XML 95 R80.htm IDEA: XBRL DOCUMENT v3.20.2
Litigation, Other Commitments and Contingencies, and Disclosures about Guarantees - Litigation (Details)
$ in Millions
1 Months Ended 3 Months Ended 9 Months Ended 24 Months Ended 30 Months Ended
May 21, 2020
Mar. 03, 2020
USD ($)
Jan. 01, 2020
Mar. 31, 2018
plaintiff
Sep. 30, 2016
Jun. 30, 2016
Sep. 30, 2015
USD ($)
Dec. 31, 2014
claim
Nov. 30, 2014
Mar. 31, 2017
claim
generation_unit
Sep. 30, 2020
USD ($)
Dec. 31, 2019
USD ($)
May 31, 2016
complaint
Sep. 27, 2019
recommendation
finding
Feb. 04, 2019
USD ($)
Loss Contingencies [Line Items]                              
Loss contingency, estimate of possible loss                     $ 5.3        
South Central Generating                              
Loss Contingencies [Line Items]                              
Indemnification asset                             $ 10.0
Contingent liability                             $ 10.0
FERC                              
Loss Contingencies [Line Items]                              
Estimated refund interest amount                     2.7        
FERC | MISO Transmission Rates                              
Loss Contingencies [Line Items]                              
Public utilities, requested rate increase (decrease), percentage (in hundredths)                 0.50%            
Gulf Coast Spinning start up costs                              
Loss Contingencies [Line Items]                              
Allegations by plaintiff, failure to perform             $ 6.5                
Gulf Coast Spinning construction of cotton spinning facility                              
Loss Contingencies [Line Items]                              
Allegations by plaintiff, failure to perform             $ 60.0                
Actions filed in the 9th Judicial District Court | Alleged Breach of Fiduciary Duties                              
Loss Contingencies [Line Items]                              
Number of actions filed | claim                   4          
Actions filed in the Civil District Court | Alleged Breach of Fiduciary Duties                              
Loss Contingencies [Line Items]                              
Number of actions filed | claim               3   3          
Larry Addison, Et Al. V. Sabine River Authority of Texas, Et Al | Pending Litigation                              
Loss Contingencies [Line Items]                              
Number of plaintiffs | plaintiff       26                      
Perry Bonin, Ace Chandler, and Michael Manuel, et al v. Sabine River Authority of Texas and Sabine River Authority of Louisiana, No. B-160173-C | Pending Litigation                              
Loss Contingencies [Line Items]                              
Number of generation units failed to repair | generation_unit                   1          
Number of generation units owned | generation_unit                   2          
CLECO POWER | LPSC 2018-2019 Fuel Audit                              
Loss Contingencies [Line Items]                              
Fuel expense                       $ 565.8      
CLECO POWER | MISO Transmission Rates                              
Loss Contingencies [Line Items]                              
Public utilities, proposed return on equity, percentage (in hundredths)     10.38%   10.32% 9.70%                  
CLECO POWER | LPSC                              
Loss Contingencies [Line Items]                              
Environmental expense   $ 26.2                          
CLECO POWER | FERC                              
Loss Contingencies [Line Items]                              
Number of findings | finding                           12  
Number of recommendations | recommendation                           59  
Estimated refund interest amount                     2.7        
Loss contingency, estimate of possible loss                     $ 0.6        
CLECO POWER | FERC | MISO Transmission Rates                              
Loss Contingencies [Line Items]                              
Number of actions filed | complaint                         2    
Public utilities, approved return on equity, percentage (In hundredths)                         12.38%    
Public utilities, proposed return on equity, percentage (in hundredths) 10.02%       9.88%               6.68%