Management's Discussion and Analysis of Operations and Financial Condition
For the three and nine months ended September 30, 2024


image_1b.jpg
Table of Contents
Three and Nine Months Results
2

image_1b.jpg
Management's Discussion and Analysis of Operations and Financial Condition

This Management's Discussion and Analysis of Operations and Financial Condition (“MD&A”) of i-80 Gold Corp. (“i-80 Gold” or the “Company”) should be read in conjunction with the Company’s unaudited condensed consolidated interim financial statements (the “Financial Statements”) for the three and nine months ended September 30, 2024, and the notes thereto. The Company's Financial Statements have been prepared in accordance with IFRS Accounting Standards as issued by the International Accounting Standards Board (“IFRS Accounting Standards” or “IFRS”) as applicable to interim financial statements including International Accounting Standard (“IAS”) 34 - Interim Financial Reporting. Unless otherwise stated, all amounts discussed herein are denominated in United States dollars ("$" or "USD") (C$ represents Canadian dollars). This MD&A was prepared as of November 12, 2024, and all information is current as of such date. Readers are encouraged to read the Company’s public information filings on i-80 Gold’s website at www.i80gold.com, on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov/edgar.

This discussion provides management's analysis of the Company’s historical operating and financial results and provides estimates of future operating and financial performance based on information currently available. Actual results may vary from estimates and the variances may be significant. Readers should be aware that historical results are not necessarily indicative of future performance. Cautionary statements regarding mineral reserves and mineral resources, and forward-looking information can be found in the Sections titled “Technical Information” and “Cautionary Statements on Forward-Looking Statements” in this MD&A.

The Company has included certain non-IFRS financial performance measures, which the Company believes, that together with measures determined in accordance with IFRS, provide investors with an improved ability to evaluate the underlying performance of the Company. Non-IFRS financial performance measures do not have any standardized meaning prescribed under IFRS, and therefore they may not be comparable to similar non-IFRS financial performance measures employed by other companies. The data is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. Descriptions and reconciliations associated with the non-IFRS financial performance measures can be found in the section titled “Non-IFRS Financial Performance Measures” in this MD&A.

OVERVIEW

Company Overview
i-80 Gold Corp. is a Nevada-focused growth-oriented gold and silver producer engaged in the exploration, development, and production of gold and silver. The Company's wholly owned principal assets include the Granite Creek mine, Ruby Hill mine, Lone Tree mine, McCoy-Cove project, and FAD project.
The Company was incorporated on November 10, 2020, in the province of British Columbia, Canada. The Company’s common shares are listed on the Toronto Stock Exchange (“TSX”) under the symbol IAU and the New York Stock Exchange (“NYSE”) under the symbol IAUX. The Company’s headquarters are located at 5190 Neil Road, Suite 460, Reno, Nevada, 89502.

Operational and Financial Overview

Third Quarter 2024

Third quarter loss per share was $0.10 per share, a decrease from $0.01 loss per share in the comparative prior year period.
Third quarter cash used in operating activities was $19.0 million, an increase in cash used from the prior year period due to lower mine operating income partially offset by lower exploration, evaluation and pre-development expense.
September 30, 2024, cash balance is $21.8 million, a decrease of $26.0 million from the end of the second quarter due to cash used in operations and cash used for capital expenditures.
During the third quarter the Company began an at-the-market equity program (“ATM program”) to raise equity. In total 11.5 million shares were issued for gross proceeds of $13.1 million.
Third quarter revenue totaled $11.5 million compared to $13.2 million in the comparative prior year period due to lower volumes sold partially offset by higher gold price.
Third quarter gold sales totaled 3,063 ounces at an average realized gold price1 of $2,422 per ounce, resulting in revenue of $7.4 million, compared to gold sales of 4,585 ounces at an average realized gold price1 of $1,895 per ounce, resulting in revenue of $8.7 million in the third quarter of 2023
Third quarter mineralized material sales totaled 14,696 tons for revenue of $4.1 million, compared to mineralized material sales totaling 16,059 tons for revenue of $4.5 million in the comparative prior year period.
Cost of sales increased by $3.2 million over the prior year quarter primarily due to an inventory impairment recognized.
The Company published its second annual sustainability report which can be found on the Company’s website.
The Company adopted a new development plan to ramp up, permit and construct five gold mines over the balance of the decade to create a mid-tier gold producer, capable of producing approximately 400,000 to 500,000 ounces of gold annually.
The Company is working to reschedule current debt obligations and to provide the additional capital required to execute the new development plan.
Management changes were also made to strengthen the management team to execute on the new development plan.

Year to Date (“YTD”) 2024

YTD loss per share was $0.26 per share, a decrease from $0.13 loss per share in the comparative prior year period.
YTD cash used in operating was $61.9 million, an increase from prior year period primarily due to lower production from the Company’s mines, partially offset by higher average realized gold prices.
1This is a Non-IFRS Measure; please see “Non-IFRS Measures” section.
3

image_1b.jpg
YTD revenue totaled $27.1 million compared to $29.1 million in the comparative prior year period.
YTD gold sales totaled 7,186 ounces at an average realized gold price1 of $2,290 per ounce, resulting in revenue of $16.5 million, compared to gold sales of 11,262 ounces at an average realized gold price1 of $1,924 per ounce, resulting in revenue of $21.7 million in the comparative prior year period of 2023.
YTD mineralized material sales totaled 29,041 tons for revenue of $10.6 million, compared to mineralized material sales totaled 22,710 tons for revenue of $7.3 million in the comparative prior year period.
Approximately 80,000 feet (core and RC) drilled with multiple positive results to expand mineralization further at the Ruby Hill mine, the Granite Creek mine and the McCoy-Cove project.

Strategic Overview

The Company underwent a leadership change during the third quarter, which prompted a review of the strategic direction of the Company. As a result, the Company adopted a new development plan which presents Management’s view of the most effective strategy to generate free cash flow while progressing earlier stage projects to provide a pipeline of growth in the medium and long-term. Management is now focused on permitting and development of five gold deposits through the balance of the decade. Consistent with the focus of i-80 Gold since inception, this plan includes the development of the three underground mines, but also includes accelerating permitting and development of the two large oxide open pit deposits, Granite Creek and Mineral Point. Collectively, these five assets have the potential to create a mid-tier gold producer. The Company has initiated a recapitalization plan of its balance sheet to support the new development plan.

The Lone Tree Autoclave remains the centralized refractory ore processing facility in the new development plan and Management intends to continue its work towards completion of the refurbishment feasibility study next year. Following completion of the study, a series of trade-off scenarios will be considered comparing full autoclave refurbishment or alternate toll milling and ore purchase agreements options that could potentially be available.

Further, Management believes that a base metal focused joint venture at the Ruby Hill project does not fit the new development plan, see “Ruby Hill Base Metal JV” section below for more information. Overall, given the Company’s balance sheet constraints and additional capital required for the new development plan all higher risk projects with low certainty of economic viability have been deferred until the balance sheet is in a stronger position and the Board approves allocating risk capital to these projects.

The Lone Tree open pit project has a variety of financial, technical, environmental and social issues to be worked through. It is expected that the project will likely remain deferred for another decade. Management believes new technologies and other solutions may become available in the future to allow the Company to unlock the value of this large open pit project.

Recapitalization Plan

The Company envisages a two-step recapitalization process which will include demonstrating a viable path to generating free cash flow, and rescheduling and/or refinancing the existing debt obligations. Phase one of this plan will include finding a solution for short-term commitments including deferral of the upcoming gold and silver deliveries scheduled for late December and early January. Phase two of the recapitalization plan involves working with our current partners as well as seeking new debt providers to restructure our existing debt and provide sufficient capital to execute on the Company’s new development plan with repayment terms that align with the Company’s ability to service that debt. Management has initiated work on this, including discussions with existing and potential new partners, and aims to complete this process in the first quarter of 2025.

Ruby Hill Base Metal Joint Venture

In November 2023, i-80 Gold entered into a non-binding Letter of Intent with a third party (see press release dated November 7, 2023), to consider a joint venture agreement for Ruby Hill with a focus on base metal exploration and development. In addition to deposits with base metal potential (Blackjack, Hilltop and FAD), the joint venture discussion included all gold and silver deposits within the Ruby Hill property, including Mineral Point.

Upon careful assessment of the joint venture terms and economics, considering the potential value of the existing gold resources in a rising gold price environment and taking into account the limited understanding of the base metal potential, i-80 Gold’s Board and Management have elected to no longer proceed with joint venture discussions. It is noteworthy that the period of exclusivity with the counterparty has expired.

i-80 Gold is electing to prioritize more advanced staged gold and silver projects with established resources and technical studies. As such exploration and development work on base metal targets have been deferred to focus on projects with the fastest timeline to cash flow generation.

Organizational Changes

Since i-80 Gold’s inception, the Company’s focus has been on asset acquisition and exploration. As the company evolves into a developer and producer the organizational structure and skill set of its employees needs to evolve to meet the new development plan in order to become a mid-tier gold producer of approximately 400,000 to 500,000 ounces of gold per year by the early 2030’s.

The three most significant changes facing i-80 Gold are i) increased emphasis on technical skills to ramp up, permit and construct five projects through the balance of the decade; ii) the requirement to restructure and re-capitalize the balance sheet in a manner that aligns to the new development plan; and iii) the additional legal and reporting requirements of becoming a US domestic issuer.

4

image_1b.jpg
In order to meet i-80 Gold’s growing and changing demands, the Company has promoted four senior technical personnel and hired three new senior positions. Management believes these organizational changes, including the promotions and new hires, add the necessary experience and bench strength to further de-risk the execution of the development plan. The cost of these changes is expected to be offset by lower third-party consultant costs.

