Early Plant Retirements
3 Months Ended
Mar. 31, 2022
Implications of Potential Early Plant Retirements [Abstract]  
Early Plant Retirements Early Plant Retirements We continuously evaluate factors that affect the current and expected economic value of our plants, including, but not limited to: market power prices, results of capacity auctions, potential legislative and regulatory solutions
to ensure plants are fairly compensated for benefits they provide through their carbon-free emissions, reliability or fuel security, and the impact of potential rules from the EPA requiring reduction of carbon and other emissions and the efforts of states to implement those final rules. The precise timing of an early retirement date for any plant, and the resulting financial statement impacts, may be affected by many factors, including the status of potential regulatory or legislative solutions, results of any transmission system reliability study assessments, the nature of any co-owner requirements and stipulations, and NDT fund requirements for nuclear plants, among other factors. However, the earliest retirement date for any plant would usually be the first year in which the unit does not have capacity or other obligations, and where applicable, just prior to its next scheduled nuclear refueling outage.
Nuclear Generation
On August 27, 2020, we announced our intention to permanently cease our operations at Byron in September 2021 and at Dresden in November 2021. Neither of these nuclear plants cleared in PJM’s capacity auction for the 2022-2023 planning year held in May 2021. Our Braidwood and LaSalle nuclear plants in Illinois did clear in the capacity auction, but were also showing increased signs of economic distress. On September 15, 2021, we announced that we have reversed our previous decision to retire Byron and Dresden given the opportunity for additional revenue under the Clean Energy Law. Our Byron, Dresden, and Braidwood nuclear plants participated in the CMC procurement process and were awarded contracts that commit each plant to operate through May 31, 2027. In addition, we no longer consider the Braidwood or LaSalle nuclear plants to be at risk for premature retirement. See Note 3 — Regulatory Matters of our 2021 Form 10-K for additional information.
As a result of the decision to early retire Byron and Dresden, there were ongoing annual financial impacts stemming from shortening the expected economic useful lives of these nuclear plants primarily related to accelerated depreciation of plant assets (including any ARC), accelerated amortization of nuclear fuel, and changes in ARO accretion expense associated with the changes in decommissioning timing and cost assumptions to reflect an earlier retirement date.
The total impact for the three months ended March 31, 2021 in the Consolidated Statements of Operations and Comprehensive Income resulting from the initial decision to early retire Byron and Dresden is summarized in the table below.
Income statement expense (pre-tax)Three Months Ended March 31, 2021
Depreciation and amortization
     Accelerated depreciation(a)
$620 
     Accelerated nuclear fuel amortization54 
Operating and maintenance
     Other charges
     Contractual offset(b)
(226)
Total$450 
_________
(a)Includes the accelerated depreciation of plant assets including any ARC.
(b)Reflects contractual offset for ARO accretion, ARC depreciation, ARO remeasurement, and excludes any changes in earnings in the NDT funds. Based on the regulatory agreement with the ICC, decommissioning-related activities are offset in the Consolidated Statements of Operations and Comprehensive Income as long as the net cumulative decommissioning-related activity result in a regulatory liability at ComEd. The offset resulted in an equal adjustment to the noncurrent payables to ComEd.

We remain committed to continued operations for our other nuclear plants receiving state-supported payments under the Illinois ZES (Clinton and Quad Cities), New Jersey ZEC program (Salem), and the New York CES (FitzPatrick, Ginna, and Nine Mile Point) assuming the continued effectiveness of each program. To the extent each program does not operate as expected over the full term, each of these plants would be at heightened risk for early retirement, which could have a material impact in future financial statements.
We continue to work with stakeholders on state policy solutions to support continued operation of our nuclear fleet, while also advocating for broader market reforms at the regional and federal level. The absence of such solutions or reforms could have a material unfavorable impact on our future results of operations.
Other Generation
In March 2018, we notified ISO-NE of our plans to early retire, among other assets, the Mystic Generating Station's units 8 and 9 (Mystic 8 and 9) absent regulatory reforms to properly value reliability and regional fuel security. Thereafter, ISO-NE identified Mystic 8 and 9 as being needed to ensure fuel security for the region and entered into a cost of service agreement with these two units for the period between June 1, 2022 - May 31, 2024. The agreement was approved by FERC in December 2018.
On June 10, 2020, we filed a complaint with FERC against ISO-NE stating that ISO-NE failed to follow its tariff with respect to its evaluation of Mystic 8 and 9 for transmission security for the 2024 to 2025 Capacity Commitment Period and that the modifications that ISO-NE made to its unfiled planning procedures to avoid retaining Mystic 8 and 9 should have been filed with FERC for approval. On August 17, 2020, FERC issued an order denying the complaint. As a result, on August 20, 2020, we announced we will permanently cease generation operations at Mystic 8 and 9 at the expiration of the cost of service commitment in May 2024. See Note 3 — Regulatory Matters of our 2021 Form 10-K for additional discussion of Mystic's cost of service agreement.
As a result of the decision to early retire Mystic 8 and 9, there are annual financial impacts stemming from shortening the expected economic useful life of Mystic 8 and 9 primarily related to accelerated depreciation of plant assets. We recorded an immaterial amount of incremental Depreciation and amortization expense for the three months ended March 31, 2022 and $20 million for the three months ended March 31, 2021.