Litigation
 
Devil’s Swamp
In October 2007, Cleco received a Special Notice for Remedial Investigation and Feasibility Study (RI/FS) from the EPA pursuant to CERCLA (also known as the Superfund statute) for a facility known as the Devil’s Swamp Lake site located just northwest of Baton Rouge, Louisiana. CERCLA establishes several classes of PRPs for a contaminated site and imposes strict, joint and several, and retroactive liability on those PRPs for the cost of response to the contamination. The special notice requested that Cleco Corporation and Cleco Power, along with many other listed PRPs, enter into negotiations with the EPA for the performance of an RI/FS at the Devil’s Swamp Lake site. The EPA identified Cleco as one of many companies that sent PCB wastes for disposal to the site. The EPA proposed to add the Devil’s Swamp Lake site to the National Priorities List on March 8, 2004, based on the release of PCBs to fisheries and wetlands located on the site, but no final listing decision has yet been made. The PRPs began discussing a potential proposal to the EPA in February 2008. The EPA issued a Unilateral Administrative Order to two PRP’s, Clean Harbors, Inc. and Baton Rouge Disposal, to conduct an RI/FS in December 2009. The Tier 1 part of the study was completed in June 2012. Field activities for the Tier 2 investigation were completed in July 2012. The draft Tier 2 remedial investigation report was submitted on December 19, 2014. Currently, the study/remedy selection task continues, and there is no record of a decision. Therefore, management is unable to determine how significant Cleco’s share of the costs associated with the RI/FS and possible response action at the site, if any, may be and whether this will have a material adverse effect on the Registrants’ financial condition, results of operations, or cash flows.

Discrimination Complaints
In December 2009, a complaint was filed in the United States District Court for the Western District of Louisiana (the Court) on behalf of eight current employees and four former employees alleging that Cleco discriminated against each of them on the basis of race. Each was seeking various remedies provided under applicable statutes prohibiting racial discrimination in the workplace, and together, the plaintiffs requested monetary compensation exceeding $35.0 million. In July 2010, the plaintiffs moved to add an additional current employee alleging that Cleco had discriminated on the basis of race. The additional plaintiff sought compensation of no less than $2.5 million and became the thirteenth plaintiff. In April 2011, Cleco entered into a settlement with one of the current employees which resulted in a dismissal of one of the thirteen cases with prejudice. In September 2011, the Court ruled on Cleco’s summary judgment motions, resulting in eleven of the twelve remaining plaintiffs having at least one claim remaining. In February 2013, the Court ruled on the second motion for summary judgment, filed by Cleco in March 2012, in each of the eleven cases and each such case was dismissed with prejudice. Appeals were filed in ten of the eleven dismissed cases to the United States Court of Appeals for the Fifth Circuit (the Fifth Circuit). In June 2013, the Fifth Circuit clerk dismissed the appeals of two of the current employees due to their failure to file a brief in support of their respective appeals. On various dates in August through November 2013, the Fifth Circuit affirmed the trial court judgments in favor of Cleco in seven of the eight remaining cases. In April 2014, the Fifth Circuit affirmed the Court’s summary judgment dismissing the wrongful termination and other discrimination claims of the one remaining plaintiff, a former employee who served as one of Cleco’s human resource representatives. Excluded from the ruling was one claim that the former employee alleged was the result of a disciplinary warning Cleco issued to the former employee. This one claim has been remanded to the Court and is set for trial on June 22, 2015. Management does not believe the result of the remaining claim will have a material effect on the Registrants’ results of operations, financial condition, or cash flows.
 
Merger
In connection with the Merger, four actions were filed in the Ninth Judicial District Court for Rapides Parish, Louisiana and three actions were filed in the Civil District Court for Orleans Parish, Louisiana. The petitions in each action generally allege, among other things, that the members of the Cleco Corporation Board of Directors breached their fiduciary duties by, among other things, conducting an allegedly inadequate sale process, agreeing to the Merger at a price that allegedly undervalues Cleco, and failing to disclose material information about the Merger. The petitions also allege that Cleco Partners, Cleco Corporation, Merger Sub, and in some cases, certain of the investors in Cleco Partners, either aided and abetted or entered into a civil conspiracy to advance those supposed breaches of duty. The petitions seek various remedies, including an injunction against the Merger and monetary damages, including attorneys’ fees and expenses.
The four actions filed in the Ninth Judicial District Court for Rapides Parish are captioned as follows:

Braunstein v. Cleco Corporation, No. 251,383B (filed October 27, 2014),
Moore v. Macquarie Infrastructure and Real Assets, No. 251,417C (filed October 30, 2014),
Trahan v. Williamson, No. 251,456C (filed November 5, 2014), and
L’Herisson v. Macquarie Infrastructure and Real Assets, No. 251,515F (filed November 14, 2014).

