XML 121 R35.htm IDEA: XBRL DOCUMENT v3.24.1.1.u2
RESTRUCTURING (Tables)
12 Months Ended
Dec. 31, 2023
Restructuring and Related Activities [Abstract]  
Schedule of Restructuring Charges by Plan
The following table summarizes the period-to-date restructuring charges by plan recognized in our Consolidated Statements of Operations:
Fiscal Year Ended
(In thousands)December 31, 2023January 1, 2023January 2, 2022
May 2021 Restructuring Plan:
Severance and benefits129 (475)4,313 
(Gain from) cost of disposal and retirement of property, plant and equipment
(1,880)60 252 
Total May 2021 Restructuring Plan(1,751)(415)4,565 
June 2022 Restructuring Plan:
Severance and benefits(348)1,981 — 
Cost of disposal and retirement of property, plant and equipment
457 599 — 
Total June 2022 Restructuring Plan109 2,580 — 
September 2023 Restructuring Plan:
Inventory impairments and other inventory related costs(1)
24,278 — — 
Severance and benefits12,745 — — 
Impairment and cost of disposal and retirement of long-lived assets, including right of use assets
74,480 — — 
Contract termination costs for capital expenditure
39,051 — — 
Other costs
817 — — 
Total September 2023 Restructuring Plan
151,371 — — 
Other Restructuring:
Severance and benefits— — 1,077 
Cost of disposal and retirement of property, plant and equipment
— (47)2,440 
Other costs
— — 
Total Other Restructurings— (47)3,519 
Total restructuring charges
$149,729 $2,118 $8,084 
(1) Included in Cost of revenue.
Schedule of Restructuring Reserve
The following table summarizes the restructuring reserve movements during fiscal year 2023:
(In thousands)January 1, 2023
(Credits) Charges
(Deduction) Settlement
December 31, 2023
May 2021 Restructuring Plan:
Severance and benefits
$42 $129 $(171)$— 
(Gain) Cost of disposal and retirement of property, plant and equipment
— (1,880)1,880 — 
Total May 2021 Restructuring Plan
42 (1,751)1,709 — 
June 2022 Restructuring Plan:
Severance and benefits521 (348)(111)62 
Cost of disposal and retirement of property, plant and equipment
— 457 (457)— 
Total June 2022 Restructuring Plan521 109 (568)62 
September 2023 Restructuring Plan:
Inventory impairments and other inventory related costs
$— $24,278 $(20,553)3,725 
Severance and benefits— 12,745 (9,694)3,051 
Impairment and cost of disposal and retirement of property, plant and equipment and Right of use Assets
$— $74,480 $(74,480)— 
Contract termination costs
— 39,051 (20,964)18,087 
Other costs
— 817 (313)504 
Total September 2023 Restructuring Plan
— 151,371 (126,004)25,367 
Total Restructuring Charges
$563 $149,729 $(124,863)$25,429