XML 120 R13.htm IDEA: XBRL DOCUMENT v2.4.0.8
Regulatory Assets and Liabilities
6 Months Ended
Jun. 30, 2013
Regulatory Assets and Liabilities Disclosure [Abstract]  
Regulatory Assets and Liabilities
Note 3 — Regulatory Assets and Liabilities
Cleco Power follows the authoritative guidance on regulated operations, which allows utilities to capitalize or defer certain costs based on regulatory approval and management’s ongoing assessment that it is probable these items will be recovered through the ratemaking process. The following table summarizes Cleco Power’s regulatory assets and liabilities at June 30, 2013 and December 31, 2012:
(THOUSANDS)
AT JUNE 30, 2013

 
AT DEC. 31, 2012

Regulatory assets – deferred taxes, net
$
213,061

 
$
210,445

Mining costs
$
15,294

 
$
16,569

Interest costs
6,123

 
6,304

Asset removal costs
901

 
867

Postretirement plan costs
149,884

 
156,458

Tree trimming costs
4,299

 
5,656

Training costs
7,252

 
7,330

Storm surcredits, net
7,654

 
6,211

Construction carrying costs
1,563

 
4,697

Lignite mining agreement contingency
3,781

 
3,781

Power purchase agreement capacity costs
11,912

 
6,217

AMI deferred revenue requirement
2,907

 
1,483

AFUDC equity gross-up
73,785

 
74,158

Rate case costs
313

 
581

Acadia Unit 1 acquisition costs
2,813

 
2,865

IRP/RFP costs

 
39

AMI pilot costs

 
22

Financing costs
9,957

 
7,282

Biomass costs
129

 
145

Total regulatory assets – other
$
298,567

 
$
300,665

Construction carrying costs

 
(8,255
)
Fuel and purchased power
9,593

 
7,833

Total regulatory assets, net
$
521,221

 
$
510,688



Tree Trimming Costs
In January 2008, the LPSC approved Cleco Power’s request to establish a regulatory asset for costs incurred to trim, cut, or remove trees that were damaged by hurricanes Katrina and Rita, but were not addressed as part of the restoration efforts. The regulatory asset was capped at $12.0 million in actual expenditures plus a 12.4% grossed-up rate of return. Recovery of these expenditures was requested in Cleco Power’s base rate application filed in July 2008 and was approved by the LPSC in October 2009. In February 2010, Cleco Power began amortizing the regulatory asset over a five-year period.
On January 29, 2013, Cleco Power requested to expend and defer up to $8.0 million in additional tree management costs. Cleco Power requested similar accounting treatment as authorized in the initial tree extraction request and requested authorization to accrue actual expenditures to a regulatory asset through the completion date of the tree extraction effort. Cleco Power anticipates a completion date of December 31, 2014 for this phase of the tree extraction project. The LPSC approved this request on April 4, 2013.

Construction Carrying Costs
In February 2006, the LPSC approved Cleco Power’s plans to build Madison Unit 3. Terms of the approval included authorization for Cleco Power to collect from customers a portion of the carrying costs of capital during the construction phase of the unit. Cleco Power’s retail rate plan established that Cleco Power return carrying costs to customers and record a regulatory asset for all carrying costs incurred by Cleco Power above the actual amount collected from customers. These costs are being amortized over a four-year period. As of June 30, 2013, Cleco Power had returned $166.0 million to customers, which represents all amounts due to be refunded to customers.

Power Purchase Agreement Capacity Costs
In March 2012, Cleco Power received approval from the LPSC for a three-year power purchase agreement with Evangeline providing 730 MW of capacity and energy beginning May 1, 2012, and ending April 30, 2015. The LPSC order allows Cleco Power to defer and recover a portion of capacity costs associated with the power purchase agreement. The deferred costs are being collected over the term of the contract.

AMI Deferred Revenue Requirement
In February 2011, the LPSC approved Cleco Power’s stipulated settlement in Docket No. U-31393 allowing Cleco Power to defer, as a regulatory asset, the estimated revenue requirements for the AMI project. The amount of the regulatory asset, including carrying charges, is capped by the LPSC at $20.0 million. The regulatory asset will amortize over the economic life of the project, currently estimated at 15 years.

Financing Costs
In 2011, Cleco Power entered into and settled two treasury rate locks. Also in 2011, Cleco Power entered into a forward starting swap contract. These derivatives were entered into in order to mitigate the interest rate exposure on coupon payments related to forecasted debt issuances. In May 2013, the forward starting interest rate swap was settled at a loss of $3.3 million. Cleco Power deferred $2.9 million of the losses as a regulatory asset. As a result of management’s assessment that it is probable that these costs will be recovered through the rate-making process, in May 2013, Cleco Power began amortizing the regulatory asset over the 25-year term of the related debt.
 
Fuel and Purchased Power Costs
The cost of fuel used for electric generation and the cost of power purchased for utility customers are recovered through the LPSC-established FAC, which enables Cleco Power to pass on to its customers substantially all such charges. For the three months ended June 30, 2013, approximately 88% of Cleco Power’s total fuel cost was regulated by the LPSC, while the remainder was regulated by FERC.
The $1.8 million increase in the under-recovered costs was primarily due to an increase in per-unit costs of fuel and purchased power and higher volumes of fuel used for electric generation, partially offset by lower volumes of purchased power.