Regulatory Matters (Regulatory Matters Narrative - Duke Energy Carolinas) (Details) - USD ($)
$ in Millions
Oct. 26, 2020
Jul. 31, 2020
Oct. 30, 2019
Sep. 30, 2019
May 21, 2019
Nov. 08, 2018
Feb. 28, 2018
Nov. 22, 2017
Aug. 25, 2017
Jun. 01, 2017
Duke Energy Carolinas | NCUC | 2017 North Carolina Rate Case                    
Public Utilities, General Disclosures [Line Items]                    
Requested rate increase (decrease), amount                 $ 647  
Requested return on equity, percent             9.90%      
Public utilities, requested equity capital structure, percentage             52.00%      
Public utilities, requested debt capital structure, percentage             48.00%      
Duke Energy Carolinas | NCUC | 2019 North Carolina Rate Case                    
Public Utilities, General Disclosures [Line Items]                    
Requested rate increase (decrease), amount       $ 291            
Requested rate increase, percentage       6.00%            
Requested rate increase (decrease), gross amount       $ 445            
Requested rate increase (decrease), rider reduction       $ 154            
Duke Energy Carolinas | NCUC | 2019 North Carolina Rate Case, additional Agreement and Stipulation of Partial Settlement                    
Public Utilities, General Disclosures [Line Items]                    
Requested rate increase (decrease), amended amount   $ 800                
Requested return on equity, percent   9.60%                
Public utilities, requested equity capital structure, percentage   52.00%                
Public utilities, requested debt capital structure, percentage   48.00%                
Regulatory asset, amortization period           5 years        
Duke Energy Carolinas | NCUC | Annual revenue requirement                    
Public Utilities, General Disclosures [Line Items]                    
Requested rate increase (decrease), amended amount   $ 45                
Duke Energy Carolinas | NCUC | Annual revenue requirement | Subsequent event                    
Public Utilities, General Disclosures [Line Items]                    
Requested rate increase (decrease), amended amount $ 262                  
Duke Energy Carolinas | PSCSC | South Carolina Rate Case 2018                    
Public Utilities, General Disclosures [Line Items]                    
Requested rate increase (decrease), amount           $ 168        
Approved return on equity percentage         9.50%          
Public utilities, approved equity capital structure, percentage         53.00%          
Public utilities, approved debt capital structure, percentage         47.00%          
Change in tax rate, deferred tax liability, income tax benefit         $ 66          
Measurement period adjustment, income tax expense (benefit)         $ 45          
Duke Energy Carolinas | PSCSC | South Carolina Rate Case 2018 | State and local jurisdiction | North Carolina Department of Revenue                    
Public Utilities, General Disclosures [Line Items]                    
Regulatory asset, amortization period         5 years          
State and local taxes reduction amount         $ 17          
Duke Energy Carolinas | Asset retirement obligations - coal ash | PSCSC | South Carolina Rate Case 2018                    
Public Utilities, General Disclosures [Line Items]                    
Regulatory assets         $ 96          
Regulatory asset, amortization period         5 years          
Recovery costs denied         $ 115          
Duke Energy Carolinas | Asset retirement obligations - unprotected EDIT, Property, Plant and Equipment | PSCSC | South Carolina Rate Case 2018                    
Public Utilities, General Disclosures [Line Items]                    
Regulatory asset, amortization period         20 years          
Duke Energy Carolinas | Asset retirement obligations - unprotected EDIT | PSCSC | South Carolina Rate Case 2018                    
Public Utilities, General Disclosures [Line Items]                    
Regulatory asset, amortization period         5 years          
Duke Energy Carolinas | Asset retirement obligations - deferred revenue | PSCSC | South Carolina Rate Case 2018                    
Public Utilities, General Disclosures [Line Items]                    
Regulatory asset, amortization period         5 years          
Duke Energy Carolinas | Deferred project costs | PSCSC | South Carolina Rate Case 2018                    
Public Utilities, General Disclosures [Line Items]                    
Regulatory assets         $ 125          
Regulatory asset, amortization period         12 years          
Duke Energy Progress [Member] | NCUC | 2017 North Carolina Rate Case                    
Public Utilities, General Disclosures [Line Items]                    
Requested rate increase (decrease), amended amount                   $ 420
Requested rate increase (decrease), amount                   $ 477
Requested return on equity, percent               9.90%    
Public utilities, requested equity capital structure, percentage               52.00%    
Public utilities, requested debt capital structure, percentage               48.00%    
Duke Energy Progress [Member] | NCUC | 2019 North Carolina Rate Case                    
Public Utilities, General Disclosures [Line Items]                    
Requested rate increase (decrease), amount     $ 464              
Requested rate increase, percentage     12.30%              
Requested rate increase (decrease), gross amount     $ 586              
Requested rate increase (decrease), rider reduction     $ 120              
Duke Energy Progress [Member] | NCUC | 2019 North Carolina Rate Case, additional Agreement and Stipulation of Partial Settlement                    
Public Utilities, General Disclosures [Line Items]                    
Requested rate increase (decrease), amended amount   $ 500                
Requested return on equity, percent   9.60%                
Public utilities, requested equity capital structure, percentage   52.00%                
Public utilities, requested debt capital structure, percentage   48.00%                
Regulatory asset, amortization period   5 years                
Duke Energy Progress [Member] | NCUC | Annual revenue requirement                    
Public Utilities, General Disclosures [Line Items]                    
Requested rate increase (decrease), amended amount   $ 25                
Duke Energy Progress [Member] | NCUC | Annual revenue requirement | Subsequent event                    
Public Utilities, General Disclosures [Line Items]                    
Requested rate increase (decrease), amended amount $ 842                  
Duke Energy Progress [Member] | PSCSC | South Carolina Rate Case 2018                    
Public Utilities, General Disclosures [Line Items]                    
Requested rate increase (decrease), amount           $ 59        
Approved return on equity percentage         9.50%          
Public utilities, approved equity capital structure, percentage         53.00%          
Public utilities, approved debt capital structure, percentage         47.00%          
Change in tax rate, deferred tax liability, income tax benefit         $ (17)          
Measurement period adjustment, income tax expense (benefit)         12          
Duke Energy Progress [Member] | PSCSC | South Carolina Rate Case 2018 | State and local jurisdiction | North Carolina Department of Revenue                    
Public Utilities, General Disclosures [Line Items]                    
State and local taxes reduction amount         (12)          
Duke Energy Progress [Member] | Asset retirement obligations - coal ash | PSCSC | South Carolina Rate Case 2018                    
Public Utilities, General Disclosures [Line Items]                    
Regulatory assets         $ 4          
Regulatory asset, amortization period         5 years          
Recovery costs denied         $ 65          
Duke Energy Progress [Member] | Asset retirement obligations - unprotected EDIT, Property, Plant and Equipment | PSCSC | South Carolina Rate Case 2018                    
Public Utilities, General Disclosures [Line Items]                    
Regulatory asset, amortization period         20 years          
Duke Energy Progress [Member] | Asset retirement obligations - unprotected EDIT | PSCSC | South Carolina Rate Case 2018                    
Public Utilities, General Disclosures [Line Items]                    
Regulatory asset, amortization period         5 years          
Duke Energy Progress [Member] | Asset retirement obligations - deferred revenue | PSCSC | South Carolina Rate Case 2018                    
Public Utilities, General Disclosures [Line Items]                    
Regulatory asset, amortization period         3 years          
15-year storm recovery bond | Duke Energy Carolinas | Subsequent event                    
Public Utilities, General Disclosures [Line Items]                    
Bond term 15 years