XML 103 R75.htm IDEA: XBRL DOCUMENT v3.20.1
Litigation, Other Commitments and Contingencies, and Disclosures about Guarantees - Litigation (Details)
$ in Millions
1 Months Ended 12 Months Ended 24 Months Ended 30 Months Ended
Mar. 11, 2020
USD ($)
Jan. 01, 2020
Nov. 07, 2019
USD ($)
Mar. 31, 2018
plaintiff
Sep. 30, 2016
Jun. 30, 2016
petition
Sep. 30, 2015
USD ($)
Dec. 31, 2014
claim
Nov. 30, 2014
Dec. 31, 2016
claim
Dec. 31, 2019
USD ($)
May 31, 2016
Mar. 31, 2020
USD ($)
Sep. 27, 2019
finding
recommendation
Feb. 04, 2019
USD ($)
Mar. 31, 2017
generation_unit
Loss Contingencies [Line Items]                                
Loss contingency, estimate of possible loss                         $ 5.1      
South Central Generating                                
Loss Contingencies [Line Items]                                
Indemnification asset                             $ 10.0  
Contingent liability                             $ 10.0  
FERC | MISO Transmission Rates                                
Loss Contingencies [Line Items]                                
Public utilities, requested rate increase (decrease), percentage (in hundredths)                 0.50%              
Gulf Coast Spinning start up costs                                
Loss Contingencies [Line Items]                                
Allegations by plaintiff, failure to perform             $ 6.5                  
Gulf Coast Spinning construction of cotton spinning facility                                
Loss Contingencies [Line Items]                                
Allegations by plaintiff, failure to perform             $ 60.0                  
Actions filed in the 9th Judicial District Court | Alleged Breach of Fiduciary Duties                                
Loss Contingencies [Line Items]                                
Number of actions filed | claim                   4            
Actions filed in the Civil District Court | Alleged Breach of Fiduciary Duties                                
Loss Contingencies [Line Items]                                
Number of actions filed | claim               3   3            
Perry Bonin, Ace Chandler, and Michael Manuel, et al v. Sabine River Authority of Texas and Sabine River Authority of Louisiana, No. B-160173-C | Pending Litigation                                
Loss Contingencies [Line Items]                                
Number of generation units failed to repair | generation_unit                               1
Number of generation units owned | generation_unit                               2
Larry Addison, Et Al. V. Sabine River Authority Of Texas, Et Al | Pending Litigation                                
Loss Contingencies [Line Items]                                
Number of plaintiffs | plaintiff       26                        
CLECO POWER | LPSC 2018-2019 Fuel Audit                                
Loss Contingencies [Line Items]                                
Fuel expense                     $ 565.8          
CLECO POWER | LPSC Nov 2010-Dec 2015 EAC Audit                                
Loss Contingencies [Line Items]                                
Number of petitions filed with the U.S. Court of Appeals | petition           6                    
CLECO POWER | MISO Transmission Rates                                
Loss Contingencies [Line Items]                                
Public utilities, proposed return on equity, percentage (in hundredths)   10.38%     10.32% 9.70%                    
CLECO POWER | LPSC                                
Loss Contingencies [Line Items]                                
Environmental expense $ 26.2                              
CLECO POWER | FERC                                
Loss Contingencies [Line Items]                                
Number of findings | finding                           12    
Number of recommendations | recommendation                           59    
Estimated refund interest amount     $ 3.5                          
Loss contingency, estimate of possible loss                         $ 1.0      
CLECO POWER | FERC | MISO Transmission Rates                                
Loss Contingencies [Line Items]                                
Public utilities, approved return on equity, percentage (In hundredths)                       12.38%        
Public utilities, proposed return on equity, percentage (in hundredths)         9.88%             6.68%