On the operations front, the promotion of four senior technical personnel is a reflection of the importance of these four individuals in reducing our execution risk as we ramp up our activities to permit and construct five mines through the balance of the decade.

On the legal front, the hiring of David Savarie as our new Senior VP General Counsel will bring in-house industry specific legal expertise that will improve our approach to and compliance with our governance and contractual commitments while also lowering our third-party legal costs. Further, this addition will immediately reduce the burden on existing management to manage the legal process in an increasingly complex environment while adding additional strength as we execute on our new development plan.

On the finance front, the Company has added two new senior financial roles, Katerina Deluca as VP of Treasury in charge of treasury and financing and Curtis Turner as VP of Strategic Planning. Mr. Turner is transitioning from VP Finance to this new role. These new positions are required to meet the increased workload associated with the balance sheet restructuring and debt reporting as well as enabling the new development plan to be executed. The VP Finance function will be managed by an incoming hire, Cindy Tseo.

The final new officer joining the team is Leily Omoumi, our new VP Corporate Development and Strategy who will also be in charge of investor relations. This position replaces the outgoing Executive Vice President, Business Development, Matt Gollat who was instrumental in the formation of i-80 Gold since its inception in 2021. Mr. Gollat has agreed to remain as an advisor in the transition to focus on the new development plan. The Company would like to thank Mr. Gollat for his contribution to the Company. The new VP Corporate Development will execute the new vision of the organization playing a key role in developing and maintaining the Company life-of-mine model as well as understanding the value of i-80 Gold and conveying that message to the market. Joining Ms. Omoumi is Jim Mackay, Director of Corporate Development and Investor Relations.

Financing Overview

Third Quarter 2024

On August 12, 2024, the Company implemented an ATM to sell through the TSX and the NYSE common shares up to an aggregate offering price of up to $50 million. For the three ended September 30, 2024, proceeds of $13.1 million were received from the issuance of 11.5 million shares sold. The Company will continue to use the ATM Program as a tool to maintain an appropriate level of liquidity as it executes on the recapitalization plan as discussed in the Recapitalization Plan section. As at November 12, 2024, the Company has issued 17.7 million common shares under the ATM Program for total gross proceeds of $20.1 million.
On October 31, 2024, The Company issued 2.1 million common shares in connection with Sprott's conversion of $3.6 million in principal and $0.9 million in interest under the Sprott Convertible Loan.

Year to Date

Contingent Payments

In the first quarter of 2024, the Company paid Waterton as part of the contingent value rights payment (production milestone) 2.7 million common shares of the Company valued at $3.6 million. In the second quarter of 2024, the Company paid Waterton $1.4 million in cash in full satisfaction of the $5.0 million contingent value rights payment (price condition). The $5.0 million payment was recorded in property, plant and equipment on the consolidated statements of financial position.

Equity Offerings

On February 20, 2024, the Company completed a non-brokered private placement of common shares. An aggregate of 13.1 million shares were issued by the Company at a price of C$1.80 per common share for aggregate gross proceeds of $17.4 million (C$23.5 million).
On May 1, 2024, the Company completed a bought deal public offering of 69.7 million units at a price of C$1.65 per unit for gross proceeds of $83.5M (C$115.0 million). Each Unit consists of one common share of the Company and one half of one common share purchase warrant.
On June 24, 2024, the Company obtained a receipt for a final short form base shelf prospectus on June 24, 2024 (the "Canadian Shelf Prospectus"). The Canadian Shelf Prospectus was filed with the securities regulators in each province and territory of Canada, and a corresponding U.S. base prospectus contained in its registration statement on Form F-10 (the "U.S. Base Prospectus") was filed with the SEC.

Gold Prepay Agreement Amendments

On March 28, 2024, the Company entered into an amending agreement in relation to the gold prepay agreement (“Gold Prepay Agreement”) with Orion Mine Finance (“Orion”) pursuant to which the March 31, 2024, quarterly delivery of 3,223 troy ounces of gold was extended from March 31, 2024, to April 15, 2024 (the "First Amending Agreement").
On April 24, 2024, the Company entered into a second amending agreement with Orion to amend the terms of the Gold Prepay Agreement (the “Second A&R Gold Prepay Agreement”). In accordance with the terms of the Second A&R Gold Prepay Agreement, Orion agreed to extend the deadline for the outstanding deliveries previously required to be made on or before April 15, 2024 under the Gold Prepay Agreement until May 10, 2024.
5

image_1b.jpg
On June 28, 2024, the Company entered into a Side Letter Agreement with Orion in relation to the June 30, 2024, quarterly delivery, whereby the Company agreed to deliver a minimum of 1,000 troy ounces of gold to Orion on or before July 1, 2024, and to deliver the remaining 2,210 ounces to Orion on or before August 31, 2024.
As of September 30, 2024, the Company had delivered 25,343 troy ounces of gold towards the Gold Prepay Agreement with Orion, leaving 18,390 troy ounces of gold remaining to be delivered under the agreement.

Silver Purchase Agreement Amendments

On January 12, 2024, the Company entered into an extension agreement in relation to the silver purchase and sale agreement entered into with affiliates of Orion (“Silver Purchase Agreement”) pursuant to which in the event that the amount of silver delivered under the Silver Purchase Agreement is less than the minimum delivery amount, the Company shall make up such difference (the “Shortfall Amount”) by delivering on or before the fifteenth day of the month immediately following such calendar year (the "Delivery Deadline"). The 2023 Shortfall Amount Delivery Deadline was extended from January 15, 2024, to April 15, 2024 (the "Extension Agreement"). In connection with the Extension Agreement, the Company paid an amendment fee of $0.2 million and issued 0.5 million common share warrants exercisable at C$2.72 per share with an exercise period of 48 months or until January 24, 2028.
On April 24, 2024, the Company entered into an amending agreement with Orion (the “Amended Silver Purchase Agreement”) to amend the terms of its Silver Purchase Agreement. In accordance with the terms of the Amended Silver Purchase Agreement, Orion agreed to extend the deadline for the outstanding deliveries required to be made on or before April 15, 2024, under the Amended Silver Purchase Agreement until May 10, 2024.
As of September 30, 2024, the Company had delivered 700,000 ounces of silver towards the Silver Purchase Agreement with Orion, leaving 500,000 ounces of silver to be delivered in 2025 and 2026 under the fixed delivery schedule.

DISCUSSION OF OPERATIONAL RESULTS

The Company owns and operates four past producing gold properties in Nevada, one of the largest gold producing regions in the world. The four gold properties are currently at various stages of redevelopment following successful exploration programs at each of the four properties. The Granite Creek underground mine is the first to be redeveloped, it is currently ramping up to full production, while the open pit heap leach deposit, adjacent to the underground mine, is at the study and permitting stage. Ruby Hill is host to what is expected to be the Company’s second underground mine. Permits are expected by the end of 2024 and construction is expected to take approximately 18 months to production. In the meantime, the Company is leaching the historic leach pads, which provide minor amounts of gold production. McCoy-Cove is expected to be the Company’s third underground gold mine. Baseline permitting work is largely in the process of being finalized over the next six months to allow the for the submittal of the permit application, which is expected to take approximately three years for approval, followed by approximately 18 months of construction. At the Company’s Lone Tree property, leaching of the historic leach pads is producing minor amounts of gold. The focus at Lone Tree is a feasibility study to evaluate the refurbishment of the autoclave to process ore from the three underground mines. The feasibility study is expected to be completed in the third quarter of 2025.

Granite Creek mine

Gold was initially discovered at Granite Creek in the mid to late 1930’s and includes the former Pinson mine. Approximately one million ounces have been produced from the property since that time. The Granite Creek mine is comprised of several land parcels which now encompass approximately 4,480 acres, located in the Potosi mining district, 27 miles northeast of Winnemucca, within the southeastern part of Humboldt County, Nevada. The seven-square miles of land contain all areas of past gold production and the area of mineral resources (underground and open pit). Granite Creek underground is anticipated to reach commercial production in 2026 from resource expansions.
6

image_1b.jpg
For Granite Creek open pit an infill drilling program is planned for 2025 to upgrade resources to a feasibility study level while permitting activities are conducted.

 Three months ended
September 30,
Nine months ended
September 30,
Operational Statistics
2024202320242023
Oxide mineralized material mined
tons18,846 13,294 45,658 29,738 
Sulfide mineralized material mined
tons11,917 9,709 21,153 20,817 
Total oxide and sulfide mineralized material mined
tons30,763 23,003 66,811 50,555 
Material mined grade
g/tonne
8.38 8.34 7.74 8.87 
Material mined gradeoz/ton0.24 0.24 0.23 0.26 
Low-grade mineralized material mined1
tons22,488 12,800 47,186 30,110 
Low-grade mineralized material grade1
g/tonne2.92 3.18 3.00 3.02 
Low-grade mineralized material grade1
oz/ton0.09 0.09 0.09 0.09 
Waste mined
tons35,916 24,753 108,404 106,830 
Processed mineralized material2
tons38,000 — 43,183 11,084 
Oxide mineralized material sold
tons14,696 16,059 29,041 22,710 
Sulfide mineralized material soldtons — 5,183 — 
Total mineralized material sold
tons14,696 16,059 34,224 22,710 
Ounces of gold soldoz315 900 315 1,344 
Underground mine development (capital development)
ft807 888 3,071 3,194 
Exploration drillingft4,923 16,144 23,413 20,944 
Financial Statistics2024202320242023
Mining cost (total mineralized material and waste)
$/ton134 124 129 103 
Processing cost (processed mineralized material)
$/ton20 N/A34 151 
Site general and administrative (“G&A”) (total mineralized material mined3)
$/ton29 18 30 26 
Royalties
$000s
358 259 1,913 475 
Capital expenditure4
$000s
5,949 4,636 21,233 13,711 
Exploration spending
$000s
1,651 1,777 4,072 2,184 
1Low-grade mineralized material extracted as part of the mining process that is below cut-off grade but incrementally economic.
2Processed mineralized material consists of toll treated material and material placed under leach.
3Total mineralized material mined consists of sulfide, oxide, and low-grade mineralized material.
4Capital expenditure based on accrual basis.

