NOTE 10 - CALLAWAY ENERGY CENTER

Under the NWPA, the DOE is responsible for disposing of spent nuclear fuel from the Callaway energy center and other commercial nuclear power plants. Under the NWPA, Ameren and other utilities who own and operated those plants are responsible for paying the disposal costs. The NWPA established the fee that these utilities pay the federal government for disposing of the spent nuclear fuel at one mill, or one-tenth of one cent, for each kilowatt hour generated by those plants and sold. The NWPA also requires the DOE annually review the nuclear waste fee against the cost of the nuclear waste disposal program and to propose to the United States Congress any fee adjustment as necessary to offset the costs of the program. As required by the NWPA, Ameren and other utilities have entered into standard contracts with the federal government, which was represented by the DOE, implementing these provisions of the NWPA. Consistent with the NWPA and its contract, Ameren Missouri collects one mill from its electric customers for each kilowatt hour of electricity that it generates and sells from its Callaway energy center.

Although the NWPA and the standard contract provide that the federal government would begin to dispose of spent nuclear fuel by 1998, the federal government acknowledged since at least 1994 that it would not meet that date. The federal government is not currently predicting when it will begin to meet its disposal obligation. Ameren Missouri has sufficient installed capacity at the Callaway energy center to store the spent nuclear fuel generated at Callaway through 2020 and has the capability for additional storage capacity for spent nuclear fuel generated through the end of the energy center's licensed life.

Until January 2009, the DOE program provided for spent nuclear fuel disposal to take place at a geologic repository to be constructed at Yucca Mountain, Nevada. Beginning in January 2009, the Obama administration announced that a repository at Yucca Mountain was unworkable and has taken steps to terminate the Yucca Mountain program, while acknowledging the federal government's continuing obligation to dispose of utilities' spent nuclear fuel. The DOE has established an advisory commission to make recommendations for the storage and disposal of utilities' spent nuclear fuel. The commission's final recommendations are scheduled to be issued in January 2012.

 

In view of the federal government's efforts to terminate the Yucca Mountain program, the Nuclear Energy Institute, a number of individual utilities, and the National Association of Regulatory Utility Commissioners sued the DOE in the United States Court of Appeals for the District of Columbia Circuit seeking the suspension of the one mill nuclear waste fee in view of the DOE's failure to undertake an appropriate fee adequacy review that reflects the current state of the nuclear waste program. That case is pending. The delay in DOE carrying out its obligation to dispose of spent nuclear fuel from the Callaway energy center is not expected to adversely affect the continued operation of the energy center.

As a result of DOE's failure to build a repository for nuclear waste or otherwise fulfill its contract obligations, Ameren Missouri and other nuclear power plant owners sued DOE to recover costs incurred for ongoing storage of their spent fuel. Ameren Missouri filed suit in 2004 to recover approximately $13 million in costs that it incurred through 2009. This amount included the cost of reracking the Callaway energy center's spent fuel pool, as well as certain NRC fees, and Missouri ad valorem taxes that Ameren Missouri would not have incurred had DOE performed its contractual obligations. In June 2011, the parties reached a settlement that included a payment to Ameren Missouri of approximately $11 million for spent fuel storage and related costs through 2010, and thereafter, annual payment of such costs after they are incurred through 2013 or any other mutually agreed extension. As a result of this settlement agreement, Ameren Missouri recorded a pretax reduction of $2 million and $2 million to its "Operating Expenses - Depreciation and amortization" and "Operating Expenses - Other operations and maintenance" expense line items, respectively, on its statement of income for the nine months ended September 30, 2011. Ameren Missouri reduced its property and plant assets by $7 million. Ameren Missouri received the DOE settlement amount in July 2011. Under the settlement, Ameren Missouri's breach of contract suit was dismissed in July 2011.

