Commitments and Contingencies COMMITMENTS AND CONTINGENCIES
ENVIRONMENTAL
The Duke Energy Registrants are subject to federal, state and local regulations regarding air and water quality, hazardous and solid waste disposal, coal ash and other environmental matters. These regulations can be changed from time to time, imposing new obligations on the Duke Energy Registrants. The following environmental matters impact all Duke Energy Registrants.
Remediation Activities
In addition to AROs recorded as a result of various environmental regulations, the Duke Energy Registrants are responsible for environmental remediation at various sites. These include certain properties that are part of ongoing operations and sites formerly owned or used by Duke Energy entities. These sites are in various stages of investigation, remediation and monitoring. Managed in conjunction with relevant federal, state and local agencies, remediation activities vary based on site conditions and location, remediation requirements, complexity and sharing of responsibility. If remediation activities involve joint and several liability provisions, strict liability, or cost recovery or contribution actions, the Duke Energy Registrants could potentially be held responsible for environmental impacts caused by other potentially responsible parties and may also benefit from insurance policies or contractual indemnities that cover some or all cleanup costs. Liabilities are recorded when losses become probable and are reasonably estimable. The total costs that may be incurred cannot be estimated because the extent of environmental impact, allocation among potentially responsible parties, remediation alternatives and/or regulatory decisions have not yet been determined at all sites. Additional costs associated with remediation activities are likely to be incurred in the future and could be significant. Costs are typically expensed as Operation, maintenance and other on the Condensed Consolidated Statements of Operations unless regulatory recovery of the costs is deemed probable.
The following table contains information regarding reserves for probable and estimable costs related to the various environmental sites. These reserves are recorded in Other within Other Noncurrent Liabilities on the Condensed Consolidated Balance Sheets.
(in millions)June 30, 2023December 31, 2022
Reserves for Environmental Remediation
Duke Energy$92 $84 
Duke Energy Carolinas23 22 
Progress Energy23 19 
Duke Energy Progress11 
Duke Energy Florida11 11 
Duke Energy Ohio36 33 
Duke Energy Indiana2 
Piedmont8 
Additional losses in excess of recorded reserves that could be incurred for the stages of investigation, remediation and monitoring for environmental sites that have been evaluated at this time are not material.
LITIGATION
Duke Energy
Texas Storm Uri Tort Litigation
Duke Energy (Parent), several Duke Energy renewables project companies, and others in the ERCOT market were named in multiple lawsuits arising out of Texas Storm Uri, which occurred in February 2021. These lawsuits seek recovery for property damages, personal injury and wrongful death allegedly caused by the power outages that plaintiffs claim were the collective failure of generators, transmission and distribution operators (TDUs), retail energy providers, and all others, including ERCOT. The cases were consolidated into a Texas state court multidistrict litigation (MDL) proceeding for discovery and pre-trial motions. Five MDL cases were designated as lead cases in which motions to dismiss were filed and all other cases were stayed. On January 28, 2023, the Court denied certain motions including those by the generator defendants and TDUs and granted others. The generators and TDUs filed petitions for Writ of Mandamus to the Texas Court of Appeals seeking to overturn the denials. The TDUs' petition, filed first, was accepted and is set for oral argument in August 2023. The generators’ petition has not yet been set for argument. After the rulings on the motions to dismiss, plaintiffs filed new lawsuits against Duke Energy (Parent), Duke Energy Renewables, LLC, and several Duke Energy renewable entities, which are included in the MDL proceeding and are currently stayed. The plaintiffs have represented to the court that they will dismiss Duke Energy (Parent) from all cases. Duke Energy cannot predict the outcome of this matter. See Note 2 for more information related to the sale of the Commercial Renewables Disposal Groups.