On November 14, 2014, the plaintiff in the Braunstein action moved for a dismissal of the action without prejudice, and that motion was granted on November 19, 2014. On December 3, 2014, the court consolidated the remaining three actions and appointed interim co-lead counsel. On December 18, 2014, the plaintiffs in the consolidated action filed a Consolidated Amended Verified Derivative and Class Action Petition for Damages and Preliminary and Permanent Injunction (the Consolidated Petition), which is now the operative petition in the consolidated action. The action names Cleco Corporation, its directors, Cleco Partners, and Merger Sub as defendants. The Consolidated Petition alleges, among other things, that the directors breached their fiduciary duties to Cleco’s shareholders and grossly mismanaged Cleco by approving the Merger Agreement because it does not value Cleco adequately, failing to structure a process through which shareholder value would be maximized, engaging in self-dealing by ignoring conflicts of interest, and failing to disclose material information about the Merger. The Consolidated Petition further alleges that all defendants conspired to commit the breaches of fiduciary duty. Cleco believes that the allegations of the Consolidated Petition are without merit and that it has substantial meritorious defenses to the claims set forth in the Consolidated Petition.
The three actions filed in the Civil District Court for Orleans Parish are captioned as follows:

Butler v. Cleco Corporation, No. 2014-10776 (filed November 7, 2014),
Creative Life Services, Inc. v. Cleco Corporation, No. 2014-11098 (filed November 19, 2014), and
Cashen v. Cleco Corporation, No. 2014-11236 (filed November 21, 2014). 

Both the Butler and Cashen actions name Cleco Corporation, its directors, Cleco Partners, Merger Sub, Macquarie Infrastructure and Real Assets Inc. (MIRA), British Columbia Investment Management Corporation, and John Hancock Financial as defendants. The Creative Life Services action names Cleco Corporation, its directors, Cleco Partners, Merger Sub, MIRA, and Macquarie Infrastructure Partners III, L.P., as defendants. On December 11, 2014, the plaintiff in the Butler action filed an Amended Class Action Petition for Damages, which is now the operative petition in that action. Each petition alleges, among other things, that the directors breached their fiduciary duties to Cleco’s shareholders by approving the Merger Agreement because it does not value Cleco adequately, failing to structure a process through which shareholder value would be maximized and engaging in self-dealing by ignoring conflicts of interest. The Butler and Creative Life Services petitions also allege that the directors breached their fiduciary duties by failing to disclose material information about the Merger. Each petition further alleges that Cleco, Cleco Partners, Merger Sub, and certain of the investors in Cleco Partners aided and abetted the directors’ breaches of fiduciary duty. On December 23, 2014, the directors and Cleco filed declinatory exceptions in each action on the basis that each action was improperly brought in Orleans Parish and should either be transferred to the Ninth Judicial District Court for Rapides Parish or dismissed. On December 30, 2014, the plaintiffs in each action jointly filed a motion to consolidate the three actions pending in Orleans Parish and to appoint interim co-lead plaintiffs and co-lead counsel. On January 23, 2015, the court in the Creative Life Services case sustained the defendants’ declinatory exceptions and dismissed the case so that it could be transferred to the Ninth Judicial District Court for Rapides Parish. On February 5, 2015, the plaintiffs in Butler and Cashen also consented to the dismissal of their cases from Orleans Parish so they could be transferred to the Ninth Judicial District Court for Rapides Parish. On February 25, 2015, the Ninth Judicial District Court for Rapides Parish held a hearing on a motion for preliminary injunction filed by plaintiffs Moore, L’Herisson, and Trahan seeking to enjoin the shareholder vote at the Special Meeting of Shareholders scheduled for February 26, 2015, for approval of the Merger Agreement. Following the hearing, the court denied the plaintiffs’ motion. On April 14, 2015, the Ninth Judicial District Court for Rapides Parish entered a scheduling order under which the plaintiffs must file a second amended petition by May 14, 2015. Cleco believes that the allegations of the petitions in each action are without merit and that it has substantial meritorious defenses to the claims set forth in each of the petitions.

