g/t.

 

10.2.7Solvent Extraction Testing

 

A PLS sample from an agitated leach test on sample 4815-001 was sent to BASF (Tucson) for isotherm analysis. The results of that testing indicated that typical non-modified solvent extraction reagents will be able to extract and strip copper effectively from the Santa Cruz PLS. Simulations at the expected copper PLS level of 6.05 grams of copper per liter of solution indicated 95.8% extraction could be expected with a 25% by volume extractant level for a circuit design of two extractors, one wash stage and two strip stages (Figure 10-5).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 190

 

 

Source: Met Engineering, 2023

 

Figure 10-5: Copper Recovery vs Organic Extractant Concentration for PLS Extraction of Copper from Santa Cruz PLS

 

10.2.8Column Leach Tests

 

The column leach work was performed to develop leach parameters at the Initial Assessment level. One phase of column leaching tests was performed on two composite samples (No.1 and No.2) representing oxide and chalcocite mineral domains in the upper ore. The two samples varied in spatial location and in the dominant oxide mineral present. Heap leach composite sample No.1 (lab sample ID 4815-002) dominant oxide mineral was chrysocolla while No.2 dominant oxide mineral was atacamite.

 

Bottle roll tests were conducted on various crush sizes of material, ranging from -2 inch to -1/2 inch, to determine the optimum crush size and the probable net acid consumption rate. Copper recovery improved as crush size decreased, without corresponding net acid consumption increase, and there was a pronounced improvement from crush size -3/4 inch to crush size -1/2 inch. Therefore, after establishing the fines generation was not too much for the -1/2 inch crushed material, it was decided to set up all the column cells at the -1/2 inch size using 4 inch diameter PVC pipe.

 

Eight column cells were set up using material from both composite samples mentioned above. Six column cells were set up as conventional bacterial assisted acidic ferric leaches to extract both copper from copper oxides and secondary copper sulfides. Various operating parameters were examined: acid cure amount (kilograms acid per tonne material, 3 and 5 kg/t), length of cure (7 and 14 days) and irrigation rates (5 and 10 liters per hour (L/h) per square meter of surface area). Two of the bacterial leaches were short columns investigating a blend of exotic material with each of the two composites. Two regular height columns (3 m) were set up as experimental chloride dopant assisted acidic ferric leaches where acid and chloride dopant levels in the curing were varied.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 191

 

All of the column cells are in operation or are in the drain down and water wash stage at this time.

 

All the column cells have run without significant incident except for very high extraction rates (and high PLS levels, +30 gpl copper) initially that drove the PLS solution pH into the 3-3.5 range and precipitated the ferric sulfate temporarily until the high acid solvent extraction raffinate rinse drove them back down and re-solubilized the ferric.

 

The chloride dopant cure columns experienced rapid extraction of the oxide copper and the secondary sulfide copper. Material with dominant copper oxide as atacamite leached faster than those with chrysocolla. The bacterial assisted leaches have reached the slow extraction period that is typically encountered with leaching secondary sulfide copper. One column cell is in the acid solution drain down mode, which will be followed by water rinse and drain down. Afterwards, it will be broken down and the residue analyzed.

 

Bacterial assisted column leaches will continue to run for several more weeks as the copper is leached from the secondary copper sulfides. The remaining seven column cells remain under acid rinse conditions at 5 L/h per square meter of area. Column cells initially operating under rinse conditions of 10 L/h per square meter of area were reduced to 5 L/h per square meter after the chalcocite leach was well underway. This change was made to increase PLS grade exiting the columns and follows typical commercial operating practice.

 

Rough estimates of total copper recovery, based on column ore weights, head grades and weights of copper in solution recovered, range from 72% to 98% after 63-70 days of rinsing. Net acid consumption, kilograms acid per tonne of ore, range from -4 to +4 kilograms acid per tonne of ore. Negative numbers are due to ferric sulfate leaching of chalcocite, which generates acid, and naturally occurring low acid consumers in the ore of sample 4815-003.

 

10.2.9Sample Mineralogy and Assays

 

PMC Laboratory Limited (British Columbia, Canada) was commissioned to provide rapid ore characterization of four composite samples from the mineral process testing program IE was executing with McClelland Labs in Sparks, Nevada. Samples were 4815-001 (mill composite sample), 4815-002 (heap leach sample No.1), 4815-003 (heap leach sample No.2) and 4815-004 (exotic mineralized material). Each sample was homogenized and between 2 and 2.5 grams was riffled out for a single polished block section per sample for analysis. Each sample’s polished block was scanned by automated scanning electron microscope (AutoSEM), specifically the Tescan Integrated Mineral Analyser (TIMA), to determine the bulk modal composition of each, as well as the deportment of copper (Cu-) bearing phases.

 

Summary of Observations

 

·Copper in the samples examined occurred mostly in three forms – chalcopyrite, chalcocite/digenite and copper oxides and malachite – however in varying abundances (Figure 10-7).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 192

 

·Primary copper sulfides (chalcopyrite, bornite) are most abundant in sample 4815-001 (Figure 10-7).

 

·The copper oxides are most abundant in sample 4815-004 with an Fe- and Cu-bearing clay (Figure 10-7).

 

·Secondary copper sulfides are the most abundant Cu-bearing minerals in samples 4815-002 and 4815-003, with lesser amounts or Cu oxides (Figure 10-7).

 

·Quartz is the predominant phase in samples 4815-001, but feldspar more so in 4815-002 and 4815-003. Micas were detected at approximately 11 mass % in all samples, except 4815-004 where its abundance is double that of the other samples (Figure 10-6).

 

·Copper oxides, chrysocolla and atacamite, and cu-bearing clays were the only cu-bearing species identified in sample 4815-004 (Figure 10-6).

 

·Due to the nature of the sampling, analysis and over-representation of coarse particles, adjusted SGs were utilized in the mineral reconciliation.

 

 

Source: Met Engineering, 2023

 

Figure 10-6: Summarized Sample Composition

 

September 2023

SEC Technical Report Summary – Santa CruzPage 193

 

 

Source: Met Engineering, 2023

 

Figure 10-7: Copper Deportment (%) of Each Sample

 

Assays for sample 4815-001 through 4815-004 are reported in Table 10-33 and Table 10-34.

 

Table 10-33: Sequential Copper Analyses, Santa Cruz Samples

 

  % Cu  
      Head Grade Cu, % of Total
Composite Acid Sol CN Sol Residual Calculated Assayed Acid Sol CN Sol Residual Total
4815-001 0.79 0.40 0.18 1.37 1.41 57.7 29.2 13.1 100.0
4815-002 0.74 0.58 0.04 1.36 1.41 54.4 42.7 2.9 100.0
4815-003 1.22 0.46 0.01 1.69 1.68 72.2 27.2 0.6 100.0
IE 2.62 0.32 0.74 3.68 3.79 71.2 8.7 20.1 100.0

 

Source: Met Engineering, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 194

 

Table 10-34: ICP Metals Analysis Results for Santa Cruz Samples

 

Santa Cruz
  Sample
Analysis Unit 4815-001 4815-002 4815-003 IE Exotic Copper
Ag mg/kg 1.46 3.15 1.57 0.09
Al % 6.46 6.51 6.28 7.08
As mg/kg 1.3 3.1 1.6 1.3
Ba mg/kg 430 420 430 140
Be mg/kg 1.25 1.53 1.24 4.76
Bi mg/kg 0.53 0.81 0.52 0.19
Ca % 0.08 0.18 0.05 0.71
Cd mg/kg 0.47 0.66 0.45 0.18
Ce mg/kg 99.3 82.8 91.3 71.1
Co mg/kg 6.6 11.0 4.5 80.2
Cr mg/kg 36 26 26 105
Cs mg/kg 2.54 3.32 2.34 5.03
Cu % 1.4501) 1.4151) 1.8101) 3.691)
Dy mg/kg 2.82 1.92 2.02 8.55
Er mg/kg 1.19 0.90 0.85 4.08
Eu mg/kg 1.04 0.86 0.94 2.20
Fe % 1.22 1.29 0.74 6.59
Ga mg/kg 13.70 13.35 12.1 17.40
Gd mg/kg 4.64 3.41 3.31 9.18
Ge mg/kg 0.19 0.12 0.14 0.19
Hf mg/kg 0.6 0.5 0.5 4.0
Ho mg/kg 0.47 0.31 0.29 1.61
In mg/kg 0.141 0.125 0.082 0.094
K % 4.79 5.10 5.50 1.89
La mg/kg 49.7 38.7 50.9 34.9
Li mg/kg 13.4 14.0 10.5 43.0
Lu mg/kg 0.17 0.14 0.11 0.40
Mg % 0.18 0.24 0.14 0.47
Mn mg/kg 36 91 45 511
Mo mg/kg 251 118 196 60.2
Na % 0.25 0.28 0.26 0.32
Nb mg/kg 4.4 4.2 4.6 30.8
Nd mg/kg 36.3 32.9 32.4 34.6
Ni mg/kg 5.4 6.1 4.7 108.5
P mg/kg 370 300 220 1,170
Pb mg/kg 20.4 27.7 28.3 8.1
Pr mg/kg 11.15 8.71 10.05 7.93
Rb mg/kg 158.0 134.0 162.0 97.8
Re mg/kg 0.219 0.011 0.107 0.002
S % 0.33 0.24 0.19 0.03
Sb mg/kg 0.27 0.14 0.17 0.30
Sc mg/kg 7.0 6.2 5.7 15.2
Se mg/kg 12 8 12 3
Sm mg/kg 6.82 5.44 5.93 7.88
Sn mg/kg 8.3 6.8 6.8 5.7
Sr mg/kg 304 113.5 193 299
Ta mg/kg 0.39 0.40 0.51 1.75
Tb mg/kg 0.58 0.39 0.42 1.46
Te mg/kg 0.13 0.13 0.05 0.14
Th mg/kg 35.8 29.9 34 11.75
Ti % 0.088 0.098 0.07 1.125
Tl mg/kg 0.66 0.70 0.70 0.24
Tm mg/kg 0.17 0.13 0.12 0.56
U mg/kg 6.1 8.1 3.4 33.2

 

September 2023

SEC Technical Report Summary – Santa CruzPage 195

 

Santa Cruz
  Sample
V mg/kg 31 39 27 144
W mg/kg 5.9 6.3 6.7 5.8
Y mg/kg 14.0 8.7 8.6 45.9
Yb mg/kg 1.09 0.87 0.82 2.93
Zn mg/kg 11 17 38 240
Zr mg/kg 14.1 13.0 9.7 153.0
ALS USA, Inc. Report No. RE22157772 RE22275100 RE23019039 RE23046119

 

Source: Met Engineering, 2023

1) Cu reported using the OG62 method.

 

10.3Process Factors and Deleterious Elements

 

There are some factors to follow up on with future testing to ensure all processing factors are effectively covered. These are confirmation of corrosion resistant materials and linings, to elevated chloride levels, for the thickeners in the counter-current-decantation system for pregnant leach solution recovery, and studying sulfide flotation with expected process water chemistry at the site. Otherwise, there are no other processing factors or deleterious elements that could have a significant effect on economic extraction. The processes proposed in the IE, CGCC, ASARCO, and Santa Cruz In-Situ studies for extraction of copper from the ore are all conventional in design and have been used economically for decades. There have been significant advances in most of these technologies since 1980, when most of the studies were conducted, which have improved the economics of these processes. Some examples are:

 

·Materials for construction of SX plants are cheaper and more resistant to chlorides in solution from leaching atacamite. SX wash circuits and/or organic coalescers eliminate the concern of chloride carryover to the EW.

 

·SX reagents are much more selective for copper extraction, react faster, separate faster from the aqueous media they are mixed with and are more robust today.

 

·SAG and ball mill grinding circuits are designed much more efficiently today and the liner and grinding media used last much longer than in 1980.

 

·Flotation cell designs are more efficient now and have raised recovery and concentrate grades.

 

·Environmental controls for dust, volatile organic compounds (VOC), and aerosol mists are much more efficient compared to 1980.

 

10.4QP Opinion

 

After completion of the review of mineral processing and metallurgical testing by The Hanna Mining Company, the United States Bureau of Mines, and the IE metallurgical test program in 2022-2023, it is the opinion of the M3 QP that the testing procedures, results, interpretations, and reporting meet standard industry practices and are adequate for this level of study.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 196

 

11Mineral Resource Estimates

 

11.1Drillhole Database

 

The work on the Mineral Resource Estimates included a detailed geological and structural re-examination of the Santa Cruz Deposit along with the East Ridge and Texaco Deposits.

 

The Santa Cruz Deposit Mineral Resource Estimate benefits from approximately 116,388 m of diamond drilling in 129 drillholes, while Texaco has 23 drillholes totaling 21,289 m, and East Ridge has 18 holes totaling 15,448 m. All holes were drilled between 1964 to 2022 (Table 11-1, Figure 11-1).

 

 

 

Source: Nordmin, 2023

 

Figure 11-1: Plan View of Santa Cruz Project Diamond Drilling by Deposit

 

Diamond drillhole samples were analyzed for total copper and acid soluble copper using AAS. A decade after initial drilling, ASARCO re-analyzed select samples for cyanide soluble copper (AAS) and molybdenum (ICP). The Company currently analyzes all samples for total copper, acid soluble copper, cyanide soluble copper, and molybdenum. Due to the re-analyses to determine cyanide soluble copper within the historic samples, there are instances where cyanide soluble copper is greater than total copper. It has been determined that the historic cyanide soluble assays are valid as they align with recent assays in 2022 drillholes. Therefore, a cap has been applied to historic cyanide soluble assays such that they must be equal to or less than the associated total copper value for each sample. A breakdown of the drillhole summary is in Table 11-1, and the number of assays used within each Mineral Resource Estimate is provided in Table 11-2.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 197

 

Table 11-1: Drillhole Summary

 

  Total Drilling IE Electric Drilling
Deposit Number of
Drillholes
Meters Meters
Intersecting
Deposit
Number of
Drillholes
Meters Meters
Intersecting
Deposit
Santa Cruz 129 116,388 57,326 41 34,769 14,172
East Ridge 18 15,448 1,501 0 0 0
Texaco 23 21,289 2,661 3 3,286 685
Total 170 153,125 61,488 44 38,055 14,857

  

Source: Nordmin, 2023

 

Table 11-2: Mineral Resource Estimate Number of Assays by Assay Type

 

Assay Type Santa Cruz
Deposit Assays
Texaco Deposit
Assays
East Ridge Deposit
Assays
Total Cu 21,898 1,403 1,389
Acid Soluble Cu 15,859 787 0
Cyanide Soluble Cu 10,278 893 0
Molybdenum 13,193 712 86

 

Source: Nordmin, 2023

 

11.2Domaining

 

11.2.1Geological Domaining

 

Geological domains were developed within the Santa Cruz Project based upon geographical, lithological, and mineralogical characteristics, along with incorporating both regional and local structural information. Local D2 fault structures separate the mineralization at the Santa Cruz, Texaco, and East Ridge Deposits. Local fault zones were created and/or extrapolated by Rogue Consulting using Seequent’s Leapfrog Geo (Leapfrog) geological software. The three Deposits were divided into two main geological domains consisting of the weathered supergene enrichment and the primary hypogene mineralization domain, each of which were further subdivided based upon their type of Cu speciation, specifically acid soluble-rich (Oxide Domain), cyanide soluble-rich (Chalcocite Enriched Domain), primary Cu sulfide (Primary Domain), and Cu oxides in overlying Tertiary sediments (Exotic Domain). Collectively, each of these domains was further sub-domained based upon their individual grade profiles. A schematic for Santa Cruz, Texaco, and East Ridge Deposit hierarchies is outlined in Figure 11-2 and Table 11-3. The following terms are assigned to the sub-domains; these represent a local definition of the grade profile: high-grade (HG), medium grade (MG), and low grade (LG).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 198

 

 

 

Source: Nordmin, 2023

 

Figure 11-2: Santa Cruz, Texaco, and East Ridge Geological Domains

 

Table 11-3: Santa Cruz, Texaco, and East Ridge Geological Domains

 

Santa Cruz Deposit
Weathered Supergene Enrichment Oxide Domain (Primarily Acid Soluble Cu)
Chalcocite Enriched Domain (Primarily Cyanide Soluble Cu)
Exotic Domain (Tertiary-Hosted “Exotic” Cu)
 Hypogene Mineralization Primary Domain (Primary Sulfide Cu)
Texaco Deposit
Weathered Supergene Enrichment Oxide Domain (Primarily Acid Soluble Cu)
Chalcocite Enriched Domain (Primarily Cyanide Soluble Cu)
 Hypogene Mineralization Primary Domain (Primary Sulfide Cu)
East Ridge Deposit
Weathered Supergene Enrichment Oxide Domain (Primarily Acid Soluble Cu)

 

Source: Nordmin, 2023

 

Exotic Cu is primarily present within the CG2 and CG3 D2 fault structures. All other Cu styles of mineralization hosted within the oracle granite lithology terminate at the contact of the tertiary sediments. The current drilling indicates that the Cu mineralization is truncated at depth by the basal faults within the region.

 

The oracle granite hosts both the laramide porphyry and diabase dykes, both of which are associated with brecciation and Cu mineralization. Secondary supergene Cu mineralization is separated from the primary hypogene mineralization by a Cu-oxide boundary layer called the chalcocite enriched domain. This domain is defined by a 2:1 relationship of acid soluble to total Cu and follows the dip of the contact of the oracle granite-tertiary sediments contact. The chalcocite enriched domain was formed by two different enrichment events. HG Cu oxides follow the trend of the laramide porphyries closely and likely contain significant amounts of primary mineralization. Cyanide soluble Cu can be found within both the supergene Cu and hypogene Cu domains as a form of secondary enrichment of chalcocite. Figure 11-3 is a conceptual example of the Santa Cruz Deposit domaining. Figure 11-4 and Figure 11-5 are examples of Texaco and East Ridge domaining.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 199

 

 

 

Source: Nordmin, 2023

 

Figure 11-3: Santa Cruz Deposit Domain Idealized Cross-section

 

 

 

Source: Nordmin, 2023

 

Figure 11-4: Texaco Deposit Domain Idealized Cross-section

 

September 2023

SEC Technical Report Summary – Santa CruzPage 200

 

 

 

Source: Nordmin, 2023

 

Note: Another discrete oxide domain exists to the south but has little interpretation due to lack of data.

 

Figure 11-5: East Ridge Deposit Domain Idealized Cross-section with Structural Control, Comprised Solely of Oxide Mineralization

 

The current mineral domains have been significantly revised based on improved understanding of the deposition mechanisms for each mineral type. The high-grade oxide domain has been revised to better reflect the supergene enrichment process. Subsequent drilling has confirmed the new interpretation, as in Figure 11-6 and Figure 11-7.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 201

 

 

 

Source: Nordmin, 2023

 

Note: The three displayed drillholes were completed after the revision in interpretation and confirm the new wireframes as they intersected high grade copper mineralization.

 

Figure 11-6: Revised Santa Cruz High-Grade Domains for Exotic, Oxide, and Primary Mineralization

 

The oxide domains consider the acid soluble copper assay to total copper assay ratio, while the chalcocite zone considers the cyanide soluble assay to total copper assay ratio. This is important as an additional level of interpretation considers possible ore type mixing and gradational zones between oxide, chalcocite, and primary ore types.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 202

 

 

 

Source: Nordmin, 2023

 

Figure 11-7: Santa Cruz Cross-section Showing Acid Soluble Copper Assay to Total Copper Assay Ratio

 

11.2.2Regression

 

Cyanide soluble and acid soluble assays were measured approximately a decade after initial diamond drilling by ASARCO, therefore assay data is not available for all sample intervals within the drillholes. A regression analysis was conducted to infill the downhole intervals that are missing relevant acid soluble and cyanide soluble data. The analysis used the relationships between all applicable data available to determine the most appropriate regression calculations using Orange Data Mining™ Software (version 3.34) and Microsoft Excel™. Regression formulas were created and applied in a recursive manner to the assays for all three Deposits using the total Cu assays, flagged Sub-Domains, and lithology to calculate acid soluble and/or cyanide soluble values. Because internal correlations differ for all Domains, Sub-Domains, and lithologies, regression contains formulas up to five levels deep to allow the most accurate correlation formula to be applied. All further references to acid soluble and cyanide soluble Cu grades apply to the full regression-applied values. Regression analyses can be found in Table 11-4 and Table 11-5.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 203

 

Table 11-4: Regression Analysis for Acid Soluble Cu

 

Sub-characterization ID Linear Formula (y=mx+b) Formula m Formula b
General
All AA (0.4868 * TCu) – 0.0619 0.4868 0.0619
STEP 1 – Domain
Exotic 1EA (0.5502 * TCu) + 0.2338 0.5502 0.2338
Oxide 1OA (0.5895 * TCu) + 0.0958 0.5895 0.0958
Chalcocite 1CA (0.2285 * TCu) + 0.0532 0.2285 0.0532
Primary 1PA (0.0912 * TCu) + 0.116 0.0912 0.116
Background 1BA (0.5823 * TCu) – 0.0551 0.5823 -0.0551
STEP 2 – Sub-Domain
Exotic LG 2ELA (0.7962 * TCu) – 0.0358 0.7962 -0.0358
Exotic HG 2EHA (0.4261 * TCu) + 1.0446 0.4261 1.0446
Oxide LG 2PLA (0.1186 * TCu) – 0.0022 0.1186 -0.0022
Oxide HG 2OHA (0.629 * TCu) + 0.3405 0.629 0.3405
Chalcocite LG 2CLA (0.4529 * TCu) – 0.0642 0.4529 -0.0642
Chalcocite MG 2CHA (0.1625 * TCu + 0.0703 0.1625 0.0703
Background 2BGA 1BA 1BA 1BA
STEP 3 – Lithology
Alluvium 3MA1 (0.9458 * TCu) – 0.0275 0.9458 -0.0275
Igneous 3MA2 (0.4594 * TCu) – 0.0611 0.4594 -0.0611
Conglomerates 3MA3 (0.8871 * TCu) – 0.0329 0.8871 -0.0329
Diabase 3MA4 AA AA AA
Mafic Conglomerate 3MA5 (0.8073 * TCu + 0.0666 0.8073 0.0666
Pinal Schist 3MA6 AA AA AA
Porphyries 3MA7 (0.5782 * TCu) – 0.0557 0.5782 -0.0557
STEP 4 – Individual Lithology
Background Porphyries 4MBA1 (0.7503 * TCu) – 0.066 0.7503 -0.066

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 204

 

Table 11-5: Regression Analysis for Cyanide Soluble Cu

  

Characterization ID Formula (y=mx+b) Formula m Formula b
General
All AC (0.4408 * TCu) – 0.0337 0.4408 -0.0337
STEP 1 – Domain
Exotic 1EC (0.3154 * TCu) – 0.2166 0.3154 -0.2166
Oxide 1OC (0.4369 * TCu) – 0.0722 0.4369 -0.0722
Chalcocite 1CC (0.8295 * TCu) – 0.1311 0.8295 -0.1311
Primary 1PC (0.7766 * TCu) – 0.2052 0.7766 -0.2052
Background 1BC (0.0565 * TCu) + 0.0047 0.0565 0.0047
STEP 2 – Sub-Domain
Exotic LG 2ELC (0.0475 * TCu) + 0.0026 0.0475 0.0026
Exotic HG 2EHC (0.398 * TCu) – 0.787 0.398 -0.787
Oxide LG 2OLC (0.7541 * TCu) – 0.1051 0.7541 -0.1051
Oxide HG 2OHC (0.3682 * TCu) – 0.3011 0.3682 -0.3011
Chalcocite LG 2CLC (0.591 * TCu) – 0.0551 0.591 -0.0551
Chalcocite MG 2CHC (0.8391 * TCu) – 0.0549 0.8391 -0.0549
Primary LG 2PLC (0.6232 * TCu) – 0.1344 0.6232 -0.1344
Primary HG 2PHC (1.0344 * TCu) – 0.3695 1.0344 -0.3695
Background 2BGC 1BC BC 1BC
Step 3 – Lithology
Alluvium 3MC1 (0.229 * TCu + 0.008 0.229 0.008
Igneous 3MC2 (0.5312 * TCu) – 0.0631 0.5312 -0.0631
Conglomerates 3MC3 AC AC AC
Diabase 3MC4 (0.826 * TCu) – 0.2475 0.826 -0.2475
Mafic Conglomerate 3MC5 (0.0467 * TCu + 0.0049 0.0467 0.0049
Pinal Schist 3MC6 AC AC AC
Porphyries 3MC7 (0.3385 * TCu) – 0.0221 0.3385 -0.0221
STEP 4 – Individual Lithology
Background Conglomerates 4MBC1 (0.0211 * TCu + 0.0038 0.0211 0.0038

 

Source: Nordmin, 2023

 

11.2.3Mineralization Domaining

 

Mineralization within the Santa Cruz, Texaco, and East Ridge Deposits is hosted within crystalline basement rocks, including the Oracle Granite, Laramide Porphyry, and Diabase Dykes.

 

Nordmin and IE examined and modeled the grade distributions for the hypogene and supergene Cu domains and their corresponding Domains. Each Domain was further domained into Sub-Domains based upon their Cu grade distribution, with grade distributions created for the Exotic, Oxides, Chalcocite Enriched, and Primary Domains. Analysis confirmed that the changes in mineralization and corresponding grade are associated with the type of Cu mineralization. The higher-grade mineralization is a result of secondary supergene enrichment and is near the contact between the Oracle Granite and Tertiary sediments. While the Primary Domain consists of moderate grade hypogene Cu that is predominately hosted within the Laramide porphyry, Diabase dykes, and associated breccias at greater depth. As such, Nordmin and IE created grade shells for each of the Cu types at multiple grade cut-offs to reflect the mineralogical and geochemical differences.

 

Mineralization wireframes were initially created to honor the known controls on each mineralization type, such as paleowater table for Cu-oxide mineralization and dike orientation for primary mineralization. When not cut-off by drilling, the wireframes terminate at either the contact of the Cu-oxide boundary layer, the Tertiary sediments/Oracle Granite contact, or the D2 fault structure. There is overlap of the Chalcocite Enriched Domain with the Oxide Domain in the weathered supergene or with the Primary Domain in the primary hypogene mineralization; no wireframe overlapping exists within a given Sub-Domain and no other Sub-Domain or Domain wireframe overlapping exists. Implicit modeling was completed in Leapfrog which produced reasonable mineral domains that represent the known controls on high-grade and low-grade mineralization. Leapfrog performs implicit modeling via their proprietary FastRBF technology, which is a mathematical algorithm developed from radial basis functions allowing the use of variables provided to create wireframes.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 205

 

Grade domain wireframes were modeled for four domains: Oxide, Primary, Chalcocite Enriched, and Exotic Domains. Each Domain consists of Sub-Domains, that are based on the following grade distributions outlined in Table 11-6.

 

Table 11-6: Santa Cruz, East Ridge, and Texaco Deposit Domain Wireframes

 

Santa Cruz Domains Sub-Domain Grade Bin
Exotic LG Total Cu 0.5-2.0%
HG Total Cu >= 2.0%
Oxide LG Acid Soluble Cu 0.5-2.0%
HG Acid Soluble Cu >= 2.0%
Chalcocite Enriched LG Cyanide Soluble Cu 0.5-1.0%
MG Cyanide Soluble Cu >= 1.0%
Primary LG Total Cu 0.5-1.0%
HG Total Cu >= 1.5%
Texaco Domains Sub-Domain Grade Bin
Oxide LG Total Cu 0.5-1.0%
MG Total Cu >= 1.0%
Chalcocite Enriched MG Total Cu >= 1.0%
Primary LG Total Cu 0.5-1.0%
East Ridge Domains Sub-Domain Grade Bin
Oxide LG Total Cu 0.5-1.0%
MG Total Cu >= 1.0%

 

Source: Nordmin, 2023

 

11.3Exploratory Data Analysis

 

The exploratory data analysis was conducted on raw drillhole data to determine the nature of the element distribution, correlation of grades within individual lithologic units, and the identification of high-grade outlier samples. Nordmin used a combination of descriptive statistics, histograms, probability plots, and XY scatter plots to analyze the grade population data using X10 GeoTM (V1.4.18). The findings of the exploratory data analysis were used to help define modeling procedures and parameters used in the Mineral Resource Estimate.

 

Descriptive statistics were used to analyze the grade distribution and continuity of each sample population, determine the presence of outliers, and identify correlations between grade and rock types for each mineral Sub-Domain.

 

The following are some data errors which were identified and rectified:

 

·One drillhole, SC-013, contained assay interval errors. The interval from 0 m to 696.77 m was removed from the flagging process and was not used in the estimate.
·CG-018 had historical collar and survey errors. This drillhole was historically re-drilled and named CG-018A. Relevant data for CG-018 can be found in CG-018A. Because all appropriate drilling data can be found in the re-drilled hole, CG-018 was removed from the database and was not used in the estimate.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 206

 

Individual drillhole tables (collar, survey, assay, etc.) were merged to create one single master de-surveyed drillhole file in Datamine Studio RMTM. The processing to create this file splits assay intervals to allow for all records in all drilling tables to be included in one single file.

 

Values in Table 11-7 are based on analysis of this master file; counts will differ when compared with the original data due to these splits.

 

Table 11-7: Santa Cruz Deposit Domain, Assays by Cu Grade Sub-Domain

 

Santa Cruz
Domain
Sub-
Domain
Sample
Count
Total
Cu
Acid Soluble
Cu
Cyanide Soluble
Cu
Mo
Exotic LG (0.5%) 555 555 322 211 292
HG (2.0%) 136 136 136 78 106
Oxide LG (0.5%) 4,765 4,765 3,588 2,662 2,949
HG (2.0%) 1,315 1,315 1,301 835 913
Chalcocite Enriched LG (0.5%) 828 828 770 692 609
MG (1.0%) 751 751 746 704 491
Primary LG (0.5%) 5,988 5,988 5,208 2,817 3,370
HG (1.5%) 351 351 351 209 184
Background 8,783 8,783 4,920 3,423 5,349
Total 23,472 23,472 17,342 11,631 14,263
 
Texaco Domain Sub-
Domain
Sample
Count
Total
Cu
Acid Soluble
Cu
Cyanide Soluble
Cu
Mo
Oxide LG (0.5%) 190 190 106 98 86
MG (1.0%) 32 32 11 4 4
Chalcocite Enriched MG (1.0%) 194 194 75 122 60
Primary LG (0.5%) 842 842 463 454 427
MG (1.0%) 150 150 135 128 135
Total 1,408 1,408 790 806 712
 
East Ridge
Domain
Sub-
Domain
Sample
Count
Total
Cu
Acid Soluble
Cu
Cyanide Soluble
Cu
Mo
Oxide LG (0.5%) 1,078 1,078 n/a n/a 67
MG (1.0%) 310 310 n/a n/a 18
Total 1,388 1,388 n/a n/a n/a

 

Source: Nordmin, 2023

 

Figure 11-8 to Figure 11-13 provide the data analysis for the total Cu for all low-grade (LG) domains at Santa Cruz, the primary LG domain at Texaco, and the oxide LG domain at East Ridge.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 207

 

 

 

 

 

Source: Nordmin, 2023

 

Figure 11-8: Histogram and Log Probability Plots for Santa Cruz Exotic Cu LG Sub-Domain

 

September 2023

SEC Technical Report Summary – Santa CruzPage 208

 

 

 

 

 

Source: Nordmin, 2023

 

Figure 11-9: Histogram and Log Probability Plots for Santa Cruz Oxide Cu LG Sub-Domain

 

September 2023

SEC Technical Report Summary – Santa CruzPage 209

 

 

 

 

 

Source: Nordmin, 2023

 

Figure 11-10: Histogram and Log Probability Plots for Santa Cruz Chalcocite Enriched Cu LG Sub-Domain

 

September 2023

SEC Technical Report Summary – Santa CruzPage 210

 

 

 

 

 

Source: Nordmin, 2023

 

Figure 11-11: Histogram and Log Probability Plots for Santa Cruz Primary Cu LG Sub-Domain

 

September 2023

SEC Technical Report Summary – Santa CruzPage 211

 

 

 

 

 

Source: Nordmin, 2023

 

Figure 11-12: Histogram and Log Probability Plots for Texaco Primary Cu LG Sub-Domain

 

September 2023

SEC Technical Report Summary – Santa CruzPage 212

 

 

 

 

 

Source: Nordmin, 2023

 

Figure 11-13: Histogram and Log Probability Plots for East Ridge Oxide Cu LG Sub-Domain

 

September 2023

SEC Technical Report Summary – Santa CruzPage 213

 

11.4Data Preparation

 

Prior to grade estimation, the data was prepared in the following matter:

 

·All drillhole assays that intersected a wireframe within each domain were assigned a set of codes representative of the domain, wireframe number, and mineralization type.
·The drillhole assay data was combined by Datamine Studio RMTM to a single static drillhole file, which was then “flagged” to intersecting Cu mineralization Sub-Domains outlined by the wireframe coding process.
·HG outlier assays in each domain were reviewed, and top cutting (capping) was applied where necessary and applicable.

 

11.4.1Assay Intervals at Minimum Detection Limits

 

Table 11-8 summarizes the assays at minimum detection in the drillhole database. The assay database provided to Nordmin by IE contained appropriately substituted half-minimum detection assay values for the current lab and analytical method.

 

Table 11-8: Assays at Minimum Detection

 

Field Count Minimum Detection
Limit
Count at
Minimum
Detection Limit
% at Minimum
Detection Limit
Santa Cruz Deposit
Cu Total (%) 21,898 0.0005/0.0025 8 0.04%
Acid Soluble Cu (%) 15,859 0.0005 155 0.98%
Cyanide Soluble Cu (%) 10,278 0.0005 343 3.34%
Mo (%) 13,193 0.0002 566 4.29%
East Ridge and Texaco Deposit
Cu Total (%) 1,792 0.0002/0.0005 11 0.61%
Acid Soluble Cu (%) 787 0.0025 171 21.72%
Cyanide Soluble Cu (%) 893 0.0025 20 2.24%
Mo (%) 798 0.0002/0.0005 9 1.13%

 

Source: Nordmin, 2023

 

11.4.2Outlier Analysis and Capping

 

Grade outliers that are much higher than the general population of assays have the potential to bias (inflate) the quantity of metal estimated in a block model. Geostatistical analysis using X-Y scatter plots, cumulative probability plots, and decile analysis was used by Nordmin to analyze the raw drillhole assay data for each domain to determine appropriate grade capping. Statistical analysis was performed independently on all Sub-Domains. After capping, the resulting change to the overall mean grades is insignificant at the Santa Cruz Deposit. Cap values for each deposit are described in Table 11-9.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 214

 

Table 11-9: Santa Cruz, Texaco, and East Ridge Capping Values

 

Santa Cruz Deposit
Domains Zone Total Copper % Acid-Soluble Cu % Cyanide-Soluble Cu % Mo
Exotic LG 10.00 No cap No cap No cap
HG 2.50 No cap No cap No cap
Oxide LG No cap No cap No cap No cap
HG 11.00 No cap No cap No cap
Chalcocite Enriched LG No cap No cap No cap No cap
MG No cap No cap No cap No cap
Primary LG No cap 4.00 No cap No cap
HG No cap No cap No cap No cap
Background 2.50 1.00 2.00 0.11
Texaco Deposit
Domains Zone Total Copper % Acid-Soluble Cu % Cyanide-Soluble Cu % Mo
Oxide LG 4.00 No cap 9.00 0.10
MG No cap No cap No cap No cap
Chalcocite MG No cap No cap No cap No cap
Primary LG No cap 3.50 No cap No cap
MG No cap No cap No cap No cap
East Ridge Deposit
Domains Zone Total Copper % Acid-Soluble Cu % Cyanide-Soluble Cu % Mo
Oxide LG1 No cap No cap No cap No cap
LG2 8.00 5.00 5.00 No cap
LG3 No cap No cap No cap No cap
Background 3.00 1.00 2.00 No cap

 

Source: Nordmin, 2023

 

11.4.3Compositing

 

Compositing of assays is a technique used to give each assay a relatively equal length and therefore reduce the potential for bias due to uneven assay lengths; it prevents the potential loss of assay data and reduces the potential for grade bias due to the possible creation of short and potentially high-grade composites that tend to be situated along the edge of a wireframe contact when using a fixed length.

 

The raw assay data was found to have a relatively narrow range of assay lengths. Assays captured within all wireframes were composited to 3.0 m regular intervals based on the observed modal distribution of assay lengths, which supports a 5.0 m x 5.0 m x 5.0 m block model (with sub-blocking). An option to use a slightly variable composite length was chosen to allow for backstitching shorter composites that are located along the edges of the composited interval. All composite assays were generated within each mineral lens with no overlaps along boundaries. The composite assays were validated statistically to ensure there was no loss of data or change to the mean grade of each assay population (Table 11-10).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 215

 

Table 11-10: Santa Cruz Deposit Composite Analysis

 

Santa Cruz Domains Sub-Domain Number of Composites
Exotic LG 526
HG 83
Oxide LG 4,064
HG 821
Chalcocite Enriched LG 483
MG 493
Primary LG 4,332
HG 251
Background n/a 9,883
Texaco Domains Sub-Domain Number of Composites
Oxide LG 141
MG 29
Chalcocite Enriched MG 147
Primary LG 598
MG 69
East Ridge Domains Sub-Domain Number of Composites
Oxide LG 1,087
MG 309

 

Source: Nordmin, 2023

 

11.4.4Specific Gravity

 

A total of 2,639 SG measurements from seventy-four diamond drillholes exist from the Santa Cruz Deposit. Measurements were calculated using the weight in air versus the weight in water method (Archimedes), by applying the following formula:

 

 

 

Nordmin determined that the required amount and distribution of SG measurements for direct estimation within the block model was not met. SG values were assigned to blocks based on Sub-Domains as seen in East Ridge and Texaco employ SG values from Santa Cruz as the two deposits lacked sufficient samples to calculate a local average. Table 11-11 gives average SG values for Santa Cruz geologic domains.

 

Table 11-11: SG Values Measured for the Santa Cruz Deposit by Geologic Domain

 

Santa Cruz Domain Sub-Domain Average SG
Exotic LG 2.52
HG 2.38
Oxide LG 2.48
HG 2.53
Chalcocite Enriched LG 2.49
MG 2.54
Primary LG 2.53
HG 2.51
Background 2.50

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 216

 

11.4.5Block Model Strategy and Analysis

 

A series of upfront test modeling was completed to define an estimation methodology to meet the following criteria:

 

·Representative of the Santa Cruz Deposit geological and structural controls
·Accounts for the variability of grade, orientation, and continuity of mineralization
·Controls the smoothing (grade spreading) or grades and the influence of outliers
·Accounts for most of the mineralization within the Santa Cruz Deposit
·Is robust and repeatable within the mineral domains
·Supports multiple domains

 

Multiple test scenarios were evaluated to determine the optimum processes and parameters to use to achieve the stated criteria. Each scenario was based on nearest neighbour (NN), inverse distance squared (ID2), inverse distance cubed (ID3), and ordinary kriging (OK) interpolation methods (only for the Santa Cruz Deposit). All test scenarios were evaluated based on global statistical comparisons, visual comparisons of composite assays versus block grades, and the assessment of overall smoothing. Based on the results of the testing, it was determined that the final resource estimation methodology would constrain the mineralization by using hard wireframe boundaries to control the spread of mineralization. OK was selected as the best and most applicable interpolation method for the Santa Cruz Deposit, and ID3 was selected as the best and most applicable interpolation method for the East Ridge and Texaco Deposits.

 

11.4.6Assessment of Spatial Grade Continuity

 

Datamine, Leapfrog Geo, and Leapfrog Edge were used to determine the geostatistical relationships of the Santa Cruz Deposit. Texaco and East Ridge Deposits did not have sufficient data density to perform variography. Independent variography was performed on composite data for each domain. Experimental grade variograms were calculated from the capped/composited assay data for each element to determine the approximate search ellipse dimensions and orientations.

 

The following was considered for each analysis:

 

·Downhole variograms were created and modeled to define the nugget effect.
·Experimental semi-variograms were calculated to determine directional variograms for the strike and down dip orientations.
·Variograms were modeled using an exponential model with practical range.
·Directional variograms were modeled using the nugget defined in the downhole variography, and the ranges for the along strike, perpendicular to strike, and down dip directions. Variograms outputs were re-oriented to reflect the orientation of the mineralization.

 

Some domains share variography parameters due to similar behavior. The variography used for Santa Cruz is provided in Table 11-12 Semi-variograms for several Cu domains are provided in Figure 11-14 to Figure 11-18.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 217

 

Table 11-12: Santa Cruz Deposit Variography Parameters

 

Domain   Rotation Angles     Structure 1   Structure 2
Type  1 2 3 Axes Nugget C1 Range 1 Range 2 Range 3 C2 Range 1 Range 2 Range 3
Exotic TCu 30 90 140 Z-Y-Z 0.20 0.26 130 90 35 0.54 300 130 50
ASCu 30 90 140 Z-Y-Z 0.20 0.26 190 100 20 0.54 233 125 44
CNCu 30 90 140 Z-Y-Z 0.25 0.75 290 125 35 0 n/a
Oxide TCu 90 40 60 Z-Y-Z 0.15 0.52 15 126 60 0.33 175 200 95
ASCu 90 40 30 Z-Y-Z 0.15 0.50 40 30 40 0.35 145 100 100
CNCu 90 30 20 Z-Y-Z 0.13 0.32 150 30 10 0.55 150 230 70
Chalcocite Enriched TCu 35 60 75 Z-Y-Z 0.25 0.75 210 200 45 0 n/a
ASCu 35 60 135 Z-Y-Z 0.13 0.87 250 245 35 0 n/a
CNCu 35 60 80 Z-Y-Z 0.20 0.80 295 225 21 0 n/a
Primary TCu 30 180 45 Z-Y-Z 0.20 0.37 130 160 80 0.43 470 195 200
ASCu 30 0 120 Z-Y-Z 0.20 0.37 200 100 50 0.43 420 200 100
CNCu 20 150 135 Z-Y-Z 0.12 0.45 100 55 45 0.43 370 310 265
Background TCu 90 30 150 Z-Y-Z 0.12 0.35 20 133 35 0.53 780 800 430
ASCu 90 30 150 Z-Y-Z 0.13 0.87 330 195 45 0 n/a
CNCu 90 30 20 Z-Y-Z 0.11 0.89 355 220 32 0.53 n/a

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 218

 

 

 

Source: Nordmin, 2023

 

Figure 11-14: Exotic Domain Total Cu Variogram

 

 

 

Source: Nordmin, 2023

 

Figure 11-15: Oxide Domain Total Cu Variogram

 

September 2023

SEC Technical Report Summary – Santa CruzPage 219

 

 

 

Source: Nordmin, 2023

 

Figure 11-16: Oxide Domain Acid Soluble Cu Variogram

 

 

 

Source: Nordmin, 2023

 

Figure 11-17: Chalcocite Enriched Domain Acid Soluble Cu Variogram

 

September 2023

SEC Technical Report Summary – Santa CruzPage 220

 

 

 

Source: Nordmin, 2023

 

Figure 11-18: Primary Domain Total Cu Variogram

 

11.4.7Block Model Definition

 

The block model shape and size are typically a function of the geometry of the deposit, the density of assay data, drillhole spacing, and the selected mining unit. Taking this into consideration, the block model was defined with parent blocks at 5.0 m x 5.0 m x 5.0 m (N-S x E-W x Elevation). All three deposits use the same model definition parameters. The block model prototype parameters are listed in Table 11-13. All three deposits employed the same prototype parameters.

 

Table 11-13: Santa Cruz, Texaco, and East Ridge Block Model Definition Parameters

 

Item Block Origin
(m)
Block Max
(m)
Block Dimension
(m)
Number of Parent
Blocks
Minimum Sub-
Block (m)
Easting 414,200 421,500 5 1,460 1.25
Northing 3,637,800 3,644,800 5 1,400 1.25
Elevation -1,200 500 5 340 1.25

 

Source: Nordmin, 2023

 

All mineral Sub-Domain wireframe volumes were filled with blocks using the parameters described in Table 11-13. Block volumes were compared to the mineral sub-domain wireframe volumes to confirm there were no significant differences. Block volumes for all sub-domains were found to be within reasonable tolerance limits for all mineral sub-domain volumes. Sub-blocking was allowed to maintain the geological interpretation and accommodate the HG, MG, and LG Sub-Domains (wireframes), the lithological SG, and the category application. Sub-blocking has been allowed to the following minimums:

 

·5.0 m x 5.0 m x 5.0 m blocks are sub-blocked two-fold to 1.25 m x 1.25 m in the N to S and E to W directions with a variable elevation calculated based on the other sizes.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 221

 

The block models were not rotated, and it was not necessary to clip them to topography due to their depth. The resource estimation was conducted using Datamine Studio RMTM version 1.12.113.0 within the NAD 83 UTM Zone 12 N projection grid.

 

11.4.8Interpolation Method

 

The Santa Cruz Deposit block model was estimated using NN, ID2, ID3, and OK interpolation methods for global comparisons and validation purposes. The OK method was used for the Mineral Resource Estimate; it was selected over ID2, ID3, and NN as the OK method was the most representative approach to controlling the smoothing of grades. The Santa Cruz Deposit was estimated using NN, ID2, ID3, OK, and the OK method was used for the Mineral Resource Estimate. The Texaco and East Ridge block models were estimated using NN, ID2, and ID3, and the ID3 method was used for the mineral estimate for the Texaco and East Ridge Deposits.

 

11.4.9Search Strategy

 

Zonal controls for all three deposits were used to constrain the grade estimates to within each LG, MG, and HG wireframe. These controls prevented the assays from individual domain wireframes from influencing the block grades of one another, acting as a “hard boundary” between the Sub-Domains. For instance, the composites identified within the Background total Cu wireframe were used to estimate the Background total Cu, and all other composites were ignored during the estimation. A “soft boundary” was used in the LG Oxide Sub-Domain, where composites from the HG model were included with the LG composites for the purposes of LG Oxide Sub-Domain estimation.

 

Search orientations for each deposit were used for estimation of the block model and were based on the shape of the modeled mineral domains; see Table 11-14 (Santa Cruz Deposit), Table 11-15 (Texaco Deposit), and Table 11-16 (East Ridge Deposit). A total of three nested searches were performed on all Sub-Domains. Table 11-14 to Table 11-16 display search parameters used in the estimation of the Santa Cruz, Texaco, and East Ridge Deposit mineral resource estimates. The search distances were based upon the variography ranges outlined in Table 11-12. The search radius of the first search was based upon the first structure of the variogram, the second search is generally two times the first search pass, and the third search pass is 8 times the initial search for the purposes of block model filling – note that this third-pass material was not considered for anything other than Inferred Categorization. Search strategies used an ellipsoidal search with a defined overall minimum and maximum number of composites as well as a maximum number of composites per hole for each block. Blocks which did not meet these criteria did not estimate and do not appear in the MRE.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 222

 

Table 11-14: Santa Cruz Block Model Search Parameters

 

Santa Cruz Deposit
Total Copper
      Pass 1 Pass 2 Pass 3
  Search Rotation Search Axes Search Distances Comps Search Distances Comps Search Distances Comps
Domain Rot 1 Rot 2 Rot 3 Axis 1 Axis 2 Axis 3 Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Exotic (LG/HG) -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Oxide LG -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 2 8 2 400 640 240 2 8 2
Oxide HG -12 -11 -5 3 2 3 50 80 30 3 10 2 100 160 60 3 8 2 400 640 240 2 8 2
Chalcocite (LG/MG) -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Primary LG -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Primary HG -12 12 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Background -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Acid Soluble Copper
      Pass 1 Pass 2 Pass 3
  Search Rotation Search Axes Search Distances Comps Search Distances Comps Search Distances Comps
Domain Rot 1 Rot 2 Rot 3 Axis 1 Axis 2 Axis 3 Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Exotic (LG/HG) -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Oxide LG -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 2 8 2 400 640 240 2 8 2
Oxide HG -12 -11 -5 3 2 3 50 80 30 3 10 2 100 160 60 3 8 2 400 640 240 2 8 2
Chalcocite (LG/MG) -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 300 480 180 2 8 2
Primary LG -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Primary HG -12 12 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Background -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 300 480 180 2 8 2
Cyanide Soluble Copper
      Pass 1 Pass 2 Pass 3
  Search Rotation Search Axes Search Distances Comps Search Distances Comps Search Distances Comps
Domain Rot 1 Rot 2 Rot 3 Axis 1 Axis 2 Axis 3 Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Exotic (LG/HG) -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Oxide LG -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Oxide HG -12 -11 -5 3 2 3 50 80 30 3 10 2 100 160 60 2 8 2 400 640 240 2 8 2
Chalcocite (LG/MG) -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Primary LG -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Primary HG -12 12 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2
Background -12 -11 -5 3 2 3 50 80 30 3 8 2 100 160 60 3 8 2 400 640 240 2 8 2

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 223

 

Table 11-15: Texaco Block Model Search Parameters

 

Texaco Deposit
Total Copper
      Pass 1 Pass 2 Pass 3
  Search Rotation Search Axes Search Distances Comps Search Distances Comps Search Distances Comps
Domain Rot 1 Rot 2 Rot 3 Axis 1 Axis 2 Axis 3 Dist 1 Dist 2 Dist 3 Min Max Max
Per Hole
Dist 1 Dist 2 Dist 3 Min Max Max
Per Hole
Dist 1 Dist 2 Dist 3 Min Max

Max
Per Hole

Oxide (LG/MG) 60 8 15 3 2 1 50 80 30 3 8 2 100 160 60 3 8 2 350 480 180 3 8 2
Chalcocite (LG/MG) 60 8 15 3 2 1 50 80 30 3 8 2 100 160 60 3 8 2 350 480 180 3 8 2
Primary LG 60 8 15 3 2 1 50 80 30 3 8 2 87.5 140 52.5 3 8 2 150 240 90 3 8 2
Primary MG 85 17 -8 3 2 1 50 80 30 3 8 2 100 160 60 3 8 2 350 480 180 3 8 2
Background 60 8 15 3 2 1 50 80 30 3 8 2 100 160 60 3 8 2 350 480 180 3 8 2
Acid Soluble Copper
      Pass 1 Pass 2 Pass 3
  Search Rotation Search Axes Search Distances Comps Search Distances Comps Search Distances Comps
Domain Rot 1 Rot 2 Rot 3 Axis 1 Axis 2 Axis 3 Dist 1 Dist 2 Dist 3 Min Max Max
Per Hole
Dist 1 Dist 2 Dist 3 Min Max Max
Per Hole
Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Oxide (LG/MG) 60 8 15 3 2 1 50 80 30 2 10 2 100 160 60 2 8 2 350 480 180 3 8 2
Chalcocite (LG/MG) 60 8 15 3 2 1 60 45 30 3 8 2 120 90 60 3 8 2 360 270 180 3 8 2
Primary LG 60 8 15 3 2 1 50 80 30 3 8 2 75 120 45 3 8 2 100 160 60 3 8 2
Primary MG 75 12 10 3 2 1 50 80 30 3 8 2 100 160 60 3 8 2 350 480 180 3 8 2
Background 60 8 15 3 2 1 60 45 30 3 8 2 120 90 60 3 8 2 360 270 180 3 8 2
Cyanide Soluble Copper
      Pass 1 Pass 2 Pass 3
  Search Rotation Search Axes Search Distances Comps Search Distances Comps Search Distances Comps
Domain Rot 1 Rot 2 Rot 3 Axis 1 Axis 2 Axis 3 Dist 1 Dist 2 Dist 3 Min Max Max
Per Hole
Dist 1 Dist 2 Dist 3 Min Max Max
Per Hole
Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Oxide (LG/MG) 60 8 15 3 2 1 50 80 30 3 8 2 100 160 60 3 8 2 350 480 180 3 8 2
Chalcocite (LG/MG) 60 8 15 3 2 1 40 50 20 3 8 2 60 75 30 3 8 2 240 350 120 3 8 2
Primary LG 60 8 15 3 2 1 50 80 30 3 8 2 100 160 60 3 8 2 - - - - - -
Primary MG 60 12 10 3 2 1 50 80 30 3 8 2 100 160 60 3 8 2 350 480 180 3 8 2
Background 60 8 15 3 2 1 40 50 20 3 8 2 75 120 30 3 8 2 240 350 120 3 8 2

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 224

 

Table 11-16: East Ridge Block Model Search Parameters

 

Texaco Deposit
Total Copper
      Pass 1 Pass 2 Pass 3
  Search Rotation Search Axes Search Distances Comps Search Distances Comps Search Distances Comps
Domain Rot 1 Rot 2 Rot 3 Axis 1 Axis 2 Axis 3 Dist 1 Dist 2 Dist 3 Min Max Max
Per Hole
Dist 1 Dist 2 Dist 3 Min Max Max
Per Hole
Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Oxide (LG/MG) -40 10 -9 3 2 1 50 80 30 3 8 2 100 160 60 3 8 2 450 640 240 3 8 2
Background -40 10 -9 3 2 1 50 80 30 3 8 2 100 160 60 3 8 2 600 960 360 3 8 2
Acid Soluble Copper
      Pass 1 Pass 2 Pass 3
  Search Rotation Search Axes Search Distances Comps Search Distances Comps Search Distances Comps
Domain Rot 1 Rot 2 Rot 3 Axis 1 Axis 2 Axis 3 Dist 1 Dist 2 Dist 3 Min Max Max
Per Hole
Dist 1 Dist 2 Dist 3 Min Max Max
Per Hole
Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Oxide (LG/MG) 60 8 15 3 2 1 50 80 30 3 8 2 100 160 60 3 8 2 350 480 180 3 8 2
Background 60 8 15 3 2 1 60 45 30 3 8 2 120 90 60 3 8 2 360 270 180 3 8 2
Cyanide Soluble Copper
      Pass 1 Pass 2 Pass 3
  Search Rotation Search Axes Search Distances Comps Search Distances Comps Search Distances Comps
Domain Rot 1 Rot 2 Rot 3 Axis 1 Axis 2 Axis 3 Dist 1 Dist 2 Dist 3 Min Max Max
Per Hole
Dist 1 Dist 2 Dist 3 Min Max Max
Per Hole
Dist 1 Dist 2 Dist 3 Min Max

Max

Per Hole

Oxide (LG/MG) 60 8 15 3 2 1 50 80 30 3 8 2 100 160 60 3 8 2 350 480 180 3 8 2
Background 60 8 15 3 2 1 40 50 20 3 8 2 60 75 30 3 8 2 240 350 120 3 8 2

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 225

 

11.5Block Model Validation

 

The Santa Cruz Deposit block model was estimated using NN, ID2, ID3, and OK interpolation methods for global comparisons and validation purposes. The OK method was used for the MRE; it was selected over ID2, ID3, and NN as the OK method was the most representative approach to controlling the smoothing of grades. The Texaco and East Ridge Deposit block models were estimated using NN, ID2, and ID3. The ID3 method was used for the mineral estimate for the Texaco and East Ridge Deposits and was used in the MRE.

 

11.5.1Visual Comparison

 

The validation of the interpolated block model was assessed by using visual assessments and validation plots of block grades versus capped assay grades and composites. The review demonstrated a good comparison between local block estimates and nearby samples without excessive smoothing in the block model.