Duke Energy Carolinas
Ruben Villano, et al. v. Duke Energy Carolinas, LLC
On June 16, 2021, a group of nine individuals went over a low-head dam adjacent to the Dan River Steam Station in Eden, North Carolina, while water tubing. Emergency personnel rescued four people and five others were confirmed deceased. On August 11, 2021, Duke Energy Carolinas was served with the complaint filed in Durham County Superior Court on behalf of four survivors, which was later amended to include all the decedents along with the survivors. The lawsuit alleges that Duke Energy Carolinas knew that the river was used for recreational purposes, did not adequately warn about the dam, and created a dangerous and hidden hazard on the Dan River by building and maintaining the low-head dam. Duke Energy Carolinas has reached an agreement that will resolve this matter to the parties' mutual satisfaction. The resolution, which did not have a material financial impact, has been approved by the Durham County Superior Court. The case was dismissed on June 6, 2023.
NTE Carolinas II, LLC Litigation
In November 2017, Duke Energy Carolinas entered into a standard FERC large generator interconnection agreement (LGIA) with NTE Carolinas II, LLC (NTE), a company that proposed to build a combined-cycle natural gas plant in Rockingham County, North Carolina. On September 6, 2019, Duke Energy Carolinas filed a lawsuit in Mecklenburg County Superior Court against NTE for breach of contract, alleging that NTE's failure to pay benchmark payments for Duke Energy Carolinas' transmission system upgrades required under the interconnection agreement constituted a termination of the interconnection agreement. Duke Energy Carolinas sought a monetary judgment against NTE because NTE failed to make multiple milestone payments. The lawsuit was moved to federal court in North Carolina. NTE filed a motion to dismiss Duke Energy Carolinas’ complaint and brought counterclaims alleging anti-competitive conduct and violations of state and federal statutes. Duke Energy Carolinas filed a motion to dismiss NTE's counterclaims. Both NTE's and Duke Energy Carolinas' motions to dismiss were subsequently denied by the court.
On May 21, 2020, in response to a NTE petition challenging Duke Energy Carolinas' termination of the LGIA, FERC issued a ruling that 1) it has exclusive jurisdiction to determine whether a transmission provider may terminate a LGIA; 2) FERC approval is required to terminate a conforming LGIA if objected to by the interconnection customer; and 3) Duke Energy may not announce the termination of a conforming LGIA unless FERC has approved the termination. FERC's Office of Enforcement also initiated an investigation of Duke Energy Carolinas into matters pertaining to the LGIA. On April 6, 2023, Duke Energy Carolinas received notice from the FERC Office of Enforcement that they have closed their non-public investigation with no further action recommended.
Following completion of discovery, Duke Energy Carolinas filed a motion for summary judgment seeking a ruling in its favor as to some of its affirmative claims against NTE and to all of NTE’s counterclaims. On June 24, 2022, the court issued an order partially granting Duke Energy Carolinas' motion by dismissing NTE's counterclaims that Duke Energy Carolinas engaged in anti-competitive behavior in violation of state and federal statutes. On October 12, 2022, the parties executed a settlement agreement with respect to the remaining breach of contract claims in the litigation and a Stipulation of Dismissal was filed with the court on October 13, 2022. On November 11, 2022, NTE filed its Notice of Appeal to the U.S. Court of Appeals for the Fourth Circuit as to the District Court's summary judgment ruling in Duke Energy Carolinas' favor on NTE's antitrust and unfair competition claims. Briefing on NTE's appeal was completed on June 30, 2023. Duke Energy Carolinas cannot predict the outcome of this matter.
Asbestos-related Injuries and Damages Claims
Duke Energy Carolinas has experienced numerous claims for indemnification and medical cost reimbursement related to asbestos exposure. These claims relate to damages for bodily injuries alleged to have arisen from exposure to or use of asbestos in connection with construction and maintenance activities conducted on its electric generation plants prior to 1985.
