XML 121 R13.htm IDEA: XBRL DOCUMENT v2.4.1.9
Regulatory Assets and Liabilities Regulatory Assets and Liabilities
12 Months Ended
Dec. 31, 2014
Regulatory Assets and Liabilities [Abstract]  
Regulatory Assets and Liabilities
Note 3 — Regulatory Assets and Liabilities
Cleco Power follows the authoritative guidance on regulated operations, which allows utilities to capitalize or defer certain costs for recovery from customers and to recognize a liability for amounts expected to be returned to customers based on regulatory approval and management’s ongoing assessment that it is probable these items will be recovered or refunded through the ratemaking process.
Under the current regulatory environment, Cleco Power believes these regulatory assets will be fully recoverable; however, if in the future, as a result of regulatory changes or competition, Cleco Power’s ability to recover these regulatory assets would no longer be probable, then to the extent that such regulatory assets were determined not to be recoverable, Cleco Power would be required to write-down such assets. In addition, potential deregulation of the industry or possible future changes in the method of rate regulation of Cleco Power could require discontinuance of the application of these authoritative guidelines.
The following table summarizes Cleco Power’s regulatory assets and liabilities:
 
AT DEC. 31,
 
 
REMAINING
RECOVERY PERIOD

(THOUSANDS)
2014

 
2013

 
Total federal regulatory asset — income taxes
$
124

 
$
12,528

 
 
Total state regulatory asset — income taxes
106,964

 
89,050

 
 
AFUDC
129,545

 
130,488

 
 
Total investment tax credit
(2,263
)
 
(2,893
)
 
 
Total regulatory assets — deferred taxes, net
234,370

 
229,173

 
*

Mining costs
11,470

 
14,019

 
4.5 yrs.

Interest costs
5,582

 
5,943

 
25 yrs.

AROs (1)
1,029

 
936

 
*

Postretirement costs (1)
160,903

 
93,333

 
*

Tree trimming costs
8,066

 
4,840

 
4 yrs.

Training costs
7,019

 
7,175

 
45 yrs.

Surcredits, net (2)
13,587

 
16,738

 
3.5 yrs.

Amended lignite mining agreement contingency (1)
3,781

 
3,781

 
*

PPA capacity costs

 
9,749

 

AMI deferred revenue requirement
5,863

 
4,682

 
11 yrs.

Production operations and maintenance expenses
14,761

 
8,459

 
*

AFUDC equity gross-up (2)
72,859

 
73,306

 
*

Rate case costs

 
45

 

Acadia Unit 1 acquisition costs
2,653

 
2,760

 
25 yrs.

Financing costs
9,402

 
9,772

 
*

Biomass costs
82

 
114

 
3 yrs.

MISO integration costs
3,275

 

 
3.5 yrs.

Coughlin transaction costs
1,060

 

 
35 yrs.

Corporate franchise tax
1,223

 

 
0.5 yrs.

Acadia FRP true-up
754

 

 
0.5 yrs.

Energy efficiency
114

 

 
1 yr.

Other
596

 

 
2.5 yrs.

Total regulatory assets
324,079

 
255,652

 
 

PPA true-up
(624
)
 

 
0.5 yrs.

Fuel and purchased power
21,554

 
(3,869
)
 
*

Total regulatory assets, net
$
579,379

 
$
480,956

 
 

(1)Represents regulatory assets in which cash has not yet been expended and the assets are offset by liabilities that do not incur a carrying cost.
(2)Represents regulatory assets for past expenditures that were not earning a return on investment at December 31, 2014.
* For information related to the remaining recovery periods, refer to the disclosures below for each specific regulatory asset.


Income Taxes
Cleco Power has recorded a net regulatory asset related to deferred income taxes in accordance with the authoritative guidance on income taxes. The related regulatory asset or liability recorded represents the effect of tax benefits or detriments that must be flowed through to customers as they are received or paid. The amounts deferred are attributable to differences between book and tax recovery periods.
Mining Costs
Cleco Power operates a generating unit jointly owned with SWEPCO that uses lignite as its fuel source. Cleco Power, along with SWEPCO, maintains a Lignite Mining Agreement with DHLC, the operator of the Dolet Hills Mine. As ordered by the LPSC, Cleco Power’s retail customers began receiving fuel cost savings through the year 2011 while actual mining costs incurred above a certain percentage of the benchmark price were deferred, and could be recovered from retail customers through the FAC only when the actual mining costs are below a certain percentage of the benchmark price.
In 2006, Cleco Power recognized that there was a possibility it may not recover all or part of the lignite mining costs it had deferred and sought relief from the LPSC. In December 2007, the LPSC approved a settlement agreement between Cleco Power, SWEPCO, and the LPSC Staff authorizing Cleco Power to recover the existing deferred mining cost balance, including interest, over 11.5 years. In connection with its approval of the Oxbow Lignite Mine acquisition, in 2009, the LPSC agreed to discontinue benchmarking and the corresponding potential to defer future lignite mining costs while preserving the recovery of the legacy deferred fuel balance previously authorized.
 