 

Figure 11-19 through Figure 11-35 are the block model validation images, displaying total Cu, acid soluble Cu, or cyanide soluble Cu grades in the block model and drillholes for Santa Cruz, Texaco, and East Ridge.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 226

 

 

 

Source: Nordmin, 2023

 

Figure 11-19: Santa Cruz Block Model Validation, Total Cu, Cross-section

 

 

 

 

Source: Nordmin, 2023

 

Figure 11-20: Santa Cruz Block Model Validation, Acid Soluble Cu, Cross-section, +/-50 m Width

 

September 2023

SEC Technical Report Summary – Santa CruzPage 227

 

 

Source: Nordmin, 2023

 

Figure 11-21: Santa Cruz Block Model Validation, Cyanide Soluble Cu, Cross-section +/-50 m Width

 

 

Source: Nordmin, 2023

 

Figure 11-22: Santa Cruz Block Model Validation, Total Cu, Cross-section +-/50 m Width

 

September 2023

SEC Technical Report Summary – Santa CruzPage 228

 

 

Source: Nordmin, 2023

 

Figure 11-23: Santa Cruz Block Model Validation, Acid Soluble Cu, Cross-section +/-50 m Width

 

 

Source: Nordmin, 2023

 

Figure 11-24: Santa Cruz Block Model Validation, Cyanide Soluble Cu, Cross-section +/-50 m Width

 

September 2023

SEC Technical Report Summary – Santa CruzPage 229

 

 

Source: Nordmin, 2023

 

Figure 11-25: Texaco Block Model Validation, Total Cu, Cross-section +/-50 m Width

 

 

Source: Nordmin, 2023

 

Figure 11-26: Texaco Block Model Validation, Acid Soluble Cu, Cross-section +/-50 m Width

 

September 2023

SEC Technical Report Summary – Santa CruzPage 230

 

 

Source: Nordmin, 2023

 

Figure 11-27: Texaco Block Model Validation, Cyanide Soluble Cu, Cross-section +/-50 m Width

 

 

Source: Nordmin, 2023

 

Figure 11-28: East Ridge Block Model Validation, Total Cu, Cross-section +/-50 m Width

 

September 2023

SEC Technical Report Summary – Santa CruzPage 231

 

 

Source: Nordmin, 2023

 

Figure 11-29: East Ridge Block Model Validation, Acid Soluble Cu, Cross-section +/-50 m Width

 

 

Source: Nordmin, 2023

 

Figure 11-30: East Ridge Block Model Validation, Cyanide Soluble Cu, Cross-section +/- 50 m Width

 

September 2023

SEC Technical Report Summary – Santa CruzPage 232

 

11.5.2Swath Plots

 

A series of swath plots were generated for total Cu, acid soluble Cu, and cyanide soluble Cu from slices throughout each deposit for various domains. They compare the block model grades for NN, ID2, ID3, and OK to the drillhole composite grades to evaluate any potential local grade bias. A review of the swath plots did not identify bias in the model that is material to the Mineral Resource Estimate, as there was a strong overall correlation between the block model grade and the capped composites used in the Mineral Resource Estimate. Figure 11-31 and Figure 11-32 are the swath plots for Santa Cruz Deposit total Cu, acid soluble Cu, and cyanide soluble Cu, Figure 11-33 is for the Texaco Deposit, and Figure 11-34 is for the East Ridge Deposit.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 233

 

 

 

 

 

 

 

Source: Nordmin, 2023

 

Figure 11-31: Santa Cruz Oxide Domain Swath Plots, Total Cu % in X, Y, and Z Directions

 

September 2023

SEC Technical Report Summary – Santa CruzPage 234

  

 

 

 

 

Source: Nordmin, 2023

 

Figure 11-32: Santa Cruz Oxide and Chalcocite Domain Swath Plots, Acid Soluble and Cyanide Soluble Cu %

 

September 2023

SEC Technical Report Summary – Santa CruzPage 235

 

 

 

 

 

 

 

Source: Nordmin, 2023

 

Figure 11-33: Texaco Primary Domain Swath Plot, Total Cu %

 

September 2023

SEC Technical Report Summary – Santa CruzPage 236

 

 

 

 

 

 

Source: Nordmin, 2023

 

Figure 11-34: East Ridge Oxide Domain Total Cu, Acid Soluble, and Cyanide Soluble Swath Plots

 

September 2023

SEC Technical Report Summary – Santa CruzPage 237

 

11.6Mineral Resource Classification

 

The Mineral Resource Estimate was classified in accordance with S-K 1300 definitions. Mineral Resource classifications were assigned to broad regions of the block model based on the Nordmin QP’s confidence and judgment related to geological understanding, continuity of mineralization in conjunction with data quality, spatial continuity based on variography, estimation parameters, data density, and block model representativeness.

 

Classification (Indicated and Inferred) was applied to the Santa Cruz, Texaco, and East Ridge Deposits based on a full review that included the examination of drill spacing, visual comparison, kriging variance, distance to nearest composite, and search volume estimation (the estimation pass in which each block was populated) along with the search ellipsoid ranges. Collectively this information was used to produce an initial classification script followed by manual wireframes application to further limit the mineral resource classification.

 

Figure 11-35 and Figure 11-36 demonstrate the resource classification in section throughout the Santa Cruz, Texaco, and East Ridge Deposits.

 

The areas of greatest uncertainty are attributed to Inferred Resources. These are areas with limited drilling or very large drill spacing (greater than 100 m). Due to lack of drilling density it is difficult to be confident in the continuity of mineralization and is therefore classified as Inferred and may be upgraded via infill drilling to support mineralization continuity. Indicated Resources are resources that have consistent drill spacing, low to moderate kriging variance and a visual comparison. In the Santa Cruz Deposit the drill spacing that supports the Indicated Resource classification constitutes approximately 80 m to 100 m. There is the possibility for Indicated Resources to be upgraded to Measured Resources via additional infill drilling that would reduce the drill spacing to < 25 m. Currently, none of the deposits have a Measured Resource. Additional uncertainty lies in the historical drill measurements including logging, assaying, and surveying. The 2021 twin drilling program conducted by IE outlined in Section 7.3.3 and 9.3 has demonstrated overall grade continuity, location, and continuity between intercepts. There is the potential for unknown errors within the database which could affect the size and quantity of Indicated and Inferred Mineral Resources.

 

While most of the Texaco Deposit is classified as Inferred, there is a small portion of Indicated Resource. There are three IE drilled holes in Texaco which have served to prove depth, continuity, and grade of the historic drilling. The East Ridge Deposit is currently classified as Inferred as the area is defined by historical drilling which has yet to be validated with modern drilling. This work is forthcoming and will help to improve resource class confidence in subsequent iterations.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 238

 

 

 

Source: Nordmin, 2023

 

Figure 11-35: Plan section Demonstrating Resource Classification, -250 m, -350 m, and -450 m Depth, with North Upward

 

September 2023

SEC Technical Report Summary – Santa CruzPage 239

 

 

Source: Nordmin, 2023

 

Figure 11-36: Texaco (left) and East Ridge (right) Plan Sections Demonstrating Resources Classification, With North Upward

 

11.7Copper Pricing

 

Mineral Resources were estimated based on a long-term copper price of US$3.70/lb.

 

Nordmin notes that US$3.70/lb copper price is approximately equal to current spot pricing. In the opinion of Nordmin, this price is generally in-line with pricing over the last 3 years and forward-looking pricing is appropriate for use during an Initial Assessment of the Project with an estimated 20-year long mine life. The values presented here may differ from the economic model, however Nordmin is of the opinion that the differences are not material. Additional commentary on selected pricing is included in Section 16.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 240

 

11.8Reasonable Prospects of Economic Extraction

 

The Mineral Resource was created using Datamine Studio RMTM version 1.7.100.0 software to create the block models for the Santa Cruz, Texaco, and East Ridge Deposits, and Deswik.CADTM 2022.1 and Deswik.SOTM 4.1 for stope optimization.

 

To demonstrate reasonable prospects for economic extraction for the Santa Cruz, Texaco, and East Ridge Mineral Resource Estimates, representational minimum mining unit shapes were created using Deswik’s minimum MSO tool. This MSO tool constrains and evaluates the block model based on economic and geometric parameters, shown in Table 11-17, generating potentially mineable shapes. The Santa Cruz Deposit was assumed to be developed as a long-life operation consisting of an underground longhole stoping plan, with an initial mining rate of 15,000 t/d to produce a Cu concentrate. The Texaco Deposit was assumed to be a longhole stoping plan at 7,000 t/d, while East Ridge was assumed to be a room & pillar plan at 3,500 t/d. The Mineral Resource Estimate comprises of all material found within the MSO wireframes generated at a cut-off of 0.70% Cu for Santa Cruz, 0.80% Cu cut-off for Texaco, and 0.90% Cu cut-off for East Ridge, including material below cut-off.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 241

 

Table 11-17: Input Parameter Assumptions

 

    December 2022 MRE
* All prices in US$   Santa Cruz Texaco East Ridge
    30m Longhole 20m Longhole Room & Pillar
  Units Flotation Flotation Flotation
Key Criteria and Inputs        
Assumed Production t/d 15,000 7,000 3,500
Annual Tonnage t/y 5,250,000 2,450,000 1,225,000
Annual Cathode Production tonnes Cu/year 30,104 4,836 7,945
  lbs Cu/year 66,366,176 10,662,107 17,516,319
% of Total % 49.6% 17.4% 50.7%
Annual Copper in Concentrate tonnes Cu/year 30,597 23,030 7,715
  lbs Cu/year 67,454,146 50,771,938 17,008,599
% of Total % 50.4% 82.6% 49.3%
Copper Price US$/lb US$3.70 US$3.70 US$3.70
Payable Copper % 96.0% 96.0% 96.0%
         
On-site Costs        
Mining Costs - Direct US$/t Proc. $24.50 $31.50 $40.00
Mining Costs - G&A US$/t Proc. $4.00 $4.00 $4.00
         
Processing - Concentrator US$/t Proc. $8.40 $8.40 $8.40
Refining - SX-EW $/lb Cu Cath $0.180 $0.180 $0.180
  US$/t Proc. $2.28 $1.50 $2.57
         
Processing - Laboratory/Water Treatment US$/t Proc. $0.50 $0.50 $0.50
Processing - G&A Costs US$/t Proc. $3.00 $3.00 $3.00
         
Total On-site Costs US$/t Proc. $42.68 $48.90 $58.47
         
Off-site and Downstream Costs        
Cathode Shipping US$/t Proc. $0.51 $0.17 $0.57
Concentrate Shipping US$/t Proc. $1.259 $2.031 $1.361
Concentrate Smelting & Refining US$/t Proc. $1.529 $2.466 $1.652
         
Total Off-site and Downstream Costs US$/t Proc. $3.29 $4.67 $3.58
         
Royalties        
         
Average Royalties %NSR 6.96% 6.06% 5.00%
  US$/t Proc. $5.95 $5.08 $4.72
         
Recoveries/Dilution        
Mining Dilution % 0.0% 0.0% 0.0%
Mining Recovery % 100.0% 100.0% 100.0%
Processing Recovery % 94.0% 94.0% 94.0%
         
MRE Selected Copper in situ Cut-off % 0.70% 0.80% 0.90%

 

Source: Nordmin, 2023

 

See Section 11.7 for Copper Pricing

 

September 2023

SEC Technical Report Summary – Santa CruzPage 242

 

11.9Mineral Resource Estimate

 

Due to a lack of sample data as well as a bias in sampling for acid soluble Cu and cyanide soluble Cu within the Primary Domain, it was determined that the acid soluble Cu and cyanide soluble Cu estimation within the Primary Domain was not representative of the actual cyanide soluble Cu within the domain and has been removed from all reports and totals. Acid soluble Cu and cyanide soluble Cu was determined to be accurate within the Exotic Domain, Oxide Domain, and Chalcocite Enriched Domain. A plan view of the Deposits is shown in Figure 11-37. The Mineral Resource Estimate, which is exclusive of mineral reserves, can be found in Table 11-18.

 

 

Source: IE, 2023

 

Figure 11-37: Plan View of the Mineral Resource Envelopes

 

September 2023

SEC Technical Report Summary – Santa CruzPage 243

 

11.9.1Mineral Resource Estimate

 

Table 11-18: In Situ Santa Cruz Project Mineral Resource Estimates at 0.70% Cu cut-off for Santa Cruz, 0.80% Cu cut-off for Texaco, and 0.90% Cu Cut-off for East Ridge

 

Classification Deposit Mineralized
Material
(kt)
Mineralized
Material
(k ton)
Total
Cu
(%)
Total
Soluble
Cu
(%)
Acid
Soluble
Cu
(%)
Cyanide
Soluble
Cu
(%)
Total
Cu
(kt)
Total
Soluble
Cu
(kt)
Acid
Soluble
Cu
(kt)
Cyanide
Soluble
Cu
(kt)
Total
Cu
(Mlb)
Indicated Santa Cruz
(0.70%
COG)
223,155 245,987 1.24 0.82 0.58 0.24 2,759 1,824 1,292 533 6,083
Texaco
(0.80%
COG)
3,560 3,924 1.33 0.97 0.25 0.73 47 35 9 26 104
East Ridge
(0.90%
COG)
0 0 0.00 0 0.00 0.00 0 0 0 0 0
Inferred Santa Cruz
(0.70%
COG)
62,709 69,125 1.23 0.92 0.74 0.18 768 576 462 114 1,694
Texaco
(0.80%
COG)
62,311 68,687 1.21 0.56 0.21 0.35 753 348 132 215 1,660
East Ridge
(0.90%
COG)
23,978 26,431 1.36 1.26 0.69 0.57 326 302 164 137 718
Total                        
Indicated All Deposits 226,715 249,910 1.24 0.82 0.57 0.25 2,807 1,859 1,300 558 6,188
Inferred All Deposits 148,998 164,242 1.24 0.82 0.51 0.31 1,847 1,225 759 466 4,072

 

Source: Nordmin, 2023

 

Notes on Mineral Resources

 

The Mineral Resources in this Estimate were independently prepared, including estimation and classification, by Nordmin Engineering Ltd. and in accordance with the definitions for Mineral Resources in S-K 1300.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. This estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

Verification included multiple site visits to inspect drilling, logging, density measurement procedures and sampling procedures, and a review of the control sample results used to assess laboratory assay quality. In addition, a random selection of the drillhole database results was compared with the original records.

The Mineral Resources in this estimate for the Santa Cruz, East Ridge, and Texaco Deposits used Datamine Studio RMTM software to create the block models.

The Mineral Resources are current to December 31, 2022.

Underground-constrained Mineral Resources for the Santa Cruz Deposit are reported at a CoG of 0.70% total copper, Texaco Deposit are reported at a CoG of 0.80% total copper and East Ridge Deposit are reported at a CoG of 0.90% total copper. The CoG reflects total operating costs to define reasonable prospects for eventual economic extracted by conventional underground mining methods with a maximum production rate of 15,000 t/d. All material within mineable shape-optimized wireframes has been included in the Mineral Resource. Underground mineable shape optimization parameters include a long-term copper price of US$3.70/lb, process recovery of 94%, direct mining costs between US$24.50 to US$40.00/processed tonne reflecting various mining method costs (long hole or room and pillar), mining general and administration cost of US$4.00/t processed, onsite processing and SX/EW costs between US$13.40 to US$14.47/t processed, offsite costs between US$3.29 to US$4.67/t processed, along with variable royalties between 5.00% to 6.96% NSR and a mining recovery of 100%.

Specific Gravity was applied using weighted averages by Deposit Sub-Domain.

All figures are rounded to reflect the relative accuracy of the estimates, and totals may not add correctly.

Excludes unclassified mineralization located along edges of the Santa Cruz, East Ridge, and Texaco Deposits where drill density is poor.

Report from within a mineralization envelope accounting for mineral continuity.

Total soluble copper means the addition of sequential acid soluble copper and sequential cyanide soluble copper assays. Total soluble copper is not reported for the Primary Domain.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 244

 

11.9.2Santa Cruz Mineral Resource Estimate

 

The Santa Cruz Deposit Mineral Resource Estimate, which is exclusive of mineral reserves, is presented in Table 11-19.

 

Table 11-19: In Situ Santa Cruz Deposit Mineral Resource Estimate, 0.70% Total Cu CoG

 

 

Mineralized

Material

(kt)

Mineralized

Material

(k ton)

Total

Cu

(%)

Total

Soluble
Cu

(%)

Acid

Soluble
Cu

(%)

Cyanide

Soluble
Cu

(%)

Total

Cu

(kt)

Total

Soluble
Cu

(kt)

Acid

Soluble
Cu

(kt)

Cyanide

Soluble
Cu

(kt)

Total
Cu

(Mlb)

Santa Cruz Deposit
0.70% Cu COG 
Classification Domain
Indicated Exotic 4,993 5,504 1.79 1.59 1.46 0.13 90 79 73 6 198
Oxide 96,746 106,644 1.44 1.29 1.10 0.19 1,388 1,244 1,064 179 3,061

Chalcocite

Enriched

45,247 49,877 1.34 1.11 0.34 0.77 608 501 154 347 1,341
Primary 76,169 83,962 0.88 N/A N/A N/A 673 N/A N/A N/A 1,484
Inferred Exotic 5,690 6,273 1.61 1.28 1.17 0.11 91 73 67 6 201
Oxide 43,252 47,678 1.23 1.02 0.88 0.14 532 411 379 62 1,172

Chalcocite

Enriched

5,779 6,371 1.25 1.07 0.28 0.79 72 62 16 46 159
Primary 7,987 8,804 0.92 N/A N/A N/A 73 N/A N/A N/A 161
Total                        
Indicated All Domains 223,155 245,987 1.24 0.82 0.58 0.24 2,759 1,824 1,292 533 6,083
Inferred All Domains 62,709 69,125 1.23 0.92 0.74 0.18 768 576 462 114 1,694

 

Source: Nordmin, 2023

Note: Refer to notes on Table 11-18.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 245

 

11.9.3Texaco Mineral Resource Estimate

 

The Texaco Deposit Mineral Resource Estimate, which is exclusive of mineral reserves, is presented in Table 11-20.

 

Table 11-20: In Situ Texaco Deposit Mineral Resource Estimate, 0.80% Total Cu CoG

 

 

Mineralized

Material

Mineralized

Material

Total

Cu

Total

Soluble

Cu

Acid

Soluble

Cu

Cyanide

Soluble

Cu

Total

Cu

Total

Soluble

Cu

Acid

Soluble

Cu

Cyanide

Soluble

Cu

Total

Cu

Texaco Deposit
0.80% Cu COG
Classification Domain (kt) (k ton)  (%) (%) (%) (%) (kt) (kt) (kt) (kt) (Mlb)
Indicated Exotic 0 0 0.00 0.00 0.00 0.00 0 0 0 0 0
Oxide 747 823 1.09 1.00 0.62 0.38 8 7 5 3 18
Chalcocite Enriched 1,944 2,143 1.55 1.40 0.21 1.18 30 27 4 23 66
Primary 869 958 1.05 N/A N/A N/A 9 N/A N/A N/A 20
Inferred Exotic 0 0 0.00 0.00 0.00 0.00 0 0 0 0 0
Oxide 7,536 8,307 1.27 1.24 1.09 0.14 96 93 82 11 211
Chalcocite Enriched 19,763 21,785 1.44 1.29 0.25 1.03 285 254 50 204 628
Primary 35,012 38,594 1.06 N/A N/A N/A 372 N/A N/A N/A 821
Total                        
Indicated All Domains 3,560 3,924 1.33 0.97 0.25 0.73 47 35 9 26 104
Inferred All Domains 62,311 68,687 1.21 0.56 0.21 0.35 753 348 132 215 1,660

 

Source: Nordmin, 2023

Note: Refer to notes on Table 11-18.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 246

 

11.9.4East Ridge Mineral Resource Estimate

 

The East Ridge Deposit Mineral Resource Estimate, which is exclusive of mineral reserves, is presented in Table 11-21.

 

Table 11-21: In Situ East Ridge Deposit Mineral Resource Estimate, 0.90% Total Cu CoG

 

 

Mineralized

Material

Mineralized

Material

Total

Cu

Total

Soluble
Cu

Acid

Soluble
Cu

Cyanide

Soluble
Cu

Total

Cu

Total

Soluble
Cu

Acid

Soluble
Cu

Cyanide

Soluble
Cu

Total

Cu

East Ridge Deposit
0.90% Cu COG 
Classification Domain (kt) (k ton) (%) (%) (%) (%) (kt) (kt) (kt) (kt) (Mlb)
Indicated Exotic 0 0 0.00 0.00 0.00 0.00 0 0 0 0 0
Oxide 0 0 0.00 0.00 0.00 0.00 0 0 0 0 0
Chalcocite Enriched 0 0 0.00 0.00 0.00 0.00 0 0 0 0 0
Primary 0 0 0.00 N/A N/A N/A 0 N/A N/A N/A 0
Inferred Exotic 0 0 0.00 0.00 0.00 0.00 0 0 0 0 0
Oxide 23,978 26,431 1.36 1.26 0.69 0.57 326 302 164 137 718
Chalcocite Enriched 0 0 0.00 0.00 0.00 0.00 0 0 0 0 0
Primary 0 0 0.00 N/A N/A N/A 0 N/A N/A N/A 0
TOTAL                        
Indicated All Domains 0 0 0.00 0.00 0.00 0.00 0 0 0 0 0
Inferred All Domains 23,978 26,431 1.36 1.26 0.69 0.57 326 164 164 137 718

 

Source: Nordmin, 2023

Note: Refer to notes on Table 11-18.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 247

 

11.10Mineral Resource Sensitivity to Reporting Cut-off

 

The updated Santa Cruz, Texaco, and East Ridge Mineral Resource Estimates to a Cu (%) cut-off are summarized in Table 11-22, Table 11-23, and Table 11-24 across all interpolation methods.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 248

 

Table 11-22: Mineral Resource Sensitivity for Santa Cruz Total Cu   

 

Santa Cruz Deposit

Mineralized

Material

(kt)

Mineralized

Material

(k ton)

Total

Cu

(%)

Acid

Soluble Cu

(%)

Cyanide

Soluble Cu

(%)

Total Cu

(kt)

Acid

Soluble Cu

(kt)

Cyanide

Soluble Cu

(kt)

Total Cu

(Mlb)

Classification

COG

(%)

Indicated 0.30 438,378 483,228 0.88 0.34 0.14 3,862 1,483 608 8,514
Inferred 0.30 277,102 305,452 0.60 0.22 0.06 1,659 613 154 3,658
Indicated 0.40 387,905 427,592 0.95 0.37 0.15 3,682 1,448 598 8,118
Inferred 0.40 169,542 186,888 0.76 0.34 0.08 1,288 572 143 2,839
Indicated 0.50 338,866 373,536 1.02 0.41 0.17 3,458 1,404 583 7,623
Inferred 0.50 104,653 115,360 0.96 0.51 0.13 1,005 534 133 2,215
Indicated 0.60 279,596 308,201 1.12 0.48 0.20 3,126 1,353 562 6,892
Inferred 0.60 78,033 86,016 1.11 0.64 0.16 864 498 124 1,904
Indicated 0.70 223,155 245,987 1.24 0.58 0.24 2,759 1,292 533 6,083
Inferred 0.70 62,709 69,125 1.23 0.74 0.18 768 462 114 1,694
Indicated 0.80 179,905 198,312 1.35 0.69 0.27 2,432 1,233 491 5,362
Inferred 0.80 51,794 57,093 1.33 0.82 0.20 689 426 101 1,519
Indicated 0.90 144,115 158,860 1.48 0.81 0.30 2,128 1,171 436 4,692
Inferred 0.90 42,840 47,223 1.43 0.91 0.21 614 389 88 1,355
Indicated 1.00 119,293 131,497 1.59 0.93 0.32 1,892 1,106 386 4,172
Inferred 1.00 36,856 40,627 1.52 0.97 0.22 559 357 79 1,232
Indicated 1.20 83,837 92,415 1.79 1.14 0.37 1,502 958 310 3,312
Inferred 1.20 26,055 28,721 1.70 1.10 0.24 443 287 61 977
Indicated 1.50 53,218 58,663 2.05 1.33 0.45 1,089 705 241 2,401
Inferred 1.50 14,892 16,416 1.99 1.29 0.30 296 193 44 652
Indicated 2.00 21,736 23,960 2.51 1.53 0.65 547 332 142 1,205
Inferred 2.00 5,935 6,542 2.43 1.59 0.37 144 95 22 318

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 249

 

 Table 11-23: Mineral Resource Sensitivity for Texaco Total Cu 

 

Texaco Deposit

Mineralized

Material

(kt)

Mineralized

Material

(k ton)

Total

Cu

(%)

Acid

Soluble Cu

(%)

Cyanide

Soluble Cu

(%)

Total Cu

(kt)

Acid

Soluble Cu

(kt)

Cyanide

Soluble Cu

(kt)

Total Cu

(Mlb)

Classification

COG

(%)

Indicated 0.30% 9,609 10,592 0.83 0.12 0.31 80 11 30 177
Inferred 0.30% 182,697 201,389 0.77 0.10 0.17 1,411 176 303 3,111
Indicated 0.40% 8,564 9,440 0.89 0.12 0.34 77 11 29 169
Inferred 0.40% 162,879 179,543 0.82 0.10 0.18 1,342 167 290 2,958
Indicated 0.50% 7,441 8,202 0.96 0.14 0.39 71 10 29 158
Inferred 0.50% 135,652 149,530 0.90 0.12 0.20 1,218 158 273 2,685
Indicated 0.60% 5,688 6,270 1.09 0.17 0.49 62 10 28 136
Inferred 0.60% 105,215 115,979 1.00 0.14 0.24 1,051 147 249 2,317
Indicated 0.70% 4,297 4,737 1.23 0.22 0.62 53 9 27 117
Inferred 0.70% 82,390 90,819 1.10 0.17 0.28 903 140 232 1,991
Indicated 0.80% 3,560 3,924 1.33 0.25 0.73 47 9 26 104
Inferred 0.80% 62,311 68,687 1.21 0.21 0.35 753 132 215 1,660
Indicated 0.90% 3,106 3,423 1.40 0.26 0.80 44 8 25 96
Inferred 0.90% 47,899 52,799 1.32 0.26 0.41 631 124 198 1,391
Indicated 1.00% 2,705 2,982 1.47 0.28 0.87 40 7 24 88
Inferred 1.00% 37,071 40,863 1.43 0.31 0.48 528 115 179 1,165
Indicated 1.20% 2,037 2,246 1.59 0.28 1.00 32 6 20 71
Inferred 1.20% 22,788 25,119 1.63 0.42 0.61 372 96 138 821
Indicated 1.50% 932 1,027 1.88 0.20 1.26 18 2 12 39
Inferred 1.50% 12,162 13,406 1.90 0.54 0.65 231 65 79 509
Indicated 2.00% 251 276 2.26 0.08 1.21 6 0 3 13
Inferred 2.00% 4,239 4,672 2.25 0.74 0.65 95 32 27 210

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 250

 

Table 11-24: Mineral Resource Sensitivity for East Ridge Total Cu - There are no Indicated Resources at East Ridge 

 

East Ridge Deposit Mineralized
Material
Mineralized
Material
Total Cu Acid Soluble Cu Cyanide Soluble
Cu
Total Cu Acid
Soluble Cu
Cyanide
Soluble Cu
Total Cu
Classification COG (kt) (k ton) (%) (%) (%) (kt) (kt) (kt) (Mlb)
Inferred 0.30% 159,015 175,284 0.62 0.25 0.25 987 392 397 2,175
Inferred 0.40% 107,999 119,049 0.75 0.31 0.31 809 338 334 1,785
Inferred 0.50% 75,452 83,172 0.88 0.39 0.37 664 292 277 1,464
Inferred 0.60% 56,069 61,806 1.00 0.46 0.42 558 255 234 1,230
Inferred 0.70% 41,496 45,741 1.12 0.53 0.47 464 221 195 1,023
Inferred 0.80% 31,172 34,361 1.24 0.61 0.52 387 190 163 852
Inferred 0.90% 23,978 26,431 1.36 0.69 0.57 326 164 137 718
Inferred 1.00% 18,886 20,818 1.47 0.76 0.62 277 143 117 612
Inferred 1.20% 11,995 13,223 1.69 0.90 0.71 202 108 86 446
Inferred 1.50% 6,142 6,771 2.02 1.11 0.87 124 68 53 274
Inferred 2.00% 2,223 2,450 2.58 1.44 1.12 57 32 25 127

 

Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 251

 

11.11Interpolation Comparison

 

Global statistical comparisons between the composite samples, NN estimates, ID2 estimates, ID3 estimates, and OK for various CoGs were compared to assess global bias, where the NN model estimates represent de-clustered composite data. Clustering of the drillhole data can result in differences between the global means of the composites and NN estimates. The OK method was used as the reporting estimation interpolation method for the Santa Cruz Deposit and the ID3 method was used for the East Ridge and Texaco Deposits (Table 11-25 through Table 11-27). NN, ID2, ID3, and OK were estimated for validation purposes for all block models, as described in Section 11.4.8. Table 11-25 (Santa Cruz Deposit), Table 11-26 (Texaco Deposit), Table 11-27 (East Ridge Deposit) demonstrate the total Cu interpolation comparison across ID2, ID3, NN, and OK (in the Santa Cruz Deposit) interpolation methods.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 252

 

Table 11-25: Santa Cruz Interpolation Comparison

 

Cut-Off

Total

Cu %

Total

Cu

OK

Total

Cu

ID2

Total
Cu

ID3

Total

Cu

NN

Acid
Soluble

Cu

OK

Acid
Soluble
Cu

ID2

Acid
Soluble
Cu

ID3

Acid
Soluble
Cu

NN

Cyanide

Soluble

Cu

OK

Cyanide
Soluble
Cu

ID2

Cyanide
Soluble
Cu

ID3

Cyanide
Soluble
Cu

NN

0.30 0.82 0.81 0.81 0.82 0.31 0.31 0.31 0.35 0.11 0.12 0.12 0.16
0.60 1.26 1.24 1.25 1.27 0.59 0.60 0.60 0.63 0.21 0.22 0.22 0.27
0.70 1.45 1.42 1.42 1.45 0.74 0.74 0.74 0.77 0.26 0.27 0.27 0.32
0.80 1.61 1.58 1.58 1.61 0.87 0.88 0.88 0.91 0.29 0.31 0.31 0.35
1.00 1.90 1.85 1.85 1.90 1.13 1.14 1.13 1.16 0.33 0.35 0.35 0.39
1.50 2.27 2.21 2.21 2.28 1.41 1.41 1.41 1.44 0.38 0.39 0.39 0.44
2.00 2.66 2.57 2.58 2.62 1.70 1.70 1.70 1.71 0.47 0.48 0.48 0.53

 

 Source: Nordmin, 2023

 

 Table 11-26: Texaco Interpolation Comparison 

 

Cut-Off

Total
Cu %

Total
Cu

ID2

Total
Cu

ID3

Total
Cu

NN

Acid
Soluble
Cu

ID2

Acid
Soluble
Cu

ID3

Acid
Soluble
Cu

NN

Cyanide
Soluble
Cu

ID2

Cyanide
Soluble
Cu

ID3

Cyanide
Soluble
Cu

NN

0.30 0.84 0.84 0.86 0.11 0.11 0.11 0.19 0.19 0.20
0.50 0.96 0.97 1.01 0.12 0.13 0.13 0.23 0.23 0.24
0.70 1.21 1.23 1.31 0.18 0.19 0.19 0.34 0.34 0.36
0.80 1.34 1.37 1.47 0.22 0.23 0.23 0.41 0.41 0.44
0.90 1.45 1.50 1.61 0.26 0.27 0.28 0.47 0.48 0.52
1.00 1.57 1.63 1.77 0.31 0.32 0.32 0.54 0.55 0.59
1.50 2.19 2.34 2.73 0.56 0.58 0.57 0.86 0.90 1.05
2.00 2.69 2.94 3.70 0.76 0.79 0.79 0.95 1.01 1.26

 

 Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 253

 

Table 11-27: East Ridge Deposit Interpolation Comparison 

 

Cut-Off

Total
Cu %

Total
Cu

ID2

Total
Cu

ID3

Total
Cu

NN

Acid
Soluble
Cu

ID2

Acid
Soluble
Cu

ID3

Acid
Soluble
Cu

NN

Cyanide
Soluble
Cu

ID2

Cyanide
Soluble
Cu

ID3

Cyanide
Soluble
Cu

NN

0.30 0.69 0.71 0.73 0.27 0.27 0.27 0.28 0.29 0.29
0.50 0.97 1.00 1.05 0.42 0.42 0.43 0.41 0.43 0.45
0.70 1.20 1.24 1.29 0.56 0.57 0.58 0.51 0.53 0.56
0.80 1.31 1.35 1.40 0.64 0.64 0.65 0.56 0.58 0.60
0.90 1.42 1.47 1.52 0.71 0.72 0.72 0.60 0.63 0.65
1.00 1.51 1.56 1.63 0.77 0.78 0.79 0.64 0.67 0.70
1.50 2.04 2.15 2.17 1.16 1.17 1.13 0.88 0.93 0.94
2.00 2.59 2.75 2.71 1.53 1.55 1.43 1.13 1.20 1.18

 

 Source: Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 254

 

11.12Factors That May Affect Mineral Resources

 

Areas of uncertainty that may materially impact the Mineral Resource Estimates include:

 

·Changes to long term metal price assumptions.
·Changes to the input values for mining, processing, and G&A costs to constrain the estimate.
·Changes to local interpretations of mineralization geometry and continuity of mineralized Sub-Domains.
·Changes to the density values applied to the mineralized zones.
·Changes to metallurgical recovery assumptions.
·Changes in assumptions of marketability of the final product.
·Variations in geotechnical, hydrogeological and mining assumptions.
·Changes to assumptions with an existing agreement or new agreements.
·Changes to environmental, permitting, and social license assumptions.
·Logistics of securing and moving adequate services, labor, and supplies could be affected by epidemics, pandemics and other public health crises, including COVID-19, or similar such viruses.

 

11.13QP Opinion

 

Nordmin is not aware of any environmental, legal, title, taxation, socioeconomic, marketing, political, or other relevant factors that would materially affect the estimation of Mineral Resources that are not discussed in this Technical Report.

 

Nordmin is of the opinion that the Mineral Resources for the Project, which were estimated using industry accepted practices, have been prepared and reported using S-K 1300 definitions.

 

Technical and economic parameters and assumptions applied to the Mineral Resource Estimate are based on parameters received from IE and reviewed within the Nordmin technical team to determine if they were appropriate. All issues relating to all relevant technical and economic factors likely to influence the prospect of economic extraction can be resolved with further work.

 

The QP considers that all issues relating to all relevant technical and economic factors likely to influence the prospect of economic extraction can be resolved with further work.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 255

 

12Mineral Reserve Estimates

 

This section is not relevant to this Technical Report Summary.

 

This work is preliminary in nature, it includes inferred mineral resources that are considered too speculative geologically to have modifying factors applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that this economic assessment will be realized.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 256

 

13Mining Methods

 

The Project is currently not in operation. Mineral resources are stated for three deposits: Santa Cruz, Texaco, and East Ridge. For mine planning work, only the Santa Cruz and East Ridge deposits were evaluated.

 

The Santa Cruz deposit is located approximately 430 to 970 m below the surface. Based on the mineralization geometry and geotechnical information, an underground longhole stoping (LHS) method is suitable for the deposit. The Santa Cruz deposit will be mined in blocks where mining within a block occurs from bottom to top with paste backfill (PBF) for support. A sill pillar is left in situ between blocks. The PBF will have sufficient strength to allow for mining adjacent to filled stopes without the need for pillars. The stopes will be 10 m wide, and stope lengths range from 12 to 33 m depending on the level, location, and sequence. A spacing of 30 m between levels has been used.

 

Within the Santa Cruz deposit, there is an Exotic domain located approximately 500 to 688 m below the surface and to the east of the main deposit. The Exotic domain consists of flatter lenses that are more amenable to drift and fill (DAF) mining. The drift will be 9 m high and 6 m wide. Drift lengths vary depending on the extents of the mineralization. An initial 5 m high and 6 m wide drift will be taken, followed by a 4 m high back slash to achieve the final dimensions. Cemented waste rockfill will be used for support. The backfill will have sufficient strength to allow mining of adjacent drifts without leaving pillars.

 

The East Ridge deposit is approximately 380 to 690 m below the surface and to the north of the main Santa Cruz deposit. The East Ridge deposit consists of two tabular lenses and will be mined using DAF with cemented waste rock backfill for support. The drift dimensions will be 9 m high, 6 m wide, and of variable length depending on the extents of the mineralization. An initial 5 m high and 6 m wide drift will be taken, followed by a 4 m high back slash to achieve the final dimensions.

 

The mine will be accessed by dual decline drifts from surface, with one drift serving as the main access and the other as a railveyor drift for material handling. Mineralization is transported from stopes via loader to an ore pass system and then to surface by the railveyor. Main intake and exhaust raises will be developed with conventional shaft sinking methods to provide air to the mine workings. The mine will target a combined production of 15,000 t/d from Santa Cruz and East Ridge. Figure 13-1 shows the location of the different deposits and the portal.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 257

 

 

Source: SRK, 2023

 

Figure 13-1: Location of the Different Zones

 

September 2023

SEC Technical Report Summary – Santa CruzPage 258

 

13.1Cut-Off Grade Calculations

 

Table 13-1 shows estimated project costs and calculated CoG’s.

 

Table 13-1: Cut-Off Grade Assumptions

 

Parameter Unit LHS Method DAF Method
On-Site Costs      
Mining Cost US$/t-proc 25.50 45.00
Process Cost US$/t-proc 11.18 11.47
G&A Costs US$/t-proc 7.00 7.00
Sub-total On-Site Cost US$/t-proc 43.68 63.47
Off-Site Cost      
Cathode Shipping US$/t-proc 0.51 0.57
Concentrate Shipping US$/t-proc 1.26 1.36
Concentrate Smelting and Refining US$/t-proc 1.53 1.65
Sub-total Off-Site Cost US$/t-proc 3.29 3.58
Royalties US$/t-proc 5.22 4.49
Total Cost US$/t-proc 52.19 71.54
Parameters      
Copper Price US$/lb 3.70 3.70
Payable Copper % 96.0 96.0
Metallurgical Recovery % 94.0 94.0
Mining Dilution % 13.5 5.0
Mining Recovery % 100.00 100.00
Calculated In Situ Cut-Off % 0.79 1.00
Selected Cut-Off for MSO % 0.80 1.00

 

Source: SRK, 2023

 

SRK notes that US$3.70/lb copper price is approximately equal to current spot pricing. In the opinion of SRK, this price is generally in-line with pricing over the last 3 years and forward-looking pricing is appropriate for use during an Initial Assessment of the Project with an estimated 20-year long mine life. The values presented here may differ from the economic model, however SRK is of the opinion that the differences are not material. Additional commentary on selected pricing is included in Section 16.

 

13.2Geotechnical

 

IE contracted geotechnical engineering consulting firm CNI based out of Tucson, Arizona, USA, to perform a geotechnical evaluation in support of an initial assessment for the Santa Cruz Copper Project located in Pinal County of southern Arizona. The purpose of the study was to provide underground mine design parameters based on recent and historic geotechnical data collected at the site. Key design recommendations were provided for the following:

 

·Longhole stope (LHS) dimensions
·Drift and fill (DAF) dimensions
·General mining sequence guidelines
·Dilution estimates based on equivalent length of slough (ELOS)
·Configurations and dimensions for access pillars and sill pillars
·Ground support requirements
·Backfill strength minimum requirements

 

13.2.1Dataset

 

Data utilized in the study include the following:

 

·MSO shapes for the Santa Cruz (S.C.) and East Ridge mining targets (received January 23, 2023), presented in Figure 13-2 and Figure 13-3.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 259

·Geomechanical data from 152 drillholes (71,620 m), as presented in Table 13-2 and on Figure 13-4.

o83 drillholes (35,555 m) are historical (prefix CG-XXX) and include RQD and recovery only.
o69 holes (36,065 m) drilled in 2021 through 2022 under IE direction (prefix SCC-XXX) and logged by CNI engineers and geologists. The 69 drillholes were logged for data using the Modified NGI Q’ system of rock mass classification.

·Rock fabric orientations from acoustic televiewer (ATV) survey data from 24 drillholes (prefix SCC-XXX) throughout the Santa Cruz area, as presented in Table 13-3 and on Figure 13-5.
·Geomechanical laboratory testing, as summarized in Table 13-4. Rock strength estimates were determined utilizing this information.
·VWP data from 13 drillholes, installed by CNI engineers and geologists.

 

 

Source: CNI, 2023

 

Figure 13-2: Plan View of Santa Cruz and East Ridge Mining Targets

 

September 2023

SEC Technical Report Summary – Santa CruzPage 260

 

 

 

Source: CNI, 2023

 

Figure 13-3: Section View (Looking East) of Santa Cruz and East Ridge Mining Targets

 

Table 13-2: Drillholes Utilized for 2023 IA

 

Drillhole ID
CG-010 CG-034 CG-055 CG-084 CG-113 SCC-020 SCC-048 SCC-089
CG-011 CG-035 CG-057 CG-085 CG-116 SCC-021 SCC-050 SCC-090
CG-012 CG-036 CG-059 CG-087 CG-118 SCC-022 SCC-052 SCC-092
CG-013 CG-037 CG-060 CG-088 SCC-001 SCC-023 SCC-053 SCC-093
CG-016 CG-038 CG-061 CG-089 SCC-002 SCC-024 SCC-054 SCC-094
CG-018A CG-039 CG-062 CG-090 SCC-003 SCC-025 SCC-056 SCC-096
CG-020 CG-040 CG-063 CG-091 SCC-004 SCC-026 SCC-057 SCC-098
CG-021 CG-041 CG-064 CG-092 SCC-005 SCC-027 SCC-058 SCC-099
CG-022 CG-042 CG-065 CG-093 SCC-006 SCC-028 SCC-059 SCC-101
CG-023 CG-043 CG-068 CG-094 SCC-007 SCC-029 SCC-063 SCC-102
CG-024 CG-044 CG-074 CG-095 SCC-008 SCC-030 SCC-065 SCC-103
CG-025 CG-045 CG-075 CG-096 SCC-009 SCC-031 SCC-068 SCC-105
CG-026 CG-046 CG-076 CG-097 SCC-010 SCC-032 SCC-073  
CG-027 CG-047 CG-077 CG-098 SCC-011 SCC-033 SCC-078
CG-028 CG-048 CG-078 CG-099 SCC-013 SCC-037 SCC-080
CG-029 CG-050 CG-079 CG-100 SCC-014 SCC-038 SCC-081
CG-030 CG-051 CG-080 CG-103 SCC-016 SCC-042 SCC-082
CG-031 CG-052 CG-081 CG-107 SCC-017 SCC-043 SCC-084
CG-032 CG-053 CG-082 CG-109 SCC-018 SCC-045 SCC-086
CG-033 CG-054 CG-083 CG-110 SCC-019 SCC-047 SCC-088

 

Source: CNI, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 261

 

 

Source: CNI, 2023

 

Figure 13-4: Plan View of Geotechnical Drillhole Collars

 

Table 13-3: ATV Drillholes by Structural Domain

 

Drillholes with ATV Survey used in Structural Investigation
SCC-006 North
Structural
Domain
SCC-001 South
Structural
Domain
SCC-009 SCC-002
SCC-021 SCC-007
SCC-022 SCC-008
SCC-023 SCC-011
SCC-026 SCC-029
SCC-032 SCC-048
SCC-045 SCC-058
SCC-052 SCC-059
SCC-053  
SCC-054
SCC-063
SCC-092
SCC-099
SCC-102

 

Source: CNI, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 262

 

Table 13-4: Summary of Geomechanical Laboratory Testing, 2023 IA

 

Test Type Number of Tests
Unconfined Compressive Strength (UCS) 26
Point Load 21
Triaxial Compressive Strength (TCS) 23
Brazilian Disk Tension 37
Small Scale Direct Shear 7
Unified Soil Classification System (USCS) 14

 

Source: CNI, 2023

 

 

Source: CNI, 2023

 

Figure 13-5: Plan View of Drillhole Collars with ATV Survey

 

The following are additional information utilized in the geotechnical evaluation:

 

·MSO shapes for the S.C. and East Ridge mining targets (received January 23, 2023), presented in Figure 13-6.
·Geology model (June 2022 model) provided by IE, including coded lithology, mineral domains, and fault wireframes.
·Various decline options provided by IE.
·A geotechnical block model was constructed using data from the 152 drilled holes. Details of the geotechnical block model are presented in the CNI report 2023 Geotechnical Block Model Santa Cruz Project (May 2023).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 263

 

13.2.2Mine Design Geotechnical Parameters

 

Table 13-5 and Table 13-6 present a summary of design parameters for mine planning using a LHS mining method. Table 13-7 presents a summary of design parameters for mine planning using a drift and fill (DAF) mining method. Due to its orebody geometry and rock quality, the mining of the East Ridge deposit is currently planned using a DAF method with jammed cemented rock backfill. The Oxide and Chalcocite-Enriched mineral domains of the Santa Cruz deposit will be mined using the LHS method, while the Exotic mineral domain will be mined using the DAF method. The primary (hypogene) mineral domain of Santa Cruz is not currently planned for production mining.

 

Table 13-5: Summary of LHS Geotechnical Design Recommendations

 

Design Parameter Recommendation
Stope height (from sill to sill) (m) 30
Stope width (from sidewall to sidewall) (m) 10
Stope length before backfilling (m) Varies by Mineral Domain, Muck Level,
and North/South Structural Domains*
Cable bolt square spacing for back (m) 2
Cable bolt length (m) 6
Sill pillar thickness (m) 30
Haulage level setback distance (m) 40
Stope orientation (azimuth) (°) 090
PBF compressive strength (kilopascals
(kPa)) at 7 days cure time
600
Estimated cement in solids (%) 3

 

Source: CNI, 2023

 

*See Table 13-6 for stope dimensions.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 264

 

Table 13-6: Summary of LHS Dimensions and ELOS by North and South Area, Mineral Domain

 

Muck
Level
Design Dimensions (m) ELOS (m)
Oxide Mineral Domain Chalcocite-Enriched Oxide Chalcocite-Enriched
Height Width Length Height Width Length Side
Walls
End
Walls
Side
Walls
End
Walls
North Area
60 30.0 10.0 11.0       0.75 0.75    
30 30.0 10.0 8.2       1.00 1.50    
0 30.0 10.0 10.8       0.75 0.75    
-30 30.0 10.0 9.6       0.75 1.00    
-60 30.0 10.0 12.0       0.50 0.75    
-90 30.0 10.0 13.4 30.0 10.0 46.5 0.50 0.50 <0.50 <0.50
-120 30.0 10.0 14.4 30.0 10.0 46.7 0.50 0.50 <0.50 <0.50
-150 30.0 10.0 16.3 30.0 10.0 29.7 <0.50 <0.50 <0.50 <0.50
-180 30.0 10.0 15.2 30.0 10.0 25.7 0.50 <0.50 <0.50 <0.50
-210 30.0 10.0 17.8 30.0 10.0 26.6 <0.50 <0.50 <0.50 <0.50
-240 30.0 10.0 19.5 30.0 10.0 25.2 <0.50 <0.50 <0.50 <0.50
-270 30.0 10.0 14.8 30.0 10.0 17.6 0.50 <0.50 <0.50 <0.50
-300 30.0 10.0 15.7 30.0 10.0 16.3 <0.50 <0.50 <0.50 <0.50
-330 30.0 10.0 16.9 30.0 10.0 13.4 <0.50 <0.50 0.50 0.50
-360 30.0 10.0 15.7 30.0 10.0 15.9 <0.50 <0.50 <0.50 <0.50
-390 30.0 10.0 15.8 30.0 10.0 20.1 <0.50 <0.50 <0.50 <0.50
-420 30.0 10.0 14.9 30.0 10.0 22.0 0.50 <0.50 <0.50 <0.50
-450 30.0 10.0 12.8 30.0 10.0 16.6 0.50 0.50 <0.50 <0.50
-480 30.0 10.0 18.2 30.0 10.0 16.1 <0.50 <0.50 <0.50 <0.50
-510 30.0 10.0 18.7 30.0 10.0 12.0 <0.50 <0.50 0.50 0.75
-540 30.0 10.0 14.9 30.0 10.0 10.2 0.50 <0.50 0.75 1.00
-570 30.0 10.0 16.5 30.0 10.0 8.2 <0.50 <0.50 1.00 1.50
-600 30.0 10.0 16.2       <0.50 <0.50    
-630                    
South Area
60 30.0 10.0 11.5       0.50 1.50    
30 30.0 10.0 8.6       1.00 2.00    
0 30.0 10.0 11.3       0.75 1.50    
-30 30.0 10.0 10.0       0.75 1.50    
-60 30.0 10.0 12.6       0.50 1.00    
-90 30.0 10.0 14.1 30.0 10.0 51.1 0.50 1.00 <0.50 <0.50
-120 30.0 10.0 15.1 30.0 10.0 51.2 0.50 0.75 <0.50 <0.50
-150 30.0 10.0 17.3 30.0 10.0 31.9 <0.50 0.75 <0.50 <0.50
-180 30.0 10.0 16.1 30.0 10.0 27.5 0.50 0.75 <0.50 <0.50
-210 30.0 10.0 18.8 30.0 10.0 28.5 <0.50 0.50 <0.50 <0.50
-240 30.0 10.0 20.6 30.0 10.0 26.9 <0.50 0.50 <0.50 <0.50
-270 30.0 10.0 15.6 30.0 10.0 18.6 0.50 0.75 <0.50 0.50
-300 30.0 10.0 16.6 30.0 10.0 17.2 <0.50 0.75 <0.50 0.75
-330 30.0 10.0 17.9 30.0 10.0 14.1 <0.50 0.50 0.50 1.00
-360 30.0 10.0 16.6 30.0 10.0 16.8 <0.50 0.75 <0.50 0.75
-390 30.0 10.0 16.7 30.0 10.0 21.4 <0.50 0.75 <0.50 <0.50
-420 30.0 10.0 15.7 30.0 10.0 23.4 0.50 0.75 <0.50 <0.50
-450 30.0 10.0 13.4 30.0 10.0 17.5 0.50 1.00 <0.50 0.75
-480 30.0 10.0 19.3 30.0 10.0 17.0 <0.50 0.50 <0.50 0.75
-510 30.0 10.0 19.8 30.0 10.0 12.6 <0.50 0.50 0.50 1.00
-540 30.0 10.0 15.7 30.0 10.0 10.7 0.50 0.75 0.75 1.50
-570 30.0 10.0 17.5 30.0 10.0 8.6 <0.50 0.75 1.00 2.00
-600 30.0 10.0 17.1       <0.50 0.75    
-630                    

 

Source: CNI, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 265

 

Table 13-7: Summary of DAF Geotechnical Design Recommendations

 

Design Parameter Recommendation
Drift span (m) 6
Floor pull maximum height (m) 9
Cemented rock fill (CRF) compressive strength (kPa) target at 28 days* 400
Estimated cement binder (%)** 3

 

Source: CNI, 2023

 

*Includes a safety factor = 2

 

**A minimum binder content of 3% was assumed to ensure no uncemented particles are in the CRF.

 

13.2.3Risks and Opportunities

 

Risks and Opportunities

 

·There will always be differences between the predicted conditions and the field conditions. Additional drilling is ongoing to better characterize and predict potential ground conditions throughout the Project area.
·Additional data have been collected in the East Ridge area since completion of the geotechnical model. Improvements in the East Ridge rock quality could allow for wider operating spans and potential stoping zones where the orebody thickness is suitable.
·All analyses assume generally dry conditions and that the mining areas are effectively depressurized. Should there be residual water within the surrounding rock mass of excavations or depressurization is incomplete, the stability of openings and ground support designs will be less than predicted.
·Maximum extraction of the orebody will be contingent on the ability to backfill stope and DAF openings tightly to their backs. Furthermore, there is uncertainty that the tailings, mine water, and mine waste rock are suitable for PBF and CRF. Additional analyses are necessary to further investigate this.
·If the results of in situ stress measurement indicate lower horizontal stresses (k<0.8), larger stopes may be possible.
·Alternative ground support types should be considered, which could optimize lengths and installation density of bolting options.

 

13.2.4Rock Quality, Strength, and Joint Orientations

 

Rock Quality

 

Rock quality was estimated using a geotechnical block model. Using this model, rock quality was predicted for each mineral domain and for each 30 m stope sublevel where MSO shapes are situated. Table 13-8 presents a summary of rock quality (Q’) estimates by muck level, which were used to determine stope dimensions. Figure 13-6 presents a cumulative distribution of Q’ for all blocks within MSO shapes.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 266

 

 

Table 13-8: Summary of Q’ Rock Quality by Mining Level

 

Muck
Level
Number
of
Blocks
By Domain, 50% Q' By Domain, 75% Q'
Exotic Oxide Chalcocite-
Enriched
Primary/
Hypogene
Exotic Oxide Chalcocite-
Enriched
Primary/
Hypogene
60 990 1.073       0.794 0.729    
30 480 1.079       0.405 0.403    
0 1,110 1.248       0.705 0.705    
-30 756 0.736     1.067 0.98 0.553   1.017
-60 3,326 0.893 1.094   1.142 0.882 0.873   0.912
-90 12,375 0.93 1.56 6.848 1.664 0.93 1.077 6.848 1.215
-120 42,434 0.299 1.839 6.992 2.157 0.186 1.227 6.867 0.971
-150 61,093 0.414 3.026 5.342 2.157 0.321 1.546 3.961 1.813
-180 62,380 0.984 3.649 4.905 4.633 0.519 1.538 3.625 2.253
-210 72,377 0.989 4.27 5.38 4.112 0.604 2.014 3.812 1.51
-240 80,218 0.83 4.307 4.801 4.24 0.511 2.349 3.526 1.753
-270 64,663 1.318 2.442 3.347 4.345 0.711 1.667 2.269 3.087
-300 58,363 0.757 3.131 2.512 3.524 0.401 1.85 1.975 1.791
-330 60,473 1.132 3.196 2.274 2.008 0.711 2.107 1.388 1.377
-360 66,713 0.925 3.358 3.751 1.43 0.562 2.164 2.202 0.946
-390 65,608 0.855 3.774 5.287 1.409 0.518 2.181 3.311 0.997
-420 60,090 0.694 3.597 4.491 1.284 0.544 1.964 3.819 0.81
-450 52,595 1.038 2.542 3.475 1.065 0.685 1.77 2.855 0.681
-480 42,619 4.493 4.369 3.249 1.475   3.357 2.72 1.066
-510 31,295 1.015 3.972 2.435 1.336   3.516 1.566 0.833
-540 29,781 1.988 3.816 2.449 1.398   2.932 1.409 1.008
-570 23,383   3.887 1.825 1.336   3.556 0.897 0.919
-600 5,686   3.472   1.283   3.429   0.87
-630 2,634       0.934       0.813

 

Source: CNI, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 267

 

 

 

Source: CNI, 2023

 

Figure 13-6: Cumulative Distribution Plot of All Q’ Data within the Santa Cruz MSO Shapes

 

The average rock quality (Q’ = 2.5) is poor according to Barton’s classification system. Rock quality is best (median Q’ = 4.5) within the middle of the orebody (between the minus 150 and minus 240 m elevations), and then lessens above and below. Table 13-9 presents summaries of modeled RQD, Q’, and geological strength index (GSI) by modeled domain within these elevation ranges.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 268

 

Table 13-9: Santa Cruz Rock Quality Summary

 

Rock Quality Type Mineral Domain Minimum Q1 Q2 Q3 Maximum
Above -150            
RQD All 11.02 37.21 50.12 61.81 88.95
Exotic 11.02 22.64 28.58 34.66 67.13
Oxide 13.75 41.29 53.28 61.94 84.24
Chalcocite-Enriched 68.23 81.22 83.45 87.93 88.95
Hypogene\Primary 15.68 37.42 49.74 64.05 81.81
Q' All 0.07 0.96 1.57 2.74 14.73
Exotic 0.07 0.20 0.39 0.59 2.81
Oxide 0.21 1.15 1.71 2.81 10.43
Chalcocite-Enriched 3.77 6.85 6.99 7.37 14.73
Hypogene\Primary 0.16 0.98 1.61 2.71 6.56
GSI All 20.57 43.60 48.04 53.08 68.21
Exotic 20.57 29.69 35.53 39.25 53.31
Oxide 29.91 45.28 48.84 53.29 65.10
Chalcocite-Enriched 55.95 61.32 61.50 61.97 68.21
Hypogene\Primary 27.73 43.82 48.27 52.96 60.93
-150 to -240            
RQD All 11.94 55.62 67.21 76.20 93.83
Exotic 17.46 37.44 47.30 57.35 74.58
Oxide 11.94 54.30 65.77 75.10 92.51
Chalcocite-Enriched 35.60 64.87 73.29 79.25 93.34
Hypogene\Primary 17.19 52.11 67.92 77.13 93.83
Q' All 0.10 2.00 4.02 5.74 14.94
Exotic 0.10 0.46 0.80 1.39 5.94
Oxide 0.15 1.85 3.84 5.52 14.04
Chalcocite-Enriched 0.87 3.65 5.06 6.74 14.94
Hypogene\Primary 0.32 1.86 3.67 5.99 11.93
GSI All 22.91 50.22 56.53 59.72 68.34
Exotic 22.91 37.03 41.98 46.94 60.01
Oxide 26.93 49.53 56.11 59.38 67.78
Chalcocite-Enriched 42.77 55.66 58.60 61.17 68.34
Hypogene\Primary 33.66 49.56 55.70 60.11 66.31
Below -240            
RQD All 7.08 37.98 50.01 61.48 90.16
Exotic 12.31 31.74 52.23 63.35 84.00
Oxide 7.08 43.69 56.06 65.60 90.16
Chalcocite-Enriched 19.74 49.23 59.49 68.88 86.22
Hypogene\Primary 9.01 33.08 42.62 52.10 87.96
Q' All 0.09 1.28 2.28 3.88 11.57
Exotic 0.20 0.54 1.03 1.81 7.00
Oxide 0.13 2.09 3.43 4.51 11.57
Chalcocite-Enriched 0.32 2.13 3.19 4.53 10.66
Hypogene\Primary 0.09 0.95 1.48 2.52 11.57
GSI All 22.23 46.24 51.43 56.19 66.04
Exotic 29.29 38.52 44.22 49.32 61.51
Oxide 25.50 50.63 55.09 57.56 66.04
Chalcocite-Enriched 33.86 50.78 54.44 57.59 65.30
Hypogene\Primary 22.23 43.54 47.54 52.33 65.91

 

Source: CNI, 2023

 

At the time that the IA block model was created, there were insufficient drill data within East Ridge to confidently interpolate rock quality. As a result, a nominal value of Q’ = 0.8 was utilized for span analyses at East Ridge based on data from Drillhole SCC-118, which is similar to the median value of the Exotic mineralization domain at Santa Cruz.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 269

 

Rock Strength

 

Most mining is planned in the mineralized domains of the Oracle Granite, and as a result, these mineral domains were the focus of the laboratory testing campaign. Figure 13-7 presents a summary of intact rock strengths based on UCS and TCS testing. While all mineral domains are similar in intact strength, the chalcocite-enriched and primary mineral domains demonstrate slightly superior intact strength.

