5. COMMITMENTS AND CONTINGENCIES

General Insurance

The Duke Energy Registrants have insurance and reinsurance coverage either directly or through indemnification from Duke Energy's captive insurance company, Bison, and its affiliates, consistent with companies engaged in similar commercial operations with similar type properties. The Duke Energy Registrants' coverage includes (i) commercial general liability coverage for liabilities arising to third parties for bodily injury and property damage; (ii) workers' compensation; (iii) automobile liability coverage; and (iv) property coverage for all real and personal property damage. Real and personal property damage coverage excludes electric transmission and distribution lines, but includes damages arising from boiler and machinery breakdowns, earthquakes, flood damage and extra expense, but not outage or replacement power coverage. All coverage is subject to certain deductibles or retentions, sublimits, exclusions, terms and conditions common for companies with similar types of operations.

The Duke Energy Registrants self-insure their electric transmission and distribution lines against loss due to storm damage and other natural disasters. As discussed further in Note 4, Duke Energy Florida maintains a storm damage reserve and has a regulatory mechanism to recover the cost of named storms on an expedited basis.

The cost of the Duke Energy Registrants' coverage can fluctuate year to year reflecting claims history and conditions of the insurance and reinsurance markets.

In the event of a loss, terms and amounts of insurance and reinsurance available might not be adequate to cover claims and other expenses incurred. Uninsured losses and other expenses, to the extent not recovered by other sources, could have a material effect on the Duke Energy Registrants' results of operations, cash flows or financial position. Each company is responsible to the extent losses may exceed limits of the coverage available.

Nuclear Insurance

Duke Energy Carolinas owns and operates the McGuire Nuclear Station (McGuire) and the Oconee Nuclear Station (Oconee) and operates and has a partial ownership interest in the Catawba Nuclear Station (Catawba). McGuire and Catawba each have two reactors. Oconee has three reactors. The other joint owners of Catawba reimburse Duke Energy Carolinas for certain expenses associated with nuclear insurance per the Catawba joint owner agreements.

Duke Energy Progress owns and operates the Robinson Nuclear Station (Robinson) and operates and has a partial ownership interest in the Brunswick Nuclear Station (Brunswick) and Harris. Robinson and Harris each have one reactor. Brunswick has two reactors. The other joint owners of Brunswick and Harris reimburse Duke Energy Progress for certain expenses associated with nuclear insurance per the Brunswick and Harris joint owner agreements.

Duke Energy Florida manages and has a partial ownership interest in Crystal River Unit 3, which has been retired. The other joint owners of Crystal River Unit 3 reimburse Duke Energy Florida for certain expenses associated with nuclear insurance per the Crystal River Unit 3 joint owner agreement.

In the event of a loss, terms and amounts of insurance available might not be adequate to cover property damage and other expenses incurred. Uninsured losses and other expenses, to the extent not recovered by other sources, could have a material effect on Duke Energy Carolinas', Duke Energy Progress' and Duke Energy Florida's results of operations, cash flows or financial position. Each company is responsible to the extent losses may exceed limits of the coverage available.

Nuclear Liability Coverage

The Price-Anderson Act requires owners of nuclear reactors to provide for public nuclear liability protection per nuclear incident up to a maximum total financial protection liability. The maximum total financial protection liability increased to a total of $13.6 billion. This amount is adjusted every five years for an inflationary provision. Total nuclear liability coverage consists of a combination of private primary nuclear liability insurance coverage and a mandatory industry risk-sharing program to provide for excess nuclear liability coverage above the maximum reasonably available private primary coverage. The United States Congress could impose revenue-raising measures on the nuclear industry to pay claims.

Primary Liability Insurance

Duke Energy Carolinas, Duke Energy Progress and Duke Energy Florida have purchased the maximum reasonably available private primary nuclear liability insurance as required by law, which currently is $375 million per station.

Excess Liability Program

This program provides $13.2 billion of coverage per incident through the Price-Anderson Act's mandatory industry-wide excess secondary financial protection program of risk pooling. This amount is the product of potential cumulative retrospective premium assessments of $127 million times the current 104 licensed commercial nuclear reactors in U.S. Under this program, licensees could be assessed retrospective premiums to compensate for public nuclear liability damages in the event of a nuclear incident at any licensed facility in the U.S. Retrospective premiums may be assessed at a rate not to exceed $19 million per year per licensed reactor for each incident. The assessment may be subject to state premium taxes.

Nuclear Property Coverage

Duke Energy Carolinas, Duke Energy Progress and Duke Energy Florida are members of NEIL, which provides insurance coverage for nuclear facilities under three policy programs: the primary property insurance program, the excess property insurance program and the accidental outage insurance program.

Pursuant to regulations of the NRC, each company's property damage insurance policies provide that all proceeds from such insurance be applied, first, to place the plant in a safe and stable condition after a qualifying accident, and second, to decontaminate the plant before any proceeds can be used for decommissioning, plant repair or restoration.

