Note 8 - Real Estate Development
6 Months Ended
Jun. 30, 2023
Notes to Financial Statements  
Real Estate Disclosure [Text Block]

8.    REAL ESTATE DEVELOPMENT

 

Equity Investments

 

Doran Canterbury I, LLC 

 

On April 2, 2018, the Company’s subsidiary Canterbury Development LLC, entered into an Operating Agreement (“Operating Agreement”) with an affiliate of Doran Companies (“Doran”), a national commercial and residential real estate developer, as the two members of a Minnesota limited liability company named Doran Canterbury I, LLC (“Doran Canterbury I”). Doran Canterbury I was formed as part of a joint venture between Doran and Canterbury Development LLC to construct an upscale apartment complex on land adjacent to the Company’s Racetrack (the “Project”).

 

On September 27, 2018, Canterbury Development LLC contributed approximately 13 acres of land as its equity contribution in the Doran Canterbury I joint venture and became a 27.4% equity member. On December 20, 2018, financing for Doran Canterbury I was secured. Doran Canterbury I has completed developing Phase I of the Project, which includes 321 units, a heated parking ramp, and a clubhouse. As the Company is able to assert significant influence, but not control, over Doran Canterbury I’s operational and financial policies, the Company accounts for the joint venture as an equity method investment. For the three and six months ended June 30, 2023, the Company recorded a loss of $596,000 and income of $1,286,000, respectively, on equity method investment related to this joint venture. The increased income for the first half of 2023 related to this joint venture is due to the receipt of insurance proceeds related to an outstanding claim. For the three and six months ended June 30, 2022, the Company recorded $497,000 and $1,012,000, respectively, in loss on equity method investments related to this joint venture. In accordance with U.S. GAAP, since we are committed to provide future member loans to Doran Canterbury I to cover the costs of construction or operating deficiencies, we also present as a liability in the accompanying Condensed Consolidated Balance Sheets the net balance recorded for our share of Doran Canterbury I's losses in excess of the amount funded into Doran Canterbury I, which was $1,900,000 and $3,186,000 at June 30, 2023 and December 31, 2022, respectively. See Note 10 of Notes to Financial Statements for a summary of member loans to Doran Canterbury I.

 

Doran Canterbury II, LLC 

 

In connection with the execution of the Amended Doran Canterbury I Agreement, on August 18, 2018, Canterbury Development LLC entered into an Operating Agreement with Doran Shakopee, LLC as the two members of a Minnesota limited liability company entitled Doran Canterbury II, LLC (“Doran Canterbury II”). The Operating Agreement was amended and restated by the members effective July 30, 2020. Under the Doran Canterbury II Operating Agreement, Doran Canterbury II will pursue development of Phase II of the Project. Phase II will include an additional 300 apartment units. Canterbury Development’s equity contribution to Doran Canterbury II for Phase II was approximately 10 acres of land, which were contributed to Doran Canterbury II on September 30, 2020. In connection with its contribution, Canterbury Development became a 27.4% equity member in Doran Canterbury II with Doran owning the remaining 72.6%. As the Company is able to assert significant influence, but not control, over Doran Canterbury II’s operational and financial policies, the Company accounts for the joint venture as an equity method investment. As of June 30, 2023, the proportionate share of Doran Canterbury II's earnings was immaterial. During the three and six months ended June 30, the Company did not make any contributions as an equity investment contribution in Doran Canterbury II. During the three and sixth months ended June 30, 2022, the Company contributed approximately $58,000 and $398,000 as an equity investment contribution in Doran Canterbury II. Under the Operating Agreement, we are required to provide future member loans to Doran Canterbury II to cover the costs of construction or operating deficiencies. See Note 10 of Notes to Financial Statements for a summary of member loans to Doran Canterbury II.

 

Canterbury DBSV Development, LLC

 

On June 16, 2020, Canterbury Development LLC, entered into an Operating Agreement with an affiliate of Greystone Construction, as the two members of a Minnesota limited liability company named Canterbury DBSV Development, LLC ("Canterbury DBSV"). Canterbury DBSV was formed as part of a joint venture between Greystone and Canterbury Development LLC for a multi-use development on the 13-acre land parcel located on the southwest portion of the Company’s racetrack. Canterbury Development LLC's equity contribution to Canterbury DBSV was approximately 13 acres of land, which were contributed to Canterbury DBSV on July 1, 2020. In connection with its contribution, Canterbury Development became a 61.87% equity member in Canterbury DBSV. As the Company is able to assert significant influence, but not control, over Canterbury DBSV’s operational and financial policies, the Company accounts for the joint venture as an equity method investment. For the three and six months ended June 30, 2023, the Company recorded $26,000 and $52,000, respectively, in loss on equity method investments related to this joint venture. For the three and six months ended June 30, 2022, the Company recorded a loss of $37,000 and income of $239,000, respectively, on equity investment related to this joint venture.