 

 

Source: CNI, 2023

 

Figure 13-7: Intact Rock Strength Summary

 

Rock mass strengths were evaluated by applying a linear approximation to a Hoek-Brown strength envelope using laboratory strength data and modeled rock quality (GSI) data; this was done to determine linear rock mass strengths for use in pillar stability analyses. Table 13-10 presents the results. Confining stress (σ3max) was limited to a nominal 70% of the mining depth by target and assumes σ3=σ1.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 270

 

Table 13-10: Santa Cruz Rock Mass Strength by Mineral Domain Summary

 

Domain Exotic Oxide Chalcocite-Enriched Primary
Number of samples 10 12 8 12
UCS (megapascals (MPa)) 27.0 27.0 33.4 40.1
mi 22.4 14.3 20.4 13.3
GSI (75% reliability) 37.5 52.3 55.0 46.6
σ3max (MPa)* 11.8 14.1 14.1 14.1
Friction angle, Φ (°) 29.1 28.2 33.8 29.2
Cohesion (MPa) 2.09 2.51 3.14 2.59

 

Source: CNI, 2023

 

*Based on 500 m depth for Exotic, 700 m depth for all others

 

Rock Joint Fabric

 

Joint orientation data from drillholes was collected using ATV survey data. Figure 13-8 presents lower hemisphere, equal area Schmidt nets, which indicate that the deposit can be divided into two dominant structural domains including north and south structural domains. While joint orientations are similar across the entirety of the Project, a slight rotation and change in inclination was identified in the southern structural domain which influences stope sidewall stability. Figure 13-9 presents the estimated division of the north and south structural domains.

 

 

Source: CNI, 2023

 

Figure 13-8: North and South Structural Domain Stereonets

 

September 2023

SEC Technical Report Summary – Santa CruzPage 271

 

 

Source: CNI, 2023

 

Figure 13-9: North and South Structural Domains

 

13.2.5Engineering Analysis

 

Santa Cruz will utilize LHS with PBF for all Oxide and Chalcocite-Enriched targets, and DAF for all Exotic targets. At East Ridge, DAF with jammed CRF will be utilized.

 

Longhole Stope Analysis

 

The LHS method requires a top cut, which is used as a drilling platform, and a bottom cut, which is used as a mucking level. The pillar between the top cut and the bottom cut is excavated by initiating a small vertical opening (slot raise) and then by line blasts that progressively open up a large excavation with four walls (two side walls and two end walls) and a back (roof). All ore is drawn from the bottom cut sublevel. Backfill is placed to fill the void space. Backfilled pillars can then be used as the sidewalls for subsequent secondary stopes. Stopes that have total strike lengths in excess of their stable length can be paneled such that consolidated backfill is placed once the stope is at its maximum stable length. Subsequent panels can be re-slotted against the poured backfill, and stoping can recommence until the entire strike length of the stope has been mined. Risks associated with subsidence are generally eliminated due to the placement of backfill in the completed stopes.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 272

 

Stability Graph Method for Stoping Dimensions

 

The Mathews stability graph method (1980) was used to evaluate stope dimensions. This method is an empirical design tool based on case histories from hard rock mines that typically have good to very good quality rock.

 

The stability graph method accounts for key factors influencing open stope design, including rock mass strength and structure, stresses surrounding the opening, and the shape and orientation of the stope. The method is based on two calculated factors: modified stability number (N’) and hydraulic radius (S). The stability number (N’) is comprised of the following components:

 

N’ = Q’ * A * B * C

 

where:

 

Q’ = Modified Q tunneling quality index

 

A = Rock stress factor

 

B = Joint orientation factor

 

C = Gravity adjustment factor

 

The hydraulic radius (S) is calculated as follows:

 

S = (area of stope face - square meters) / (perimeter of stope face - meters)

 

N’ and S values are used to classify the excavations as one of the following:

 

·Stable zone

·Stable without support

·Stable with support

·Supported transition zone

·Caving zone

 

The analysis assumes the following:

 

·The horizontal in situ stresses are less than the vertical in situ stress (a stress ratio, k, of 0.8), which has been measured at other underground mining projects in southern Arizona

·Mining depths down to 1,000 m

·Q’ based on the 75% reliability values from modeled blocks within each 30 m mining level by mineral domain as presented in Table 13-8

·Stopes oriented in west-to-east (090° azimuth) alignment

·Flat stope backs and vertical stope walls

·Stope walls that are oriented oblique to the primary joint orientation. The south domain has less dominant jointing parallel to the stope side walls, which is advantageous for stope lengths.

·A nominal UCS of 34.5 MPa

·10 m width (based on end wall stability) and 30 m height for all stopes. Wider and/or taller stope dimensions were considered; however, this results in an excessive frequency of end walls within the transition or caving zone.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 273

 

Mathews Stability Graph Results

 

Each mining sublevel was analyzed to predict maximum stable stope configurations by mineral domain. The stability charts updated by Hutchinson and Diederichs (1996) were utilized for all stope dimension evaluations. For non-supported surfaces (such as end walls and side walls), it is recommended that the upper boundary of the transition zone between stable and caving cases be used for design (Hutchinson and Diederichs, 1996). For stope backs, the stability number was plotted to the stable with support line and assumes effective cable bolt support across the stope spans. Stopes were optimized for length for each 30 m stope sublevel while maintaining constant stope widths. With effective support installed within stope backs, stability is controlled by sidewall dimensions. Table 13-11, Table 13-12, Figure 13-10, and Figure 13-11 present results of the Mathews stability graph analyses for side and end walls for the North and South domains.

 

Table 13-11: Stability Graph Results, North Domain

 

Muck
Level
North Domain
Stability Number (N') Maximum Hydraulic Radius (m)
Oxide Chalcocite-Enriched Oxide Chalcocite-Enriched
Backs Side
Walls
End
Walls
Backs Side
Walls
End
Walls
Backs Side
Walls
End
Walls
Backs Side
Walls
End
Walls
60 0.03 4.15 3.15       4.76 4.01 3.63      
30 0.02 2.29 1.74       4.71 3.23 2.92      
0 0.03 4.01 3.05       4.75 3.97 3.59      
-30 0.02 3.15 2.39       4.73 3.63 3.28      
-60 0.03 4.97 3.77       4.78 4.29 3.88      
-90 0.04 6.13 4.65 0.27 38.95 29.58 4.81 4.63 4.19 5.47 9.12 8.25
-120 0.05 6.98 5.30 0.27 39.06 29.67 4.83 4.86 4.39 5.47 9.13 8.26
-150 0.06 8.79 6.68 0.16 22.53 17.11 4.87 5.29 4.78 5.18 7.46 6.75
-180 0.06 7.78 5.91 0.15 18.33 13.92 4.87 5.05 4.57 5.14 6.92 6.26
-210 0.08 10.18 7.73 0.15 19.27 14.64 4.94 5.58 5.04 5.16 7.05 6.37
-240 0.09 11.88 9.02 0.14 17.83 13.54 4.98 5.90 5.34 5.13 6.85 6.19
-270 0.07 7.37 5.60 0.09 10.04 7.62 4.89 4.96 4.48 4.97 5.55 5.02
-300 0.07 8.18 6.22 0.08 8.74 6.64 4.91 5.15 4.66 4.93 5.28 4.77
-330 0.08 9.32 7.08 0.06 6.14 4.66 4.95 5.40 4.88 4.85 4.64 4.19
-360 0.09 8.21 6.23 0.09 8.35 6.34 4.96 5.16 4.66 4.96 5.19 4.69
-390 0.09 8.27 6.28 0.13 12.56 9.54 4.96 5.17 4.67 5.10 6.02 5.45
-420 0.08 7.45 5.66 0.15 14.48 11.00 4.93 4.98 4.50 5.16 6.35 5.74
-450 0.07 5.59 4.25 0.11 9.02 6.85 4.90 4.48 4.05 5.04 5.34 4.83
-480 0.13 10.61 8.06 0.11 8.60 6.53 5.11 5.66 5.12 5.03 5.24 4.74
-510 0.14 11.11 8.44 0.06 4.95 3.76 5.12 5.76 5.21 4.88 4.28 3.87
-540 0.12 7.41 5.63 0.06 3.56 2.71 5.05 4.97 4.49 4.85 3.80 3.43
-570 0.14 8.99 6.83 0.04 2.27 1.72 5.13 5.33 4.82 4.78 3.22 2.91
-600 0.14 8.67 6.58       5.11 5.26 4.76      
-630                        

 

Source: CNI, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 274

 

Table 13-12: Stability Graph Results, South Domain

 

Muck
Level
South Domain
Stability Number (N') Maximum Hydraulic Radius (m)
Oxide Chalcocite-Enriched Oxide Chalcocite-Enriched
Backs Side
Walls
End
Walls
Backs Side
Walls
End
Walls
Backs Side
Walls
End
Walls
Backs Side
Walls
End
Walls
60 0.03 4.57 1.84       4.76 4.16 2.98      
30 0.02 2.52 1.02       4.71 3.35 2.40      
0 0.03 4.42 1.78       4.75 4.11 2.94      
-30 0.02 3.46 1.39       4.73 3.76 2.69      
-60 0.03 5.47 2.20       4.78 4.44 3.18      
-90 0.04 6.75 2.71 0.27 42.90 17.26 4.81 4.80 3.44 5.47 9.45 6.77
-120 0.05 7.69 3.09 0.27 43.01 17.30 4.83 5.03 3.61 5.47 9.46 6.78
-150 0.06 9.68 3.90 0.16 24.81 9.98 4.87 5.48 3.92 5.18 7.73 5.54
-180 0.06 8.56 3.45 0.15 20.18 8.12 4.87 5.24 3.75 5.14 7.17 5.14
-210 0.08 11.21 4.51 0.15 21.23 8.54 4.94 5.78 4.14 5.16 7.30 5.23
-240 0.09 13.08 5.26 0.14 19.63 7.90 4.98 6.12 4.38 5.13 7.10 5.08
-270 0.07 8.12 3.27 0.09 11.05 4.45 4.89 5.14 3.68 4.97 5.75 4.12
-300 0.07 9.01 3.63 0.08 9.62 3.87 4.91 5.34 3.82 4.93 5.46 3.91
-330 0.08 10.27 4.13 0.06 6.76 2.72 4.95 5.60 4.01 4.85 4.80 3.44
-360 0.09 9.04 3.64 0.09 9.20 3.70 4.96 5.34 3.83 4.96 5.37 3.85
-390 0.09 9.11 3.66 0.13 13.83 5.56 4.96 5.36 3.84 5.10 6.24 4.47
-420 0.08 8.20 3.30 0.15 15.95 6.42 4.93 5.15 3.69 5.16 6.58 4.71
-450 0.07 6.16 2.48 0.11 9.94 4.00 4.90 4.64 3.32 5.04 5.53 3.96
-480 0.13 11.68 4.70 0.11 9.47 3.81 5.11 5.87 4.20 5.03 5.43 3.89
-510 0.14 12.24 4.92 0.06 5.45 2.19 5.12 5.97 4.28 4.88 4.44 3.18
-540 0.12 8.16 3.28 0.06 3.92 1.58 5.05 5.15 3.69 4.85 3.93 2.82
-570 0.14 9.90 3.98 0.04 2.50 1.00 5.13 5.52 3.96 4.78 3.33 2.39
-600 0.14 9.55 3.84       5.11 5.45 3.90      
-630                        

 

Source: CNI, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 275

 

 

Source: CNI, 2023

 

Figure 13-10: North Domain Stability Graph Results (10 m Wide, 30 m High)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 276

 

 

Source: CNI, 2023

 

Figure 13-11: South Domain Stability Graph Results (10 m Wide, 30 m High)

 

Ground Support for Stopes and Production Headings

 

To maintain back stability, cable bolt support in addition to primary support is required for all stope backs. Based on the empirical charts by Hutchinson and Diederichs, cables (single strand) should be spaced on a nominal 2 m square pattern and should be a minimum of 6 m in length. Table 13-13 presents a summary of ground support for stope top cuts.

 

Figure 13-12 presents an example of stope cable support.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 277

 

 

Table 13-13: Stope and Production Headings Ground Support

 

Primary/
Secondary
Support
Category
Q
value
Estimated
RMR76\
GSI
% of
MSO
Shapes
Advance
Length
(m)
Support Type
Primary
support
Category 1 >1.0 >44 83 3* 2.4 m #7 rebar** on 1.2 m x 1.2 m spacing with welded mesh (10 cm/6 Ga.) to within 1.5 m of sill
Category 2 0.7 to 1.0 <44 17 2.5 2.4 m #7 rebar** on 1.2 m x 1.2 m spacing with welded mesh (10 cm/6 Ga.) and 5 cm of shotcrete to within 1.5 m of sill
Secondary
support
All stope top cuts 6.0 m cable bolts (single strand) on 2.0 m x 2.0 m spacing in the backs (minimum three each per row); installed prior to stoping

 

Source: CNI, 2023

 

cm = centimeter

 

4 m advances are possible when Q > 3.0; estimated 45% of MSO shape

 

**12-ton capacity inflatable friction bolts are acceptable alternative to rebar in headings with <1 year service life

 

***Stoping not recommended in areas with Q < 0.7

 

RMR76: Bieniawski’s rock mass rating system

 

 

Source: CNI, 2023

 

Figure 13-12: Cable Bolt Support

 

Dilution Estimates Using the ELOS Method

 

The equivalent length of overbreak was estimated using the ELOS chart (Clark and Pakalnis, 1997). The ELOS chart is an extension of the Mathews stability graph, using empirical evidence to estimate the amount of overbreak for different ground conditions at varying hydraulic radii. Intentionally mining stopes of poorer rock quality at widths beyond their stable configuration will lead to additional sloughing. The ELOS method is widely used to predict dilution in LHS mining.

 

Table 13-14 presents the ELOS design zones. Dilution estimates based on the ELOS design zones were predicted by mineral domain and stope level at the specified dimension. Dilution estimates are presented in Table 13-6 and plotted on Figure 13-13 and Figure 13-14 for the North and South structural domains, respectively.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 278

 

Table 13-14: ELOS Design Zones

 

ELOS Range ELOS Design Zones
ELOS < 0.5 m Blast damage only; surface is self-supporting.
ELOS = 0.5 to 1.0 m Minor sloughing; some failure from unsupported stope wall should be
anticipated before a stable shape configuration is achieved.
ELOS = 1.0 to 2.0 m Moderate sloughing; significant failure from unsupported stope wall is
anticipated before reaching stable shape configuration.
ELOS > 2.0 m Severe sloughing; large failures from unsupported stope wall should
be anticipated. Wall collapse is possible.

 

Source: CNI, 2023

 

 

Source: CNI, 2023

 

Figure 13-13: North Domain ELOS Estimates (10 m Wide, 30 m High)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 279

 

 

Source: CNI, 2023

 

Figure 13-14: South Domain ELOS Estimates (10 m Wide, 30 m High)

 

PBF

 

Stope panels will be backfilled with PBF delivered via a reticulation system. The purpose of the PBF is to support and confine the sidewalls of primary stopes and allow rapid cure so that stope panels can be re-slotted against PBF endwalls. Consequently, the PBF must remain stable at a full vertical stope height when adjacent secondary stopes are opened, or when re-slotting a stope panel. PBF strength estimates by stope height were calculated using the frictionless wedge model proposed by Mitchell et al. and are presented on Figure 13-15. Assuming a 35 m total exposed wall height, 600 kPa are required to achieve a 1.5 factor of safety (FoS).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 280

 

 

Source: CNI, 2023

 

Figure 13-15: PBF Strength Estimates

 

An estimated 3% cement in solids will be required to achieve the strength target, as presented on Figure 13-16 (Saw, Villaescusa, 2011); this should allow for sufficient cure (7 days) in the case that a stope panel is backfilled and the subsequent panel is being re-slotted against the cured fill. Laboratory testing on Santa Cruz tailings materials is ongoing to verify adequacy for PBF usage.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 281

 

 

Source: CNI, 2023

 

Figure 13-16: Cement in Solids Estimate

 

Some secondary stopes will not be exposed for re-slotting or adjacent mining and as a result do not need to achieve a free-standing strength criterion. In these cases, a minimum 2% to 3% binder is necessary to prevent liquefaction. To be suitable for trafficability (mobile equipment operating atop the fill), a capping fill strength of 500 kPa is required for the uppermost nominal 5 m.

 

Dilution Estimates Using the ELOS Method

 

A staggered 1-3-5 sequence will be utilized, as presented on Figure 13-17. The sequence offers the advantage of allowing several primary stopes to be mined simultaneously, which increases productivity. To maintain pillar stability, both sides of a pillar cannot be mined simultaneously. Stopes should be staggered such that panels are backfilled before opening the nearest stope in section. By utilizing this sequence with a staggered leading panel, a 3x pillar width (of rock or backfill) is maintained between concurrently open stope panels. Furthermore, one full stope sublevel must be mined above a secondary pillar before recovering it. Stope top cut and bottom cut development cannot commence until the adjacent stopes are filled to the entire vertical extent (Figure 13-18). As the stope sequence progresses, mining-induced stress redistributions will occur, which may be detrimental to later stage stope recovery and accesses.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 282

 

 

Source: CNI, 2023

 

*BF = Back Filled

 

Figure 13-17: Staggered 1-3-5 Sequence Plan View

 

 

Source: CNI, 2023

 

*BF = Back Filled

 

Figure 13-18: 1-3-5 Sublevel Vertical Sequence Section View

 

Access Pillars and Sill Pillars

 

Level haulage should be set back at least 40 m (to haulage centerline) from the nearest stope brow, as presented on Figure 13-19. Access should be shared between the primary stope and an adjacent secondary stope in order to maintain sufficient rock pillar between the accesses, stopes, and haulage to accommodate abutment loadings. Pillar stability was evaluated using Wilson’s confined core method of pillar stability (1972).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 283

 

 

Source: CNI, 2023

 

Figure 13-19: Haulage Setback Minimum Distances

 

As presented on Figure 13-20, a sill pillar is planned between the minus 300 to minus 270 m elevations to divide stoping blocks so that the uppermost stopes may be brought into production prior to completing development to the lower levels. The 30 m sill pillar was evaluated using Carter’s scaled span method (2014). This method considers the thickness, length, and width of the sill pillar to predict stability based on rock quality. Rock quality estimates are based on the modeled blocks within the sill pillar zone, as presented in Table 13-15. Figure 13-21 presents the results of the sill pillar analysis. The resulting classifications of the sill pillar (Classes B to D) are considered acceptable provided that monitoring instrumentation is installed and individual stopes beneath the sill pillar are open for no longer than 1 year of service life based on Carter’s exposure guidelines presented on Figure 13-22.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 284

 

 

Source: CNI, 2023

 

Figure 13-20: Proposed Sill Pillar

 

Table 13-15: Sill Pillar Rock Qualities and Carter Classification

 

Q' Reliability Sill Pillar Thickness (m) FoS Carter Class
50% 2.70 30 1.4 B
75% 1.62 1.1 D

 

Source: CNI, 2023

 

 

Source: CNI, 2023

 

Figure 13-21: Carter’s Scaled Span Sill Pillar Estimate

 

September 2023

SEC Technical Report Summary – Santa CruzPage 285

 

 

Source: CNI, 2023

 

Figure 13-22: Carter’s Scaled Span Exposure Guidelines

 

Drift and Fill Analysis

 

In poor rock quality or areas which do not have appropriate geometry for LHS, DAF mining will be conducted. Specific areas where DAF are to be utilized include the Exotic mineralization of Santa Cruz and East Ridge. In DAF mining, the ore zone is split into drift-sized slices or lifts. Each slice is mined and then promptly backfilled using CRF jammed tightly to the back. After jamming is completed, adjacent drifts can be mined alongside the backfilled drifts in primary-secondary-tertiary (PST) sequence. Once an entire slice horizon is depleted (typically in a chevron pattern or transverse based on the size and shape of the orebody), DAF mining can progress overhand, operating atop the jammed CRF.

 

Rock quality estimates of the East Ridge and Exotics mineral domains are summarized below:

 

·East Ridge Q’ estimate: 0.6 to 1.0 based on SCC-118 due to paucity of block model data; however, it should be noted that subsequent data (collected after the completion of the block model) from East Ridge indicates improved rock quality (RQD between 30% and 50%) within the mineralized zones.

·Exotics of Santa Cruz Q’ estimate: 0.8 based on the median block model estimate from all exotic data.

 

For all DAF span and height estimation, Q’ was estimated as 0.8, which correlates to an RMR76 equal to 42. Based on this RMR, a 6 m design span will be used based on the critical span curve presented on Figure 13-23 (Brady, Pakalnis et al., 2004). Drift floors can be excavated to a maximum vertical slice height of 9 m based on Grimstad and Barton’s support chart (1993), which also predicts similar spans (Figure 13-24). Due to the temporary service life of each drift and narrow spans, ground support can be limited to primary support specified for production headings, as summarized in Table 13-13. Furthermore, due to the precise method of mining, dilution from overbreak is generally considered minimal.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 286

 

 

Source: CNI, 2023

 

Figure 13-23: Critical Span Curve

September 2023

SEC Technical Report Summary – Santa CruzPage 287

 

  

 

 

Source: CNI, 2023

 

Figure 13-24: Ground Support Chart for DAF Span and Maximum Height

 

Cemented Rock Backfill

 

To achieve full recovery of the orebody in DAF, drifts must be carefully jammed with backfill. Cemented rock backfill can be trucked into the drifts and compacted using a rammer jammer to achieve tight filling to the back.

 

According to the Mitchell Solution, for a maximum 9 m-tall slice, an estimated 400 kPa are required to achieve a safety factor of 2. A nominal 3% cement binder is required to achieve adequate binder dispersion through the aggregate fill, prevent liquefaction, and be suitable for trafficking when mobile equipment is operating overhand. It is currently uncertain whether run-of-mine waste will be suitable for CRF usage at Santa Cruz. Additional investigation should be conducted to address this.

 

PST Sequence

 

The PST sequence (Figure 13-25) enables access to multiple mining faces that can be advanced simultaneously, which improves productivity along an operating level (ore slice). However, primary and secondary cuts must be jammed tightly, or tertiary cuts will likely be irrecoverable.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 288

 

 

 

Source: CNI, 2023

 

Figure 13-25: PST DAF Mining Sequence

 

13.2.6Primary Ground Support for Development

 

Primary ground support for development varies based on the anticipated ground conditions estimated from the geotechnical block model. Table 13-16 summarizes the ground support specifications for permanent development, which includes four discrete ranges of ground conditions specified by Q’.

 

Table 13-16: Primary Ground Support for Permanent Development

 

  Support
Category
Q value Estimated
RMR76\GSI
Advance
Length (m)
Support Type
  Category 1 >2.0 >50 3.0 2.4 m #7 rebar on 1.2 m x 1.2 m spacing with welded mesh (10 cm/6 Ga.) to within 1.5 m of sill
  Category 2 0.7 to 2.0 41 to 50 2.5 2.4 m #7 rebar on 1.2 m x 1.2 m spacing with welded mesh (10 cm/6 Ga.) and 5 cm of shotcrete to within 1.5 m of sill
  Category 3 0.07 to 0.7 20 to 40 1.2 10 cm of fiber-reinforced shotcrete (FRS) and 2.4 m #7 rebar on 1.2 m x 1.2 m spacing with welded mesh (10 cm/6 Ga.) down to sill
  Category 4 <0.07 <20 0.5 to 1.0 15 cm of FRS and 2.4 m #7 rebar on 1.2 m x 1.2 m spacing with welded mesh (10 cm/6 Ga.) down to sill with 6 count #7 rebar arch spaced each 2.4 m and encased in 35 mm of shotcrete; forepoling (spiling)

 

Source: CNI, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 289

 

Ground support at a minimum will include 2.4 m rebar (minimum #7 gauge, Grade 60 steel) on 1.2 m x 1.2 m spacing and welded wire mesh. Additional ground support (shotcrete, fibercrete, steel arches, etc.) is required in zones of poor or extremely poor-quality ground. In Category 4 ground, spiling or forepoling is required.

 

Additional, deeper ground support is necessary for three-way and four-way intersections. Four-way intersections should be avoided whenever possible due to wider spans. Ground support specifications in intersections and passing/muck bays are in addition to the bolting standard for advance drifting. Because of the increased spans, secondary (deep) bolt lengths of 3.65 m on 1.8 m x 1.8 m spacing are required. Deep support should include either cable bolts (single or double strand) or #8 rebar (minimum Grade 60 steel) to provide the additional capacity to support deeper wedges, which are more likely in wider spans.

 

Ground support categories were estimated using the ground support chart developed by Grimstad and Barton (1993), as presented on Figure 13-26. An excavation support ratio (ESR) value of 1.6 was assumed, which is typical for permanent mine openings. The support requirements for production headings (Table 13-13) utilize an ESR of 3.0 due to their more temporary service lives.

 

 

 

Source: CNI, 2023

 

Figure 13-26: Ground Support Category Estimates Using the Ground Support Chart

 

Where development is intended to be permanent infrastructure with a service life greater than 1 year, fully grouted resin rebar bolts are required. Friction-type bolts, such as Swellex or Split Sets, are susceptible to corrosion in environments that are rich in sulfide mineralization. However, in drifts with shorter service lives (<1 year), inflatable friction bolts may be a suitable alternative to rebar.

 

Bolt lengths (2.4 m) and spacing are based on the results of both kinematic wedge deterministic analyses and empirical analysis. Wedge stability was evaluated at various tunnel azimuth orientations based on joint orientations from ATV data. Figure 13-27 presents the results of the kinematic wedge analyses by area, with orientations resulting in small skinny wedges truncated to a maximum FoS of 10. The ATV data were divided spatially into two areas with differing structural trends, as presented on Figure 13-28. The structural domains are identical to the North and South structural stoping domains.

 

 

Source: CNI, 2023

 

Figure 13-27: Kinematic Wedge Analysis Results

 

September 2023

SEC Technical Report Summary – Santa CruzPage 290

 

 

 

Source: CNI, 2023

 

Figure 13-28: Structural Analysis with Dominant Joint Set Orientations

 

13.2.7Boxcut and Decline Access

 

A boxcut of nominal 20 m total depth will be excavated into the alluvium to establish a portal face for decline entry. Multiple decline options were evaluated which access the orebody from the north and west. The most current option is presented in Figure 13-29, which also includes the distribution of development within ground support categories.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 291

 

 

Source: CNI, 2023

 

Figure 13-29: Isometric View of Most Recent Mine Design with Ground Support Estimates

 

Based on rock qualities and strengths along the potential routes, decline development is amenable to road header development with a shield, with sporadic drill and blast required through stronger rock types (thin intervals of diabase). Additional details regarding ground characterization and decline development requirements are summarized in the CNI memo, Decline Characterization and Support Estimation (December 2022). The actual locations and designs for the boxcut entry and decline railveyor pathways are still to be determined.

 

13.3Hydrogeology

 

Historical hydrogeological data available for the Santa Cruz Project was reviewed and evaluated to develop the hydrogeological conceptual site model. Using the historical data and the results of recent hydrogeologic testing conducted by Ivanhoe, the groundwater flow model developed by Montgomery & Associates was updated and finalized. The groundwater flow model was used to evaluate multiple passive and active dewatering scenarios for the proposed mine plan.

 

13.3.1Surface Water

 

The Santa Cruz Project area is located within the Gila River basin, and contains two surface water features in the northeast portion of the Project area, the Santa Cruz Wash Canal and the North Branch Santa Cruz Wash. The Santa Cruz Wash Canal confluences with the North Branch Santa Cruz Wash in the most northern portion of the Project property, which then reports to the Gila River further to the northwest via a series of irrigation canals and levees. Both surface water features are ephemeral with the exception of intermittent flow originating from upstream municipal sources. Flow direction is roughly southeast to northwest.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 292

 

A surface water monitoring program that involves collecting samples for water quality at multiple points along the North Branch Santa Cruz Wash and Santa Cruz Wash Canal began in 2023 and will continue, on a quarterly basis, for baseline studies.

 

13.3.2Hydrogeology Investigations

 

The Santa Cruz Project has been the subject of multiple studies aimed at characterizing the hydrogeologic properties of the stratigraphy within the Project area and the surrounding region. Aquifer testing completed during the late 1970s and early 1980s at the behest of the Santa Cruz Copper Company (e.g., Harshbarger & Associates, 1978a; Harshbarger & Associates, 1978b; Harshbarger & Montgomery, 1980; Harshbarger & Montgomery, 1981) established an early conceptual hydrogeological model and characterized the physical properties of major water-bearing geologic units. Continuing in the late 1980s through the end of the 1990s, additional hydrogeologic studies were completed by the Santa Cruz Joint Venture and the U.S. Bureau of Mines in support of the Santa Cruz In Situ Copper Mining Research project (Montgomery & Associates, 1989; 1990a; 1990b; 1991; 1992a; 1992b; 1992c; 1993; 1995; 1997; and 1998). More than fifteen additional pumping tests were conducted at five new hydrogeologic characterization wells and five new test wells. During this period, fluid movement investigations using spinner flowmeter logging provided additional estimates of the hydraulic conductivity of different hydrogeologic zones.

 

More recently, IE contracted Montgomery & Associates to conduct packer testing at the Santa Cruz Project to estimate hydraulic parameters for bedrock and conglomerate lithologic units near the proposed decline and part of the proposed underground mine (Montgomery & Associates, 2023). Between October 22, 2022 and April 11, 2023, forty-five successful packer tests were completed at depths ranging from 182.1 to 684.6 m below ground surface in exploration boreholes SCC-101, SCC-106, SCC-111, SCC-124, and SCC-128. Presently, IE monitors pore pressure, which can be converted to groundwater elevation, in 71 vibrating wireline piezometers that were installed starting in 2021 across 14 locations (Figure 13-30).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 293

 

 

Source: INTERA, 2023

 

Figure 13-30: Boreholes and Well Locations of Collected Hydrogeology Data used in Groundwater Model

 

13.3.3Hydrogeologic Conceptual Site Model

 

The hydrogeology of the Santa Cruz Project can be generally divided into 3 main rock types: alluvium, conglomerates, and oracle granite. Each rock type can be further subdivided into different hydrostratigraphic units, which are portions of a body of rock that by virtue of their physical properties have a distinct influence on the storage or movement of groundwater. The hydraulic properties based on previous test work for each of these hydrostratigraphic units are described in INTERA (2023) and are summarized below.

 

Alluvium

 

The quaternary alluvium, or basin-fill, is composed of poorly sorted silt and sand, over an area approximately 70 to 100 m thick. In the Santa Cruz Project area, groundwater levels are below the alluvial deposits.

 

Conglomerates

 

There are four Tertiary conglomerate units recognized in the study area: the Gila conglomerate, the Whitetail conglomerate, the Basal conglomerate, and the Mafic conglomerate. The Gila conglomerate underlies the alluvium and ranges in thickness from 150 to 300 m. The Whitetail conglomerate is considered to be the stratigraphically lower and older equivalent of the Gila conglomerate. The Whitetail conglomerate is separated from the Gila conglomerate by a thin layer of the Apache leap tuff and ranges in thickness from approximately 100 to 400 m in the Santa Cruz Project area. The Gila conglomerate and whitetail conglomerate are thickest where they overlie the paleo-valleys of the faulted and tilted oracle granite. Both the Gila conglomerate and the whitetail conglomerate are characterized by semi-consolidated to consolidated coarse sediments and consist of cobble to boulder sized clasts with interbedded layers of moderately to poorly sorted sand and gravel. The Mafic conglomerate and Basal conglomerate are not extensive formations and are only present in localized areas across the Santa Cruz Project area.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 294

 

Depth to groundwater in the Santa Cruz Project area is approximately 150 m below ground surface, in the Gila conglomerate. Most early aquifer test investigations on the conglomerates were completed across the entirety of the conglomerate units, and occasionally included alluvium, and often were referred to as part of the basin fill deposits. The hydraulic conductivity of the undifferentiated conglomerates range from approximately 1.8E-4 centimeters per second (cm/s) to 4.2E-3 cm/s (summarized in INTERA, 2023). Analysis of recent borehole packer testing by Montgomery & Associates (2023) provided estimates of hydraulic conductivity for distinct units including 7.1E-6 cm/s for the lower Gila Conglomerate. Hydraulic conductivity estimates of packer tests on the Whitetail Conglomerate range from a minimum of 1.8E-7 cm/s to a maximum of 3.2E-6 cm/s (Montgomery & Associates, 2023). Additional estimates of hydraulic conductivity from tests conducted in the lower portions of the conglomerates range from 1.3E-5 cm/s to 8.3E-4 cm/s (Montgomery & Associates, 1997). Results of the aquifer tests and packer tests in the lower portion of the conglomerates indicate that the permeability of the conglomerates decreases with depth.

 

Oracle Granite

 

The precambrian oracle granite unconformably underlies the conglomerate units at varying depths of approximately 200 to 650 m below ground surface due to faulting and tilting caused by tectonic extension events of the mid-Cenozoic Period. Laramide monzonite porphyry and younger Precambrian diabase dikes and sills intrude the oracle granite. The upper part of the oracle granite comprises a leached zone that has been weathered, fractured, and locally brecciated. Copper oxide and sulfide zones with varying degrees of mineralization exist within the lower part of the oracle granite. Because of these different zones, the hydraulic conductivity of the oracle granite is highly variable, ranging from 9.9E-12 cm/s to 4.4E-3 cm/s (summarized in INTERA, 2023), and generally decreases with depth (Montgomery & Associates, 1989).

 

Emplaced within the oracle granite are laramide quartz monzonite porphyry intrusions dipping approximately 30˚ to 40˚ to the southwest (M&A, 1992b) that make up about 15% of the host rock within the Santa Cruz deposit (Kreis, 1982). Estimated hydraulic conductivity of the laramide porphyry is between 2.1E-7 cm/s and 2.1E-6 cm/s, based on packer tests conducted by Montgomery & Associates (2023). The oracle granite is also intruded by diabase dikes and sills dipping approximately 40˚ to 50˚ to the south-southwest (Montgomery & Associates, 1992b; Nelson, 1991). Previous work summarized in INTERA (2023) shows that hydraulic conductivity of the diabase dikes ranges from 4.9E-12 cm/s to 7.1E-6 cm/s.

 

13.3.4Groundwater Flow Model

 

A preliminary groundwater flow model was developed by Montgomery & Associates in late-2022 and early-2023. The model was further refined and finalized by INTERA (2023) to estimate the mine dewatering requirements for the proposed Mine Plan described in Section 14.6. The model described in INTERA (2023) was used to compare mine dewatering requirements under passive and active dewatering scenarios.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 295

 

The mine plan contains several important attributes used in adapting the model to evaluate residual passive inflow. For each mine working, e.g., decline, ore drives, stopes, etc, the mine plan outlines the scheduled construction of the features as well as the specified ground type that the workings will be constructed in. The ground type reflects the level of sealing, such as shotcrete, that will be applied to the opening once constructed. One modification was made for implementation of the mine plan in the model: the footwall and ore drives extending into the conglomerate in the Santa Cruz area were modified to reflect the lower hydraulic conductivity of the granite to further reduce passive inflows. Under the passive scenario, groundwater pumping was not used to depressurize the aquifer and reduce inflows.

 

Under the active dewatering scenario, different rates and distributions of groundwater pumping wells were used to evaluate the potential benefits of reducing inflows through pumping from the surface during year 2 of mine development when the upper part of the decline is constructed. The residual passive inflow for the decline is especially important in year 2 of mining. The hydraulic conductivity of the conglomerate is higher in the area where the upper decline is planned, which allows for higher inflow rates to the decline during construction through the conglomerate. To reduce inflows during this period, active pumping scenarios were investigated to reduce the hydraulic pressure in the aquifer leading to reduced residual passive inflow in the decline. In the active dewatering scenario, pumping occurs during year 1 and 2 of mine development only.

 

The simulated residual passive inflow for the 25-year LoM, which represents the annual average residual passive inflow rates by year, is shown in Figure 13-31 for the active dewatering scenario. Results are shown for the Santa Cruz area, the East Ridge area, the Exotics, the combined decline and railveyor (presented as the decline), and the total average annual residual passive inflow of all areas of the mine plan combined. A sensitivity analysis of active dewatering simulations showed that 3 wells along the decline, completed in the conglomerate, each pumping 1,000 gpm, would reduce the residual passive inflow in the conglomerate in year 2 from 2,054 gpm to 986 gpm (as shown in Figure 13-31). The effects of pumping in years 1 and 2 on residual passive inflow after year 2 are negligible. Model results show that the residual passive inflow for the first 10 years of mining are at or below 12,000 gpm. From year 11 through 25 of LoM, the residual passive inflow ranges from approximately 15,000 gpm to 18,000 gpm.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 296

 

 

 

Source: INTERA, 2023

 

Figure 13-31: Mine Residual Passive Inflow (RPI) by Area and Total Mine Plan Combined with Active Dewatering During Years 1 and 2

 

The distribution of residual passive inflow across the mine is shown in Figure 13-32. The residual passive inflow for the decline is highest along the upper part of the decline where 30+ gpm inflows are indicated. This is the area of highest concern for inflows during construction of the Decline and is where the pumping in years 1 and 2 has the greatest effect on reducing residual passive inflow. Other areas of the mine show varying levels of inflow. The Exotics show a high percentage (86%) of higher residual passive inflow due to their location in the conglomerate. The Santa Cruz and East Ridge areas show varying residual passive inflow with high percentages of 0 to 5 gpm and 5 to 15 gpm inflows. These areas of lower residual passive inflow represent both stopes, that are only open for short periods during mining, and regions of low hydraulic conductivity in the oracle granite and porphyry.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 297

 

 

Source: INTERA, 2023

 

Figure 13-32: Model Estimates of Residual Passive Inflows Mine Workings

 

13.4Mine Dewatering

 

13.4.1Ramp Dewatering

 

During initial ramp construction, three surface dewatering wells will be utilized in Year 1 and Year 2 to depressurize the portion of the decline hosted in the conglomerate. A number of scenarios were evaluated with the numerical groundwater model using three variables: number of wells, total pumping rate, and well locations. The results for the optimal scenario showed that three specifically located dewatering wells with a total discharge of 3,000 gpm provided appropriate depressurization and reduction in residual passive inflow with 2 years of pumping. The scenario’s pumping rate of 3,000 gpm was effective to provide safe development through the water table at this location. The analysis also showed that pumping durations longer than 2 years had negligible improvements to conditions once shotcrete was properly completed in the target area. Figure 13-33 shows the surface dewatering well locations near the decline.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 298

 

 

 

Source: INTERA, 2023

 

Figure 13-33: Surface Dewatering Well Locations

 

13.4.2Mining Area Dewatering

 

The maximum expected water flow to the mine that needs to be managed is 18,000 gallons per minute (GPM), and the pumping system is designed to handle 20,000 gpm. Figure 13-31 shows the annual average RPI for the different zones through the LoM.

 

The mine pumping system is divided into two systems, the Santa Cruz upper system and the East Ridge – Santa Cruz lower system. The Santa Cruz upper system consists of a main sump on level -270 with two trains of 4 pumps in series. The water is pumped to an intermediate pumping station on the decline at elevation 75 with two trains of 4 pumps in series to pump the water to surface.

 

The East Ridge – Santa Cruz lower system will pump water from Santa Cruz lower to East Ridge and then to the surface. At East Ridge, one sump is installed on level -150 with two trains of 3 pumps in series. The mine water is pumped to an intermediate pumping station, different from the one in the Santa Cruz upper system, on the decline at elevation 75 with two trains of 4 pumps in series to pump the water to surface. At Santa Cruz lower, a sump is installed on level -570 with two trains of 3 pumps in series pumping to an intermediate sump on level -270. The intermediate sump consists of 2 trains of 3 pumps in series to pump the water to the East Ridge sump and subsequently to surface.

 

Initially, one train can be operational and the other one will be on standby. Eventually, the standby train will need to be operational more frequently.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 299

 

All pumps use high wear-resistant slurry pumps. Santa Cruz upper system uses dual 16” schedule 40 steel pipes as the main pipe with 16” DR11 HDPE pipes where appropriate to surface. The Santa Cruz lower sump uses dual 12” Schedule 40 steel pipes as the main pipe with 12” DR11 HDPE pipes where appropriate. The East Ridge sump uses dual 16” schedule 40 steel pipes as the main pipe with 16” DR11 HDPE pipes where appropriate to surface. Pipes for the Santa Cruz upper and East Ridge will run on the decline. Pipes for Santa Cruz lower can either run on the decline or in vertical raises. Figure 13-34 shows the dewatering system piping and instrumentation diagram (P&ID).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 300

 

 

Source: Miller, 2023

 

Figure 13-34: Dewatering System P&ID

 

September 2023

SEC Technical Report Summary – Santa CruzPage 301

 

Sinking skids consisting of 400 HP pumps that will be used during the decline development. Additionally, 15 HP to 30 HP transfer pumps will dewater the active headings.

 

Keeping water away from working faces and managing the inflows will be a key to achieving the mine plan presented here, particularly for the main decline,

 

13.5Identifying Potentially Minable Areas

 

For the Santa Cruz Oxide and chalcocite enriched domains, a LHS method is selected. The Santa Cruz Exotic domain and East Ridge deposit will use a DAF mining method. Stope optimization (MSO) within Deswik software was used to determine potentially economically minable material. Wall dilution was not applied at the optimization stage. A range of mining cut-offs were run to identify higher grade mining areas and understand the sensitivity of the deposit to CoG.

 

Table 13-17 shows stope optimization parameters used. Once stopes are generated, the stopes are cut to the appropriate lengths based on the location and sequence as determined by geotechnical data.

 

Table 13-17: MSO Parameters

 

  Parameter Units LHS DAF
  Stope width m 10 6
  Stope height m 30 9
  Stope length m 5 to 500 5 to 500
  Copper cut-off % 1.0 1.0

 

Source: SRK, 2023

 

Table 13-18 through Table 13-20 and Figure 13-35 through Figure 13-37 show the stope optimization results.

 

Table 13-18: Santa Cruz Deposit MSO Summary

 

  Santa Cruz Deposit
  Oxide and Chalcocite MSO Summary
  Cut-Off (%) Tonnage (kt) AsCu (%) CnCu (%) TCu (%) Contained Cu (Mlb)
  0.60 190,113 0.85 0.31 1.32 5,532
  0.80 154,085 0.95 0.34 1.47 4,994
  0.90 136,810 1.01 0.34 1.55 4,675
  1.00 121,724 1.07 0.35 1.62 4,347
  1.10 107,077 1.13 0.36 1.70 4,013
  1.20 93,664 1.19 0.37 1.77 3,655
  1.30 81,976 1.24 0.39 1.85 3,343
  1.40 70,748 1.28 0.42 1.92 2,995
  1.50 60,595 1.31 0.45 2.00 2,672
  1.75 39,308 1.39 0.53 2.20 1,906
  2.00 24,387 1.44 0.64 2.40 1,290
  2.25 13,980 1.50 0.75 2.61 804
  2.50 7,212 1.47 0.94 2.83 450

 

Source: SRK, 2023

September 2023

SEC Technical Report Summary – Santa CruzPage 302

 

Table 13-19: Santa Cruz Exotic Deposit MSO Summary

 

Santa Cruz Deposit
Exotic MSO Summary
Cut-Off (%) Tonnage (kt) AsCu (%) CnCu (%) TCu (%) Contained Cu (Mlb)
0.60 11,230 1.45 0.12 1.85 458
0.80 8,553 1.74 0.14 2.21 417
0.90 7,625 1.88 0.15 2.37 398
1.00 6,931 2.00 0.16 2.51 384
1.10 6,355 2.11 0.16 2.64 370
1.20 5,818 2.22 0.17 2.78 357
1.30 5,337 2.33 0.18 2.91 342
1.40 4,947 2.43 0.19 3.03 330
1.50 4,553 2.53 0.20 3.16 317
1.75 3,833 2.75 0.22 3.45 292
2.00 3,237 2.97 0.25 3.72 265
2.25 2,736 3.20 0.27 4.01 242
2.50 2,368 3.39 0.29 4.25 222

 

Source: SRK, 2023

 

Table 13-20: East Ridge Deposit MSO Summary

 

East Ridge Deposit
MSO Summary
Cut-Off (%) Tonnage (kt) AsCu (%) CnCu (%) TCu (%) Contained Cu (Mlb)
0.60 59,054 0.47 0.45 1.06 1,380
0.80 36,245 0.62 0.55 1.29 1,031
0.90 28,706 0.70 0.60 1.40 886
1.00 23,200 0.77 0.64 1.51 772
1.10 19,087 0.83 0.69 1.61 677
1.20 15,435 0.91 0.73 1.72 585
1.30 12,345 0.99 0.79 1.84 501
1.40 9,898 1.06 0.84 1.96 428
1.50 8,124 1.13 0.89 2.07 371
1.75 5,346 1.28 1.00 2.31 272
2.00 3,137 1.47 1.14 2.62 181
2.25 2,130 1.62 1.25 2.86 134
2.50 1,526 1.74 1.34 3.05 103

 

Source: SRK, 2023

 

 

Source: SRK, 2023

 

Figure 13-35: Santa Cruz Oxide and Chalcocite Undiluted MSO Results (Looking to the Northwest)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 303

 

 

Source: SRK, 2023

 

Figure 13-36: Santa Cruz Exotic Undiluted MSO Results (Looking to the Southwest)

 

 

Source: SRK, 2023

 

Figure 13-37: East Ridge Undiluted MSO Results (Looking to the West)

 

13.5.1Dilution

 

The mining dilution estimate for LHS is based on ELOS (Clark and Pakalnis, 1997). ELOS is an empirical design method that is used to estimate the amount of overbreak/slough that will occur in an underground opening based on rock quality and the hydraulic radius of the opening. ELOS was applied to in situ rock exposed and to the PBF walls wherever mining will occur adjacent to a secondary stope. In addition to the ELOS allowances, an additional allowance was used to account for backfill dilution from the floor when mucking a stope. Table 13-21 shows the dilution assumptions.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 304

 

Table 13-21: Dilution Assumptions

 

 

Source: CNI, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 305

 

Backfill dilution is assumed to have zero grade. The rock portion of primary stopes in the Santa Cruz longhole areas is expected to contain grade. The grade applied to rock dilution is based on querying block model grades just outside the stope designs in a representative area. This exercise showed that the dilution was approximately 75% of the stope grade, and therefore for the mine plan the grade applied to the rock dilution is 75% of the stope grade. For drift and fill areas, dilution is assumed to be 5% based on benchmarking data and dilution is assumed to have zero grade. Development headings are assumed to have 0% dilution. Table 13-22 summarizes the total dilution for the various stopes by mining method.

 

Table 13-22: Total Dilution

 

Description Value
LHS dilution in primaries 6%
LHS dilution in secondaries 10%
LHS dilution grade 75%
DAF stope dilution 5%
Development dilution 0%

 

Source: SRK, 2023

 

Further dilution studies are recommended for future work to confirm or modify the factors used here.

 

13.5.2Stope Recovery Factor

 

Stope recovery factors of 91% and 98% were used for LHS and DAF, respectively. The following items were considered to calculate these factors:

 

·Material loss into floor of 0.1 m

 

·Material loss to mucking along sides and in blind corners

 

·Additional loss factor due to rockfalls, misdirected loads, and other geotechnical reasons

 

A development recovery factor of 100% was used for all lateral development. Tight filling will be necessary to achieve these recoveries.

 

13.5.3Development Allowance

 

Additional ramp allowance factors were used to account for additional excavations not included in the design; Table 13-23 summarizes these allowance assumptions. These items should be designed at the detailed planning stage. The average length item shown in the table is the representative length of ramp that the listed allowances are applied to.

 

Table 13-23: Development Allowance Assumptions

 

Type Units Main Ramp Railveyor
Average length m 500 100
Drill bays m3 135  
Electrical bays m3 91  
Pump stations m3 324  
Passing bays m3 780  
Railveyor drive station m3 0 33
Total additional allowance m3 1,330 33
Expressed as a percentage of representative length of development % 9.8 1.2

 

Source: SRK , 2023

m3: Cubic meter

 

September 2023

SEC Technical Report Summary – Santa CruzPage 306

 

13.5.4Block Model Indicator Shells

 

Prior to undertaking mine planning, SRK reviewed the resource presented in Section 11 of this report and identified areas of higher risk which in SRK’s opinion should not be included in the mine plan. For the use in mine planning, SRK have generated a re-domaining exercise for the exotic oxide and oxide domains to identify areas of potential risk that require further drilling for mine planning purposes. SRK treated faults and geologic constraints as hard boundaries and grade shells were generated using Leapfrog’s implicit modeling tools. Structural trends were applied to generate grade shells that honor the crescent shape of the mineralized domains as defined by Nordmin, which resulted in geologically constrained and statistically supported grade shells. Based on a visual review of the existing model and drilling composites SRK selected an ISO value of 0.25 (probability factor of 25% percent) to the indicator shells as a limit for risk to the mine plan. Only areas inside the indicator shells are used for the mine plan described in the following sections.

 

13.6Mine Design

 

13.6.1Santa Cruz - Longhole Stope

 

LHS stopes will be 10 m wide and 30 m high with varying length. Each stope will have a 5 m x 5 m access located at the top and bottom of the stope. Figure 13-38 shows a typical stope cross-section. Top accesses will be used for drilling and backfilling, and the bottom access will be used for mucking. The stopes will be drilled from top down, and rings will be blasted from the end of a stope towards the access. The blasted material will be remotely mucked from the bottom access and dumped into the ore pass.

 

 

Source: SRK, 2023

 

Figure 13-38: Typical Stope Cross-Section

 

September 2023

SEC Technical Report Summary – Santa CruzPage 307

 

A primary/secondary stoping sequence will be used, where on any given level, primary stopes must be separated by a secondary stope. Extraction of the secondary stope can only occur after the two immediately adjacent primary stopes and the two primary stopes immediately above have been mined, backfilled, and have had time to cure. Figure 13-39 shows the mining sequence. Backfilling will be an integral part of the LHS mining cycle, and a 14 day cure time is planned.

 

 

Source: SRK, 2023

 

Figure 13-39: Typical Mining Sequence

 

The primary stope accesses (5 m x 5 m) will be connected to a 5 m wide x 5.5 m high footwall access, which is offset a minimum 20 m away from the end of the stopes. Secondary stope accesses will branch off of the primary stope access to reduce the amount of development and to maintain an adequate pillar between primary stope accesses.

 

13.6.2Santa Cruz Exotic and East Ridge, Drift and Fill

 

DAF stopes will be 6 m wide x 9 m high and varying length. Stopes will be accessed perpendicularly via 5 m wide x 5 m high attack ramps. A 6 m wide x 5 m high initial cut will be drilled and blasted. Once the blasted material is extracted, vertical holes will be drilled into the back to slash the remaining 4 m height. Cemented waste rock fill will be placed in the emptied stope for support. A rammer jammer will be used to ensure the backfill is tight to the back. Figure 13-40 and Figure 13-41 show the attack ramp access to stopes and typical stope cycle, respectively.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 308

 

 

Source: SRK, 2023

 

Figure 13-40: Attack Ramp Access to Stopes

 

 

Source: SRK, 2023

 

Figure 13-41: Typical Stope Cycle

 

Stopes will follow a primary/secondary/tertiary sequence. Primary stopes will be mined, backfilled, and cured before an adjacent secondary can be mined. Tertiary stopes follow secondary stopes in a similar manner.

 

13.6.3Development

 

A dual decline will be developed from the plant site to access the Santa Cruz and East Ridge deposits. The declines are each 5 m wide x 5.5 m high. Figure 13-42 shows a schematic tunnel layout showing railveyor in the decline. Every 100 m, the railveyor tunnel will be slashed to 6 m wide for a length of 5 m to allow for sufficient room for drive stations, railveyor, and maintenance truck access.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 309

 

 

Source: SRK, 2023

 

Figure 13-42: Railveyor Decline Cross-Section

 

The second decline is for personnel/materials access and will accommodate utilities as necessary. During development, ventilation ducting will be necessary; however, for the long term, ventilation will be removed.

 

13.6.4Mine Plan Resource

 

Figure 13-43 shows the completed mine plan. Table 13-24 summarizes the total tonnage and grades within the mine plan by area.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 310

 

 

Source: SRK, 2023

 

Figure 13-43: Mine Design, Santa Cruz, Santa Cruz Exotic, and East Ridge

 

Table 13-24: Mine Plan Summary

 

Classification Domain Tonnage
(kt)
Total
Soluble
Cu (%)
Acid
Soluble
Cu (%)
Cyanide
Soluble
Cu (%)
Indicated Santa Cruz 73,582 1.62 1.05 0.39
East Ridge - - - -
Santa Cruz Exotic 1,131 2.79 2.28 0.22
Inferred Santa Cruz 14,991 1.45 0.98 0.32
East Ridge 9,799 1.76 0.95 0.75
Santa Cruz Exotic 741 2.47 1.83 0.17
Indicated + Inferred Santa Cruz 88,573 1.60 1.04 0.38
East Ridge 9,799 1.76 0.95 0.75
Santa Cruz Exotic 1,872 2.66 2.09 0.20
Indicated Total 74,713 1.64 1.07 0.39
Inferred Total 25,530 1.60 0.99 0.48
Indicated + Inferred Total 100,244 1.63 1.05 0.41

 

Note: 4.94Mt of marginal material at a grade of 0.56% is not included in this table.