Losses resulting from non-certified acts of terrorism are covered as common occurrences, such that if non-certified terrorist acts occur against one or more commercial nuclear power plants insured by NEIL within a 12-month period, they would be treated as one event and the owners of the plants where the act occurred would share one full limit of liability. The full limit of liability is currently $3.2 billion. NEIL sublimits the total aggregate for all of their policies for non-nuclear terrorist events to approximately $1.83 billion.

Primary Property Insurance

This policy provides $500 million of primary property damage coverage. The deductible per occurrence is $3 million for Catawba, and $10 million for the remaining nuclear facilities. This policy also has a 10 percent deductible provision excess of these deductibles for natural catastrophe damage.

Excess Property Insurance

This policy provides excess property, decontamination and decommissioning liability insurance of $2.25 billion for Catawba, $750 million each for Oconee, McGuire, Brunswick, Harris and Robinson; and $560 million for Crystal River Unit 3. All nuclear facilities except for Catawba and Crystal River Unit 3 also share an additional $1 billion insurance limit above their dedicated underlying excess. This shared additional excess limit is not subject to reinstatement in the event of a loss.

Crystal River Unit 3's primary and excess property insurance is on an actual cash value basis. NEIL coverage does not include property damage to or resulting from the containment structure except coverage does apply to decontamination and debris removal, if required following an accident, to ensure public health and safety or if property damage results from a terrorism event.

NEIL sublimits property damage losses to $1.5 billion for non-nuclear accidental property damage.

Accidental Outage Insurance

This policy provides replacement power expense coverage resulting from an accidental property damage outage of a nuclear unit. Coverage amounts decrease in the event more than one unit at a station is out of service due to a common accident. Initial coverage begins after a 12-week deductible period. Coverage continues at 100 percent of the weekly limits for 52 weeks and 80 percent of the weekly limits for the next 110 weeks.

The Catawba units are insured for up to $4 million per week. The McGuire units are insured for up to $4 million per week. The Oconee units are insured for up to $3 million per week. The Brunswick units are insured for up to $3 million per week. The Harris unit is insured for up to $3 million per week. The Robinson unit is insured for up to $2 million per week. The accidental outage policy limit is $490 million for McGuire and Catawba, $378 million for Oconee, $406 million for Brunswick, $364 million for Harris, and $308 million for Robinson.

NEIL sublimits the accidental outage recovery to the first 104 weeks of coverage not to exceed $328 million from non-nuclear accidental property damage.

Potential Retroactive Premium Assessments

In the event of NEIL losses, NEIL's board of directors may assess member companies retroactive premiums of amounts up to 10 times their annual premiums for up to six years after a loss. The current potential maximum assessments for Duke Energy Carolinas are $42 million for primary property insurance, $36 million for excess property insurance and $29 million for accidental outage insurance. The current potential maximum assessments for Duke Energy Progress are $33 million for primary property insurance, $32 million for excess property insurance and $14 million for accidental outage insurance. The current potential maximum assessments for Duke Energy Florida are $6 million for primary property insurance and $4 million for excess property insurance.

The maximum assessment amounts include 100 percent of Duke Energy Carolinas', Duke Energy Progress', and Duke Energy Florida's potential obligations to NEIL for their share of jointly owned reactors. However, the other joint owners of the jointly owned reactors are obligated to assume their pro rata share of liability for retrospective premiums and other premium assessments resulting from the Price-Anderson Act's excess secondary financial protection program of risk pooling, or from the NEIL policies.

ENVIRONMENTAL

Duke Energy is subject to international, federal, state, and local regulations regarding air and water quality, hazardous and solid waste disposal, and other environmental matters. The Subsidiary Registrants are subject to federal, state, and local regulations regarding air and water quality, hazardous and solid waste disposal and other environmental matters. These regulations can be changed from time to time, imposing new obligations on the Duke Energy Registrants.

The following environmental matters impact all of the Duke Energy Registrants.

Remediation Activities

The Duke Energy Registrants are responsible for environmental remediation at various contaminated sites. These include some properties that are part of ongoing operations and sites formerly owned or used by Duke Energy entities. These sites are in various stages of investigation, remediation, and monitoring. Managed in conjunction with relevant federal, state, and local agencies, activities vary with site conditions and locations, remediation requirements, complexity, and sharing of responsibility. If remediation activities involve joint and several liability provisions, strict liability, or cost recovery or contribution actions, the Duke Energy Registrants could potentially be held responsible for contamination caused by other potentially responsible parties, and may also benefit from insurance policies or contractual indemnities that cover some or all cleanup costs. Liabilities are recorded when losses become probable and are reasonably estimable. The total costs that may be incurred cannot be estimated because the extent of environmental impact, allocation among potentially responsible parties, remediation alternatives, and/or regulatory decisions has not yet been determined. Additional costs associated with remediation activities are likely to be incurred in the future and could be significant. Costs are typically expensed as Operation, maintenance and other in the Consolidated Statements of Operations unless regulatory recovery of the costs is deemed probable.

