XML 72 R13.htm IDEA: XBRL DOCUMENT v2.4.0.8
Regulatory Assets and Liabilities
9 Months Ended
Sep. 30, 2013
Regulatory Assets and Liabilities Disclosure [Abstract]  
Regulatory Assets and Liabilities
Note 3 — Regulatory Assets and Liabilities
Cleco Power follows the authoritative guidance on regulated operations, which allows utilities to capitalize or defer certain costs based on regulatory approval and management’s ongoing assessment that it is probable these items will be recovered through the ratemaking process. The following table summarizes Cleco Power’s regulatory assets and liabilities at September 30, 2013 and December 31, 2012:
(THOUSANDS)
AT SEPT. 30, 2013

 
AT DEC. 31, 2012

Regulatory assets – deferred taxes, net
$
217,550

 
$
210,445

Mining costs
$
14,657

 
$
16,569

Interest costs
6,033

 
6,304

Asset removal costs
919

 
867

Postretirement plan costs
146,597

 
156,458

Tree trimming costs
4,945

 
5,656

Training costs
7,214

 
7,330

Surcredits, net
16,738

 
6,211

Construction carrying costs

 
4,697

Lignite mining agreement contingency
3,781

 
3,781

Power purchase agreement capacity costs
13,316

 
6,217

AMI deferred revenue requirement
3,960

 
1,483

AFUDC equity gross-up
73,518

 
74,158

Rate case costs
179

 
581

Acadia Unit 1 acquisition costs
2,786

 
2,865

IRP/RFP costs

 
39

AMI pilot costs

 
22

Financing costs
9,864

 
7,282

Biomass costs
122

 
145

Total regulatory assets – other
$
304,629

 
$
300,665

Construction carrying costs

 
(8,255
)
Fuel and purchased power
6,851

 
7,833

Total regulatory assets, net
$
529,030

 
$
510,688



Surcredits, Net
Cleco Power has recorded surcredits as the result of a settlement with the LPSC that addressed, among other things, the recovery of the storm damages related to hurricanes and uncertain tax positions. In the settlement, Cleco Power was required to implement surcredits to provide ratepayers with the economic benefit of the carrying charges of certain accumulated deferred income tax liabilities at a rate of return which was set by the LPSC. The settlement, through a true-up mechanism, allows the surcredits to be adjusted to reflect the actual tax deductions allowed by the IRS.
Cleco Power also was allowed to record a corresponding regulatory asset in an amount representing the flow back of the carrying charges to ratepayers. This amount is being amortized over various terms of the established surcredits.
As a result of a settlement with the LPSC, Cleco Power is required to implement a surcredit when funds are withdrawn from the restricted storm reserve. In September 2012, Cleco Power withdrew $10.0 million from the restricted storm reserve to pay for storm damages, resulting in the establishment of a new surcredit. This surcredit will be utilized to partially replenish the storm reserve.
In the third quarter of 2013, Cleco Power recorded a true-up to the surcredits to reflect the actual tax deductions allowed by the IRS for storm damages and uncertain tax positions. As a result of the true-up, Cleco Power has recorded a regulatory asset that represents the amounts that will be collected from ratepayers in future periods.

Construction Carrying Costs
In February 2006, the LPSC approved Cleco Power’s plans to build Madison Unit 3. Terms of the approval included authorization for Cleco Power to collect from customers a portion of the carrying costs of capital during the construction phase of the unit. Cleco Power’s retail rate plan established that Cleco Power return carrying costs to customers and record a regulatory asset for all carrying costs incurred by Cleco Power above the actual amount collected from customers. These costs were amortized over a four-year period. As of June 30, 2013, Cleco Power had returned $166.0 million to customers, which represents all amounts due to be refunded to customers.

Power Purchase Agreement Capacity Costs
In March 2012, Cleco Power received approval from the LPSC for a three-year power purchase agreement with Evangeline providing 730 MW of capacity and energy beginning May 1, 2012 and ending April 30, 2015. The LPSC order allows Cleco Power to defer and recover a portion of capacity costs associated with the power purchase agreement. The deferred costs are being collected over the term of the contract.

AMI Deferred Revenue Requirement
In February 2011, the LPSC approved Cleco Power’s stipulated settlement in Docket No. U-31393 allowing Cleco Power to defer, as a regulatory asset, the estimated revenue requirements for the AMI project. The amount of the regulatory asset, including carrying charges, is capped by the LPSC at $20.0 million. The regulatory asset will amortize over the economic life of the project, currently estimated at 15 years.

Financing Costs
In 2011, Cleco Power entered into and settled two treasury rate locks. Also in 2011, Cleco Power entered into a forward starting swap contract. These derivatives were entered into in order to mitigate the interest rate exposure on coupon payments related to forecasted debt issuances. In May 2013, the forward starting interest rate swap was settled at a loss of $3.3 million. Cleco Power deferred $2.9 million of the losses as a regulatory asset. As a result of management’s assessment that it is probable that these costs will be recovered through the ratemaking process, Cleco Power is amortizing the regulatory asset over the terms of the related debt issuances.
 
Fuel and Purchased Power Costs
The cost of fuel used for electric generation and the cost of power purchased for utility customers are recovered through the LPSC-established FAC, which enables Cleco Power to pass on to its customers substantially all such charges. For the three months ended September 30, 2013, approximately 88% of Cleco Power’s total fuel cost was regulated by the LPSC, while the remainder was regulated by FERC.
The $1.0 million decrease in the under-recovered costs was primarily due to higher fuel cost recovery revenue partially offset by an increase in per-unit costs of fuel and purchased power and higher volumes of fuel used for electric generation.