Source: SRK, 2023

 

This work is preliminary in nature, it includes inferred mineral resources that are considered too speculative geologically to have modifying factors applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that this economic assessment will be realized.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 311

 

13.7Production Schedule

 

The production schedule is based on the mine design discussed in previous sections and was completed using Deswik software. Productivities were developed from first principles. Inputs from mining contractors and equipment vendors were considered for key parameters, such as capital cost, life of equipment, development rates, etc. The rates developed from first principles were adjusted based on benchmarking and SRK’s experience and judgment.

 

Table 13-25 shows the productivity rates used for the mine scheduling, followed by a description of the general and activity-specific parameters upon which the productivity rates are based. Decline and railveyor drift is assumed to be excavated simultaneously with a roadheader. The rest of the development is assumed to be excavated through drill and blast methods using bulk emulsion. Multiple areas/faces are mined at the same time to generate the production schedule. Stoping rates include drilling, blasting, and mucking for the slot and stope.

 

Table 13-25: Productivity Rates

 

Activity Type Dimensions Rate
Roadheader
drifting
Decline 5.0 m x 5.5 m 8.0 meters per day (m/d)
Railveyor 6.0 m x 6.0 m 8.0 m/d
Railveyor 5.0 m x 5.5 m 8.0 m/d
Drill and
blast drifting
Ramp 5.0 m x 5.5 m 4.0 m/d
Level access 5.0 m x 5.5 m 4.0 m/d
Footwall drive 5.0 m x 5.5 m 4.0 m/d
Ore drive 5.0 m x 5.0 m 4.0 m/d
Ore pass access 5.0 m x 5.5 m 4.0 m/d
Vent drives 5.0 m x 5.0 m 4.0 m/d
Vent drives 5.0 m x 6.0 m 4.0 m/d
Vent drives 6.0 m x 6.0 m 4.0 m/d
Attack ramps 5.0 m x 5.0 m 4.0 m/d
Underground shop 5.0 m x 5.0 m 4.0 m/d
Underground bay 6.0 m x 6.0 m 4.0 m/d
Stoping LHS stoping - 960 t/d
DAF stoping - 335 t/d
Vertical
development
Ventilation intake shaft 6.5 m diameter 1.4 m/d
Ventilation exhaust shaft 6.0 m diameter 1.4 m/d
Ventilation raise 4.0 m diameter 1.4 m/d
Blasted raise 5.0 m x 6.0 m 3.3 m/d
Blasted raise 5.0 m x 5.0 m 3.3 m/d
Blasted raise for ore pass 2.0 m x 2.0 m 3.0 m/d
Backfill PBF - 8,900 m3/day
Cemented rock backfill - 1,000 m3/day

 

Source: SRK, 2023

 

Ventilation shafts are assumed to be conventional shaft sinking at a rate of 1.4 m/d. The shaft wall will be supported by 12 inches of concrete. Ventilation raise is assumed to be excavated with the raiseboring method with a liner installed once boring is complete. The blasted drop raises will be drilled off by the production drill and blasted in a series of three blasts. Safescape escape ladders will be installed in select raises as secondary escape ways. Table 13-26 presents general schedule parameters applicable to all underground mining activities.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 312

 

Table 13-26: Schedule Parameters for Underground Mining

 

Schedule Parameters Units Value
Annual mining days Days/year 365
Mining days per week Days/week 7
Shifts per day Shifts/day 2
Scheduled shift length Hours/shift 12
Scheduled Deductions
Shift change Hours/shift 0.25
Travel time Hours/shift  0.50
Equipment inspection Hours/shift 0.25
Lunch break Hours/shift 1.00
Equipment parking/reporting Hours/shift 0.50
Total scheduled deductions Hours/shift 2.50
Operating time (scheduled shift length less scheduled deductions) Hours/shift 9.50
Effective time (operating time reduced to a 50-minute hour (i.e., multiplied by 83.3%) Hours/shift 7.92

 

Source: SRK, 2023

 

Table 13-27 details key assumptions regarding ore and waste material characteristics.

 

Table 13-27: Material Characteristics

 

Characteristic Units Value
In situ ore density t/m3 2.70
In situ waste density t/m3 2.50
Swell % 40
Loose ore density t/m3 1.93
Loose waste density t/m3 1.79

 

Source: SRK, 2023

 

The production schedule targets 15,000t/d of mineralized material to the process facility. This is a very high overall production for an underground mine and require an average of 23 LHS headings and 2 CAF headings over the LoM and a maximum of 30 LHS headings and 6 CAF headings.

 

Portal boxcut and alluvium decline development is assumed to start in 2026. Decline and railveyor activities begin in 2027 through to 2028 to access the top portion of the mine. Decline and railveyor resumes in 2033 to access the bottom of the mine. Stoping begins in 2029 with a 1-year ramp-up period until the mine and plant are operating at full capacity. Table 13-28 to Table 13-29 summarize the production schedule and development schedule, respectively. Figure 13-44 shows the mine production schedule by year.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 313

 

Table 13-28: Summarized Production Schedule

 

Years Without Inferred* With Inferred**

Total

Tonnage

(kt)

Total

Soluble Cu

(%)

Total

Waste

(kt)

Total

Tonnage

(kt)

Total

Soluble Cu

(%)

Total

Waste

(kt)

2027     477     477
2028 430 1.35 479 430 1.35 488
2029 2,542 1.66 57 3,366 1.71 120
2030 4,061 1.69 22 5,471 1.71 22
2031 4,420 1.57 82 5,474 1.63 85
2032 4,650 1.55 98 5,474 1.66 98
2033 4,342 1.61 95 5,474 1.66 215
2034 4,489 1.64 127 5,474 1.69 127
2035 4,255 1.71 228 5,474 1.71 236
2036 4,410 1.67 44 5,439 1.64 44
2037 4,806 1.56 89 5,462 1.57 106
2038 4,138 1.59 114 5,474 1.58 114
2039 4,665 1.72 13 5,473 1.72 13
2040 4,576 1.64 73 5,474 1.62 77
2041 4,029 1.55 35 5,474 1.56 41
2042 4,154 1.59 63 5,474 1.56 65
2043 4,219 1.58 28 5,475 1.56 28
2044 4,137 1.62 10 5,475 1.61 22
2045 3,921 1.70 14 5,475 1.67 21
2046 3,796 1.64 25 5,475 1.64 26
2047 2,074 1.66   3,066 1.56  
2048 266 1.46   368 1.43  
Total 78,380 1.62 2,173 100,244 1.63 2,426

 

Source: SRK, 2023 

* 3.44Mt of marginal material at a grade of 0.56% is not included in this table.

** 4.94Mt of marginal material at a grade of 0.56% is not included in this table.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 314

 

 

Table 13-29: Detailed Production Schedule (with inferred)

 

Production
Summary

Row
Total

Unit 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048

Santa Cruz

Ox/Chalc. En.

                                               

Santa Cruz

Ox/Chalc.

En. Total

88,573 kt   430 2,685 4,580 4,677 4,744 4,666 4,753 4,900 4,864 4,870 4,791 4,862 5,079 4,976 4,917 4,933 5,083 4,889 4,688 2,817 368
Diluted TCu 1.60 %   1.35 1.64 1.68 1.56 1.51 1.59 1.61 1.68 1.63 1.48 1.57 1.65 1.62 1.55 1.57 1.56 1.62 1.65 1.61 1.59 1.43
Diluted ASCu 1.04 %   0.68 1.14 1.15 1.04 1.03 1.18 1.10 1.17 1.10 1.06 0.99 0.98 0.92 1.00 0.96 0.98 0.96 1.04 1.00 1.14 0.96
Diluted CNCu 0.38 %   0.38 0.32 0.37 0.37 0.33 0.26 0.33 0.31 0.35 0.25 0.35 0.49 0.49 0.37 0.44 0.42 0.48 0.46 0.45 0.32 0.29
Santa Cruz Exotic                                                

Santa Cruz

Exotic Total

1,872 kt       19 174 135 39 35 60 28 310 10 378 4 33 68 151 40 234 155    
Diluted Tcu 2.66 %       1.32 1.59 2.96 2.04 5.53 3.34 5.33 3.20 1.51 2.79 1.10 2.56 2.31 1.86 2.55 2.37 2.63    
Diluted ASCu 2.09 %       1.06 1.40 2.34 1.52 3.64 2.47 4.12 2.42 0.86 2.29 0.69 2.09 1.94 1.47 1.99 1.91 2.05    
Diluted CNCu 0.20 %       0.09 0.09 0.36 0.19 0.82 0.39 0.68 0.26 0.06 0.11 0.03 0.13 0.13 0.11 0.19 0.17 0.16    
East Ridge                                                

East Ridge

Total

9,799 kt     681 872 623 596 769 686 515 546 282 674 233 391 466 489 390 351 352 632 250  
Diluted Tcu 1.76 %     2.00 1.87 2.15 2.57 2.03 2.01 1.74 1.53 1.32 1.61 1.37 1.54 1.56 1.42 1.46 1.32 1.51 1.65 1.3  
Diluted ASCu 0.95 %     1.10 1.02 1.19 1.44 1.11 1.12 0.93 0.83 0.68 0.85 0.71 0.82 0.82 0.74 0.79 0.70 0.81 0.89 0.7  
Diluted CNCu 0.75 %     0.86 0.80 0.93 1.12 0.87 0.87 0.74 0.64 0.54 0.68 0.57 0.65 0.65 0.59 0.61 0.54 0.64 0.70 0.5  
Total                                                
Total Tonnage 100,244 kt     3,366 5,471 5,474 5,474 5,474 5,474 5,474 5,439 5,462 5,474 5,473 5,474 5,474 5,474 5,475 5,475 5,475 5,475 3,066 368
Diluted Tcu 1.63 %     1.71 1.71 1.63 1.66 1.66 1.69 1.71 1.64 1.57 1.58 1.72 1.62 1.56 1.56 1.56 1.61 1.67 1.64 1.56 1.43
Diluted ASCu 1.05 %     1.13 1.13 1.07 1.11 1.17 1.12 1.16 1.09 1.12 0.97 1.06 0.91 0.99 0.95 0.98 0.95 1.06 1.01 1.10 0.96
Diluted CNCu 0.41 %     0.43 0.44 0.42 0.41 0.35 0.40 0.35 0.38 0.27 0.39 0.46 0.50 0.40 0.45 0.43 0.49 0.46 0.47 0.33 0.29

Marginal

Material

4,942 kt   463.9 584.0 240.0 195.0 320.9 471.6 359.1 431.1 268.9 343.0 258.7 182.2 193.7 84.6 145.4 134.3 106.7 74.5 46.6 37.1  
Marginal Tcu 0.56 %   0.47 0.58 0.60 0.58 0.57 0.53 0.54 0.53 0.61 0.55 0.52 0.62 0.57 0.51 0.61 0.67 0.61 0.60 0.65 0.68  
Marginal AsCu 0.24 %   0.07 0.19 0.21 0.21 0.37 0.19 0.29 0.23 0.40 0.18 0.16 0.28 0.28 0.39 0.38 0.34 0.27 0.33 0.38 0.44  
Marginal CNCu 0.11 %   0.09 0.17 0.21 0.17 0.09 0.07 0.07 0.11 0.09 0.08 0.10 0.12 0.13 0.06 0.10 0.12 0.18 0.17 0.16 0.16  

Waste and

Backfill Summary

                                               

Waste Tonnage

with Marginal

7,367 kt 477 952 704 262 280 419 687 486 667 313 449 372 196 271 126 210 162 129 96 72 37  

Waste Tonnage

minus Marginal

2,426 kt 477 488 120 22 85 98 215 127 236 44 106 114 13 77 41 65 28 22 21 26    
Pastefill Total                                                

High Strength

Pastefill

25,838,273 m3     776,684 1,527,669 1,369,851 1,536,362 1,396,269 1,546,885 1,591,011 1,464,343 1,374,605 1,248,770 1,385,978 1,525,083 1,364,139 1,407,813 1,423,979 1,503,444 1,287,281 1,305,805 712,154 90,150

Low Strength

Pastefill

5,144,684 m3       18,128 193,367 116,813 172,684 142,632 205,732 289,788 295,190 370,606 305,210 271,236 375,358 327,685 312,242 392,332 524,393 404,600 336,752 89,937
Total Rockfill                                                
CRF Total 4,315,695 m3     219,999 329,067 300,393 257,014 319,025 261,920 237,675 205,990 238,578 253,373 194,246 133,191 216,743 172,410 227,972 142,461 215,148 287,123 103,365  
Rockfill Total 227,671 m3         9,726 15,231 13,717       41,126 3,239 41,267 8,754   1,079 29,631 7,337 26,450 30,115    

 

Source: SRK, 2023

Note: Marginal material is broken out separately and not included in totals for each area.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 315

 

Table 13-30: Detailed Development Schedule (with inferred)

 

Development Summary Row Total Unit 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048
Lateral Development 308,261 m 6,254 19,531 22,822 18,167 18,237 18,246 23,422 17,792 18,777 14,029 18,993 17,773 13,541 14,802 12,486 13,711 12,746 8,547 7,855 8,361 2,169  
Decline 7,017 m 2,928 2,837         1,252                              
Decline Crosscut 643 m 398 245                                        
Railveyor 6x6 2,578 m 2,578                                          
Railveyor 5x5.5 3,761 m 350 2,277         1,134                              
Railveyor Access 367 m   104 178       85                              
Ramp 1,082 m   1,082                                        
Level Access 4,043 m   1,110 605       934 349 163 103 591 189                    
Footwall Drive 16,336 m   3,739 2,597 200 533 717 704 1,395 1,704 573 2,108 593 386 407   467 214          
Hangingwall Drive 505 m               30 185 100         127 63            
Hangingwall Access 334 m     334                                      
Ore Drive 250,222 m   6,905 15,591 16,818 16,703 16,401 16,763 15,233 14,564 12,898 14,263 16,069 12,427 13,677 12,223 12,376 12,418 7,581 7,557 7,733 2,024  
Ore pass Access 2,256 m   309 374 124 137 108 167 129 212 75 35 336 102 127   20            
Vent Drive 5 x 5 2,065 m   287 246 47 245 69 61 170 59 57 375 197 80 111     60          
Vent Drive 5 x 6 2,592 m   636 248   41 9 477 266 632   238         45            
Vent Drive 6 x 6 864 m     830 33                                    
Underground Shop 100 m     100                                      
Underground Bay 157 m     157                                      
Attack Ramp 13,338 m     1,562 945 579 942 1,845 221 1,259 222 1,383 389 546 479 136 740 54 965 298 628 145  
Vertical Development 3,812 m   1,287 527 180 180   412 351 124   210 492 19       30          
6 m Vent Raise 489 m   489                                        
6.5 m Vent Raise 552 m   552                                        
4 m Vent Raise 128 m     86       42                              
5 x 6 Raise 540 m   65 103 60       12 30   120 150                    
5 x 5 Raise 804 m     120 120 180     95 30   90 120 19       30          
2 x 2 Raise 1,299 m   182 218       370 244 64     222                    

 

Source: SRK, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 316

 

 

 

 

Source: SRK, 2023

 

Figure 13-44: Mine Production Schedule Colored by Year (with Inferred)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 317

 

13.8Mining Operations

 

13.8.1Stoping

 

Stopes will be mined using the LHS method. Individual stope blocks are designed to be 10 m wide, up to 30 m long in secondaries, and will have a transverse orientation. Levels are spaced 30 m apart, and each stope block will have a top and bottom access (5 m x 5 m flat back drifts).

 

Stopes will be drilled downward from the top access using 90 mm-diameter holes (stope production rings will be drilled with a top-hammer drill). A bottom up, primary/secondary extraction sequence will be followed. Primary stopes will be backfilled with high-strength PBF, and secondary stopes will be backfilled with low-strength PBF.

 

Stope extraction will occur in two steps. During the first step, a slot will be drilled with a V30 Machine Roger at the far end of the stope and 10 fan-drilled slash holes. The slot is required to create sufficient void space for the remainder of the stope to be blasted. During the second step, production rings will be blasted five rows at a time (12 blastholes per ring) until the stope is completely extracted. The number of five-row blasts in a given stope will depend on the length of the stope. All blasting will be performed with bulk emulsion.

 

Ore will be remotely mucked from the bottom stope access using an 8.8 m3 (17-t) loader. The loader will transport the ore to the nearest ore pass on the level. The ore pass will load the railveyor and haul the ore to surface.

 

13.8.2Drift and Fill (DAF)

 

The stopes will be mined using the DAF method. The stopes will be 6 m wide, 9 m high, and at varying lengths. A 5 m x 5 m attack ramp will provide access to each cut, and the stopes in each cut will be mined in a PST sequence.

 

Stopes are mined in two steps. A horizontal cut is first taken at 6 m wide and 5 m high using a development jumbo. After the ore is extracted and the stope is supported, a 4 m back slash is taken to extract the remaining ore. Broken muck may be left behind as a platform to support the stope before being emptied. Ore from the Exotic domain in Santa Cruz will be mucked by loaders and transported to the ore pass system. Ore from the East Ridge deposit will be loaded to a fleet of 42-t haul trucks and transported to the main ore pass system.

 

13.8.3Underground Material Handling System

 

The underground material handling system is designed to provide some storage capacity underground and be an efficient, automated system for moving the rock to surface via railveyor. For the Santa Cruz stoping areas, material will be brought to one of several ore passes via long-haul dump truck (LHD) directly from the stopes. For the Santa Cruz Exotic domain and East Ridge deposit, an LHD will load a truck near the mining face, and the truck will transport material to an ore pass. Figure 13-45 shows the location of ore passes.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 318

 

 

 

Source: SRK, 2023

 

Figure 13-45: Ore Pass Locations in Red

 

Material from the ore passes will be stored in a bin until the railveyor arrives for loading. The number of train cars and frequency of train arrival will need to be determined in future studies; however, at this time, the railveyor is not seen as a bottleneck and can be adapted as necessary. Note that railveyor is a newer technology existing at several operations worldwide, however it is currently not widely used in the industry.

 

13.8.4Backfill

 

The Santa Cruz mine will be backfilled using cemented tailings paste. The backfill replaces excavated ore to provide support for the remaining rock and reduces the need for pillars.

 

The Santa Cruz Paste Plant will receive thickened tailings slurry from the concentrator via a pipeline. A large, agitated buffer tank will be located adjacent to the paste plant to provide some tailings storage and operational flexibility in tailings supply. A portion of the tailings slurry stream will be dewatered using vacuum disc filters and the resulting filter cake recombined with the remainder of the tailings slurry stream in two continuous mixers. The ratio of slurry to filter cake will be adjusted to maintain the desired solids content and flow properties of the paste. Binder will be added in the mixers according to strength requirements for each underground stope.

 

A network of boreholes and piping will distribute the paste from the plant to underground stopes using gravity flow. Each stope will employ a barricade to confine the paste within the stope until it cures, and mining can progress in the adjacent stope or panel.

 

Production Rate

 

The underground mining rate is planned to be 15,000 t/d. After considering availability, utilization, and concentrate production, the concentrator will produce 15,000 t/d of tailings when operating or roughly 625 tph. Tailings will be diverted to either the paste plant, or to the tailings management facility for permanent storage.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 319

 

The design of the paste system will include a single paste plant as it poses the least operational complexity and lowest capital cost. The design challenges associated with high production rates can be mitigated without causing additional risks to the Project.

 

Underground Distribution System

 

The underground distribution system will consist of a network of boreholes and steel piping to convey the paste from the paste plant to the stopes throughout the mine. The paste plant is designed to operate at 625 tph of tailings plus binder and sufficient water to make a paste product which can flow through a pipeline. The resulting flowrate of that paste is approximately 450 to 475 m3/h.

 

Based on estimated velocities and the expected paste production rate, the line size can be calculated to be 16-inch nominal pipe which would result in a pipeline velocity of 1.3 m/s. Boreholes should be cased unless there is certainty that the boreholes will be dry (not add any water to the paste) and will be stable. The assumption for Santa Cruz is that all boreholes will be drilled oversize and cased with steel pipe which will either be grouted in place or hung in the boreholes. The diameter of the casing should match the level piping at 16-inch nominal pipe size. Boreholes should be drilled at 70˚ from horizontal or less to reduce wear and damage from free-falls.

 

It was determined that if the paste plant was located centrally above the orebody, gravity flow could be used and paste pumps would not be required. The long section contained in Figure 13-46 highlights the central distribution trunkline in black. The trunkline transports the paste to levels where it’s transported horizontally along footwall drives to the extents of the orebody. The colored shading shows the maximum allowable pipeline friction loss under gravity flow for that distribution route. Benchmark friction loss for paste system indicates that the friction loss in the larger pipelines should range from 5 to10 kPa/m for this system. A second optional borehole from the paste plant is shown in red to allow higher friction paste to be reticulated to the North if needed.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 320

 

 

 

Source: SRK, 2023

 

Figure 13-46: Long Section of Paste Distribution System and Maximum Allowable Friction Loss for Gravity Flow (looking East)

 

Paste Process Design

 

Table 13-31 shows the design criteria for the paste plant.

 

Table 13-31: Design Criteria

 

Design Parameter Criteria
Tailings production rate 15,000 t/d or 625 tph
Tailings solids specific gravity 2.67
Thickener underflow solids content 64% (w/w)
Paste solids content 73.8 – 75.7 % (w/w)
Binder content 2-7%
Mixer retention time 2 minutes minimum

 

Source: Barr, 2023

 

Tailings will be received in a large, agitated tank at the paste plant. This tank provides needed buffering capacity between the concentrator and paste plant to allow for switching of line when the paste plant is not operating and short operational interruptions from the concentrator. It is also recommended that the concentrator have a similarly sized buffer tank to double the storage and blending capacity after the thickener.

 

The thickened tailings slurry feed to the paste plant contains too much water for paste production. Vacuum disc filters will be used to dewater a portion of the tailings stream. The control system of the paste plant will measure and adjust the ratio of tailings which require filtration to achieve the desired target moisture of the final paste backfill. The Santa Cruz Paste Plant will require 4 operating filters to achieve the design capacity of the system. It is recommended that a fifth redundant filter be considered in future study stages.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 321

 

The paste mixers will blend tailings filter cake, thickened tailings slurry and binder to make the backfill for Santa Cruz. The flow rate through the mixer will be approximately 475 m3/h. This flow rate makes the retention time in mixers available on the market to be too short. It is recommended to utilize two continuous mixers in series to achieve the desired retention time in the mixer to properly blend tailings, binder, and slurry.

 

A single 1,500 t binder silo has been included in the design. This provides sufficient capacity to operate for 48 hours at a binder consumption rate of 5%. Preliminary UCS testing indicates lower binder contents may be possible at Santa Cruz. Future study stages should examine the stability and proximity of the binder supply for the mine to determine the required binder storage.

 

Binder will be metered into the paste process using a rotary valve and screw conveyors. A continuous mass flow measuring instrument is recommended between screw conveyors. The paste plant control system will calculate the required binder flow rate based on the tailings flow rate and the recipe input by the operator.

 

Figure 13-47 shows the Santa Cruz paste backfill process flow sheet.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 322

 

 

 

Source: Barr, 2023

 

Figure 13-47: Santa Cruz Paste Process Flow Sheet

 

September 2023

SEC Technical Report Summary – Santa CruzPage 323

 

13.8.5Grade Control

 

Short and mid-range production drilling will precede advancement of individual levels and headings. As headings are advanced, the geologic controls will be verified spatially, with grab samples taken and assayed as each round advances. Any observed controlling geology, lithology, structures, geochemical features, etc. will be mapped, reconciled to, and updated in the model. During advance, a geologist will determine whether to route the material as ore or waste. If a determination cannot be made immediately, the material can be stockpiled in an underground muckbay while awaiting the assay results. If areas of high model variability are encountered, in-stope drilling may be conducted to refine the short-term mill feed predictability. Model performance will be tracked over time and adjustments will be made if needed.

 

13.8.6Ventilation

 

The ventilation design required to support the development and production at the Santa Cruz Project incorporates four connections to surface: one service access decline, one exhaust railveyor decline, one dedicated exhaust shaft, and one dedicated fresh air raise as shown in Figure 13-48. Because of the automated electric haulage provided by the railveyor system and the use of electric equipment, the airflow quantity required to ventilate the mine is reduced from what a typical diesel equipment fleet would require. However, because of the geologic setting and high thermal gradient, refrigeration will be required for the ventilation system for a portion of the year The main benefit with respect to the electrification of the mining equipment will be the reduction in refrigeration. The diesel equipment fleet would present a heat load likely greater than three times the heat load developed by the electric equipment fleet. In addition, the production of CO2 may be reduced by as much as 70% to 80% with the use of an electric equipment fleet; however, this will be required to be confirmed through future studies.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 324

 

 

 

Source: SRK, 2023

 

Figure 13-48: General Ventilation Infrastructure and Layout

 

September 2023

SEC Technical Report Summary – Santa CruzPage 325

 

The basic airflow requirement for the mine is based on achieving a minimum design air velocity in various point-of-use areas, as shown in Table 13-32.

 

Table 13-32: General Airflow Calculations

 

Zone Point of Use Number
of
Areas
Air
Velocity
(m/s)
Dimension (m) Airflow
(m3/s)
Airflow
(m3/s)
Height Width
Main Zone Production mucking 10 0.75 5 5 187.5 375
Development/setup 10 0.50 5 5 125
Open level footwall 1 0.50 5 5 12.5
Development level 1       50
East
Ridge
Lower Production mucking 2 0.75 5 5 18.75 112.5
Development/setup 2 0.50 5 5 12.5
Upper Production mucking 2 0.75 5 5 18.75
Development/setup 2 0.50 5 5 12.5
Development           50
General Light shop         25 25
Leakage (15%)             77
Total             564

 

Source: SRK, 2023

m/s: Meters per second

m3/s: Cubic meters per second

 

There will be two basic independently ventilated/exhausted mining zones: East Ridge and Main Zone. The East Ridge mining zone will draw airflow in from both the fresh air shaft and service decline and exhaust the airflow to surface through the railveyor decline. The air velocity in the railveyor decline will be high, but it will be in the same direction as the materials’ movement, which will minimize the dust liberation. An exhaust booster fan will be required to be installed in the ramp leading to the railveyor from the East Ridge mining zone. The Main Zone will draw airflow in from the fresh air shaft and service decline and will exhaust through the perimeter exhaust raise that extends to surface. To upcast the lower portion of the railveyor, a small booster fan will be required to be installed at the last crosscut between the railveyor and service declines. The main exhaust fan installation for the Main Zone will be located on surface at the top of the exhaust shaft. Individual stopes can be ventilated with 100-kilowatt (kW) auxiliary fans and 1.4 m flexible duct.

 

A high-level ventilation model was developed using the VentSIM software so that the overall life-of-mine (LoM) fan operating points could be determined, which would include leakage, decline interactions, and general level ventilation. This model established the applied fan power for the operating fan installations, as shown in Table 13-33.

 

Table 13-33: Main Fan LoM Operating Points

 

Fan
Location
Airflow
(m3/s)
Pressure (kPa)
0.5 kPa Added
Losses
Power
(kW) (80%
Efficiency)
Notes
Temporary portal fan 225 2.4 675 Used for decline construction to establish flow through ventilation prior to the shafts
East Ridge railveyor exhaust fan 200 2.8 700 Two fans mounted in parallel in a bulkhead to draw airflow through East Ridge and upcast the conveyor
Base of railveyor exhaust fan 50 2.6 165 To upcast the conveyor away from the Main Zone
Main Zone exhaust fan 500 4.1 2,562 Two fans mounted in parallel on the surface to provide Main Zone exhaust

 

Source: SRK, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 326

 

A basic heat balance was developed for the ventilation system to identify the initial required refrigeration quantity to be applied to the fresh air raise at the surface. Although refrigeration could be applied at places other than the surface, the surface was chosen because it allows for an easier installation/construction, easier maintenance, and a greater degree of flexibility, which will allow for expansion if the mine progresses deeper or if production is increased. The heat balance considered the electric equipment fleet and fans, compression, rock mass, and the natural cooling from the circulating airflow. Table 13-34 identifies the equipment and operating parameters used to calculate the equipment heat load.

 

The thermal gradient of 2.1°C/100 m with a surface rock temperature of 24.8°C was identified by site drilling logs dated November 11, 2022. This was input to the ventilation model without any equipment loads so that the heat developed from only the rock mass could be identified. This is a general assumption and will change depending upon production rates, stope orientations, number of active headings, and the exposure of the rock mass to airflow. The age of the exposed rock was kept fresh to help balance the heat generated from backfill which was not separately identified. At this stage, a thermal model was not developed. A thermal model will be useful to identify discrete areas which may have elevated air temperatures.

 

To add both a degree of conservativeness and a more reasonable working environment for non-acclimated personnel, a reject wet bulb temperature of 26°C was used to derive the cooling capacity of the natural intake airflow. Figure 13-49 provides a summary of the heat balance, which reflects an applied refrigeration quantity of approximately 8.4 megawatts of refrigeration (MW(R)).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 327

 

 

Table 13-34: Overall LoM Equipment Heat Loads

 

Equipment Potential Make and Model Power Source* Peak
Power (kW)
On Shift
Utilization (%)
Estimated Motor
Utilization (%)
Power
Utilized (kW)
Equipment
Numbers
Total
Power (kW)
LHD Epiroc ST18 (17.5t) BEV BEV 450 100 50 225 8 1,800
Haul truck Epiroc MT54 (54t) BEV 567 100 50 283.5 7 1,985
Jumbo Epiroc Boomer M2C BEV BEV/tethered 150 60 25 22.5 6 135
Scaler MacLean RB3-EV BEV/tethered 110 40 25 11 2 22
Bolter Epiroc Boltec M BEV BEV/tethered 150 50 25 18.75 6 113
Cable bolter MacLean CB3-EV BEV/tethered 150 60 25 22.5 3 68
Rockbreaker MacLean RB3-EV BEV 150 40 25 15 2 30
ITH Epiroc Simba E7C BEV BEV 150 80 25 30 5 150
Small LHD Epiroc ST3.5 (6t) BEV 75 40 25 7.5 2 15
Probe hole drill Epiroc Boomer E1 C BEV/tethered 140 20 25 7 1 7
Shotcrete sprayer MacLean SS5-EV BEV/tethered 200 60 50 60 2 120
Transmixer MacLean TM3-EV BEV 200 60 75 90 3 270
Explosives loader MacLean EC3-EV BEV 200 40 75 60 5 300
Personnel carrier (bus) MacLean PC3-EV BEV 150 20 75 22.5 3 68
Light vehicles (shifters,
crews, management, etc.)
Kovatera KT200e BEV 150 35 25 13.125 9 118
Cable reeler/ electrician Kovatera KF200e BEV 150 50 25 18.75 2 38
Mine rescue Kovatera KT200e BEV 150 5 100 7.5 2 15
Maintenance (mechanic) Kovatera KF200e BEV 150 40 75 45 5 225
Fuel/lube truck MacLean FL3-EV BEV 150 10 75 11.25 1 11
Grader MacLean GR3-EV BEV 200 40 100 80 1 80
Boom truck MacLean BT3-EV BEV 200 50 75 75 2 150
Scissor lift MacLean LR3-EV BEV 200 50 50 50 2 100
Telehandler Genie GTH-1056 (5.5t) BEV 130 20 75 19.5 3 59
Skidsteer Kovaco ECO BEV 81 40 50 16.2 3 49
Portable compressor
(service cable bolter,
mechanical, production)
  BEV 75 30 100 22.5 12 270
Diamond drill Epiroc Diamec 6 BEV 90 40 100 36 3 108
Stope development fans     100 100 75 75 10 750
Stope production fans     100 100 75 75 10 750
General fans     50 100 75 37.5 5 188
Total electric equipment heat load             7,990

 

Source: SRK, 2023

*BEV = Battery Electric Vehicle

 

September 2023

SEC Technical Report Summary – Santa CruzPage 328

 

 

Source: SRK, 2023

 

Figure 13-49: Refrigeration Summary Breakdown

 

Refrigeration will not be required all year. Once the general surface wet bulb temperature is drawn below 18°C wet bulb, refrigeration will not be required, as shown on Figure 13-50.

 

 

Source: SRK, 2023

 

Figure 13-50: Seasonal Refrigeration Operation

 

To establish the maximum refrigeration requirement on an annual basis over the LoM, the factors of depth and production rate were modulated based on the mine schedule. The refrigeration quantities shown on Figure 13-51 identify the possibility to develop the surface refrigeration plant in stages with modular units, with the first unit in 2025 and the second unit in 2034.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 329

 

 

Source: SRK, 2023

 

Figure 13-51: Refrigeration Requirements Over the LoM

 

13.8.7Mine Services

 

Electrical

 

Power to the mine is delivered from the main substation to the mine electrical building at the Portal via 13.8 kV power lines. From the Portal electrical building, three 13.8 kV power lines are hung down the decline to level -270, at the bottom of the upper block. From there, mine power centers will be installed on various levels to provide power to the working face. The power will support the mine working faces and the battery charging stations for the BEV equipment.

 

Health and Safety

 

The mine design includes refuge stations placed throughout the mine. Escape ladders are installed in vent raises to serve as secondary egress. A stench warning system through the ventilation system will notify workers of emergency conditions.

 

Manpower

 

Decline, railveyor, and ventilation shaft development are assumed to be contractor operated. Mine development and production will be owner operated. The estimated management and technical staff is 50, and operating and maintenance personnel is 274. Table 13-35 shows the estimated number of management and technical staff. Table 13-36 shows the estimated number of operating and maintenance personnel.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 330

 

Table 13-35: Management and Technical Staff Labor Estimate

 

Department/Section Category Shift Hours Maximum Staff
Mine Technical Staff     43
Underground Mine Manager Salary 8 1
Underground Mine General Foreman Salary 8 2
Technical Services Manager Salary 8 1
Chief Mining Engineer Salary 8 1
Senior Mining Engineer Salary 8 2
Long-Term Planning Engineer Salary 8 1
Short-Term Planning Engineer Salary 8 2
Backfill Engineer Salary 8 1
Ventilation Engineer Salary 8 1
Ventilation Technician Salary 8 2
Surveyors Salary 8 6
Senior Geotechnical Engineer Salary 8 1
Geotechnical Engineer Salary 8 1
Geotechnical Technician Salary 8 1
Chief Mine Geologist Salary 8 1
Senior Mine Geologist Salary 8 1
Beat Geologist Salary 8 6
Senior Modeling Geologist Salary 8 1
Infill Drilling Supervisor Salary 8 1
Senior Field Logging Geologist Salary 8 1
Core Logger Salary 8 4
Project Lead Salary 8 1
Mechanical Engineer Salary 8 2
Civil Engineer Salary 8 2
Mine Maintenance Staff     7
Maintenance Superintendent Salary 8 1
Maintenance General Foreman Salary 8 1
Maintenance Planning Coordinator Salary 8 1
Maintenance Planning Engineer Salary 8 1
Maintenance Planning Technician Salary 8 3

 

Source: SRK, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 331

 

Table 13-36: Operating and Maintenance Labor Estimate

 

Department/Section Category Shift Hours Maximum Staff
Mine Operations Labor     219
Development Supervisor Hourly 12 3
Jumbo Operator Hourly 12 12
Bolter Operator Hourly 12 15
Cablebolter Operator Hourly 12 6
Service Crew Hourly 12 18
Production Supervisor Hourly 12 3
Truck Driver Hourly 12 12
LHD Operator Hourly 12 33
Production Drill Operator Hourly 12 21
Lead Blaster Hourly 12 21
Blaster Helper Hourly 12 21
Grader Operator Hourly 12 3
Utility/Laborer/Nipper/Helper Hourly 12 25
Underground Pastefill and Construction Supervisor Hourly 12 1
Pastefill Piping Crew Hourly 12 1
Pastefill Barricade Crew Hourly 12 3
Pastefill Plant Operator Hourly 12 1
Shotcrete Operator Hourly 12 6
Construction Crew Hourly 12 9
Backfill Plant Supervisor Hourly 12 1
Backfill Plant Operator Hourly 12 1
Backfill Plant Helper Hourly 12 3
Binder Transport and Delivery Operator Hourly 12 3
Mine Maintenance Hourly Labor     55
Underground Shop Supervisor Hourly 12 1
Underground Shop Mechanic Hourly 12 19
Underground Millwright Hourly 12 4
Underground Shop Electrician Hourly 12 19
Underground Shop Welder Hourly 12 3
Underground Shop Mechanic Helper Hourly 12 3
Underground Shop Electrician Helper Hourly 12 3
Underground Shop Welder Helper Hourly 12 2

 

Source: SRK, 2023

 

Equipment

 

Santa Cruz will primarily use a battery electric fleet for development and production. Auxiliary equipment is mostly diesel. Table 13-37 shows the estimated required mobile equipment. Note that use of battery electric equipment is newer technology and is currently not widely used in the industry.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 332

 

Table 13-37: Santa Cruz Estimated Mobile Equipment

 

Major Mobile Equipment Requirement
Epiroc BEV M20 - Jumbo - BE 4
Epiroc BEV Boltec M10 - Mechanical Bolter 5
Epiroc BEV M6 - Simba Longhole 7
Maclean EC3 - Emulsion Charger 7
MacLean SS5 - Shotcrete Sprayer 1
MacLean TM3 - Transmixer Truck 1
Epiroc BEV ST18 - LHD, 8.8 m3, 17 t - BE 11
Epiroc ST18 - LHD, 8.8 m3, 17 t 0
Epiroc MT42 - Haulage Truck, 42 t 0
Eprioc BEV MT42 - Haulage Truck, 42 t - BE 4
Epiroc BEV Cabletec M - Cablebolter 1
MacLean SL3 - Scissor Lift 4
MacLean FL3 - Fuel/Lube Truck 2
MacLean GR5 - Grader 2
MacLean BT3 - Boom Truck 2
Miller Toyota Hurth - Mechanic Truck 3
Miller Toyota Van - Personnel Carrier, 9 per. 20

 

Source: SRK, 2023

 

13.9QP Opinion

 

It is the opinion of SRK that the level of information and work regarding the mine design and mine planning and associated estimates are appropriate for an initial assessment and represent good industry practice that align with S-K 1300 reporting. SRK considers that all issues relating to all relevant technical and economic factors likely to influence the prospect of economic extraction can be resolved with further work.

 

It is the opinion of CNI, responsible for the mine geotechnical evaluation, that the level of geotechnical studies are appropriate for an initial assessment and represent good industry practice that align with S-K 1300 reporting.

 

It is the opinion of INTERA, responsible for the hydrogeology evaluation and the groundwater flow model, that the level of information and work regarding the hydrogeology and the mine dewatering estimates are appropriate for an initial assessment and represent industry accepted practices.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 333

 

14Processing and Recovery Methods

 

14.1Operation Results

 

All plant equipment will be sized for the ultimate plant production estimated to be 15,000 dry metric tonnes per day (t/d) at 94% utilization on a 24-hour per day, 365 day per year basis (15,957 dry t/d operating rate).

 

Santa Cruz Project ore mineralization can be subdivided into four (4) copper containing major groups:

 

·Exotic domain - Copper found in basal gravels
·Oxide domain - Chrysocolla and atacamite hosted in oracle granite
·Chalcocite domain – supergene chalcocite with or without chalcopyrite hosted in oracle granite
·Primary domain – hypogene chalcopyrite, molybdenite, bornite, covellite hosted in oracle granite

 

Primary hypogene sulfides are not included in the mine plan.

 

Table 14-1 shows the planned operating schedule and throughput targets per the mine plan.

 

Table 14-1: Planned Operating Schedule and Target Throughputs

 

Description Unit Value
Plant Throughput    
Overall Plant Feed t/y 5,475,000
Overall Plant Feed t/d 10,800 to 16,300
Operating Schedule    
Shift/Day - 2
Hours/Shift h/s 12
Hours/Day h/d 24
Days/Year d/a 365
Unit Operation Availability    
Crushing Circuit % Approx. 70
Crushing Rate t/h 888
Grinding and Flotation % 94
Grinding Circuit Onward t/h 665
Plant Feed Grade (LoM)    
Copper (TCu) % 1.60
Acid Soluble Copper (ASCu) % 1.04
Cyanide Soluble Copper (CNCu) % 0.38
Copper Production    
Cathode Production    
Copper in Cathode LoM t 1,032,000
Copper Recovery from SX-EW % 62.2%
Annual Cathode Production t 32,000 to 61,400
Concentrate Production    
Copper in Concentrate LoM t 555,000
Copper Recovery from Concentrator % 33.4%
Annual Copper in Concentrate t 14,000 to 35,100
Combined Copper Recovery % 95.4

 

Source: M3, 2023

t/h = tonnes per hour

 

Operating Schedule

 

·Hours per shift 12
·Shifts per day 2
·Days per week 7
·Days per year 365

 

September 2023

SEC Technical Report Summary – Santa CruzPage 334

 

Material Placement Rate

 

·Tonnes per day, average (actual tonnage varies by year) 15,000
 · Tonnes, average (actual tonnage varies by year) 7,000-16,000
 · Years of Operation Planned 20

 

Area Characteristics

 

·Run of Mine Ore, (100%) minus, mm 500
 ·SG (bulk density) 1.7
 ·P80, mm 144

 

14.2Processing Overview

 

The current flowsheet includes:

 

·Crushing of ROM ore to 80% passing 144 mm
·SAG and Ball mill grinding to 80% passing 300 microns
·Whole ore agitated leaching in sulfuric acid in five tanks in series
·PLS recovery in a 5-stage CCD wash of leach residue
·2-stage neutralization of leach residue with limestone in the first stage and with lime in second stage
·Tertiary grinding of leach residue in a vertical mill to 80% passing 106 microns
·Rougher flotation one bank of six tank cells
·Regrinding of rougher concentrate in a vertical mill to 80% passing 74 microns
·2-stage copper concentrate cleaning and a cleaner scavenger flotation
·Concentrate thickening
·Concentrate filtration in a horizontal press filter
·Tailing (rougher and cleaner tailing) thickening
·Pumping of tailing to the TSF
·Reclamation of water from the TSF back to the process plant

 

14.3Processing Method

 

The following items summarize the process operations required to extract copper from the Santa Cruz:

 

14.3.1Comminution

 

·The primary crushing circuit will be located on the surface and will be fed directly from the Railveyor.
·Size reduction of the ore by a primary crusher to reduce the ore size from run of mine (ROM) to 80 percent passing 144 mm. Crushed ore will be conveyed to a covered coarse ore stockpile located near the concentrator.
·Stockpiling the primary crushed ore and then reclaiming by feeders and conveying to the grinding circuit.
·Grinding ore in a conventional semi-autogenous (SAG) and ball mill circuit to a product size of 80 percent passing 300 microns prior to processing in a tank leach circuit. The primary grinding circuit will consist of one SAG mill operating in closed circuit with a screen. The secondary grinding circuit will consist of a single ball mill operating in closed circuit with hydrocyclones.
·Ground slurry will be dewatered prior to being sent to the leach plant. Ground mineralized material is thickened in a pre-leach thickener and then conditioned in a conditioning tank to bring the leach tank feed to 50% solids.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 335

 

14.3.2Whole Ore Leaching

 

·The slurry will be leached with sulfuric acid in a series of five lined agitated tanks with a capacity of 862 m3, each.
·The PLS slurry then discharges at a rate of 1,380 m3/h to five stages of counter current decantation (CCD) thickeners to wash the leach residue as thickener bed and recovery pregnant leach solution (PLS) as thickener overflow. The final thickener underflow reports to the neutralization circuit.

 

14.3.3Solvent Extraction / Electrowinning

 

·The PLS reports to the PLS clarifier where it settles any residual solids. The clarifier overflow reports to the PLS pond, while the clarifier underflow is recycled back to the CCD circuit.
·The double lined PLS pond serves to settle any residual solids for eight hours and de-aerate PLS before it is pumped to the solvent extraction circuit.
·Copper is extracted from PLS in a series of three mix tanks, each for two stages of extraction settlers. The organic (diluent and extractant) into which copper is partitioned, reports to the organic scrubber for aqueous removal. The barren PLS aqueous phase reports to the raffinate pond. Scrubbed organic advances to the loaded organic tank.

 

Loaded organic is pumped to the mix tanks of the organic wash stage where more aqueous entrainment from the PLS is removed and the organic is cleaned of any remaining chloride contamination prior to stripping with electrolyte. Clean organic advances to the mix tanks of the stripper section:

 

·Copper is stripped from the organic into electrolyte via two mix tanks, each, in two stages of strip settlers by strong acid in the lean electrolyte creating a rich electrolyte.
·Rich electrolyte is filtered in electrolyte filters to remove any residual organic phase. The filtered rich electrolyte is then heated by a heat exchanger and pumped to the electrowinning cells in the EW tank house.
·There are 140 EW cells in the EW tank house with 60 cathode blanks and 61 lead anodes per EW cell. The harvesting cycle for copper cathode is seven days.
·The lean electrolyte is pumped back through the heat exchanger and ultimately reports to the strip settler circuit.
·Copper cathodes are stripped from cathode blanks in a robotic stripping machine, washed, sampled and stacked for market.

 

14.3.4Leach Residue Neutralization

 

·The leach residue is neutralized in a neutralization tank using limestone slurry at grind size of 80% passing 44 microns.
·A second stage of leach residue neutralization is made using milk of lime slurry.
·The neutralized slurry is ground in a single tertiary mill operating in closed circuit with hydrocyclones to an 80% passing of 106 microns prior to processing in a flotation plant.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 336

 

14.3.5Flotation Circuit

 

·The flotation plant will consist of a conventional copper flotation circuit. The rougher flotation circuit will consist of one bank of six 200 m3 flotation tank cells. The rougher tailing will report to the tailing thickener.
·The rougher concentrate will be reground using a vertical stirred mill to 100% passing of 74 microns. The ground rougher concentrate reports to the cleaner circuit. The cleaner circuit consists of two stages of four tank cells each and one cleaner scavenger stage.
·Copper concentrate from the discharge of the second cleaner stage reports to the concentrate thickener where it will be thickened to a slurry density of 60% to 65% solids.
·Concentrate slurry will be washed and filtered in a press filter, and stored in a bunker from where it will be shipped to an offsite smelter by trucks.

 

14.3.6Tailing

 

·Flotation tails will be thickened in a tailing thickener and pumped to a conventional tailings storage facility at a slurry density of 65% solids.
·A split of approximately half of the tailing slurry reports to the paste backfill plant where it is mixed with cement and other amendments to provide structural backfill in the underground mine.
·Solution from the tailing dewatering will be recycled for reuse in the process. Plant water stream types will include process water, fresh water, and potable water.

 

14.3.7Reagents

 

Storage, preparation, and distribution of reagents to be used in the process. Reagents which require storage and distribution will include:

 

·Sulfuric acid for leaching
·Diluent and extractant for SX
·Cobalt sulfate and guar smoothing agents in EW
·Mist-op for acid mist suppression
·Limestone and lime for neutralization of leach residue
·Milk of lime for pH control in flotation
·Sodium isobutyl xanthate (SIBX) or potassium amyl xanthate (PAX), or possibly an alkyl di-thiophosphate based reagent as collectors
·Methyl isobutyl carbinol (MIBC) or equivalent as frother
·Flocculant for dewatering concentrate and tailing

 

September 2023

SEC Technical Report Summary – Santa CruzPage 337

 

14.4Flowsheet

 

The Santa Cruz process flow diagram is shown as Figure 14-1. This flowsheet is the basis for the Equipment List, equipment selection and plant layout described below.

 

 

Source: M3, 2023

 

Figure 14-1: Conceptual Flowsheet for the Santa Cruz Process Plant

 

September 2023

SEC Technical Report Summary – Santa CruzPage 338

 

14.5Plant Design and Equipment Design

 

14.5.1Plant Layout

 

The Santa Cruz plant has been laid out to the west of the underground mine in a north-south arrangement of facilities. Figure 14-2 is a layout drawing of the plant facilities (north facing to the right).

 

Material produced from the underground is transported via a railveyor, which daylights at the mine portal and runs along the surface to a bin that feeds the primary jaw crusher which discharges to the covered coarse ore stockpile. Coarse crushed ore is reclaimed to the SAG mill via a belt conveyor.

 

 

 

Source: M3, 2023

 

Figure 14-2: Conceptual Santa Cruz Plant Layout

 

Comminution operations include the jaw crusher, stockpile and reclaim, SAG mill and ball mill are arranged end-to-end with the ball mill sump between them.

 

The Pre-Leach thickener is situated due north of the ball mill. From there, unit operations are arranged west to east over 500 m: agitated leach tanks, CCD thickeners, neutralization tanks, tertiary grinding, rougher flotation, concentrate regrinding, cleaner flotation, concentrate dewatering and filtration, and tailing dewatering.

 

The PLS pond lies 200 m north of the CCD thickeners. From there, solvent extraction circuit, tank farm and EW tankhouse are arranged south to north.

 

The main substation that powers the site is located due west of the grinding area.

 

The chiller station that supports that underground mine is located due east of solvent extraction.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 339

 

14.5.2Equipment Design

 

An Equipment List has been compiled for the Santa Cruz plant based on the flowsheets, the Metsim mass balance, the Process Design Criteria, and comparisons with similar projects of similar scale. This equipment is summarized below by area:

 

· Primary Crusher – 888 t/h; fed by the railveyor discharge surge bin by a vibrating grizzly. 130 mm closed setting. Size: Metso C150 or equivalent; Stockpile feed conveyor is 300 m long by 36 inch wide belt. 680 t/h capacity
· Stockpile – Total storage – 60,000 t; Live storage – 15,000 t; Stockpile cover 74 m diameter by 30 m high; Reclaim by three apron feeders (two operating) at a rate of 340 t/h. SAG mill feed conveyor has a 782 t/h rate of which 665 t/h is fresh feed and 117 t/h is from recycled pebbles. The SAG mill feed conveyor measures 200 m long x 1.2 m wide, 20 m lift
· SAG mill – 7.6 m diameter by 3.4 m EGL; Synchronous 4.8 MW motor; F80 = 144 mm; P80 = 2 mm; Relining machine to handle cast steel liners
· Two SAG mill 3.6 m x 7.3 m double deck discharge screens (one operating, one standby), 782 t/h capacity
· Ball Mill – 4.8 m diameter x 7.3 m long; pinion drive 2.8 MW motor
· Primary cyclone cluster – 2,625 m3/h slurry at 37% slurry density. Overflow flow rate is 1,380 m3/h with a P80 = 300 microns
· Pre-Leach Thickener – 1,380 m3/h capacity; 32 m diameter, conventional thickener; underflow density = 70%
· Leach Tanks – Five operating; 862 m3 working volume; 10 m diameter x 11 m high; C.S. with HDPE or other lining; MOC must tolerate chloride as well a sulfate. Solids density of 50%; chlorobutyl rubber lined agitators with 90 kW power each
· CCD Thickeners – Five operating; 30 m in diameter; high rate thickener; C.S. tank with HDPE or brick lining; chlorobutyl rubber lined mechanism; MOC must tolerate chloride as well as sulfate. Feed solids density is 41.5%; Underflow solids density is 70%
· Solvent Extraction Settlers/Mix Tanks – Three stages of mix tanks per settler, 25 m3 volume , 3 minutes retention time; FRP construction, 2 Extraction Settlers with dimensions 16 m x 21 m; FRP construction
· Strip Settlers – Two stages of strip settlers; 16 m x 21 m; flowrate = 582 m3/h; FRP construction; one mix tank for first settler stage; 2 mix tanks for second stage
· Electrolyte Filters – Four multimedia filters; 316SS construction; total flow rate = 300 m3/h; max flow rate per filter is 100 m3/h. One filter scour air blower 576 m3/h at 50 kPa; Fed from 8m diameter x 6 m high 316SS Filter Feed Tank
· EW Tankhouse – 140 polymer concrete EW cells arranged in two rows; 6.5 m long x 1.25 m wide; Solution feed = 240 l/min/cell; Current density = 330 A per/m2; cell voltage drop 2.1V with current efficiency of 92%; 60 316SS cathode blanks per cell; 61 lead anodes per cell; Rich electrolyte Cu grade = 52 g/l; Lean electrolyte grade = 33 g/l
· Cathode Stripping Machine – Fully automatic, robotic; features include washing, stripping and stacking cathode copper; designed to produce 197 cathodes per hour
· EW Crane – Class E 10-ton crane; travel speed 91.5 m/min; acid vapor resistant design; no aluminum motor housings
· Residue Neutralization Tanks – Two 450 m3 capacity agitated tanks; 8.3 m dia x 8.8 m; C.S. with chlorobutyl rubber lining; first tank for neutralization w/ limestone at 50% solids density; second tank for neutralization w/ lime at 50% solids density; to accommodate approximately 900 m3/h slurry flow rate

 

September 2023

SEC Technical Report Summary – Santa CruzPage 340

 

· Residue Grinding Mill – One vertical stirred mill; Metso VTM-2500 or equal; 355 t/h feed rate; product size P80 = 106 microns
· Rougher Flotation – Six 200 m3 tank cells; feed flow rate = 1,795 m3/h at 30% solids & 15% froth factor; concentrate flow rate = 151 m3/h; at 28% solids
· Concentrate Regrind Mill – vertical stirred mill; VTM-200; Feed flow rate = 295 m3/h slurry with 52 t/h of solids, P80 = 74 microns
· Cleaner Flotation – First cleaner is one bank of four 50 m3 tank cells; feed flow rate = 295 m3/h at 19% solids and 15% froth factor; concentrate flow rate = 63 m3/h; concentrate flow rate at 28% solids; tailing flow rate = 232 m3/h at 16% solids
· First Cleaner Scavenger – One bank of 50 m3 tank cells, feed flow rate = 232 m3/h at 16% solids and 15% froth factor; concentrate flow rate = 3.6 m3/h at 28% solids; tailing flow rate = 228 m3/h at 16% solids
· Second Cleaner - Cleaner is one bank of four 10 m3 tank cells; feed flow rate = 131 m3/h at 16% solids and 15% froth factor; concentrate flow rate = 32 m3/h; at 28% solids; tailing flow rate = 99 m3/h at 10% solids
· Tailing Thickener – One thickener, 27 m in diameter. Feed flow rate = 525 m3/h of slurry containing 653 t/h of solids; underflow density of 63% solids
· Limestone Preparation – Feed is P100 = 50 mm; Combination of cone crusher, ball mill, and hydrocyclone to produce limestone with P80 = 44 microns
· Lime Package – 300 t silo, vertical stirred mill, mixing and distribution tanks; piping and pumps

 

14.6Consumable Requirements

 

The Santa Cruz plant has two full process lines, one for copper hydrometallurgical recovery of acid soluble (oxide) copper and a conventional copper flotation concentrator for the recovery of copper sulfide minerals as mineral concentrate. In between these process lines is a neutralization section of the plant to prepare the leach residue to be suitable for the flotation concentrator. The suite of consumables and reagents for both process lines is listed in Figure 14-3.

 

The upstream comminution section of the plant requires wear liners for the crusher and grinding mills. The grinding mills also require grinding media, steel balls in the SAG and ball mills and ceramic media in the vertical stirred mills in the flotation section.

 

The copper hydrometallurgical section requires sulfuric acid for agitated tank leaching. The solvent extraction circuit requires large quantities of diluent (organic), and extractant, which partitions the copper ions in solution between the aqueous and organic phases. The EW tank house requires cobalt sulfate and guar to smooth the electrowinning of copper on to cathode blanks. It also requires a mist suppressant to diminish sulfuric acid inside the tank house.

 

The neutralization section requires both limestone and lime for treatment of leach residue. Both consumables must be ground at the plant to a fine grind size to achieve maximum neutralization efficiency.