The following table contains information regarding reserves for probable and estimable costs related to the various environmental sites. These reserves are recorded in Other within Deferred Credits and Other Liabilities on the Consolidated Balance Sheets.

                      
(in millions)Duke Energy Duke Energy Carolinas Progress Energy Duke Energy Progress Duke Energy Florida Duke Energy Ohio Duke Energy Indiana
Balance at December 31, 2010$ 88 $ 13 $ 35 $ 12 $ 23 $ 50 $ 11
Provisions / adjustments  6     10   1   9   5   1
Cash reductions  (33)   (1)   (22)   (2)   (20)   (27)   (3)
Balance at December 31, 2011  61   12   23   11   12   28   9
Provisions / adjustments  39   1   19   5   14   5   3
Cash reductions  (25)   (1)   (9)   (2)   (7)   (18)   (4)
Balance at December 31, 2012  75   12   33   14   19   15   8
Provisions / adjustments  26     4   (1)   5   20   1
Cash reductions  (22)   (1)   (10)   (5)   (5)   (8)   (2)
Balance at December 31, 2013$ 79 $ 11 $ 27 $ 8 $ 19 $ 27 $ 7
                      

Additional losses in excess of recorded reserves that could be incurred for the stages of investigation, remediation and monitoring for environmental sites that have been evaluated at this time are presented in the table below.
    
(in millions) 
Duke Energy$ 74
Duke Energy Carolinas  29
Progress Energy  5
Duke Energy Progress  2
Duke Energy Florida  3
Duke Energy Ohio  35
Duke Energy Indiana  5
    

Regulations

Clean Water Act 316(b)

The EPA proposed a cooling water intake structures rule on April 20, 2011. The proposed rule advances one main approach and three alternatives. Based on the main approach proposed, most, if not all of the steam electric generating facilities the Duke Energy Registrants own are likely affected sources unless retired prior to implementation of the 316(b) requirements.

The revised deadline for issuance of the final 316(b) rule is April 17, 2014. If the rule is finalized as proposed, modifications to affected power plant cooling water intake structures could be required by mid-to-late 2017. The Duke Energy Registrants are unable to predict the outcome of this rulemaking, but the impact could be significant.

Cross-State Air Pollution Rule (CSAPR)

On August 8, 2011, the final Cross-State Air Pollution Rule (CSAPR) was published in the Federal Register. The CSAPR established state-level annual SO2 budgets and annual seasonal NOx budgets that were to take effect on January 1, 2012.

On August 21, 2012, the D.C. Circuit Court vacated the CSAPR. The court also directed the EPA to continue administering the Clean Air Interstate Rule (CAIR). The CAIR requires additional reductions in SO2 and NOx emissions beginning in 2015. On June 24, 2013, the U.S. Supreme Court (Supreme Court) granted the EPA's petitions for a writ of certiorari. The Supreme Court is likely to issue its decision on the merits by mid-2014.

The Duke Energy Registrants cannot predict the outcome of the proceedings. Continued compliance with CAIR pending the outcome of the rehearing process will not result in the Duke Energy Registrants adding new emission controls.

Coal Combustion Residuals (CCR)

On June 21, 2010, the EPA proposed a regulation under the Resource Conservation and Recovery Act, related to CCR or coal combustion byproducts associated with the generation of electricity. The EPA proposal contains two regulatory options whereby CCRs not employed in approved beneficial use applications would either (i) be regulated as hazardous waste or (ii) continue to be regulated as non-hazardous waste.

On October 29, 2013, the U.S. District Court for the District of Columbia directed the EPA to provide the Court, within 60 days of the Order, a proposed schedule for completing the CCR rulemaking. On January 29, 2014, the EPA filed a consent decree agreeing to issue the final rule by December 19, 2014. The Duke Energy Registrants cannot predict the outcome of this rulemaking, but the impact could be significant.

Steam Electric Effluent Limitation Guidelines

On June 7, 2013, the EPA proposed Steam Electric Effluent Limitations Guidelines (ELGs). The EPA is under a court order to finalize the rule by May 22, 2014. The EPA has proposed eight options for the rule, which vary in stringency and cost. The proposed regulation applies to seven waste streams, including wastewater from air pollution control equipment and ash transport water. Most, if not all of the steam electric generating facilities the Duke Energy Registrants own are likely affected sources. Compliance is proposed as soon as possible after July 1, 2017, but may extend until July 1, 2022. The Duke Energy Registrants are unable to predict the outcome of the rulemaking, but the impact could be significant.