LPSC Audits

Fuel Audit
The cost of fuel used for electric generation and the cost of power purchased for utility customers are recovered through the LPSC-established FAC that enables Cleco Power to pass on to its customers substantially all such charges. Recovery of FAC costs is subject to periodic fuel audits by the LPSC. The LPSC FAC General Order issued in November 1997, in Docket No. U-21497 provides that an audit of FAC filings will be performed at least every other year. Cleco Power has FAC filings for the years 2009 through 2014 that remain subject to audit. In November 2014, the LPSC initiated an audit of Cleco Power’s fuel and purchased power expenses for the years 2009 through 2013. The total amount of fuel expense included in the audit is $1.73 billion. Cleco Power has responded to several sets of data requests from the LPSC Staff and the responses are currently under review. Management is unable to predict or give a reasonable estimate of the possible range of a disallowance, if any, related to this audit. Historically, the disallowances have not been material. If a disallowance of fuel costs is ordered, resulting in a refund, any such refund could have a material adverse effect on the Registrants’ results of operations, financial condition, and cash flows.

Environmental Audit
In July 2009, the LPSC issued Docket No. U-29380 Subdocket A, which provides for an EAC to recover from customers certain costs of environmental compliance. The costs eligible for recovery are prudently incurred air emissions credits associated with complying with federal, state, and local air emission regulations that apply to the generation of electricity reduced by the sale of such allowances. Also eligible for recovery are variable emission mitigation costs, which are the costs of reagents such as ammonia and limestone that are a part of the fuel mix used to reduce air emissions, among other things. Cleco Power anticipates incurring additional environmental compliance expenses beginning in the second quarter of 2015 for additional reagents associated with compliance with MATS. These expenses will be eligible for recovery through Cleco Power’s EAC and subject to periodic review by the LPSC. Cleco Power has EAC filings for the period November 2010 through December 2014 that remain subject to audit.
 
Transmission Return on Equity
In November 2013, a group of industrial customers from the northern region of MISO and other stakeholders filed a complaint at FERC seeking to reduce the return on equity component of the transmission rates that MISO transmission owners, including Cleco, may collect under the MISO tariff. The complainants are seeking to reduce the current 12.38% return on equity used in MISO’s transmission rates to a proposed 9.15%. A group of MISO transmission owners filed responses to the complaint, defending the current return on equity and seeking dismissal of the complaint. In October 2014, FERC issued an order finding that the current MISO return on equity may be unjust and unreasonable and setting the issue for hearing, subject to the outcome of settlement discussions. Settlement discussions did not resolve the dispute and FERC set the proceeding for a hearing for the week of August 17, 2015, with a decision expected in the third quarter of 2016. In November 2014, a group of MISO transmission owners, including Cleco, filed a request with FERC for an incentive to increase the new return on equity by 0.5% for RTO participation. On January 5, 2015, FERC granted the request. The collection of the adder is delayed until the resolution of the return on equity complaint proceeding. Management is unable to determine if there will be a reduction in the current return on equity. Any reduction could result in a potential refund to customers. Management is unable to determine the amount of potential refund. Management believes a reduction, if any, in the return on equity, as well as any resulting refund, will not have a material adverse effect on the Registrants’ results of operations, financial condition, or cash flows. 

Other
Cleco is involved in various litigation matters, including regulatory, environmental, and administrative proceedings before various courts, regulatory commissions, arbitrators, and governmental agencies regarding matters arising in the ordinary course of business. The liability Cleco may ultimately incur with respect to any one of these matters in the event of a negative outcome may be in excess of amounts currently accrued. Management regularly analyzes current information and, as of March 31, 2015, believes the probable and reasonably estimable liabilities based on the eventual disposition of these matters is $8.3 million and has accrued this amount.
 