Interest Costs
Cleco Power’s deferred interest costs include additional deferred capital construction financing costs authorized by the LPSC. These costs are being amortized over the estimated lives of the respective assets constructed.
 
AROs
The regulatory asset represents amounts associated with Cleco Power’s AROs. Applying the authoritative guidance for asset retirement and environmental obligations, Cleco Power has recorded an ARO for the retirement of certain ash disposal facilities. At December 31, 2014 and 2013, Cleco Power had $5.1 million and $0.9 million, respectively, in AROs recorded in other deferred credits. In December 2014, Cleco Power recorded an additional $4.1 million of AROs related to ash disposal facilities at Cleco Power’s generating stations. The related ARO asset will be depreciated over the remaining life of the units. For more information on the accounting treatment of Cleco Power’s AROs, see Note 2 — “Summary of Significant Accounting Policies — AROs.”
 
Postretirement Costs
Authoritative guidance on retirement benefits compensation requires companies to recognize the funded status of their postretirement benefit plans as a net liability or asset. The net liability or asset is defined as the difference between the benefit obligation and the fair market value of plan assets. For defined benefit pension plans, the benefit obligation is the projected benefit obligation. Historically, the LPSC has allowed Cleco Power to recover pension plan expense. Cleco Power, therefore, recognizes a regulatory asset based on its determination that these costs can be collected from customers. These costs are amortized to pension expense over the average service life of the remaining plan participants, 10.4 years for Cleco’s plan, when it exceeds certain thresholds. The amount and timing of the recovery will be based on the changing funded status of the pension plan in future periods. For more information on Cleco’s pension plan and adoption of these authoritative guidelines, see Note 8 — “Pension Plan and Employee Benefits.”
Tree Trimming Costs
In January 2008, the LPSC approved Cleco Power’s request to establish a regulatory asset for costs incurred to trim, cut, or remove trees that were damaged by Hurricanes Katrina and Rita, but were not addressed as part of the restoration efforts. The regulatory asset was capped at $12.0 million in actual expenditures, plus a 12.4% grossed-up rate of return. Recovery of these expenditures was approved by the LPSC in October 2009. In February 2010, Cleco Power began amortizing the regulatory asset over a five-year period.
In January 2013, Cleco Power requested to expend and defer up to $8.0 million in additional tree management costs. Cleco Power requested similar accounting treatment as authorized in the initial tree extraction request and requested authorization to accrue actual expenditures to a regulatory asset through the completion date of the tree extraction effort. The LPSC approved this request in April 2013. Cleco Power completed the tree extraction project in February 2015.
 
Training Costs
In February 2008, the LPSC approved Cleco Power’s request to establish a regulatory asset for training costs associated with existing processes and technology for new employees at Madison Unit 3. Recovery of these expenditures was approved by the LPSC in October 2009. In February 2010, Cleco Power began amortizing the regulatory asset over a 50-year period.

Surcredits, Net
Cleco Power has recorded surcredits as the result of a settlement with the LPSC that addressed, among other things, the recovery of the storm damages related to hurricanes and uncertain tax positions. In the settlement, Cleco Power was required to implement surcredits to provide ratepayers with the economic benefit of the carrying charges of certain accumulated deferred income tax liabilities at a rate of return which was set by the LPSC. The settlement, through a true-up mechanism, allows the surcredits to be adjusted to reflect the actual tax deductions allowed by the IRS.
Cleco Power also was allowed to record a corresponding regulatory asset in an amount representing the flow back of the carrying charges to ratepayers. This amount is being amortized over various terms of the established surcredits.
As a result of a settlement with the LPSC, Cleco Power is required to implement a surcredit when funds are withdrawn from the restricted storm reserve. In March 2014, Cleco Power withdrew $4.0 million from the restricted storm reserve to pay for storm damages, resulting in the establishment of a new surcredit. This surcredit will be utilized to partially replenish the storm reserve.
In the third quarter of 2013 and the first quarter of 2014, Cleco Power recorded a true-up to the surcredits to reflect the actual tax deductions allowed by the IRS for storm damages and uncertain tax positions. As a result of the true-ups, Cleco Power has recorded a regulatory asset that represents excess surcredits refunded to customers that will be collected from ratepayers in future periods. These amounts are being collected and amortized over a four-year period.
On June 18, 2014, the LPSC approved Cleco Power’s FRP extension. A provision of the FRP extension was to reduce base rates by the amount of the surcredits, beginning July 1, 2014. For more information on the FRP extension, see Note 11 — “Electric Customer Credits.”

