XML 82 R10.htm IDEA: XBRL DOCUMENT v2.4.0.6
Regulatory Assets and Liabilities
3 Months Ended
Mar. 31, 2012
Regulatory Assets and Liabilities Disclosure [Abstract]  
Regulatory Assets and Liabilities
Note 3 — Regulatory Assets and Liabilities
Cleco Power follows the authoritative guidance on regulated operations, which allows utilities to capitalize or defer certain costs based on regulatory approval and management’s ongoing assessment that it is probable these items will be recovered through the ratemaking process. The following table summarizes Cleco Power’s regulatory assets and liabilities at March 31, 2012, and December 31, 2011:
 
AT MARCH 31,

 
AT DECEMBER 31,

(THOUSANDS)
2012

 
2011

Regulatory assets – deferred taxes, net
$
215,793

 
$
214,421

Mining costs
$
18,480

 
$
19,117

Interest costs
6,575

 
6,667

Asset removal costs
818

 
829

Postretirement plan costs
130,790

 
132,556

Tree trimming costs
7,693

 
8,371

Training costs
7,447

 
7,486

Storm surcredits, net
6,481

 
9,254

Construction carrying costs
9,395

 
10,883

Lignite mining agreement contingency
3,781

 
3,781

AFUDC equity gross-up
74,125

 
74,346

Rate case costs
983

 
1,117

Acadia Unit 1 acquisition costs
2,945

 
2,971

IRP/RFP costs
391

 
508

AMI pilot costs
120

 
153

Financing costs
6,944

 
4,433

Biomass costs
151

 

Total regulatory assets – other
$
277,119

 
$
282,472

Construction carrying costs
(31,552
)
 
(40,322
)
Fuel and purchased power
(6,198
)
 
2,136

Total regulatory assets, net
$
455,162

 
$
458,707


 
Construction Carrying Costs
In February 2006, the LPSC approved Cleco Power’s plans to build Madison Unit 3. Terms of the approval included authorization for Cleco Power to collect from customers an amount equal to 75% of the LPSC-jurisdictional portion of the carrying costs of capital during the construction phase of the unit. Cleco Power’s retail rate plan, which was approved in October 2009, established that Cleco Power return carrying costs to customers and record a regulatory asset for all carrying costs incurred by Cleco Power above the actual amount collected from customers. On February 12, 2010, Madison Unit 3 commenced commercial operations and Cleco Power began returning the construction carrying costs to customers. These costs are being amortized over a four-year period. As of March 31, 2012, Cleco Power had returned $134.9 million to customers. At March 31, 2012, $28.5 million was due to be returned to customers within one year.
 
Fuel and Purchased Power Costs
The cost of fuel used for electric generation and the cost of power purchased for utility customers are recovered through the LPSC-established fuel adjustment clause, which enables Cleco Power to pass on to its customers substantially all such charges. For the three months ended March 31, 2012, approximately 90% of Cleco Power’s total fuel cost was regulated by the LPSC, while the remainder was regulated by FERC.
The $8.3 million decrease was primarily due to $6.8 million of lower per unit costs of fuel and purchased power and a $2.0 million decrease in mark-to-market losses on natural gas positions, which was primarily due to the contractual expiration of certain positions.

Financing Costs
In 2011, Cleco Power entered into and settled two treasury rate locks. Of the $26.8 million in settlements, $7.0 million was recorded as a regulatory asset relating to ineffectiveness of the hedge relationship. As a result of management’s assessment that it is probable that the ineffectiveness will be recovered through the rate-making process, Cleco Power will amortize the regulatory asset over the 30-year term of the related debt issuance.

Biomass Test Burn Costs
In November 2011, the LPSC approved Cleco Power’s request to establish a regulatory asset for the non-fuel, non-capital portion of costs incurred to conduct a test burn of biomass fuel at Madison Unit 3. These costs will be amortized over a five-year period.