LIABILITIES FOR DISPOSED OPERATIONS
6 Months Ended
Jun. 28, 2014
Environmental Remediation Obligations [Abstract]  
LIABILITIES FOR DISPOSED OPERATIONS
LIABILITIES FOR DISPOSED OPERATIONS
In accordance with the Separation Agreement, as between Rayonier and the Company, the Company assumed certain environmental liabilities not included in the Company’s historical combined financial statements, as these operations were previously managed by Rayonier. These environmental liabilities relate to previously disposed operations, which include Rayonier’s Port Angeles, Washington dissolving pulp mill that was closed in 1997; Rayonier’s wholly-owned subsidiary, Southern Wood Piedmont Company (“SWP”), which ceased operations other than environmental investigation and remediation activities in 1989; and other miscellaneous assets held for disposition. SWP owns or has liability for ten inactive former wood treating sites that are subject to the Resource Conservation and Recovery Act, the Comprehensive Environmental Response, Compensation and Liability Act of 1980 and/or other similar federal or state statutes relating to the investigation and remediation of environmentally-impacted sites.

An analysis of the liabilities for disposed operations since the separation follows:
 
June 28,
 
2014
Balance, beginning of period
$

Net transfer of liabilities with Rayonier
73,840

Expenditures charged to liabilities

Increase to liabilities (a)
18,419

Balance, end of period
92,259

Less: Current portion
(7,406
)
Non-current portion
$
84,853


(a) As a result of the Distribution, the Company is subject to certain legal requirements relating to the provision of annual financial assurance regarding environmental remediation at certain disposed sites. To comply with these requirements, the Company purchased surety bonds from an insurer, with the Company’s repayment obligations (if the bonds are drawn upon) secured by the issuance of a letter of credit by the Company’s revolving credit facility lender. As a result of its obligations to procure financial assurance annually for the foreseeable future, the Company recorded a corresponding increase to liabilities for disposed operations. See Note 12Guarantees for additional information.

Below are the disclosures for specific site liabilities where current estimates exceed 10 percent of the total liabilities for disposed operations at June 28, 2014. An analysis of the activity from the separation to June 28, 2014 is as follows:

 
Activity (in millions)
 
Liabilities Assumed at Separation
 
Expenditures
 
Increase
(Reduction)
to
Liabilities
 
June 28,
2014
Liability
Augusta, Georgia
$
10.8

 
$

 
$
7.3

 
$
18.1

Spartanburg, South Carolina
10.9

 

 
3.5

 
14.4

East Point, Georgia
9.4

 

 
4.3

 
13.7

Baldwin, Florida
10.2

 

 
2.1

 
12.3

Other SWP sites
18.1

 

 
1.1

 
19.2

Total SWP
59.4

 

 
18.3

 
77.7

Port Angeles, Washington
8.1

 

 
0.1

 
8.2

All other sites
6.4

 

 

 
6.4

TOTAL
$
73.9

 
$

 
$
18.4

 
$
92.3



A brief description of each of these sites is as follows (all spending was incurred by Rayonier prior to the Distribution):
Augusta, Georgia — SWP operated a wood treatment plant at this site from 1928 to 1988. The majority of visually contaminated surface soils have been removed, and remediation activities currently consist primarily of a groundwater treatment and recovery system. The site operates under a 10-year hazardous waste permit issued pursuant to the Resource Conservation and Recovery Act, which expires in 2014. Current cost estimates could change if recovery or discharge volumes increase or decrease significantly, or if changes to current remediation activities are required in the future. Total spending as of June 28, 2014 was $69.4 million. Liabilities are recorded to cover obligations for the estimated remaining remedial, monitoring activities and financial assurance through 2033.
Spartanburg, South Carolina — SWP operated a wood treatment plant at this site from 1925 to 1989. Remediation activities include: (1) a recovery system and biological wastewater treatment plant, (2) an ozone-sparging system treating soil and groundwater and (3) an ion-exchange resin system treating groundwater. In 2012, SWP entered into a consent decree with the South Carolina Department of Health and Environmental Control which governs future investigatory and assessment activities at the site. Depending on the results of this investigation and assessment, additional remedial actions may be required in the future. Therefore, current cost estimates could change. Total spending as of June 28, 2014 was $41.1 million. Liabilities are recorded to cover obligations for the estimated remaining assessment, remedial, monitoring activities and financial assurance through 2033.
East Point, Georgia — SWP operated a wood treatment plant at this site from 1908 to 1984. This site operates under a 10-year Resource Conservation and Recovery Act hazardous waste permit, which is currently in the renewal process. In 2009, SWP entered into a consent order with the Environmental Protection Division of the Georgia Department of Natural Resources which requires that SWP perform certain additional investigatory, analytical and potentially, remedial activity. Therefore, while active remedial measures are currently ongoing, additional remedial measures may be necessary in the future. Total spending as of June 28, 2014 was $22.3 million. Liabilities are recorded to cover obligations for the estimated remaining assessment, remedial, monitoring activities and financial assurance through 2033.
Baldwin, Florida — SWP operated a wood treatment plant at this site from 1954 to 1987. This site operates under a 10-year hazardous waste permit issued pursuant to the Resource Conservation and Recovery Act, which expires in 2016. Visually contaminated surface soils have been removed, and current remediation activities primarily consist of a groundwater recovery and treatment system. Investigation and assessment of other potential areas of concern are ongoing in accordance with the facility’s Resource Conservation and Recovery Act permit and additional remedial activities may be necessary in the future. Therefore, current cost estimates could change. Total spending as of June 28, 2014 was $22.2 million. Liabilities are recorded to cover obligations for the estimated remaining assessment, remedial, monitoring activities and financial assurance through 2033.
Port Angeles, Washington — Rayonier operated a dissolving pulp mill at this site from 1930 until 1997. The site and the adjacent marine areas (a portion of Port Angeles harbor) have been in various stages of the assessment process under the Washington Model Toxics Control Act (“MTCA”) since about 2000, and several voluntary interim soil clean-up actions have also been performed during this time. In 2010, Rayonier entered into an agreed order with the Washington Department of Ecology (“Ecology”), under which the MTCA investigatory, assessment and feasibility and alternatives study process will be completed on a set timetable, subject to approval of all reports and studies by Ecology. Upon completion of all work required under the agreed order and negotiation of an approved remedy, additional remedial measures for the site and adjacent marine areas may be necessary in the future. Total spending as of June 28, 2014 was $44 million. Liabilities are recorded to cover obligations for the estimated assessment, remediation, monitoring obligations and financial assurance that are deemed probable and estimable at this time.
The Company is exposed to the risk of reasonably possible additional losses in excess of the established liabilities. As of June 28, 2014, this amount could range up to $33 million, attributable to several of the applicable sites, and arises from uncertainty over the availability, feasibility and effectiveness of certain remediation technologies, additional or different contamination that may be discovered, development of new or more effective environmental remediation technologies, potential changes in applicable law and regulations, and the exercise of discretion in interpretation of applicable law and regulations by governmental agencies.
The Company believes established liabilities are sufficient for probable costs expected to be incurred over the next 20 years with respect to its disposed operations. Remedial actions for these sites vary, but include on-site (and in certain cases off-site) removal or treatment of contaminated soils and sediments, recovery and treatment/remediation of groundwater, and source remediation and/or control.