Commitments
Leases - The Company leases its facilities, office buildings and equipment under operating leases that expire at various dates through December 2020. The Company’s headquarters are used for corporate administration, research and development, sales and marketing and manufacturing, and currently consists of approximately 31,000 square feet of occupied space in Sunnyvale, California under lease through December 2018. In April 2018, the Company entered into a new lease for the Company's headquarters commencing in January 2019 to occupy approximately 181,000 square feet of office space in San Jose, California through December 2028.
During the three months ended September 30, 2018 and 2017, rent expense for all occupied facilities was $1.7 million and $1.4 million, respectively. During the nine months ended September 30, 2018 and 2017, rent expense for all occupied facilities was $4.6 million and $4.3 million, respectively.
Beginning in December 2015, the Company is a party to master lease agreements that provide for the sale of Energy Servers to third parties and the simultaneous leaseback of the systems which the Company then subleases to customers. The lease agreements expire on various dates through 2025 and there was no recorded rent expense for the three and nine months ended September 30, 2018 and 2017.
At September 30, 2018, future minimum lease payments under operating leases were as follows (in thousands):
Remainder of 2018
$
2,011

2019
8,725

2020
7,581

2021
5,097

2022
4,382

Thereafter
25,249

 
$
53,045


Purchase Commitments with Suppliers and Contract Manufacturers - In order to reduce manufacturing lead-times and to ensure an adequate supply of inventories, the Company has agreements with its component suppliers and contract manufacturers to allow them to procure long lead-time component inventory based on a rolling production forecast. The Company is contractually obligated to purchase long lead-time component inventory procured by certain manufacturers in accordance with its forecasts. The Company can generally give notice of order cancellation at least 90 days prior to the delivery date. However, the Company issues purchase orders to its component suppliers and third-party manufacturers that may not be cancelable. As of September 30, 2018 and December 31, 2017, the Company had no material open purchase orders with its component suppliers and third-party manufacturers that are not cancelable.
Power Purchase Agreement Program - Under the terms of the Bloom Electrons program (see Note 12 - Power Purchase Agreement Programs), customers agree to purchase power from the Company’s Energy Servers at negotiated rates, generally for periods of up to twenty-one years. The Company is responsible for all operating costs necessary to maintain, monitor and repair the Energy Servers, including the fuel necessary to operate the systems under certain PPA contracts. The risk associated with the future market price of fuel purchase obligations is mitigated with commodity contract futures.
The PPA Entities guarantee the performance of Energy Servers at certain levels of output and efficiency to its customers over the contractual term. The PPA Entities monitor the need for any accruals arising from such guarantees, which are calculated as the difference between committed and actual power output or between natural gas consumption at warranted efficiency levels and actual consumption, multiplied by the contractual rates with the customer. Amounts payable under these guarantees are accrued in periods when the guarantees are not met and are recorded in cost of service revenue in the consolidated statements of operations. The Company made no such expense during the three months ended September 30, 2018 and 2017 and $0.9 million and $3.7 million was expensed for the nine months ended September 30, 2018 and 2017, respectively.
In June 2015, PPA V entered into a $131.2 million credit agreement to fund the purchase and installation of Energy Servers. The lenders have commitments to a letter of credit (LC) facility with the aggregate principal amount of $6.2 million. The LC facility is to fund the Debt Service Reserve Account. The amount reserved under the letter of credit as of September 30, 2018 and December 31, 2017 was $4.7 million and $4.4 million, respectively.
Contingencies
Indemnification Agreements - The Company enters into standard indemnification agreements with its customers and certain other business partners in the ordinary course of business. The Company’s exposure under these agreements is unknown because it involves future claims that may be made against the Company but have not yet been made. To date, the Company has not paid any claims or been required to defend any action related to its indemnification obligations. However, the Company may record charges in the future as a result of these indemnification obligations.
Warranty Costs - The Company generally warrants its products sold to its direct customers for one year following the date of acceptance of the products (the standard one-year warranty). As part of its MSAs, the Company provides output and efficiency guarantees (collectively “performance guarantees”) to its customers when systems operate below contractually specified levels of efficiency and output. Such amounts have not been material to date.
The standard one-year warranty covers defects in materials and workmanship under normal use and service conditions, and against manufacturing or performance defects. The Company’s warranty accrual represents its best estimate of the amount necessary to settle future and existing claims during the warranty period and as of the balance sheet date.
The Company’s obligations under its standard one-year warranty and MSA agreements are generally in the form of product replacement, repair or reimbursement for higher customer electricity costs. Further, if the Energy Servers run at a lower efficiency or power output than the Company committed under its performance guarantee, the Company will reimburse the customer for the underperformance. The Company’s aggregate reimbursement obligation for this performance guarantee for each order is capped at a portion of the purchase price.