 

The mineral concentrator section requires a suite of organic collectors and frothers.

 

Flocculant is required to promote settling in the various thickeners and CCDs in the plant.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 341

 

Figure 14-3 lists the primary reagents and consumables used in the Santa Cruz plant. Other reagents and consumables not described above: diatomaceous earth and anti-scalant, are relatively minor.

 

 

 

Source: M3, 2023

 

Figure 14-3: Santa Cruz Plant Primary Reagents and Consumables

 

14.7QP Opinion

 

Based on the results of metallurgical testwork reported in Section 10 of this report, the land and permitting status of the Project, and the maturity of design for the Santa Cruz plant, it is the opinion of the M3 QP that the layout designs, equipment sizing and designs, and interpretations meet standard industry practices and are adequate for this level of study.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 342

 

15Infrastructure

 

15.1Location & Roads

 

The Santa Cruz Project is located 11 km west of Casa Grande, Arizona. It is approximately 9 km southwest of ASARCO’s Sacaton open pit copper deposit. The Santa Cruz Project covers a three primary copper deposits and various exploration areas along a belt of deposits approximately 11 km long and 1.6 km wide. The Santa Cruz Project located in in Township 6 S, Range 4E, Section 13, Quarter C.

 

From a standpoint of logistics, the Santa Cruz Project is well accessed and well served by highways and paved roads surrounding the property. Figure 15-1 shows the location of the Santa Cruz Project relative to highway and road access to the property. Two US Interstate highways, I-8 to the south and I-10 on the east are 8 km and 15 km from the Project site, respectively. State Highway 84 between Casa Grande and Stanfield borders the south of the property. The West Maricopa – Casa Grande highway borders the property on the northeast side and runs parallel to the United Pacific Southern Pacific (USPS) rail line. A network of paved and improved unpaved roads run along section and quarter section lines throughout the Project area.

 

 

 

Source: M3, 2023

 

Figure 15-1: Project Location and Road Network

 

September 2023

SEC Technical Report Summary – Santa CruzPage 343

 

15.2Project Layout

 

The Santa Cruz Project lies in a flat valley west of the city of Casa Grande. The land is nearly completely level except for a small depression along the wide ancestral Santa Cruz flood plain. The Santa Cruz mine and plant site are shown on the Project site plan as Figure 15-2. Prominent features included in the site plan include the mine portal, the trace of the railveyor that delivers mineralized material from the underground mine to the plant, the plant site proper, the Tailing Storage Facility (TSF), two phases of the mine solar field, the borrow pit for the TSF impoundment fill, the paste backfill plant, the mine administration buildings, the mine workshops and ancillary facilities, the proposed main substation, and the water settling pond for collecting mine dewatering water. With the exception of the TSF, these facilities lie outside of the Santa Cruz River flood plain.

 

The layout as presented reflects the current level of study. Modifications to the Project site plan will be evaluated as engineering and permitting progress at more advanced levels of study.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 344

 

 

 

Source: M3, 2023

 

Figure 15-2: Santa Cruz Site Plan

 

September 2023

SEC Technical Report Summary – Santa CruzPage 345

 

Figure 15-3 is a general arrangement showing some of the mine and plant facilities in better detail. One of the priorities in the layout of the facilities is to keep some separation between the mine and plant buildings.

 

A minimum of the facilities were located directly above the Santa Cruz mineral deposit to avoid any subsidence that could disturb surface facilities. Most of the mine shops that are located within the outline of the Santa Cruz mineral deposit footprint are light structures with a minimum of potential for settling.

 

Figure 15-3 also show the location of the ventilation chiller located on the east side of the plant. The Chiller needs to be located where is can best access the underground workings to support mining in hot conditions. The paste backfill plant is also located over the top of the Santa Cruz mineral deposit to be able to reach the stopes that require backfill by gravity.

 

The water settling pond will be the collection point for dewatering water from development wells during construction and water pumped from the underground mine sumps during development and operations. It will also collect reclaim water from the TSF and filtrate from the paste backfill plant.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 346

 

 

Source: M3, 2023

 

Figure 15-3: Santa Cruz General Arrangement Detail

 

September 2023

SEC Technical Report Summary – Santa CruzPage 347

 

15.3Rail

 

The Santa Cruz Project has excellent access to railroads. The Union Pacific/Southern Pacific (UPSP) main line is a coast-to-coast railroad that in runs within 5 km of the center of the property. It has numerous sidings along the W Maricopa – Casa Grande Highway that access factories and businesses along its length. While no rail siding and rail unloading yard are presently planned for the Santa Cruz Project, the proximity of the rail line to the Project for short distinct provides logistical advantages for the delivery of the primary consumables: sulfuric acid, cement, limestone, and lime, and the outbound shipping of mineral concentrates and copper cathodes to smelters, ports, and offtakers.

 

Figure 15-4 shows the UPSP network of railroads across the United States. The major smelters in the US and in nearby Sonora, Mexico can be accessed by rail from the Santa Cruz Project. Also, the major transshipment ports all have rail access that provide advantages for the Santa Cruz Project.

 

 

 

Source: M3, 2023

 

Figure 15-4: UPSP Rail Network Across Western US

 

The Burlington Northern Santa Fe (BNSF) railroad also has routes across northern Arizona, connecting to California as well as points to the east. Figure 15-5 shows the routes of the BNSF and the spur that accesses the Phoenix area. The BNSF system directly accesses the Port of Long Beach, CA as well as the other west coast ports.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 348

 

 

 

Source: M3, 2023

 

Figure 15-5: BNSF Rail Network Across Western US

 

15.4Port Facilities

 

There are several candidates for port facilities on the west coast that can support the Project. The Port of Long Beach is the largest container port in the US. The Port of Los Angeles can support international shipping as can ports located in San Francisco and Stockton, California. In Mexico, the Port of Guaymas is used for shipping mineral concentrates to overseas smelters.

 

There is a sulfuric acid terminal in Stockton, California that could be an inexpensive source of acid for the property. Figure 15-6 shows the location of the nearest ports as well as the distribution of inland smelters.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 349

 

 

 

Source: M3, 2023

 

Figure 15-6: Ports and Copper Smelters in the Western US and Mexico

 

Smelters are located in Arizona at Hayden (ASARCO) and Miami (Freeport McMoran). The Hayden smelter is currently closed and the future of this facility is currently unknown. The Kennecott smelter (Rio Tinto) in Magna, Utah, is also accessible by railroads. Another inland smelter is the Nacozari smelter (Grupo Mexico) located in Sonora, Mexico. This facility accepts mineral concentrates from ASARCO mines and supplies sulfuric acid to its properties.

 

15.5Tailings Disposal

 

KCB prepared the TSF initial assessment design for the Santa Cruz Project.

 

15.5.1TSF Siting and Foundation Characterization

 

The TSF is located within the Project’s property boundary and sited to avoid: the underground ore body outline, mine’s infrastructure, and the 1% annual exceedance probability (AEP) (1 in 100 yr return period) floodplain from Federal Emergency Management Agency (FEMA) (2007) flood hazard mapping (Figure 15-7). The TSF is sited primarily in the 1 in 0.2% AEP (500-yr return period) floodplain (FEMA 2007).

 

September 2023

SEC Technical Report Summary – Santa CruzPage 350

 

Subsurface geotechnical hydrogeological investigations have not been performed to characterize the properties or conditions of the TSF foundation for design. Drilling conducted in other areas of the Project site, and surficial geology maps produced by the US Geological Survey (Klawon et al. 1998) indicate the TSF is founded on thick (> 200 m) floodplain sediments (CNI 2022). As such, these sediments are the likely foundation units that will influence TSF design. The regional groundwater table in the TSF footprint is assumed to be > 100 m below surface based on investigations performed in the mine area.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 351

 

 

Source: KCB, 2023

 

Figure 15-7:Site Location, General TSF Layout, and Flood Risk

 

September 2023

SEC Technical Report Summary – Santa CruzPage 352

 

15.5.2Design Basis

 

The following summarizes key design basis assumptions for the TSF:

 

The TSF operating life is 23 years. Based on annual tailings production and underground backfill requirement estimates, an average of 6,750 tonnes per day (t/day) and a maximum of 9,800 t/day of tailings will be sent to the TSF.

The TSF will have capacity to store all tailings that are not used for underground backfill. For TSF design, a target total tailings tonnage of 56.7 Mt was selected.

The tailings comprise ~30% sand-sized and ~70% silt/clay sized particles based on index testing performed to date. Based on understanding of the ore body geochemistry, ore and tailings processing methods and tailings test work completed to date, IE has indicated that the tailings are assumed to be non-potentially acid generating (NPAG).

Tailings will be transported from the plant site at 60% to 65% solids by weight and discharged as a slurry from a perimeter embankment. For TSF sizing KCB assumed an average tailings beach slope angle of 1%.

An average tailings dry density of 1.4 t/m3 for TSF sizing, resulting in a total storage volume of 40.5 Mm3. The TSF starter dam will be sized to store the first two years of tailings production (1.0 Mm3).

The TSF will meet stability, water management and closure criteria that align with ADEQ (2005) and internationally recognized guidelines for TSF design (GTR 2020, CDA 2019).

 

15.5.3Design Features

 

The ultimate TSF footprint is shown on Figure 15-7 and covers an area of approximately 170 hectares. Pipeline(s) and associated pumps, designed by others (not shown on Figure 15-7), will transport thickened tailings slurry from the plant site to the TSF. Due to very little topographic relief within the TSF footprint (from 403 masl to 407.3 masl), the TSF will have a ring dyke/perimeter embankment configuration with tailings deposited from the embankment crest towards the middle of the impoundment. The TSF footprint is expanded, as far as practical, to reduce overall embankment fill requirements and improve embankment fill to storage ratios.

 

Key features of the TSF during operations are summarized below and illustrated on a schematic cross section on Figure 15-8.

 

A starter dam constructed from compacted, structural fill sourced from within the TSF impoundment. Details are summarized in Table 15-1.

 

A progressively raised, perimeter embankment constructed from compacted, structural fill sourced from an on-site borrow area and a geomembrane liner for seepage control (details summarized in Table 15-1). The perimeter embankment will be raised using a centerline approach whereby the embankment centerline established with the starter dam is maintained throughout operations and each raise is constructed by placing fill onto the tailings beach and onto the downstream slope of the previous raise. The centerline of the embankment remains founded on structural fill throughout operations. This approach has the following benefits:

oEliminates need to develop a structural zone within the deposited tailings to meet stability compliance criteria.

oMaintaining the centerline simplifies liner raising.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 353

 

A liner system within the TSF impoundment, below the tailings, comprised of low permeability layers (80 mil high-density polyethylene (HDPE) liner overlying a 300 mm thick layer of low-permeability compacted fill) and an above-liner drainage layer (450 mm thick layer of 19 mm-minus sand and gravel with perforated HDPE pipes spaced 60 m apart), to limit seepage into the foundation. The perforated pipes in the above-liner drainage layer will report to solid HDPE pipes which run below the embankment and convey water to the perimeter sumps (see below). This approach generally follows the ADEQ (2005) Prescriptive guidelines for TSF design. The requirements for the liner system will be reviewed in future design stages when the geochemical characteristics of the tailings, process water and foundation are better understood.

Riprap for embankment slope erosion protection which will be progressively placed as the ultimate downstream slope of the perimeter embankment is established; and

Contact water collection ditches and sumps along the toe of the embankment to collect slope surface runoff and flow from the above-liner drainage layer.

 

Table 15-1: Starter Dam and Ultimate Embankment Summary

 

Parameter Starter Dam Perimeter Embankment
(End of Operations)
Storage Capacity 1.35 Mt tailings (1.0 Mm3) + Operating Pond + Inflow Design Flood (IDF) (0.3 m) + 1.0 m freeboard 56.7 Mt tailings (40.5 Mm3) + Operating Pond + IDF (0.3 m) + 1.0 m freeboard
Crest Elevation 409.2 masl. 453.5 masl
Crest and Slope Details

3H:1V downstream slope

2H:1V upstream slope

25 m crest width

3H:1V downstream slope

Vertical upstream face

25 m crest width

Height 2 to 6 m 46 to 50 m
Fill Volume 0.6 Mm3 19.8 Mm3

 

Source: KCB, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 354

 

 

 

Source: KCB, 2023

 

Note: Not to scale

 

Figure 15-8: TSF Embankment Schematic Cross Section During Operations

 

September 2023

SEC Technical Report Summary – Santa CruzPage 355

 

15.5.4Embankment Stability

 

TSF stability was analyzed using the 2D limit-equilibrium analysis software Slope/W (GeoStudio 2021.3) for the following scenarios:

 

Static: normal loading conditions with effective friction angles assigned to all materials.

Post-Earthquake: post-earthquake loading conditions using effective friction angles for the fill and foundation, and residual, undrained shear strength (i.e., liquefied strength) for the tailings.

oUncertainties regarding the tailings’ response to seismic loading at this design stage are managed by the assumption that all tailings will liquefy during design earthquake loading. This approach is consistent with guidelines (e.g., GTR 2020) for new TSF designs with potentially brittle failure modes.

 

The pseudo-static criterion referenced in the ADEQ (2005) guidelines is not appropriate for this design, where the tailings are assumed to be susceptible to liquefaction. A deformation analysis may be appropriate for future design stages to confirm containment integrity under seismic loading.

 

The target FoS was achieved for both loading scenarios (Table 15-2). The critical slip surfaces for both loading scenarios were shallow, passing through the embankment fill. Higher FoS was calculated for slip surfaces passing through the tailings. This is due to the embankment design and the resulting wide structural zone supporting the tailings.

 

Table 15-2: TSF Target and Calculated FoS

 

Scenario Target FoS Calculated FoS
Static 1.5 2.0
Post-Earthquake 1.2 2.0

 

Source: KCB, 2023

 

15.5.5Water Management

 

The TSF impoundment will have capacity to store the 72-hour probable maximum flood (PMF) volume above the assumed operating pond volume, while maintaining a minimum 1.0 m freeboard below the embankment crest. The TSF will not have an emergency spillway since the impoundment can store the PMF volume.

 

The perimeter ditches and sumps located along the downstream toe of the ultimate embankment will collect peak flow reporting from the TSF slopes and collect TSF seepage from the above-liner drainage layer (refer to Section 15.5.3). Water collected in the sumps will be returned to the plant site for reuse in processing or treated, if required, and discharged.

 

The TSF pond has a net water deficit on an annual basis due to high evaporation rates, as such, the TSF will not be able to supply mill makeup water consistently throughout the year.

 

15.5.6Closure Plan

 

At closure, additional riprap armoring will be placed on the embankment slope and toe to resist the slope runoff and floodplain inundation during the PMF. The TSF impoundment will be re-graded to prevent ponding and covered with a soil cover and vegetated to limit infiltration and resist erosion. Channels will be constructed over the impoundment surface and embankment slopes for surface water routing. Refer to Figure 15-9 for a schematic cross section illustrating some of these features.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 356

 

 

 

Source: KCB, 2023

 

Note: Not to scale

 

Figure 15-9: TSF Embankment Schematic Cross Section – Closure

 

September 2023

SEC Technical Report Summary – Santa CruzPage 357

 

15.6Power

 

15.6.1Power Sources

 

Power for the Project could be provided from a number of sources or combination of sources ranging from grid supply to microgrid renewable energy supply. The goal of the mine development is to achieve much of the energy supply from renewable sources either at the start or through a phased in approach during the mine operation. Two independent third parties (Sage Geosystems and KR Saline & Associates), with experience with local grid supplied power and with renewable supplied power, have produced studies for this report regarding energy supply and the potential energy cost per megawatt hour.

 

Regular grid supplied power could come from one of three potential suppliers that have transmission lines and substations nearby the Project site: Electrical District No.3 (ED-3), Arizona Public Service (APS) or Salt River project (SRP) are the potential suppliers. The latter two are the largest utilities in Arizona and ED-3 is a small local supplier to the Maricopa Stanfield area including the Maricopa Stanfield Irrigation and Drainage District (MSIDD). Figure 15-10 shows the various power transmission lines within close proximity of the Santa Cruz Project. The proposed mine substation and surface facilities lie in the ED-3 service area. ED-3 could be the grid power supplier in the future.

 

 

Source: M3, 2023

 

Figure 15-10: Transmission lines near the Santa Cruz Project

 

Renewable energy supply (energy storage, batteries probably) could come from an independent power provider (over-the-fence contract agreement), a microgrid renewable energy system or as wheeled in renewable energy as APS supplies currently to some customers. Renewable energy could be generated and stored on site in the first two options mentioned. There is very high solar irradiation at site (Arizona has the highest solar irradiation factor in the nation) so PV solar energy would be an option. Additionally, the site is situated over a significant source of geothermal energy that could be used to generate power by conventional geothermal methods. A combination of solar, geothermal and battery storage was evaluated by both consultants mentioned above.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 358

 

Several energy supply solutions were evaluated ranging from all or a portion of the power coming from the grid from ED-3 and/or all or a portion coming from renewable energy provided by an independent power provider. Without consideration for escalation over the next twenty years, the cost of energy ranged from a low of US$71 per megawatt hour (large industrial supply rate from ED-3) to US$121 per megawatt hour for a renewable energy supply from a combination of solar, geothermal and battery storage (from an independent power provider). The base economic case for the Project uses the option where 30% of the energy comes from a local grid source (ED-3 at US$71 per megawatt) and 70% comes from an independent power provider (utilizing a combination of PV solar, geothermal and battery storage at US$121 per megawatt). The weighted average energy cost in the base case is US$106 per megawatt hour.

 

15.6.2Power Distribution

 

Grid power to the site will likely come from the 69kV power line operated by Pinal County Electrical District 3 (ED3). The nearest substation drop from the ED3 power line is located at intersection of State Highway 84 and South Anderson Road, a distance of 5 km from the Santa Cruz main substation at the plant site. At this substation, power will be transformed to 13.8 kV for sitewide power distribution to facilities. Overhead power lines will follow existing roads wherever possible for ease of maintenance and re-use of existing power poles.

 

Each cluster of process facility will have its own E building and transformer to step down power to the needed voltage. Most process facilities require 480V 3phase 60Hz power for operations. The grinding mills, the EW rectifiers, the chiller facility and the mine ventilation fans will require a higher voltage supply, most likely 4,160 volts.

 

The underground mine requires three power circuits to be distributed for the mine dewatering pumps, the railveyor, and for a power recharging station for underground vehicles. Three 13.8 kV feeders will be installed on a pole line along 2.5 km of existing roads to the mine E-building at the surface outside the mine portal. From there, the 13.8 kV feeders will be run down the main mine decline for a distance of 5 km to the main mine load center where the power will be stepped down to its operating voltages.

 

Duct banks will be used inside the plant at road crossings wherever necessary.

 

15.6.3Power Consumption

 

The Santa Cruz Project has a total connected load of 60.8 MW and an annual consumption of between 436,000 MWh and 473,000 MWh in peak years of production.

 

The connected power for the underground mine equipment averages 26.2 MW. The total annual consumption attributed to the UG mine over the LoM averages 211,000 MWh/y. The high consumers of power in the underground mine are:

 

Mine ventilation fans

Mine dewatering pumping system

Railveyor material conveying system

 

September 2023

SEC Technical Report Summary – Santa CruzPage 359

 

Battery recharging station for electric UG mining equipment

AC cable mobile equipment

Paste backfill plant

 

The connected power for the Santa Cruz process plant and surface facilities is 34.6 MW, the annual power consumption during peak production years is 242,000 MW/y. The large consumers of power include:

 

Grinding mills (SAG and ball mills)

Leach tank agitators

Electrowinning of copper by DC power

Regrinding and flotation

Slurry pumping o various facilities and unit operations

Ventilation chiller

 

The usage load of connected power for the Santa Cruz operation averages 86% of connected power at peak production. is an estimation of power consumption by Year of operation over the course of the mine life.

 

Mine dewatering from surface wells during pre-production will require generator power for approximately 3 MW of connected power during Years -3 and -2. These costs will be capitalized and are not part of the annual operating costs. Table 15-3 summarizes the power consumption for the Santa Cruz Project over the LoM.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 360

 

Table 15-3: Summary of Power Consumption over the LoM for Surface and Underground Facilities

 

Year Surface Underground Mine Total
Connected, MW Usage, MWh Connected, MW Usage, MWh Connected, MW Usage, MWh
-3            
  Running on diesel gensets first 2 years of the Project  
-2    
-1 - - 16.53 124,219 16.53 124,219
1 34.63 167,067 21.71 175,131 56.34 342,198
2 34.63 242,404 23.07 194,771 57.70 437,175
3 34.63 240,467 23.45 195,762 58.08 436,229
4 34.63 248,805 23.71 196,467 58.34 445,272
5 34.63 252,963 23.71 197,508 58.34 450,470
6 34.63 249,898 24.60 204,476 59.23 454,374
7 34.63 252,419 24.60 205,393 59.23 457,812
8 34.63 245,601 24.60 202,295 59.23 447,896
9 34.63 245,958 27.74 229,451 62.37 475,409
10 34.63 235,323 27.74 229,213 62.37 464,537
11 34.63 245,119 27.74 227,543 62.37 472,662
12 34.63 232,192 27.74 227,129 62.37 459,321
13 34.63 236,439 27.74 225,636 62.37 462,075
14 34.63 234,413 27.74 226,731 62.37 461,144
15 34.63 236,333 27.74 226,729 62.37 463,061
16 34.63 235,125 27.96 224,423 62.59 459,548
17 34.63 243,957 27.96 224,034 62.59 467,991
18 34.63 239,995 27.92 223,040 62.55 463,035
19 34.63 102,431 27.92 204,691 62.55 307,122
20 34.63 8,743 27.74 184,385 62.37 193,129
  34.63 4,395,651 26.16 4,224,809 60.79 8,620,460

 

Source: M3, 2023

 

15.7Water

 

The main sources of water for the Santa Cruz Project will come from non-contact dewatering water estimated to be 6 Mm3/y and residual passive inflows from precipitation estimated to be approximately 2 Mm3/y. Another 170,000 m3 per water comes from moisture in mined material. Other sources of water: rainwater on ponds, are insignificant.

 

Precipitation in the Casa Grande area over the years from 2016 to 2020 averages 22 cm/y. Annual evaporation of water averages nearly 250 cm per year (cm/y), far outweighing precipitation.

 

The total water consumption for the Santa Cruz operation is estimated to be 3,500,000 m3/y (400 m3/h). The largest sink for water is entrained water from the TSF. Approximately 37% of the tailing by weight is water is 37% of which 30% remains entrained after tailing consolidation. That amount translates to 1.65 million cubic meters per year (Mm3/y) of water lost to the TSF. Water entrained in paste backfill amounts to approximately 850,000 m3 per year. The third largest consumer of water at Santa Cruz is water for dust control, estimated to be 290,000 m3 per year. Potable water consumption, evaporation from the PLS pond, evaporation for the Water settling pond, and evaporation from the Raffinate pond are each under 100,000 m3 per year.

 

Water will be recovered from TFS seepage and from filtration of tailing slurry during preparation of paste backfill for underground operation amounting to a combined 600,000 to 700,000 m3 per year. These two sources of water will be recycled to the Process Water tank, provided the quality of the water is sufficient for use in leaching and flotation.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 361

 

Water available for stakeholder distribution is estimated to average approximately 25 Mm3/y over the LoM including the development years from early dewatering. The amount of water available for distribution increases from approximately 20 Mm3 per year in the early years to nearly 30 Mm3/y in the latter years of the mine life due to deeper levels of development and greater inflows are more water at depth. This amount of water for distribution amounts to approximately 3,040 m3/h.

 

15.8Pipelines

 

A natural gas pipeline crosses the Santa Cruz property and accesses various residential customers, farms, and businesses west of Casa Grande. Natural gas could be used in the Santa Cruz plant for hot water heaters for the EW tankhouse and possibly for onsite emergency power generation. Figure 15-11 shows the distribution of natural gas pipelines within the Project site. A section of the pipeline crosses the proposed location of the TSF, so it is probable that this section of the gas line would have to be relocated at some point during Project development.

 

 

 

Source: M3, 2023

 

Figure 15-11: Transmission lines near the Santa Cruz Project

 

September 2023

SEC Technical Report Summary – Santa CruzPage 362

 

15.9QP Opinion

  

Met Engineering is of the opinion that the sources and prices of power are well understood and have been interpreted from reliable studies and evaluations by experts in this field.

 

It is the opinion of KCB, responsible for the TSF design, that the level of assessment and design are appropriate for an initial assessment and represent good industry practice.

 

It is the opinion of M3, responsible for the infrastructure, that the level of assessment and design are appropriate for an initial assessment and represent good industry practice.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 363

 

16Market Studies

 

16.1Market Information

 

Copper metal is a ductile metal with high electrical and thermal conductivity. It is used extensively in building construction, equipment manufacture, power generation and transmission, electrical motors and cabling, and electronics.

 

Copper is a globally traded commodity that has established benchmark pricing in the form of exchanges such as the London Metals Exchange (LME) or Commodity Exchange Inc. (COMEX). Copper from mine sites is typically sold as either electrowon copper cathode or as a concentrate or precipitate containing a significant amount of copper metal. In 2022, the US copper production totaled 1.26 Mt (USGS, 2023a). Slightly less than half of this production (approximately 44%) was in the form of electrowon copper.

 

Electrowon copper cathode can be sold to downstream manufacturers for use while copper concentrate must first be smelted to produce blister, matte or anode and potentially further refined before being useful to downstream users.

 

16.1.1Market for Santa Cruz

 

The Santa Cruz Project is envisioned to produce both copper cathode and copper concentrate.

 

IE has indicated that the copper produced from Santa Cruz will be sold into regional markets within which the Project is located. The Project is envisioned to produce generic copper cathode grading at least 99.9% and concentrate grading greater than 35% copper.

 

16.1.2Copper Demand

 

Copper is required for electrification and equipment manufacturing. In developing areas, copper consumption mainly occurs in the form of infrastructure build-out and the manufacture of equipment and electronics. In developed areas, consumption is typically driven by infrastructure replacement or upgrades and equipment manufacture. The drive toward electrification increases the demand for copper as a result of an increase in power generation, transmission and consumption.

 

Electrification and continuing development in previously undeveloped areas of the world requires a significant amount of copper and is expected to continue to be a driving force for the consumption of copper. This results in a long-term positive outlook for copper demand over the next several decades. This is somewhat tempered in the near term should significant economic headwinds materialize that slow global growth.

 

16.1.3Copper Supply

 

The USGS estimates that the global copper mine production at 22 Mt in 2022 (USGS, 2023b). The process for discovering, studying, building and bringing new mines into production or out of production is one that can take decades to complete. This results in a slow supply response within the copper market and the likely development of supply deficits and surpluses that will create price volatility. In the long term, these deficits and surpluses will diminish as new operations come online or expansions of existing operations are completed, or existing operation shut down or depleted. However, the market is unlikely to remain in balance for significant periods of time due to the slow supply response and price volatility will result.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 364

 

16.1.4Trailing Price

 

Table 16-1 presents the average annual price for copper (LME Grade A).

 

Table 16-1: Average Annual and Spot Pricing

 

Year Year 5 Year 4 Year 3 Year 2 Year 1 Spot (August 15, 2023)
Price (US$/lb) 2.77 2.60 3.78 4.28 3.81 3.69

 

Source: SRK (S&P Global Data) , 2023

 

The 3-year trailing average is US$3.95/lb.

 

16.1.5Study Price and Sales Terms

 

Pricing

 

A price of US$3.80/lb has been selected for this study exercise. This price is below the three year trailing average, equal to the 1 year trailing average and slightly elevated from the current spot price. In the opinion of SRK, this price is generally in-line with pricing over the last 3 years and forward looking pricing is appropriate for use during an Initial Assessment of the Project with an estimated mine life extending into 2048. As the Project progresses, more detailed market work in the form of market studies will be completed to support further study efforts. SRK cautions that price forecasting is an inherently forward looking exercise dependent upon numerous assumptions. The uncertainty around timing of supply and demand forces has the potential create a volatile price environment and SRK fully expects that the price will move significantly above and below the selected price over the expected life of the Project. In light of this expected volatility, it is SRK’s opinion that the selected price is a reasonable assumption for the evaluation of a long term mining asset with a 20+ year life as it provides a neutral price point both in line with historical pricing and with expected long term pricing.

 

Cathode

 

Cathode is assumed to be 100% payable with no premium or discount applied. This approach assumes that the cathode has not received registration or certification that would result in in a premium; nor is the cathode assumed to contain any deleterious or penalty elements.

 

Concentrate

 

Concentrate terms are generic terms and do not reflect the presence of any deleterious or penalty elements within the concentrate. Table 16-2 presents the concentrate terms applied for this study.

 

Table 16-2: Concentrate Terms

 

Item Unit Value
Payability % 96.5
Treatment Charge US$/dmt 65
Refining Charge US$/lb 0.065
Transport Cost US$/wmt 90

 

Source: SRK, 2023

September 2023

SEC Technical Report Summary – Santa CruzPage 365

 

16.2Contracts and Status

 

Table 16-3 provides a list of major contracts needed to develop and operate the Project.

 

Table 16-3: Major Contracts

 

Contract Description Status
Drilling Contracts for diamond coring, reverse circulation, tricone rotary, and shallow sonic boring Executed
     
Mine Decline Development Contracts for decline development using roadheader Not executed
Mine Vertical Development Contracts for shaft sinking and raisebores Not executed
Mine Supplies Contracts for explosive delivery, ground support, ventilation, electrical, pumping and miscellaneous consumables Not executed
Major Equipment Providers Contracts for major equipment including production equipment, auxiliary equipment, UG infrastructure and miscellaneous equipments Not executed
Concentrates sales Contracts for the offtake of copper
concentrate to generate revenue. Must include conditions for conc. grade, moisture, and penalties as well as payables
Not executed
Cathode Sales Offtake agreement or sales agreement with commodity warehouse. Must include payables, strike price, cathode purity, and penalties for impurities. Not executed
     
Concentrate
transport
Contracts for transport of copper
concentrate to buyers.
Not executed
Power Supply Contracts for supply of local grid power and for renewable power from independent power provider Not Executed
Sulfuric Acid Contract for long-term supply of sulfuric acid Not executed
Limestone/Lime Contract for long-term supply including transportation to site Not executed
Cement Contract for supply of cement for the paste backfill plant including transportation to the site Not Executed
Diesel/Light Vehicle Fuel Supply Contract for the supply and delivery of fuel for surface vehicles and diesel underground vehicles to the site Not Executed

  

Source: SRK, M3, Met Engineering, Nordmin, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 366

 

17Environmental Studies, Permitting, and Plans, Negotiations, or Agreements with Local Individuals or Groups

 

17.1Environmental Study Results

 

17.1.1Flora and Fauna

 

Site flora and fauna are described in a biological evaluation by WestLand Engineering & Environmental Services (WestLand) (2022a) and are summarized here. Undisturbed uplands within and surrounding the property are open with a shrubland community dominated by creosote bush, saltbush, burroweed (Isocoma tenuisecta), desert ironwood (Olneya tesota), barrel cactus (Echinocactus spp.), white thorn (Acacia constricta), and velvet mesquite shrubs (Prosopis velutina). Much of the property south of North Branch Santa Cruz Wash contains abandoned agricultural fields. These abandoned agricultural areas contain the same vegetation community as the less-disturbed areas but with an appreciably higher annual grass and forb component. North Branch Santa Cruz Wash within the property supports xeroriparian vegetation dominated by velvet mesquite, wolfberry (Lycium sp.) creosote bush, and crucifixion thorn (Canotia holacantha). Desert broom (Baccharis sarothroides), Mexican palo verde (Parkinsonia aculeata), desert hackberry (Celtis ehrenbergiana), cocklebur (Xanthium strumarium), and nonnative and invasive tamarisk (Tamarix sp.) are present along North Branch Santa Cruz Wash in low densities, as well as a lone Fremont cottonwood (Populus fremontii). Bermuda grass (Cynodon dactylon) and other grasses and forbs line the irrigation levee that confines Santa Cruz Wash.

 

WestLand (2022a) describes that wildlife species activity observed within or close to the property include coyote (Canis latrans), javelina (Tayassu tajacu), gray fox (Urocyon cinereoargenteus), round-tailed ground squirrel (Xerospermophilus tereticaudus), common raven (Corvus corax), phainopepla (Phainopepla nitens), Cooper’s hawk (Accipiter cooperii), great blue heron (Ardea herodias), mourning dove (Zenaida macroura), black-tailed jackrabbit (Lepus californicus), greater roadrunner (Geococcyx californianus), turkey vulture (Cathartes aura), and hummingbird spp. (family Trochilidae). Carp spp. (family Cyprinidae) and catfish spp. (family Ictaluridae) were observed in the East Main canal bording a portion of the southwest corner of the property (WestLand, 2022a).

 

17.1.2Threatened and Endangered Species

 

Special-status species include species designated by the USFWS as endangered, threatened, proposed for listing, or candidate for listing under the Endangered Species Act and species protected under the Bald and Golden Eagle Protection Act (BEGPA), Endangered Species Act-listed, proposed, and candidate species. WestLand (2022a) evaluated the federal protection status, known suitable habitat, total range, and distribution in Arizona and determined that there are no Endangered Species Act species with potential to occur within the property. No USFWS designated or proposed critical habitat occurs on the property. A search of the Heritage Data Management System using the Arizona Game and Fish Department Online Environmental Review Tool found no records of Endangered Species Act listed special-status species within 3 miles (5 km) of the property (WestLand, 2022a). Two BEGPA species (golden eagle and bald eagle) were determined to have some potential to occur within the property (WestLand, 2022a).

 

A review of publicly available bald eagle sighting records in the area (ebird, 2023) show eagles perching on transmission poles and irrigation pivots to the west of the property, likely foraging in the agricultural field, irrigation canals, and ponds. There are no breeding behavior observations in the records. An incidental take permit from USFWS may be required for construction activities within 660 ft or blasting within a half-mile of an active eagle nest. As there are no known eagle nests in the area at this time, the Project is not expected to need an incidental take permit. Bald eagle use of the properties to the west of the Project will continue to be tracked, and best management practices will be implemented to protect bald eagles.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 367

 

17.1.3Migratory Bird Treaty Act

 

The Migratory Bird Treaty Act (MBTA) is intended to ensure the sustainability of all protected migratory bird species and currently includes protection of 1,106 avian species. Pre-construction clearance surveys are conducted weekly within the Project area to avoid the incidental take of migratory birds during active and evolving exploratory drilling operations.

 

Nesting migratory bird species identified in the Project area include the horned lark (Eremophila alpestris), red-tailed hawk (Buteo jamaicensis), mourning dove (Zenaida macroura), nighthawk (Chordeilinae sp.), cactus wren (Campylorhynchus brunneicapillus), raven (Corvus corax), ground sparrow (Spizella pusilla), and burrowing owl (Athene cunicularia) (WestLand, 2023).

 

All employees and contractors are trained on MBTA requirements and the Project’s migratory bird survey and monitoring protocols. Pre-construction clearance surveys and implementation of beneficial practices and procedures to protect migratory bird species will continue throughout the life of the Project.

 

17.1.4Surface Water Mapping

 

Under Section 404 of the Clean Water Act (CWA), the U.S. Army Corps of Engineers (USACE) is responsible for regulating the discharge of fill to surface water features determined to be Waters of the United States (WOTUS). WestLand (2022b) developed a Geographic Information System (GIS) delineation of the ordinary high-water mark (OHWM) within the surface water features of the property using current, publicly available aerial photography and subsequent, targeted field reconnaissance. This delineation was created based on the practices typically utilized by the USACE in assessing ephemeral channels in the arid Southwest.

 

Westland (2022b) concluded that much of the property has been previously disturbed from its natural state. These disturbances include flood control features, such as the canal identified as the Santa Cruz Wash Canal, paved and unpaved roads, and agricultural practices. These disturbances have removed all potential natural surface water features that may have existed in this area. The only features within the property that possess characteristics of an OHWM (and may be potential WOTUS) are the North Branch of the Santa Cruz Wash and the constructed Santa Cruz Wash Canal.

 

The North Branch of the Santa Cruz Wash is the downgradient extension of the Santa Cruz River between the Santa Cruz Flats to the south and the confluence with the Gila River to the north. This feature possesses the characteristics of an OHWM including changes in soil character, debris, scour, and an abrupt change in plant community. Based on the observed vegetation, it is possible that the channels of this feature may possess adjacent wetlands. The constructed Santa Cruz Wash Canal also serves a similar function as the North Branch, namely channeling flows from the Santa Cruz River northward through the City of Maricopa and the Ak-Chin Indian Community, towards the confluence with the Gila River to the north. As this canal serves to connect two other potential WOTUS (the Santa Cruz River and the Gila River), the canal is itself a potential WOTUS.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 368

 

It is important to note that the USACE retains the final authority for determining the presence of WOTUS and has, to date, not been asked to provide its concurrence with this delineation. However, the Project has been designed to avoid impacting potential WOTUS and is not expected to require a permit under Section 404 of the CWA.

 

17.1.5Cultural Heritage

 

An archeological evaluation of the property was completed by SWCA in 2005 and 2006 (Foster et al., 2006). In 2022, IE enlisted WestLand and their tribal monitor team to complete a Class III Cultural Survey to reassess 20 previously recorded sites (Middleton, 2022) and their eligibility for listing in the National Register of Historic Places (NRHP). Of the 20 sites reassessed, five sites were recommended eligible for listing in the NRHP. Despite there being no federal permitting or requirements under Section 106 of the National Prehistoric Preservation Act for private lands, the Santa Cruz team is committed to working directly with descendant communities to help preserve and protect places of important cultural value.

 

17.1.6Air Quality

 

The Santa Cruz Project is committed to responsible environmental management, with a particular focus on minimizing air quality impacts. This section provides an overview of the anticipated air emissions and the control measures that will be implemented to reduce those emissions. Through a thorough assessment of air emissions and the implementation of effective mitigation strategies, the Project is expected to be categorized as a synthetic minor source.

 

The challenges of operating in an arid climate are of particular concern to the Santa Cruz Project, especially regarding the location of the Project, within the West Pinal County PM10 (particulate matter emissions with a diameter less than 10 microns) Nonattainment Area. Recognizing this, the Project will take specific measures to control and effectively mitigate dust. These measures will be in alignment with both local and state requirements, demonstrating the Project's commitment to environmental stewardship.

 

The primary sources of air pollutants from the Project include:

 

Dust: Generated from mining activities, material handling, transportation, stockpiling, and windblown dust.

 

Combustion Emissions: Emissions from the operation of generators, equipment, and other fuel-burning equipment.

 

The Project is expected to be a synthetic minor source for regulated air pollutants. This means that while potential uncontrolled emissions may be above major source thresholds, they will be reduced to levels below major source thresholds through the implementation of operational restrictions and emission control technologies and practices.

 

The Santa Cruz Project will employ a multifaceted approach to air quality management, focusing on both the prevention and mitigation of emissions:

 

Water Sprays and Enclosures: For material handling activities, water sprays and enclosures will be strategically utilized to control dust emissions. Water sprays help increase the material moisture content, reducing the potential for dust generation, while enclosures capture and contain the dust and limit the potential dust generation from exposure to high winds.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 369

 

Control of Fugitive Dust within the West Pinal PM10 Nonattainment Area: Recognizing the specific requirements of the West Pinal PM10 nonattainment area, additional control measures will be put in place to reduce PM10. This will include enhanced dust suppression techniques using water or chemical suppressants, paving areas of high traffic, and the potential implementation of operational restrictions (e.g., reduced speed limits or pausing work during high wind events). The Project's dust control measures will be designed to comply with all applicable regulations and guidelines for this specific nonattainment area.

 

Selective Catalytic Reduction (SCR) for Generators: Non-emergency generators will be equipped with SCR systems, a technology that converts nitrogen oxides into nitrogen and water. This method is highly effective in reducing emissions associated with combustion activities.

 

Regular Monitoring and Maintenance: As required by regulations and applicable permits, continuous monitoring, scheduled inspections, regular maintenance of equipment, and documentation of such activities may be implemented to ensure that all emission controls are functioning effectively, and best management practices are being followed. Additionally, comprehensive employee training is integral to this process, equipping personnel with the necessary knowledge and skills to prevent, recognize, and mitigate avoidable emissions.

 

17.1.7Carbon Intensity

 

As part of IE’s commitment to responsible resource extraction, a comprehensive carbon impact assessment has been conducted. This assessment evaluates the expected Scope 1 and Scope 2 emissions associated with the Project over its lifetime and compares these emissions to the average carbon intensity for copper mining.

 

The global warming potentials (GWPs) used in this assessment were derived from Table A–1 to Subpart A of Part 98 of the US Code of Federal Regulations. This table provides the 100-year GWPs for various greenhouse gases (GHGs), as defined in the Intergovernmental Panel on Climate Change's (IPCC) Fourth Assessment Report (AR4). Utilizing these GWPs allows for the conversion of different GHGs into carbon dioxide equivalents (CO2e), standardizing their impact on global warming. Scope 1 emissions include all direct GHG emissions that are emitted from sources owned or controlled by the organization. In the context of the Santa Cruz Project, these emissions primarily originate from on-site fuel combustion and ore extraction processes.

 

The direct emissions will mainly come from the combustion of diesel fuel for the operation of mining equipment, excavation, material handling, and transportation of the extracted ore. Emissions will also be produced from the use of explosives in the development and mining processes.

 

The calculation of Scope 1 emissions relies on methodologies grounded in industry standards and federal guidelines. Specifically, emissions from fuel combustion were estimated using the emission factors outlined in Tables C-1 and C-2 to Subpart C of Part 98 from Title 40 of the US Code of Federal Regulations. These tables provide greenhouse gas emission factors for various types of fuel, which have been integral to estimating the emissions resulting from onsite fuel combustion processes. In addition to this, industry-standard emission factors to capture the emissions generated from other direct sources, such as the usage of explosives in mining operations, were also utilized.

 

Scope 2 emissions refer to those resulting from the generation of electricity, steam, heating, and cooling that are purchased or acquired by an organization. In the context of the Santa Cruz Project, these emissions include the electricity consumed in various activities such as the crushing and grinding of ore, as well as ancillary functions like lighting, ventilation, and office operations.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 370

 

The Santa Cruz Project, however, is forging an innovative path by planning to utilize a solar and geothermal-driven microgrid. This state-of-the-art system will enable the Project to use 70% renewably generated electricity by the third year of construction and operation, drastically reducing Scope 2 emissions. By using solar and geothermal energy, the Project not only aligns with environmental best practices but also demonstrates leadership in sustainable energy in the mining industry. The CO2 equivalent (CO2e) emissions avoided by using 70% renewable energy are shown in Figure 17-1.

 

 

 

Source: Tipple Consulting, 2023

 

Figure 17-1: Scope 1 and 2 CO2e Emissions and Avoided Emissions

 

The Scope 2 emissions for the early phase of Santa Cruz Project were derived from representative emission factors from neighboring utility providers. These representative emission factors represent the estimated emissions generated per unit of electricity consumed and are important for estimating the greenhouse gas emissions associated with the use of purchased electricity.

 

The carbon intensity of a mining Project represents the amount of CO2e emissions generated per unit of copper equivalent. A review of sustainability reports from 2021 and 2022 shows that carbon intensities in the global copper mining industry generally range from 1.5 to 6.5 t CO2e per tonne of recovered copper. The average figure stands at approximately 3.9 t CO2e per tonne of copper equivalent, encompassing both Scope 1 and 2 emissions.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 371

 

Two examples of future mining Projects with a strong emphasis on minimizing global warming impact have reported their expected carbon intensities as in Table 17-1.

 

Table 17-1: Expected Carbon Intensity of Other Mining Projects

 

Location

Carbon Intensity (Scope 1 and 2)

tonne CO2e/tonne copper equivalent

Type of Product
Argentina 0.90 – 1.07 cathode/concentrate
United States 0.12 concentrate

 

Source: Tipple Consulting, 2023

 

For the Santa Cruz Project, which will produce a combination of copper cathode and copper concentrate (approximately two thirds cathode), the anticipated average carbon intensity is 0.49 t CO2e per tonne of copper for Scope 1 and 2 emissions across both development and mining stages. Considering only the mining phase (projected to span from 2029 to 2048), the expected carbon intensity is somewhat lower, dropping to 0.45 t CO2e per tonne of copper equivalent. Further, Santa Cruz’s production of mostly copper cathode will minimize the emissions associated with processing the mined copper into a usable raw material after the sale of the copper product, in contrast to projects that focus solely on producing copper concentrate.

 

Employing a 70% renewable microgrid will allow the Santa Cruz Project to produce copper with one of the industry's lowest carbon intensities. Such intensities highlight IE 's commitment to implementing cutting-edge mining techniques, conserving energy, and utilizing renewable energy. The annual carbon intensities for 70% renewable microgrid utilization can be seen in Figure 17-2.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 372

 

 

 

Source: Tipple Consulting, 2023

 

Figure 17-2: Annual CO2e Emissions and Intensities

 

17.1.8Surface Water Monitoring

 

A baseline surface water monitoring program (Section 13.3.1) has been implemented to support permitting processes.

 

17.1.9Groundwater Monitoring

 

Area water quality data, spanning from roughly 1976 to 2000, have been reviewed to understand historic baseline conditions. Additional water quality sampling to establish a current baseline is planned for this year. Review of the historic water quality indicates that area bedrock and overburden water quality generally meet Arizona Drinking Water Standards (ADWS) with a few exceptions:

 

· Water quality in many overburden wells exceeds ADWS for gross alpha (15 picocuries per liter (pCi/L)), with concentrations as high as 50 pCi/L (uncorrected for natural uranium or radon).
· Numerous overburden wells and a few bedrock wells indicate arsenic above ADWS (0.01 milligrams per liter (mg/L) (revised proposed standard)), with concentrations approximating 0.04 to 0.05 mg/L.
· Nitrate concentrations in a number of overburden wells exceeds ADWS (44 mg/L), with concentrations as high as 55 mg/L.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 373

 

It is suspected that elevated nitrate concentrations are associated with area agricultural activities, whereas the arsenic and gross alpha exceedances are likely tied to local leaching of overburden and mineralized bedrock, as supported by the ongoing materials characterization program.

 

A groundwater monitoring program to continue collecting baseline water quality data is in development.

 

17.1.10Material Characterization

 

Material characterization studies have been initiated and are ongoing. The purpose of the mine characterization studies for the Santa Cruz Project is to develop the site environmental conceptual model and to understand both long-term material environmental behavior and environmental risks associated with various planned waste facilities. Baseline water quality studies have also been initiated to quantify pre-mining water quality within and around the planned project footprint.

 

Anticipated mine material types can be developed into three broad project classes, as follows:

 

· Mine-access material includes both overburden and bedrock material that must be mined to develop the Project. The mine-access material may potentially be stored on the surface during or after development of underground access to the mine area. Access area overburden has been extensively characterized, while access area bedrock material is currently being sampled and characterized.
· Mine area material refers to mineralized bedrock that will be excavated predominantly as ore for processing with accompanying minor waste rock. A preliminary set of mineralized bedrock samples has been characterized, with additional samples currently being characterized and more samples anticipated in future years.
· Ore processing residuals are initial bench-scale samples of mill/flotation tailings and heap leach spent ore that have been characterized. Additional tailings and spent ore samples are expected in future years as the mine and metallurgical plans evolve and as associated geochemical test programs advance. Paste tailings samples are currently being generated and will be characterized later this year.

 

Results of the various characterization programs indicate that the following broad conclusions can be drawn about expected environmental behavior of various material types that will comprise future waste facilities at Santa Cruz:

 

· All overburden (access material) material is non-acid-generating and contains considerable neutralization potential that makes it potentially useful as borrow/construction material that would not generate acidic and/or metalliferous drainage (AMD)/metal leaching (ML). Overburden material also exhibits low-level arsenic-leaching potential, which will need to be further evaluated (especially in light of potentially elevated baseline arsenic in groundwater; see previous section).
· Mine-area, mineralized bedrock is mixed potentially acid-generating and non-acid-generating. Although exact proportions are currently unknown as characterization studies continue, bedrock appears likely to be at least 50% non-acid-generating. Under acidic conditions, bedrock drainage quality is expected to be acidic pH (~3), with high concentrations of sulfate and chalcophile metals. Under alkaline conditions, bedrock indicates some potential in initial materials-characterization testing to leach low to very low concentrations of oxy-anions (e.g., antimony and selenium), natural uranium, and presumably some natural uranium decay products.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 374

 

Spent ore and tailings are both likely to be non-acid-generating based on preliminary test results. Tailings process water is expected to be alkaline, contain high sulfate and likely very high chloride (due to processing of atacamite). Spent ore process water will likely be acidic.

 

17.2Permitting and Authorizations

 

Table 17-2 lists the federal, state, and local permits required as a precursor for project construction.

 

Table 17-2: Permitting Table

 

Jurisdiction Agency Permit Needed Description Comment
Federal USEPA RCRA Resource Conservation Recovery Act – Hazardous Waste Management Waste accumulation threshold will determine when hazardous waste ID number (permit) is required
Federal USFWS MBTA Migratory Bird Treaty Act Ongoing monitoring and implementation of beneficial practices throughout life of project
Federal USEPA Class V UIC Permit Underground Injection Control Permit for tailings paste backfill Permit by rule or individual permit depending on materials characterization; UIC program expected to be under state jurisdiction by 2027
State ADEQ APP Aquifer Protection Prescriptive or Individual Permit Facility-specific permit for tailings, waste rock, and contact water ponds
State ADEQ Recycled Water
Discharge Permit
Redistribution of excess treated water to priority users For distribution of treated water for third party uses (e.g., irrigated crops).
State ADWR 45-513 – Groundwater
Withdrawal Permit
Permit to withdraw groundwater for dewatering purposes in an Active Management Area Project is within the Pinal Active Management Area
State ASMI MLRP Mined Land Reclamation Plan Closure plans developed as part of IA/PFS.
State Arizona Department
of Transportation
(ADOT)
Encroachment Permit Permit for access off Hwy 84 Traffic Impact Analysis completion required prior to permit submittal
County PCAQCD Air Quality
Control Permit
Air permit determined by quantity of emissions from stationary sources and process emissions Required for any industrial operation that has the potential to emit 5.5 pounds per day or 1 ton per year of any regulated air pollutant is required to obtain a permit from Pinal County Air Quality
County PCAQCD Dust Permit – West
Pinal Non-Attainment
Pinal County Dust Control Permit Existing permit will be amended as needed
City City of Casa
Grande
Special Flood Hazard
Area Development Permit
Any development that is proposed within a floodplain requires a permit Likely not required as facilities have been designed to avoid development within Special Flood Hazard Areas
City City of Casa
Grande
General Plan
Amendment
Major amendment to city plan Required to include mining operations and infrastructure within city limits.
City City of Casa
Grande
Major Site Plan/PAD
Plan
Major Amendment to existing PAD plan Required to accommodate industrial use/mining operations in a PAD zone

 

Source: IE, 2023

September 2023

SEC Technical Report Summary – Santa CruzPage 375

 

17.3Requirements and Plans for Waste and Tailings Disposal, Site Monitoring, and Water Management During Operations and After Mine Closure

 

Arizona Best Available Demonstrated Control Technology (BADCT) guidance defines discharge as “the addition of a pollutant from a facility either directly to an aquifer or to the land surface or to the vadose zone in such a manner that there is a reasonable probability that the pollutant will reach the aquifer.” Operators must demonstrate, within their mine plans, that such discharges will be prevented or that waste facility design effectively manages any discharge to prevent discharge from traveling beyond compliance points. BADCT stipulates the following with respect to planning for materials and water management and design of storage facilities:

 

·Applicant proposes and presents a waste characterization plan to the ADEQ. A site-specific sampling and analysis plan has been submitted to ADEQ and is continuously revised as new test material becomes available.
·Waste facilities can be designed with pre-designated engineered containment (prescriptive approach) under the assumption that facilities will be discharging and that the discharge will need to be managed.
·Waste facilities can also be designed without pre-designated containment (individual approach). This approach places the burden on the operator to demonstrate that any facility discharge will not result in downgradient impacts to aquifer, vadose zone, or land surface.
·Monitoring for compliance with facility Aquifer Protection Permit (APP) will be dictated by the conditions of the permit.

 

Based on BADCT guidance for materials and water management and the results of characterization testing performed to date, the following plans would be typical for waste and tailings disposal, site monitoring, and water management during operations and after mine closure:

 

·Metal Leaching/Acid Rock Drainage (ML/ARD) Management Plan: The ML/ARD management plan should include definitions and classification criteria for potentially metal-leaching and acid-generating materials, handling and storage plan, monitoring plan, sampling plan, and contingency plan.
·TSF Operations, Maintenance, and Surveillance (OMS) Manual: The OMS manual contents should include information such as governance (such as roles, responsibilities, and authority, communication, training) TSF description, operational requirements (such as performance objectives and Trigger Action Response Plan (TARP)), maintenance requirements, surveillance requirements (number, type, instrumentation, frequency), and linkages with the Emergency Response Plan.
·Site-Wide Water Management Plan (WMP): The site-wide WMP should include information specific to the TSF, such as TSF water balance, water management plan, protection against floodplain, flood management, seepage management, discharge management, risks of TSF runoff/seepage discharge to the receiving environment, TSF water quality and quantity mitigation measures, and trigger response plan for upset conditions.
·Site-Wide Surface Water and Groundwater Monitoring Plan: The site-wide water monitoring plan should include information such as monitoring objectives, methods, rationale for the monitoring locations and depths, water quality parameters to be monitored, sampling frequency and period, analytical testing procedures, QA/QC methods, and reporting requirements.
·Post-Closure Monitoring and Maintenance Plan: The plan should include information specific to the TSF, such as environmental monitoring requirements, annual dam safety inspections, and post-closure maintenance requirements for the TSF closure cover, closure channels, slope and toe riprap.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 376

 

17.4Post-Performance or Reclamations Bonds

 

The eventual closure and reclamation of the Santa Cruz Project will be directed and regulated under two separate and somewhat interconnected regulatory programs in Arizona. Both programs are well established in Arizona statutes and rules, are subject to licensing timeframes and the agencies are required by statute to issue approvals when credible applications are deemed administratively and technically complete.

 

·The first program, established in Chapter 5 of Title 11 of Arizona Revised Statutes (ARS) authorizes the Arizona State Mine Inspector (ASMI) to establish mined land reclamation requirements. The ASMI’s primary role in this context is the approval (or denial) of mined land reclamation plans submitted by all metalliferous and aggregate mining units and exploration operations with surface disturbances greater than five acres on private lands within the State of Arizona.
·The second program, established in ARS Title 49 Chapter 2, authorizes the Arizona Department of Environmental Quality (ADEQ) to regulate discharges (or potential discharges) to an aquifer or vadose zone in the State or requires those who operate a facility that discharges to obtain an APP. While typically considered an operational permit, the APP program also considers the eventual cessation of operations and the restoration of vadose and aquifer conditions.

 

17.4.1Arizona State Mine Inspector: Reclamation Plan

 

The ASMI reviews and analyzes reclamation plans (including reclamation cost estimates) and approves or denies proposed reclamation plans. ASMI is also responsible for the coordinated review and approval of reclamation plans with other state and federal land use agencies as well as conducting on-site inspections to determine compliance with the Mined Land Reclamation Act and Rules. Reclamation rules cannot replace or duplicate provisions of Title 49 (see Section 17.4.2) that regulate mining operations with regards to the protection of public health and the environment.

 

ASMI also has the responsibility to receive an appropriate reclamation financial assurance mechanism to guarantee that reclamation activities and related costs as defined in the Plan can be conducted by a third party in the event of an operator default. Requirements for a Mined Land Reclamation plan cannot supersede an APP closure plan for the same mining unit although financial assurance requirements shall not be redundant, inconsistent or contradictory.