Mining rates and gold production for the quarter and nine months of 2024 were lower than planned due to an increase in ground water ingress into underground working areas, which negatively impacted productivity and development advancement rates. To address the higher water rates, the mine is adding additional pumping capacity, deepening an existing de-watering well and reworking the de-watering system to allow for additional flow capacity in the water treatment facility. Management expects that production and costs will continue to be negatively impacted until these measures are completed, which is expected to occur by the end of the third quarter of 2025.

The Company continues to encounter elevated oxide mineralized material. A significant portion of this mineralized material that was lower grade was deemed suitable for processing via heap leach at the Lone Tree heap leach facility. This material is stockpiled and subsequently transported to Lone Tree for leaching. During the quarter, this material was placed on the leach pad but not placed under leach until late in the quarter and recovery of ounces will take place after the quarter end. This is in part responsible for the lack of ounce production even though the mineralized material mined increased significantly period over period. In addition, during the three months ended, no sulfide mineralized material was processed under the toll milling agreement. As of September 30, 2024, all of the remaining sulfide mineralized material under the toll milling agreement has been delivered to NGM and the Company anticipates that the sulfide mineralized material will be processed in the fourth quarter.

Subsequent to the quarter end, on October 14, 2024, the toll milling agreement with NGM expired. The terms of the agreement provide for a good faith renegotiation or extension of the agreement as long as certain conditions are met. The Company is currently engaged with NGM to establish an extension or updated agreement for processing of the i80 refractory material. If the Company is unable to obtain an extension of the Autoclave Toll Milling Agreement in a timely manner (or at all), the Company will be required to seek other arrangements for the processing of refractory material from its Granite Creek mine. For the year 2024, the Company anticipates that approximately 25% of the ounces produced from Granite Creek fall under the Toll Milling Agreement and the Company does not anticipate that percentage will increase materially over the next 12 months.

Capital expenditures for the three and nine months focused mainly on underground development and de-watering. The increased capital period over period is related increased footage as noted in the table above. Furthermore, the water treatment plant contributed to $0.5 million in capital spending for the 9 month period.

7

image_1b.jpg
During the third quarter, Management began a process to update the technical report and has begun the permitting process for the Granite Creek open pit heap leach project. An updated study is expected in 2025. Permitting is expected to take approximately three years and construction a further 18 months. Management is currently considering construction of heap leach pads instead of heap leach and CIL plants as indicated in the last technical report (2021). Further studies are expected to determine the superior economic route.

During the three months ended September 30, 2024, approximately 5,000 feet of directional core drilling was completed. The drilling program was focused on infilling, upgrading and expanding the resources in the South Pacific Zone. As the ground condition contributed to high drilling costs, the Company paused this program and decided to develop an underground exploration drift to complete this drilling program. It is anticipated that the budget program will remain the same, but the timeline to complete will be delayed allowing for the development of the drift which was commenced in the fourth quarter of 2024.

Ruby Hill mine

During the 1990’s, an ore body was discovered, which became the Archimedes pit. Later discoveries included the Ruby Deeps sulfide deposit with the most recent discovery of the Hilltop zone. The Ruby Hill mine is located within the Battle Mountain-Eureka Trend, and is host to the Archimedes open pit and multiple gold, silver and base metal deposits. The Ruby Hill Mine includes the Archimedes underground, the Mineral Point deposit, an open pit heap leach project, as well as several base metal deposits. Mineral Point is a large oxide gold and silver deposits with the potential to become the Company’s largest gold producing asset. Processing infrastructure at Ruby Hill includes a primary crushing plant, grinding mill, leach pad, and carbon-in-column circuit.

Permitting for Archimedes underground is anticipated by the end of 2024 or early 2025 with construction to commence in the first half of 2025. The Mineral Point deposit drill program is expected to begin in early 2025 to support geotechnical, metallurgical and hydrology studies for baseline data to complete a Preliminary Economic Assessment (“PEA”) during 2025.

 Three months ended
September 30,
Nine months ended
September 30,
Operational Statistics
2024202320242023
Ounces of gold soldoz906 1,910 1,861 4,781 
Exploration drillingft 8,345 4,032 74,684 
Financial Statistics2024202320242023
Mining cost
$/oz
 —  11 
Processing cost (processed oz)
$/oz984 726 1,142 642 
Site G&A (processed oz)
$/oz432 310 607 263 
Royalties
$000s64 105 126 250 
Capital expenditure1
$000s
 11 118 30 
Exploration spending
$000s
354 3,484 986 15,024 
1Capital expenditure based on accrual basis.

During the quarter and nine months ended September 30, 2024, the Company continued to recover ounces from the heap leach pads at Ruby Hill. While efforts are made to optimize the ounces recovered, the ounces recovered was lower than the comparable periods and the Company anticipates that production will continue to decrease and become uneconomic soon.

There was minimal spending on capital projects for nine months and nil spending for the three months. However, during the third quarter, the Company commissioned a scoping study to provide an initial assessment of the economics of the Mineral Point deposit.

Exploration spending for the three and nine months was related to metallurgical tests and drilling for metallurgical samples, respectively.

Feasibility work on the base metal deposits including Hilltop, Blackjack and FAD have been suspended for the foreseeable future as the Company focuses on ramping up, permitting and developing the three underground and two open pit heap leach gold projects through the balance of the decade. As a result of the adoption of the new gold-focused strategy, the base metal JV, for which the Company has been advancing over the past year, has been terminated.

McCoy-Cove project

Modern exploration for copper and gold in the McCoy Mining District started in the 1960s. The McCoy-Cove project covers 30,923 acres and is located 32 miles south of the town of Battle Mountain, in the Fish Creek Mountains of Lander County, Nevada, and lies within the McCoy Mining District. The McCoy-Cove project is, for the most part, on land controlled by the U.S. Department of Interior, Bureau of Land Management ("BLM") and patented mining claims. The McCoy-Cove project consists of 1,535 100%-owned unpatented claims and twelve leased patented claims.

McCoy-Cove is a high-grade underground development project. Baseline work in advance of a federal permitting action submittal to the Nevada Bureau of Land Management (BLM) is proceeding on plan. Management is targeting the submittal of an Environmental Impact Statement (EIS) in mid-2025. An EIS will be required primarily due to the significant project disturbance acres and impact on water. The permitting process is expected to take three years. In parallel with the permitting process, an infill drill program is under way to expand mineral reserves and resources as well as engineering work to complete a feasibility study in 2025.
8

image_1b.jpg

Baseline field studies including biological, geochemical and hydrological continue to move forward to support the planned permitting submittal timeline of mid-2025. An air quality impact analysis report and global climate change technical memorandum were submitted and accepted by the BLM. The initial groundwater flow model has been completed and the Company is currently optimizing the design of the de-watering infrastructure and expects to include the model in the updated technical studies to be published in 2025. The permitting process is expected to take approximately three years to complete followed by 18 months of construction, primarily de-watering and underground development as well as some light surface infrastructure work.

 Three months ended
September 30,
Nine months ended
September 30,
Operational Statistics
2024202320242023
Exploration drillingft34,268 16,789 52,244 48,048 
Financial Statistics2024202320242023
Capital expenditure1
$000s
 470  5,637 
Exploration spending
$000s
3,984 3,184 8,512 10,241 
1Capital expenditure based on accrual basis.

Underground delineation drilling continued during the third quarter on Helen and CSD Gap with two core rigs, with approximately 34,000 feet of core drilled bringing total drilling over the course of the infill campaign to approximately 96,000 feet. A further 20,000 feet of drilling is planned into the first quarter of 2025 to complete the program. The 2024/2025 drill program will be included in an updated feasibility study expected in 2025.

Lone Tree mine

The Lone Tree mine is a historic producing mine that completed mining operations in 2006. The Lone Tree mine is a development project located within the Battle Mountain-Eureka Trend, midway between the Company's Granite Creek mine and McCoy-Cove underground project. The property consists of the past-producing Lone Tree mine and processing facility, as well as the nearby Buffalo Mountain deposit and the Brooks open pit mine, which is currently on care and maintenance. Processing infrastructure at Lone Tree includes an autoclave, carbon-in-leach mill, flotation mill, heap leach facility, assay lab and gold refinery, tailings dam, waste dumps and several buildings that the Company anticipates will be useful for developing all mining projects, including a warehouse, maintenance shop and administration building.

During the third quarter ended September 30, 2024, Management continued to review the value engineering studies in preparation for a feasibility study on the refurbishment of the autoclave, scheduled to be completed in 2025. The refurbishment of the autoclave at Lone Tree would process sulfide ore from the three underground mines, Granite Creek, Archimedes at Ruby Hill and McCoy-Cove. The Lone Tree open pit is expected to remain in inventory into the 2030’s as the Company focuses ramp up, permitting and development of its three underground mines and two open pit heap leach mines.

