Contributed Assets
In connection with the IPO, the Partnership acquired a 10.6% interest in OpCo and a 100% interest in OpCo GP. OpCo owns the Contributed Assets.
Other assets contributed to OpCo in conjunction with the IPO include the deferred turnaround costs associated with Lake Charles Olefins and Calvert City Olefins, co-products inventories, goodwill and other assets. Additionally, OpCo assumed the August 2013 Promissory Notes in the amount of $246,056.
The Predecessor's combined financial statements reflect certain assets, liabilities and business activities that were retained by Westlake and, therefore, are not reflected in the Partnership's consolidated financial statements. Assets and liabilities which are reflected in the Predecessor's combined financial statements but which were retained by Westlake include working capital accounts, ethylene and other inventories, an equity interest in a pipeline joint venture, deferred federal income taxes, certain long-term debt payable to Westlake and other long-term liabilities. Ethylene business activities retained by Westlake include, but are not limited to, procuring feedstock, managing inventory and commodity risk and transporting ethylene from manufacturing facilities. See Note 17 for details of the Predecessor's net liabilities retained by Westlake.
Initial Public Offering
On July 30, 2014, the Partnership's common units began trading on the New York Stock Exchange under the ticker symbol "WLKP." On August 4, 2014, the Partnership completed the IPO of 12,937,500 common units at a price to the public of $24.00 per unit ($22.53 per unit net of underwriting discount), including 1,687,500 common units that were issued pursuant to the exercise in full of the underwriters' over-allotment option.
In connection with the IPO, in exchange for Westlake's contribution of a 5.8% limited partner interest in OpCo and OpCo's general partner interest to the Partnership, Westlake received:
1,436,115 common units and 12,686,115 subordinated units; and
the Partnership's general partner interest and its incentive distribution rights.
The Partnership received net proceeds of $286,088 from the IPO, net of underwriting discounts, structuring fees and offering expenses of approximately $24,412. The Partnership used the net proceeds from the IPO to purchase an additional 4.8% limited partner interest in OpCo, resulting in the Partnership owning a 10.6% limited partner interest in OpCo. The Partnership recorded the incremental 4.8% limited partner interest in OpCo at its historical carrying value of $43,516 and the excess cash paid over historical carrying value of $242,572 as a decrease to the General partner—Westlake capital account. Accordingly, the Partnership's consolidated financial statements reflect the 89.4% limited partner interest in OpCo that was retained by Westlake as a noncontrolling interest.
From the period beginning August 4, 2012 to July 31, 2013, Westlake incurred approximately $151,729 in capital expenditures (the "Pre-August 2013 Capex") with respect to the assets contributed to OpCo. The portion of these capital expenditures incurred before January 1, 2013 was accounted for as an adjustment to Net investment, as it was funded through equity. The portion of the capital expenditures incurred from January 1, 2013 through July 31, 2013 was accounted for as a liability and is reflected as such on the Predecessor's combined financial statements, and the associated liability was retained by Westlake in connection with the IPO. During the period from August 1, 2013 through August 3, 2014, Westlake funded capital expenditures of $246,056 related to the Contributed Assets under the terms of the August 2013 Promissory Notes. At the close of the IPO, the outstanding balance of the August 2013 Promissory Notes was $246,056.
OpCo used the $286,088 it received from the Partnership in exchange for a 4.8% limited partner interest in OpCo to (1) establish a $55,419 turnaround reserve, (2) reimburse Westlake $151,729 for the Pre-August 2013 Capex, and (3) repay $78,940 of the August 2013 Promissory Notes assumed by OpCo. Immediately after the repayment, the outstanding indebtedness payable to Westlake under the August 2013 Promissory Notes was $167,116.
Agreements with Westlake and Related Parties
The agreements described below became effective on August 4, 2014, concurrent with the closing of the IPO.
Ethylene Sales Agreement
OpCo entered into a 12-year ethylene sales agreement with Westlake (the "Ethylene Sales Agreement"). The Ethylene Sales Agreement requires Westlake to purchase a minimum volume of ethylene each year equal to 95% of OpCo's planned ethylene production per year (the "Minimum Commitment"), subject to certain exceptions and a maximum commitment of 3.8 billion pounds per year. So long as Westlake is not in default under the Ethylene Sales Agreement, if OpCo's actual production exceeds planned production, Westlake has the option to purchase up to 95% of the excess production (the "Excess Production Option").
