XML 116 R12.htm IDEA: XBRL DOCUMENT v2.4.0.6
Regulatory Assets and Liabilities
12 Months Ended
Dec. 31, 2012
Regulatory Assets and Liabilities Disclosure [Abstract]  
Regulatory Assets and Liabilities
Cleco Power follows the authoritative guidance on regulated operations, which allows utilities to capitalize or defer certain costs based on regulatory approval and management’s ongoing assessment that it is probable these items will be recovered through the ratemaking process.
Under the current regulatory environment, Cleco Power believes these regulatory assets will be fully recoverable; however, if in the future, as a result of regulatory changes or competition, Cleco Power’s ability to recover these regulatory assets would no longer be probable, then to the extent that such regulatory assets were determined not to be recoverable, Cleco Power would be required to write-down such assets. In addition, potential deregulation of the industry or possible future changes in the method of rate regulation of Cleco Power could require discontinuance of the application of these authoritative guidelines.
The following chart summarizes Cleco Power’s regulatory assets and liabilities at December 31, 2012 and 2011.
 
AT DEC. 31,
 
 
REMAINING
RECOVERY PERIOD
RETURN ON EQUITY
(THOUSANDS)
2012

 
2011

 
Total federal regulatory asset — income taxes
$
24,222

 
$
34,127

 
N/A

 
Total state regulatory asset — income taxes
57,480

 
51,720

 
N/A

 
AFUDC
132,267

 
132,802

 
N/A

 
Total investment tax credit
(3,524
)
 
(4,228
)
 
N/A

 
Total regulatory assets — deferred taxes, net
210,445

 
214,421

 
 
 
Mining costs
16,569

 
19,117

 
6.5 yrs.

No
Interest costs
6,304

 
6,667

 
27 yrs.

No
Asset removal costs
867

 
829

 
37 yrs.

No
Postretirement plan costs
156,458

 
132,556

 
N/A

No
Tree trimming costs
5,656

 
8,371

 
2 yrs.

Yes
Training costs
7,330

 
7,486

 
47 yrs.

Yes
Storm surcredits, net
6,211

 
9,254

 
10 yrs.

No
Construction carrying costs
4,697

 
10,883

 
0.75 yrs.

No
Lignite mining agreement contingency
3,781

 
3,781

 
N/A

No
Power purchase agreement capacity costs
6,217

 

 
2.5 yrs.

Yes
AMI deferred revenue requirement
1,483

 

 
15 yrs.

Yes
AFUDC equity gross-up
74,158

 
74,346

 
N/A

No
Rate case costs
581

 
1,117

 
1 yr.

No
Acadia Unit 1 acquisition costs
2,865

 
2,971

 
27 yrs.

No
IRP/RFP costs
39

 
508

 

No
AMI pilot costs
22

 
153

 
0.5 yrs.

No
Financing costs
7,282

 
4,433

 
29 yrs.

No
Biomass costs
145

 

 
5 yrs.

No
Total regulatory assets - other
300,665

 
282,472

 
 

 
Construction carrying costs
(8,255
)
 
(40,322
)
 
0.6 yrs.

No
Fuel and purchased power
7,833

 
2,136

 
N/A

No
Total regulatory assets, net
$
510,688

 
$
458,707

 
 

 

 
Income Taxes
Cleco Power has recorded a net regulatory asset related to deferred income taxes in accordance with the authoritative guidance on income taxes. The related regulatory asset or liability recorded represents the effect of tax benefits or detriments that must be flowed through to customers as they are received or paid. Generally, the recovery periods for regulatory assets and liabilities are based on assets’ lives, which are typically 30 years or greater. The amounts deferred are attributable to differences between book and tax recovery periods.
 