 Three months ended
September 30,
Nine months ended
September 30,
Operational Statistics
2024202320242023
Ounces of gold soldoz1,842 1,775 5,010 5,138 
Financial Statistics2024202320242023
Processing cost (processed oz)
$/oz697 801 732 820 
Site G&A (processed oz)
$/oz142 272 184 235 
Capital expenditure1
$000s
71 3,163 578 12,895 
1Capital expenditure based on accrual basis.

The Company continues to recover ounces from the leach pads at Lone Tree. Due to optimization of the leaching process, the ounces produced are in line with the production for the comparative three and nine month periods. The Company will continue to process ounces from the leach pads as long as it is economical to do so.

Capital spending for the three and nine months is related to general infrastructure in sustaining the operations and activities at Lone Tree along with the spending related to the technical work on the refurbishment of the Autoclave processing plant.
9

image_1b.jpg
DISCUSSION OF FINANCIAL RESULTS
 Three months ended
September 30,
Nine months ended
September 30,
(in thousands of USD)2024202320242023
Revenue
11,509 13,215 27,107 29,073 
Cost of sales
(15,449)(12,244)(42,346)(30,975)
Depletion, depreciation and amortization(552)(1,444)(1,003)(5,589)
Mine operating loss(4,492)(473)(16,242)(7,491)
Expenses
Exploration, evaluation and pre-development6,019 10,014 13,867 30,088 
General and administrative4,554 4,136 15,139 13,724 
Property maintenance2,549 2,763 7,818 7,992 
Share-based payments794 244 1,935 2,455 
Loss before the following(18,408)(17,630)(55,001)(61,750)
Other (expense) income (10,331)21,488 (7,097)43,150 
Finance expense(9,322)(8,133)(28,508)(22,698)
Loss before income taxes(38,061)(4,275)(90,606)(41,298)
Deferred tax recovery 76  8,020 
Loss and comprehensive loss for the period(38,061)(4,199)(90,606)(33,278)
Financial results for the three months ended September 30, 2024
Revenue

Revenue for the three months ended September 30, 2024 was $11.5 million, a decrease of 13% from $13.2 million in the comparative prior year period. During the three months ended September 30, 2024, mineralized material sale totaled 14,696 tons and gold ounces sold totaled 3,063 ounces at an average realized gold price1 of $2,422 per ounce, compared to mineralized material sale of 16,059 tons and gold ounces sold of 4,585 at an average realized gold price1 of $1,895 per ounce during the same period of 2023, a decrease of 1,522 in gold ounces sold or 33%. The lower revenue was driven by a decrease of $1.3 million in gold sales and a decrease of $0.4 million in mineralized material revenue. Granite Creek experienced lower than planned production due to underground water issues, partially offset by higher average realized gold price1.
Three months ended
September 30,
Spot price per ounce of gold
20242023% Change
Average2,475 1,928 28 %
Low2,329 1,871 24 %
High2,664 1,976 35 %
Average realized2,422 1,895 28 %
Cost of sales     
Cost of sales for the three months ended September 30, 2024 was $15.4 million, which was an increase of 26% from cost of sales of $12.2 million in the comparative prior year period, largely related to inventory impairment of $3.3 million from higher cost per ounce due to lower production due to underground de-watering efforts at the Granite Creek mine.
Depreciation, depletion and amortization
Depreciation, depletion, and amortization expense for the three months ended September 30, 2024 was $0.6 million, a decrease of 62% compared to $1.4 million from the prior year period. The lower depreciation in 2024 is due to the majority of the processing equipment being fully depreciated at Ruby Hill in 2023.
1This is a Non-IFRS Measure; please see “Non-IFRS Measures” section.
10

image_1b.jpg
Exploration and pre-development expenses
Three months ended
September 30,
(in thousands of USD)20242023
Granite Creek, Nevada1,651 1,777 
Ruby Hill, Nevada354 3,484 
McCoy-Cove, Nevada3,984 3,184 
Buffalo Mountain, Nevada15 — 
FAD, Nevada15 1,538 
Other (i)
 31 
Total exploration, evaluation and pre-development6,019 10,014 
(i)Other includes charges for regional technical services costs not charged to a property.

For the three months ended September 30, 2024, the company incurred $6.0 million of exploration, evaluation and pre-development expenses, 40% lower compared to the three-month period ended September 30, 2023. The lower exploration expense for the three months ended September 30, 2024 was primarily a result of the Company pausing activities at the Ruby Hill mine during the due diligence period for the proposed joint venture, resulting in a reduction in exploration expense of $3.1 million, partially offset by $0.8 million increase at McCoy-Cove.
Other (expense) income

 Three months ended
September 30,
(in thousands of USD)20242023
(Loss) gain on convertible loan derivatives
(721)13,574 
(Loss) gain on warrants
(3,587)7,357 
(Loss) gain on Gold Prepay derivative
(2,998)2,190 
(Loss) gain on Silver Purchase derivative
(1,276)822 
Loss on Gold Prepay Agreement modification
 (1,831)
Loss on deferred consideration
 (357)
Gain (loss) on foreign exchange
293 (77)
(Loss) gain on sales from Gold Prepayment Agreement
(2,914)284 
Other income (expense)
872 (474)
Total other (expense) income
(10,331)21,488 
Gain and loss on revaluation of the fair value for embedded derivatives of the Gold Prepay and Silver Purchase Agreement are driven by changes in the gold and silver forward prices during the period.
Gain and loss on revaluation of the fair value of warrants and convertible loan derivatives were driven by changes in the Company’s share price during the period.

Gain and loss on sale of gold for the Gold Prepayment Agreement is due to changes of the realized gold price compared to the pricing at inception of the agreement.

The loss on Gold Prepay Agreement modification recognized in the three months ended September 30, 2023 was related to the amendment to the Gold Prepay Agreement whereby additional warrants were issued and fees paid.

Finance Expense
 Three months ended
September 30,
(in thousands of USD)20242023
Interest accretion on Gold Prepay Agreement2,413 1,931 
Interest accretion on convertible loans2,728 2,303 
Interest accretion on convertible debentures2,454 2,056 
Interest accretion on silver purchase agreement697 863 
Environmental rehabilitation accretion688 720 
Amortization of finance costs341 242 
Interest paid1 18 
Total finance expense9,322 8,133 

11

image_1b.jpg
Finance expense for the three months ended September 30, 2024 was $9.3 million, an increase of $1.2 million compared to the three months ended September 30, 2023, primarily from higher interest accretion due to higher balances owing on Gold Prepay agreement, convertible loans and convertible debentures.
Financial results for the nine months ended September 30, 2024
Revenue

Revenue for the nine months ended September 30, 2024 was $27.1 million, a decrease of 7% from $29.1 million in the comparative prior year period. During the nine months ended September 30, 2024, mineralized material sold totaled 29,041 tons and gold ounces sold totaled 7,186 ounces at an average realized gold price1 of $2,290 per ounce, compared to mineralized material sales of 22,710 tons and gold ounces sold of 11,262 at an average realized gold price1 of $1,924 per ounce during the same period of 2023, a decrease of 4,076 in gold ounces sold or 36%. The lower revenue was primarily driven by lower ounces sold at the Ruby Hill mine and Granite Creek mine, partially offset by higher average realized gold price1.
Nine months ended
September 30,
Spot price per ounce of gold
20242023% Change
Average2,295 1,931 19 %
Low1,985 1,811 10 %
High2,664 2,049 30 %
Average realized2,290 1,924 19 %
Cost of sales     
Cost of sales for the nine months ended September 30, 2024 was $42.3 million, which was an increase of 37% from cost of sales of $31.0 million in the comparative prior year period, largely related to inventory impairment of $12.1 million from an updated assumption used to estimate recoverable ounces mined and stockpiled at the Granite Creek mine, and higher cost per ounce due to lower production due to underground de-watering efforts at the Granite Creek mine.

Depreciation, depletion and amortization

Total depreciation, depletion, and amortization expense for the nine months ended September 30, 2024 was $1.0 million, a decrease of 82% compared to $5.6 million from the prior year period. The lower depreciation in 2024 is due to the majority of the processing equipment being fully depreciated at Ruby Hill in 2023.
Exploration and pre-development expenses
Nine months ended
September 30,
(in thousands of USD)20242023
Granite Creek, Nevada4,072 2,184 
Ruby Hill, Nevada986 15,024 
McCoy-Cove, Nevada8,512 10,241 
FAD, Nevada238 2,282 
Buffalo Mountain, Nevada48 — 
Other (i)
11 357 
Total exploration, evaluation and pre-development13,867 30,088 
(i)Other includes charges for regional technical services costs not charged to a property.

For the nine months ended September 30, 2024, the company incurred $13.9 million of exploration, evaluation and pre-development expenses compared to $30.1 million of expenses for nine months ended September 30, 2023. The lower exploration expense for the nine months ended September 30, 2024 was a result of the Company pausing activities at Ruby Hill during the due diligence exclusivity period for the potential joint-venture partner. The decrease of $16.2 million is primarily due to $14.0 million lower spending at Ruby Hill as described above and $1.7 million lower spending related to McCoy-Cove due to a delay in the commencing of the drilling exploration activities, offset by slightly higher spending at the Granite Creek mine from surface drilling activities.
1This is a Non-IFRS Measure; please see “Non-IFRS Measures” section.
12

image_1b.jpg
Other (expense) income
 Nine months ended
September 30,
(in thousands of USD)20242023
Gain on convertible loan derivatives
8,424 24,037 
Gain on warrants
687 17,532 
Loss on Gold Prepay derivative
(7,913)(63)
(Loss) gain on Silver Purchase derivative
(6,579)1,274 
Loss on Gold Prepay Agreement modification
(667)(1,831)
Loss on Silver Purchase Agreement modification
(440)— 
Gain on investments
 997 
Gain on convertible debenture
 900 
(Loss) gain on sales from Gold Prepayment Agreement
(3,975)546 
Gain (loss) on foreign exchange
673 (32)
Loss on deferred consideration
 (1,135)
Other income
2,693 925 
Total other (expense) income
(7,097)43,150 
The gain and loss on the valuation of the derivatives of the Gold Prepay and Silver Purchase Agreements are driven by changes in the gold and silver forward prices during the period.
The gain and loss on the valuation of the fair value of warrants, convertible loan and convertible debenture derivatives were driven by an changes in the Company’s share price during the period.

