2022 North Carolina Rate Case | NCUC                      
Public Utilities, General Disclosures [Line Items]                      
Proposed rate period (in years) 3 years                    
2022 North Carolina Rate Case | NCUC | Forecast                      
Public Utilities, General Disclosures [Line Items]                      
Requested rate increase (decrease), amount     $ 587 $ 615 $ 140 $ 127     $ 138 $ 151  
Requested return on equity (as a percent)     15.00%         16.00%      
2022 North Carolina Rate Case | NCUC | Forecast | Subsequent event                      
Public Utilities, General Disclosures [Line Items]                      
Requested rate increase (decrease), amount             $ 320       $ 326
2022 South Carolina Rate Case | PSCSC                      
Public Utilities, General Disclosures [Line Items]                      
Approved rate increase (decrease), amount   $ 52                  
2022 South Carolina Rate Case, Retail Rate Case | PSCSC                      
Public Utilities, General Disclosures [Line Items]                      
Approved rate increase (decrease), amount   $ 36                  
Approved return on equity percentage (as a percent)   9.60%                  
2022 South Carolina Rate Case, Retail Rate Case | PSCSC | Equity                      
Public Utilities, General Disclosures [Line Items]                      
Approved return on equity percentage (as a percent)   52.43%                  
2022 South Carolina Rate Case, Retail Rate Case | PSCSC | Debt                      
Public Utilities, General Disclosures [Line Items]                      
Approved return on equity percentage (as a percent)   47.57%                  
2022 South Carolina Rate Case, Coal Ash Basin Closure Costs | PSCSC                      
Public Utilities, General Disclosures [Line Items]                      
Deferred compliance costs period (in years)   7 years                  