Greenhouse Gas New Source Performance Standards (NSPS)

On January 8, 2014, the EPA proposed a rule to establish carbon dioxide (CO2) emissions standards for new pulverized coal, IGCC, natural gas combined cycle, and simple cycle electric generating units commencing construction on or after the date the proposal appears in the Federal Register. Future coal and IGCC units will be required to employ carbon capture and storage technology to meet the proposed standard.

The Duke Energy Registrants do not expect a material impact on their future results of operations or cash flows based on the EPA's proposal. The final rule, however, could be significantly different from the proposal. It is not known when the EPA might finalize the rule.

On June 25, 2013, the President of the United States issued a memorandum directing the EPA to propose CO2 emissions requirements for existing fossil-fueled electric generating units by June 1, 2014, and to finalize the guidelines for states to develop their own regulations for implementing the guidelines by June 1, 2015. The memorandum directed the EPA to require states to submit their implementation regulations for approval by June 30, 2016.

The Duke Energy Registrants are unable to predict the outcome of this rulemaking, but the impact could be significant.

Mercury and Air Toxics Standards (MATS)

The final MATS rule, previously referred to as the Utility MACT Rule, was issued on February 16, 2012. The final rule establishes emission limits for hazardous air pollutants from new and existing coal-fired and oil-fired steam electric generating units. The rule requires sources to comply with emission limits by April 16, 2015. Under the Clean Air Act (CAA), permitting authorities have the discretion to grant up to a one-year compliance extension, on a case-by-case basis, to sources that are unable to complete the installation of emission controls before the compliance deadline. Strategies to achieve compliance with the final rule will include installing new air emission control equipment, developing monitoring processes, fuel switching, and accelerating retirement of some coal-fired electric-generating units. For additional information, refer to Note 4 regarding potential plant retirements.

Several petitions for review of the final rule were filed with the D.C. Circuit Court. A decision is expected in the first half of 2014. The Duke Energy Registrants cannot predict the outcome of the litigation or how it might affect their compliance with the MATS requirements.

Refer to the table below for a summary of estimated costs to comply with the MATS regulations.

Estimated Cost and Impacts of EPA Rulemakings

The ultimate compliance requirements for MATS, Clean Water 316(b), CCRs and ELGs will not be known until all the rules have been finalized. For planning purposes, the Duke Energy Registrants currently estimate the cost of new control equipment that may need to be installed on existing power plants to comply with these EPA regulations could total $4.5 billion to $5.5 billion, excluding AFUDC, over the next 10 years. The table below includes estimated costs for new control equipment necessary to comply with the MATS rule, which is the only rule that has been finalized.

        
(in millions)    
Duke Energy$ 525 to$ 625
Duke Energy Carolinas  40 to  50
Progress Energy  25 to  40
Duke Energy Progress  10 to  15
Duke Energy Florida  15 to  25
Duke Energy Ohio  35 to  50
Duke Energy Indiana  425 to  485
        

The Duke Energy Registrants also expect to incur increased fuel, purchased power, operation and maintenance, and other expenses, and costs for replacement generation for potential coal-fired power plant retirements as a result of these EPA regulations. The actual compliance costs incurred may be materially different from these estimates based on the timing and requirements of the final EPA regulations. The Duke Energy Registrants intend to seek rate recovery of amounts incurred associated with regulated operations in complying with these regulations. Refer to Note 4 for further information regarding potential plant retirements and regulatory filings related to the Duke Energy Registrants.

Litigation

Duke Energy

Dan River Ash Basin Release

On February 2, 2014, a break in a stormwater pipe beneath an ash basin at Duke Energy Carolinas' retired Dan River steam station caused a release of ash basin water and ash into the Dan River. On February 8, 2014, a permanent plug was installed in the stormwater pipe stopping the release of materials into the river. Duke Energy Carolinas estimates 30,000 to 39,000 tons of ash and 24 million to 27 million gallons of basin water were released into the river. Duke Energy Carolinas continues to work with local and state officials responding to this event. On February 10, 2014, Duke Energy received a subpoena for the production of documents, issued by the United States Attorney for the Eastern District of North Carolina in connection with a criminal investigation related to the release. A second subpoena was issued by the same United States Attorney on February 18, 2014, which expanded the document production to cover all fourteen of the North Carolina facilities with coal ash ponds.

It is not possible to predict whether Duke Energy will incur any liability or to estimate the damages, if any, it might incur in connection with these matters.

Progress Energy Merger Shareholder Litigation

On May 31, 2013, the Delaware Chancery Court consolidated four shareholder derivative lawsuits filed in 2012. The Court also appointed a lead plaintiff and counsel for plaintiffs and designated the case as In Re Duke Energy Corporation Derivative Litigation. The lawsuit names as defendants eleven members of the Duke Energy board of directors who were also members of the pre-merger Duke Energy board of directors (Legacy Duke Energy Directors). Duke Energy is named as a nominal defendant. The case alleges claims for breach of fiduciary duties of loyalty and care in connection with the post-merger change in CEO. The case is stayed pending resolution of the Nieman v. Duke Energy Corporation, et al. case in North Carolina.