The gain and loss for the purchase of gold in settlement of the Gold Prepayment Agreement is due to changes of the realized gold price compared to the price at inception of the agreement.

The gain and loss on the Gold Prepay and Silver Purchase Agreement modifications recognized in the nine months ended September 30, 2024 and the prior year comparative period were related to the amendments to the agreements whereby additional consideration was provided to Orion.

The gain on investments recorded in the nine months ended September 30, 2023 were related to the Company’s investment in Paycore.

Finance Expense
 Nine months ended
September 30,
(in thousands of USD)20242023
Interest accretion on convertible loans7,795 6,677 
Interest accretion on Gold Prepay Agreement7,716 5,897 
Interest accretion on silver purchase agreement2,376 2,510 
Interest accretion on convertible debentures7,000 4,780 
Environmental rehabilitation accretion2,191 2,160 
Amortization of finance costs975 633 
Interest paid455 41 
Total finance expense28,508 22,698 

Finance expense for the nine months ended September 30, 2024 was $28.5 million, an increase of $5.8 million compared to the nine months ended September 30, 2023, primarily due to higher interest accretion due to higher balances owing on the convertible loans and the Gold Prepay Agreement and a full period of interest accretion on convertible debentures of $2.2 million as compared to a partial period in 2023.

Income Taxes
For the nine months ended September 30, 2024, deferred tax recovery of nil decreased from a deferred tax recovery of $8.0 million. The Company reversed its deferred tax liability as result of recognizing of tax losses during the nine months ended September 30, 2023.

13

image_1b.jpg
Selected Quarterly Information
The following is a summary of selected operating and financial information from the past eight quarters.
(in thousands of USD, unless otherwise noted)Q3Q2Q1Q4Q3Q2Q1Q4
20242024202420232023202320232022
Gold sales (ounces)3,063 1,636 2,486 3,350 4,585 4,329 2,349 6,769 
Oxidized material sales (tons)14,696 4,178 10,167 31,711 16,059 6,651 — — 
Sulfide material sales (tons) (i) 5,183 — 29,512 — — — — 
Revenue11,509 7,184 8,413 25,837 13,215 11,310 4,548 11,647 
Costs of sales(15,449)(18,994)(7,904)(21,878)(12,244)(12,188)(6,542)(13,530)
Depletion, depreciation and amortization(552)(74)(377)(1,613)(1,444)(2,724)(1,421)(1,579)
Mine operating income / (loss)(4,492)(11,884)132 2,346 (473)(3,602)(3,415)(3,462)
Other significant income / (loss):
Exploration, evaluation and pre-development(6,019)(5,065)(2,782)(8,825)(10,014)(11,095)(8,979)(6,625)
General and administrative(4,554)(6,007)(4,578)(4,788)(4,136)(4,397)(5,191)(4,509)
Property maintenance(2,549)(1,864)(3,405)(2,321)(2,763)(2,781)(2,449)(2,111)
Share‑based payments(794)(612)(530)(667)(244)(903)(1,308)(820)
Other (expense) / income(10,331)(1,519)4,753 (8,228)21,488 10,476 11,185 (43,696)
Finance expense(9,322)(9,880)(9,306)(9,208)(8,133)(7,898)(6,667)(5,954)
Loss for the period(38,061)(36,831)(15,716)(31,919)(4,199)(15,962)(13,118)(63,938)
(i)In December 2023, the Company entered into a sulfide mineralized material sales and purchase agreement with a third party.
Quarterly results are predominantly affected by the number and mix of gold ounces sold, oxidized and sulfide mineral material sold due to different payability, the average realized price per ounce, the cost of sales, and any unusual items. The quarterly year-over-year changes in revenue were primarily related to corresponding changes in gold and mineralized material sold, partially offset by increase in average realized gold price1.


1This is a Non-IFRS Measure; please see “Non-IFRS Measures” section.
14

image_1b.jpg
DISCUSSION OF FINANCIAL POSITION
Balance Sheet Review
Assets
Cash equivalents increased by $5.5 million from $16.3 million at December 31, 2023 to $21.8 million at September 30, 2024. Refer to the Liquidity and Capital Resources section below for further details.

Property, plant and equipment increased from $638.6 million at December 31, 2023 to $656.2 million at September 30, 2024, the increase was mainly due to capital investment for development work of $18.2 million and $3.0 million in mining equipment at the Granite Creek mine.

Restricted cash and cash equivalents decreased from $44.5 million at December 31, 2023 to $39.9 million at September 30, 2024, primarily due to $5.0 million release of collateral on the surety bonds related to closure obligations at the Lone Tree property.
Liabilities
Total liabilities increased from $297.4 million December 31, 2023 to $301.7 million at September 30, 2024, an increase of $4.3 million. The increase in total liabilities was primarily from increases in other liabilities of $12.8 million due to changes in the fair value of warrants and the embedded derivatives on the Gold Prepay and Silver Purchase Agreement, partially offset by decreases in accounts payable and accrued liabilities due to increased payment to vendors of $5.8 million in the current period and decrease in long term debt of $3.5 million from debt repayment.
LIQUIDITY AND CAPITAL RESOURCES
Liquidity Outlook
For the period ended
(in thousands of USD)September 30, 2024December 31, 2023
Cash and cash equivalents21,776 16,277 
Working capital(92,927)(92,852)

As of September 30, 2024, the working capital deficit was comparable to December 31, 2023. Changes in cash and cash equivalents are discussed in the cash flow section.

The Company through its recapitalization plan discussed in the Strategic Overview continues to work toward a deferral of the scheduled deliveries under the Gold Prepay Agreement and Silver Purchase Agreement, which will provide the necessary liquidity to execute on its recapitalization and refinancing plan expected before the end of the first quarter of 2025.

The Company’s ability to continue to operate and execute its new development plan and fulfill its commitments as they come due is dependent upon its success in restructuring its current debt obligations and obtaining additional financing. While Management has been successful in raising additional funds in the past, there can be no assurance that it will be able to do so in the future. Given the Company’s working capital deficit, current operating losses and Management’s expectation of future losses until it has fully executed its new development plan, the inability of the Company to arrange appropriate financing in a timely manner could result in the carrying value of the Company’s assets being subject to material adjustment. These conditions indicate the existence of material uncertainties which cast significant doubt as to the Company’s ability to continue as a going concern.

Equity
Outstanding share data
As of November 12, 2024
Common Shares
404,788,128
Warrants
48,185,249
Stock Options
10,601,184
Restricted Share Units ("RSU")
2,865,555
Deferred Share Units ("DSU")
884,087










15

image_1b.jpg


Share Capital

For the three months ended September 30, 2024, the only equity activity was the ATM Program.

During the nine months ended September 30, 2024, the Company issued the following shares:

Share issuance
Shares issuedProceeds
(000s)
($000s)
Brokered placement
69,69874,644 
Private placement
13,06417,436 
ATM Program
11,49813,073 
Granite Creek contingent payments
2,7273,564 
Exercise of stock options944 2,010 
97,931110,727 
Contingent Payment - On February 9, 2024, the Company issued 1.6 million common shares to Waterton at a price of C$1.80 for total gross proceeds of $2.1 million (C$2.9 million) as partial consideration of the contingent value rights payment related to Granite Creek due upon production of the first ounce of gold (excluding ordinary testing and bulk sampling programs) following a 60 consecutive day period where gold prices have exceeded $2,000 per ounce, as further described in Note 8 (a) of the Financial Statements
Contingent Payment - On March 20, 2024, the Company issued 1.1 million common shares to Waterton at a price of C$1.73 for total gross proceeds of $1.4 million (C$2.0 million) as partial consideration of the contingent value rights payment related to Granite Creek, as further described in Note 8 (a) of the Financial Statements.
Private Placement of Common Shares - On February 20, 2024, the Company completed a non-brokered private placement of common shares. An aggregate of 13.1 million shares were issued by the Company at a price of C$1.80 per common share for aggregate gross proceeds of $17.4 million (C$23.5 million).
Brokered Placement - On May 1, 2024, the Company completed a bought deal public offering of an aggregate of 69.7 million Units at a price of C$1.65 per Unit for aggregate gross proceeds to the Company of approximately $83.5 million (C$115.0 million). Each Unit consists of one common share in the capital of the Company and one-half of one common share purchase warrant of the Company. The Company incurred $4.5 million in transaction costs in connection with the Offering, of which $4.1 million was allocated to shares issued and presented as a reduction to share capital within the statement of changes in equity.
ATM Program - For the period from August 12, 2024 to September 30, 2024, the Company issued 11.5 million common shares under the ATM Program at a weighted average share price of $1.14 per common share for total gross proceeds of $13.1 million. Transaction costs incurred of $0.4 million are presented as a reduction to share capital.

ATM Program and Filing of Prospectus Supplement

The Company obtained a receipt for a final short form base shelf prospectus on June 24, 2024 (the "Canadian Shelf Prospectus"). The Canadian Shelf Prospectus was filed with the securities regulators in each province and territory of Canada, and a corresponding U.S. base prospectus contained in its registration statement on Form F-10 (the "U.S. Base Prospectus") was filed with the SEC.