Off-Balance Sheet Commitments
Cleco Corporation and Cleco Power have entered into various off-balance sheet commitments, in the form of guarantees and standby letters of credit, in order to facilitate their activities and the activities of Cleco Corporation’s subsidiaries and equity investees (affiliates). Cleco Corporation and Cleco Power have also agreed to contractual terms that require the Registrants to pay third parties if certain triggering events occur. These contractual terms generally are defined as guarantees in the authoritative guidance.
Cleco Corporation entered into these off-balance sheet commitments in order to entice desired counterparties to contract with its affiliates by providing some measure of credit assurance to the counterparty in the event Cleco’s affiliates do not fulfill certain contractual obligations. If Cleco Corporation had not provided the off-balance sheet commitments, the desired counterparties may not have contracted with Cleco’s affiliates, or may have contracted with them at terms less favorable to its affiliates.
The off-balance sheet commitments are not recognized on Cleco and Cleco Power’s Condensed Consolidated Balance Sheets because management has determined that Cleco and Cleco Power’s affiliates are able to perform these obligations under their contracts and that it is not probable that payments by Cleco or Cleco Power will be required.
In January 2006, Cleco Corporation provided a $0.5 million guarantee to Entergy Mississippi for Attala’s obligations under the Interconnection Agreement. This guarantee will be effective until obligations are performed or extinguished.
The State of Louisiana allows employers of certain financial net worth to self-insure their workers’ compensation benefits. Cleco Power has a certificate of self-insurance from the Louisiana Office of Workers’ Compensation and is required to post a $3.7 million letter of credit, an amount equal to 110% of the average losses over the previous three years, as surety.
Cleco Power provides a letter of credit to MISO pursuant to the credit requirements of FTRs. At March 31, 2015, the letter of credit was $2.0 million. The letter of credit automatically renews each year and reduces Cleco Power’s credit facility capacity.
Cleco Corporation provided a guarantee to Entergy Louisiana and Entergy Gulf States as a result of the sale of the Perryville facility in 2004. This is a continuing guarantee and all obligations of Cleco Corporation will continue until the guaranteed obligations have been fully performed or otherwise extinguished. The maximum amount of the potential payment to Entergy Louisiana and Entergy Gulf States is $42.4 million. Currently, management does not expect to be required to pay Entergy Louisiana and Entergy Gulf States under the guarantee.
On behalf of Acadia, Cleco Corporation provided guarantees and indemnifications as a result of the sales of Acadia Unit 1 to Cleco Power and Acadia Unit 2 to Entergy Louisiana in 2010 and 2011, respectively. At March 31, 2015, the remaining indemnifications relate to the fundamental organizational structure of Acadia. These remaining indemnifications have no limitations as to time or maximum potential future payments. Currently, management does not expect to be required to pay Cleco Power or Entergy Louisiana under the guarantees.
Cleco Corporation provided indemnifications to Cleco Power as a result of the transfer of Coughlin to Cleco Power in March 2014. Cleco Power also provided indemnifications to Cleco Corporation and Evangeline as a result of the transfer of Coughlin to Cleco Power. The maximum amount of the potential payment to Cleco Power, Cleco Corporation, and Evangeline for their respective indemnifications is $40.0 million, except for indemnifications relating to the fundamental organizational structure of each respective entity, of which the maximum amount is $400.0 million. Currently, management does not expect to be required to make any payments under these guarantees.

On-Balance Sheet Guarantees
As part of the Amended Lignite Mining Agreement, Cleco Power and SWEPCO, joint owners of Dolet Hills, have agreed to pay the loan and lease principal obligations of the lignite miner, DHLC, when due if they do not have sufficient funds or credit to pay. Any amounts paid on behalf of the miner would be credited by the lignite miner against future invoices for lignite delivered. At March 31, 2015, Cleco Power had a liability of $3.8 million related to the amended agreement. The maximum projected payment by Cleco Power under this guarantee is estimated to be $69.3 million; however, the Amended Lignite Mining Agreement does not contain a cap. The projection is based on the forecasted loan and lease obligations to be incurred by DHLC, primarily for purchases of equipment. Cleco Power has the right to dispute the incurrence of loan and lease obligations through the review of the mining plan before the incurrence of such loan and lease obligations. The Amended Lignite Mining Agreement is not expected to terminate pursuant to its terms until 2036 and does not affect the amount the Registrants can borrow under their credit facilities. Currently, management does not expect to be required to pay DHLC under the guarantee.
Generally, neither Cleco Corporation nor Cleco Power has recourse that would enable them to recover amounts paid under their guarantee or indemnification obligations. There are no assets held as collateral for third parties that either Cleco Corporation or Cleco Power could obtain and liquidate to recover amounts paid pursuant to the guarantees or indemnification obligations.