On August 3, 2012, Duke Energy was served with a shareholder Derivative Complaint, which was transferred to the North Carolina Business Court (Krieger v. Johnson, et al.). The lawsuit names as defendants, William D. Johnson and the Legacy Duke Energy Directors. Duke Energy is named as a nominal defendant. The lawsuit alleges claims for breach of fiduciary duty in granting excessive compensation to Mr. Johnson. A decision on a motion to dismiss made by the Legacy Duke Energy Directors remains pending.

Two shareholder Derivative Complaints, filed in 2012 in federal district court in Delaware, were consolidated as Tansey v. Rogers, et al. The case alleges claims for breach of fiduciary duty and waste of corporate assets, as well as claims under Section 14(a) and 20(a) of the Exchange Act. Duke Energy is named as a nominal defendant. On May 17, 2013, the judge granted defendants' motion to stay the litigation until a decision is rendered on the motion to dismiss in the Nieman v. Duke Energy Corporation, et al. case in North Carolina.

Duke Energy, the Legacy Duke Energy Directors and certain Duke Energy officers are also defendants in a purported securities class action lawsuit (Nieman v. Duke Energy Corporation, et al)This lawsuit consolidates three lawsuits originally filed in July 2012, and is pending in the United States District Court for the Western District of North Carolina. The plaintiffs allege federal Securities Act and Exchange Act claims based on allegations of materially false and misleading representations and omissions in the Registration Statement filed on July 7, 2011, and purportedly incorporated into other documents, all in connection with the post-merger change in CEO. The claims are purportedly brought on behalf of a class of all persons who purchased or otherwise acquired Duke Energy securities between June 11, 2012 and July 9, 2012. On July 26, 2013, the Magistrate Judge recommended the District Court Judge deny the defendants' motion to dismiss. On October 2, 2013, the District Judge heard defendants' objections to this recommendation. A decision is pending on the motion to dismiss.

It is not possible to predict whether Duke Energy will incur any liability or to estimate the damages, if any, it might incur in connection with these lawsuits.

Alaskan Global Warming Lawsuit

On February 26, 2008, the governing bodies of an Inupiat village in Alaska, filed suit in the U.S. Federal Court for the Northern District of California against various defendants including Duke Energy. On May 20, 2013, the plaintiffs' Petition for Certiorari to the Supreme Court was denied, ending the case.

Price Reporting Cases

A total of five lawsuits were filed against Duke Energy affiliates and other energy companies and remain pending in a consolidated, single federal court proceeding in Nevada.

Each of these cases contain similar claims, that defendants' allegedly manipulated natural gas markets by various means, including providing false information to natural gas trade publications and entering into unlawful arrangements and agreements in violation of the antitrust laws of the respective states. Plaintiffs seek damages in unspecified amounts.

On July 19, 2011, the judge granted a defendant's motion for summary judgment in two of the remaining five cases to which Duke Energy affiliates are a party. The U.S. Court of Appeals for the Ninth Circuit subsequently reversed the lower court's decision. On August 26, 2013, the defendants, including Duke Energy, filed a petition for certiorari to the U.S. Supreme Court, which remains pending.

It is not possible to predict whether Duke Energy will incur any liability or to estimate the damages, if any, it might incur in connection with the remaining matters. However, based on Duke Energy's past experiences with similar cases of this nature, it does not believe its exposure under these remaining matters is material.

Crescent Resources Litigation

On September 3, 2010, the Crescent Resources (Crescent) Litigation Trust sued Duke Energy along with various affiliates and several individuals, including current and former employees of Duke Energy, in the U.S. Bankruptcy Court for the Western District of Texas.

On November 15, 2013 the parties reached a settlement. Duke Energy recorded a net pretax charge of $22 million to Operations, maintenance and other in its Consolidated Statements of Operations related to the settlement in 2013.

Brazil Expansion Lawsuit

On August 9, 2011, the State of São Paulo sued Duke Energy International Geracao Paranapenema S.A. (DEIGP) in Brazilian state court. The lawsuit claims DEIGP is under a continuing obligation to expand installed generation capacity in the State of São Paulo by 15 percent pursuant to a stock purchase agreement under which DEIGP purchased generation assets from the state. On August 10, 2011, a judge granted an ex parte injunction ordering DEIGP to present a detailed expansion plan in satisfaction of the 15 percent obligation. DEIGP has previously taken a position the expansion obligation is no longer viable given changes that have occurred in the electric energy sector since privatization. DEIGP submitted its proposed expansion plan on November 11, 2011, but reserved objections regarding enforceability. No trial date has been set. It is not possible to predict whether Duke Energy will incur any liability or to estimate the damages, if any, it might incur in connection with this matter.