In December 2011, Ameren Missouri intends to submit a license extension application with the NRC to extend its Callaway energy center's operating license from 2024 to 2044. If the Callaway energy center's license is extended, additional spent fuel storage will be required. Ameren Missouri plans to install a dry spent fuel storage facility at its Callaway energy center and intends to begin transferring spent fuel assemblies to this facility prior to 2020.

Electric utility rates charged to customers provide for the recovery of the Callaway energy center's decommissioning costs, which include decontamination, dismantling, and site restoration costs, over an assumed 40-year life of the nuclear center, ending with the expiration of the energy center's current operating license in 2024. It is assumed that the Callaway energy center site will be decommissioned based on the immediate dismantlement method and removed from service. Ameren and Ameren Missouri have recorded an ARO for the Callaway energy center decommissioning costs at fair value, which represents the present value of estimated future cash outflows. Decommissioning costs are included in the costs of service used to establish electric rates for Ameren Missouri's customers. These costs amounted to $7 million in each of the years 2010, 2009, and 2008. Every three years, the MoPSC requires Ameren Missouri to file an updated cost study for decommissioning its Callaway energy center. Electric rates may be adjusted at such times to reflect changed estimates. This cost study was filed with the MoPSC in September 2011. Based on the results of this updated cost study and associated financial analysis, Ameren Missouri recommended to the MoPSC that the current rate of deposits to the trust fund continue to be appropriate and do not need to be changed. Amounts collected from customers are deposited in an external trust fund to provide for the Callaway energy center's decommissioning. If the assumed return on trust assets is not earned, we believe that it is probable that any such earnings deficiency will be recovered in rates. The fair value of the nuclear decommissioning trust fund for Ameren Missouri's Callaway energy center is reported as "Nuclear decommissioning trust fund" in Ameren's consolidated balance sheet and Ameren Missouri's balance sheet. This amount is legally restricted and may be used only to fund the costs of nuclear decommissioning. Changes in the fair value of the trust fund are recorded as an increase or decrease to the nuclear decommissioning trust fund, with an offsetting adjustment to the related regulatory asset or regulatory liability.

Union Electric Company [Member]
 
Callaway Energy Center

NOTE 10 - CALLAWAY ENERGY CENTER

Under the NWPA, the DOE is responsible for disposing of spent nuclear fuel from the Callaway energy center and other commercial nuclear power plants. Under the NWPA, Ameren and other utilities who own and operated those plants are responsible for paying the disposal costs. The NWPA established the fee that these utilities pay the federal government for disposing of the spent nuclear fuel at one mill, or one-tenth of one cent, for each kilowatt hour generated by those plants and sold. The NWPA also requires the DOE annually review the nuclear waste fee against the cost of the nuclear waste disposal program and to propose to the United States Congress any fee adjustment as necessary to offset the costs of the program. As required by the NWPA, Ameren and other utilities have entered into standard contracts with the federal government, which was represented by the DOE, implementing these provisions of the NWPA. Consistent with the NWPA and its contract, Ameren Missouri collects one mill from its electric customers for each kilowatt hour of electricity that it generates and sells from its Callaway energy center.

Although the NWPA and the standard contract provide that the federal government would begin to dispose of spent nuclear fuel by 1998, the federal government acknowledged since at least 1994 that it would not meet that date. The federal government is not currently predicting when it will begin to meet its disposal obligation. Ameren Missouri has sufficient installed capacity at the Callaway energy center to store the spent nuclear fuel generated at Callaway through 2020 and has the capability for additional storage capacity for spent nuclear fuel generated through the end of the energy center's licensed life.

Until January 2009, the DOE program provided for spent nuclear fuel disposal to take place at a geologic repository to be constructed at Yucca Mountain, Nevada. Beginning in January 2009, the Obama administration announced that a repository at Yucca Mountain was unworkable and has taken steps to terminate the Yucca Mountain program, while acknowledging the federal government's continuing obligation to dispose of utilities' spent nuclear fuel. The DOE has established an advisory commission to make recommendations for the storage and disposal of utilities' spent nuclear fuel. The commission's final recommendations are scheduled to be issued in January 2012.

