COMMITMENTS AND CONTINGENCIES
Investigations and Litigation
ARPA: On February 28, 2014, Arkansas River Power Authority ("ARPA") filed suit against Babcock & Wilcox Power Generation Group, Inc. ("PGG OpCo") in the United States District Court for the District of Colorado (Case No. 14-cv-00638-CMA-NYW) alleging breach of contract, negligence, fraud and other claims arising out of PGG OpCo's delivery of a circulating fluidized bed boiler and related equipment used in the Lamar Repowering Project pursuant to a 2005 contract.
In 2009, PGG OpCo informed ARPA that the boiler would require a selective non-catalytic reduction system in order to achieve contractual emissions guarantees, which PGG OpCo supplied in 2010. PGG OpCo recommended additional modifications in 2011 and 2012 to ensure the boiler would meet contractual emissions guarantees; however, ARPA has not installed all of the recommended modifications. ARPA has not announced whether it intends to complete and commission the Lamar plant.
On April 16, 2014, PGG OpCo filed an Answer asserting numerous defenses, including waiver, prevention of performance and failure to mitigate damages and Counterclaims alleging bad faith, breach of contract and unjust enrichment. ARPA filed an Answer to the Counterclaims on May 7, 2014. The District Court granted leave for ARPA to amend its Complaint, and ARPA's First Amended Complaint was accepted on March 20, 2015. PGG OpCo filed its Answer to the First Amended Complaint on April 1, 2015. Discovery is substantially completed and a trial date has been set for June 2016.
We believe that ARPA has asserted damages theories that are highly speculative and without legal or economic support as a litigation tactic. We also believe most of the alleged damages are expressly waived and/or capped in enforceable provisions of the 2005 contract. We cannot estimate the possible loss at this time. However, in addition to establishing other relevant sub-caps and including an explicit waiver of a broad range of damages, including consequential damages, the 2005 contract provides an overall cap of liability at the original contract price of approximately $20.5 million. ARPA has alleged various theories of possible liability and damages that would lead to vastly different measures of damages, making it impracticable to estimate a range of possible outcomes; however, ARPA's damage claims total approximately $170 million. PGG OpCo does not believe it is probable that ARPA will be successful in any of its claims. PGG OpCo believes it has strong defenses and intends to aggressively defend this matter and pursue its counterclaims. However, if ARPA were to prevail on all or any significant portion of its claims in this matter, the outcome could have a material adverse effect on our financial condition.
Other Litigation: Due to the nature of our business, we are, from time to time, involved in routine litigation or subject to disputes or claims related to our business activities, including, among other things:
performance- or warranty-related matters under our customer and supplier contracts and other business arrangements; and
workers' compensation claims, premises liability claims and other claims.
Based upon our prior experience, we do not expect that any of these other litigation proceedings, disputes and claims will have a material adverse effect on our consolidated financial condition, results of operations or cash flows.
Insurance: Upon the February 22, 2006 effectiveness of the settlement relating to the Chapter 11 proceedings involving several of our subsidiaries, most of our subsidiaries contributed substantial insurance rights to the asbestos personal injury trust, including rights to (1) certain pre-1979 primary and excess insurance coverages and (2) certain of our 1979-1986 excess insurance coverage. These insurance rights provided coverage for, among other things, asbestos and other personal injury claims, subject to the terms and conditions of the policies. The contribution of these insurance rights was made in exchange for the agreement on the part of the representatives of the asbestos claimants, including the representative of future claimants, to the entry of a permanent injunction, pursuant to Section 524(g) of the United States Bankruptcy Code, to channel to the asbestos trust all asbestos-related claims against our subsidiaries and former subsidiaries arising out of, resulting from or attributable to their operations, and the implementation of related releases and indemnification provisions protecting those subsidiaries and their affiliates from future liability for such claims. Although we are not aware of any significant, unresolved claims against our subsidiaries and former subsidiaries that are not subject to the channeling injunction and that relate to the periods during which such excess insurance coverage related, with the contribution of these insurance rights to the asbestos personal injury trust, it is possible that we could have underinsured or uninsured exposure for non-derivative asbestos claims or other personal injury or other claims that would have been insured under these coverages had the insurance rights not been contributed to the asbestos personal injury trust.