Duke Energy Carolinas

New Source Review (NSR)

In 1999-2000, the U.S. Department of Justice (DOJ) on behalf of the EPA filed a number of complaints and notices of violation against multiple utilities, including Duke Energy Carolinas, for alleged violations of the NSR provisions of the CAA. The government alleges the utilities violated the CAA by not obtaining permits for certain projects undertaken at certain coal plants or installing the best available emission controls for SO2, NOx and particulate matter. The complaints seek the installation of pollution control technology on various generating units that allegedly violated the CAA, and unspecified civil penalties in amounts of up to $37,500 per day for each violation. Duke Energy Carolinas asserts there were no CAA violations because the applicable regulations do not require permitting in cases where the projects undertaken are “routine” or otherwise do not result in a net increase in emissions.

In 2000, the government sued Duke Energy Carolinas in the U.S. District Court in Greensboro, North Carolina. The EPA claims 29 projects performed at 25 of Duke Energy Carolinas' coal-fired units violate the NSR provisions. Duke Energy Carolinas asserts the projects were routine or not projected to increase emissions. The parties filed a stipulation in which the United States dismissed with prejudice 16 claims. In exchange, Duke Energy Carolinas dismissed certain affirmative defenses. The parties filed opposing motions for summary judgment on the remaining claims. In November 2013, the Court denied Duke Energy's motion for summary judgment. A decision on the DOJ's motion for summary judgment remains pending. Duke Energy requested leave to file another motion for summary judgment on alternative grounds. That motion for leave, as well as the Plaintiff's motion for summary judgment, remains pending.

It is not possible to predict whether Duke Energy Carolinas will incur any liability or to estimate the damages, if any, it might incur in connection with this matter. Ultimate resolution of these matters could have a material effect on the results of operations, cash flows or financial position of Duke Energy Carolinas. However, the appropriate regulatory recovery will be pursued for costs incurred in connection with such resolution.

Asbestos-related Injuries and Damages Claims

Duke Energy Carolinas has experienced numerous claims for indemnification and medical cost reimbursement related to asbestos exposure. These claims relate to damages for bodily injuries alleged to have arisen from exposure to or use of asbestos in connection with construction and maintenance activities conducted on its electric generation plants prior to 1985. As of December 31, 2013, there were 96 asserted claims for non-malignant cases with the cumulative relief sought of up to $24 million, and 31 asserted claims for malignant cases with the cumulative relief sought of up to $11 million. Based on Duke Energy Carolinas' experience, it is expected that the ultimate resolution of most of these claims likely will be less than the amount claimed.

Duke Energy Carolinas has recognized asbestos-related reserves of $616 million at December 31, 2013 and $751 million at December 31, 2012. These reserves are classified in Other within Deferred Credits and Other Liabilities and Other within Current Liabilities on the Consolidated Balance Sheets. These reserves are based upon the minimum amount of the range of loss for current and future asbestos claims through 2033, are recorded on an undiscounted basis and incorporate anticipated inflation. It is possible Duke Energy Carolinas may incur asbestos liabilities in excess of the recorded reserves.

Duke Energy Carolinas has third-party insurance to cover certain losses related to asbestos-related injuries and damages above an aggregate self-insured retention of $476 million. Duke Energy Carolinas' cumulative payments began to exceed the self-insurance retention in 2008. Future payments up to the policy limit will be reimbursed by the third-party insurance carrier. The insurance policy limit for potential future insurance recoveries indemnification and medical cost claim payments is $897 million in excess of the self-insured retention. Receivables for insurance recoveries were $649 million at December 31, 2013 and $781 million at December 31, 2012. These amounts are classified in Other within Investments and Other Assets and Receivables on the Consolidated Balance Sheets. Duke Energy Carolinas is not aware of any uncertainties regarding the legal sufficiency of insurance claims. Duke Energy Carolinas believes the insurance recovery asset is probable of recovery as the insurance carrier continues to have a strong financial strength rating.

Progress Energy

Synthetic Fuels Matters

Progress Energy and a number of its subsidiaries and affiliates are defendants in lawsuits arising out of a 1999 Asset Purchase Agreement. Parties to the Asset Purchase Agreement include U.S. Global, LLC (Global) and affiliates of Progress Energy.

In a case filed in the Circuit Court for Broward County, Florida, in March 2003 (the Florida Global Case), Global requested an unspecified amount of compensatory damages, as well as declaratory relief. In November 2009, the court ruled in favor of Global. In December 2009, Progress Energy made a $154 million payment, which represented payment of the total judgment, including prejudgment interest, and a required premium equivalent to two years of interest, to the Broward County Clerk of Court bond account. Progress Energy continued to accrue interest related to this judgment.

