The following table summarizes Cleco’s net regulatory assets and liabilities:

Cleco
AT DEC. 31,
(THOUSANDS)20202019
Total Cleco Power regulatory assets, net$275,469 $152,549 
2016 Merger adjustments (1)
Fair value of long-term debt119,553 127,977 
Postretirement costs15,411 17,399 
Financing costs7,592 7,935 
Debt issuance costs5,254 5,665 
Total Cleco regulatory assets, net$423,279 $311,525 
(1) Cleco regulatory assets include acquisition accounting adjustments as a result of the 2016 Merger.
Schedule of Regulatory Liabilities
The following table summarizes Cleco’s net regulatory assets and liabilities:

Cleco
AT DEC. 31,
(THOUSANDS)20202019
Total Cleco Power regulatory assets, net$275,469 $152,549 
2016 Merger adjustments (1)
Fair value of long-term debt119,553 127,977 
Postretirement costs15,411 17,399 
Financing costs7,592 7,935 
Debt issuance costs5,254 5,665 
Total Cleco regulatory assets, net$423,279 $311,525 
(1) Cleco regulatory assets include acquisition accounting adjustments as a result of the 2016 Merger.
CLECO POWER  
Regulatory Assets and Liabilities [Line Items]  
Schedule of Regulatory Assets
The following table summarizes Cleco Power’s regulatory assets and liabilities:

Cleco Power
AT DEC. 31,
REMAINING
RECOVERY PERIOD (YRS.)
(THOUSANDS)20202019
Regulatory assets
Acadia Unit 1 acquisition costs$2,019 $2,124 19
Accumulated deferred fuel28,194 22,910 *
AFUDC equity gross-up (1)
69,670 72,766 *
AMI deferred revenue requirement
2,591 3,136 5
AROs5,488 3,668 *
Coughlin transaction costs876 906 28.5
COVID-19 executive order2,953 — *
Deferred storm restoration costs -
Hurricane Delta
17,051 — *
Deferred storm restoration costs -
Hurricane Laura
54,406 — *
Deferred storm restoration costs -
Hurricane Zeta
3,493 — *
Dolet Hills closure costs48,982 — *
Emergency declarations
270 1,349 0.5
Energy efficiency2,820 2,820 2
Financing costs7,184 7,554 *
Interest costs3,708 3,958 *
Non-service cost of postretirement benefits
9,901 6,739 *
Other4,229 987 *
Postretirement costs165,437 151,543 *
Production operations and maintenance expenses
4,058 7,985 *
Rodemacher Unit 2 closure costs1,333 — *
St. Mary Clean Energy Center3,479 — *
Surcredits, net (1)
 145 *
Training costs6,085 6,241 39
Tree trimming costs11,807 11,341 *
Total regulatory assets456,034 306,172 
Regulatory liabilities
AFUDC(4,218)— *
Corporate franchise tax, net(763)(1,145)*
Deferred taxes, net(175,584)(146,948)*
Other (834)*
St. Mary Clean Energy Center (4,696)*
Total regulatory liabilities(180,565)(153,623)
Total regulatory assets, net$275,469 $152,549  
(1)Represents regulatory assets for past expenditures that were not earning a return on investment at December 31, 2020, and 2019, respectively. All other assets are earning a return on investment.
* For information related to the remaining recovery periods, refer to the following disclosures for each specific regulatory asset.
Schedule of Regulatory Liabilities
The following table summarizes Cleco Power’s regulatory assets and liabilities:

Cleco Power
AT DEC. 31,
REMAINING
RECOVERY PERIOD (YRS.)
(THOUSANDS)20202019
Regulatory assets
Acadia Unit 1 acquisition costs$2,019 $2,124 19
Accumulated deferred fuel28,194 22,910 *
AFUDC equity gross-up (1)
69,670 72,766 *
AMI deferred revenue requirement
2,591 3,136 5
AROs5,488 3,668 *
Coughlin transaction costs876 906 28.5
COVID-19 executive order2,953 — *
Deferred storm restoration costs -
Hurricane Delta
17,051 — *
Deferred storm restoration costs -
Hurricane Laura
54,406 — *
Deferred storm restoration costs -
Hurricane Zeta
3,493 — *
Dolet Hills closure costs48,982 — *
Emergency declarations
270 1,349 0.5
Energy efficiency2,820 2,820 2
Financing costs7,184 7,554 *
Interest costs3,708 3,958 *
Non-service cost of postretirement benefits
9,901 6,739 *
Other4,229 987 *
Postretirement costs165,437 151,543 *
Production operations and maintenance expenses
4,058 7,985 *
Rodemacher Unit 2 closure costs1,333 — *
St. Mary Clean Energy Center3,479 — *
Surcredits, net (1)
 145 *
Training costs6,085 6,241 39
Tree trimming costs11,807 11,341 *
Total regulatory assets456,034 306,172 
Regulatory liabilities
AFUDC(4,218)— *
Corporate franchise tax, net(763)(1,145)*
Deferred taxes, net(175,584)(146,948)*
Other (834)*
St. Mary Clean Energy Center (4,696)*
Total regulatory liabilities(180,565)(153,623)
Total regulatory assets, net$275,469 $152,549  
(1)Represents regulatory assets for past expenditures that were not earning a return on investment at December 31, 2020, and 2019, respectively. All other assets are earning a return on investment.
* For information related to the remaining recovery periods, refer to the following disclosures for each specific regulatory asset.