Mining Costs
Cleco Power operates a generating unit jointly owned with SWEPCO that uses lignite as its fuel source.
Cleco Power (along with SWEPCO) maintains a Lignite Mining Agreement with DHLC, the operator of the Dolet Hills mine. As ordered then by the LPSC, Cleco Power’s retail customers began receiving fuel cost savings through the year 2011 while actual mining costs incurred above a certain percentage of the benchmark price were deferred, and could be recovered from retail customers through the FAC only when the actual mining costs are below a certain percentage of the benchmark price. The benchmark price used the GDP-IPD index as a proxy for the numerous escalators in the previous mining contract. During the course of the contract, Cleco Power and SWEPCO determined that the GDP-IPD index did not appropriately reflect the increase in mining costs caused by sharp increases in diesel fuel and electricity costs associated with the mining operation. Because of this disconnect between the GDP-IPD index and actual mining costs, a significant amount of mining costs was being deferred by Cleco Power.
In 2006, Cleco Power recognized that there was a possibility it may not recover all or part of the lignite mining costs it had deferred and sought relief from the LPSC. In December 2007, the LPSC approved a settlement agreement between Cleco Power, SWEPCO and the LPSC Staff authorizing Cleco Power to recover the existing deferred mining cost balance, including interest, over approximately 11.5 years. The settlement also established a new benchmark utilizing the contract’s escalators to assure a minimum 2% savings to customers compared to the costs under the prior mining contract. Under the settlement, the benchmarking was scheduled to end after April 2011. Cleco Power and SWEPCO also agreed to commit to continued operation of the mining operation through 2026 as long as the operation of the mine was considered prudent. Cleco Power did not record any additional deferred fuel costs under the new benchmarking method.
In connection with its approval of the Oxbow Lignite Mine acquisition, in 2009 the LPSC agreed to discontinue benchmarking and the corresponding potential to defer future lignite mining costs while preserving the recovery of the legacy deferred fuel balance previously authorized.
 
Interest Costs
Cleco Power’s deferred interest costs include additional deferred capital construction financing costs authorized by the LPSC. These costs are being amortized over the estimated lives of the respective assets constructed.
 
Asset Removal Costs
Under the authoritative guidance for asset retirement and environmental obligations, Cleco Power determined that a liability exists for cleanup and closing costs of solid waste facilities associated with its generating stations that use lignite for fuel. Applying these guidelines, Cleco Power determined that a liability exists for costs which may be incurred in the future for removal of asbestos from its general service buildings, the removal of transmission towers on leased right-of-ways and for the abatement of PCBs in transformers.
At December 31, 2012 and 2011, the liability for solid waste facility closure costs at the generating station using lignite is estimated at $0.6 million and $0.5 million, respectively, and is included in other deferred credits. At December 31, 2012 and 2011, Cleco Power’s liability for removal of asbestos is estimated at $0.3 million and also is included in other deferred credits.
 
Postretirement Costs
Authoritative guidance on retirement benefits compensation requires companies to recognize the funded status of their postretirement benefit plans as a net liability or asset. The net liability or asset is defined as the difference between the benefit obligation and the fair market value of plan assets. For defined benefit pension plans, the benefit obligation is the projected benefit obligation. Historically, the LPSC has allowed Cleco Power to recover pension plan expense. Cleco Power, therefore, recognizes a regulatory asset based on its determination that these costs can be collected from customers. The amount and timing of the recovery will be based on the changing funded status of the pension plan in future periods. For more information on Cleco’s pension plan and adoption of these authoritative guidelines, see Note 8 — “Pension Plan and Employee Benefits.”
 
Tree Trimming Costs
In January 2008, the LPSC approved Cleco Power’s request to establish a regulatory asset for costs incurred to trim, cut, or remove trees that were damaged by hurricanes Katrina and Rita, but were not addressed as part of the restoration efforts. The regulatory asset was capped at $12.0 million in actual expenditures plus a 12.4% grossed-up rate of return. Recovery of these expenditures was requested in Cleco Power’s base rate application filed in July 2008 and was approved by the LPSC in October 2009. In February 2010, Cleco Power began amortizing the regulatory asset over a five-year period.
 
Training Costs
In February 2008, the LPSC approved Cleco Power’s request to establish a regulatory asset which is being charged with training costs associated with existing processes and technology for new employees at Madison Unit 3. Recovery of these expenditures was requested in Cleco Power’s base rate application filed in July 2008 and were covered by the retail rate plan which was approved by the LPSC in October 2009. In February 2010, Cleco Power began amortizing the regulatory asset over a 50-year period.
 