Delaware Economic Development Authority - In March 2012, the Company entered into an agreement with the Delaware Economic Development Authority to provide a grant of $16.5 million as an incentive to establish a new manufacturing facility in Delaware and to provide employment for full time workers at the facility over a certain period of time. The grant contains two types of milestones that the Company must complete to retain the entire amount of the grant proceeds. The first milestone was to provide employment for 900 full time workers in Delaware by the end of the first recapture period of September 30, 2017. The second milestone was to pay these full time workers a cumulative total of $108.0 million in compensation by September 30, 2017. There are two additional recapture periods at which time the Company must continue to employ 900 full time workers and the cumulative total compensation paid by the Company is required to be at least $324.0 million by September 30, 2023. As of September 30, 2018, the Company had 335 full time workers in Delaware and paid $86.0 million in cumulative compensation. As of December 31, 2017, the Company had 305 full time workers in Delaware and paid $69.3 in cumulative compensation. The Company has so far received $12.0 million of the grant which is contingent upon meeting the milestones through September 30, 2023. In the event that the Company does not meet the milestones, it may have to repay the Delaware Economic Development Authority, including up to $5.0 million on September 30, 2021 and up to an additional $2.5 million on September 30, 2023. As of September 30, 2018, the Company had paid $1.5 million for recapture provisions and has recorded $10.5 million in other long-term liabilities for potential recapture.
Self-Generation Incentive Program (SGIP) - The Company’s PPA Entities’ customers receive payments under the SGIP which is a program specific to the State of California that provides financial incentives for the installation of qualifying new self-generation equipment that the Company owns. The SGIP program issues 50% of the fully anticipated amount in the first year the equipment is placed into service. The remaining incentive is then paid based on the size of the equipment (i.e., nameplate kilowatt capacity) over the subsequent five years.
The SGIP program has operational criteria primarily related to fuel mixture and minimum output for the first five years after the qualified equipment is placed in service. If the operational criteria are not fulfilled, it could result in a partial refund of funds received. However, for certain PPA Entities, the Company makes SGIP reservations on behalf of the PPA Entity and, therefore, the PPA Entity bears the risk of loss if these funds are not paid.
Investment Tax Credits - Through December 31, 2016, purchase of the Company’s Energy Servers were eligible for federal investment tax credits, or ITCs, that accrued to eligible property under Internal Revenue Code Section 48. The ITC program has operational criteria for the first five years after the qualified equipment is placed in service. If the qualified energy property is disposed or otherwise ceases to be investment credit property before the close of the five year recapture period is fulfilled, it could result in a partial reduction of the incentives. The Company's purchase of Energy Servers were by the PPA Entities and, therefore, the PPA Entities bear the risk of repayment if the assets placed in service do not meet the ITC operational criteria in the future.
Legal Matters - From time to time, the Company is involved in disputes, claims, litigation, investigations, proceedings and/or other legal actions consisting of commercial, securities and employment matters that arise in the ordinary course of business. The Company reviews all legal matters at least quarterly and assesses whether an accrual for loss contingencies needs to be recorded. The assessment reflects the impact of negotiations, settlements, rulings, advice of legal counsel and other information and events pertaining to a particular situation. The Company records an accrual for loss contingencies when management believes that it is both probable that a liability has been incurred and the amount of the loss can be reasonably estimated. Legal matters are subject to uncertainties and are inherently unpredictable, so the actual liability in any such matters may be materially different from the Company’s estimates. If an unfavorable resolution were to occur, there exists the possibility of a material adverse impact on the Company’s consolidated financial condition, results of operations or cash flows for the period in which the resolution occurs or on future periods.
In July 2018, two former executives of Advanced Equities, Inc., Keith Daubenspeck and Dwight Badger, filed a Statement of Claim with the American Arbitration Association in Santa Clara, CA, against the Company, Kleiner Perkins, Caufield & Byers, LLC (“KPCB”), New Enterprise Associates, LLC (“NEA”) and affiliated entities of both KPCB and NEA seeking to compel arbitration and alleging a breach of a confidential agreement executed between the parties on June 27, 2014 (“Confidential Agreement”) . This Statement of Claim sought, among other things, to void the indemnification and confidentiality provisions under the Confidential Agreement and to recover attorneys’ fees and costs. The Statement of Claim was dismissed without prejudice on July 22, 2018.  On September 19, 2018, an Amended Statement of Claim was filed by Messrs. Daubenspeck and Badger with the American Arbitration Association in Santa Clara, CA, against the parties.  The Amended Statement of Claim alleges a breach of the Confidentiality Agreement and fraud in the inducement, securities fraud, racketeering and other claims.  The Company’s response is currently due by November 30, 2018.  The Company believes the Amended Statement of Claim to be without merit and as a result, the Company has recorded no loss contingency related to this claim.