 

Beginning in 1997, an owner or operator of a new exploration operation or new mining unit cannot create a surface disturbance of more than five contiguous acres until a reclamation plan and financial assurance mechanism are approved by ASMI. Generally, reclamation must be initiated within two years following the cessation of mining activity although the ASMI can generally extend the period in which to initiate reclamation if the operator can demonstrate a reasonable likelihood that the Project can resume. Once closure is initiated, the final reclamation measures shall be performed as stated in the approved reclamation plan (as amended) unless the mining operation is reactivated.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 377

 

17.4.2Arizona Department Of Environmental Quality: Aquifer Protection Permit

 

The ADEQ shall consider any application for an individual permit if the application furnishes a design of the discharging facilities sufficient to document those elements of the facility affecting discharge, a description of how the facilities will be operated, a demonstration of existing and proposed pollutant control measures, a hydrogeologic study defining and characterizing the pollution management area and the discharge impact area, a background aquifer analysis, a characterization of the pollutants discharged by the facility and a closure strategy.

 

Discharging facilities must be designed, constructed, and operated to ensure the greatest degree of discharge reduction achievable through the application of Best Available Demonstrated Control Technologies (BADCT) including, where practicable, technologies that result in no discharge of pollutants. Once permitted, facilities must be constructed and operated in a manner that discharged pollutants cannot cause or contribute to a violation of aquifer water quality standards at the applicable point of compliance for the facility.

 

Regarding closure, ADEQ may consider a closure strategy and cost estimate rather than a detailed closure plan. Like the ASMI-required bonding requirements, the closure cost estimate shall be based on the costs for a third party to implement the closure strategy or plan (including conducting post-closure monitoring and maintenance) unless the surety mechanism is a self-assurance or a corporate guarantee.

 

Unless specifically exempted or designed, constructed and operated so that there will be no migration of pollutants directly to the aquifer or to the vadose zone, mine facilities such as surface impoundments, waste rock or overburden disposal units, tailings impoundments, and leaching facilities are generally considered to be discharging facilities and must be operated pursuant to either an individual APP or general permit.

 

17.5Status of Permit Applications

 

17.5.1Arizona State Mine Inspector: Reclamation Plan

 

Although exploration activities previously conducted by IE are subject to an exploration level reclamation plan, IE must submit and obtain approval for a Mined Land Reclamation Plan as established in Chapter 5 of Title 11 in ARS (Plan) prior to initiating actual mining operations. Unreclaimed disturbances from prior or ongoing exploration activities can simply be incorporated into the disturbance footprint of the operating Plan or reclaimed under the existing exploration level plan.

 

Future mining operations that are the subject of this document will require a Plan. The Plan should be developed once IE has completed at least 75% design drawings for all surface disturbances and structures at the site subject to the Plan. The closure of discharging facilities as defined in APP rules (such as tailings impoundments, process ponds and waste rock stockpiles) must be included within the approved Plan even though the detailed plans and approach to closing these facilities are documented in the APP and approved by the ADEQ. Consequently, the present project design status prevents any substantive APP activities at this time.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 378

 

17.5.2Arizona Department of Environmental Quality: Aquifer Protection Permit

 

Future mining operations that are the subject of this document will require an approved APP as established in Chapter 2, Title 49 of ARS. Although the ADEQ does allow pre-application meetings and certain preliminary permitting activities to be conducted under 30% design drawings, the APP can only be approved once IE has submitted at least 75% design drawings for all surface disturbances and structures at the site subject to the permit. Consequently, the Project’s design status prevents any substantive APP activities at this time.

 

The closure of discharging facilities as defined in APP rules (such as tailings impoundments, process ponds and waste rock stockpiles) must be included within the approved Plan even though the detailed plans and approach to closing these facilities are documented in the APP and approved by the ADEQ. Costs for closing these facilities must be addressed in the APP application package although the ARS expressly prohibits duplicative bonding requirements.

 

17.5.3Known Requirements to Post Performance or Reclamation Bonds

 

Aside from the pending reclamation plan for exploration activities at the site, IE has no current obligations to tender post mining performance or reclamation bonds for the Project. Once the facility achieves the level of design necessary to advance to mine development and operation, IE will need to submit and gain approval of an ADEQ-approved APP and an ASMI-approved Plan. The closure approach and related closure cost estimates must be submitted following approval and before facility construction and operation.

 

Although a Plan has not yet been developed for the Santa Cruz Project, a preliminary closure cost estimate has been developed. Based on the conceptual design plan described in this document, the estimated closure costs for the Santa Cruz Project are US$27 million.

 

17.6Local Individuals and Groups

 

In alignment with IE’s community engagement and partnership standards, the Santa Cruz Project is being developed with a well-defined strategy to establish and uphold the support of the surrounding communities. At present, the Project has initiated early-stage community outreach and is actively assessing potential partnerships within the local community.

 

The Santa Cruz Project recognizes the need to keep stakeholders well informed about the Project’s potential economic and community benefits and IE’s commitment to safety and the environment. To achieve this, the Santa Cruz team has initiated meetings with various key groups, including local community leaders, neighboring communities, and regional- and state-level representatives. Consistent communication will continue through the development of a community working group. This group will provide a forum for stakeholder involvement and will allow interested community members to engage with the team as the Project progresses.

 

Furthermore, the Project team recognizes the potential impacts of noise and dust from the proposed activities and is taking proactive steps to address them. During the facility design phase, engineering controls will be incorporated to minimize noise and dust disturbances and maintain harmony with the surrounding community. IE plans to create an all-encompassing environmental, social, and governance framework designed to effectively address any community concerns and ensure that the Santa Cruz Project operates in a socially responsible manner.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 379

 

17.7Mine Closure

 

As discussed above, the present level of design considered in this document is insufficient to generate specific closure or reclamation plans as required by ASMI and ADEQ for facility construction and operation. It is possible, based on the conceptual mine plans and facility layout discussed herein, to contemplate certain closure and reclamation obligations and approaches for the following site elements:

 

17.7.1Waste and Development Rock Closure and Reclamation Approach

 

Generally, the APP permitting process will determine the geochemical reactivity of those materials. This geochemical characterization informs the need as well as means and methods for capping and covering these materials to prevent stormwater contamination and seepage that could continue to impact the vadose zone or underlying aquifer. If characterization of these materials suggest that the “wastes” are geochemically inert, then isolation measures needed to prevent water-rock interactions are not necessary. Sufficient geochemical modeling has not been completed to assess if these materials will be inert.

 

The ASMI will not address or review the adequacy of closure or capping systems in the Plan. However, ASMI will require a geotechnical analysis to demonstrate that the stockpiles are safe and stable under static and pseudo-static conditions.

 

17.7.2Tailings Closure and Reclamation Approach

 

Again, the APP permitting process will determine the geochemical reactivity of tailings materials. This geochemical characterization informs the need as well as means and methods for capping and covering these materials to prevent stormwater contamination and seepage that could continue to impact the vadose zone or underlying aquifer. If characterization of these materials suggest that the “wastes” are geochemically inert, then isolation measures needed to prevent water-rock interactions are not necessary to protect groundwater but still may be required to meet stability requirements below. Sufficient geochemical modeling has not been completed to assess if these materials will be inert.

 

As with waste and development rock, the ASMI will not address or review the adequacy of closure or capping systems in the Plan. However, ASMI will require a geotechnical analysis by the Engineer of Record to demonstrate that the tailings impoundment is safe and stable under static and pseudo-static conditions and that the impoundment is practically drained and dewatered.

 

17.7.3General Grading and Revegetation Approach

 

There are typically no grading or revegetation requirements included in an approved APP. The ASMI-approved reclamation plan will address all grading, site recontouring and revegetation requirements. To the extent practicable, the Plan will require the grading and recontouring to restore surface topography and drainage patterns. Roads and other compacted areas must be ripped and scarified to encourage the establishment and success of revegetation efforts. Material stockpiles should be graded and contoured to reduce erosive effects of rainfall events, enhance long-term stability, and reduce ponding and infiltration.

 

Inert materials (such as broken concrete and asphalt) generated from facility decommissioning activities can be buried on-site without a permit provided those materials are categorically inert or are determined to be inert via approved testing protocols.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 380

 

17.7.4Mill and Process Area Closure and Reclamation Approach

 

The approved closure approach or plan will require that all process liquid and solid residues will be removed from the mill and leaching circuits. These facilities can be rinsed with the resultant liquids and sediments discharged to an onsite permitted process pond. Liquids can be allowed to evaporate but remaining sludges and sediments must be characterized and profiled for offsite transportation and disposal in order to achieve “Clean Closure” under APP rules.

 

All solid wastes, laboratory and assay chemicals, and general household wastes must be removed from the structures prior to structural decommissioning. These materials must be recycled or characterized and profiled for appropriate offsite transportation and disposal.

 

17.7.5Process and Chemical Ponds Closure and Reclamation Approach

 

The approved ADEQ APP will require that process ponds are eventually drained and cleaned to remove remaining sludges and sediments. Liquids can be allowed to evaporate but remaining sludges and sediments must be characterized and profiled for offsite transportation and disposal in accordance with APP rules. Once drained and cleaned, pond liners can be perforated and buried onsite or transported from the property as solid waste.

 

The ASMI-approved Plan will not address pond closure per se, but any remaining surface depressions must be regraded to achieve the safe and stable requirements of the reclamation rules. These efforts would typically be addressed in the general grading and reclamation approach.

 

17.7.6Structural Decommissioning Approach

 

The ADEQ-approved APP closure plan will not specifically address the decommissioning of surface structures aside from the requirement that any process liquids or residues are not discharged in an uncontrolled manner.

 

The ASMI approved Plan will address structural decommissioning efforts to the extent that closure cost estimates include the demolition and removal of all surface facilities not specifically excluded from the Plan. The ASMI does allow the retention of specific structures such as water wells, utility infrastructure or buildings where these structures can enhance the productive post-mining use of the property. These facilities must be specifically identified in the approved Plan.

 

Again, any remaining surface depressions must be regraded to achieve the safe and stable requirements of the reclamation rules. Inert materials (such as broken concrete and asphalt) generated from facility decommissioning activities can be buried on-site without permit provided those materials are categorically inert or are determined to be inert via approved testing protocols. These efforts would typically be addressed in the general grading and reclamation approach.

 

17.7.7Underground Operations Closure Approach

 

The ADEQ approved APP will require that all fuels, chemicals, wastes, and explosives used in the development and operation of underground operations are removed and disposed to prevent potential impacts to mine flooding. Fluid-containing equipment and machinery left underground must be drained and any hydrocarbon-impacted “soils” occurring as a result of maintenance activities must be removed and properly disposed.

 

Geochemical and hydrologic modeling required in the APP should predict the resulting rock-water and water-water interactions occurring as a consequence of mine flooding. If these interactions have the potential to impact the aquifer above a specific alert level as measured at the approved points of compliance, then actions prescribed in the APP must be implemented. Sufficient geochemical and hydrologic modeling has not been completed to assess this possibility.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 381

 

The ASMI-approved Plan will require that the mine portal and any associated escape or ventilation shafts be appropriately closed and sealed to establish long term safety and stability.

 

17.7.8Aquifer Restoration and Post Closure Monitoring Approach

 

Post closure monitoring related to the APP may include confirmation sampling related to the clean closure of any process areas or individual discharging facilities and the long-term monitoring of groundwater conditions across the site following closure. IE will be required to maintain, survey and routinely sample the monitoring well network including the point of compliance wells until such time as groundwater conditions have stabilized and no constituents of interest are at risk of exceeding an alert level at any of the points of compliance. It is estimated that post closure monitoring will be required for at least ten (10) years depending on the speed at which the aquifer rebounds from dewatering and aquifer conditions stabilize.

 

The ASMI-approved Plan will require site monitoring to document the effectiveness of grading and reclamation efforts including the success of revegetation. The Plan will require the maintenance of fencing and other site barriers, the removal of trash or wildcat dumping and the repair of any erosion damage to capped and covered structures.

 

Once groundwater conditions have stabilized and ADEQ grants closure, IE must abandon all monitoring and point of compliance wells in accordance with the APP. Following revegetation success after at least four (4) growing seasons, the ASMI can determine that the site has been successfully reclaimed and return all or part of the reclamation bond established with the ASMI.

 

Certain facilities (like a large tailings impoundment, for instance) may not achieve clean closure and would thus require long-term monitoring and Engineer of Record involvement. Depending on how quickly these facilities dewater and stabilize, certain types of legacy facilities may not ever be released and declared closed. However, characterization and design efforts at the site have not progressed sufficiently to determine the long-term closure requirements of any facilities.

 

17.8QP Opinion

 

H&A has opined on the Federal and State permitting and closure standards that will impact the closure and reclamation of the Project. This assessment is based on the current regulatory requirements, referenced costing assumptions and sources, and the current level of design and Project planning provided by IE.

 

The LCG is of the opinion that the environmental assessments summarized herein, including geochemical materials characterization and baseline water quality studies, meet industry standards, reflect current regulatory requirements and are appropriate for the current level of design and project planning provided by IE.

 

It is the opinion of Tetra Tech, accountable for environmental assessments, permits, plans, as well as negotiations and agreements with local entities, asserts that given current regulatory conditions and IE 's present project design and planning stage, the recognized plans and permitting requirements are adequate for an initial assessment.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 382

 

18Capital and Operating Costs

 

Estimation of capital and operating costs is essential to the evaluation of the economic viability of a prospective project. These factors, combined with revenue and other expense projections, form the basis for the financial analysis presented in Section 19. Capital (CAPEX) and operating (OPEX) costs for the Santa Cruz Project were estimated on the basis of an IA mine plan, plant design, estimates of materials and labor based on that design, analysis of the process flowsheet and predicted consumption of power and supplies, budgetary quotes for major equipment, labor requirements, and estimates from consultants and potential suppliers to the Project.

 

Capital and operating costs are incurred and reported in US dollars and are estimated at an IA level with an accuracy +/-50%.

 

18.1Capital Cost Estimates

 

The Project is currently in the exploration stage. The Santa Cruz Project consists of an underground copper mine that has a conceptual mine schedule containing 105.2 Mt of exotic, oxide, supergene (secondary) sulfide mineralized material. The Santa Cruz process plant is designed to handle 5.5 Mt/y over a period of 20 years. The daily throughput of the process plant is 15,000 tonnes per day (t/d) of mineralized material.

 

18.1.1Mining Capital Cost

 

The mining capital cost estimate is based on first principal cost model build-up and budgetary quotes. The total capital estimate is US$960.48 million, this includes an estimated capital of US$878.08 million plus 9.4% contingency of US$82.40 million.

 

The construction capital is supported by the following items:

 

·Schedule of mine equipment purchases
·Budgetary estimates for portal, decline and railveyor development
·Budgetary estimates for paste backfill plant and distribution system
·Budgetary estimates for mine dewatering
·Budgetary estimates for vertical shaft development
·Cost model estimate to install underground facilities like shops, ventilation systems, refuge chambers, pumping systems, paste distribution, fuel distribution, ancillary equipment, etc.

 

Development costs are derived from the mining schedule prepared by SRK. The prepared mining schedule includes meters of development during pre-production, this schedule of meters was combined with unit costs, based on site specific data, to estimate the cost of this development operation. The breakdown of the estimated initial capital costs is shown in Table 18-1.

 

Table 18-1: Estimated Mining Initial Capital Cost

 

Item US$ (million)
Capital Development Cost 166.99
Equipment Purchase and Rebuilds 241.24
Mine Services 17.96
Owner Cost 32.75
Contingency 38.76
Total 497.7

 

Source: SRK, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 383

 

The Santa Cruz Project will require sustaining capital to maintain the equipment and all supporting infrastructure necessary to continue operations until the end of its projected production schedule. The sustaining capital cost estimate developed includes the costs associated with the engineering, procurement, construction and commissioning. The cost estimate is based on designs and cost models prepared by SRK with site specific inputs from IE. The estimate indicates that the Project requires sustaining capital of US$462.78 million to support the projected production schedule through the LoM. The sustaining capital cost is shown in Table 18-2.

 

Table 18-2: Estimated Mining Sustaining Capital Cost

 

Item US$ (million)
Capital Development Cost 60.79
Equipment Purchase and Rebuilds 322.64
Mine Services 0.00
Owner Cost 35.71
Contingency 43.63
Total 462.78

 

Source: SRK, 2023

 

Table 18-3 shows the mining capital spend schedule.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 384

 

Table 18-3: Mining Capital Spend Schedule

 

   

Period

(Yrs)

2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037
    Period -3 -2 -1 1 2 3 4 5 6 7 8 9
    Total

Initial

CAPEX

Initial

CAPEX

Initial

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Capital Development Cost

M$ 227.78 0.00 53.27 113.72 11.00 0.67 1.45 1.35 26.58 3.56 4.41 1.36 5.03

Equipment Purchase

M$ 563.89 74.50 52.33 114.41 19.23 19.95 21.93 23.77 21.45 20.89 15.42 10.11 40.99
Services M$ 17.96 0.49 3.23 14.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Owner Cost M$ 68.46 0.25 10.30 22.20 3.55 1.33 1.50 1.52 10.53 2.56 2.30 0.82 4.23
Subtotal M$ 878.08 75.24 119.13 264.57 33.78 21.95 24.88 26.64 58.57 27.01 22.13 12.29 50.24

Contingency (9.4%)

M$ 82.40 7.72 9.96 21.09 4.41 1.91 2.54 2.72 5.38 2.44 2.47 1.50 5.70

Total Mining CAPEX with Contingency

M$ 960.48 82.96 129.09 285.66 38.20 23.86 27.42 29.36 63.94 29.45 24.60 13.79 55.94

 

   

Period

(Yrs)

2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048
    Period 10 11 12 13 14 15 16 17 18 19 20
    Total

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Sustaining

CAPEX

Capital Development Cost

M$ 227.78 2.10 0.85 0.95 0.19 0.89 0.41 0.00 0.00 0.00 0.00 0.00

Equipment Purchase

M$ 570.77 28.58 8.64 6.37 16.81 23.76 14.33 10.57 7.97 11.88 0.00 0.00
Services M$ 17.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Owner Cost M$ 68.46 2.26 0.81 0.79 0.97 1.42 0.95 0.17 0.00 0.00 0.00 0.00
Subtotal M$ 884.97 32.94 10.29 8.11 17.97 26.07 15.69 10.74 7.97 11.88 0.00 0.00

Contingency (9.4%)

M$ 83.09 3.00 0.98 0.66 1.62 2.55 1.38 1.40 1.20 1.78 0.00 0.00

Total Mining CAPEX with Contingency

M$ 968.05 35.94 11.27 8.76 19.59 28.62 17.07 12.14 9.17 13.66 0.00 0.00

 

Source: SRK, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 385

 

18.1.2Process Capital Cost

 

Capital costs for the Santa Cruz process plant were primarily estimated using historical equipment quotes from recent M3 projects, material take-offs (MTOs) for earthwork, concrete, steel, and some overland piping, internet quotes for plant mobile equipment, and estimates based on experience with similar projects of this type. The capital cost estimate for the plant is shown in Table 18-4. Some of the costs and quantity estimates used by M3 were supplied by other consultants.

 

Table 18-4 summarizes the initial capital costs for the Project. The process capital categories include:

 

Direct Costs

 

·Civil Earthworks, Concrete, Steelwork by MTO (comparison with similar facilities from other constructed projects

·Factored Estimates for Piping, Electrical, and Instrumentation & Controls based on Plant Equipment priced from similar projects

·Power Supply Equipment & Infrastructure

·Fresh and Process Water Equipment, Ponds & Infrastructure

·Ancillary Facilities (Buildings)

·Freight

 

Indirect Costs

 

·Construction indirect costs: mobilization, temporary facilities, temporary, power,

·Engineering, Procurement and Construction Management (EPCM) costs

·Vendor Support & Spares

·Contingency

 

Owners Costs

 

·Owners Management Team Construction

·Plant Pre-Production

·Security

·Project Insurance

·Recruiting & Training

·Warehouse Spares

·Permits & Environmental

 

Note that Owners costs includes an allocation of US$30 million plus first fills plus plant mobile equipment.

 

Table 18-4: Estimated Initial Plant Capital Cost Summary

 

Description Hours

Total Cost

(US$ million)

% of Total Capital Cost
Directs 1,290,000 345.4 61.3
Indirects   72.0 12.8
Contingency   111.3 19.7
Owner's Costs   35.0 6.2
Escalation   - 0.0
Total Capital Cost (TCC)   563.7 100.0

 

Source: M3, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 386

 

The initial capital cost for the Santa Cruz plant and infrastructure facilities totals US$563.7 million. This capital cost includes all process areas facilities in the Santa Cruz plant proper starting with the primary crushing, and continuing through grinding, agitated leaching, solvent extraction and electrowinning, leach residue neutralization, leach residue grinding, rougher flotation, concentrate regrinding, cleaner flotation, concentrate dewatering and tailing dewatering and pumping to the TSF. The initial capex includes the ventilation chiller for the underground mine, the main plant substation, fresh and process water ponds, and the batch plant, and the surface ancillary buildings.

 

The initial plant capex excludes the mining capex, mining pre-production, the paste backfill plant, the mine ventilation fans, and initial TSF costs. These costs are captured elsewhere in the financial build-up.

 

The expenditures percentages by development year are:

 

·Year -3: 10%

·Year -2: 35%

·Year -1: 50%

·Year 1: 5%

 

Table 18-5 shows the annual expenditure schedule for the process capital.

 

Table 18-5: Process Plant Capital Cost Expenditure Schedule (US$ Million)

 

Item

Tot.Cost

($M)

Yr-3

($M)

Yr-2

($M)

Yr-1

($M)

Yr1

($M)

Project Management 10.0 3.4 3.4 3.3 0
Engineering 25.0 11.2 11.2 2.7 0
Dewatering 10.0 3.8 6.3 0.0 0
Long Lead Procurement 80.0 33.8 37.4 8.9 0
Balance of Plant Procurement 49.7 0.0 19.9 29.8 0
Freight 16.0 0.0 5.8 10.2 0
Construction 250.0 4.2 81.3 149.8 14.6
Vendor Support 6.0 0.0 0.0 5.5 0.5
First Fills 5.0 0.0 0.0 5.0 0.0
Contingency 112.0 0.0 32.0 66.7 13.1
Total 563.7 56.4 197.3 281.9 28.2

 

Source: M3, 2023

 

No sustaining capital costs have been included for the Santa Cruz process plant. The mine life is 20 years and the capital equipment will be designed to last for the duration of the Project. Preventative maintenance and periodic rebuilds/relining is captured in the annual maintenance cost estimation. The only place where sustaining capital is expected is in the TSF for annual embankment enlargement which was estimated separately.

 

18.1.3Tailings Capital Costs

 

The capital components that make-up the tailings management system consist of the TSF embankment, the tailings impoundment and liner, water reclaim system, TSF under-liner drains, TSF surface water diversions, and the civil work that is required to route the tailings and reclaim water lines between the process plant and the TSF. MTO’s for the TSF water diversions, embankment and impoundment construction, liner, over-liner drain, and under-liner drain were estimated by KCB. The water reclaim system consists of seepage ponds sump pumps, pipeline, and process water storage tank, estimated by M3.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 387

 

KCB provided a year-by-year Bill of Quantities for the conceptual Santa Cruz design. Current civil rates were applied to KCB’s quantities. The largest cost center for the TSF comes from the yearly embankment construction from the borrow-to-fill rate for the TSF embankment, which is expanded every year. In this case, IE solicited a budgetary proposal from Turner Mining Group (TMG), a local constructor, to provide material for the TSF embankment. TMG provided a price of US$6.36 per yd3 which converts to US$8.42/m3.

 

Other unit rates for geomembrane lining, drain piping, overliner and underliner, and trenching align with 2023 civil and piping rates for southern Arizona. Table 18-6 and Table 18-7 show a summary of the TSF initial and sustaining capital costs over the LoM. Indirects and contingency have only been applied to the initial capex.

 

Table 18-6: Estimated TSF Initial Capital Cost

 

Item US$ Million
Directs 48.8
Indirects 11.3
Contingency 15.0
Total 75.1

 

Source: M3, 2023

 

Table 18-7: Estimated TSF Sustaining Capital Cost

 

Item US$ Million
Sustaining 382.2
Closure 104.6
Total 486.8

 

Source: M3, 2023

 

Table 18-8 shows the annual expenditure schedule for the TSF.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 388

 

Table 18-8: TSF Capital Cost Expenditure Schedule

 

 

Directs

(US$ million)

Indirects

(US$ million)

Contingency

(US$ million)

Sustaining Capex

(US$ million)

Closure

(US$ million)

Annual

Total

Year-1 48.8 11.3 15.0 - - 75.1
Year1       19.0   19
Year2       19.0   19
Year3       19.0   19
Year4       17.9   17.85
Year5       16.2   16.17
Year6       16.2   16.17
Year7       16.2   16.17
Year8       16.2   16.17
Year9       16.2   16.17
Year10       16.2   16.17
Year11       17.8   17.8
Year12       17.8   17.8
Year13       17.8   17.8
Year14       17.8   17.8
Year15       17.8   17.8
Year16       17.8   17.8
Year17       17.8   17.8
Year18       17.8   17.8
Year19       17.8   17.8
Year20       17.8   17.8
Year21       16.2   16.17
Year22       16.2   16.17
Year23           0
Year24         40.0 40
Year25         64.6 64.6
Total 48.8 11.3 15.0 382.2 104.6 561.91

 

Source: M3, 2023

 

18.1.4Basis for Cost Estimates

 

Mining Capital Costs

 

The mining equipment requirements were based on the mine production schedule, and estimates for scheduled production time, mechanical availabilities, equipment utilization, and operating efficiencies.

 

Estimates of annual operating hours for each type of equipment were made, and equipment units were utilized in the mining operations until a unit reached its planned equipment life, after which a replacement unit was added to the fleet, if necessary. Major mining equipment rebuild (overhaul) costs were included in the mining equipment capital cost estimates.

 

The mining equipment capital cost estimate was based on the following:

 

·All replacement mining units are based on new equipment purchases.

·Freight cost and spare parts for mining equipment was generally estimated to be between 3% and 5%.

·Mining equipment rebuilds were included at appropriate intervals in the mining capital costs.

·Contingency was included in the mining equipment capital cost estimate. Contingency range from 5%, when there are budgetary quotes, to 15% from first principal build-ups.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 389

 

Process Capital Costs

 

The key elements of the capital cost estimation methodology are summarized below:

 

·Equipment capacities, duty specification and quantities were determined from flowsheets, process design criteria, material mass balance, and engineering calculations for service and duty.

·EPCM rates were estimated based on M3’s updated rate of 16.8% of direct constructed cost. That cost is broken down into seven components: management/accounting, engineering, project services, project control, construction management, EPCM fee, and temporary facilities.

 

Tailings Capital Costs

 

The key elements of the capital cost estimation methodology are summarized below:

 

·MTOs by year were provided by KCB

·Earthworks, lining, and piping rates from standard schedule

·Borrow-to-fill provided by budgetary quotation from TMG

 

18.2Operating Cost Estimates

 

For mining, the operating costs were estimated by SRK from a first principles basis.

 

Process operating costs were estimated based on the best current pricing for labor, power, reagents, and consumables. Maintenance, spares and services were estimated as factors of capital equipment. As with capital costs, operating costs are captured in US dollars and are estimated at an IA level withing an accuracy bound of +/- 50%.

 

18.2.1Mine Operating Cost

 

SRK estimated the required mining equipment fleet, required production operating hours, and manpower to arrive at an estimate of the mining costs that the mining operations would incur. The mining costs were developed from first principles and compared to recent actual costs. The mining operating costs are presented in the following categories:

 

·Drilling

·Blasting

·Loading

·Hauling

·Backfill

·Support Equipment Operations

·Miscellaneous Operations (various support operations, etc.)

·Mine Engineering (mine technical personnel and technical consulting)

·Mine Administration and Supervision (mine and maintenance supervision, etc.)

·Freight (for equipment supplies and parts, excluding freight for fuel)

·Contingency

 

A maintenance cost was allocated to each category that required equipment maintenance. A US$2/t rehandling cost is used for rehandling the surface ore stockpile to the mill in early mine life. Additionally, the operating expense, totaling US$9.78 million, associated with handling the development ore in construction year 3 is capitalized. A summary of the LoM unit mine operating costs is presented in Table 18-9.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 390

 

Table 18-9: Mining Operating Costs

 

LoM Tonnes Mined (000)  107,134*
Category US$000 US$/t Mined
Operating Development 481,021 4.49
Production (Drilling, Blasting, Loading, Hauling and Backfill) 1,139,843 10.64
Other mining costs (Services, Maintenance, Rehab and Definition Drilling) 458,564 4.28
Mine engineering and administration 592,085 5.54
Contingency (9.5%) 254,664 2.39
Total 2,926,177 27.33

 

* LoM Tonnes mined includes 100,244 kt of process material, 4,942 kt of marginal material and 1,948 kt of waste.

 

Source: SRK, 2023

 

Table 18-10 shows the mine operating expenditure schedule.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 391

 

Table 18-10: Mine Operating Expenditure Schedule

 

    Period(Yrs) 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037
    Period -3 -2 -1 1 2 3 4 5 6 7 8 9

Operating Development

k$ 481,021   - 8,929 30,263 33,609 31,959 31,241 33,788 28,861 27,159 24,032 26,995

Production (Drilling, Blasting, Loading, Hauling and Backfill)

k$ 1,139,843   - - 36,941 63,673 62,392 62,735 63,402 63,095 64,187 61,561 62,172

Other mining costs (Services, Maintenance, Rehab and Definition Drilling)

k$ 458,564   - - 17,744 19,482 20,041 20,105 21,527 22,126 22,190 22,190 24,996

Mine engineering and administration

k$ 592,085   - - 25,375 28,320 31,552 32,432 33,133 33,133 33,133 33,133 33,133
Contingency (9.5%) k$ 254,664   - 851 10,517 13,830 13,912 13,966 14,475 14,033 13,981 13,433 14,041
Total k$ 2,926,177   - 9,822 121,161 159,165 160,066 160,536 166,580 161,281 160,564 154,224 161,398

 

    Period(Yrs) 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048  
    Period 10 11 12 13 14 15 16 17 18 19 20  

Operating Development

k$ - 8,929 30,263 33,609 31,959 31,241 33,788 28,861 27,159 24,032 26,995 -  

Production (Drilling, Blasting, Loading, Hauling and Backfill)

k$ - - 36,941 63,673 62,392 62,735 63,402 63,095 64,187 61,561 62,172 -  

Other mining costs (Services, Maintenance, Rehab and Definition Drilling)

k$ - - 17,744 19,482 20,041 20,105 21,527 22,126 22,190 22,190 24,996 -  

Mine engineering and administration

k$ - - 25,375 28,320 31,552 32,432 33,133 33,133 33,133 33,133 33,133 -  
Contingency (9.5%) k$ - 851 10,517 13,830 13,912 13,966 14,475 14,033 13,981 13,433 14,041 -  
Total k$ - 9,822 121,161 159,165 160,066 160,536 166,580 161,281 160,564 154,224 161,398 -  

 

Source: SRK, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 392

 

The annual mining cost and unit costs are presented in Figure 18-1.

 

 

Source: SRK, 2023

 

Figure 18-1: Mining Unit Cost Profile

 

The basis for the mining operating cost estimates includes the following parameters:

 

Diesel fuel cost of US$3.17/US gallon (delivered to site)
Power cost of US$0.11/kWh, which is comprised of 70% Renewable power at US$0.121/kWh and 30% Grid power at US$0.071/kWh
Average insitu density for waste of 2.5 t/m3
Average insitu density for ore of 2.7 t/m3
Estimated average tire lives of:
oWheel loaders: 2,000 operating hours
oHaul trucks: 2,500 operating hours
oOther major mining equipment: 1,000 – 2,000 operating hours
3% freight cost on mining operating and maintenance supplies
9.5% contingency is included in the mining operating cost estimates

 

Employee wages, bonus and wage burdens (20%) were based on information provided by IE. The costs for maintenance supplies and materials were based on estimates presented in the current InfoMine mining cost service publications. Other mining related costs were provided by IE.

 

Included in the mine operating cost estimate are the following:

 

Labor (supervision, operations, maintenance, administrative, etc.)
Maintenance (tools, spare parts)
Consumables
Lubricants and fuels
Electricity
Other recurring expenses needed for mine operations

 

September 2023

SEC Technical Report Summary – Santa CruzPage 393

 

SRK performed a benchmarking exercise comparing the mining cost build up to other mining operations using the longhole stoping method. Figure 18-2 shows the benchmarking results and Santa Cruz mining cost is roughly in-line with other operations of this size, however, SRK notes that there ae not too many underground operations of this size and the ones shown here are from Latin America which has quite different labor rates. Additional study work is recommended to further detail costs for the specific mining method presented here to confirm or modify the estimated costs.

 

 

Source: SRK, 2023

 

Figure 18-2: Longhole Stoping Mining Cost Benchmarking

 

18.2.2Processing Operating Cost

 

The process plant operating costs are summarized by the categories of labor, electric power, liners (wear steel), grinding media, reagents, maintenance parts, and supplies and services, as presented in Table 18-11.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 394

 

Table 18-11: Process Plant OPEX Summary by Category

 

Operating & Maintenance

Average Annual Cost

(US$000)

$/t processed

(US$)

LoM Operating Cost

(US$000)

%
Labor 11,119 2.11 222,383 16.8%
Electrical Power 23,297 4.43 465,939 35.1%
Reagents 18,447 3.51 368,947 27.8%

Wear Parts

(Liners & grinding media)

6,811 1.30 136,221 10.3%
Maintenance Parts 5,993 1.14 119,865 9.0%
Supplies and Services 628 0.12 12,557 0.9%
Total (US$) $66,296 $12.61 $1,325,912 100.0%

 

Source: M3, 2023

 

TSF operating costs are included in the processing operating costs and include labor, power, reagents, and maintenance.

 

Table 18-12 shows the process operating expenditure schedule.

 

Table 18-12: Process Operating Expenditure Schedule

 

Operating Year Total Ore Processed (Mt) Plant Opex
  Mt US$ Million US$/Mt
1 4.84 57.77 11.93
2 5.71 71.59 12.54
3 5.67 71.06 12.53
4 5.80 72.60 12.53
5 5.95 73.79 12.41
6 5.83 72.91 12.50
7 5.91 73.55 12.45
8 5.71 71.81 12.58
9 5.81 72.28 12.45
10 5.73 70.60 12.31
11 5.66 71.52 12.65
12 5.67 69.91 12.33
13 5.56 69.99 12.59
14 5.62 69.99 12.45
15 5.61 70.19 12.51
16 5.58 69.92 12.53
17 5.55 70.91 12.78
18 5.52 70.28 12.73
19 3.10 40.78 13.14
20 0.37 14.44 39.23
Total 105.19 $1,325.91 $12.61

 

Source: M3, 2023

 

18.2.3General and Administrative Operating Costs

 

G&A costs include management, accounting, human resources, environmental and safety compliance, laboratory, community relations, communications, insurance, legal, training, and other costs not associated with either mining or processing. The LoM G&A cost estimated for the Project are presented in Table 18-3.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 395

 

Table 18-13: Life-of Mine General and Administration Cost Detail

 

 

Average Annual Cost

(US$000)

$/t Processed

(US$)

LoM Operating Cost

(US$000)

Labor (G&A + laboratory) 8,192 1.56 163,843
Accounting (excluding labor) 152 0.03 3,036
Safety & Environmental (excluding labor) 121 0.02 2,429
Human Resources (excluding labor) 59 0.01 1,178
Security (excluding labor) 152 0.03 3,036
Office Operating Supplies and Postage 59 0.01 1,178
Maintenance Supplies 179 0.03 3,588
Propane 78 0.01 1,564
Communications 117 0.02 2,346
Small Vehicles 117 0.02 2,346
Real Property Tax 1,564 0.30 31,277
Legal & Audit 276 0.05 5,520
Consultants 586 0.11 11,729
Janitorial Services 96 0.02 1,913
Insurances 920 0.17 18,399
Subs, Dues, Public Relations, and Donations 55 0.01 1,104
Travel, Lodging, and Meals 184 0.03 3,680
Recruiting/Relocation 184 0.03 3,680
Personal Protective Equipments 83 0.02 1,656
Medical/First-aid 126 0.02 2,528
License Fees 120 0.02 2,392
Laboratory (excluding labor) 396 0.08 7,923
Total $13,817 $2.63 $276,341

 

Source: M3, 2023

 

Table 18-14 shows the G&A expenditure schedule.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 396

 

Table 18-14: G&A Expenditure Schedule

 

Operating Year Total Ore
Processed
G&A Opex Lab Opex Total G&A
  Mt US$ Million US$/t US$ Million US$/t US$ Million US$/t
1 4.84 12.54 2.59 1.30 0.27 13.84 2.86
2 5.71 13.59 2.38 1.30 0.23 14.90 2.61
3 5.67 13.59 2.40 1.30 0.23 14.90 2.63
4 5.80 13.59 2.35 1.30 0.23 14.90 2.57
5 5.95 13.59 2.29 1.30 0.22 14.90 2.51
6 5.83 13.59 2.33 1.30 0.22 14.90 2.55
7 5.91 13.59 2.30 1.30 0.22 14.90 2.52
8 5.71 13.59 2.38 1.30 0.23 14.90 2.61
9 5.81 13.59 2.34 1.30 0.22 14.90 2.57
10 5.73 13.59 2.37 1.30 0.23 14.90 2.60
11 5.66 13.59 2.40 1.30 0.23 14.90 2.63
12 5.67 13.59 2.40 1.30 0.23 14.90 2.63
13 5.56 13.59 2.45 1.30 0.23 14.90 2.68
14 5.62 13.59 2.42 1.30 0.23 14.90 2.65
15 5.61 13.59 2.42 1.30 0.23 14.90 2.66
16 5.58 13.59 2.44 1.30 0.23 14.90 2.67
17 5.55 13.59 2.45 1.30 0.24 14.90 2.68
18 5.52 13.59 2.46 1.30 0.24 14.90 2.70
19 3.10 7.09 2.29 0.87 0.28 7.96 2.57
20 0.37 0.84 2.29 0.45 1.23 1.29 3.52
Total 105.19 251.54 2.39 24.80 0.24 276.34 2.63

 

Source: M3, 2023

 

18.3QP Opinion

 

It is the opinion of SRK responsible for the mine cost modeling that the level of information and work regarding these issues and estimates are appropriate for an initial assessment and represent good industry practice that align with S-K 1300 reporting.

 

It is the opinion of M3 responsible for the process plant and G&A capital and operating costs that the level of information and work regarding these issues and estimates are appropriate for an initial assessment and represent good industry practice that align with S-K 1300 reporting.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 397

 

19Economic Analysis

 

19.1General Description

 

SRK prepared a cash flow model to evaluate the Santa Cruz Project on a real basis. This model was prepared on an annual basis from the start of operation through the exhaustion of mineable material. This section presents the main assumptions used in the cash flow model and the resulting indicative economics. The model results are presented in U.S. dollars (US$), unless otherwise stated.

 

This assessment is preliminary in nature and is based on mineral resources. Unlike mineral reserves, mineral resources do not have demonstrated economic viability. This assessment also includes inferred mineral resources that are considered too speculative geologically to have modifying factors applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that this economic assessment will be realized.

 

The economic model is based on mine plans that were prepared as outlined in previous sections. Inferred resources account for approximately 21% of the tonnage contained within the mine plan. The economic results of the Project both without inferred resources and including inferred resources are presented within this section. However, the removal of the inferred material from the mine plan is a gross adjustment and no recalculation of fixed capital and operating costs has been completed for the scenario without inferred mineral resources.

 

Capital and operating costs were developed in previous sections and the build-ups and associated accuracy, and contingency can be found in those sections.

 

All results and technical and cost information are presented in this section on a 100% basis reflective of IE’s ownership unless otherwise noted.

 

As with the capital and operating cost and pricing forecasts, the economic analysis is inherently a forward-looking exercise. These estimates rely upon a range of assumptions and forecasts that are subject to change depending upon macroeconomic conditions, operating strategy and new data collected through future study and operation.

 

19.1.1Basic Model Parameters

 

Key criteria used in the analysis are presented throughout this section. Basic model parameters are summarized in Table 19-1.

 

Table 19-1: Basic Model Parameters

 

Description Value
TEM time zero start date January 1, 2024
Delay to construction (years) 2
Construction period (years) 3
Mine life (years) 20
Discount rate 8%

 

Source: SRK, IE, 2023

 

All costs incurred prior to the model start date are considered sunk costs. The potential impact of these costs on the economics of the Project is not evaluated. This includes contributions to depreciation and working capital as these items are assumed to have a zero balance at model start.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 398

 

The model continues several years beyond the mine life to incorporate closure costs in the cash flow analysis.

 

The selected discount rate is 8% as directed by IE.

 

19.1.2External Factors

 

Pricing

 

Modeled prices are based on the prices developed in the Market Study section of this report. The prices are modeled as US$3.80/lb of copper over the life of the Project.

 

All product streams produced by the operation are modeled as being subject to the price presented above.

 

Taxes and Royalties

 

As modeled the Project is subject to a combined state and federal income tax rate estimated at 24.87%. All expended capital is subject to depreciation. Two depreciation methods are utilized:

 

Mine Development Costs – Certain costs associated with development of the underground mine are depreciated via an accelerated depreciation schedule that is presented in Table 19-2. Approximately 33% of the LoM capital is assumed to be subject to this accelerated depreciation schedule.

 

Table 19-2: Mine Development Cost Accelerated Depreciation Schedule

 

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
73% 6% 6% 6% 6% 3%

 

Source: SRK, 2023

 

Other – All other capital depreciation occurs via straight line method over a 10 year period.

 

Property tax has been included as a line item in the model. This line item is approximately US$100 million over the life of the mine and has been included as a G&A cost.

 

The Project is modeled as being subject to Arizona Mineral Severance Tax payable at a rate of 2.5% on revenue minus production costs.

 

Taxable income is adjusted by depletion is calculated via cost depletion methodology and percentage depletion methodology appropriate to a copper operation and varies depending upon the year of operation.

 

The Project is subject to a number of royalties as outlined in previous sections. These royalties vary in rate and area of influence. The material subject to royalties was provided in the mining schedule and the appropriate rates were applied in the model. This approach results in a combined net smelter royalty rate of approximately 7.4% and totaling approximately US$742.5 million over the life of the Project for the scenario without Inferred material and approximately 7.1% and totaling approximately US$909.5 million over the life of the Project for the scenario that includes the Inferred material.

 

Working Capital

 

The assumptions used for working capital in this analysis are as follows:

 

Accounts Receivable (A/R): 15 day delay
Accounts Payable (A/P): 30 day delay
Zero opening balance for A/R and A/P

 

September 2023

SEC Technical Report Summary – Santa CruzPage 399

 

19.1.3Technical Factors

 

Mining Profile

 

The modeled mining profile was developed by SRK. The details of mining profile are presented previously in this report. No modifications were made to the profile for use in the economic model. The modeled profile is presented in Figure 19-1 and Figure 19-2.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 400

 

 

Source: SRK, 2023

 

Figure 19-1: Santa Cruz Mining Profile (Tabular Data in Table 19-13 - Without Inferred Material)

 

 

Source: SRK, 2023

 

Figure 19-2: Santa Cruz Mining Profile (Tabular Data in Table 19-14 – Including Inferred Material)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 401

 

A summary of the modeled LoM mining profile is presented in Table 19-3.

 

This assessment is preliminary in nature and is based on mineral resources. Unlike mineral reserves, mineral resources do not have demonstrated economic viability. This assessment also includes inferred mineral resources that are considered too speculative geologically to have modifying factors applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that this economic assessment will be realized.

 

The economic model is based on mine plans that were prepared as outlined in previous sections. Inferred resources account for approximately 21% of the tonnage contained within the mine plan.

 

Table 19-3: Santa Cruz Mining Summary

 

LoM Mining  Unit Value (without inferred) Value (with Inferred) 
Santa Cruz Ore Mined tonnes 77,213,577 88,573,207
East Ridge Ore Mined tonnes - 9,799,031
Exotic Ore Mined tonnes 1,166,912 1,871,821
Total Ore Mined tonnes 78,380,490 100,244,060
Marginal Material Mined tonnes 4,479,258 4,941,504
Total Grade Bearing Mined tonnes 82,859,748 105,185,563
Waste Mined tonnes 1,695,035 1,948,116
Total Material Mined tonnes 84,554,783 107,133,680
Total Copper Grade      
Santa Cruz % 1.61% 1.60%
East Ridge % - 1.76%
Exotic % 2.81% 2.66%
Total % 1.62% 1.63%
Marginal % 0.55% 0.56%
Contained Metal (TCu)      
Santa Cruz tonnes 1,240,177 1,414,388
East Ridge tonnes - 172,526
Exotic tonnes 32,823 49,727
Total tonnes 1,273,000 1,636,641
Marginal tonnes 24,671 27,673

 

Source: SRK, 2023

 

Processing Profile

 

The processing profile is a result of the mining profile and the application of stockpile logic to the mining profile. The recovery profile was developed external to the model as outlined in the sections above. No modifications to the recovery profile were made in the model. The modeled profile is presented in Figure 19-3 and Figure 19-4.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 402

 

 

Source: SRK, 2023

 

Figure 19-3: Santa Crus Processing Profile (Tabular Data in Table 19-13 - Without Inferred Material)

 

 

Source: SRK, 2023

 

Figure 19-4: Santa Cruz Processing Profile (Tabular Data in Table 19-14 – Including Inferred Material)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 403

 

A summary of the modeled LoM processing profile is presented in Table 19-4.

 

Table 19-4: Santa Cruz Processing Summary

 

LoM Processing  Unit Value (without Inferred) Value (with Inferred)
Ore Feed tonnes 82,859,748 105,185,563
Average Feed Grade % TCu 1.57% 1.58%
Contained Metal (Total) tonnes 1,297,671 1,664,313
Cathode Recovery % 62.03% 62.03%
Concentrate Recovery % 33.33% 33.33%
Overall Copper Recovery % 95.36% 95.36%
Copper Recovered to Cathode tonnes 804,939 1,032,325
Copper Recovered to Concentrate tonnes 432,527 554,773
Total Recovered Copper tonnes 1,237,465 1,587,098
Cathode Produced tonnes 804,939 1,032,325
Concentrate Produced (48% Cu) dmt 901,097 1,155,777

 

Source: SRK, 2023

 

Operating Costs

 

Operating costs modeled in US dollars and can be categorized as mining, processing and G&A costs. Within the model laboratory costs have been captured as processing costs and G&A costs include estimated property tax payments over the life of the operation. No contingency amounts have been added to the operating costs within the model. A summary of the operating costs over the life of the operation is presented in Figure 19-5.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 404

 

 

Source: SRK, 2023

 

Figure 19-5: LoM Operating Cost Summary (Tabular Data in Table 19-13)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 405

 

The contributions of the different operating cost segments over the life of the operation are presented in Figure 19-6.

 

 

Source: SRK, 2023

 

Figure 19-6: LoM Operating Cost Contributions

 

Mining

 

The mining cost profile was developed external to the model and incorporated into the model as fixed costs and variable costs. Variable costs are applied to material reclaimed from construction period stockpiles in ramp-up. Note that this table includes approximately US$ 10 million in preproduction mining costs that are capitalized in order to present a complete analysis of the cost per tonne mined. The result of this approach is presented in Table 19-5.

 

Table 19-5: Santa Cruz Mining Cost Summary

 

LoM Mining Costs Unit Value
Mining Costs US$ million 2,928
Mining Cost (without inferred) US$/t mined 34.63
Mining Cost
(including inferred)
US$/t mined 27.33

 

Source: SRK, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 406

 

Processing

 

Processing costs were developed external to the model and incorporated into the model. The result of this approach is presented in Table 19-6.

 

Table 19-6: Santa Cruz Processing Cost Summary

 

LoM Processing Costs Unit Value
Processing Costs US$ million  1,351
Processing Cost (without inferred) US$/t processed 16.30
Processing Cost (including inferred) US$/t processed  12.84

 

Source: SRK, 2023

 

G&A

 

G&A cost profiles were developed external to the model and incorporated into the model as fixed costs. In addition to the G&A cost developed in earlier sections, property tax for the operation is included in the G&A cost. The fixed costs presented Table 19-7 and the result is presented in Table 19-8.

 

Table 19-7: G&A Fixed Costs

 

G&A LoM Unit Value
G&A US$ million  251.5
Property Tax US$ million  96.5
Total US$ million 348.1

 

Source: SRK, 2023

 

Table 19-8: Santa Cruz G&A Cost Summary

 

LoM SG&A Costs Unit Value
G&A Costs US$ million  348
G&A Cost
(without inferred)
US$/t processed 4.20
G&A Cost
 (including inferred)
US$/t processed  3.31

 

Source: SRK, 2023

 

Selling Cost

 

Selling costs consist of the transport costs associated with moving the operation’s product to the selling point. And the treatment and refining charges incurred. These costs are presented on a 100% basis in Table 19-9.

 

Table 19-9: Transport Costs and TC/RCs

 

Item Unit Value
Payability % 96.5%
Treatment Cost US$/t concentrate 65
Refining Cost US$/lb Cu 0.065
Transport Costs US$/t concentrate 90

 

Source: SRK, 2023

 

No transport cost is applied to the cathode product as it is assumed to be sold at mine gate as indicated by IE.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 407

 

Capital Costs

 

Initial capital estimates and expenditure schedule were developed external to the model as outlined in the previous sections. No additional contingency has been included in the model. Table 19-10 outlines the initial capital expenditure.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 408

 

Table 19-10: Modeled Initial Capital

 

Initial Capital Cost Unit Value
Underground Capital Development Cost US$ million 167.0
Underground Equipment Purchase US$ million 240.4
Underground Rebuilds US$ million 0.8
Underground Services US$ million 18.0
Underground Owner Cost US$ million 10.9
Underground Related Contingency Costs US$ million 34.8
Underground Capitalized Opex US$ million 35.6
Mill And Surface Capital US$ million 563.7
TSF US$ million 75.1
Total US$ million 1,146.3

 

Source: SRK, 2023

 

Sustaining capital is modeled on an annual basis and is used in the model as developed in previous sections. No contingency amounts have been added to the sustaining capital within the model. General closure costs are modeled as sustaining capital and are captured as a one-time payment the year following cessation of operations. For the tailings impoundment, closure costs run several years past the end of the mine life, and these costs have been captured by extending the model life beyond the end of the mine life.

 

Total sustaining capital is presented in Table 19-11.

 

Table 19-11: Modeled Sustaining Capital

 

Sustaining Capital Unit Value
Underground Mining US$ million 462.8
Tailings US$ million 486.6
Closure US$ million 27.0
Total US$ million 976.4

 

Source: SRK, 2023

 

The modeled capital profile is presented in Figure 19-7.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 409

 

 

Source: SRK, 2023

 

Figure 19-7: Santa Cruz Capital Profile (Tabular Data in Table 19-13)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 410

 

19.2Results

 

It should be noted that this assessment is preliminary in nature and is based on mineral resources. Unlike mineral reserves, mineral resources do not have demonstrated economic viability. This assessment also includes inferred mineral resources that are considered too speculative geologically to have modifying factors applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that this economic assessment will be realized.

 

The economic analysis metrics are prepared on annual after-tax basis in US$. The results of the analysis are presented in Table 19-12. The results indicate that, at a copper price of US$3.80/lb and without inferred material, the Project returns an after-tax NPV at 8% of US$0.5 billion calculated from the start of construction and an after tax IRR of 14% and a payback period from the start of construction of 10 years. When the inferred material is included in the economic analysis, the after tax NPV @ 8% increases to US$1.3 billion, and the after tax IRR increases to 23% and the payback period decreases to 7 years from the start of construction.

 

As the stage of study for the Santa Cruz Project is the Initial Assessment, no reserves are estimated for use in this analysis. The economic evaluation was completed using resource material that includes material in the Inferred category. To evaluate the risk associated with the use of Inferred material in the mine plan, a model was completed where the Inferred material was removed from the mine plan. SRK notes that the model result without Inferred material should be viewed with caution as the removal of the Inferred material is a gross adjustment and no corresponding adjustments to capital, operating cost or mill performance were made as the mine planning, capital and operating costs were developed around the larger scenario including the inferred resources in order to present a clear picture of the risk associated with Inferred resources and the potential impact of low confidence material on the economic result of a project.

 

This estimated cash flow is inherently forward-looking and dependent upon numerous assumptions and forecasts, such as macroeconomic conditions, mine plans and operating strategy, that are subject to change.