These filings allow the Company to make offerings of common shares, warrants, debt securities, subscription receipts and units (collectively, the “Securities”), or any combination thereof, from time to time over a 25-month period in both Canada and the United States. Upon filing its annual 10-K the Company's current U.S. Base Prospectus will no longer be available for future securities offerings. The Securities may be offered in amounts, at prices and on terms to be determined at the time of sale and, subject to applicable regulations, may include “at-the-market” offerings, public offerings or strategic investments. The specific terms of future offerings of Securities, if any such offerings occur, will be set forth in one or more prospectus supplement(s) to be filed with applicable securities regulators.

The ATM Program has been implemented pursuant to the terms of an equity distribution agreement dated August 12, 2024 (the "Equity Distribution Agreement"), among the Company, National Bank Financial Inc., and a syndicate of underwriters (collectively, the "Agents"). The ATM Program allows i-80, through the Agents, to, from time to time, offer and sell in Canada and the United States through the facilities of the TSX and the NYSE American stock exchange (the “NYSE American”) such number of common shares in the capital of the Company (the “Shares”) as would have an aggregate offering price of up to $50 million.

The offering of Shares under the ATM Program are made through and qualified in Canada by, a prospectus supplement dated August 12, 2024 (the “Canadian Prospectus Supplement”) to the Canadian Shelf Prospectus, each filed with the securities commissions in each of the provinces and territories of Canada, and in the United States pursuant to a prospectus supplement dated August 12, 2024 (the “U.S. Prospectus Supplement”) to the Company's U.S. Base Prospectus filed with the SEC.

The ATM Program will be effective until the filing of the Company's annual 10-K (on or prior to March 31, 2025), unless terminated before such date by i-80 or otherwise in accordance with the Equity Distribution Agreement. Once the 10-K is filed, the Company will be required to file a new registration statement for purposes of qualifying any future prospectus issuance of securities in the United States. The timing and extent of the use of the ATM Program will be at the discretion of the Company. Accordingly, total gross proceeds from equity offerings under the ATM Program, if any, could be significantly less than $50 million. As of November 12, 2024, $29.9 million is still available to be issued under the ATM Program.
16

image_1b.jpg

Share Purchase Warrants

Share purchase warrants outstanding as at September 30, 2024:

In connection with the Orion financing package the Company completed during the fourth quarter of 2021, the Company issued 5.5 million common share warrants exercisable at C$3.28 per share with an exercise period of 36 months or until December 13, 2024. On September 20, 2023, in connection with the Gold Prepay Agreement the Company extended the expiry date by an additional twelve months to December 13, 2025. The initial fair value of the warrants recognized on inception was $3.5 million and at September 30, 2024 $0.5 million.
In connection with the Paycore acquisition from 2023 the Company issued a total of 3.8 million common share warrants for Paycore warrants outstanding on the date of acquisition. The replacement warrants are comprised of 0.3 million common share warrants at an exercise price of C$2.40 per common share until February 9, 2025, and 3.3 million common share warrants at an exercise price of C$4.02 per common share until May 2, 2025. The initial fair value of the warrants recognized on inception was $2.7 million and at September 30, 2024 $0.1 million.
In connection with the Gold Prepay Agreement entered into during the third quarter of 2023, the Company issued 3.8 million common share warrants exercisable at C$3.17 per share with an exercise period of 36 months or until September 20, 2026. The warrants include a four month hold period. The initial fair value of the warrants recognized on inception was $1.9 million and at September 30, 2024 $0.6 million.
In connection with the Silver Purchase Extension Agreement entered into during the first quarter of 2024, the Company issued 0.5 million common share warrants exercisable at C$2.72 per share with an exercise period of 48 months or until January 24, 2028. The warrants include a four month hold period. The initial fair value of the warrants recognized on inception was $0.3 million and at September 30, 2024 was $0.2 million.
As part of the Brokered Placement, 34.8 million warrants were issued, exercisable to acquire one common share of the Company for a period of 48 months from closing of the Offering at an exercise price of C$2.15 per share. On May 1, 2024, share purchase warrants issued in connection with the Offering commenced trading on the TSX under the symbol "IAU.WT".The 34.8 million common share warrants issued in connection with the offering were valued at $8.9 million at inception using the closing price of the warrants of C$0.35 on May 1, 2024.

The below table compares the actual use of proceeds as at September 30, 2024 with the expected uses described in the Prospectus dated April 25, 2024 in connection with the Brokered Placement:
Use of proceeds (in millions of US dollars)
Expected Use of Proceeds
Actual Use of Proceeds
Variance
Development and expansion at the Granite Creek Project$7,257 $6,284 $973 
Working capital requirements of the McCoy-Cove Project11,8384,922 6,916 
Working capital requirements of the Ruby Hill Project9,6772,221 7,456 
Working capital requirements of the Lone Tree Project13,0003,532 9,468 
General working capital/corporate purposes21,81410,461 11,353 
Debt Repayments16,423 32,205 (15,782)
Total$80,009 $59,625 $20,384 
The actual use of proceeds includes spending during the period of May 1 through September 30, 2024, or 5 months of the 15 month projected timeline for the expected use of proceeds. The use of proceeds excluded any revenue generated and associated costs to produce the revenue for those projects that produce revenue from the sale of ounces or mineralized material.

For development and expansion at the Granite Creek Project, the spending included an increase in spending for de-watering equipment, drilling of an additional de-watering well and related capital. This increase in spending was offset due to pausing the surface drilling program at the South Pacific Zone as the Company determined it was more cost effective to develop an exploration drift and complete the drill program from underground.

The increase of use of proceeds related to debt repayments is due to delivering the ounces related to the second quarter gold prepay. The second quarter gold prepay payment was anticipated to be deferred in the expected use of proceeds. In addition, due to the increase in precious metal pricing, the first quarter gold prepay and the 2023 silver prepay delivery that was deferred until the second quarter resulted in high payments than expected. This increase in the gold and silver prices also elevated the value of the second quarter gold prepayment.

The use of proceeds for McCoy-Cove are driven by the drilling program. The drilling program is advancing and is expected to be completed during the first half of 2025.


17

image_1b.jpg
Cash Flows

Three months ended
September 30,
Nine months ended
September 30,
(in thousands of U.S. dollars, unless otherwise noted)2024202320242023
OPERATING ACTIVITIES
Loss for the period$(38,061)$(4,199)$(90,606)$(33,278)
Items not affecting cash and adjustments21,154 (11,778)40,717 (19,050)
Change in non-cash working capital(2,094)1,540 (12,008)(1,463)
Cash used in operating activities$(19,001)$(14,437)$(61,897)$(53,791)
INVESTING ACTIVITIES
Capital expenditures on property, plant and equipment(4,723)(11,572)(14,142)(34,389)
Restricted cash(447)3,596 4,589 (11,073)
Other assets — 425 — 
Net cash acquired in acquisition of Paycore Minerals Inc. —  10,027 
Purchase of investments —  (894)
Cash used in investing activities$(5,170)$(7,976)$(9,128)$(36,329)
FINANCING ACTIVITIES
Proceeds from shares issued in brokered placement — 83,500 — 
Proceeds from shares issued in equity financing 27,693 17,436 27,693 
Proceeds from shares issued in ATM Program12,965 — 12,965 — 
Net proceeds from Gold Prepay Agreement 18,932  18,932 
Net proceeds on Convertible Debentures —  61,906 
Contingent payments —  (11,000)
Principal repayment on Gold Prepay Agreement(14,101)(3,989)(23,818)(12,192)
Principal repayment on Silver Purchase Agreement (28)(8,387)(5,690)
Share issue costs(397)(1,632)(4,878)(1,632)
Stock option and warrant exercises38 44 933 1,947 
Finance fees paid(564)— (1,514)— 
Other(98)(149)(385)(340)
Cash (used in) provided by financing activities$(2,157)$40,871 $75,852 $79,624 
Change in cash and cash equivalents during the period(26,328)18,458 4,827 (10,496)
Cash and cash equivalents, beginning of period47,812 19,355 16,277 48,276 
Effect of exchange rate changes on cash held292 (78)672 (45)
Cash and cash equivalents, end of period$21,776 $37,735 $21,776 $37,735 

Cash flows for the three months ended September 30, 2024

Cash used in operating activities for the three months ended September 30, 2024, was $19.0 million compared to $14.4 million cash used in operating activities in the comparative periods of 2023. The $4.6 million increase in cash used in operating activities was primarily due to lower mine operating income partially offset by lower exploration, evaluation and pre-development expenses.

Cash used in investing activities for the three months ended September 30, 2024 was $5.2 million compared to $8.0 million in the comparative periods of 2023. Cash used in investing activities for the three months ended September 30, 2024 primarily relates to capital expenditures on mine development of $4.7 million at the Granite Creek mine. Cash used in investing activities for the three months ended September 30, 2023 was primarily related to capital investment of $11.6 million for development work at Granite Creek, the exploration ramp at McCoy-Cove and the engineering and design work on the autoclave at Lone Tree, partially offset by funds returned from the surety bonds of $3.6 million.

Cash used in financing activities for the three months ended September 30, 2024 was $2.2 million compared to cash provided by financing activities of $40.9 million in the comparative period of 2023. Cash used in financing activities for the three months ended September 30, 2024, was primarily due to $14.1 million repayment on the Gold Prepay Agreement, partially offset by $13.0 million cash provided by proceeds from the ATM Program. Cash provided by financing activities for the three months ended September 30, 2023 was primarily driven by proceeds received of $27.7 million from the equity financing and net proceeds received of $18.9 million from the 2023 gold prepay accordion, offset by repayment on the Gold Prepay Agreement of $4.0 million.