Storm Surcredits, Net
Cleco Power has recorded a storm surcredit as the result of a settlement with the LPSC that addressed, among other things, the recovery of the storm damages related to hurricanes Katrina and Rita. In the settlement, Cleco Power was required to implement a surcredit to provide ratepayers with the economic benefit of the carrying charges of all accumulated deferred income tax liabilities due to the storm damage costs at a 12.2% rate of return which was set in LPSC Order No. U-29157A. The accumulated deferred income tax liability includes the tax benefit on deductions for operation and maintenance expenses, casualty loss, and depreciation against taxable income in the year incurred and all subsequent periods. The settlement, through a true-up mechanism, allows the surcredit to be adjusted to reflect the actual tax deductions allowed by the IRS.
Cleco Power also was allowed to record a corresponding regulatory asset in an amount representing the flow back of the carrying charges to ratepayers. This amount is being amortized over the life of the storm recovery bonds. The corresponding regulatory asset will be adjusted through the same surcredit true-up mechanism at the time of a final determination of the tax benefit for storm damage costs by the IRS.
As a result of the settlement with the LPSC, Cleco Power is required to implement a surcredit when funds are withdrawn from the restricted storm reserve. In September 2012 and September 2011, Cleco Power withdrew $10.0 million and $2.0 million, respectively, from the restricted storm reserve to pay for storm damages resulting in the establishment of a surcredit. Cleco Power will replenish the restricted storm reserve with the surcredit.
 
Construction Carrying Costs
In February 2006, the LPSC approved Cleco Power’s plans to build Madison Unit 3. Terms of the approval included authorization for Cleco Power to collect from customers an amount equal to 75% of the LPSC-jurisdictional portion of the carrying costs of capital during the construction phase of the unit. Cleco Power’s retail rate plan, which was approved in October 2009, established that Cleco Power return carrying costs to customers and record a regulatory asset for all carrying costs incurred by Cleco Power above the actual amount collected from customers. On February 12, 2010, Madison Unit 3 commenced commercial operations and Cleco Power began returning the construction carrying costs to customers. These costs are being amortized over a four-year period. At December 31, 2012, the regulatory liability and the related regulatory asset were $8.3 million and $4.7 million, respectively. As of December 31, 2012, Cleco Power had returned $158.2 million to customers. At December 31, 2012, the remaining $8.3 million is due to be returned to customers within one year.
 
Amended Lignite Mining Agreement Contingency
In April 2009, Cleco Power and SWEPCO entered into a series of transactions to acquire additional lignite reserves and mining equipment from NAC, each agreeing to purchase a 50% ownership interest in Oxbow from NAC for a combined price of $25.7 million. Through mineral lease agreements and ownership of fee land, Oxbow controls approximately 43 million tons of lignite reserves in an area referred to as the Oxbow Mine. Cleco Power, SWEPCO, and DHLC entered into the Amended Lignite Mining Agreement which requires DHLC to mine lignite at the existing Dolet Hills Mine along with the Oxbow Mine and deliver the lignite to the Dolet Hills Power Station at cost plus a specified management fee. The two mining areas are expected to be sufficient to provide the Dolet Hills Power Station with lignite fuel until at least 2026.
Among the provisions of the Amended Lignite Mining Agreement, it is a requirement that if DHLC is unable to pay for loans and lease payments when due, Cleco Power will pay 50% of the amounts due. Any payments under this provision will be considered a prepayment of lignite to be delivered in the future and will be credited to future invoices from DHLC. This provision meets the recognition requirements as a guarantee to an unrelated third party. Cleco Power recognized a liability of $3.8 million upon the closing of the transactions. A regulatory asset of $3.8 million was also recognized due to Cleco Power’s ability to recover prudent fuel costs from customers through the FAC. The liability and related regulatory asset will be derecognized when the Amended Lignite Mining Agreement terminates. The maximum projected payment by Cleco Power under this guarantee is estimated to be $72.5 million; however, the Amended Lignite Mining Agreement does not contain a cap. The projection is based on the forecasted loan and lease obligations to be incurred by DHLC, primarily for purchases of equipment. Cleco Power has the right to dispute the incurrence of loan and lease obligations through the review of the mining plan before the incurrence of such loan and lease obligations.
 