Duke Energy Carolinas has recognized asbestos-related reserves of $446 million at June 30, 2023, and $457 million at December 31, 2022. These reserves are classified in Other within Other Noncurrent Liabilities and Other within Current Liabilities on the Condensed Consolidated Balance Sheets. These reserves are based on Duke Energy Carolinas' best estimate for current and future asbestos claims through 2042 and are recorded on an undiscounted basis. In light of the uncertainties inherent in a longer-term forecast, management does not believe they can reasonably estimate the indemnity and medical costs that might be incurred after 2042 related to such potential claims. It is possible Duke Energy Carolinas may incur asbestos liabilities in excess of the recorded reserves.
Duke Energy Carolinas has third-party insurance to cover certain losses related to asbestos-related injuries and damages above an aggregate self-insured retention. Receivables for insurance recoveries were $595 million at June 30, 2023, and at December 31, 2022. These amounts are classified in Other within Other Noncurrent Assets and Receivables within Current Assets on the Condensed Consolidated Balance Sheets. Any future payments up to the policy limit will be reimbursed by the third-party insurance carrier. Duke Energy Carolinas is not aware of any uncertainties regarding the legal sufficiency of insurance claims. Duke Energy Carolinas believes the insurance recovery asset is probable of recovery as the insurance carrier continues to have a strong financial strength rating.
The reserve for credit losses for insurance receivables is $12 million for Duke Energy and Duke Energy Carolinas as of June 30, 2023, and December 31, 2022. The insurance receivable is evaluated based on the risk of default and the historical losses, current conditions and expected conditions around collectability. Management evaluates the risk of default annually based on payment history, credit rating and changes in the risk of default from credit agencies.
Duke Energy Indiana
Coal Ash Insurance Coverage Litigation
In June 2022, Duke Energy Indiana filed a civil action in Indiana Superior Court against various insurance companies seeking declaratory relief with respect to insurance coverage for coal combustion residuals-related expenses and liabilities covered by third-party liability insurance policies. The insurance policies cover the 1969-1972 and 1984-1985 periods and provide third-party liability insurance for claims and suits alleging property damage, bodily injury and personal injury (or a combination thereof). A trial date has not yet been set. On June 30, 2023, Duke Energy Indiana and Associated Electric and Gas Insurance Services (AEGIS) reached a confidential settlement, the results of which were not material, and as a result, AEGIS was dismissed from the litigation on July 13, 2023. The lawsuit remains pending as to the other insurers, but is stayed until October 21, 2023, to allow for further settlement negotiations. Duke Energy Indiana cannot predict the outcome of this matter.
Other Litigation and Legal Proceedings
The Duke Energy Registrants are involved in other legal, tax and regulatory proceedings arising in the ordinary course of business, some of which involve significant amounts. The Duke Energy Registrants believe the final disposition of these proceedings will not have a material effect on their results of operations, cash flows or financial position. Reserves are classified on the Condensed Consolidated Balance Sheets in Other within Other Noncurrent Liabilities and Other within Current Liabilities.
OTHER COMMITMENTS AND CONTINGENCIES
General
As part of their normal business, the Duke Energy Registrants are party to various financial guarantees, performance guarantees and other contractual commitments to extend guarantees of credit and other assistance to various subsidiaries, investees and other third parties. These guarantees involve elements of performance and credit risk, which are not fully recognized on the Condensed Consolidated Balance Sheets and have uncapped maximum potential payments. However, the Duke Energy Registrants do not believe these guarantees will have a material effect on their results of operations, cash flows or financial position.
In addition, the Duke Energy Registrants enter into various fixed-price, noncancelable commitments to purchase or sell power or natural gas, take-or-pay arrangements, transportation, or throughput agreements and other contracts that may or may not be recognized on their respective Condensed Consolidated Balance Sheets. Some of these arrangements may be recognized at fair value on their respective Condensed Consolidated Balance Sheets if such contracts meet the definition of a derivative and the NPNS exception does not apply. In most cases, the Duke Energy Registrants’ purchase obligation contracts contain provisions for price adjustments, minimum purchase levels and other financial commitments.