Rate And Regulatory Matters (Tables)
9 Months Ended
Sep. 30, 2019
Public Utilities, General Disclosures [Abstract]  
Schedule of Wind Generation Facilities The following table provides information with respect to each build-transfer agreement:    
 
 
Up-to 400-Megawatt Facility
 
Up-to 300-Megawatt Facility
Build-transfer agreement date
 
May 2018
 
May 2019
Wind facility developer
 
Terra-Gen, LLC
 
Invenergy Renewables, LLC(a)
Location
 
Northeastern Missouri
 
Northwestern Missouri
Status of certificate of convenience and necessity from the MoPSC
 
Approved October 2018
 
Approved August 2019
Status of final interconnection costs
 
Received July 2019
 
Received July 2019
Status of RTO transmission interconnection agreement
 
Executed August 2019
 
Executed October 2019
Status of FERC approval
 
Received December 2018
 
Received October 2019
Expected completion date
 
By the end of 2020
 
By the end of 2020
(a)
In October 2019, Invenergy Renewables, LLC acquired the project from Enel North America, Inc.