18

image_1b.jpg
Cash flows for the nine months ended September 30, 2024

Cash used in operating activities for the nine months ended September 30, 2024, was $61.9 million compared to $53.8 million cash used in operating activities in the comparable period of 2023. The increase of $8.1 million in cash used in operating activities for the nine months ended September 30, 2024 was primarily related to the $10.5 million change in working capital related to operations. The $2.4 million increase in cash outflows from operating activities before working capital was primarily due to lower exploration, evaluation and pre-development expenses of $16.2 million partially offset by higher mine operating loss.

Cash used in investing activities for the nine months ended September 30, 2024 was $9.1 million compared to $36.3 million for the nine months ended September 30, 2023. Cash used in investing activities for the nine months ended September 30, 2024 was primarily driven by capital expenditures of $14.1 million partially offset by funds returned from surety bonds of $4.6 million. Cash used in investing activities for the nine months ended September 30, 2023 was primarily driven by $12.9 million and $6.5 million in mine development expenditures at Granite Creek and McCoy Cove, respectively, engineering and design work on the autoclave at Lone Tree of $12.5 million, additional funds placed into the surety bonds of $11.1 million, and additional funds spent on purchasing of investments of $0.9 million, partially offset by funds received of $10.0 million from the Paycore acquisition.

Cash provided by financing activities for the nine months ended September 30, 2024 was $75.9 million compared to $79.6 million for the nine months ended September 30, 2023. Cash provided by financing activities for the nine months ended September 30, 2024 was primarily from proceeds from bought deal public offering of $83.5 million, net proceeds of $17.4 million from the equity financing, $13.0 million from proceeds from the ATM equity program, partially offset by payments on the Gold Prepay and Silver Purchase Agreement of $23.8 million and $8.4 million, respectively and share issuance costs of $4.9 million. Cash used in investing activities for the nine months ended September 30, 2023 was primarily driven by net proceeds from the convertible debenture of $61.9 million, proceeds received of $27.7 million from the equity financing and net proceeds received of $18.9 million from the 2023 gold prepay accordion, partially offset by payments on the Gold Prepay and Silver Purchase Agreement of $12.2 million and $5.7 million, respectively, and a contingent payment of $11.0 million in satisfaction of the First and Second Milestone Payments for the deferred consideration of the acquisition of Ruby Hill.

COMMITMENTS AND CONTINGENCIES

The Company has described its commitments and contingencies in to Note 20 of the Financial Statements for the three and nine months ended September 30, 2024.

Off Balance Sheet Arrangements

The Company has no off-balance sheet other than the commitments disclosed in the Financial Statements for the three and nine months ended September 30, 2024.

CRITICAL ACCOUNTING JUDGEMENTS AND ESTIMATES, POLICIES AND CHANGES

Critical accounting policies and estimates used to prepare our financial statements are discussed with our audit committee as they are implemented on an annual basis. The were no significant changes in our critical accounting policies or estimates since December 31, 2023. For further details on the Company’s accounting policies and estimates, refer to the Company’s audited consolidated financial statements for the year ended December 31, 2023.

Transition to US Generally Accepted Accounting Principles

Historically, and including these condensed consolidated interim financial statements, the Company has prepared its financial statements under IFRS Accounting Standards for reporting as permitted by security regulators in Canada, as well as in the United States under the status of a foreign private issuer as defined by the United States Securities and Exchange Commission (the “SEC”). On June 28, 2024, the Company determined that it will no longer qualify as a foreign private issuer under the SEC rules as of January 1, 2025. As a result, beginning January 1, 2025 the Company is required to report with the SEC on domestic forms and comply with domestic company rules. Consequently, the Company will be required to prepare its financial statements using United States Generally Accepted Accounting Principles (“US GAAP”) effective beginning with the Company’s 2024 annual consolidated financial statements and for all subsequent reporting periods. The transition to US GAAP will be made retrospectively. The Company is currently evaluating the impact of the conversion to US GAAP on the financial statements. The Company expects it will meet the transition work to US GAAP to meet its reporting timelines for fiscal 2024.

NON-IFRS FINANCIAL PERFORMANCE MEASURES

The Company has included certain terms or performance measures commonly used in the mining industry that are not defined under IFRS Accounting Standards in this document. These include: adjusted loss, adjusted loss per share, and average realized price per ounce. Non-IFRS financial performance measures do not have any standardized meaning prescribed under IFRS Accounting Standards, and therefore, they may not be comparable to similar measures employed by other companies. The data presented is intended to provide additional information and should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS Accounting Standards and should be read in conjunction with the Company's Financial Statements.

Definitions

“Average realized gold price” per ounce of gold sold is a non-IFRS measure and does not constitute a measure recognized by IFRS Accounting Standards and does not have a standardized meaning defined by IFRS Accounting Standards. It may not be comparable to information in other gold producers’ reports and filings.
19

image_1b.jpg

“Adjusted loss” and “adjusted loss per share” are non-IFRS measures that the Company considers to better reflect normalized earnings because it eliminates temporary or non-recurring items such as: gain (loss) on warrants, gain (loss) on convertible debentures and loans, gain (loss) on fair value measurement of gold and silver prepayment agreement, loss on Gold Prepay Agreement modification, loss on Silver Purchase Agreement modification, and inventory impairments. Adjusted loss per share is calculated using the weighted average number of shares outstanding under the basic calculation of earnings per share as determined under IFRS.

Average realized gold price per ounce of gold sold

Three months ended
September 30,
Nine months ended
September 30,
(in thousands of U.S. dollars, unless otherwise noted)2024202320242023
Nevada production
Revenue per financial statements11,509 13,215 27,107 29,073 
Mineralized material sales revenue(4,090)(4,456)(10,577)(7,277)
Revenue without mineralized material sales7,419 8,758 16,530 21,796 
Silver revenue from mining operations(1)(70)(72)(131)
Gold revenue from mining operations7,418 8,688 16,458 21,665 
Ounces of gold sold3,063 4,585 7,186 11,262 
Average realized gold price ($/oz)2,422 1,895 2,290 1,924 
Lone Tree
Revenue4,522 3,417 11,507 10,092 
Silver revenue from mining operations(1)— (29)(19)
Gold revenue from mining operations4,521 3,417 11,478 10,073 
Ounces of gold sold1,842 1,775 5,010 5,138 
Average realized gold price ($/oz)2,454 1,925 2,291 1,960 
Ruby Hill
Revenue2,105 3,623 4,232 9,125 
Silver revenue from mining operations— (70)(43)(112)
Gold revenue from mining operations2,105 3,553 4,189 9,013 
Ounces of gold sold906 1,910 1,861 4,781 
Average realized gold price ($/oz)2,323 1,860 2,251 1,885 
Granite Creek
Revenue4,882 6,175 11,368 9,856 
Mineralized material sales revenue(4,090)(4,456)(10,577)(7,277)
Gold revenue from mining operations792 1,719 791 2,579 
Ounces of gold sold315 900 315 1,344 
Average realized gold price ($/oz)2,514 1,910 2,511 1,919 

20

image_1b.jpg
Adjusted loss

Adjusted loss and adjusted loss per share exclude a number of temporary or one-time items detailed in the following table:
Three months ended
September 30,
Nine months ended
September 30,
(in thousands of U.S. dollars, unless otherwise noted)(i)
2024202320242023
Net loss for the period
$(38,061)$(4,199)$(90,606)$(33,278)
Adjust for:
(Loss) gain on convertible loans
(721)13,574 8,424 24,037 
(Loss) gain on warrants
(3,587)7,357 687 17,532 
(Loss) gain on Gold Prepay derivative
(2,998)2,190 (7,913)(63)
(Loss) gain on Silver Purchase derivative
(1,276)822 (6,579)1,274 
Gain on convertible debenture
 —  900 
Loss on Gold Prepay Agreement modification
 (1,831)(667)(1,831)
Loss on Silver Purchase Agreement modification
 — (440)— 
Inventory impairments(3,331)— (12,095)(8,531)
Loss on deferred consideration (357) (1,135)
Total adjustments(11,913)21,755 (18,583)32,183 
Adjusted loss for the period
$(26,148)$(25,954)$(72,023)$(65,461)
Weighted average shares for the period386,474,070 287,128,970 350,581,065 266,207,340 
Adjusted loss per share for the period
$(0.07)$(0.09)$(0.21)$(0.25)