 

Table 19-12: Indicative Economic Results

 

LoM Cash Flow (Unfinanced) Units Value (without Inferred) Value (with Inferred)
Total Revenue US$ million 10,031.6 12,865.9
Total Opex US$ million (4,616.9) (4,617.0)
Operating Margin US$ million 5,414.7 8,248.9
Operating Margin Ratio % 54% 64%
Taxes Paid US$ million (426.6) (984.8)
Free Cash Flow US$ million 3,241.1 5,350.1
Before Tax    
Free Cash Flow US$ million 2,549.5 5,216.7
NPV at 8% US$ million 583.4 1,642.5
IRR % 15% 25%
After Tax    
Free Cash Flow US$ million 2,122.9 4,231.9
NPV at 8% US$ million 457.7 1,316.6
IRR % 14% 23%
Payback years 10 7

 

Source: SRK, 2023

 

The economic results and back-up chart information for charts within this section are presented on an annual basis in Figure 19-8, Figure 19-9, Table 19-13, and Table 19-14.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 411

 

 

 

Source: SRK, 2023

 

Figure 19-8:Annual Cash Flow Summary without Inferred Material (Tabular Data in Table 19-13 – Without Inferred Material)

 

 

Source: SRK, 2023

 

Figure 19-9: Annual Cash Flow Summary with Inferred Material (Tabular Data in Table 19-14 – Including Inferred Material)

 

September 2023

SEC Technical Report Summary – Santa CruzPage 412

 

Table 19-13: Economic Results - Tabular Data (without Inferred material)

 

Report Table                            
Period Start       1-Jan-24 1-Jan-25 1-Jan-26 1-Jan-27 1-Jan-28 1-Jan-29 1-Jan-30 1-Jan-31 1-Jan-32 1-Jan-33 1-Jan-34
Period End       31-Dec-24 31-Dec-25 31-Dec-26 31-Dec-27 31-Dec-28 31-Dec-29 31-Dec-30 31-Dec-31 31-Dec-32 31-Dec-33 31-Dec-34
Delay       1 1 - - - - - - - - -
Construction       - - 1 1 1 - - - - - -
Operations       - - - - - 1 1 1 1 1 1
  Counters                          
  Calendar Year Num#   2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034
  Days in Period Num#   366 365 365 365 366 365 365 365 366 365 365
  Delay Year Num#   1 2 - - - - - - - - -
  Construction Year Num#   - - 1 2 3 - - - - - -
  Operations Year Num#   - - - - - 1 2 3 4 5 6
  Project Cash Flow (unfinanced)                          
  Revenue US$ 10,031,617,219 - - - - - 412,058,230 540,765,556 544,916,026 570,760,402 555,925,636 584,347,810
  Operating Cost US$ (4,616,927,384) - - - - - (197,827,037) (252,782,385) (251,744,034) (254,203,423) (261,548,146) (255,485,142)
  Royalty US$ (742,470,325) - - - - - (50,656,317) (40,178,526) (40,478,516) (42,385,254) (41,301,146) (42,994,995)
  Working Capital Adjustment US$ - - - - - - (674,143) (772,464) (255,911) (852,955) 1,206,323 (1,666,364)
  Initial Capex (excl. financing) US$ (1,118,145,146) - - (139,332,319) (326,387,722) (652,425,106) - - - - - -
  Sustaining Capital US$ (1,004,582,085) - - - - - (85,357,740) (42,835,855) (46,395,396) (47,203,914) (80,112,842) (45,623,051)
  Tax Paid US$ (426,563,685) - - - - - - - (2,008,991) (1,999,756) (7,050,828) (7,215,720)
  Project Net Cash Flow US$ 2,122,928,593 - - (139,332,319) (326,387,722) (652,425,106) 77,542,994 204,196,326 204,033,179 224,115,101 167,118,996 231,362,539
  Cumulative Net Cash Flow US$   - - (139,332,319) (465,720,040) (1,118,145,146) (1,040,602,153) (836,405,827) (632,372,648) (408,257,547) (241,138,551) (9,776,012)
  Operating Cost (LOM)                          
  Mining Cost US$ 2,916,396,693 - - - - - 120,839,344 158,914,078 159,855,316 160,478,820 166,324,004 161,247,363
  Processing Cost US$ 1,350,709,303 - - - - - 59,072,476 72,896,025 72,369,144 73,908,664 75,097,022 74,214,719
  G&A Cost US$ 348,086,428 - - - - - 17,915,217 19,237,322 19,519,574 19,815,938 20,127,121 20,023,061
  Mine Plan                          
  Santa Cruz Ore tonnes 77,213,577 - - - - 430,215 2,541,947 4,041,575 4,301,238 4,515,170 4,319,572 4,453,811
  East Ridge Ore tonnes - - - - - - - - - - - -
  Exotic Ore tonnes 1,166,912 - - - - - - 19,207 118,351 134,528 22,673 34,861
  Marginal Material tonnes 4,479,258 - - - - 437,265 552,826 230,241 187,358 318,605 380,359 345,028
  Waste tonnes 1,695,035 - - - - 479,177 56,693 22,287 81,514 97,599 95,093 126,644
  Santa Cruz Tcu % 1.61% - - - - 1.35% 1.66% 1.69% 1.57% 1.51% 1.60% 1.61%
  East Ridge TCu % #DIV/0! - - - - - - - - - - -
  Exotic TCu % 2.81% - - - - - - 1.32% 1.65% 2.96% 2.14% 5.53%
  Marginal TCu % 0.55% - - - - 0.48% 0.59% 0.59% 0.56% 0.57% 0.53% 0.53%
  Production Profile                          
  Equivalent Copper Sold lbs 2,639,899,268 - - - - - 108,436,376 142,306,725 143,398,954 150,200,106 146,296,220 153,775,740
  C1 Cost US$/lb   - - - - - 1.82 1.78 1.76 1.69 1.79 1.66
  C2 Cost US$/lb   - - - - - 4.85 3.10 3.12 3.06 3.36 3.04
  C3 Cost US$/lb   - - - - - 5.32 3.40 3.41 3.36 3.66 3.34
  Capital Profile                          
  Initial Capital US$ 1,146,331,004 - - 139,332,319 326,387,722 652,425,106 28,185,858 - - - - -
  Sustaining Capital US$ 976,396,228 - - - - - 57,171,882 42,835,855 46,395,396 47,203,914 80,112,842 45,623,051
  Cumulative Capital US$   - - 139,332,319 465,720,040 1,118,145,146 1,203,502,886 1,246,338,741 1,292,734,136 1,339,938,050 1,420,050,892 1,465,673,943
  Processing Profile                          
  Tonnes Processed   82,859,748 - - - - - 3,962,254 4,291,023 4,606,948 4,968,304 4,722,604 4,833,700
  Recovery to Cathode     - - - - - 62.02% 63.13% 62.92% 63.98% 65.77% 63.35%
  Recovery to Concentrate     - - - - - 33.34% 32.18% 32.40% 31.30% 29.43% 31.96%

 

September 2023

SEC Technical Report Summary – Santa CruzPage 413

 

Report Table                            
Period Start       1-Jan-35 1-Jan-36 1-Jan-37 1-Jan-38 1-Jan-39 1-Jan-40 1-Jan-41 1-Jan-42 1-Jan-43 1-Jan-44 1-Jan-45
Period End       31-Dec-35 31-Dec-36 31-Dec-37 31-Dec-38 31-Dec-39 31-Dec-40 31-Dec-41 31-Dec-42 31-Dec-43 31-Dec-44 31-Dec-45
Delay       - - - - - - - - - - -
Construction       - - - - - - - - - - -
Operations       1 1 1 1 1 1 1 1 1 1 1
  Counters                          
  Calendar Year Num#   2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045
  Days in Period Num#   365 366 365 365 365 366 365 365 365 366 365
  Delay Year Num#   - - - - - - - - - - -
  Construction Year Num#   - - - - - - - - - - -
  Operations Year Num#   7 8 9 10 11 12 13 14 15 16 17
  Project Cash Flow (unfinanced)                          
  Revenue US$ 10,031,617,219 579,860,548 581,976,845 592,173,376 518,073,180 625,446,106 585,965,370 486,009,537 514,764,533 521,583,740 519,642,603 517,139,129
  Operating Cost US$ (4,616,927,384) (255,846,964) (248,146,838) (255,957,606) (255,144,278) (247,821,754) (241,773,603) (242,884,596) (241,104,629) (244,310,441) (230,343,515) (232,584,416)
  Royalty US$ (742,470,325) (42,840,748) (43,078,497) (43,878,969) (37,710,215) (44,035,841) (40,328,805) (33,436,494) (34,693,240) (35,873,512) (36,736,427) (36,508,867)
  Working Capital Adjustment US$ - 214,147 (710,237) 213,325 2,978,365 (5,014,437) 1,136,888 4,187,589 (1,328,011) (16,750) (1,061,574) 280,446
  Initial Capex (excl. financing) US$ (1,118,145,146) - - - - - - - - - - -
  Sustaining Capital US$ (1,004,582,085) (40,771,637) (29,956,968) (72,108,195) (52,113,768) (29,057,490) (26,548,305) (37,378,840) (46,404,322) (34,853,513) (29,923,933) (26,951,719)
  Tax Paid US$ (426,563,685) (20,590,030) (21,143,375) (23,324,834) (19,239,475) (7,136,065) (54,706,741) (49,861,526) (27,035,235) (32,175,101) (35,046,508) (39,045,672)
  Project Net Cash Flow US$ 2,122,928,593 220,025,316 238,940,929 197,117,097 156,843,809 292,380,520 223,744,803 126,635,669 164,199,096 174,354,423 186,530,645 182,328,901
  Cumulative Net Cash Flow US$   210,249,303 449,190,233 646,307,330 803,151,138 1,095,531,658 1,319,276,461 1,445,912,130 1,610,111,227 1,784,465,650 1,970,996,295 2,153,325,197
  Operating Cost (LOM)                          
  Mining Cost US$ 2,916,396,693 160,650,830 154,348,776 161,336,124 162,707,217 154,944,322 151,023,563 152,854,950 151,686,962 155,079,474 141,834,445 146,245,760
  Processing Cost US$ 1,350,709,303 74,851,534 73,115,847 73,584,771 71,903,773 72,828,492 71,218,915 71,292,444 71,295,306 71,494,389 71,219,633 72,216,997
  G&A Cost US$ 348,086,428 20,344,599 20,682,215 21,036,711 20,533,288 20,048,940 19,531,125 18,737,202 18,122,361 17,736,578 17,289,437 14,121,659
  Mine Plan                          
  Santa Cruz Ore tonnes 77,213,577 4,218,715 4,390,044 4,612,163 4,128,933 4,397,222 4,571,863 4,009,141 4,100,450 4,115,608 4,118,135 3,831,891
  East Ridge Ore tonnes - - - - - - - - - - - -
  Exotic Ore tonnes 1,166,912 36,725 20,227 194,215 9,533 267,512 3,974 19,847 53,601 103,141 18,667 89,209
  Marginal Material tonnes 4,479,258 385,651 251,710 286,988 241,012 162,290 187,566 81,027 122,440 119,659 65,905 67,379
  Waste tonnes 1,695,035 228,087 43,970 88,717 113,504 13,290 73,427 35,359 63,380 27,784 9,651 13,775
  Santa Cruz Tcu % 1.61% 1.69% 1.65% 1.47% 1.59% 1.64% 1.64% 1.54% 1.58% 1.57% 1.61% 1.69%
  East Ridge TCu % #DIV/0! - - - - - - - - - - -
  Exotic TCu % 2.81% 4.17% 5.33% 3.64% 1.51% 2.94% 1.10% 2.96% 2.46% 1.89% 2.72% 2.05%
  Marginal TCu % 0.55% 0.51% 0.60% 0.54% 0.50% 0.60% 0.57% 0.51% 0.57% 0.65% 0.58% 0.60%
  Production Profile                          
  Equivalent Copper Sold lbs 2,639,899,268 152,594,881 153,151,801 155,835,099 136,335,047 164,591,081 154,201,413 127,897,247 135,464,351 137,258,879 136,748,053 136,089,244
  C1 Cost US$/lb   1.68 1.62 1.64 1.87 1.51 1.57 1.90 1.78 1.78 1.68 1.71
  C2 Cost US$/lb   3.03 2.98 3.08 3.36 2.30 2.34 2.77 2.67 2.60 2.48 2.49
  C3 Cost US$/lb   3.32 3.27 3.38 3.64 2.59 2.63 3.05 2.95 2.88 2.77 2.78
  Capital Profile                          
  Initial Capital US$ 1,146,331,004 - - - - - - - - - - -
  Sustaining Capital US$ 976,396,228 40,771,637 29,956,968 72,108,195 52,113,768 29,057,490 26,548,305 37,378,840 46,404,322 34,853,513 29,923,933 26,951,719
  Cumulative Capital US$   1,506,445,580 1,536,402,548 1,608,510,743 1,660,624,511 1,689,682,001 1,716,230,306 1,753,609,146 1,800,013,468 1,834,866,981 1,864,790,915 1,891,742,634
  Processing Profile                          
  Tonnes Processed   82,859,748 4,641,090 4,661,982 5,093,366 4,379,479 4,827,025 4,763,402 4,110,016 4,276,490 4,338,408 4,202,707 3,988,479
  Recovery to Cathode     63.83% 63.27% 65.96% 59.52% 60.29% 56.41% 61.46% 59.80% 61.02% 58.86% 61.58%
  Recovery to Concentrate     31.46% 32.04% 29.23% 35.95% 35.15% 39.19% 33.93% 35.66% 34.38% 36.63% 33.80%

 

September 2023

SEC Technical Report Summary – Santa CruzPage 414

 
Report Table                            
Period Start       1-Jan-46 1-Jan-47 1-Jan-48 1-Jan-49 1-Jan-50 1-Jan-51 1-Jan-52 1-Jan-53 1-Jan-54 1-Jan-55 1-Jan-56
Period End       31-Dec-46 31-Dec-47 31-Dec-48 31-Dec-49 31-Dec-50 31-Dec-51 31-Dec-52 31-Dec-53 31-Dec-54 31-Dec-55 31-Dec-56
Delay       - - - - - - - - - - -
Construction       - - - - - - - - - - -
Operations       1 1 1 1 1 1 1 1 - - -
  Counters                          
  Calendar Year Num#   2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056
  Days in Period Num#   365 365 366 365 365 365 366 365 365 365 366
  Delay Year Num#   - - - - - - - - - - -
  Construction Year Num#   - - - - - - - - - - -
  Operations Year Num#   18 19 20 21 22 23 24 25 - - -
  Project Cash Flow (unfinanced)                          
  Revenue US$ 10,031,617,219 482,640,217 267,532,945 30,035,428 - - - - - - - -
  Operating Cost US$ (4,616,927,384) (237,565,964) (146,369,106) (63,483,509) - - - - - - - -
  Royalty US$ (742,470,325) (34,627,783) (18,496,526) (2,229,647) - - - - - - - -
  Working Capital Adjustment US$ - 1,827,206 1,344,393 2,936,773 (3,972,606) - - - - - - -
  Initial Capex (excl. financing) US$ (1,118,145,146) - - - - - - - - - - -
  Sustaining Capital US$ (1,004,582,085) (31,445,734) (17,786,713) (17,786,713) (43,169,739) (16,169,739) - (40,031,207) (64,594,754) - - -
  Tax Paid US$ (426,563,685) (38,447,682) (29,069,603) (11,466,542) - - - - - - - -
  Project Net Cash Flow US$ 2,122,928,593 142,380,261 57,155,390 (61,994,209) (47,142,345) (16,169,739) - (40,031,207) (64,594,754) - - -
  Cumulative Net Cash Flow US$   2,295,705,457 2,352,860,848 2,290,866,638 2,243,724,293 2,227,554,554 2,227,554,554 2,187,523,347 2,122,928,593 2,122,928,593 2,122,928,593 2,122,928,593
  Operating Cost (LOM)                          
  Mining Cost US$ 2,916,396,693 151,836,766 97,041,909 47,146,670 - - - - - - - -
  Processing Cost US$ 1,350,709,303 71,586,110 41,654,733 14,888,310 - - - - - - - -
  G&A Cost US$ 348,086,428 14,143,087 7,672,464 1,448,530 - - - - - - - -
  Mine Plan                          
  Santa Cruz Ore tonnes 77,213,577 3,775,490 2,073,928 266,463 - - - - - - - -
  East Ridge Ore tonnes - - - - - - - - - - - -
  Exotic Ore tonnes 1,166,912 20,641 - - - - - - - - - -
  Marginal Material tonnes 4,479,258 28,032 27,916 - - - - - - - - -
  Waste tonnes 1,695,035 25,086 - - - - - - - - - -
  Santa Cruz Tcu % 1.61% 1.64% 1.66% 1.46% - - - - - - - -
  East Ridge TCu % #DIV/0! - - - - - - - - - - -
  Exotic TCu % 2.81% 1.51% - - - - - - - - - -
  Marginal TCu % 0.55% 0.54% 0.61% - - - - - - - - -
  Production Profile                          
  Equivalent Copper Sold lbs 2,639,899,268 127,010,583 70,403,407 7,904,060 - - - - - - - -
  C1 Cost US$/lb   1.87 2.08 8.03 - - - - - - - -
  C2 Cost US$/lb   2.69 2.95 11.03 - - - - - - - -
  C3 Cost US$/lb   2.99 3.23 11.31 - - - - - - - -
  Capital Profile                          
  Initial Capital US$ 1,146,331,004 - - - - - - - - - - -
  Sustaining Capital US$ 976,396,228 31,445,734 17,786,713 17,786,713 43,169,739 16,169,739 - 40,031,207 64,594,754 - - -
  Cumulative Capital US$   1,923,188,368 1,940,975,081 1,958,761,793 2,001,931,532 2,018,101,271 2,018,101,271 2,058,132,478 2,122,727,232 2,122,727,232 2,122,727,232 2,122,727,232
  Processing Profile                          
  Tonnes Processed   82,859,748 3,824,162 2,101,844 266,463 - - - - - - - -
  Recovery to Cathode     60.46% 66.25% 63.40% - - - - - - - -
  Recovery to Concentrate     34.96% 28.93% 31.90% - - - - - - - -

 

Source: SRK, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 415

 

Table 19-14: Economic Results - Tabular Data (including Inferred material)

 

Report Table     r                      
Period Start       1-Jan-24 1-Jan-25 1-Jan-26 1-Jan-27 1-Jan-28 1-Jan-29 1-Jan-30 1-Jan-31 1-Jan-32 1-Jan-33 1-Jan-34
Period End       31-Dec-24 31-Dec-25 31-Dec-26 31-Dec-27 31-Dec-28 31-Dec-29 31-Dec-30 31-Dec-31 31-Dec-32 31-Dec-33 31-Dec-34
Delay       1 1 - - - - - - - - -
Construction       - - 1 1 1 - - - - - -
Operations       - - - - - 1 1 1 1 1 1
  Counters                          
  Calendar Year Num#   2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034
  Days in Period Num#   366 365 365 365 366 365 365 365 366 365 365
  Delay Year Num#   1 2 - - - - - - - - -
  Construction Year Num#   - - 1 2 3 - - - - - -
  Operations Year Num#   - - - - - 1 2 3 4 5 6
  Project Cash Flow (unfinanced)                          
  Revenue US$ 12,865,918,857 - - - - - 534,266,541 734,977,306 696,950,686 716,270,272 722,943,893 730,087,939
  Operating Cost US$ (4,616,980,576) - - - - - (197,827,037) (252,835,578) (251,744,034) (254,203,423) (261,548,146) (255,485,142)
  Royalty US$ (909,496,543) - - - - - (57,187,409) (51,539,446) (49,247,823) (50,312,425) (50,782,156) (50,993,865)
  Working Capital Adjustment US$ - - - - - - (5,696,403) (3,727,138) 1,473,022 (568,474) 306,078 (791,920)
  Initial Capex (excl. financing) US$ (1,118,145,146) - - (139,332,319) (326,387,722) (652,425,106) - - - - - -
  Sustaining Capital US$ (1,004,582,085) - - - - - (85,357,740) (42,835,855) (46,395,396) (47,203,914) (80,112,842) (45,623,051)
  Tax Paid US$ (984,805,100) - - - - - - (691,787) (40,160,510) (43,250,679) (45,374,529) (37,312,612)
  Project Net Cash Flow US$ 4,231,909,406 - - (139,332,319) (326,387,722) (652,425,106) 188,197,953 383,347,502 310,875,947 320,731,357 285,432,297 339,881,350
  Cumulative Net Cash Flow US$   - - (139,332,319) (465,720,040) (1,118,145,146) (929,947,193) (546,599,691) (235,723,745) 85,007,612 370,439,909 710,321,259
  Operating Cost (LoM)                          
  Mining Cost US$ 2,916,396,693 - - - - - 120,839,344 158,914,078 159,855,316 160,478,820 166,324,004 161,247,363
  Processing Cost US$ 1,350,709,303 - - - - - 59,072,476 72,896,025 72,369,144 73,908,664 75,097,022 74,214,719
  G&A Cost US$ 348,086,428 - - - - - 17,915,217 19,237,322 19,519,574 19,815,938 20,127,121 20,023,061
  Mine Plan                          
  Santa Cruz Ore tonnes 88,573,207 - - - - 430,215 2,685,405 4,579,715 4,677,475 4,744,123 4,666,098 4,753,313
  East Ridge Ore tonnes 9,799,031 - - - - - 680,703 871,652 623,423 595,812 769,043 686,299
  Exotic Ore tonnes 1,871,821 - - - - - - 19,207 173,564 134,528 39,337 34,861
  Marginal Material tonnes 4,941,504 - - - - 463,861 584,019 239,983 195,024 320,944 471,607 359,088
  Waste tonnes 1,948,116 - - - - 488,306 120,352 22,287 84,759 97,981 214,948 126,644
  Santa Cruz Tcu % 1.60% - - - - 1.35% 1.64% 1.68% 1.56% 1.51% 1.59% 1.61%
  East Ridge TCu % 1.76% - - - - - 2.00% 1.87% 2.15% 2.57% 2.03% 2.01%
  Exotic TCu % 2.66% - - - - - - 1.32% 1.59% 2.96% 2.04% 5.53%
  Marginal TCu % 0.56% - - - - 0.47% 0.58% 0.60% 0.58% 0.57% 0.53% 0.54%
  Production Profile                          
  Equivalent Copper Sold lbs 3,385,768,120 - - - - - 140,596,458 193,415,081 183,408,075 188,492,177 190,248,393 192,128,405
  C1 Cost US$/lb   - - - - - 1.41 1.31 1.37 1.35 1.37 1.33
  C2 Cost US$/lb   - - - - - 3.74 2.54 2.67 2.65 2.82 2.62
  C3 Cost US$/lb   - - - - - 4.16 2.82 2.96 2.94 3.11 2.91
  Capital Profile                          
  Initial Capital US$ 1,146,331,004 - - 139,332,319 326,387,722 652,425,106 28,185,858 - - - - -
  Sustaining Capital US$ 976,396,228 - - - - - 57,171,882 42,835,855 46,395,396 47,203,914 80,112,842 45,623,051
  Cumulative Capital US$   - - 139,332,319 465,720,040 1,118,145,146 1,203,502,886 1,246,338,741 1,292,734,136 1,339,938,050 1,420,050,892 1,465,673,943
  Processing Profile                          
  Tonnes Processed   105,185,563 - - - - - 4,844,204 5,710,556 5,669,486 5,795,408 5,946,084 5,833,561
  Recovery to Cathode     - - - - - 62.02% 63.13% 62.92% 63.98% 65.77% 63.35%
  Recovery to Concentrate     - - - - - 33.34% 32.18% 32.40% 31.30% 29.43% 31.96%

 

September 2023

SEC Technical Report Summary – Santa CruzPage 416

 

Report Table                            
Period Start       1-Jan-35 1-Jan-36 1-Jan-37 1-Jan-38 1-Jan-39 1-Jan-40 1-Jan-41 1-Jan-42 1-Jan-43 1-Jan-44 1-Jan-45
Period End       31-Dec-35 31-Dec-36 31-Dec-37 31-Dec-38 31-Dec-39 31-Dec-40 31-Dec-41 31-Dec-42 31-Dec-43 31-Dec-44 31-Dec-45
Delay       - - - - - - - - - - -
Construction       - - - - - - - - - - -
Operations       1 1 1 1 1 1 1 1 1 1 1
  Counters                          
  Calendar Year Num#   2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045
  Days in Period Num#   365 366 365 365 365 366 365 365 365 366 365
  Delay Year Num#   - - - - - - - - - - -
  Construction Year Num#   - - - - - - - - - - -
  Operations Year Num#   7 8 9 10 11 12 13 14 15 16 17
  Project Cash Flow (unfinanced)                          
  Revenue US$ 12,865,918,857 740,663,382 703,648,089 678,173,920 677,128,331 733,936,249 690,917,170 663,772,684 667,930,989 667,664,444 683,054,334 711,473,628
  Operating Cost US$ (4,616,980,576) (255,846,964) (248,146,838) (255,957,606) (255,144,278) (247,821,754) (241,773,603) (242,884,596) (241,104,629) (244,310,441) (230,343,515) (232,584,416)
  Royalty US$ (909,496,543) (52,344,536) (50,162,519) (49,367,714) (46,362,946) (50,526,441) (46,400,428) (43,906,667) (43,752,245) (44,617,789) (47,063,297) (48,852,204)
  Working Capital Adjustment US$ - (404,868) 911,572 1,665,582 (23,879) (2,936,423) 1,294,083 1,183,557 (317,188) 274,445 (1,755,459) (1,008,701)
  Initial Capex (excl. financing) US$ (1,118,145,146) - - - - - - - - - - -
  Sustaining Capital US$ (1,004,582,085) (40,771,637) (29,956,968) (72,108,195) (52,113,768) (29,057,490) (26,548,305) (37,378,840) (46,404,322) (34,853,513) (29,923,933) (26,951,719)
  Tax Paid US$ (984,805,100) (47,653,073) (51,876,561) (47,799,002) (32,022,225) (35,992,391) (77,382,929) (71,849,697) (64,231,583) (64,215,330) (65,578,545) (73,064,449)
  Project Net Cashflow US$ 4,231,909,406 343,642,304 324,416,774 254,606,986 291,461,234 367,601,749 300,105,988 268,936,440 272,121,023 279,941,817 308,389,583 329,012,139
  Cumulative Net Cashflow US$   1,053,963,563 1,378,380,337 1,632,987,323 1,924,448,557 2,292,050,307 2,592,156,294 2,861,092,735 3,133,213,757 3,413,155,574 3,721,545,157 4,050,557,296
  Operating Cost (LoM)                          
  Mining Cost US$ 2,916,396,693 160,650,830 154,348,776 161,336,124 162,707,217 154,944,322 151,023,563 152,854,950 151,686,962 155,079,474 141,834,445 146,245,760
  Processing Cost US$ 1,350,709,303 74,851,534 73,115,847 73,584,771 71,903,773 72,828,492 71,218,915 71,292,444 71,295,306 71,494,389 71,219,633 72,216,997
  G&A Cost US$ 348,086,428 20,344,599 20,682,215 21,036,711 20,533,288 20,048,940 19,531,125 18,737,202 18,122,361 17,736,578 17,289,437 14,121,659
  Mine Plan                          
  Santa Cruz Ore tonnes 88,573,207 4,900,033 4,864,180 4,870,245 4,790,891 4,862,207 5,079,352 4,976,008 4,916,815 4,933,324 5,082,887 4,888,669
  East Ridge Ore tonnes 9,799,031 514,572 546,294 281,730 674,042 233,284 391,141 465,817 489,403 390,410 351,231 352,061
  Exotic Ore tonnes 1,871,821 59,858 28,232 310,199 9,533 377,944 3,974 32,667 68,247 150,790 40,439 233,853
  Marginal Material tonnes 4,941,504 431,148 268,934 343,030 258,734 182,247 193,733 84,554 145,400 134,273 106,709 74,534
  Waste tonnes 1,948,116 235,553 43,970 106,399 113,504 13,290 77,151 40,989 64,660 27,784 22,370 21,496
  Santa Cruz Tcu % 1.60% 1.68% 1.63% 1.48% 1.57% 1.65% 1.62% 1.55% 1.57% 1.56% 1.62% 1.65%
  East Ridge TCu % 1.76% 1.74% 1.53% 1.32% 1.61% 1.37% 1.54% 1.56% 1.42% 1.46% 1.32% 1.51%
  Exotic TCu % 2.66% 3.34% 5.33% 3.20% 1.51% 2.79% 1.10% 2.56% 2.31% 1.86% 2.55% 2.37%
  Marginal TCu % 0.56% 0.53% 0.61% 0.55% 0.52% 0.62% 0.57% 0.51% 0.61% 0.67% 0.61% 0.60%
  Production Profile                          
  Equivalent Copper Sold lbs 3,385,768,120 194,911,416 185,170,550 178,466,821 178,191,666 193,141,118 181,820,308 174,677,022 175,771,313 175,701,169 179,751,140 187,229,902
  C1 Cost US$/lb   1.31 1.34 1.43 1.43 1.28 1.33 1.39 1.37 1.39 1.28 1.24
  C2 Cost US$/lb   2.55 2.58 2.88 2.81 2.04 2.07 2.18 2.19 2.16 2.02 1.97
  C3 Cost US$/lb   2.84 2.87 3.17 3.09 2.33 2.36 2.46 2.47 2.44 2.31 2.26
  Capital Profile                          
  Initial Capital US$ 1,146,331,004 - - - - - - - - - - -
  Sustaining Capital US$ 976,396,228 40,771,637 29,956,968 72,108,195 52,113,768 29,057,490 26,548,305 37,378,840 46,404,322 34,853,513 29,923,933 26,951,719
  Cumulative Capital US$   1,506,445,580 1,536,402,548 1,608,510,743 1,660,624,511 1,689,682,001 1,716,230,306 1,753,609,146 1,800,013,468 1,834,866,981 1,864,790,915 1,891,742,634
  Processing Profile                          
  Tonnes Processed   105,185,563 5,905,612 5,707,639 5,805,204 5,733,200 5,655,682 5,668,200 5,559,045 5,619,864 5,608,798 5,581,265 5,549,117
  Recovery to Cathode     63.83% 63.27% 65.96% 59.52% 60.29% 56.41% 61.46% 59.80% 61.02% 58.86% 61.58%
  Recovery to Concentrate     31.46% 32.04% 29.23% 35.95% 35.15% 39.19% 33.93% 35.66% 34.38% 36.63% 33.80%

 

September 2023

SEC Technical Report Summary – Santa CruzPage 417

 

Report Table                            
Period Start       1-Jan-46 1-Jan-47 1-Jan-48 1-Jan-49 1-Jan-50 1-Jan-51 1-Jan-52 1-Jan-53 1-Jan-54 1-Jan-55 1-Jan-56
Period End       31-Dec-46 31-Dec-47 31-Dec-48 31-Dec-49 31-Dec-50 31-Dec-51 31-Dec-52 31-Dec-53 31-Dec-54 31-Dec-55 31-Dec-56
Delay       - - - - - - - - - - -
Construction       - - - - - - - - - - -
Operations       1 1 1 1 1 1 1 1 - - -
  Counters                          
  Calendar Year Num#   2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056
  Days in Period Num#   365 365 366 365 365 365 366 365 365 365 366
  Delay Year Num#   - - - - - - - - - - -
  Construction Year Num#   - - - - - - - - - - -
  Operations Year Num#   18 19 20 21 22 23 24 25 - - -
  Project Cash Flow (unfinanced)                          
  Revenue US$ 12,865,918,857 697,888,993 373,321,896 40,848,113 - - - - - - - -
  Operating Cost US$ (4,616,980,576) (237,565,964) (146,369,106) (63,483,509) - - - - - - - -
  Royalty US$ (909,496,543) (47,981,240) (25,063,078) (3,032,314) - - - - - - - -
  Working Capital Adjustment US$ - 967,715 5,842,742 6,841,122 (3,529,463) - - - - - - -
  Initial Capex (excl. financing) US$ (1,118,145,146) - - - - - - - - - - -
  Sustaining Capital US$ (1,004,582,085) (31,445,734) (17,786,713) (17,786,713) (43,169,739) (16,169,739) - (40,031,207) (64,594,754) - - -
  Tax Paid US$ (984,805,100) (78,888,417) (73,941,723) (33,519,058) - - - - - - - -
  Project Net Cash Flow US$ 4,231,909,406 302,975,353 116,004,019 (70,132,360) (46,699,202) (16,169,739) - (40,031,207) (64,594,754) - - -
  Cumulative Net Cash Flow US$   4,353,532,649 4,469,536,668 4,399,404,308 4,352,705,106 4,336,535,367 4,336,535,367 4,296,504,160 4,231,909,406 4,231,909,406 4,231,909,406 4,231,909,406
  Operating Cost (LoM)                          
  Mining Cost US$ 2,916,396,693 151,836,766 97,041,909 47,146,670 - - - - - - - -
  Processing Cost US$ 1,350,709,303 71,586,110 41,654,733 14,888,310 - - - - - - - -
  G&A Cost US$ 348,086,428 14,143,087 7,672,464 1,448,530 - - - - - - - -
  Mine Plan                          
  Santa Cruz Ore tonnes 88,573,207 4,687,544 2,816,684 368,024 - - - - - - - -
  East Ridge Ore tonnes 9,799,031 632,462 249,654 - - - - - - - - -
  Exotic Ore tonnes 1,871,821 154,588 - - - - - - - - - -
  Marginal Material tonnes 4,941,504 46,623 37,060 - - - - - - - - -
  Waste tonnes 1,948,116 25,675 - - - - - - - - - -
  Santa Cruz Tcu % 1.60% 1.61% 1.59% 1.43% - - - - - - - -
  East Ridge TCu % 1.76% 1.65% 1.27% - - - - - - - - -
  Exotic TCu % 2.66% 2.63% - - - - - - - - - -
  Marginal TCu % 0.56% 0.65% 0.68% - - - - - - - - -
  Production Profile                          
  Equivalent Copper Sold lbs 3,385,768,120 183,654,998 98,242,604 10,749,503 - - - - - - - -
  C1 Cost US$/lb   1.29 1.49 5.91 - - - - - - - -
  C2 Cost US$/lb   2.04 2.28 8.13 - - - - - - - -
  C3 Cost US$/lb   2.33 2.56 8.41 - - - - - - - -
  Capital Profile                          
  Initial Capital US$ 1,146,331,004 - - - - - - - - - - -
  Sustaining Capital US$ 976,396,228 31,445,734 17,786,713 17,786,713 43,169,739 16,169,739 - 40,031,207 64,594,754 - - -
  Cumulative Capital US$   1,923,188,368 1,940,975,081 1,958,761,793 2,001,931,532 2,018,101,271 2,018,101,271 2,058,132,478 2,122,727,232 2,122,727,232 2,122,727,232 2,122,727,232
  Processing Profile                          
  Tonnes Processed   105,185,563 5,521,217 3,103,397 368,024 - - - - - - - -
  Recovery to Cathode     60.46% 66.25% 63.40% - - - - - - - -
  Recovery to Concentrate     34.96% 28.93% 31.90% - - - - - - - -

 

Source: SRK, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 418

 

19.3Sensitivity Analysis

 

SRK performed a sensitivity analysis to determine the relative sensitivity of the Project’s NPV to a number of key parameters (Figure 19-10). This is accomplished by flexing each parameter upwards and downwards by 10%. The inclusion of the inferred material is included as a sensitivity and is an exception to the 10% flex utilized for other variables. Within the constraints of this analysis, the Project appears to be most sensitive to, material classification, commodity prices, recovery assumptions within the processing plant and mined grades.

 

SRK cautions that this sensitivity analysis is for information only and notes that these parameters were flexed in isolation within the model and are assumed to be uncorrelated with one another which may not be reflective of reality. Additionally, the amount of flex in the selected parameters may violate physical or environmental constraints present at the operation.

 

 

Source: SRK, 2023

 

Figure 19-10: NPV Sensitivity Analysis

 

September 2023

SEC Technical Report Summary – Santa CruzPage 419

 

20Adjacent Properties

 

20.1Cactus Project

 

The Cactus project in Pinal County, Arizona, is owned by the Arizona Sonoran Copper Company (ASCU, https://arizonasonoran.com/). The project includes the past producing Sacaton open pit mine and stockpile and further land holdings. The Cactus project is located approximately 9.4 km northeast of IE’s Santa Cruz project.

 

The QP has been unable to verify the geology and mineralization on the adjacent Cactus project. The Cactus project is not necessarily indicative of the mineralization of the Santa Cruz Project.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 420

 

21Other Relevant Data and Information

 

There are no additional relevant data or information that would be material to the mineral resource of mine plan for the Santa Cruz Project, beyond what is discussed in the other sections of this report.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 421

 

22Interpretation and Conclusions

 

22.1Geology

 

The Santa Cruz Project is comprised of several areas along a southwest-northeast corridor representing portions of a large porphyry copper system separated by extensional Basin and Range normal faults. Each area has experienced variable periods of erosion, supergene enrichment, fault displacement, and tilting into their present positions.

 

The bedrock geology at the Santa Cruz Project is dominated by Oracle Granite with lesser Proterozoic Diabase intrusions and Laramide porphyry intrusions. There are three main types of copper mineralization found within the Santa Cruz Project: primary hypogene sulfide mineralization which consists of primary cu-sulfide minerals; secondary supergene sulfide mineralization which consists of dominantly chalcocite; and secondary supergene oxide mineralization which consists of mainly atacamite and chrysocolla. Modeling of the Santa Cruz Deposit was divided into four main Cu domains which represent different subcategories of Cu mineralization: the Exotic Domain, Oxide Domain, Chalcocite Enriched Domain, and Primary Domain. The Santa Cruz Deposit contains all 4 domains, whereas the Texaco Deposit contains no exotic copper, and the East Ridge Deposit only consists of the Oxide Domain (primarily acid soluble Cu).

 

The Santa Cruz Deposit Mineral Resource Estimate was created from the main drillhole database containing 116,388 m of diamond drilling in 129 drillholes, while the Texaco MRE was created from 23 drillholes totaling 21,289 m, and the East Ridge MRE comprises of 18 holes totaling 15,448 m. All drillholes were drilled between 1964 and 2022. Historic diamond drillhole samples were analyzed for total Cu and acid soluble Cu using AAS. Later samples were re-analyzed for cyanide soluble Cu (AAS) and molybdenum (ICP). The Company currently analyzes all samples for total Cu, acid soluble Cu, cyanide soluble Cu, and molybdenum. Due to the re-analyses to determine cyanide soluble Cu within historic samples, there are instances where cyanide soluble Cu is greater than total Cu. It has been determined that the historic cyanide soluble assays are valid as they align with recent assays in 2022 drillholes.

 

Geological domains were developed within the Santa Cruz Project based upon geographical, lithological, and mineralogical characteristics, along with incorporating both regional and local structural information; local D2 fault structures separate the mineralization at the adjacent Santa Cruz and Texaco Deposits. The Santa Cruz, Texaco, and East Ridge Deposits were divided into four main geological domains based upon their type of Cu speciation, specifically acid soluble (Oxide Domain), cyanide soluble (Chalcocite Enriched Domain), primary Cu sulfide (Primary Domain), and exotic Cu (Cu oxides in overlying Tertiary sediments).

 

Once a geologic interpretation was established, wireframes were created. When not cut-off by drilling, the wireframes terminate at either the contact of the Cu-oxide boundary layer, the Tertiary sediments/Oracle Granite contact, or the D2 fault. There is an overlap of the Chalcocite Enriched Domain with both the Oxide Domain in the weathered supergene and with the Primary Domain in the primary hypogene mineralization. Otherwise, no wireframe overlapping exists within a given grade domain. Implicit modeling was completed in Leapfrog GeoTM which produced reasonable mineral domains that appropriately represent the known controls on grade mineralization.

 

A block model for each deposit was created that incorporated lithological, structural, and mineralization trends. Each block model was fully validated.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 422

 

Nordmin feels that the interpreted geological and mineralization domains produced accurately represents the deposit style of the Santa Cruz, Texaco, and East Ridge Deposits.

 

22.2Exploration, Drilling, and Analytical Data Collection in Support of Mineral Resource Estimation

 

The exploration programs completed by IE and previous operators are appropriate for the deposit style. The programs delineated the Santa Cruz, Texaco, and East Ridge Deposits. Diamond drilling indicates the potential to further define and potentially expand on known exploration areas.

 

The quantity and the quality of lithological, collar, and downhole survey data collected in the various exploration programs by various operators are sufficient to support the. The sampling is representative of total Cu, acid soluble Cu, cyanide soluble Cu, and molybdenum data in the Santa Cruz, Texaco, and East Ridge Deposits reflecting areas of higher and lower grades, which has been confirmed by 2021 and 2022 diamond drillhole twinning of historic, high-grade drillholes. The twin-hole analysis compared the collar locations, downhole surveys, logging (lithology, alteration, and mineralization), sampling, and assaying between the two groups to determine if the historical holes had valid information and would not be introducing a bias within the geological model or Resource Estimate. Nordmin was able to match most of the intervals for each of the pairs and plotted the grades for Cu, Cu-SEQ, and Mo. In Nordmin’s opinion, for most of the pairs, the assay results compared very well; the high-grade (HG) and low-grade (LG) zones were similar, and the grades tended to cluster in the same local ranges. In Nordmin’s opinion, the twinning has provided a reasonably consistent verification of the earlier Hanna-Getty and ASARCO drill results across all deposits, particularly considering the differences in the assay, survey methods, and QA/QC protocols. Nordmin considered the QA/QC protocols in place for the Project to be acceptable and in line with standard industry practice. Based on the data validation and results of standard, blank, and duplicate analyses, Nordmin is of the opinion that the assay and SG databases are of sufficient quality for the creation of a Mineral Resource Estimate for the Project.

 

Nordmin is not aware of any drilling, sampling, or recovery factors that could materially impact the accuracy and reliability of the results. In Nordmin’s opinion the drilling, core handling, logging, and sampling procedures meet or exceed industry standards, and are adequate for the purpose of Mineral Resource Estimation.

 

22.3Mineral Resource Estimate

 

The Mineral Resource Estimate was classified in accordance with S-K 1300 definitions. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. This estimate of Mineral Resources may be materially affected by environmental permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

 

Mineral Resource Classification was assigned to broad regions of the Santa Cruz, Texaco, and East Ridge Deposit block models based on the Nordmin QP’s confidence and judgment related to several factors as defined in Section 11.To demonstrate reasonable prospects for eventual economic extraction for the Santa Cruz, Texaco, and East Ridge Mineral Resource Estimates, representational minimum mining unit shapes were created using Deswik’s minimum MSO tool.

 

The Santa Cruz Project Mineral Resource Estimate, which is exclusive of mineral reserves, is presented in Table 22-1.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 423

 

Table 22-1: In Situ Mineral Resource Estimate for Santa Cruz, Texaco, and East Ridge Deposits

 

Classification Deposit

Mineralized

Material

(kt)

Mineralized

Material

(k ton)

Total

Cu

(%)

Total

Soluble Cu

(%)

Acid

Soluble Cu

(%)

Cyanide

Soluble

Cu (%)

Total Cu

(kt)

Total

Soluble Cu

(kt)

Acid

Soluble Cu

(kt)

Cyanide

Soluble Cu

(kt)

Total Cu

(Mlb)

Indicated

Santa Cruz

(0.70% CoG)

223,155 245,987 1.24 0.82 0.58 0.24 2,759 1,824 1,292 533 6,083

Texaco

(0.80% CoG)

3,560 3,924 1.33 0.97 0.25 0.73 47 35 9 26 104

East Ridge

(0.90% CoG)

0 0 0.00 0.00 0.00 0.00 0 0 0 0 0
Inferred

Santa Cruz

(0.70% CoG)

62,709 69,125 1.23 0.92 0.74 0.18 768 576 462 114 1,694

Texaco

(0.80% CoG)

62,311 68,687 1.21 0.56 0.21 0.35 753 348 132 215 1,660

East Ridge

(0.90% CoG)

23,978 26,431 1.36 1.26 0.69 0.57 326 302 164 137 718
Total
Indicated All Deposits 226,715 249,910 1.24 0.82 0.57 0.25 2,807 1,859 1,300 558 6,188
Inferred All Deposits 148,998 164,242 1.24 0.82 0.51 0.31 1,847 1,225 759 466 4,072

 

Source: Nordmin, 2023

 

Notes on Mineral Resources:

 

The Mineral Resources in this Estimate were independently prepared, including estimation and classification, by Nordmin Engineering Ltd. and in accordance with the definitions for Mineral Resources in S-K 1300.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. This estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

Verification included multiple site visits to inspect drilling, logging, density measurement procedures and sampling procedures, and a review of the control sample results used to assess laboratory assay quality. In addition, a random selection of the drillhole database results was compared with the original records.

The Mineral Resources in this estimate for the Santa Cruz, East Ridge, and Texaco Deposits used Datamine Studio RMTM software to create the block models.

The Mineral Resources are current to December 31, 2022.

Underground-constrained Mineral Resources for the Santa Cruz Deposit are reported at a cut-off grade of 0.70% total copper, Texaco Deposit are reported at a cut-off grade of 0.80% total copper and East Ridge Deposit are reported at a cut-off grade of 0.90% total copper. The cut-off grade reflects total operating costs to define reasonable prospects for eventual economic extracted by conventional underground mining methods with a maximum production rate of 15,000 tonnes/day. All material within mineable shape-optimized wireframes has been included in the Mineral Resource.

Underground mineable shape optimization parameters include a long-term copper price of US$3.70/lb, process recovery of 94%, direct mining costs between US$24.50-$40.00/processed tonne reflecting various mining method costs (long hole or room and pillar), mining general and administration cost of US$4.00/t processed, onsite processing and SX/EW costs between US$13.40-$14.47/t processed, offsite costs between US$3.29 to US$4.67/t processed, along with variable royalties between 5.00% to 6.96% NSR and a mining recovery of 100%.

Specific Gravity was applied using weighted averages by Deposit Sub-Domain.

All figures are rounded to reflect the relative accuracy of the estimates, and totals may not add correctly.

Excludes unclassified mineralization located along edges of the Santa Cruz, East Ridge, and Texaco Deposits where drill density is poor.

Report from within a mineralization envelope accounting for mineral continuity. Total soluble copper means the addition of sequential acid soluble copper and sequential cyanide soluble copper assays. Total soluble copper is not reported for the Primary Domain.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 424

 

There is a potential to increase the Mineral Resource by using infill drilling to expand and increase the Mineral Resource category.

 

Areas of uncertainty that may materially impact the Mineral Resource Estimate include:

 

Changes to long term metal price assumptions.

Changes to the input values for mining, processing, and G&A costs to constrain the estimate.

Changes to local interpretations of mineralization geometry and continuity of mineralized zones.

Changes to the density values applied to the mineralized zones.

Changes to metallurgical recovery assumptions.

Changes in assumption of marketability of the final product.

Variations in geotechnical, hydrogeological, and mining assumptions.

Changes to assumptions with an existing agreement or new agreements.

Changes to environmental, permitting, and social license assumptions.

 

Logistics of securing and moving adequate services, labor, and supplies could be affected by epidemics, pandemics and other public health crises including COVID-19 or similar viruses.

 

These risks and uncertainties may cause delays in economic resource extraction and/or cause the resource to become economically non-viable.

 

22.4Mining Methods

 

The Project is currently not in operation. Mineral resources are stated for three areas: Santa Cruz, Texaco, and East Ridge. For mine planning work, only the Santa Cruz and East Ridge areas were evaluated.

 

Santa Cruz is located approximately 430 to 970 m below the surface. Based on the mineralization geometry and geotechnical information, an underground longhole stoping (LHS) method is suitable for the deposit. The Santa Cruz deposit will be mined in blocks where mining within a block occurs from bottom to top with paste backfill (PBF) for support. A sill pillar is left in situ between blocks.

 

Within the Santa Cruz deposit, there is an Exotic domain located approximately 500 to 688 m below the surface and to the east of the main deposit. The Exotic domain consists of flatter lenses that are more amenable to drift and fill (DAF) mining. Cemented waste rockfill will be used for support. The backfill will have sufficient strength to allow mining of adjacent drifts without leaving pillars.

 

The East Ridge deposit is approximately 380 to 690 m below the surface and to the north of the main Santa Cruz deposit. The East Ridge deposit consists of two tabular lenses and will be mined using DAF with cemented waste rock backfill for support.

 

The groundwater flow model developed for the Santa Cruz Project shows that with an active dewatering scenario of pumping from the surface approximately 3,000 gpm for the first 2 years of LoM that the annual average residual passive inflows for the first 10 years of the mine are at or below 12,000 gpm. From year 11 through 25 of LoM, the residual passive inflows range from approximately 15,000 to 18,000 gpm.

 

Optimizations were run issuing various cut-off grades to identify higher grade areas and to understand the sensitivity of the deposit to cut-off grade.

 

The mine will be accessed by dual decline drifts from surface, with one drift serving as the main access and the other as a railveyor drift for material handling. Mineralization is transported from stopes via loader to an ore pass system and then to surface by the railveyor. Main intake and exhaust raises will be developed with conventional shaft sinking methods to provide air to the mine workings. The mine will target a combined production of 15,000 t/d from Santa Cruz and East Ridge.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 425

 

Portal boxcut is assumed to start in 2026. Decline and railveyor activities begin in 2027 through to 2028 to access the top portion of the mine. Decline and railveyor resumes in 2033 to access the bottom of the mine. Stoping begins in 2029 with a 1 -year ramp-up period until the mine and plant are operating at full capacity. The currently defined mine life is approximately 3 years of construction and 20 years of production.

 

22.5Metallurgy and Processing

 

Investigating heap leaching of Exotic, Oxide and Chalcocite mineral domains. The test program for heap leaching is in progress and is reported as such in section 10. Some early results are described below. Column leach testing will complete in the fourth quarter of 2023.

 

22.6Project Infrastructure

 

As the Santa Cruz Project is situated in close proximity to Casa Grande, an existing city in Arizona with development and industry, the Project infrastructure road access, rail access, access to ports and smelters, the supply of grid power, and the availability of water for operations for the Santa Cruz Project is well situated.

 

Power consumption will average 450,000 MW per year over the LoM. Power can initially be provided to the site by grid power from a 69kV transmission line operated by Pinal County ED3. The nearest substation to the Project is 5 km from the current location for the main Santa Cruz mine substation. The Project will ultimately replace grid power with renewable power from solar and other sources that IE is investigating now. IE envisions an overall split of 70% renewable power and 30% grid power when the project reaches maturity.

 

There appears to be a large water surplus at the Santa Cruz Project due the amount of water that must be pumped to dewater the underground ahead of and during mining operations. The supply of water from dewatering and a smaller component from passive water inflows averages approximately 3,040 m3 per hour over the LoM while water consumption averages 400 m3 per hour. The surplus of water can be distributed to local stakeholders for use.

 

In KCB’s opinion, the TSF design approach is viable and appropriate for this stage of design. KCB has identified several key risks that could potentially impact the TSF design approach, which should be investigated in future design stages:

 

No site-specific information is currently available in the TSF footprint to characterize foundation conditions for design. For this design, KCB has assumed conditions based on surficial geology maps, surface observations and subsurface data from other areas of the Project site. Unfavorable foundation conditions may be identified that influence design.

Geotechnical and geochemical testing on tailings is limited at this stage. The limited testing represents uncertainty related to geotechnical properties (e.g., tailings strength; beach angles) and geochemical management requirements. KCB elected to include a low-permeability liner in the TSF design to manage uncertainties around geochemical characterization.

The TSF could be impacted by significant flood events (the footprint is within the 1 in 500-yr flood plain and borders the 1 in 100-yr flood plain). Embankment erosion protection is included in the design; however, sizing and extent of protection is not based on site-specific flood mapping.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 426

 

The identified embankment fill borrow area is located within the 1 in 100-yr return period floodplain, and conceptually will be developed as a pit. Although the regional groundwater table is understood to be well below surface (>125 m) on the site, subsurface conditions in this area are not well understood. Flooding or groundwater rise to the level of the pit would impact the borrow pit and borrow operations.

KCB has assumed that all engineered fills except riprap will be sourced from on-site borrow areas; however, borrow areas have not been characterized to confirm suitability. Fill zones with tighter constraints (e.g., select fill for the perimeter embankment liner corridor; low-permeability fill for the low-permeability layer; clean sand and gravel for the above-liner drainage layer) may require significant processing (e.g., screening; washing) if on-site sources are used.

Wind-blown tailings or construction materials could impact and exceed air quality standards if areas of the impoundment or embankment are left unmitigated. At this design stage, KCB assume that dusting can be controlled through beach wetting, compaction of the embankment fill and progressive placement of embankment slope closure cover/armoring, or use of temporary dust management alternatives prior to placement of the closure cover.

 

Recommended studies for to address the key uncertainties/risks in the future design stages are presented in Section 23.4.3.

 

22.7Environmental, Closure, and Permitting

 

The Project is located on private land and permitting is primarily with the State of Arizona, Pinal County, and City of Casa Grande. The ability to operate on private land has the potential to reduce lengthy permitting timelines that result from federal permitting processes.

 

Baseline studies are underway for resources of concern and studies will continue as the Project develops. There are no known occurrences of federally listed threatened and endangered species and there are no planned impacts to potential federally regulated waters of the US. Portions of the Project site is a known nesting area for burrowing owls protected under the Migratory Bird Treaty Act and US Fish and Wildlife beneficial practices to avoid and minimize impacts to birds have been and will continue to be implemented as the Project develops.

 

The utilization of a renewable microgrid will allow the Santa Cruz Project to produce copper with one of the industry's lowest carbon intensities. Such intensities highlight IE 's commitment to implementing cutting-edge mining techniques, conserving energy, and utilizing renewable energy.

 

Aside from the pending reclamation plan for exploration activities at the site, IE has no current obligations to tender post mining performance or reclamation bonds for the Project. Once the facility achieves the level of design necessary to advance to mine development and operation, IE will need to submit and gain approval of an ADEQ-approved APP and an ASMI-approved Plan. The closure approach and related closure cost estimates must be submitted following approval and before facility construction and operation.

 

IE plans to create an all-encompassing environmental, social, and governance framework designed to effectively address any community concerns and ensure that the Santa Cruz Project operates in a socially responsible manner.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 427

 

22.8Project Economics

 

The Santa Cruz Project consists of an underground mine and processing facility producing both copper concentrate and copper cathode. The operation is expected to have a 20-year mine life. Under the forward-looking assumptions modeled and documented in this report, the operation is forecast to generate positive cash flow. This estimated cash flow is inherently forward-looking and dependent upon numerous assumptions and forecasts, such as macroeconomic conditions, mine plans and operating strategy, that are subject to change.

 

This assessment is preliminary in nature and is based on mineral resources. Unlike mineral reserves, mineral resources do not have demonstrated economic viability. This assessment also includes inferred mineral resources that are considered too speculative geologically to have modifying factors applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that this economic assessment will be realized.

 

The economic model is based on mine plans that were prepared as outlined in previous sections. Inferred resources account for approximately 21% of the tonnage contained within the mine plan. The economic results of the Project both without inferred resources and including inferred resources are presented within this section. However, the removal of the inferred material from the mine plan is a gross adjustment and no recalculation of fixed capital and operating costs has been completed for the scenario without inferred mineral resources.

 

The results indicate that, at a copper price of US$3.80/lb, the Project without inferred material returns an after-tax NPV at 8% of US$0.5 billion calculated from the start of construction, an after tax IRR of 14% and a payback period from the start of construction of 10 years. When the inferred material is included in the economic analysis, the after tax NPV @ 8% increases to US$1.3 billion, the after tax IRR increases to 23% and the payback period decreases to 7 years from the start of construction.

 

The sensitivity analysis performed for this report indicates that the operation’s NPV is most sensitive to the classification of material, the commodity price received, processing plant performance and variations in the grade of ore mined.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 428

 

23Recommendations

 

The recommended program is for the company to complete a preliminary feasibility level (PFS) Technical Report Summary. The work program required to complete a PFS will consist of associated infill and exploration drilling, analytical and metallurgical test work, hydrogeological and geotechnical drilling, geological modeling, mine planning, and environmental baseline studies to support permitting efforts.

 

23.1Resources and Reserves

 

To advance the Project to a PFS level, Nordmin recommends that infill drilling is performed and that drill results are incorporated into an updated resource model that would allow for the Indicated Mineral Resource to be developed into an initial Probable Mineral Reserve with a focus on the initial 5 years of production. Drilling should be targeted to continue to upgrade Inferred Mineral Resources to Indicated Mineral Resources.

 

Additional drilling is expected to target an:

 

The Santa Cruz deposit high-grade exotic copper domain.

The Southern East Ridge oxide domain.

The Texaco deposit to the south (Texaco Ridge).

Primary Domains, that are not mined or processed in this Initial Assessment.

 

Subsequent to a new resource model, engineering work should be completed to a PFS level of study which will provide reserves for the Project.

 

23.2Mining Methods

 

SRK recommends exploring different mining orientations for the Santa Cruz LHS. Currently the Santa Cruz deposit is mining in a transverse orientation. There are areas that require long ore drives to access. Exploring different orientations can potentially lead to shorter ore drives and consequently shorter hauls to the ore passes.

 

SRK recommends optimizing the stope size when additional geotechnical information is available. Larger stopes allow for more efficient mining and lower operating costs.

 

SRK recommends evaluating recovering the sill pillar between the upper and lower blocks. The sill pillar is mineralized and it is left in-situ in the current mine plan.

 

23.2.1Geotechnical Recommendations

 

To advance the geotechnical understanding of the Project to a PFS level of study the following investigations are recommended:

 

Incorporate additional drill data to further characterize rock quality domains, rock strengths, and geological structure. East Ridge and Texaco should be targeted for additional drilling.

Update the geotechnical block model with additional drill data and lithology interpretation.

Update all stability analyses using new rock characterization data. This includes stope optimization studies and sill pillar recovery techniques.

Continue exploration drilling along potential decline routes to improve decline placement within better rock qualities.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 429

 

Conduct in-situ stress measurements to better understand the current stress field at site. These learnings can be applied to stability analyses and used in numerical modeling.

Conduct numerical modeling of the mine sequence to better understand redistributions of mining induced stresses which could be detrimental to stability.

An underhand DAF method should be considered for mining at East Ridge and the Exotics at Santa Cruz. An underhand method might allow wider DAF spans but would require additional cement binder and a higher minimum compressive strength requirement.

A study should be conducted to evaluate whether mine waste aggregate is suitable for CRF.

 

23.2.2Hydrogeology

 

To advance the understanding of the site hydrogeology to the PFS stage, the following investigations are recommended:

 

Additional characterization of the conglomerates and non-mineralized Oracle Granite around the proposed Decline.

Additional characterization of the variability of hydraulic parameters of the mineralized Oracle Granite, along with the porphyry and diabase intrusions, around the Santa Cruz, East Ridge, and Texaco Deposits.

Characterization of the hydraulic parameters of the conglomerate within the Exotics at the Santa Cruz Deposit.

Hydrogeological characterization of the impact of faulting on groundwater movement.

Installation of monitoring wells to collect baseline groundwater data.

