XML 18 R21.htm IDEA: XBRL DOCUMENT v3.19.3
Regulation and Rates
9 Months Ended
Sep. 30, 2019
Regulated Operations [Abstract]  
Regulation and Rates
Note 12 — Regulation and Rates
At September 30, 2019, Provision for rate refund on Cleco and Cleco Power’s Condensed Consolidated Balance Sheets consisted primarily of $38.4 million for the estimated refund for the tax-related benefits from the TCJA, $3.0 million for the estimated refund related to the FERC audit, $2.8 million for the cost of service savings refunds, $2.3 million for estimated FRP refunds, and $1.9 million for potential reductions to the transmission ROE. For more information about the FERC audit, see Note 14 — “Litigation, Other Commitments and Contingencies, and Disclosures about Guarantees — Litigation — FERC Audit.”

Transmission ROE
A complaint was filed with FERC seeking to reduce the ROE component of the transmission rates that MISO transmission owners, including Cleco, may collect under the MISO tariff. As of September 30, 2019, Cleco Power had $1.9 million accrued for potential ROE reductions. For more information on the ROE complaints, see Note 14 — “Litigation, Other Commitments and Contingencies, and Disclosures about Guarantees — Litigation — Transmission ROE.”

FRP
Cleco Power’s annual retail earnings are subject to an FRP that was approved by the LPSC in June 2014. Under the terms of Cleco Power’s current FRP, Cleco Power is allowed to earn a target ROE of 10.0%, while providing the opportunity to earn up to 10.9%. Additionally, 60.0% of retail earnings between 10.9% and 11.75%, and all retail earnings over 11.75%, are required to be refunded to customers. The amount of credits due to customers, if any, is determined by Cleco Power and the LPSC, annually. Credits are typically included on customers’ bills the following summer, but the amount and timing of the refunds are ultimately subject to LPSC approval. On June 28, 2019, Cleco Power filed an application with the LPSC for a new FRP, with anticipated new rates being effective July 1, 2020. Cleco Power has responded to several sets of data requests relating to the new FRP.
Cleco Power must file annual monitoring reports no later than October 31 for the 12-month period ending June 30. On October 31, 2017, Cleco Power filed its monitoring report for the 12-month period ended June 30, 2017, which indicated that no refund was due as a result of the FRP and $1.2 million was due as a result of the cost of service savings from the 2016 Merger Commitments. The $1.2 million cost of service savings from the 2016 Merger Commitments were refunded in September 2018. Cleco Power expects the LPSC to approve the 2017 FRP monitoring report in the fourth quarter of 2019.
On October 31, 2018, Cleco Power filed its monitoring report for the 12-month period ended June 30, 2018, which indicated that no refund was due as a result of the FRP and $1.2 million of cost of service savings refunds are due to be returned to eligible customers. On December 21, 2018, Cleco Power responded to the first set of data requests for the 2018 FRP monitoring report.
On October 4, 2019, Cleco Power filed comments and supporting testimony to the LPSC’s initial and final report for the 2017 FRP monitoring report regarding the realignment of SSR revenues between fuel and base revenues. Cleco Power proposed the re-allocation of SSR revenues, which would result in no additional FRP refund for the 12-month period ended June 30, 2017, and $2.3 million of additional FRP refunds for the 12-month period ended June 30, 2018. At September 30, 2019, Cleco Power had $2.3 million accrued for the estimated FRP refunds relating to the 12-month period ended June 30, 2018.
On October 31, 2019, Cleco Power filed its monitoring report for the 12-month period ended June 30, 2019, which indicated that no refund was due as a result of the FRP and $1.2 million of cost of service savings refunds are due to be returned to eligible customers. At September 30, 2019, Cleco Power had $1.2 million accrued for the estimated cost of service savings refunds relating to the 12-month period ended June 30, 2019.

TCJA
The provisions of the TCJA reduced the top federal statutory corporate income tax rate from 35% to 21%. As a result of the tax rate reduction, on January 1, 2018, Cleco Power began accruing an estimated reserve for the reduction in the federal statutory corporate income tax rate. In February 2018, the LPSC directed utilities, including Cleco Power, to provide considerations of the appropriate manner to flow through to ratepayers the benefits of the reduction in corporate income taxes as a result of the TCJA. After various filings and settlement discussions, on July 10, 2019, the LPSC approved Cleco Power’s rate refund of $79.2 million, plus interest, for the reduction in the statutory federal tax rate for the period from January 2018 to June 2020. The refund is being credited to customers over 12 months beginning August 1, 2019. At September 30, 2019, Cleco Power had $38.4 million accrued for the estimated federal tax-related benefits from the TCJA and $3.0 million accrued for related interest.
Also, on July 10, 2019, the LPSC approved Cleco Power’s motion to address the rate redesign and the regulatory liability for excess ADIT, resulting from the enactment of the TCJA, in Cleco Power’s application for its next FRP, which was filed on June 28, 2019.

SSR
In September 2016, Cleco Power filed an Attachment Y with MISO requesting retirement of Teche Unit 3 effective April 1, 2017. MISO conducted a study which determined the proposed retirement of Teche Unit 3 would result in violations of specific applicable reliability standards for which no mitigation is available. As a result, MISO designated Teche Unit 3 as an SSR unit until such time that an appropriate alternative solution could be implemented to mitigate reliability issues. One mitigating factor identified was Cleco Power’s Terrebonne to Bayou Vista Transmission project. The Terrebonne to Bayou Vista project was completed in April 2019. Cleco Power received a termination notice, effective April 30, 2019, and filed paperwork to withdraw the filed Attachment Y. While operating as an SSR unit, Cleco Power received monthly payments that included recovery of expenses, including capital expenditures, related to the operations of Teche Unit 3. Additionally, MISO allocated SSR costs to the load serving entities that required the operation of the SSR unit, including Cleco Power. These payments and cost allocations were finalized as part of a MISO SSR settlement approved in December 2018. Cleco Power operated Teche Unit 3 as an SSR unit from April 2017 until April 2019.
After the end of the final SSR agreement, which was terminated on April 30, 2019, Cleco Power expects Teche Unit 3 to be available to run until the estimated 2021 in-service date of Bayou Vista to Segura Transmission project, at which time Cleco Power does not expect to offer the unit into MISO, barring any grid or customer reliability issues or other similar reasons. At September 30, 2019, Cleco Power had $6.1 million accrued for the net capital refund for capital expenditures paid for by third parties. As part of the settlement, one of the load serving entities agreed to reimburse Cleco Power for their portion of the capital refund. Management is unable to determine the timing of the capital refund.