XML 134 R117.htm IDEA: XBRL DOCUMENT v3.20.4
Litigation, Other Commitments and Contingencies, and Disclosures about Guarantees - Risk and Uncertainties (Details) - Cleco Power - USD ($)
$ in Millions
1 Months Ended
Oct. 31, 2020
Jun. 30, 2020
Dec. 31, 2020
Dec. 31, 2019
Litigation [Line Items]        
Increase in ARO liabilities $ 0.3 $ 3.3    
Oxbow        
Litigation [Line Items]        
Costs to be billed     $ 0.3 $ 0.2
Dolet Hills Power Station        
Litigation [Line Items]        
Increase in ARO liabilities   $ 3.3    
Investment balance     99.0  
Dolet Hills Power Station | DHLC        
Litigation [Line Items]        
Costs to be billed     154.2  
Oxbow | Oxbow        
Litigation [Line Items]        
Costs to be billed     $ 7.7