RISKS AND RISK MANAGEMENT

Readers of this MD&A are encouraged to read the “Risk Factors” as more fully described in the Company’s filings with the Canadian Securities Administrators, including its Annual Information Form for the year ended December 31, 2023, available under the Company’s issuer profile on SEDAR+ at www.sedarplus.ca. The following, while not exhaustive, are important Risk Factors to consider: Inability to Obtain Additional Financing and Reduction in Scope of Planned Business Objectives, The Company's mining operations are inherently dangerous various factors could result in an interruption of the Company's operations and impact its business and financial condition; The estimation of mineral reserves and mineral resources may be imprecise and depends upon subjective factors; Estimated mineral reserves and mineral resources may not be realized in actual production; Company's results of operations and financial position may be adversely affected by inaccurate estimates; Company's mineral resources do not have demonstrated economic viability and may never be classified as proven or probable mineral reserves; Fluctuating commodity prices may result in the Company not receiving an adequate return on invested capital and a loss of all or part of an investment in securities of the Company may result; Failure to further develop the Ruby Hill Project, the Granite Creek Project, McCoy-Cove project or the Lone Tree Project may result in a material adverse effect on the Company's business, financial condition, results of operations, cash flows and prospects; Company is not able to obtain any additional financing required to advance exploration and development; Company may not be able to generate sufficient cash to service all of its indebtedness and may be forced to take other actions to satisfy its obligations under such indebtedness, which may not be successful; Failure to achieve capital and operational cost estimates could have an adverse impact on the Company's future cash flows and financial condition; Forecasts of future production are estimates and actual production may be less than estimated, which could have a material adverse effect on the Company's results of operations and financial condition; Inability to renegotiate the toll milling agreement; Company may continue to have negative cash flow from operating activities in future periods; Company is dependent on a small number of key employees; Failure to retain directors and senior management; reliance on third parties for important relationships and services; the Company's financial statements may not reflect what the Company's financial position, results of operations or cash flows will be in the future; A failure or breach of the Company's network systems could corrupt the Company's financial or operational data; no assurance that the Company's title to mineral projects will be secured; The Company's activities are subject to extensive governmental regulation; Public Health Risks; Interference in the maintenance or provision of the Company's infrastructure; Information technology failures or cyber security incidents; Labor difficulties; Failure to maintain or obtain permits and licenses; Company's operations are subject to extensive environmental regulation; land reclamation requirements; surety bonds risk, hazards associated with mining activities; Existing or future competition in the mining industry; fail to select appropriate acquisition targets and may not be able to integrate any acquired businesses; acquisition risks; Company's directors and officers may be subject to conflicts of interest; non compliance from ESTMA; developing and maintaining relationships with local communities; disputes with third parties and an inability to resolve these disputes favorably; Damage to the Company's image and reputation; Climate change; access to the resources and materials it needs; mineral properties or mineral projects may be subject to various land payments; The Company has significant shareholders that may be able to significantly affect the outcome of important matters; Geological, hydrological, and climatic events; Rising inflation could lead to increased costs; Securities analysts or other third parties may publish inaccurate or unfavorable research reports; Internal control over financial reporting and disclosure controls and procedures cannot provide complete assurance of error-free reporting; International conflict and other geopolitical tensions or events, such as the current Russia-Ukraine conflict, may have an adverse effect on the Company's business, financial condition and results of operations; No guarantee of positive return on investment; There is no certainty that an active trading market for the Common Shares will develop or be sustained; Common Shares may be subject to significant price and volume fluctuations; The Company may need to sell additional Common Shares to finance its operations and such future sales may dilute shareholders' equity position in the Company; Sales by existing shareholders in the public market could reduce the price of the Common Shares and impair the Company's ability to raise additional capital; The Company's dual listing may increase the volatility of the Common Shares; A decline in the price of Common Shares could impede the Company's ability to raise additional capital to finance its operations and may materially adversely affect its business plan and ability to meet obligations as
21

image_1b.jpg
they become due; The Company may become involved in, named as a party to or the subject of, various legal proceedings and third party disputes, including regulatory proceedings, tax proceedings and other legal actions or disputes relating to, among other things, personal injuries, property damage, contract disputes and their business activities; The Company has no history of earnings and has no current plans to pay dividends in the foreseeable future; Forward-looking statements are based on assumptions and the actual results of the Company may differ materially from those suggested by the forward-looking statements; As a foreign private issuer, the Company is subject to different United States securities laws and rules than a United States domestic issuer, which may limit the information publicly available to United States investors; The Company relies upon certain accommodations available to it as an "emerging growth company"; Enforcement of Civil Liabilities in the United States.
Financial Instruments and Related Risks

The Company is exposed to financial instrument risk (credit risk, liquidity risk and market risk), where material these risks are reviewed by the Board of Directors. For details on the Company’s financial instruments and related risks, see Note 21 in the Company’s Financial Statements for the three and nine months ended September 30, 2024.

Management of Capital Risk

The Company's objectives when managing capital are to safeguard the Company's ability to continue as a going-concern in order to pursue the exploration and development of its mineral properties and to maintain a flexible capital structure which optimizes the costs of capital at an acceptable risk.

The Company manages its capital structure and makes adjustments to it in light of changes in economic conditions and the risk characteristics of the underlying assets. To maintain or adjust the capital structure, the Company may attempt to issue new shares, acquire or dispose of assets or acquire new debt.

In order to maximize ongoing exploration and development efforts, the Company does not pay out dividends. The Company's investment policy is to invest its short-term excess cash in highly liquid short-term interest-bearing investments with short-term maturities, selected with regard to the expected timing of expenditures from continuing operations.

To effectively manage its capital requirements, the Company has in place a planning and budgeting process to help determine the funds required to ensure the Company has the appropriate liquidity to meet its operating and growth objectives.

MANAGEMENT’S REPORT ON INTERNAL CONTROL OVER FINANCIAL REPORTING

In compliance with the Canadian Securities Administrators’ Regulation, we have filed certificates signed by the Chief Executive Officer (“CEO”) and the Chief Financial Officer (“CFO”) that, among other things, report on the design of disclosure controls and procedures and the design of internal controls over financial reporting.

Disclosure Controls and Procedures

The CEO and the CFO have designed disclosure controls and procedures or have caused them to be designed under their supervision, in order to provide reasonable assurance that (i) material information relating to the Company has been made known to them; and (ii) information required to be disclosed in the Company’s filings is recorded, processed, summarized and reported within the time periods specified in securities legislation. There were no changes made to i-80 Gold’s disclosure controls and procedures in the three and nine months ended September 30, 2024. Based on this evaluation, the CEO and CFO have concluded that the Company’s disclosure controls and procedures were effective as at September 30, 2024.

Internal Control over Financial Reporting

The CEO and the CFO have also designed internal controls over financial reporting (“ICFR”) or have caused them to be designed under their supervision, in order to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with IFRS. In making this assessment, management used the criteria set forth by the Committee of Sponsoring Organizations of the Treadway Commission (“COSO”) in Internal Control – Integrated Framework (COSO 2013). Any system of internal control over financial reporting, no matter how well designed, has inherent limitations. Therefore, even those systems determined to be effective can provide only reasonable, not absolute, assurance with respect to financial statement preparation and presentation. There have been no significant changes in our internal controls during the nine months ended September 30, 2024 that have materially affected, or are reasonably likely to materially affect, i-80 Gold’s internal control over financial reporting. Based on this assessment management concluded that the Company’s internal controls over financial reporting were effective as of September 30, 2024.

Limitations of Controls and Procedures

Further, the design of a control system must reflect the fact that there are resource constraints, and the benefits of controls must be considered relative to their costs. Also, projections of any evaluation of effectiveness to future periods are subject to the risk that any design will not succeed in achieving its stated goals under all potential future conditions. Accordingly, because of the inherent limitations in a cost-effective control system, misstatements due to error or fraud may occur and not be detected.

TECHNICAL INFORMATION

Scientific and technical information contained in this MD&A has been reviewed and approved by Tim George, PE, and Tyler Hill, CPG-12146, who are the Qualified Persons, as the term is defined in NI 43-101. For more detailed information regarding the Company’s
22

image_1b.jpg
material mineral properties and technical information related thereto, including a complete list of current technical reports applicable to such properties, please refer to the Company’s Annual Information Form and other continuous disclosure documents filed by the Company on SEDAR+ at www.sedarplus.ca, and on the Company’s website at www.i80gold.com.

Mineral Resources referenced herein are not Mineral Reserves and do not have demonstrated economic viability. Mineral Resource estimates do not account for mineability, selectivity, mining loss, and dilution. The Mineral Resource estimates include Inferred Mineral Resources that are normally considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as Mineral Reserves. There is also no certainty that these Inferred Mineral Resources will be converted to Measured and Indicated categories through further drilling, or into Mineral Reserves, once economic considerations are applied.

CAUTIONARY STATEMENT ON FORWARD LOOKING STATEMENTS

Certain information set forth in this MD&A, including but not limited to management's assessment of the Company's future plans and operations, the perceived merit of projects or deposits, and the anticipated timing of permitting, the impact and anticipated timing of the Company’s development plan and recapitalization plan, the anticipated timing of permitting, production, project development or technical studies contains forward looking statements. All statements other than statements of historical fact are forward-looking statements. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "continues", "forecasts", "projects", "predicts", "intends", "anticipates" or "believes", or variations of, or the negatives of, such words and phrases, or state that certain actions, events or results "may", "could", "would", "should", "might" or "will" be taken, occur or be achieved. Readers are cautioned that the assumptions used in the preparation of information, although considered reasonable at the time of preparation, may prove to be inaccurate and, as such, reliance should not be placed on forward looking statements. The Company's actual results, performance or achievement could differ materially from those expressed in, or implied by, these forward-looking statements and, accordingly, no assurance can be given that any of the events anticipated by the forward-looking statements will transpire or occur, or if any of them do so, what benefits, if any, that the Company will derive there from. By their nature, forward looking statements are subject to numerous risks and uncertainties, some of which are beyond the Company’s control, including general economic and industry conditions, volatility of commodity prices, title risks and uncertainties, ability to access sufficient capital from internal and external sources, currency fluctuations, construction and operational risks, licensing and permit requirements, environmental risks, competition from other industry participants, the lack of availability of qualified personnel or management, imprecision of resource, reserve or production estimates and stock market volatility. Please see “Risks and Risk Management” in this MD&A for more information regarding risks regarding the Company. All forward-looking statements contained in this MD&A speak only as of the date of this MD&A or as of the dates specified in such statements. The Company disclaims any intention or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise except as required by applicable law.

Additional information relating to i-80 Gold can be found on i-80 Gold’s website at www.i80gold.com, SEDAR+ at www.sedarplus.ca, and on EDGAR at www.sec.gov/edgar.

23