Amended Lignite Mining Agreement Contingency
In April 2009, Cleco Power and SWEPCO entered into a series of transactions to acquire additional lignite reserves and mining equipment from the North American Coal Corporation (NAC), each agreeing to purchase a 50% ownership interest in Oxbow from NAC for a combined price of $25.7 million. Cleco Power, SWEPCO, and DHLC entered into the Amended Lignite Mining Agreement which requires DHLC to mine lignite at the existing Dolet Hills Mine along with the Oxbow Mine and deliver the lignite to the Dolet Hills Power Station at cost plus a specified management fee. The mining areas are expected to be sufficient to provide the Dolet Hills Power Station with lignite fuel until at least 2036.
Among the provisions of the Amended Lignite Mining Agreement, it is a requirement that if DHLC is unable to pay for loans and lease payments when due, Cleco Power will pay 50% of the amounts due. Any payments under this provision will be considered a prepayment of lignite to be delivered in the future and will be credited to future invoices from DHLC. This provision meets the recognition requirements as a guarantee to an unrelated third party. Cleco Power recognized a liability of $3.8 million upon the closing of the transactions. A regulatory asset of $3.8 million was also recognized due to Cleco Power’s ability to recover prudent fuel costs from customers through the FAC. The liability and related regulatory asset will be derecognized when the Amended Lignite Mining Agreement terminates. The maximum projected payment by Cleco Power under this guarantee is estimated to be $69.3 million; however, the Amended Lignite Mining Agreement does not contain a cap. The projection is based on the forecasted loan and lease obligations to be incurred by DHLC, primarily for purchases of equipment. Cleco Power has the right to dispute the incurrence of loan and lease obligations through the review of the mining plan before the incurrence of such loan and lease obligations.
 
PPA Capacity Costs and PPA True-up
In March 2012, Cleco Power received approval from the LPSC for a three-year PPA with Evangeline providing 730 MW of capacity and energy beginning May 1, 2012, and ending April 30, 2015. The LPSC order allowed Cleco Power to defer and recover a portion of capacity costs associated with the PPA. On March 15, 2014, Coughlin was transferred to Cleco Power, and the PPA was terminated. At June 30, 2014, the regulatory asset was fully amortized.
In preparing the FRP monitoring report for the year ended June 30, 2014, Cleco Power determined it had recovered $0.6 million above the actual PPA capacity costs. Cleco Power recorded the overcollection as a regulatory liability and will return it to customers over 12 months beginning July 1, 2015.

AMI Deferred Revenue Requirement
In February 2011, the LPSC approved Cleco Power’s stipulated settlement in Docket No. U-31393 allowing Cleco Power to defer, as a regulatory asset, the estimated revenue requirements for the AMI project. The amount of the regulatory asset, including carrying charges, is capped by the LPSC at $20.0 million. On June 18, 2014, the LPSC approved Cleco Power’s FRP extension and the AMI regulatory asset and project capital costs were included in rate base. The AMI deferred revenue requirement is being recovered over the remaining economic life of the meters, or 11 years, beginning July 1, 2014.

Production Operations and Maintenance Expenses
In September 2009, the LPSC authorized Cleco Power to defer, as a regulatory asset, production operations and maintenance expenses, net of fuel and payroll, above the retail jurisdictional portion of $25.6 million annually (deferral threshold). On June 18, 2014, the LPSC approved Cleco Power’s FRP extension, which increased the operations and maintenance deferral threshold to $45.0 million annually. The amount of the regulatory asset is capped at $23.0 million. Also, as part of the FRP extension, the LPSC allowed Cleco Power to recover the amount deferred in any calendar year over the following three-year regulatory period, beginning on July 1, when the annual rates are set. In December 2013, Cleco Power deferred $8.5 million as a regulatory asset and began recovering this amount on July 1, 2014. In December 2014, Cleco Power deferred an additional $7.7 million as a regulatory asset and will begin recovering this amount on July 1, 2015.

AFUDC Equity Gross-Up
Cleco Power capitalizes equity AFUDC as a cost component of construction projects in accordance with the authoritative guidance for regulated operations. Cleco Power has recorded a regulatory asset to recover the tax gross-up related to the equity component of AFUDC. These costs are being amortized over the estimated lives of the respective assets constructed.
 
Rate Case Costs
In September 2009, the LPSC approved Cleco Power’s request to recover costs incurred as a result of Cleco Power’s rate case filed in July 2008. The new rates became effective upon the commercial operation of Madison Unit 3 on February 12, 2010, and Cleco Power began amortizing the regulatory asset over a four-year period. At December 31, 2014, the regulatory asset was fully amortized.

