Litigation [Abstract]                        
Provision for rate refund                 $ 3,734,000   $ 3,974,000  
Loss Contingency, Estimate of Possible Loss                 4,600,000      
FERC | MISO Transmission Rates                        
Litigation [Abstract]                        
Public Utilities, Requested rate increase (decrease), Percentage (in hundredths)         0.50%              
Gulf Coast Spinning start up costs                        
Litigation [Abstract]                        
Allegations by plaintiff, failure to perform       $ 6,500,000                
Gulf Coast Spinning construction of cotton spinning facility                        
Litigation [Abstract]                        
Allegations by plaintiff, failure to perform       $ 60,000,000                
Cleco Power [Member]                        
Litigation [Abstract]                        
Provision for rate refund                 3,734,000   3,974,000  
Cleco Power [Member] | LPSC 2014-2015 Fuel Audit                        
Litigation [Abstract]                        
Fuel Costs             $ 582,600,000          
Cost disallowance in audit, excluding interest                   $ 0    
Cleco Power [Member] | LPSC Nov2010-Dec2015 EAC audit                        
Litigation [Abstract]                        
Environmental expenses included in audit               $ 81,200,000        
Number of petitions filed with the U.S. Court of Appeals | petition                       6
Cleco Power [Member] | FERC | MISO Transmission Rates                        
Litigation [Abstract]                        
Public Utilities, Approved Return on Equity, Percentage (In hundredths)   10.32%       12.38%            
Public Utilities, Proposed Return on Equity, Percentage (in hundredths)     9.70%     6.68%            
Customer Refundable Fees, Refund Payments $ 1,200,000                      
Provision for rate refund                 $ 2,000,000      
Cleco Power [Member] | Maximum | LPSC Nov2010-Dec2015 EAC audit                        
Litigation [Abstract]                        
Cost disallowance in audit, excluding interest                     $ 100,000