Power Purchase Agreement Capacity Costs
In March 2012, Cleco Power received approval from the LPSC for a three-year power purchase agreement with Evangeline providing 730 MW of capacity and energy beginning May 1, 2012, and ending April 30, 2015. The LPSC order allows Cleco Power to defer and recover a portion of capacity costs associated with the power purchase agreement. The deferred costs are being collected over the term of the contract.

AMI Deferred Revenue Requirement
In February 2011, the LPSC approved Cleco Power’s stipulated settlement in Docket No. U-31393 allowing Cleco Power to defer, as a regulatory asset, the estimated revenue requirements for the AMI project. The amount of the regulatory asset, including carrying charges, was capped by the LPSC at $20.0 million. The regulatory asset will amortize by the end of the economic life of the project, currently estimated at 15 years.

AFUDC Equity Gross-Up
Cleco Power capitalizes equity AFUDC as a cost component of construction projects in accordance with the authoritative guidance for regulated operations. Cleco Power has recorded a regulatory asset to recover the tax gross-up related to the equity component of AFUDC. These costs are being amortized over the estimated lives of the respective assets constructed. In the first quarter of 2010, AFUDC equity gross-up was reclassed from Regulatory assets and liabilities – deferred taxes, net to Regulatory assets – other.
 
Rate Case Costs
In October 2009, the LPSC approved Cleco Power’s request to recover costs incurred as a result of Cleco Power’s rate case filed in July 2008. The new rates became effective upon the commercial operation of Madison Unit 3 on February 12, 2010, and Cleco Power began amortizing the regulatory asset over a four-year period.

Acadia Unit 1 Acquisition Costs
In October 2009, the LPSC approved Cleco Power’s request to establish a regulatory asset for costs incurred as a result of the acquisition by Cleco Power of Acadia Unit 1 and half of Acadia Power Station’s related common facilities. Recovery of these expenditures was requested in Cleco Power’s base rate application filed in July 2008, and these expenditures were covered by the retail rate plan which was approved by the LPSC in October 2009. The new rates became effective upon the commencement of commercial operation of Madison Unit 3 and Cleco Power began amortizing the regulatory asset over a 30-year period. For more information regarding the Acadia Unit 1 transaction, see Note 18 — “Acadia Transactions — Acadia Unit 1.”
 
IRP/RFP Costs
In October 2009, the LPSC approved Cleco Power’s request to establish a regulatory asset to recover IRP and RFP costs incurred. The new rates became effective upon the commencement of commercial operation of Madison Unit 3 and Cleco Power began amortizing the regulatory asset over a three-year period.
 
AMI Pilot Costs
In September 2009, the LPSC approved Cleco Power’s request to establish a regulatory asset to recover AMI pilot costs incurred. Recovery of these expenditures was approved by the LPSC in October 2009. The new rates became effective upon the commercial operation of Madison Unit 3. In March 2010, Cleco Power began amortizing these costs over a three-year period.
Financing Costs
In 2011, Cleco Power entered into and settled two treasury rate locks. Also in 2011, Cleco Power entered into a forward starting swap contract in order to mitigate the interest rate exposure on coupon payments related to a forecasted debt issuance. As a result of management’s assessment that it is probable that these costs will be recovered through the rate-making process, Cleco Power will amortize the regulatory asset over the term of the related debt issuance.

Biomass Test Burn Costs
In November 2011, the LPSC approved Cleco Power’s request to establish a regulatory asset for the non-fuel, non-capital portion of costs incurred to conduct a test burn of biomass fuel at Madison Unit 3. In August 2012, Cleco Power began amortizing these costs over a five-year period.

Fuel and Purchased Power Costs
The cost of fuel used for electric generation and the cost of power purchased for utility customers are recovered through the LPSC-established FAC, which enables Cleco Power to pass on to its customers substantially all such charges. For 2012, approximately 89% of Cleco Power’s total fuel cost was regulated by the LPSC, while the remainder was regulated by FERC.
The $5.7 million increase in the under-recovered costs was primarily due to an $12.2 million increase in fuel and purchased power costs. Partially offsetting this increase was a $6.5 million decrease in losses on natural gas positions.