XML 218 R59.htm IDEA: XBRL DOCUMENT v2.4.0.8
Regulatory Matters (Schedule of Net Carrying Value Of Facilities As Well As the Remaining Non-current Regulatory Assets) (Details) (USD $)
In Millions, unless otherwise specified
6 Months Ended
Jun. 30, 2013
MW
Megawatt of potential plants to be retired 3,244
Remaining net book value of potential plants to be retired $ 326 [1]
Duke Energy Carolinas [Member]
 
Megawatt of potential plants to be retired 200 [2]
Remaining net book value of potential plants to be retired 15 [1],[2],[3]
Retired MW   
Megawatts committed to be retired   
Progress Energy [Member]
 
Megawatt of potential plants to be retired 1,448
Remaining net book value of potential plants to be retired 173 [1]
Duke Energy Progress [Member]
 
Megawatt of potential plants to be retired 575 [4]
Remaining net book value of potential plants to be retired 61 [1],[3],[4]
Duke Energy Florida [Member]
 
Megawatt of potential plants to be retired 873 [5]
Remaining net book value of potential plants to be retired 112 [1],[5]
Duke Energy Ohio [Member]
 
Megawatt of potential plants to be retired 928 [6]
Remaining net book value of potential plants to be retired 11 [1],[6]
Duke Energy Indiana [Member]
 
Megawatt of potential plants to be retired 668 [7]
Remaining net book value of potential plants to be retired $ 127 [1],[7]
[1] Included in Property, plant and equipment, net as of June 30, 2013, on the Condensed Consolidated Balance Sheets, unless otherwise noted.
[2] Includes Lee Units 1 and 2. Excludes 170 MW Lee Unit 3 that is expected to be converted to gas in 2014.
[3] Remaining net book value of Duke Energy Progress' Sutton Station is included in Generation facilities to be retired, net, on the Condensed Consolidated Balance Sheets at June 30, 2013.
[4] Includes Sutton Station, which is expected to be retired by the end of 2013.
[5] Includes Crystal River Units 1 and 2.
[6] Includes Beckjord Station Units 2 through 6 and Miami Fort Unit 6. Beckjord has no remaining book value.