Other Commitments
 
NMTC Fund
In 2008, Cleco Corporation and US Bancorp Community Development (USBCDC) formed the NMTC Fund. Cleco Corporation has a 99.9% membership interest in the NMTC Fund and USBCDC has a 0.1% interest. The purpose of the NMTC Fund is to invest in projects located in qualified active low-income communities that are underserved by typical debt capital markets. These investments are designed to generate NMTCs and Historical Rehabilitation tax credits. The NMTC Fund was later amended to include renewable energy investments. The majority of the energy investments qualify for grants under Section 1603 of the ARRA. The tax benefits received from the NMTC Fund reduce the federal income tax obligations of Cleco Corporation. In total, Cleco Corporation will contribute $283.7 million of equity contributions to the NMTC Fund and will receive at least $302.0 million in the form of tax credits, tax losses, capital gains/losses, earnings, and cash over the life of the investment, which ends in 2017. The $18.3 million difference between equity contributions and total benefits received will be recognized over the life of the NMTC Fund as net tax benefits are delivered. The following table reflects remaining future equity contributions:
(THOUSANDS)
CONTRIBUTION

Nine months ending Dec. 31, 2015
$
4,091

Years ending Dec. 31,
 

2016
2,707

2017
2,707

Total
$
9,505



Of the $9.5 million, $4.1 million is due to be paid within the next 12 months. Due to the right of offset, the investment and associated debt are presented on Cleco’s Condensed Consolidated Balance Sheet in the line item Tax credit fund investment, net. The amount of tax benefits delivered in excess of capital contributions as of March 31, 2015, was $27.0 million. The amount of tax benefits delivered but not utilized as of March 31, 2015, was $120.2 million and is reflected as a deferred tax asset.
The equity contribution does not contain a stated rate of interest. Cleco Corporation has recorded the asset and investment at its calculated fair value at inception within the framework of the authoritative guidance. In order to calculate the fair value, management used an imputed rate of interest assuming Cleco Corporation obtained financing of a similar nature from a third party. The imputed interest rate was used in a net present value model in order to calculate the fair value of the remaining portion of the delayed equity contributions. The following table contains the disclosures required by the authoritative guidelines for equity investments with a 6% imputed interest rate: 
(THOUSANDS)
 
Equity contributions
 
Principal payment schedule above:
$
9,505

Less: unamortized discount
726

Total
$
8,779



The gross investment amortization expense will be recognized over a nine-year period, with three years remaining under the amended NMTC Fund, using the cost method in accordance with the authoritative guidance for investments. The basis of the investment is reduced by the grants received under Section 1603 of the ARRA, which allows certain projects to receive a federal grant in lieu of tax credits, and other cash. Periodic amortization of the investment and the deferred taxes generated by the basis reduction temporary difference are included as components of income tax expense.

Other
On April 17, 2015, the EPA published the final rule in the Federal Register for regulating the disposal and management of CCRs from coal-fired power plants under “Subtitle D” of the Resource Conservation and Recovery Act. The “Subtitle D” option will regulate CCRs in a manner similar to industrial solid waste. The final rule does not require expensive synthetic lining of existing impoundments. Management is currently evaluating the effect of the final rule, and does not expect any adjustment to the ARO to have a material effect on the Registrants’ results of operations, financial condition, or cash flows.
Cleco has accrued for liabilities related to third parties and employee medical benefits.

Risks and Uncertainties
 
Cleco Corporation
Cleco Corporation could be subject to possible adverse consequences if Cleco’s counterparties fail to perform their obligations or if Cleco Corporation or its affiliates are not in compliance with loan agreements or bond indentures.

Other
Access to capital markets is a significant source of funding for both short- and long-term capital requirements not satisfied by operating cash flows. If Cleco Corporation’s credit ratings were to be downgraded by Moody’s or S&P, Cleco Corporation would be required to pay additional fees and higher interest rates under its bank credit and other debt agreements.
Changes in the regulatory environment or market forces could cause Cleco to determine its assets have suffered an other-than-temporary decline in value, whereby an impairment would be required to be taken and Cleco’s financial condition could be materially adversely affected.

Cleco Power
Cleco Power began participating in the MISO market in December 2013. Energy prices in the MISO market are based on LMP, which includes a component directly related to congestion on the transmission system. Pricing zones with greater transmission congestion may have higher LMP costs. Physical transmission constraints present in the MISO market could increase energy costs within Cleco Power’s pricing zone. Cleco Power uses FTRs to mitigate the transmission congestion risk. Changes to anticipated transmission paths may result in an unexpected increase in energy costs to Cleco Power.
Access to capital markets is a significant source of funding for both short- and long-term capital requirements not satisfied by operating cash flows. Cleco Power pays fees and interest under its bank credit agreements based on the highest rating held. If Cleco Power’s credit ratings were to be downgraded by Moody’s or S&P, Cleco Power would be required to pay additional fees and higher interest rates under its bank credit agreements. Cleco Power’s collateral for derivatives is based on the lowest rating held. If Cleco Power’s credit ratings were to be downgraded by Moody’s or S&P, Cleco Power would be required to pay additional collateral for derivatives.