 

In view of the federal government's efforts to terminate the Yucca Mountain program, the Nuclear Energy Institute, a number of individual utilities, and the National Association of Regulatory Utility Commissioners sued the DOE in the United States Court of Appeals for the District of Columbia Circuit seeking the suspension of the one mill nuclear waste fee in view of the DOE's failure to undertake an appropriate fee adequacy review that reflects the current state of the nuclear waste program. That case is pending. The delay in DOE carrying out its obligation to dispose of spent nuclear fuel from the Callaway energy center is not expected to adversely affect the continued operation of the energy center.

As a result of DOE's failure to build a repository for nuclear waste or otherwise fulfill its contract obligations, Ameren Missouri and other nuclear power plant owners sued DOE to recover costs incurred for ongoing storage of their spent fuel. Ameren Missouri filed suit in 2004 to recover approximately $13 million in costs that it incurred through 2009. This amount included the cost of reracking the Callaway energy center's spent fuel pool, as well as certain NRC fees, and Missouri ad valorem taxes that Ameren Missouri would not have incurred had DOE performed its contractual obligations. In June 2011, the parties reached a settlement that included a payment to Ameren Missouri of approximately $11 million for spent fuel storage and related costs through 2010, and thereafter, annual payment of such costs after they are incurred through 2013 or any other mutually agreed extension. As a result of this settlement agreement, Ameren Missouri recorded a pretax reduction of $2 million and $2 million to its "Operating Expenses - Depreciation and amortization" and "Operating Expenses - Other operations and maintenance" expense line items, respectively, on its statement of income for the nine months ended September 30, 2011. Ameren Missouri reduced its property and plant assets by $7 million. Ameren Missouri received the DOE settlement amount in July 2011. Under the settlement, Ameren Missouri's breach of contract suit was dismissed in July 2011.

In December 2011, Ameren Missouri intends to submit a license extension application with the NRC to extend its Callaway energy center's operating license from 2024 to 2044. If the Callaway energy center's license is extended, additional spent fuel storage will be required. Ameren Missouri plans to install a dry spent fuel storage facility at its Callaway energy center and intends to begin transferring spent fuel assemblies to this facility prior to 2020.

Electric utility rates charged to customers provide for the recovery of the Callaway energy center's decommissioning costs, which include decontamination, dismantling, and site restoration costs, over an assumed 40-year life of the nuclear center, ending with the expiration of the energy center's current operating license in 2024. It is assumed that the Callaway energy center site will be decommissioned based on the immediate dismantlement method and removed from service. Ameren and Ameren Missouri have recorded an ARO for the Callaway energy center decommissioning costs at fair value, which represents the present value of estimated future cash outflows. Decommissioning costs are included in the costs of service used to establish electric rates for Ameren Missouri's customers. These costs amounted to $7 million in each of the years 2010, 2009, and 2008. Every three years, the MoPSC requires Ameren Missouri to file an updated cost study for decommissioning its Callaway energy center. Electric rates may be adjusted at such times to reflect changed estimates. This cost study was filed with the MoPSC in September 2011. Based on the results of this updated cost study and associated financial analysis, Ameren Missouri recommended to the MoPSC that the current rate of deposits to the trust fund continue to be appropriate and do not need to be changed. Amounts collected from customers are deposited in an external trust fund to provide for the Callaway energy center's decommissioning. If the assumed return on trust assets is not earned, we believe that it is probable that any such earnings deficiency will be recovered in rates. The fair value of the nuclear decommissioning trust fund for Ameren Missouri's Callaway energy center is reported as "Nuclear decommissioning trust fund" in Ameren's consolidated balance sheet and Ameren Missouri's balance sheet. This amount is legally restricted and may be used only to fund the costs of nuclear decommissioning. Changes in the fair value of the trust fund are recorded as an increase or decrease to the nuclear decommissioning trust fund, with an offsetting adjustment to the related regulatory asset or regulatory liability.