Commitments and Contingencies (Environmental Matters) (Details) (USD $)
Jun. 30, 2011
properties
Dec. 31, 2010
MACT standard emission limits based on existing coal and oil-fired generating units, percentage 12.00%  
Reduction in mercury emissions included in the proposed federal MACT standard 91.00%  
Number of states included in the CAIR regulations 28  
Number of states included in CSAPR 23  
Expected percentage reduction in SO2 emissions by 2014 included in CSAPR 73.00%  
Expected percentage reduction in NOx emissions by 2014 included in the proposed transport rule 54.00%  
Threshold amount of greenhouse emissions in tons that will require operating permit under title V operating permit program of the Clean Air Act 75,000  
Threshold, in millions of gallons of water per day, for power plants to be regulated under the EPA's proposed Clean Water Act rules 2  
Threshold, in percentage, of water used for cooling at a power plant to be regulated under the EPA's proposed Clean Water Act rules 25.00%  
Level of intake velocity (feet per second) included in the EPA's proposed Clean Water Act rules 0.5  
Property, plant and equipment, net $ 17,945,000,000 $ 17,853,000,000
Hutsonville [Member]
   
Property, plant and equipment, net 26,000,000  
Meredosia [Member]
   
Property, plant and equipment, net 1,000,000  
Unit One, E.D. Edwards Energy Center [Member]
   
Property, plant and equipment, net 18,000,000  
Minimum [Member] | Estimated Capital Costs 2016 - 2020 [Member]
   
Estimated capital costs to comply with existing and known federal and state air emissions regulations 975,000,000  
Minimum [Member] | Estimated Capital Costs 2011 Through 2020[Member]
   
Estimated capital costs to comply with existing and known federal and state air emissions regulations 1,990,000,000  
Maximum [Member] | Estimated Capital Costs 2012 - 2015 [Member]
   
Estimated capital costs to comply with existing and known federal and state air emissions regulations 1,035,000,000  
Maximum [Member] | Estimated Capital Costs 2016 - 2020 [Member]
   
Estimated capital costs to comply with existing and known federal and state air emissions regulations 1,195,000,000  
Maximum [Member] | Estimated Capital Costs 2011 Through 2020[Member]
   
Estimated capital costs to comply with existing and known federal and state air emissions regulations 2,405,000,000  
Ameren Missouri [Member] | Manufactured Gas Plant [Member]
   
Number of remediation sites 10  
Ameren Illinois [Member] | Manufactured Gas Plant [Member]
   
Number of remediation sites 44  
Manufactured Gas Plant [Member]
   
Loss contingency range of possible loss minimum 121,000,000  
Loss contingency range of possible loss maximum 199,000,000  
Accrual for environmental loss contingencies 121,000,000 [1]  
Manufactured Gas Plant [Member] | Iowa [Member]
   
Number of remediation sites 1  
Ameren Illinois [Member] | Former Coal Ash Landfill [Member]
   
Loss contingency range of possible loss minimum 500,000  
Loss contingency range of possible loss maximum 6,000,000  
Accrual for environmental loss contingencies 500,000  
Ameren Illinois [Member] | Other Environmental [Member]
   
Accrual for environmental loss contingencies 800,000  
Ameren Missouri [Member] | Former Coal Tar Distillery [Member]
   
Loss contingency range of possible loss minimum 2,000,000  
Loss contingency range of possible loss maximum 5,000,000  
Accrual for environmental loss contingencies 2,000,000  
Ameren Missouri [Member] | Sauget Area 2 [Member]
   
Loss contingency range of possible loss minimum 400,000  
Loss contingency range of possible loss maximum 10,000,000  
Accrual for environmental loss contingencies 400,000  
Estimated Capital Costs [Member]
   
Reduction in capital expenditure estimate for environmental compliance 1,100,000,000  
Estimated Capital Costs 2011 [Member]
   
Estimated capital costs to comply with existing and known federal and state air emissions regulations 175,000,000  
Ameren Illinois [Member]
   
Property, plant and equipment, net $ 4,657,000,000 $ 4,576,000,000