On October 3, 2012, the Florida Fourth District Court of Appeals reversed the lower court ruling. The court held that Global was entitled to approximately $90 million of the amount paid into the registry of the court. Progress Energy was entitled to a refund of the remainder of the funds. Progress Energy received cash and recorded a $63 million pretax gain for the refund in December 2012. The gain was recorded in Income from Discontinued Operations, net of tax in the Consolidated Statements of Operations.

On May 9, 2013, Global filed a Seventh Amended Complaint asserting a single count for breach of the Asset Purchase Agreement and seeking specific performance. A trial is scheduled to commence in the second quarter of 2014.

In a second suit filed in the Superior Court for Wake County, N.C., Progress Synfuel Holdings, Inc. et al. v. U.S. Global, LLC (the North Carolina Global Case), the Progress Energy Affiliates seek declaratory relief consistent with their interpretation of the Asset Purchase Agreement. In August 2003, the Wake County Superior Court stayed the North Carolina Global Case, pending the outcome of the Florida Global Case. Based upon the verdict in the Florida Global Case, Progress Energy anticipates dismissal of the North Carolina Global Case.

Progress Energy does not expect the resolution of these matters to have a material effect on it results of operations, cash flows or financial position.

Duke Energy Progress and Duke Energy Florida

Spent Nuclear Fuel Matters

On December 12, 2011, Duke Energy Progress and Duke Energy Florida sued the United States in the U.S. Court of Federal Claims. The lawsuit claims the DOE breached a contract in failing to accept spent nuclear fuel under the Nuclear Waste Policy Act of 1982 and asserts damages for the cost of on-site storage. Claims for all periods prior to 2006 have been resolved. Duke Energy Progress and Duke Energy Florida assert damages of $84 million and $21 million, respectively, for the period January 1, 2006 through December 31, 2010. Duke Energy Progress and Duke Energy Florida may file subsequent damage claims as they incur additional costs. Duke Energy Progress and Duke Energy Florida cannot predict the outcome of this matter.

Duke Energy Ohio

Antitrust Lawsuit

In January 2008, four plaintiffs, including individual, industrial and nonprofit customers, filed a lawsuit against Duke Energy Ohio in federal court in the Southern District of Ohio. Plaintiffs alleged Duke Energy Ohio conspired to provide inequitable and unfair price advantages for certain large business consumers by entering into non-public option agreements in exchange for their withdrawal of challenges to Duke Energy Ohio's Rate Stabilization Plan (RSP) implemented in early 2005. A ruling is pending on the plaintiffs' motion to certify this matter as a class action. It is not possible to predict whether Duke Energy Ohio will incur any liability or to estimate the damages which may be incurred in connection with this lawsuit.

Asbestos-related Injuries and Damages Claims

Duke Energy Ohio has been named as a defendant or co-defendant in lawsuits related to asbestos exposure at its electric generating stations. The impact on Duke Energy Ohio's results of operations, cash flows or financial position of these cases to date has not been material. Based on estimates under varying assumptions concerning uncertainties, such as, among others: (i) the number of contractors potentially exposed to asbestos during construction or maintenance of Duke Energy Ohio generating plants, (ii) the possible incidence of various illnesses among exposed workers, and (iii) the potential settlement costs without federal or other legislation that addresses asbestos tort actions, Duke Energy Ohio estimates that the range of reasonably possible exposure in existing and future suits over the foreseeable future is not material. This assessment may change as additional settlements occur, claims are made, and more case law is established.

Duke Energy Indiana

Edwardsport IGCC

On December 11, 2012, Duke Energy Indiana filed an arbitration action against General Electric Company and Bechtel Corporation in connection with their work at the Edwardsport IGCC facility. Duke Energy Indiana is seeking damages of not less than $560 million. An arbitration hearing is scheduled for October 2014. Duke Energy Indiana cannot predict the outcome of this matter.

Other Litigation and Legal Proceedings

The Duke Energy Registrants are involved in other legal, tax and regulatory proceedings arising in the ordinary course of business, some of which involve significant amounts. The Duke Energy Registrants believe the final disposition of these proceedings will not have a material effect on their results of operations, cash flows or financial position.

The table below presents recorded reserves based on management's best estimate of probable loss for legal matters discussed above and the associated insurance recoveries. The reasonably possible range of loss for all non-asbestos related matters in excess of recorded reserves is not material.