The fee for each pound of ethylene purchased by Westlake from OpCo up to the Minimum Commitment in any calendar year will equal:
the actual price OpCo pays Westlake to purchase ethane (or other feedstock, such as propane, if applicable) to produce each pound of ethylene, subject to a specified cap and a floor on the amount of feedstock that should be needed to produce each pound of ethylene; plus
the actual price OpCo pays Westlake to purchase natural gas to produce each pound of ethylene, subject to a specified cap and a floor on the amount of natural gas that should be needed to produce each pound of ethylene; plus
OpCo's estimated operating costs (including selling, general and administrative expenses), divided by OpCo's planned ethylene production for the year (in pounds); plus
a five-year average of OpCo's expected future maintenance capital expenditures and other turnaround expenditures, divided by OpCo's planned ethylene production capacity for the year (in pounds); less
the proceeds (on a per pound of ethylene basis) received by OpCo from the sale of co-products (including, but not limited to, propylene, crude butadiene, pyrolysis gasoline and hydrogen) associated with producing the ethylene purchased by Westlake; plus
a $0.10 per pound margin.
The fee for the Excess Production Option, if exercised, equals OpCo's estimated variable operating costs of producing the incremental ethylene, net of revenues from co-products sales plus a $0.10 per pound margin.
The estimated operating costs and the expected future maintenance capital expenditures and other turnaround expenditures will be adjusted at the end of each year, to be applicable for the fee for the next calendar year, to reflect certain changes in forecasted costs.
The result of the fee structure is that OpCo should recover the portion of its total operating costs and maintenance capital expenditures and other turnaround expenditures corresponding to the portion of OpCo's aggregate production that is purchased by Westlake. The Ethylene Sales Agreement has an initial term extending until December 31, 2026 and automatically renews thereafter for successive 12-month terms unless terminated.
Feedstock Supply Agreement
OpCo entered into a feedstock supply agreement with Westlake, pursuant to which Westlake agreed to sell to OpCo ethane and other feedstock in amounts sufficient for OpCo to produce the ethylene to be sold under the Ethylene Sales Agreement (the "Feedstock Supply Agreement"). The Feedstock Supply Agreement provides that OpCo may obtain feedstock from Westlake based on Westlake's total cost of purchasing and delivering the feedstock, including applicable transportation, storage and other costs. Title and risk of loss for all feedstock purchased by OpCo through the Feedstock Supply Agreement passes to OpCo upon delivery to one of three delivery points described in the Feedstock Supply Agreement.
The Feedstock Supply Agreement has an initial term extending until December 31, 2026 and automatically renews thereafter for successive 12-month terms unless terminated by either party; provided, however, that such agreement can only be renewed in the event the Ethylene Sales Agreement is renewed simultaneously. The Feedstock Supply Agreement may, in certain circumstances, terminate concurrently with the termination of the Ethylene Sales Agreement.
Services and Secondment Agreement
OpCo entered into a services and secondment agreement with Westlake, pursuant to which OpCo provides Westlake with certain services required for the operation of Westlake's facilities; and Westlake provides OpCo with comprehensive operating services for OpCo's facilities, ranging from services relating to the maintenance and operations of the common facilities necessary for the operation of OpCo's units, to making available certain shared utilities such as electricity and natural gas that are necessary for the operation of OpCo's units. Westlake also seconds employees to OpCo to allow OpCo to operate its facilities. Such seconded employees will be under the control of OpCo while they work on OpCo's facilities.
The services and secondment agreement has an initial 12-year term. The services and secondment agreement may be renewed thereafter upon agreement of the parties and shall automatically terminate if the Ethylene Sales Agreement terminates under certain circumstances. Westlake and OpCo each can terminate the services and secondment agreement under certain circumstances, including if the other party materially defaults on the performance of its obligations and such default continues for a 30-day period.
Site Lease Agreements
OpCo entered into two site lease agreements with Westlake pursuant to which Westlake leases to OpCo the real property underlying Lake Charles Olefins and Calvert City Olefins, respectively, and grants OpCo rights to access and use certain other portions of Westlake's ethylene production facilities that are necessary to operate OpCo's production facilities. OpCo owes Westlake one dollar per site per year. The site lease agreements each have a term of 50 years. Each of the site lease agreements may be renewed if agreed by the parties.
Omnibus Agreement
The Partnership entered into an omnibus agreement with Westlake that addresses (1) Westlake's indemnification of the Partnership for certain matters, including environmental and tax matters, (2) the provision by Westlake of certain management and other general and administrative services to the Partnership and its general partner and (3) the Partnership's reimbursement to Westlake for such services. The omnibus agreement also addresses Westlake's right of first refusal on any proposed transfer of the ethylene production facilities that serve Westlake's other facilities and Westlake's right of first refusal on any proposed transfer of the Partnership's equity interests in OpCo.