XML 65 R47.htm IDEA: XBRL DOCUMENT v3.24.0.1
Jointly Owned Generation Units (Tables)
12 Months Ended
Dec. 31, 2023
Jointly Owned Utility Plant Interests [Line Items]  
Schedule of Jointly Owned Generation Units
At December 31, 2023, the investment in and accumulated depreciation for each generating facility on Cleco’s and Cleco Power’s Consolidated Balance Sheets were as follows:
Cleco
 AT DEC. 31, 2023
(THOUSANDS, EXCEPT PERCENTAGES AND MW)UTILITY PLANT
 IN SERVICE
ACCUMULATED DEPRECIATIONCONSTRUCTION WORK IN PROGRESSOWNERSHIP INTEREST PERCENTAGERATED
CAPACITY (MW)
OWNERSHIP INTEREST (MW)
Acadia Power Station common facilities (1)
$17,384 $3,304 $977 50 %
Brame Energy Center
Rodemacher Unit 2$85,827 $39,798 $257 30 %523 157 
Common facilities - Nesbitt Unit 1 and Rodemacher Unit 2$3,336 $678 $16 62 %
Common facilities - Rodemacher Unit 2 and Madison Unit 3$2,979 $330 $2 69 %
Common facilities - Nesbitt Unit 1, Rodemacher Unit 2, and Madison Unit 3$10,696 $2,090 $337 77 %
(1) Cleco Power has a 100% ownership interest in Acadia Unit 1. The common facilities at the Acadia Power Station are jointly owned.
CLECO POWER  
Jointly Owned Utility Plant Interests [Line Items]  
Schedule of Jointly Owned Generation Units
Cleco Power
 AT DEC. 31, 2023
(THOUSANDS, EXCEPT PERCENTAGES AND MW)UTILITY PLANT
 IN SERVICE
ACCUMULATED DEPRECIATIONCONSTRUCTION WORK IN PROGRESSOWNERSHIP INTEREST PERCENTAGERATED
CAPACITY (MW)
OWNERSHIP INTEREST (MW)
Acadia Power Station common facilities (1)
$18,158 $4,079 $977 50 %
Brame Energy Center
Rodemacher Unit 2$159,407 $113,378 $257 30 %523 157 
Common facilities - Nesbitt Unit 1 and Rodemacher Unit 2$4,744 $2,085 $16 62 %
Common facilities - Rodemacher Unit 2 and Madison Unit 3$3,069 $420 $2 69 %
Common facilities - Nesbitt Unit 1, Rodemacher Unit 2, and Madison Unit 3$20,739 $12,133 $337 77 %
(1) Cleco Power has a 100% ownership interest in Acadia Unit 1. The common facilities at the Acadia Power Station are jointly owned.