       
  December 31,
(in millions)2013 2012
Reserves for Legal and Other Matters(a)     
Duke Energy(b)$ 824 $ 846
Duke Energy Carolinas(b)  616   751
Progress Energy  78   79
Duke Energy Progress  10   12
Duke Energy Florida(c)  43   47
Duke Energy Indiana  8   8
Probable Insurance Recoveries(d)     
Duke Energy(e)$ 649 $ 781
Duke Energy Carolinas(e)  649   781
       
(a)Classified in the respective Consolidated Balance Sheets in Other within Deferred Credits and Other Liabilities and Other within Current Liabilities.
(b)Includes reserves for asbestos-related injuries and damages claims.
(c)Includes workers' compensation claims.
(d)Classified in the respective Consolidated Balance Sheets in Other within Investments and Other Assets and Receivables.
(e)Relates to recoveries associated with asbestos-related injuries and damages claims.
       

OTHER COMMITMENTS AND CONTINGENCIES

General

As part of their normal business, the Duke Energy Registrants are party to various financial guarantees, performance guarantees, and other contractual commitments to extend guarantees of credit and other assistance to various subsidiaries, investees, and other third parties. These guarantees involve elements of performance and credit risk, which are not fully recognized on the Consolidated Balance Sheets and have unlimited maximum potential payments. However, the Duke Energy Registrants do not believe these guarantees will have a material effect on their results of operations, cash flows or financial position.

Purchase Obligations

Purchased Power

Duke Energy Progress, Duke Energy Florida, and Duke Energy Ohio have ongoing purchased power contracts, including renewable energy contracts, with other utilities, wholesale marketers, co-generators, and qualified facilities (QFs). These purchased power contracts generally provide for capacity and energy payments. In addition, Duke Energy Progress, Duke Energy Florida, and Duke Energy Ohio have various contracts to secure transmission rights.

The following table presents executory purchased power contracts, excluding contracts classified as leases.

      Minimum Purchase Amount at December 31, 2013
(in millions) Contract Expiration 2014 2015 2016 2017 2018 Thereafter Total
Duke Energy Progress(a) 2019-2022 $ 36   36 $ 36 $ 37 $ 37 $ 69 $ 251
Duke Energy Florida(b) 2014-2025   288   295   295   288   303   2,139   3,608
Duke Energy Ohio(c) 2014-2015   250   97           347
                         
(a)Contracts represent 100 percent of net plant output.
(b)Contracts represent between 2 percent and 100 percent of net plant output.
(c)Contracts represent between 1 percent and 24 percent of net plant output.
                         

Operating and Capital Lease Commitments

The Duke Energy Registrants lease office buildings, railcars, vehicles, computer equipment and other property and equipment with various terms and expiration dates. Additionally, Duke Energy Progress has a capital lease related to firm gas pipeline transportation capacity. Duke Energy Progress and Duke Energy Florida have entered into certain purchased power agreements, which are classified as leases. Consolidated capitalized lease obligations are classified as Long-term debt or Other within Current Liabilities on the Consolidated Balance Sheets. Amortization of assets recorded under capital leases is included in Depreciation and amortization and Fuel used in electric generation – regulated on the Consolidated Statements of Operations.

The following table presents rental expense for operating leases. These amounts are included in Operation, maintenance and other on the Consolidated Statements of Operations.

          
  Years Ended December 31,
(in millions)201320122011
Duke Energy$ 321 $ 232 $ 104
Duke Energy Carolinas  39   38   43
Progress Energy  225   232   104
Duke Energy Progress  153   164   88
Duke Energy Florida  72   68   15
Duke Energy Ohio  14   14   19
Duke Energy Indiana  22   20   24
          

The following table presents future minimum lease payments under operating leases, which at inception had a non-cancelable term of more than one year.
                      
  December 31, 2013
(in millions)Duke Energy Duke Energy Carolinas Progress Energy Duke Energy Progress Duke Energy Florida Duke Energy Ohio Duke Energy Indiana
2014$ 175 $ 34 $ 93 $ 55 $ 39 $ 12 $ 18
2015  159   29   89   51   39   11   15
2016  147   24   90   51   39   8   12
2017  137   20   89   50   39   7   9
2018  117   15   78   40   38   5   7
Thereafter  1,034   67   773   459   314   18   8
Total$ 1,769 $ 189 $ 1,212 $ 706 $ 508 $ 61 $ 69
                      

The following table presents future minimum lease payments under capital leases.
                      
  December 31, 2013
(in millions)Duke Energy Duke Energy Carolinas Progress Energy Duke Energy Progress Duke Energy Florida Duke Energy Ohio Duke Energy Indiana
2014$ 171 $ 6 $ 47 $ 20 $ 26 $ 9 $ 5
2015  167   6   47   20   27   7   4
2016  169   6   47   21   26   6   4
2017  166   6   46   21   26   3   2
2018  176   6   45   21   25   3   2
Thereafter  1,453   25   475   261   213   2   28
Minimum annual payments  2,302   55   707   364   343   30   45
Less amount representing interest  (786)   (27)   (454)   (275)   (179)   (3)   (30)
Total$ 1,516 $ 28 $ 253 $ 89 $ 164 $ 27 $ 15