 

23.2.3Ventilation

 

The development and specification of the ventilation system will be critical to the success of the Project in that the mining zones are located in an area of elevated ground/water temperatures. It is recommended that a series of staged ventilation and thermal models be developed to simulate the ventilation system and predict the climatic temperatures in the working areas. The refinement of the ventilation system through proper modeling will directly impact the timing of the ventilation infrastructure and annual electric power consumption totals.

 

23.3Mineral Processing

 

It is recommended to conduct PFS level studies of both the preferred mill processing system with a conventional slurry type tailings storage facility and cemented paste backfill, and the potentially less costly heap leach processing system. Both mineral process testing studies would focus on geometallurgy and deposit variability regarding economic copper recovery and recovery of other economic by-products, such as molybdenite concentrate.

 

The high-level scope of the mill processing PFS level study would include:

 

Geometallurgy and variability sample selection, preparation and characterization

Comminution studies (SAG Power Index, JK Tech’s Drop Weight Test, High-Pressure Grinding Rolls, Bond Ball Mill Work Index, Artificial Intelligence) including leach residue and rougher concentrate regrind optimization

Leach – Float studies: kinetic bottle roll leach tests followed by rougher flotation and cleaner flotation testing. Use qualitative testing to evaluate settling and filtration characteristics of pre-leach, leach residue and tailings. Evaluate smelter penalty elements

 

September 2023

SEC Technical Report Summary – Santa CruzPage 430

 

Locked cycle flotation testing on geometallurgical units determined from test program

Neutralization testing of acidic leach residue

Solvent extraction testing of PLS samples of various grades and contaminant levels at copper extractant manufacturer

Liquid-solid separation testing on geometallurgical units: pre-leach, leach residue, tailings, rougher concentrate and cleaner concentrate

Evaluate new flotation technologies

Develop recovery formulas for agitated leaching and flotation for each geometallurgical unit

Examine alternative flow sheets

Process vessel materials of construction corrosion testing

Cemented paste backfill testing with tailings

Geotechnical testing of tailings

Geochemical testing of tailings

 

The high-level scope of the heap leach processing PFS level study would include:

 

Geometallurgy and variability sample selection, preparation and characterization

Crushing study

Column leach study

Ferric iron generation column leach study

PLS solvent extraction isotherm testing

Geotechnical study of heap leach material

Geochemical study of heap leach residue and solution

Cemented paste backfill testing with materials locally available

 

23.4Infrastructure

 

23.4.1Power

 

The Project needs to secure grid power supply in order to complete development and commence operations. IE must continue its discussions with ED3, the local power utility, to investigate the conditions, costs for connection and system upgrades, and timeframe to connect to grid power from the local ED3 substation nearest the Santa Cruz property. Third party utility consultants can be employed to speak with ED3 on behalf of IE, and also investigate the possibilities with Salt River Project (SRP) and Public Service of Arizona (APS) for the supply of power from their nearby transmission lines.

 

IE also should continue its investigations into renewable power options for the Project to develop costs and timelines for installing solar and other green power generating facilities on or near the site.

 

23.4.2Water

 

IE will continue to evaluate the quality of groundwater to model the total dissolved solids and constituents in groundwater over time. The need to distribute water to agricultural and other stakeholders is dependent on meeting water quality standards for those uses.

 

IE will commence stakeholder engagement in concert with permitting activities to determine the best path forward for distributing or re-injecting excess groundwater.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 431

 

23.4.3Tailings Storage

 

KCB recommend the following key studies to advance the TSF design:

 

Conduct a tailings alternatives assessment following a multiple accounts analysis (MAA) framework. The alternatives assessment must consider technical, environmental, and social objectives, and engage a range of project stakeholders.

Conduct a site investigation program to evaluate the geotechnical, hydrogeological and geochemical properties of the TSF foundation, and suitability of potential borrow sources. The investigation should comprise drilling, test pitting, geophysics, in-situ hydrogeological testing, sampling and associated laboratory testing.

Perform additional test work (geotechnical, rheological and geochemical) on the tailings. Geochemical testing should include static and kinetic testing to understand long-term acid rock drainage and metal leaching potential, to inform geochemical management strategy.

Conduct site-specific flood-routing modeling to assess TSF and borrow area flood risk.

Perform a TSF staging assessment and review embankment design approach. This assessment should evaluate beach wetting as a viable approach for dust suppression and serve as key input to the TSF water balance.

Develop a TSF water balance as an input to the site-wide water balance. If warranted, investigate TSF configurations with smaller impoundment footprints to limit evaporation loss.

Evaluate the design of the TSF liner system based on modeling and consider changes to seepage management strategy based on findings of the tailings characterization. If an impoundment drainage layer is required, explore alternatives to running outlet pipes below the TSF embankment.

Consider tailings processing methods (e.g., filtration, cycloning) to produce construction materials and offset borrow requirements.

Conduct a site-specific seismic hazard assessment.

 

23.5Environmental and Permitting

 

Recommendations for environmental and permitting would include the following:

 

Continue environmental baseline data collection to support major local county and state permitting programs.

Continue permitting activities and agency engagement for Pinal County Class II air permit, City of Casa Grande General Plan amendment and zoning changes, Arizona Department of Environmental Quality Aquifer Protection and Reclaim Water Discharge permits, and Arizona Department of Water Resources dewatering permit.

As the facility engineering progresses, advance the closure and reclamation design and engage Arizona State Mining Inspector to obtain an approved Plan.

Develop and implement a community working group to keep local stakeholders informed about the Project’s potential economic and community benefits, as well as the Company’s commitment to safety and the environment.

 

23.6Recommended Work Program Costs

 

Table 23-1 summarizes the costs for recommended work programs.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 432

 

Table 23-1: Summary of Costs for Recommended Work

 

Discipline Program Description Cost (US$)
Drilling Resource Infill, Hydrogeology, Geotechnical, Geometallurgical Variability 29.2 million
Engineering Studies Geotechnical, Mining Optimization, Hydrogeology, Ventilation, Power, Process Flowsheet, Tailings Storage 16.1 million
Laboratory Testing Geotechnical, Backfill, Water Quality, Metallurgical Recovery, Geometallurgical Variability 5.6 million
Pilot Plant Metallurgical Flowsheet and Recovery 3.3 million
Permitting Permitting 3.0 million
PFS Report PFS Reporting and QP Work for all disciplines 5.5 million
Total US$   $62.7 million

 

Source: SRK, 2023

 

September 2023

SEC Technical Report Summary – Santa CruzPage 433

 

24References

 

Anderson, T. H., (2015). Jurassic (170–150 Ma) basins: The tracks of a continental-scale fault, the Mexico-Alaska megashear, from the Gulf of Mexico to Alaska.

 

Arizona Department of Environmental Quality (ADEQ). 2005. “Arizona Mining Guidance Manual Best Available Demonstrated Control Technology (BADCT)”.

 

Asmus, B., (2013). Gossan or the iron cap. Retrieved from https://en.archaeometallurgie.de/gossan-iron-cap/

 

Balla, J. C., (1972). The relationship of Laramide stocks to regional structure in central Arizona.

 

Banks, N. G., Cornwall, H. R., Silberman, M. L., Creasey, S. C., & Marvin, R. F.,(1972). Chronology of Intrusion and Ore Deposition at Ray, Arizona; Part I, K-Ar Ages. Economic Geology, 67(7), 864-878.

 

Berger, B., Ayuso, R., Wynn, J., & Seal, R., (2008). Preliminary Model of Porphyry Copper Deposits. USGS Open-File Report 2008-1321. Retrieved from http://pubs.er.usgs.gov/usgspubs/ofr/ofr20081321

 

Call & Nicholas Inc. (CNI). 2022. “Decline Characterization and Support Estimation”. December 14.

 

Canadian Dam Association (CDA). 2019. “Technical Bulletin: Application of Dam Safety Guidelines to Mining Dams.”

 

Chávez, W. X., (2021). Weathering of Copper Deposits and Copper Mobility: Mineralogy, Geochemical Stratigraphy, and Exploration Implications. SEG Discovery, (126), 16-27.

 

Dilles, John H., et al., (2000). Overview of the Yerington porphyry copper district: Magmatic to nonmagmatic sources of hydrothermal fluids, their flow paths, alteration affects on rocks, and Cu-Mo-Fe-Au ores.

 

Cook III, S. S. (1994)., The geologic history of supergene enrichment in the porphyry copper deposits of southwestern North America (Doctoral dissertation, The University of Arizona).

 

Cummings, R. B., & Titley, S. R., (1982). Geology of the Sacaton porphyry copper deposit. Advances in Geology of the Porphyry Copper Deposits, Southwest North America, 507-521.

 

eBird, (2023). EBird: An online database of bird distribution and abundance [web application]. eBird, Cornell Lab of Ornithology, Ithaca, New York. Available: http://www.ebird.org. (Accessed: August 1, 2023).

 

Federal Emergency Management Agency (FEMA). 2007. Map number 04021C1150E and 04021C1175E, effective on 12/4/2007. Accessed June 28, 2023. https://msc.fema.gov/portal/home

 

Fernández-Mort, A., & Riquelme, R. A.-Z., (2018). genetic model based on evapoconcentration for sediment-hosted exotic-copper mineralization in arid environments: the case of the El Tesoro Central copper deposit, Atacama Desert, Chile. Miner Deposita, 53, 775-795. Retrieved from https://doi.org/10.1007/s00126-017-0780-2

 

Foster, Michael S., Ron Ryden, and Cara Bellavia, (2006). An Archaeological Evaluation of the Legends Project Area, West of the Town of Casa Grande, Pinal County, Arizona. Cultural Resources Report 9596-094. SWCA Environmental Consultants, Phoenix, Arizona.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 434

 

Global Tailings Review (GTR). 2020. “Global Industry Standard on Tailings Management” (GISTM). August.

 

Harlan, S. S., (1993). Paleomagnetism of Middle Proterozoic diabase sheets from central Arizona. Canadian Journal of Earth Sciences, 30(7), 1415-1426.

 

Harshbarger and Associates, (1978a). Analysis of aquifer test data and preliminary dewater design, Casa Grande West, Pinal County, Arizona. Interim report prepared for Casa Grande Copper Company (IR-A550-78-1). January 12.

 

Harshbarger and Associates, (1978b). Analysis of Aquifer Test TW-2 and Modified Dewater Design, Casa Grande West, Pinal County, Arizona (Report R-A550-78-2). Prepared for Casa Grande Copper Company. April 20.

 

INTERA Incorporated (INTERA), (2023). Hydrogeology and Groundwater Modeling for the Santa Cruz Project. Prepared for Ivanhoe Electric. August 2023.

 

Klawon J., P. Pearthree, S. Skotnicki, C. and Ferguson. 1998. “Geology and Geologic Hazards of the Casa Grande Area, Pinal County, Arizona. Arizona Geological Survey Open-File Report 98-23”. September.

 

Kreis, (1978). A Structural and Related Mineral Reinterpretation of the Santa Cruz Horst Block. Internal report.

 

Kreis, H.G., (1982). Geology and copper reserves of the lands area, Santa Cruz project, Pinal County, Arizona. Prepared for ASARCO Incorporated. August 27.

 

Leveille, R. A., & Stegen, R. J., (2012). The southwestern North America porphyry copper province.

 

Lipske, J. L., & Dilles, J. H., (2000). Advanced argillic and sericitic alteration in the subvolcanic environment of the Yerington porphyry copper system, Buckskin Range, Nevada.

 

Liu, S., Nelson, K., Yunker, D., Hipke, W., and Corkhill, F., (2014). Regional Groundwater Flow Model of the Pinal Active Management Area, Arizona: Model Update and Calibration (Model Report No. 26). Arizona Department of Water Resources, Hydrology Division. February.

 

Lowell, J., & Guilbert, J., (1970). Lateral and vertical alteration-mineralization zoning in porphyry ore deposits. Economic Geology, 65, 373-408.

 

Middleton, Sherri M., (2022). A Class III Cultural Resources Assessment of 20 Archaeological Sites on Private Land In Support of the Santa Cruz Copper Project Near Casa Grande, Arizona, WestLand Engineering & Environmental Services, November 3, 2022.

 

Montgomery & Associates (formerly Errol L. Montgomery & Associates, Incorporated), (1989). Well construction, development, and pumping test results for hydrogeological characterization well (D-6-4)13abd[HC-1], Santa Cruz In Situ Copper Mining Research Project, Pinal County, Arizona. August 10.

 

Montgomery & Associates (formerly Errol L. Montgomery & Associates, Incorporated), (1990a). Results of 48-hour pumping test at on-site groundwater monitor well (D-6-4)13abc1[SM-1], January 1990, Santa Cruz In Situ Copper Mining Research Project, Pinal County, Arizona. Prepared for Santa Cruz Joint Venture.

 

Montgomery & Associates (formerly Errol L. Montgomery & Associates, Incorporated), (1990b). Well construction, development, and pumping test results for process water well (D-6-4)13bcb[PW-1], Santa Cruz In Situ Copper Mining Research Project, Pinal County, Arizona. Prepared for Santa Cruz Joint Venture.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 435

 

Montgomery & Associates (formerly Errol L. Montgomery & Associates, Incorporated), (1991). Analysis of lower copper oxide zone hydraulic testing at injection and recovery wells T-1, T-2, T-3, T-4, and T-5, June 1990 and January 1991, prior to tracer test, Santa Cruz In Situ Copper Mining Research Project, Pinal County, Arizona. February 22.

 

Montgomery & Associates (formerly Errol L. Montgomery & Associates, Incorporated), (1992a). Phase I & II Technical Report, Santa Cruz In Situ Copper Mining Research Project, Pinal County, Arizona. Prepared for Santa Cruz Joint Venture. February 24.

 

Montgomery & Associates (formerly Errol L. Montgomery & Associates, Incorporated), (1992b). Hydrogeologic Conditions and Groundwater Related Permitting, Santa Cruz In Situ Copper Mining Research Project, Pinal County, Arizona. By Charles F. Barter.

 

Montgomery & Associates (formerly Errol L. Montgomery & Associates, Incorporated), (1992c). Aquifer protection permit application for in situ mining test, Santa Cruz In Situ Mining Research Project, Pinal County, Arizona. Prepared for Santa Cruz Joint Venture. May 22. 3 volumes.

 

Montgomery & Associates (formerly Errol L. Montgomery & Associates, Incorporated), (1993). Analysis of Groundwater Control Operations for Prefeasibility Study for Block Cave Mining, Santa Cruz Deposit, Pinal County, Arizona. Prepared for Freeport Mining Company. October 27.

 

Montgomery & Associates (formerly Errol L. Montgomery & Associates, Incorporated), (1995). Results of 12-Hour Pumping Test at Test Well T-3, May 1995, Prior to In Situ Mining Test, Santa Cruz In Situ Copper Mining Research Project, Pinal County, Arizona. Report. September 20.

 

Montgomery & Associates (formerly Errol L. Montgomery & Associates, Incorporated), (1997). Results of Drilling, Construction, and Testing Hydrogeologic Characterization Wells HC-2, HC-3, HC-4, and HC-5 Santa Cruz In Situ Copper Mining Project, Pinal County, Arizona (Volume I). Final Report. August 14.

 

Montgomery & Associates (formerly Errol L. Montgomery & Associates, Incorporated), (1998). Compilation of research investigation and results for in situ mining conducted at Santa Cruz test site, February 12, 1996 through February 15, 1998, Santa Cruz In Situ Copper Mining Research Project, Pinal County, Arizona. September 30.

 

Montgomery & Associates. 2023. Results of 2022 and 2023 Packer Testing, Santa Cruz – Pinal County, AZ (Project #: 3457.07). Technical Memorandum. Natalie Speaks, Brady Nock, and Colin Kikuchi. June 1.

 

Mote, T., Becker, T., Renne, P., & Brimhall, G., (2001). Chronology of Exotic Mineralization at El Salvador, Chile, by 40Ar/39Ar Dating of Copper Wad and Supergene Alunite. Economic Geology, 351-366. doi:10.2113/96.2.351.

 

Mountain States Engineering (1980). ASARCO Study, Section 5.3.2.

 

Münchmeyer, C., (1998). Exotic Deposits - Products of Lateral Migration of Supergene Solutions from Porphyry Copper Deposits. Andean Copper Deposits: New Discoveries, Mineralization, Styles and Metallogeny. Francisco Camus, Richard M. Sillitoe, Richard Petersen.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 436

 

Nelson, P.H., (1991). Geophysical Logs from a Copper Oxide Deposit, Santa Cruz Project, Casa Grande, Arizona (USGS Open-File Report 91-357).

 

Tosdal, R. M., & Wooden, J. L., (2015). Construction of the Jurassic magmatic arc, southeast California and southwest Arizona. Geological Society of America Special Papers, 513, 189-221.

 

Scarborough, R., & Meader, N., (1989). Geologic Map of the Northern Plomosa Mountains, Yuma [La Paz] County, Arizona.

 

Sell, J.D., (1976). A Structural and Related Mineral Reinterpretation of the Santa Cruz Horst Block - Santa Cruz Project Studies, Pinal County, Arizona, internal report from Sell to F.T. Greybeal.

 

Sillitoe, R. H., (2010). Porphyry Copper Systems. Economic Geology. Retrieved from https://doi.org/10.2113/gsecongeo.105.1.3

 

USGS (2023a). Mineral Industry Surveys, Copper in April 2023,July 2023

 

USGS (2023b). Copper, prepared by Daniel M. Flanagan, dflanagan@usgs.gov

 

Vikre, P., Graybeal, F., & Koutz, F., (2014). Concealed Basalt-Matrix Diatremes with Cu-Au-Ag-(Mo)-Mineralized Xenoliths, Santa Cruz Porphyry Cu-(Mo) System, Pinal County, Arizona. Economic Geology. doi:10.2113/econgeo.109.5.1271

 

Watts, A. B., Karner, G., & Steckler, M. S., (1982). Lithospheric flexure and the evolution of sedimentary basins. Philosophical Transactions of the Royal Society of London. Series A, Mathematical and Physical Sciences, 305(1489), 249-281.

 

Watts Griffis McQuat, Evoy, E.F., (1982). Casa Grande Copper Company Ore Reserve Study for the Hanna Mining Company.

 

WestLand. WestLand Engineering & Environmental Services, (2022a). Biological Evaluation for the Texaco Exploration Project in Casa Grande, Arizona, March 18,2022.

 

WestLand. WestLand Engineering & Environmental Services, (2022b). OHWM Evaluation: Santa Cruz Exploration Project, March 21, 2022 (rev).

 

WestLand Engineering & Environmental Services, (2023). Draft Ivanhoe Electric Preconstruction Biological Resources Surveys Summary Report, March 1, 2023.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 437

 

25Reliance on Information Provided by the Registrant

 

The Consultant’s opinion contained herein is based on information provided to the Consultants by IE throughout the course of the investigations. Table 25 1 of this section of the Technical Report Summary will:

 

(i) Identify the categories of information provided by the registrant;

 

(ii) Identify the particular portions of the Technical Report Summary that were prepared in reliance on information provided by the registrant pursuant to Subpart 1302 (f)(1), and the extent of that reliance; and

 

(iii) Disclose why the qualified person considers it reasonable to rely upon the registrant for any of the information specified in Subpart 1302 (f)(1).

 

Table 25-1: Reliance on Information Provided by the Registrant

 

Category Report Item/ Portion Portion of
Technical Report
Summary
Disclose why the Qualified
Person considers it reasonable
to rely upon the registrant
Claims List 3 3.3 Mineral Title IE provided SRK with a current listing of claims. The information was sourced from IE’s Land Manager and is backed by the The Title Opinion and Reliance letter by Marian Lalonde dated August 30, 2023, of Fennemore Law, Tucson, Arizona
Market Plans 16 Table Text IE has indicated that the product from the mine will be sold regionally and that the cathode product will be sold at mine gate.
Discount Rates 19 19 Economic Analysis IE provided SRK with discount rates for the economic analysis. The selected discount rate is in-line with SRK’s experience on other projects.
Tax rates and government royalties 19 19 Economic Analysis SRK was provided with income and applicable property tax estimates by IE for application within the model. These rates are in line with SRK’s understanding of the tax regime at the Project location.

 

September 2023

SEC Technical Report Summary – Santa CruzPage 438

 

Appendices

 

September 2023

SEC Technical Report Summary – Santa CruzPage 439

 

Appendix A: Property and Rights

 

September 2023

SEC Technical Report Summary – Santa CruzPage 440

 

Owner Claim Name Serial Number Disposition Case Type Last Assmt Year Location Date Acreage Meridian Township Range Section Subdiv Active Serial Count Lead Case Serial Number
Mesa Cobre Holding Corporation SCX 1 AMC460163 ACTIVE LODE 2020 2/26/2020 20.66 14 0060S 0040E 003 NW,SW AMC460163 AMC460163
Mesa Cobre Holding Corporation SCX 2 AMC460164 ACTIVE LODE 2020 2/26/2020 20.66 14 0060S 0040E 003 NW,SW AMC460164 AMC460163
Mesa Cobre Holding Corporation SCX 3 AMC460165 ACTIVE LODE 2020 2/26/2020 20.66 14 0060S 0040E 003 NW,SW AMC460165 AMC460163
Mesa Cobre Holding Corporation SCX 4 AMC460166 ACTIVE LODE 2020 2/26/2020 20.66 14 0060S 0040E 003 NW,SW AMC460166 AMC460163
Mesa Cobre Holding Corporation SCX 5 AMC460167 ACTIVE LODE 2020 2/26/2020 20.66 14 0060S 0040E 003 NE,NW,SW,SE AMC460167 AMC460163
Mesa Cobre Holding Corporation SCX 6 AMC460168 ACTIVE LODE 2020 3/1/2020 20.66 14 0060S 0040E 003 NE,SE AMC460168 AMC460163
Mesa Cobre Holding Corporation SCX 7 AMC460169 ACTIVE LODE 2020 3/1/2020 20.66 14 0060S 0040E 003 NE,SE AMC460169 AMC460163
Mesa Cobre Holding Corporation SCX 8 AMC460170 ACTIVE LODE 2020 3/1/2020 20.66 14 0060S 0040E 003 NE,SE AMC460170 AMC460163
Mesa Cobre Holding Corporation SCX 9 AMC460171 ACTIVE LODE 2020 3/1/2020 20.66 14 0060S 0040E 003 NE,SE AMC460171 AMC460163
Mesa Cobre Holding Corporation SCX 10 AMC460172 ACTIVE LODE 2020 2/26/2020 20.66 14 0060S 0040E 004 SE AMC460172 AMC460163
Mesa Cobre Holding Corporation SCX 11 AMC460173 ACTIVE LODE 2020 2/26/2020 20.66 14 0060S 0040E 003 SW,SE AMC460173 AMC460163
Mesa Cobre Holding Corporation SCX 12 AMC460174 ACTIVE LODE 2020 2/26/2020 20.66 14 0060S 0040E 003 SW AMC460174 AMC460163
Mesa Cobre Holding Corporation SCX 13 AMC460175 ACTIVE LODE 2020 2/26/2020 20.66 14 0060S 0040E 010 NE,NW AMC460175 AMC460163
Mesa Cobre Holding Corporation SCX 14 AMC460176 ACTIVE LODE 2020 3/1/2020 20.66 14 0060S 0040E 003 SE AMC460176 AMC460163
Mesa Cobre Holding Corporation SCX 15 AMC460177 ACTIVE LODE 2020 3/1/2020 12.4 14 0060S 0040E 003 SE AMC460177 AMC460163
Mesa Cobre Holding Corporation SCX 16 AMC460178 ACTIVE LODE 2020 3/1/2020 20.66 14 0060S 0040E 003 SE AMC460178 AMC460163
Mesa Cobre Holding Corporation SCX 17 AMC460179 ACTIVE LODE 2020 3/1/2020 12.4 14 0060S 0040E 002 SW AMC460179 AMC460163
Mesa Cobre Holding Corporation SCX 18 AMC460180 ACTIVE LODE 2020 2/26/2020 20.66 14 0060S 0040E 034 SE AMC460180 AMC460163
Mesa Cobre Holding Corporation SCX 19 AMC460181 ACTIVE LODE 2020 2/26/2020 20.66 14 0070S 0040E 002 NE,SE AMC460181 AMC460163
Mesa Cobre Holding Corporation SCX 20 AMC460182 ACTIVE LODE 2020 2/26/2020 20.66 14 0070S 0040E 002 SE AMC460182 AMC460163
Mesa Cobre Holding Corporation SCX 21 AMC460183 ACTIVE LODE 2020 2/26/2020 20.66 14 0070S 0040E 001 SW AMC460183 AMC460163
Mesa Cobre Holding Corporation SCX 22 AMC460184 ACTIVE LODE 2020 2/26/2020 20.66 14 0070S 0040E 001 NW,SW AMC460184 AMC460163
Mesa Cobre Holding Corporation SCX 23 AMC460185 ACTIVE LODE 2020 2/26/2020 12.4 14 0070S 0040E 001 SW AMC460185 AMC460163
Mesa Cobre Holding Corporation SCX 24 AMC460186 ACTIVE LODE 2020 2/26/2020 20.66 14 0070S 0040E 001 SW,SE AMC460186 AMC460163
Mesa Cobre Holding Corporation SCX 25 AMC460187 ACTIVE LODE 2020 2/26/2020 12.4 14 0070S 0040E 001 SW,SE AMC460187 AMC460163
Mesa Cobre Holding Corporation SCX 26 AMC460188 ACTIVE LODE 2020 3/8/2020 20.66 14 0060S 0030E 033 NW AMC460188 AMC460163
Mesa Cobre Holding Corporation SCX 27 AMC460189 ACTIVE LODE 2020 3/8/2020 20.66 14 0060S 0030E 032 NE AMC460189 AMC460163
Mesa Cobre Holding Corporation SCX 28 AMC460190 ACTIVE LODE 2020 3/8/2020 20.66 14 0060S 0030E 033 NW AMC460190 AMC460163
Mesa Cobre Holding Corporation SCX 29 AMC460191 ACTIVE LODE 2020 3/8/2020 20.66 14 0060S 0030E 033 NW AMC460191 AMC460163
Mesa Cobre Holding Corporation SCX 30 AMC460192 ACTIVE LODE 2020 3/8/2020 20.66 14 0060S 0030E 032 NE,SE AMC460192 AMC460163
Mesa Cobre Holding Corporation SCX 31 AMC460193 ACTIVE LODE 2020 3/8/2020 20.66 14 0060S 0030E 033 NW AMC460193 AMC460163
Mesa Cobre Holding Corporation SCX 32 AMC460194 ACTIVE LODE 2020 3/8/2020 20.66 14 0060S 0030E 033 NW,SW AMC460194 AMC460163
Mesa Cobre Holding Corporation SCX 33 AMC460195 ACTIVE LODE 2020 3/8/2020 20.66 14 0060S 0030E 033 NE,NW AMC460195 AMC460163
Mesa Cobre Holding Corporation SCX 34 AMC460196 ACTIVE LODE 2020 3/8/2020 20.66 14 0060S 0030E 033 NE,NW,SW,SE AMC460196 AMC460163
Mesa Cobre Holding Corporation SCX 35 AMC460197 ACTIVE LODE 2020 3/9/2020 20.66 14 0060S 0030E 032 SE AMC460197 AMC460163
Mesa Cobre Holding Corporation SCX 36 AMC460198 ACTIVE LODE 2020 3/9/2020 20.66 14 0070S 0030E 003 NW AMC460198 AMC460163
Mesa Cobre Holding Corporation SCX 37 AMC460199 ACTIVE LODE 2020 3/9/2020 20.66 14 0060S 0030E 033 SW AMC460199 AMC460163
Mesa Cobre Holding Corporation SCX 38 AMC460200 ACTIVE LODE 2020 3/9/2020 20.66 14 0070S 0030E 003 NW AMC460200 AMC460163
Mesa Cobre Holding Corporation SCX 39 AMC460201 ACTIVE LODE 2020 3/9/2020 20.66 14 0060S 0030E 033 SW AMC460201 AMC460163
Mesa Cobre Holding Corporation SCX 40 AMC460202 ACTIVE LODE 2020 3/9/2020 20.66 14 0070S 0030E 003 NW AMC460202 AMC460163
Mesa Cobre Holding Corporation SCX 41 AMC460203 ACTIVE LODE 2020 3/9/2020 20.66 14 0060S 0030E 033 SW AMC460203 AMC460163
Mesa Cobre Holding Corporation SCX 42 AMC460204 ACTIVE LODE 2020 3/9/2020 20.66 14 0060S 0030E 033 SW AMC460204 AMC460163
Mesa Cobre Holding Corporation SCX 43 AMC460205 ACTIVE LODE 2020 3/9/2020 20.66 14 0060S 0030E 033 SW,SE AMC460205 AMC460163
Mesa Cobre Holding Corporation SCX 44 AMC460206 ACTIVE LODE 2020 3/9/2020 20.66 14 0070S 0030E 003 NE,NW AMC460206 AMC460163
Mesa Cobre Holding Corporation SCX 45 AMC460207 ACTIVE LODE 2020 3/9/2020 20.66 14 0060S 0030E 033 SE AMC460207 AMC460163
Mesa Cobre Holding Corporation SCX 46 AMC460208 ACTIVE LODE 2020 3/9/2020 20.66 14 0070S 0030E 003 NE AMC460208 AMC460163
Mesa Cobre Holding Corporation SCX 47 AMC460209 ACTIVE LODE 2020 3/9/2020 20.66 14 0060S 0030E 033 SE AMC460209 AMC460163
Mesa Cobre Holding Corporation SCX 48 AMC460210 ACTIVE LODE 2020 3/9/2020 20.66 14 0070S 0030E 003 NE AMC460210 AMC460163
Mesa Cobre Holding Corporation SCX 49 AMC460211 ACTIVE LODE 2020 3/9/2020 20.66 14 0060S 0030E 033 SE AMC460211 AMC460163
Mesa Cobre Holding Corporation SCX 50 AMC460212 ACTIVE LODE 2020 3/9/2020 20.66 14 0060S 0030E 033 SE AMC460212 AMC460163
Mesa Cobre Holding Corporation SCX 51 AMC460213 ACTIVE LODE 2020 3/9/2020 20.66 14 0060S 0030E 034 SW AMC460213 AMC460163
Mesa Cobre Holding Corporation SCX 52 AMC460214 ACTIVE LODE 2020 3/9/2020 20.66 14 0060S 0030E 033 SE AMC460214 AMC460163
Mesa Cobre Holding Corporation SCX 53 AMC460215 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 003 NW,SW AMC460215 AMC460163
Mesa Cobre Holding Corporation SCX 54 AMC460216 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NW AMC460216 AMC460163
Mesa Cobre Holding Corporation SCX 55 AMC460217 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 003 NW,SW AMC460217 AMC460163
Mesa Cobre Holding Corporation SCX 56 AMC460218 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NW AMC460218 AMC460163

 

September 2023

SEC Technical Report Summary – Santa CruzPage 441

 

Owner Claim Name Serial Number Disposition Case Type Last Assmt Year Location Date Acreage Meridian Township Range Section Subdiv Active Serial Count Lead Case Serial Number
Mesa Cobre Holding Corporation SCX 57 AMC460219 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 003 NW,SW AMC460219 AMC460163
Mesa Cobre Holding Corporation SCX 58 AMC460220 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NW AMC460220 AMC460163
Mesa Cobre Holding Corporation SCX 59 AMC460221 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 003 NW,SW AMC460221 AMC460163
Mesa Cobre Holding Corporation SCX 60 AMC460222 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 003 SW AMC460222 AMC460163
Mesa Cobre Holding Corporation SCX 61 AMC460223 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 003 NE,NW,SW,SE AMC460223 AMC460163
Mesa Cobre Holding Corporation SCX 62 AMC460224 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NE,NW AMC460224 AMC460163
Mesa Cobre Holding Corporation SCX 63 AMC460225 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 003 NE,SE AMC460225 AMC460163
Mesa Cobre Holding Corporation SCX 64 AMC460226 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NE AMC460226 AMC460163
Mesa Cobre Holding Corporation SCX 65 AMC460227 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0030E 003 NE,SE AMC460227 AMC460163
Mesa Cobre Holding Corporation SCX 66 AMC460228 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0030E 010 NE AMC460228 AMC460163
Mesa Cobre Holding Corporation SCX 67 AMC460229 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0030E 003 NE,SE AMC460229 AMC460163
Mesa Cobre Holding Corporation SCX 68 AMC460230 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0030E 003 SE AMC460230 AMC460163
Mesa Cobre Holding Corporation SCX 69 AMC460231 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0030E 003 NE,SE AMC460231 AMC460163
Mesa Cobre Holding Corporation SCX 70 AMC460232 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0030E 002 SW AMC460232 AMC460163
Mesa Cobre Holding Corporation SCX 71 AMC460233 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NW AMC460233 AMC460163
Mesa Cobre Holding Corporation SCX 72 AMC460234 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NW,SW AMC460234 AMC460163
Mesa Cobre Holding Corporation SCX 73 AMC460235 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NW AMC460235 AMC460163
Mesa Cobre Holding Corporation SCX 74 AMC460236 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NW,SW AMC460236 AMC460163
Mesa Cobre Holding Corporation SCX 75 AMC460237 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NW AMC460237 AMC460163
Mesa Cobre Holding Corporation SCX 76 AMC460238 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NW,SW AMC460238 AMC460163
Mesa Cobre Holding Corporation SCX 77 AMC460239 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NW AMC460239 AMC460163
Mesa Cobre Holding Corporation SCX 78 AMC460240 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NW,SW AMC460240 AMC460163
Mesa Cobre Holding Corporation SCX 79 AMC460241 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NE,NW AMC460241 AMC460163
Mesa Cobre Holding Corporation SCX 80 AMC460242 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NE,NW,SW,SE AMC460242 AMC460163
Mesa Cobre Holding Corporation SCX 81 AMC460243 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NE AMC460243 AMC460163
Mesa Cobre Holding Corporation SCX 82 AMC460244 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NE,SE AMC460244 AMC460163
Mesa Cobre Holding Corporation SCX 83 AMC460245 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NE AMC460245 AMC460163
Mesa Cobre Holding Corporation SCX 84 AMC460246 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NE,SE AMC460246 AMC460163
Mesa Cobre Holding Corporation SCX 85 AMC460247 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NE AMC460247 AMC460163
Mesa Cobre Holding Corporation SCX 86 AMC460248 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NE,SE AMC460248 AMC460163
Mesa Cobre Holding Corporation SCX 87 AMC460249 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 010 NE AMC460249 AMC460163
Mesa Cobre Holding Corporation SCX 88 AMC460250 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NW,SW AMC460250 AMC460163
Mesa Cobre Holding Corporation SCX 89 AMC460251 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NW AMC460251 AMC460163
Mesa Cobre Holding Corporation SCX 90 AMC460252 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NW,SW AMC460252 AMC460163
Mesa Cobre Holding Corporation SCX 91 AMC460253 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NW AMC460253 AMC460163
Mesa Cobre Holding Corporation SCX 92 AMC460254 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NW,SW AMC460254 AMC460163
Mesa Cobre Holding Corporation SCX 93 AMC460255 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NW AMC460255 AMC460163
Mesa Cobre Holding Corporation SCX 94 AMC460256 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NW,SW AMC460256 AMC460163
Mesa Cobre Holding Corporation SCX 95 AMC460257 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NW AMC460257 AMC460163
Mesa Cobre Holding Corporation SCX 96 AMC460258 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NW,SW AMC460258 AMC460163
Mesa Cobre Holding Corporation SCX 97 AMC460259 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NE,NW AMC460259 AMC460163
Mesa Cobre Holding Corporation SCX 98 AMC460260 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NE,NW,SW,SE AMC460260 AMC460163
Mesa Cobre Holding Corporation SCX 99 AMC460261 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NE AMC460261 AMC460163
Mesa Cobre Holding Corporation SCX 100 AMC460262 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NE,SE AMC460262 AMC460163
Mesa Cobre Holding Corporation SCX 101 AMC460263 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NE AMC460263 AMC460163
Mesa Cobre Holding Corporation SCX 102 AMC460264 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NE AMC460264 AMC460163
Mesa Cobre Holding Corporation SCX 103 AMC460265 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NE AMC460265 AMC460163
Mesa Cobre Holding Corporation SCX 104 AMC460266 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NE AMC460266 AMC460163
Mesa Cobre Holding Corporation SCX 105 AMC460267 ACTIVE LODE 2020 2/29/2020 20.66 14 0070S 0030E 011 NE,SE AMC460267 AMC460163
Mesa Cobre Holding Corporation SCX 106 AMC460268 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0040E 003 SW AMC460268 AMC460163
Mesa Cobre Holding Corporation SCX 107 AMC460269 ACTIVE LODE 2020 3/31/2020 20.66 14 0070S 0040E 010 NW AMC460269 AMC460163
Mesa Cobre Holding Corporation SCX 108 AMC460270 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0040E 010 NW AMC460270 AMC460163
Mesa Cobre Holding Corporation SCX 109 AMC460271 ACTIVE LODE 2020 3/31/2020 20.66 14 0070S 0040E 010 NW AMC460271 AMC460163
Mesa Cobre Holding Corporation SCX 110 AMC460272 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0040E 003 SW AMC460272 AMC460163
Mesa Cobre Holding Corporation SCX 111 AMC460273 ACTIVE LODE 2020 3/31/2020 20.66 14 0070S 0040E 010 NW AMC460273 AMC460163
Mesa Cobre Holding Corporation SCX 112 AMC460274 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0040E 010 NW AMC460274 AMC460163

 

September 2023

SEC Technical Report Summary – Santa CruzPage 442

 

Owner Claim Name Serial Number Disposition Case Type Last Assmt Year Location Date Acreage Meridian Township Range Section Subdiv Active Serial Count Lead Case Serial Number
Mesa Cobre Holding Corporation SCX 113 AMC460275 ACTIVE LODE 2020 3/31/2020 20.66 14 0070S 0040E 010 NW AMC460275 AMC460163
Mesa Cobre Holding Corporation SCX 114 AMC460276 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0040E 003 SW,SE AMC460276 AMC460163
Mesa Cobre Holding Corporation SCX 118 AMC460277 ACTIVE LODE 2020 3/6/2020 18.6 14 0070S 0040E 021 SW AMC460277 AMC460163
Mesa Cobre Holding Corporation SCX 119 AMC460278 ACTIVE LODE 2020 3/6/2020 18.6 14 0070S 0040E 021 SW AMC460278 AMC460163
Mesa Cobre Holding Corporation SCX 120 AMC460279 ACTIVE LODE 2020 3/6/2020 18.6 14 0070S 0040E 020 SE AMC460279 AMC460163
Mesa Cobre Holding Corporation SCX 121 AMC460280 ACTIVE LODE 2020 3/6/2020 18.6 14 0070S 0040E 021 SW AMC460280 AMC460163
Mesa Cobre Holding Corporation SCX 122 AMC460281 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 020 SE AMC460281 AMC460163
Mesa Cobre Holding Corporation SCX 123 AMC460282 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 029 NE AMC460282 AMC460163
Mesa Cobre Holding Corporation SCX 124 AMC460283 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 029 NE AMC460283 AMC460163
Mesa Cobre Holding Corporation SCX 125 AMC460284 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 028 NW AMC460284 AMC460163
Mesa Cobre Holding Corporation SCX 126 AMC460285 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 028 NW,SW AMC460285 AMC460163
Mesa Cobre Holding Corporation SCX 127 AMC460286 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 028 SW AMC460286 AMC460163
Mesa Cobre Holding Corporation SCX 128 AMC460287 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 028 SW AMC460287 AMC460163
Mesa Cobre Holding Corporation SCX 129 AMC460288 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 028 SW AMC460288 AMC460163
Mesa Cobre Holding Corporation SCX 130 AMC460289 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 028 SW AMC460289 AMC460163
Mesa Cobre Holding Corporation SCX 131 AMC460290 ACTIVE LODE 2020 3/6/2020 9.99 14 0070S 0040E 028 NW AMC460290 AMC460163
Mesa Cobre Holding Corporation SCX 132 AMC460291 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 028 NW AMC460291 AMC460163
Mesa Cobre Holding Corporation SCX 133 AMC460292 ACTIVE LODE 2020 3/6/2020 9.99 14 0070S 0040E 028 NE,NW AMC460292 AMC460163
Mesa Cobre Holding Corporation SCX 134 AMC460293 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 028 NE,NW AMC460293 AMC460163
Mesa Cobre Holding Corporation SCX 135 AMC460294 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 028 NW,SW AMC460294 AMC460163
Mesa Cobre Holding Corporation SCX 136 AMC460295 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 028 SW AMC460295 AMC460163
Mesa Cobre Holding Corporation SCX 137 AMC460296 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 028 NE,NW,SW,SE AMC460296 AMC460163
Mesa Cobre Holding Corporation SCX 138 AMC460297 ACTIVE LODE 2020 3/6/2020 20.66 14 0070S 0040E 028 SW,SE AMC460297 AMC460163
Mesa Cobre Holding Corporation SCX 139 AMC460298 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 NW AMC460298 AMC460163
Mesa Cobre Holding Corporation SCX 140 AMC460299 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 NW,SW AMC460299 AMC460163
Mesa Cobre Holding Corporation SCX 141 AMC460300 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 NW AMC460300 AMC460163
Mesa Cobre Holding Corporation SCX 142 AMC460301 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 NW,SW AMC460301 AMC460163
Mesa Cobre Holding Corporation SCX 143 AMC460302 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 NW AMC460302 AMC460163
Mesa Cobre Holding Corporation SCX 144 AMC460303 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 NW,SW AMC460303 AMC460163
Mesa Cobre Holding Corporation SCX 145 AMC460304 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 NW AMC460304 AMC460163
Mesa Cobre Holding Corporation SCX 146 AMC460305 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 NW,SW AMC460305 AMC460163
Mesa Cobre Holding Corporation SCX 147 AMC460306 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 027 NE,NW AMC460306 AMC460163
Mesa Cobre Holding Corporation SCX 148 AMC460307 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 027 NE,NW,SW,SE AMC460307 AMC460163
Mesa Cobre Holding Corporation SCX 149 AMC460308 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 027 NE AMC460308 AMC460163
Mesa Cobre Holding Corporation SCX 150 AMC460309 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 027 NE,SE AMC460309 AMC460163
Mesa Cobre Holding Corporation SCX 151 AMC460310 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 027 NE AMC460310 AMC460163
Mesa Cobre Holding Corporation SCX 152 AMC460311 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 027 NE,SE AMC460311 AMC460163
Mesa Cobre Holding Corporation SCX 153 AMC460312 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 027 NE AMC460312 AMC460163
Mesa Cobre Holding Corporation SCX 154 AMC460313 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 027 NE,SE AMC460313 AMC460163
Mesa Cobre Holding Corporation SCX 155 AMC460314 ACTIVE LODE 2020 3/3/2020 16.7 14 0070S 0040E 026 NW AMC460314 AMC460163
Mesa Cobre Holding Corporation SCX 156 AMC460315 ACTIVE LODE 2020 3/3/2020 16.7 14 0070S 0040E 027 NE,SE AMC460315 AMC460163
Mesa Cobre Holding Corporation SCX 157 AMC460316 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 SW AMC460316 AMC460163
Mesa Cobre Holding Corporation SCX 158 AMC460317 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 SW AMC460317 AMC460163
Mesa Cobre Holding Corporation SCX 159 AMC460318 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 SW AMC460318 AMC460163
Mesa Cobre Holding Corporation SCX 160 AMC460319 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NW AMC460319 AMC460163
Mesa Cobre Holding Corporation SCX 161 AMC460320 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 SW AMC460320 AMC460163
Mesa Cobre Holding Corporation SCX 162 AMC460321 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 SW AMC460321 AMC460163
Mesa Cobre Holding Corporation SCX 163 AMC460322 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 SW AMC460322 AMC460163
Mesa Cobre Holding Corporation SCX 164 AMC460323 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NW AMC460323 AMC460163
Mesa Cobre Holding Corporation SCX 165 AMC460324 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 SW,SE AMC460324 AMC460163
Mesa Cobre Holding Corporation SCX 166 AMC460325 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NE,NW AMC460325 AMC460163
Mesa Cobre Holding Corporation SCX 167 AMC460326 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 SE AMC460326 AMC460163
Mesa Cobre Holding Corporation SCX 168 AMC460327 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 SE AMC460327 AMC460163
Mesa Cobre Holding Corporation SCX 169 AMC460328 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 027 SE AMC460328 AMC460163
Mesa Cobre Holding Corporation SCX 170 AMC460329 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NE AMC460329 AMC460163
Mesa Cobre Holding Corporation SCX 171 AMC460330 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 027 SE AMC460330 AMC460163

 

September 2023

SEC Technical Report Summary – Santa CruzPage 443

 

Owner Claim Name Serial Number Disposition Case Type Last Assmt Year Location Date Acreage Meridian Township Range Section Subdiv Active Serial Count Lead Case Serial Number
Mesa Cobre Holding Corporation SCX 172 AMC460331 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 027 SE AMC460331 AMC460163
Mesa Cobre Holding Corporation SCX 173 AMC460332 ACTIVE LODE 2020 3/3/2020 16.7 14 0070S 0040E 027 SE AMC460332 AMC460163
Mesa Cobre Holding Corporation SCX 174 AMC460333 ACTIVE LODE 2020 3/3/2020 10.02 14 0070S 0040E 026 SW AMC460333 AMC460163
Mesa Cobre Holding Corporation SCX 175 AMC460334 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 035 NW AMC460334 AMC460163
Mesa Cobre Holding Corporation SCX 176 AMC460335 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 035 NW AMC460335 AMC460163
Mesa Cobre Holding Corporation SCX 177 AMC460336 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NW AMC460336 AMC460163
Mesa Cobre Holding Corporation SCX 178 AMC460337 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NW,SW AMC460337 AMC460163
Mesa Cobre Holding Corporation SCX 179 AMC460338 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NW AMC460338 AMC460163
Mesa Cobre Holding Corporation SCX 180 AMC460339 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NW,SW AMC460339 AMC460163
Mesa Cobre Holding Corporation SCX 181 AMC460340 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NW AMC460340 AMC460163
Mesa Cobre Holding Corporation SCX 182 AMC460341 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NW,SW AMC460341 AMC460163
Mesa Cobre Holding Corporation SCX 183 AMC460342 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NW AMC460342 AMC460163
Mesa Cobre Holding Corporation SCX 184 AMC460343 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NW,SW AMC460343 AMC460163
Mesa Cobre Holding Corporation SCX 185 AMC460344 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NE,NW AMC460344 AMC460163
Mesa Cobre Holding Corporation SCX 186 AMC460345 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NE,NW,SW,SE AMC460345 AMC460163
Mesa Cobre Holding Corporation SCX 187 AMC460346 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NE AMC460346 AMC460163
Mesa Cobre Holding Corporation SCX 188 AMC460347 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NE,SE AMC460347 AMC460163
Mesa Cobre Holding Corporation SCX 189 AMC460348 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NE AMC460348 AMC460163
Mesa Cobre Holding Corporation SCX 190 AMC460349 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NE,SE AMC460349 AMC460163
Mesa Cobre Holding Corporation SCX 191 AMC460350 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NE AMC460350 AMC460163
Mesa Cobre Holding Corporation SCX 192 AMC460351 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NE,SE AMC460351 AMC460163
Mesa Cobre Holding Corporation SCX 193 AMC460352 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 034 NE AMC460352 AMC460163
Mesa Cobre Holding Corporation SCX 194 AMC460353 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 035 NW,SW AMC460353 AMC460163
Mesa Cobre Holding Corporation SCX 195 AMC460354 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 035 NW AMC460354 AMC460163
Mesa Cobre Holding Corporation SCX 196 AMC460355 ACTIVE LODE 2020 3/4/2020 20.66 14 0070S 0040E 035 NW,SW AMC460355 AMC460163
Mesa Cobre Holding Corporation SCX 197 AMC460356 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 035 NW AMC460356 AMC460163
Mesa Cobre Holding Corporation SCX 198 AMC460357 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 035 NW,SW AMC460357 AMC460163
Mesa Cobre Holding Corporation SCX 199 AMC460358 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 035 NW AMC460358 AMC460163
Mesa Cobre Holding Corporation SCX 200 AMC460359 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 035 NW,SW AMC460359 AMC460163
Mesa Cobre Holding Corporation SCX 201 AMC460360 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 035 NW AMC460360 AMC460163
Mesa Cobre Holding Corporation SCX 202 AMC460361 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 035 NW,SW AMC460361 AMC460163
Mesa Cobre Holding Corporation SCX 203 AMC460362 ACTIVE LODE 2020 3/5/2020 20.66 14 0070S 0040E 034 SW AMC460362 AMC460163
Mesa Cobre Holding Corporation SCX 204 AMC460363 ACTIVE LODE 2020 3/5/2020 20.66 14 0070S 0040E 034 SW AMC460363 AMC460163
Mesa Cobre Holding Corporation SCX 205 AMC460364 ACTIVE LODE 2020 3/5/2020 20.66 14 0070S 0040E 034 SW AMC460364 AMC460163
Mesa Cobre Holding Corporation SCX 206 AMC460365 ACTIVE LODE 2020 3/5/2020 20.66 14 0070S 0040E 034 SW AMC460365 AMC460163
Mesa Cobre Holding Corporation SCX 207 AMC460366 ACTIVE LODE 2020 3/5/2020 20.66 14 0070S 0040E 034 SW,SE AMC460366 AMC460163
Mesa Cobre Holding Corporation SCX 208 AMC460367 ACTIVE LODE 2020 3/5/2020 20.66 14 0070S 0040E 034 SE AMC460367 AMC460163
Mesa Cobre Holding Corporation SCX 209 AMC460368 ACTIVE LODE 2020 3/5/2020 20.66 14 0070S 0040E 034 SE AMC460368 AMC460163
Mesa Cobre Holding Corporation SCX 210 AMC460369 ACTIVE LODE 2020 3/5/2020 20.66 14 0070S 0040E 034 SE AMC460369 AMC460163
Mesa Cobre Holding Corporation SCX 211 AMC460370 ACTIVE LODE 2020 3/5/2020 20.66 14 0070S 0040E 035 SW AMC460370 AMC460163
Mesa Cobre Holding Corporation SCX 212 AMC460371 ACTIVE LODE 2020 3/5/2020 20.66 14 0070S 0040E 035 SW AMC460371 AMC460163
Mesa Cobre Holding Corporation SCX 213 AMC460372 ACTIVE LODE 2020 3/5/2020 20.66 14 0070S 0040E 035 SW AMC460372 AMC460163
Mesa Cobre Holding Corporation SCX 214 AMC460373 ACTIVE LODE 2020 3/5/2020 20.66 14 0070S 0040E 035 SW AMC460373 AMC460163
Mesa Cobre Holding Corporation SCX 215 AMC460374 ACTIVE LODE 2020 3/3/2020 20.66 14 0070S 0040E 035 SW AMC460374 AMC460163
Mesa Cobre Holding Corporation SCX 216 AMC460375 ACTIVE LODE 2020 4/6/2020 20.66 14 0050S 0050E 022 SE AMC460375 AMC460163
Mesa Cobre Holding Corporation SCX 217 AMC460376 ACTIVE LODE 2020 4/6/2020 9.64 14 0050S 0050E 022 SE AMC460376 AMC460163
Mesa Cobre Holding Corporation SCX 218 AMC460377 ACTIVE LODE 2020 4/6/2020 9.7 14 0050S 0050E 022 SE AMC460377 AMC460163
Mesa Cobre Holding Corporation SCX 219 AMC460378 ACTIVE LODE 2020 3/1/2020 20.66 14 0050S 0050E 022 SE AMC460378 AMC460163
Mesa Cobre Holding Corporation SCX 220 AMC460379 ACTIVE LODE 2020 3/1/2020 9.64 14 0050S 0050E 022 SE AMC460379 AMC460163
Mesa Cobre Holding Corporation SCX 221 AMC460380 ACTIVE LODE 2020 3/1/2020 9.7 14 0050S 0050E 022 SE AMC460380 AMC460163
Mesa Cobre Holding Corporation SCX 222 AMC460381 ACTIVE LODE 2020 4/6/2020 16.53 14 0070S 0040E 010 NE AMC460381 AMC460163
Mesa Cobre Holding Corporation SCX 223 AMC460382 ACTIVE LODE 2020 3/8/2020 17.22 14 0070S 0040E 003 SE AMC460382 AMC460163
Mesa Cobre Holding Corporation SCX 224 AMC460383 ACTIVE LODE 2020 4/6/2020 13.77 14 0070S 0040E 010 NE AMC460383 AMC460163
Mesa Cobre Holding Corporation SCX 225 AMC460384 ACTIVE LODE 2020 3/31/2020 20.66 14 0070S 0040E 010 NW,SW AMC460384 AMC460163
Mesa Cobre Holding Corporation SCX 226 AMC460385 ACTIVE LODE 2020 3/31/2020 20.66 14 0070S 0040E 010 NW,SW AMC460385 AMC460163
Mesa Cobre Holding Corporation SCX 227 AMC460386 ACTIVE LODE 2020 3/31/2020 20.66 14 0070S 0040E 010 NW,SW AMC460386 AMC460163

 

September 2023

SEC Technical Report Summary – Santa CruzPage 444

 

Owner Claim Name Serial Number Disposition Case Type Last Assmt Year Location Date Acreage Meridian Township Range Section Subdiv Active Serial Count Lead Case Serial Number
Mesa Cobre Holding Corporation SCX 228 AMC460387 ACTIVE LODE 2020 3/31/2020 20.66 14 0070S 0040E 010 NW,SW AMC460387 AMC460163
Mesa Cobre Holding Corporation SCX 229 AMC460388 ACTIVE LODE 2020 3/31/2020 8.61 14 0070S 0040E 010 NE,NW,SW,SE AMC460388 AMC460163
Mesa Cobre Holding Corporation SCX 230 AMC460389 ACTIVE LODE 2020 3/31/2020 20.66 14 0070S 0040E 009 SE AMC460389 AMC460163
Mesa Cobre Holding Corporation SCX 231 AMC460390 ACTIVE LODE 2020 3/31/2020 15.84 14 0070S 0040E 010 SW,SE AMC460390 AMC460163
Mesa Cobre Holding Corporation SCX 232 AMC460391 ACTIVE LODE 2020 3/31/2020 17.22 14 0070S 0040E 010 SW AMC460391 AMC460163
Mesa Cobre Holding Corporation SCX 233 AMC460392 ACTIVE LODE 2020 3/31/2020 13.2 14 0070S 0040E 010 SW,SE AMC460392 AMC460163
Mesa Cobre Holding Corporation SCX 244 AMC460393 ACTIVE LODE 2020 4/7/2020 20.66 14 0070S 0040E 010 SW AMC460393 AMC460163
Mesa Cobre Holding Corporation SCX 245 AMC460394 ACTIVE LODE 2020 4/7/2020 15.84 14 0070S 0040E 010 SW AMC460394 AMC460163
Mesa Cobre Holding Corporation SCX 246 AMC460395 ACTIVE LODE 2020 4/6/2020 20.66 14 0070S 0040E 010 NE,NW AMC460395 AMC460163
Mesa Cobre Holding Corporation SCX 247 AMC460396 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0040E 003 SE AMC460396 AMC460163
Mesa Cobre Holding Corporation SCX 248 AMC460397 ACTIVE LODE 2020 4/6/2020 16.53 14 0070S 0040E 010 NE AMC460397 AMC460163
Mesa Cobre Holding Corporation SCX 249 AMC460398 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0040E 003 SE AMC460398 AMC460163
Mesa Cobre Holding Corporation SCX 250 AMC460399 ACTIVE LODE 2020 4/6/2020 16.53 14 0070S 0040E 010 NE AMC460399 AMC460163
Mesa Cobre Holding Corporation SCX 251 AMC460400 ACTIVE LODE 2020 3/8/2020 20.66 14 0070S 0040E 003 SE AMC460400 AMC460163

 

September 2023