XML 34 R13.htm IDEA: XBRL DOCUMENT v3.23.1
Sponsorship Revenue and Associated Commitments
12 Months Ended
Dec. 31, 2022
Sponsorship Revenue and Associated Commitments [Abstract]  
Sponsorship Revenue and Associated Commitments

Note 6: Sponsorship Revenue and Associated Commitments

 

Johnson Controls, Inc.

 

On July 2, 2020, the Company entered into an Amended and Restated Sponsorship and Naming Rights Agreement (the “Naming Rights Agreement”) among Newco, PFHOF and Johnson Controls, Inc. (“JCI” or “Johnson Controls”), that amended and restated the Sponsorship and Naming Rights Agreement, dated as of November 17, 2016 (the “Original Sponsorship Agreement”). Among other things, the Amended Sponsorship Agreement: (i) reduced the total amount of fees payable to Newco during the term of the Amended Sponsorship Agreement from $135 million to $99 million; (ii) restricted the activation proceeds from rolling over from year to year with a maximum amount of activation proceeds in one agreement year to be $750,000; and (iii) renamed the “Johnson Controls Hall of Fame Village” to “Hall of Fame Village”. This is a prospective change, which the Company reflected beginning in the third quarter of 2020.

 

JCI has a right to terminate the Naming Rights Agreement if the Company does not provide evidence to JCI by October 31, 2021 that it has secured sufficient debt and equity financing to complete Phase II, or if Phase II is not open for business by January 2, 2024, in each case subject to day-for-day extension due to force majeure and a notice and cure period. In addition, under the Naming Rights Agreement JCI’s obligation to make sponsorship payments to the Company may be suspended commencing on December 31, 2020, if the Company has not provided evidence reasonably satisfactory to JCI on or before December 31, 2020, subject to day-for-day extension due to force majeure, that the Company has secured sufficient debt and equity financing to complete Phase II.

 

Additionally, on October 9, 2020, Newco, entered into a Technology as a Service Agreement (the “TAAS Agreement”) with JCI. Pursuant to the TAAS Agreement, JCI will provide certain services related to the construction and development of the Hall of Fame Village (the “Project”), including, but not limited to, (i) design assist consulting, equipment sales and turn-key installation services in respect of specified systems to be constructed as part of Phase 2 and Phase 3 of the Project and (ii) maintenance and lifecycle services in respect of certain systems constructed as part of Phase 1, and to be constructed as part of Phase 2 and Phase 3, of the Project. Under the terms of the TAAS Agreement, Newco has agreed to pay JCI up to an aggregate of approximately $217 million for services rendered by JCI over the term of the TAAS Agreement. As of December 31, 2022 and December 31, 2021, approximately $195 million and $199 million, respectively, was remaining under the TAAS Agreement.

 

As of December 31, 2022, scheduled future cash to be received under the Naming Rights Agreement is as follows:

 

   Unrestricted   Activation   Total 
2022 (past due)  $4,000,000   $750,000   $4,750,000 
2023   4,000,000    750,000    4,750,000 
2024   4,250,000    750,000    5,000,000 
2025   4,250,000    750,000    5,000,000 
2026   4,250,000    750,000    5,000,000 
Thereafter   35,531,251    6,000,000    41,531,251 
Total  $56,281,251   $9,750,000   $66,031,251 

 

As services are provided, the Company is recognizing revenue on a straight-line basis over the expected term of the Amended Sponsorship Agreement. During the year ended December 31, 2021, the Company recognized $4,497,864, of net sponsorship revenue related to the Naming Rights Agreement.

 

On May 10, 2022, the Company received from JCI a notice of termination (the “TAAS Notice”) of the TAAS Agreement effective immediately. The TAAS Notice states that termination of the TAAS Agreement by JCI is due to Newco’s alleged breach of its payment obligations. Additionally, JCI in the TAAS Notice demands the amount which is the sum of: (i) all past due payments and any other amounts owed by Newco under the TAAS Agreement; (ii) all commercially reasonable and documented subcontractor breakage and demobilization costs; and (iii) all commercially reasonable and documented direct losses incurred by JCI directly resulting from the alleged default by the Company and the exercise of JCI’s rights and remedies in respect thereof, including reasonable attorney fees.

 

Also on May 10, 2022, the Company received from JCI a notice of termination (“Naming Rights Notice”) of the Name Rights Agreement, effective immediately. The Naming Rights Notice states that the termination of the Naming Rights Agreement by JCI is due to JCI’s concurrent termination of the TAAS Agreement. The Naming Rights Notice further states that the Company must pay JCI, within 30 days following the date of the Naming Rights Notice, $4,750,000. The Company has not made such payment to date. The Naming Rights Notice states that Newco is also in breach of its covenants and agreements, which require Newco to provide evidence reasonably satisfactory to JCI on or before October 31, 2021, subject to day-for-day extension due to force majeure, that Newco has secured sufficient debt and equity financing to complete Phase II.

 

The Company disputes that it is in default under either the TAAS Agreement or the Naming Rights Agreement. The Company believes JCI is in breach of the Naming Rights Agreement and the TAAS Agreement due to their failure to make certain payments in accordance with the Naming Rights Agreement, and, on May 16, 2022, provided notice to JCI of these breaches. The Company is pursuing dispute resolution pursuant to the terms of the Naming Rights Agreement to simultaneously defend against JCI’s allegations and pursue its own claims. The ultimate outcome of this dispute cannot presently be determined. However, in management’s opinion, the likelihood of a material adverse outcome is remote. Accordingly, adjustments, if any, that might result from the resolution of this matter have not been reflected in the accompanying consolidated financial statements. During the year ended December 31, 2022, the Company suspended its revenue recognition until the dispute is resolved and has recorded an allowance against the amounts due as of December 31, 2022 in the amount of $4,812,500. The balances due under the Naming Rights Agreement as of December 31, 2022 and December 31, 2021 amounted to $6,635,417 and $1,885,417, respectively.

 

The Company and JCI are currently undergoing the process of binding arbitration. The ultimate outcome of this dispute cannot presently be determined.

 

Other Sponsorship Revenue

 

The Company has additional revenue primarily from sponsorship programs that provide its sponsors with strategic opportunities to reach customers through our venue including advertising on our website. Sponsorship agreements may contain multiple elements, which provide several distinct benefits to the sponsor over the term of the agreement and can be for a single or multi-year term. These agreements provide sponsors various rights such as venue naming rights, signage within our venues, and advertising on our website and other benefits as detailed in the agreements.

 

As of December 31, 2022, scheduled future cash to be received under the agreements, excluding the Johnson Controls Naming Rights Agreement, is as follows:

 

2023  $2,929,720 
2024   2,406,265 
2025   2,317,265 
2026   2,167,265 
2027   1,757,265 
Thereafter   4,514,529 
Total  $16,092,309 

 

As services are provided, the Company is recognizing revenue on a straight-line basis over the expected term of the agreement. During the years ended December 31, 2022 and 2021, the Company recognized $2,697,487 and $6,023,863 of net sponsorship revenue, respectively.