 

The following table summarizes changes to the Equity investment and Investee losses in excess of equity investment lines on our consolidated balance sheets for the six months ended June 30, 2023:

 

  

Equity Investment

  

Investee losses in excess of equity investment

  

Net Equity Investment

 

Net Equity Investment Balance at 12/31/22

 $6,863,517  $(3,185,923) $3,677,594 
             

Q1 Equity investment income (loss)

  (23,232)  1,881,744   1,858,512 
             

Q2 Equity investment income (loss)

  (26,071)  (596,109)  (622,180)
             

Net Equity Investment Balance at 6/30/23

 $6,814,214  $(1,900,288) $4,913,926 

 

Tax Increment Financing

 

On August 8, 2018, the City Council of the City of Shakopee, Minnesota approved a Contract for Private Redevelopment (“Redevelopment Agreement”) between the City of Shakopee Economic Development Authority (“Shakopee EDA”) and Canterbury Park Holding Corporation and its subsidiary Canterbury Development LLC in connection with a Tax Increment Financing District (“TIF District”) that the City had approved in April 2018. The City of Shakopee, the Shakopee EDA and the Company entered into the Redevelopment Agreement on August 10, 2018.

 

Under the Original Agreement, the Company agreed to undertake a number of specific infrastructure improvements within the TIF District, and the City agreed that a portion of the tax revenue generated from the developed property will be paid to the Company to reimburse it for its expense in constructing these improvements. Under the Original Agreement, the total estimated cost of TIF eligible improvements to be borne by the Company was $23,336,500.

 

On  January 25, 2022, the Company received the fully executed First Amendment to the Contract for Private Redevelopment (the “First Amendment”) among the Company, the City of Shakopee, and the Shakopee EDA, which is effective as of  September 7, 2021. Under the First Amendment and as part of the authorized changes regarding the responsibilities of the Company and the City, improvements on Unbridled Avenue will be primarily constructed by the City of Shakopee. As a result, the total estimated cost of TIF eligible improvements to be borne by the Company was reduced by $5,744,000 to an amount not to exceed $17,592,881. In order to reimburse the Company for the qualified costs related to constructing the developer improvements, the Authority will issue and the Company will receive a TIF Note in the maximum principal amount of $17,592,881. The First Amendment also memorialized that the Company completed the Shenandoah Drive improvements as required prior to  December 31, 2019. The City is obligated to issue bonds to finance the portion of the improvements required to be constructed by the City. 

 

A detailed Schedule of the Public Improvements under the First Amendment, the timeline for their construction and the source and amount of funding is set forth in Exhibit 10.1 of the Form 8-K filed on  January 31, 2022. The Company expects to substantially complete the remaining developer improvements by  July 17, 2027 and will be reimbursed for costs of the developer improvements incurred by no later than  July 17, 2027. The total amount of funding that the Company will be paid as reimbursement under the TIF program for these improvements is not guaranteed, however, and will depend in part on future tax revenues generated from the developed property.

 

As of June 30, 2023, the Company recorded a TIF receivable of approximately $13,631,000, which represents $11,305,000 of principal and $2,326,000 of interest. Management believes future tax revenues generated from current development activity will exceed the Company's development costs and thus, management believes no allowance related to this receivable is necessary. As of December 31, 2022, the Company recorded a TIF receivable of approximately $13,294,000, which represented $11,301,000 of principal and $1,993,000 of interest. 

 

The Company expects to finance its improvements under the Redevelopment Agreement with funds from its current operating resources and existing credit facility and, potentially, third-party financing sources.

 

Recently Closed Transactions under Real Estate Agreements

 

On April 28, 2023, the Company completed the sale of 37 acres of land to Bloomington Investments, LLC, an entity related to Swervo Development ("Swervo"), for total consideration of $8,800,000. Included in this amount is $500,000 of cash being held in escrow related to a contingency for the now completed demolition of barns that existed on the land prior to the sale. The cash in escrow is currently recorded as a receivable on the Condensed Consolidated Balance Sheets. The land sold is situated adjacent to County Road 83 and Unbridled Avenue in the northeast corner of the Company's campus. With the land sale and government approvals now complete, Swervo expects construction of its planned 19,000-capacity open air amphitheater to begin this Summer, with the venue opening anticipated to be Summer 2025. Following the land sale, Canterbury will continue the redevelopment of the horse stabling area, which serves its racing business, with new barns and a new dormitory complex.