Acadia Unit 1 Acquisition Costs
In October 2009, the LPSC approved Cleco Power’s request to establish a regulatory asset for costs incurred as a result of the acquisition by Cleco Power of Acadia Unit 1 and half of Acadia Power Station’s related common facilities. Recovery of these expenditures was approved by the LPSC in October 2009. The new rates became effective upon the commencement of commercial operation of Madison Unit 3 and Cleco Power began amortizing the regulatory asset over a 30-year period.

Financing Costs
In 2011, Cleco Power entered into and settled two treasury rate locks. Also in 2011, Cleco Power entered into a forward starting swap contract. These derivatives were entered into in order to mitigate the interest rate exposure on coupon payments related to forecasted debt issuances. In May 2013, the forward starting interest rate swap was settled at a loss of $3.3 million. Cleco Power deferred $2.9 million of the losses as a regulatory asset, which is being amortized over the terms of the related debt issuances.

Biomass Costs
In November 2011, the LPSC approved Cleco Power’s request to establish a regulatory asset for the non-fuel, non-capital portion of costs incurred to conduct a test burn of biomass fuel at Madison Unit 3. In August 2012, Cleco Power began amortizing these costs over a five-year period.

MISO Integration Costs
On June 18, 2014, the LPSC approved Cleco Power’s request to recover the non-capital integration costs associated with Cleco Power joining MISO. The MISO integration costs are being recovered over a four-year period, beginning July 1, 2014.

Coughlin Transaction Costs
On January 15, 2014, the LPSC authorized Cleco Power to create a regulatory asset for the Coughlin transfer transaction costs. The Coughlin transaction costs are being recovered over a 35-year period, beginning July 1, 2014.

Corporate Franchise Tax
As part of the FRP extension approved by the LPSC on June 18, 2014, Cleco Power was authorized to recover the retail portion of state corporate franchise taxes paid through a rider. In April 2014, a payment of $3.7 million was remitted to the State of Louisiana, of which the retail portion was $3.0 million. The deferred corporate franchise taxes are being recovered over 12 months, beginning July 1, 2014. In the third quarter of 2014, Cleco filed its franchise tax return, which reflected a corporate franchise tax of $3.0 million, of which the retail portion was $2.4 million. At December 31, 2014, Cleco had a regulatory liability of $0.3 million for amounts overcollected from July to December 2014 which is netted against the remaining regulatory asset of $1.5 million. The overcollection at December 31, 2014 along with future overcollections in January through June 2015 will be returned to customers when the new FRP rates are set beginning July 1, 2015.

Acadia FRP True-up
For the FRP period July 1, 2013 through June 30, 2014, Cleco Power was authorized by the LPSC to recover the estimated revenue requirement of $58.3 million related to Acadia Unit 1. In June 2014, Cleco Power determined that it had under-recovered $0.8 million in revenue during the period from customers based on the actual revenue requirement for Acadia Unit 1. The amount representing the under-collection was deferred and is expected to be recovered from customers over 12 months, beginning July 1, 2015.

Energy Efficiency
In September 2013, the LPSC issued a General Order adopting rules promoting energy efficiency programs by jurisdictional electric and natural gas utilities. Cleco Power subsequently filed with the LPSC its intent to participate in the Phase I Quick Start portion of the LPSC’s energy efficiency initiative, which runs November 1, 2014 through June 30, 2017. During Phase I, Cleco Power designed several energy efficiency programs and began offering these programs to customers in November 2014. The incremental costs incurred by Cleco Power to design and implement the programs was recorded as a regulatory asset and are being recovered from customers over the initial year of Phase I.

Other
On June 18, 2014, the LPSC approved Cleco Power’s FRP extension which authorized the recovery of previously deferred costs incurred as a result of Cleco Power’s FRP extension filing, the 2003 through 2008 fuel audit, and a biomass study. These costs are being recovered over a three-year period, beginning July 1, 2014.

Fuel and Purchased Power
The cost of fuel used for electric generation and the cost of power purchased for utility customers are recovered through the LPSC-established FAC, which enables Cleco Power to pass on to its customers substantially all such charges. For 2014, approximately 82% of Cleco Power’s total fuel cost was regulated by the LPSC, while the remainder was regulated by FERC.
The $25.4 million increase in the under/over-recovered costs was primarily due to an $18.3 million increase for the settlement of previously open FTR positions and a mark-to-market loss on current open FTR positions. Also contributing was a $7.1 million increase in fuel costs and power purchases as a result of extended plant outages, the addition of a new wholesale customer, and the timing of collection of fuel expenses.